1 City of Davis ERP Project Charter Version.1 April 6, 2015

2 Table of Contents 1 Introduction Purpose Project Description Background Business Problem Project Definition Scope Goals and Objectives Critical Success Factors Major Deliverables Assumptions and Constraints Oversight Requirements... 5

3 1 Introduction 1.1 Purpose The Project Charter defines the project and gives authority to the project manager to begin initiation activities and deliverables for the ERP project. The charter represents a joint understanding and approval of the project by key stakeholders such as Information Systems, Department staff, Administrative Services, the City Manager and other Project Stakeholders. 1.2 Project Description Modify, upgrade or replace the current Financial Management System (NaviLine - SunGard Public Sector) to meet three main needs: 1. Financial Accounting, Budgeting, inspections and other land management needs for City operations. 2. Online servicing needs for our community (Click 2 Gov): and, 3. Provide enhanced Business Intelligence (BI) tools to allow for improved budgeting and reporting of financial and business data. 2 Background The Financial System is running on the latest version of NaviLine - SunGard Public Sector with GL/GMBA and Land Modules as show below. Page 3 of 5

4 The Naviline system is outsourced and hosted by Sungard. Additional features have been requested by departments and SunGard presented various options to provide the requested features: 1. Modify the current Naviline system and provide enhanced BI Tools. 2. Upgrade to the Sungard ONESolution 2.1 Business Problem The project aims to meet multiple business problems: 1. The City currently uses a Program Based method of accounting; where costs are accumulated indirectly in a home fund account for a program and then distributed equitably across all direct funds that utilize service. While this method of accounting worked efficiently for the City many years ago when City population and services were significantly smaller, the method is much less effective today. Program Based accounting requires a large amount of overhead to process indirect costs and allocate the across each direct program. Changing the accounting method to Fund Based accounting will reduce the amount of time it takes to allocate costs, develop budgets, and report financial data each month. 2. There is a high need to increase online services to the community. a. Building Permits Online b. Business Licenses Online c. Misc. Receivables d. Account Payment Inquiry e. Credit Card at the Counter f. Work Order Planning and Engineering 3. The City Council and the Finance and Budget Committee require budget and finance information in various forms to clearly identify where City Costs are allocated, provide financial transparency to the community, and to look for areas of cost reduction/improvement. 3 Project Definition 3.1 Scope Investigate, select, and implement the best ERP solution to meet current and future business needs. 3.2 Goals and Objectives Goal: Objectives: Select and Implement an ERP System for the City of Davis: 1. Conduct a business analysis of each department to determine the ERP needs for the department. 2. Determine the Finance and Budget reporting needs of the City Council and Finance: 3. Conduct a requirements analysis and determine if the City: Page 4 of 5

5 Should the City continue to use Naviline, implement enhancements and change the method of accounting used from Program Based Accounting to Fund Based Accounting. Should the City purchase ONE Solution Should the City peruse a new ERP vendor 3.3 Critical Success Factors Critical success factors will be documented in the project plan as business needs are identified during the development of the Business Requirements Document and through interviews with City Council/Finance and Budget Committee and COD Departments. 3.4 Major Deliverables 1. Cross Functional Process Maps of business processes for each department; Current Business Process, Disconnects, and Areas for improvement. 2. Requirements Document 3. Request for Quote 4. Project Plan and Schedule Attached is a list of deliverables and high level project activities that will be completed during the Initiation and Planning phases of the project. A full project plan and schedule will be developed as part of the planning phase. The Plan and Schedule will be presented to the Finance and Budget committee, before implementation begins. 3.5 Assumptions and Constraints Assumptions and constraints to be considered: It is assumed that the City will remain with Sungard. If the requirements analysis show that another vendor should be considered, it may add considerable cost and time to the project. Known issues o The Information Technology and Finance Departments have limited staff to manage this project. Additional resources; consultants or additional staff are required to ensure project success. 3.6 Oversight and Reporting Requirements The oversight and reporting requirements will be documented in the project plan during the planning phase of the project identifying the methodology for project reporting, risk management, issue management and change management. Page 5 of 5

Capital Improvement Projects

Capital Improvement Projects REPORT # 2011-12 AUDIT Of the Richmond City Department of Parks, Recreation and Community Facilities Capital Improvement Projects TABLE OF CONTENTS Executive Summary..... i Comprehensive List of Recommendations

More information

ADDENDUM #1 TO REQUEST FOR PROPOSAL: ENTERPRISE RESOURCE PLANNING (ERP) - BUDGET SOFTWARE MODULE SYSTEM (CLOUD BASED) September 25, 2017

ADDENDUM #1 TO REQUEST FOR PROPOSAL: ENTERPRISE RESOURCE PLANNING (ERP) - BUDGET SOFTWARE MODULE SYSTEM (CLOUD BASED) September 25, 2017 ADDENDUM #1 TO REQUEST FOR PROPOSAL: ENTERPRISE RESOURCE PLANNING (ERP) - BUDGET SOFTWARE MODULE SYSTEM (CLOUD BASED) September 25, 2017 A. This Addendum shall be considered part of the bid documents for

More information

FEE REVIEW BACKGROUNDER: HOME INSPECTORS

FEE REVIEW BACKGROUNDER: HOME INSPECTORS FEE REVIEW BACKGROUNDER: HOME INSPECTORS September 29, 2017 We are undertaking a fee review for each of our licensed sectors, as current licensing fees and other charges expire on December 31, 2017. As

More information

REQUEST FOR PROPOSALS RFP #6570 EXHIBIT 3: SCOPE OF WORK

REQUEST FOR PROPOSALS RFP #6570 EXHIBIT 3: SCOPE OF WORK Materials Management Department 901-B Texas Street Denton, Texas 76209 REQUEST FOR PROPOSALS RFP #6570 EXHIBIT 3: SCOPE OF WORK The City of Denton is seeking the best value solution for the: SUPPLY OF

More information

Company Name PRELIMINARY PROJECT SCOPE STATEMENT <PROJECT NAME> COMPANY NAME STREET ADDRESS CITY, STATE ZIP CODE DATE

Company Name PRELIMINARY PROJECT SCOPE STATEMENT <PROJECT NAME> COMPANY NAME STREET ADDRESS CITY, STATE ZIP CODE DATE Company Name PRELIMINARY PROJECT SCOPE STATEMENT COMPANY NAME STREET ADDRESS CITY, STATE ZIP CODE DATE TABLE OF CONTENTS PROJECT AND PRODUCT OBJECTIVES...2 PRODUCT OR SERVICE REQUIREMENTS

More information

State of Michigan s Project SIGMA

State of Michigan s Project SIGMA State of Michigan s Project SIGMA Presented to State Association of Accountants, Auditors and Business Administrators (SAAABA) Ruth Schwartz, CPA, Project Director April 21, 2015 Topics for Today Project

More information

The FIX Protocol: An Introduction

The FIX Protocol: An Introduction The FIX Protocol: An Introduction Marcio Castro, Co-Chair FIX Protocol Latin America Subcommittee, IT Officer - Trading and Market Data systems at BM&F BOVESPA The FIX Protocol: A Brief Introduction For

More information

IT Procurement and Contract Management

IT Procurement and Contract Management IT Procurement and Contract Management June 28, 2017 Report 201702 City Auditor: Jed Johnson, CIA, CGAP Major Contributor: Christy Rodriguez, CPA Contents Overall Conclusion... 1 Authorization... 1 Objective(s)...

More information

Item 08E 1 of 14

Item 08E 1 of 14 MEETING DATE: September 20, 2017 PREPARED BY: Marta D. Lundgren, Finance Manager DEPT. DIRECTOR: Tim Nash DEPARTMENT: Finance CITY MANAGER: Karen P. Brust SUBJECT: City of Encinitas Merchant Processing

More information

Corporate Governance and risk reporting. How Can Environmental Issues Affect Company Ratings and Future Environmental Reporting Requirements

Corporate Governance and risk reporting. How Can Environmental Issues Affect Company Ratings and Future Environmental Reporting Requirements Corporate Governance and risk reporting How Can Environmental Issues Affect Company Ratings and Future Environmental Reporting Requirements Warsaw, March 16, 2005 Agenda Corporate Governance in TP Group

More information

Audited Financial Statements STATE REGULATORY REGISTRY LLC. December 31, 2017

Audited Financial Statements STATE REGULATORY REGISTRY LLC. December 31, 2017 Audited Financial Statements STATE REGULATORY REGISTRY LLC December 31, 2017 Contents Independent Auditor s Report 1 Financial Statements Statements of financial condition 2 Statements of operations and

More information

Chapter 7 Department of Transportation and Infrastructure. Pre-mixed Asphalt Procurement

Chapter 7 Department of Transportation and Infrastructure. Pre-mixed Asphalt Procurement Pre-mixed Asphalt Procurement Chapter 7 Department of Transportation and Infrastructure Pre-mixed Asphalt Procurement Contents Why We Chose this Project.. 259 Background...... 260 Objective and Methodology......

More information

St. Johns County School District, Florida

St. Johns County School District, Florida St. Johns County School District, Florida Contract Compliance Review SunGard Public Sector, Inc. Prepared By: Internal Auditors June 25, 2013 TABLE OF CONTENTS SECTION PAGE Transmittal Letter... 1 Executive

More information

3.08. OntarioBuys Program. Chapter 3 Section. Background. Ministry of Finance

3.08. OntarioBuys Program. Chapter 3 Section. Background. Ministry of Finance Chapter 3 Section 3.08 Ministry of Finance OntarioBuys Program Chapter 3 VFM Section 3.08 Background OntarioBuys is a government initiative launched in 2004 to achieve savings in the procurement of goods

More information

Agenda item 18: Policies on the formal replenishment process

Agenda item 18: Policies on the formal replenishment process Page 10 Also requests the Secretariat to take into account in developing the terms of reference of the procedure: (i) (ii) The need for the assets of the GCF to be covered by the appropriate privileges

More information

Template : Project Initiation Document (PID)

Template : Project Initiation Document (PID) Template 6.2.11: Project Initiation Document (PID) Purpose The Project Initiation Document, also known as a PID, is the agreed document in use in the HSE to assist people undertaking projects. Available

More information

JPM Global High Yield/Leveraged Finance Conference. Date: 2/27/12

JPM Global High Yield/Leveraged Finance Conference. Date: 2/27/12 JPM Global High Yield/Leveraged Finance Conference Date: 2/27/12 Forward Looking Statements Any statements contained in this presentation that are not statements of historical fact, including statements

More information

UNDERSTANDING THE GIPS STANDARDS: A GUIDE FOR ASSET OWNERS

UNDERSTANDING THE GIPS STANDARDS: A GUIDE FOR ASSET OWNERS UNDERSTANDING THE GIPS STANDARDS: A GUIDE FOR ASSET OWNERS Ethics. Integrity. Fair representation. Full disclosure. All are essential principles for investment managers to succeed. But these principles

More information

Nordea Funds Valuation Principles

Nordea Funds Valuation Principles Nordea Funds Valuation Principles May 2018 Board of Directors of Nordea Funds Ltd Table of content 1 PURPOSE... 3 2 GOVERNANCE... 3 2.1 Review of valuation principles... 3 2.2 Independence of valuation...

More information

CORPORATE SERVICES GENERAL ISSUES COMMITTEE

CORPORATE SERVICES GENERAL ISSUES COMMITTEE 5.2 GENERAL ISSUES COMMITTEE February 13, 2018 Mike Zegarac General Manager OVERVIEW 2 Citizen and Customer Services 546-CITY (Customer Contact Centre) askcity@hamilton.ca (Email inquiries) Municipal Service

More information

Employees Provident Fund

Employees Provident Fund Employees Provident Fund Sri Lanka No. 13, Sir Baron Jayathilake Mawatha, Colombo 01 Tel Number: +9411 2206601 Fax Number: +94112206630 E-mail Address: sepf@cbsl.lk REQUEST FOR EXPRESSION OF INTEREST (EOI)

More information

SAGE 100 ERP TIPS AND TRICKS BANK RECONCILIATION Presented by Target System Technology, Inc.

SAGE 100 ERP TIPS AND TRICKS BANK RECONCILIATION Presented by Target System Technology, Inc. SAGE 100 ERP TIPS AND TRICKS BANK RECONCILIATION Presented by Target System Technology, Inc. (copyright 2015) Sage 100 ERP Standard and Sage 100 ERP Advanced are register trademarks of Sage Software. Crystal

More information

USAID Business Enabling Project in Serbia JOB DESCRIPTION AND STATEMENT OF WORK

USAID Business Enabling Project in Serbia JOB DESCRIPTION AND STATEMENT OF WORK USAID Business Enabling Project in Serbia JOB DESCRIPTION AND STATEMENT OF WORK Position: Public Finance and IT Specialist Employer: Cardno Emerging Markets USA Ltd., Washington DC, Belgrade Representative

More information

Manitoba Public Insurance s Accessibility Plan

Manitoba Public Insurance s Accessibility Plan Page 1 of 18 Manitoba Public Insurance s 2017-18 Accessibility Plan Original Plan Date: January 2017 Annual Review: January 2018 Page 2 of 18 Section A: Baseline Report Overview of programs and services

More information

Version 2.0- Project. Q: What is the current status of your project? A: Completed

Version 2.0- Project. Q: What is the current status of your project? A: Completed Baker College, MI Project: Develop an institutional quality assurance framework to measure institutional effectiveness and drive continuous quality improvement efforts Version 2.0- Project What is the

More information

Framework for the euro foreign exchange reference rates

Framework for the euro foreign exchange reference rates Framework for the euro foreign exchange reference rates The euro foreign exchange reference rates (also known as the ECB reference rates), the European Central Bank in its capacity as the administrator

More information

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk

More information

Quality Assurance Team Charter

Quality Assurance Team Charter Quality Assurance Team Charter Version 1.0 01 NOV 2006 INTENT The intent of the Quality Assurance Team Charter (Charter) is to establish a common understanding of the authority and responsibilities of

More information

Capital Area Council of Governments FY 2019 Cost Policy Statement and Cost Allocation Plan

Capital Area Council of Governments FY 2019 Cost Policy Statement and Cost Allocation Plan Capital Area Council of Governments FY 2019 Cost Policy Statement and Cost Allocation Plan The Capital Area Council of Governments uses the cost allocation method prescribed in OMB Uniform Administrative

More information

TD Bank Group Director Independence Policy

TD Bank Group Director Independence Policy TD Bank Group Director Independence Policy Summary This policy formalizes the Board s approach to determining director independence and was approved by the Board. Regulatory Background This policy complies

More information

(Refer to the complete solicitation document for full details.) Utility Bill Printing and Mailing Services. Issue Date: August 1, 2010

(Refer to the complete solicitation document for full details.) Utility Bill Printing and Mailing Services. Issue Date: August 1, 2010 CITY OF CASSELBERRY, FLORIDA REQUEST FOR PROPOSAL (RFP) Issued by: Lou Emma Cromity, Purchasing Agent 95 Triplet Drive, Casselberry, Florida 32707 lcromity@casselberry.org Fax No.: (407)262-7700 ext. 1142

More information

Impact of VAT Compliance on Business. Pierre Arman Market Lead for Tax & Accounting Thomson Reuters MENA Qatar Chamber of Commerce February 2018

Impact of VAT Compliance on Business. Pierre Arman Market Lead for Tax & Accounting Thomson Reuters MENA Qatar Chamber of Commerce February 2018 Impact of VAT Compliance on Business Pierre Arman Market Lead for Tax & Accounting Thomson Reuters MENA Qatar Chamber of Commerce February 2018 Agenda Preparing for VAT in the GCC Lessons learned in 2017

More information

NOTICE OF INTENTION TO ADOPT A CONFLICT OF INTEREST CODE FOR OPTIONS FOR YOUTH SAN BERNARDINO, INC.

NOTICE OF INTENTION TO ADOPT A CONFLICT OF INTEREST CODE FOR OPTIONS FOR YOUTH SAN BERNARDINO, INC. NOTICE OF INTENTION TO ADOPT A FOR OPTIONS FOR YOUTH SAN BERNARDINO, INC. NOTICE IS HEREBY GIVEN that Options for Youth San Bernardino, Inc. ( Corporation ), a California nonprofit public benefit corporation,

More information

ADMINISTRATIVE SERVICES DEPARTMENT

ADMINISTRATIVE SERVICES DEPARTMENT ADMINISTRATIVE SERVICES DEPARTMENT DEPARTMENT Assistant City Manager Budget & Financial Fiscal Services Human Resources Information Technology Regular Full Time 31.00 Regular Part Time - Temporary Part

More information

PROJECT CHARTER VERSION: V01 REVISION DATE: [ ]

PROJECT CHARTER VERSION: V01 REVISION DATE: [ ] PROJECT CHARTER VERSION: V01 REVISION DATE: [03.22.10] Approval of the Project Charter indicates an understanding of the purpose and content described in this document. By signing this document, each individual

More information

Capital Area Council of Governments FY 2018 Cost Policy Statement and Cost Allocation Plan

Capital Area Council of Governments FY 2018 Cost Policy Statement and Cost Allocation Plan Capital Area Council of Governments FY 2018 Cost Policy Statement and Cost Allocation Plan The Capital Area Council of Governments uses the cost allocation method prescribed in OMB Uniform Administrative

More information

Performance Budgeting for Federal Agencies. A Framework. JOHN MERCER (link to John Mercer's Website) IN PARTNERSHIP WITH AMS MARCH 18, 2002

Performance Budgeting for Federal Agencies. A Framework. JOHN MERCER (link to John Mercer's Website) IN PARTNERSHIP WITH AMS MARCH 18, 2002 Performance Budgeting for Federal Agencies A Framework JOHN MERCER (link to John Mercer's Website) IN PARTNERSHIP WITH AMS MARCH 18, 2002 For additional information please contact us at: John Mercer: GPRA@john-mercer.com

More information

REQUEST FOR COMMENTS

REQUEST FOR COMMENTS EXPOSURE DRAFT Reporting on Audited Financial Statements Proposed New and Revised Singapore Standards on Auditing (SSAs) and Related Conforming Amendments May 2015 REQUEST FOR COMMENTS This Exposure Draft

More information

Proposed revised/new IAIS Glossary Definitions related to governance and group supervision for consultation June 2015

Proposed revised/new IAIS Glossary Definitions related to governance and group supervision for consultation June 2015 Proposed revised/new IAIS Glossary Definitions related to governance and group supervision for consultation June 2015 This document contains the proposed new or revised definitions to be included in the

More information

Key Aspects for Managing a Project

Key Aspects for Managing a Project Key Aspects for Managing a Project What is a Project? Definition: A project is a temporary endeavor undertaken to create a unique product, service or result. The temporary nature of projects indicates

More information

Dale R. Kluga, President 2831 W. 83 rd Street, Darien, Illinois Phone Fax

Dale R. Kluga, President 2831 W. 83 rd Street, Darien, Illinois Phone Fax Cobra Capital Bank Leasing Program Solutions that work Cobra Capital Background Status of Leasing Industry Bank Alliance Bank Benefits Customer Benefits How to Recognize Leasing Opportunities When to Call

More information

Ministry of Seniors Affairs Program Guidelines. For The. Fire Sprinkler Retrofit Program For Licensed Small or Rural Retirement Homes

Ministry of Seniors Affairs Program Guidelines. For The. Fire Sprinkler Retrofit Program For Licensed Small or Rural Retirement Homes Ministry of Seniors Affairs Program Guidelines For The Fire Sprinkler Retrofit Program For Licensed Small or Rural Retirement Homes October 11, 2017 1 Table of Contents Introduction... 3 Important Dates...

More information

Five-Day Schedule and Course Content

Five-Day Schedule and Course Content Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course

More information

Service Efficiency Consultants Studies Extent of Value for Money From Studies Has Not Been Clearly Demonstrated

Service Efficiency Consultants Studies Extent of Value for Money From Studies Has Not Been Clearly Demonstrated AUDITOR GENERAL S REPORT ACTION REQUIRED Service Efficiency Consultants Studies Extent of Value for Money From Studies Has Not Been Clearly Demonstrated Date: February 11, 2015 To: From: Wards: Audit Committee

More information

TEEKAY LNG PARTNERS L.P. Corporate Governance Guidelines

TEEKAY LNG PARTNERS L.P. Corporate Governance Guidelines TEEKAY LNG PARTNERS L.P. Corporate Governance Guidelines The following guidelines have been approved by the Board of Directors (the "Board") of Teekay GP L.L.C., a Marshall Islands limited liability company

More information

General Discussion A&E Services Consultants

General Discussion A&E Services Consultants WSDOT Local Agency Guidelines M 36-63.01 Chapter 31 Chapter 31 General Discussion To be eligible for reimbursement of Federal Highway Administration (FHWA) funds for payments to a consultant, the procedures

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Capital Delivery Review Implementation Plan Date: December 20, 2016 To: From: Toronto Transit Commission Board Chief Executive Officer Summary The TTC provides stewardship

More information

Guard Your Investment in Valuable Contracts

Guard Your Investment in Valuable Contracts Guard Your Investment in Valuable Contracts 1 PRESENTERS Mark Steranka Partner Moss Adams Consulting Robert Gutierrez, CPA, JD Manager Moss Adams Consulting 2 AGENDA Why Audit Contracts Federal Contracts

More information

Information Technology Project Management Fifth Edition

Information Technology Project Management Fifth Edition Information Technology Project Management Fifth Edition By Jack T. Marchewka Northern Illinois University 4-1 Copyright 2015 John Wiley & Sons, Inc. Project Planning: The Project Infrastructure Chapter

More information

AMERICAN SOFTWARE, INC.

AMERICAN SOFTWARE, INC. ˆ200G4i3f7shhq7zLyŠ 200G4i3f7shhq7zLy GA0113AM022800 12.8.8.0 ADG davir0at 06-Dec-2018 11:38 EST 645446 TX 1 4* Page 1 of 2 UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM

More information

Child Welfare Digital Services Project. Cost Management Plan

Child Welfare Digital Services Project. Cost Management Plan Child Welfare Digital Services Project Cost Management Plan January 2017 CWDS Cost Management Plan January 2017 Revision History Revision / Version # Date of Release Author Summary of Changes V 1.0 4/22/14

More information

Project Connect. May 9, 2012

Project Connect. May 9, 2012 Project Connect May 9, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting

More information

2011 NIPA Retirement Plan TPA Study.

2011 NIPA Retirement Plan TPA Study. 211 NIPA Retirement Plan TPA Study Content 2 I. Sales & Marketing II. Management Practices III. Behaviors and Preferences I. Sales and Marketing 3 Please indicate the following based on 28, 29, and 21

More information

TAX. Good, Better, Best. Argentina. kpmg.com/goodbetterbest

TAX. Good, Better, Best. Argentina. kpmg.com/goodbetterbest TAX Good, Better, Best Argentina kpmg.com/goodbetterbest ii / Good, Better, Best Argentina Contents Introduction 1 Focus on Argentina 2 Clarity of accountabilities tax and reputational risk captures boards

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC

More information

College Finance Department Program Review and Strategic Plan

College Finance Department Program Review and Strategic Plan College Finance Department Program Review and Strategic Plan 2017-2022 Lane Community College Table of Contents Department Overview... 1 Guiding Principles and Mission... 2 Staffing and Structure... 3

More information

Base Erosion and Profit Shifting Project and Developing Economies

Base Erosion and Profit Shifting Project and Developing Economies 2015/FMP/WKSP1/021 Session: 6 Base Erosion and Profit Shifting Project and Developing Economies Submitted by: OECD Workshop on Fiscal Management Through Transparency and Reforms Bagac, Philippines 9-10

More information

The DFSA Rulebook. Authorised Market Institutions (AMI) AMI/VER16/06-14

The DFSA Rulebook. Authorised Market Institutions (AMI) AMI/VER16/06-14 The DFSA Rulebook Authorised Market Institutions (AMI) PART 1: INTRODUCTION... 1 1. APPLICATION, INTERPRETATION AND OVERVIEW... 1 1.1 Application... 1 PART 2: APPLICATION AND AUTHORISATION... 3 2. APPLICATION

More information

Guam Power Authority Financial Strength

Guam Power Authority Financial Strength Guam Power Authority Financial Strength September 2009 Baker Tilly Virchow Krause, LLP Highly effective utilities Make finance/accounting a strategic partner Link their budgets to their strategic plan

More information

URBAN REFORMS AGENDA AT ULB LEVEL

URBAN REFORMS AGENDA AT ULB LEVEL 1. Mandatory Reforms at City Level Commitment as per the MoA for the current financial year a) Implementation of Accounting Reforms URBAN REFORMS AGENDA AT ULB LEVEL Progress made during the Quarter Installed

More information

PROMOTION OF E-PAYMENTS IN TRINIDAD & TOBAGO

PROMOTION OF E-PAYMENTS IN TRINIDAD & TOBAGO PROMOTION OF E-PAYMENTS IN TRINIDAD & TOBAGO February 6, 2014 Presentation to Bankers Association of Trinidad and Tobago Held at First Citizens Bank, Queens Park East OUTLINE Background on Electronic Payments

More information

TRINITY COUNTY. Board Item Request Form Phone (530)

TRINITY COUNTY. Board Item Request Form Phone (530) County Contract No. 15-188.1 Department Auditor/Controller TRINITY COUNTY 2.01 Board Item Request Form 2016-09-20 Contact Angela Bickle, Auditor-Controller Phone (530) 623-1317 Requested Agenda Location

More information

Total ERO Enterprise 2019 Budgets and Assessments Analysis

Total ERO Enterprise 2019 Budgets and Assessments Analysis Total ERO Enterprise 2019 Budgets and Assessments Analysis The following includes an overview of the development of the proposed NERC, Regional Entity, and WIRAB 2019 Business Plan and Budgets (BP&Bs)

More information

FAIS NOTICE 53 OF 2017 FINANCIAL SERVICES BOARD FINANCIAL ADVISORY AND INTERMEDIARY SERVICES ACT, 2002

FAIS NOTICE 53 OF 2017 FINANCIAL SERVICES BOARD FINANCIAL ADVISORY AND INTERMEDIARY SERVICES ACT, 2002 FAIS NOTICE 53 OF 2017 FINANCIAL SERVICES BOARD FINANCIAL ADVISORY AND INTERMEDIARY SERVICES ACT, 2002 BI-ANNUAL COMPLIANCE REPORT FOR CATEGORY II AND IIA FINANCIAL SERVICES PROVIDER, 2017 In terms of

More information

Major Types. Employee. Non employee travel for business Student. In State Out of State Foreign

Major Types. Employee. Non employee travel for business Student. In State Out of State Foreign The University Of Oklahoma Health Sciences Center Traveler Training Major Types Employee In State Out of State Foreign Non employee travel for business Student Types of Travel In State No pre authorization

More information

Achieve PMP Exam Success Five-Day Course Syllabus

Achieve PMP Exam Success Five-Day Course Syllabus Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course

More information

Good governance through financial management

Good governance through financial management Good governance through financial management Evolution of good governance through financial management at the Organization of American States (OAS) Presenters *: Javier Arnaiz, CGFM Diego Yrivarren, CGFM

More information

SAO FINANCIAL REPORTING. by Karen McLaine Financial Management Department October 24 th, 2017

SAO FINANCIAL REPORTING. by Karen McLaine Financial Management Department October 24 th, 2017 SAO FINANCIAL REPORTING by Karen McLaine Financial Management Department October 24 th, 2017 Introduction SAO Financial Accounting Functions SI/SAO Financial Information Systems Financial Information Systems

More information

FTA SUBRECIPIENT MONITORING

FTA SUBRECIPIENT MONITORING FTA SUBRECIPIENT MONITORING JANUARY 2016 Contents Purpose... 3 Monitoring Process... 3 Elaboration of FTA Requirements and Subrecipient Guidelines... 8 Subrecipient Funding Agreement Execution... 9 Ongoing

More information

CHARTER TOWNSHIP OF BLOOMFIELD REQUEST FOR PROPOSAL (RFP) FOR INVESTMENT ADVISER AND CONSULTING SERVICES FOR

CHARTER TOWNSHIP OF BLOOMFIELD REQUEST FOR PROPOSAL (RFP) FOR INVESTMENT ADVISER AND CONSULTING SERVICES FOR CHARTER TOWNSHIP OF BLOOMFIELD REQUEST FOR PROPOSAL (RFP) FOR INVESTMENT ADVISER AND CONSULTING SERVICES FOR 401(a) DEFINED CONTRIBUTION PLAN, 457(b) DEFERRED COMPENSATION PLAN, RETIREE HEALTH CARE TRUST

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL September 19, 2015 REQUEST FOR PROPOSAL INSURANCE ADMINISTRATOR FOR THE CALIFORNIA ASSOCIATION OF MUTUAL WATER COMPANIES JOINT POWERS INSURANCE AUTHORITY The California Association of Mutual Water Companies

More information

Overview of Services

Overview of Services A proud member of Retirement Plan Advisory Group Overview of Services From cost control to compliance and counsel to communication presented by RPAG member: Cognis Retirement Group, LLC info@cognisretirementgroup.com

More information

Ways To Reduce Risk In Construction Loans

Ways To Reduce Risk In Construction Loans Ways To Reduce Risk In Construction Loans Unlike most real estate backed loans, construction and renovation loans carry other inherent risks that require constant oversight. At the end of the day, as a

More information

Electricity trading and risk management in liberalised market

Electricity trading and risk management in liberalised market www.pwc.com/jp Electricity trading and risk management in liberalised market PricewaterhouseCoopers Agenda Page 1 Current electricity trading in Japan 1 2 Evolution of trading in a deregulated market 5

More information

How can you be more efficient at managing indirect tax?

How can you be more efficient at managing indirect tax? How can you be more efficient at managing indirect tax? Indirect Tax Process and Technology kpmg.com/indirecttax Contents 2 How do you manage indirect tax in today s challenging environment? 4 Governance

More information

Trillium Health Partners Foundation. Financial Statements March 31, 2015

Trillium Health Partners Foundation. Financial Statements March 31, 2015 Trillium Health Partners Foundation Financial Statements June 4, 2015 Independent Auditor s Report To the Members of Trillium Health Partners Foundation We have audited the accompanying financial statements

More information

Departments will be given credit (or a reduction of allocations) for the following item:

Departments will be given credit (or a reduction of allocations) for the following item: O R E G O N H E A L T H & S C I E N C E U N I V E R S I T Y O V E R H E A D C O S T ( O C A ) M E T H O D O L O G Y D E S C R I P T I O N F O R T H E F I S C A L Y E A R E N D I N G J U N E 3 0, 2 0 1

More information

Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012

Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012 Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012 for the Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012 and Regulations June 2013 www.epa.govt.nz

More information

3(38) Fiduciary Services. 3(21) Co-Fiduciary Services & INVESTMARK FIDUCIARY SERVICES FOR RETIREMENT PLANS

3(38) Fiduciary Services. 3(21) Co-Fiduciary Services & INVESTMARK FIDUCIARY SERVICES FOR RETIREMENT PLANS INVESTMARK FIDUCIARY SERVICES FOR RETIREMENT PLANS Reduce Your Liability and Keep Your Company s Plan Strong and Compliant 3(38) Fiduciary Services 3(21) Co-Fiduciary Services & The Direction of Wealth

More information

Branch Corporate Strategic Planning

Branch Corporate Strategic Planning Introduction Corporate Strategic Planning provides leadership and drives the integration and coordination of the City s strategic planning process with an emphasis on ensuring the achievement of Council

More information

RFP# Charter Bus Services

RFP# Charter Bus Services RFP#2017-12-001 - Charter Bus Services Assigned Buyer: Adriana Jimenez Telephone Number: 713-348-4071 E-Mail Address: abj2@rice.edu Rice University welcomes competitive Request for Proposals (RFP) from

More information

City of Markham. Property Tax Revenue Audit. October 26, 2016

City of Markham. Property Tax Revenue Audit. October 26, 2016 City of Markham Property Tax Revenue Audit October 26, 2016 PREPARED BY: MNP LLP 300-111 Richmond Street West Toronto, ON M5H 2G4 MNP CONTACT: Geoff Rodrigues, CPA, CA, CIA, CRMA, ORMP Partner, National

More information

LFA Spot Checks of ACT Co-payment Mechanism First-Line Buyers: Terms of Reference

LFA Spot Checks of ACT Co-payment Mechanism First-Line Buyers: Terms of Reference August 2014 LFA Spot Checks of ACT Co-payment Mechanism First-Line Buyers: Terms of Reference Background and Rationale The Private Sector Co-payment Mechanism for ACTs ( Co-payment Mechanism ) is a financing

More information

Financial Services CONTENTS Year Preliminary Capital. 2. Issues for Discussion Performance Preliminary Capital

Financial Services CONTENTS Year Preliminary Capital. 2. Issues for Discussion Performance Preliminary Capital CAPITAL BUDGET NOTES Financial Services 2018 2027 CAPITAL BUDGET AND PLAN OVERVIEW Financial Services' 10-Year Preliminary Capital balances the need to maintain current technology for enterprise-wide financial

More information

Independent Auditor Policy Nationwide Mutual Insurance Company Nationwide Mutual Fire Insurance Company Nationwide Corporation

Independent Auditor Policy Nationwide Mutual Insurance Company Nationwide Mutual Fire Insurance Company Nationwide Corporation Independent Auditor Policy Nationwide Mutual Insurance Company Nationwide Mutual Fire Insurance Company Nationwide Corporation The Independent Auditor Policy (the Policy ) of Nationwide Mutual Insurance

More information

SANFORD AIRPORT AUTHORITY

SANFORD AIRPORT AUTHORITY SANFORD AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) FOR PROFESSIONAL AUDIT SERVICES The Sanford Airport Authority (the SAA ) is soliciting proposals from qualified independent Certified Public Accountants

More information

Session III: Country Experiences on Data Collection and Monitoring of Insurance Industry

Session III: Country Experiences on Data Collection and Monitoring of Insurance Industry Session III: Country Experiences on Data Collection and Monitoring of Insurance Industry - Malaysia s perspective OECD-Asia Regional Seminar: Enhancing Transparency & Monitoring of Insurance Market 23-24

More information

TEEKAY OFFSHORE PARTNERS L.P. Corporate Governance Guidelines

TEEKAY OFFSHORE PARTNERS L.P. Corporate Governance Guidelines TEEKAY OFFSHORE PARTNERS L.P. Corporate Governance Guidelines The following guidelines have been approved by the Board of Directors (the "Board") of Teekay Offshore GP L.L.C., a Marshall Islands limited

More information

Office of Inspector General University of South Florida

Office of Inspector General University of South Florida Office of Inspector General University of South Florida Project # A-1718DOE-017 November 2018 Executive Summary In accordance with the Department of Education s fiscal year (FY) 2017-18 audit plan, the

More information

General management: update

General management: update PROGRAMME, BUDGET AND ADMINISTRATION EBPBAC16/2 COMMITTEE OF THE EXECUTIVE BOARD 3 May 2012 Sixteenth meeting Provisional agenda item 4.1 General management: update Report by the Secretariat 1. This document

More information

[Project Title] Project Scope Statement

[Project Title] Project Scope Statement [Project Title] Project Scope Statement Prepared by: Version: Date: Project Sponsor: Project Manager: Senior Manager: Approval Signatures Project Sponsor Project Manager Senior Manager/s Other Stakeholder

More information

Helena, 57, Mount Carmel Road, Bandra West, Mumbai

Helena, 57, Mount Carmel Road, Bandra West, Mumbai Helena, 57, Mount Carmel Road, Bandra West, Mumbai 400050. CITIZENCREDIT CO-OPERATIVE BANK is one of the fastest growing Banks in the Cooperative Banking Sector, with a business mix of around Rs. 4263

More information

Review of Water and Wastewater Services General Professional Consultant Services Agreements

Review of Water and Wastewater Services General Professional Consultant Services Agreements Review of Water and Wastewater Services General Professional Consultant Services Agreements July 14, 2009 Report No. 08-15 Office of the County Auditor Evan A. Lukic, CPA County Auditor Table of Contents

More information

Request for Proposals (RFP)

Request for Proposals (RFP) Scope of Service RFP # RFP issued by Request for Proposals (RFP) PeopleSoft Financial systems enhancement project 2016RFP-16 First Nations Health Authority (FNHA) Issue date July 25, 2016 Amount N/A Closing

More information

For further information, please contact Guy Leroux at

For further information, please contact Guy Leroux at BChydro m R GENE IONS Joanna Sofield Chief Regulatory Officer Phone: (604 623-4046 Fax: (604 623-4407 bchyd roregulatorygroup@bchydro.com July 13 2009 Ms. Erica M. Hamilton Commission Secretary British

More information

Labuan Reinsurance Brokerage Company Invoice

Labuan Reinsurance Brokerage Company Invoice Client to provide Address to be provided Date: Tuesday, January 16, 2018 Company Reg. No.: 921530 Invoice No: 2018 01 015p Professional services for Labuan offshore company (without travel) Notes Year

More information

IPO Readiness. IPO Milestones Timeline. CMA review and decision. IPO decision. Subscription period. IPO readiness. Submit IPO application

IPO Readiness. IPO Milestones Timeline. CMA review and decision. IPO decision. Subscription period. IPO readiness. Submit IPO application IPO Readiness IPO Milestones Timeline IPO decision IPO readiness Appoint advisors Preparation phase Submit IPO application CMA review and decision IPO book building Subscription period List on The Exchange

More information

Investment outsourcing options for your pension plan

Investment outsourcing options for your pension plan Fiduciary solutions for CORPORATE PENSION PLANS Investment outsourcing options for your pension plan INVESTED. TOGETHER. Managing complexity Managing a pension plan is not getting any easier. Rapid-fire

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS Neighborhood Housing & Public Facilities Improvements Programs Community Development Block Grant (CDBG) Program May 6, 2016 Page 1 of 12 REQUEST FOR QUALIFICATIONS (RFQ) GENERAL,

More information

Improving Allocative Efficiency and Budget Execution for Family Planning

Improving Allocative Efficiency and Budget Execution for Family Planning Improving Allocative Efficiency and Budget Execution for Family Planning ATTAINING SUSTAINABLE FINANCING FOR FAMILY PLANNING IN SUB-SAHARAN AFRICA ACCRA, JANUARY 2018 LOYCE CHILIMSUNGWI and ADEEL ISHTIAQ

More information