A New Method of Cost Contingency Management
|
|
- Domenic George
- 6 years ago
- Views:
Transcription
1 A New Method of Cost Contingency Management Mohammed Wajdi Hammad, Alireza Abbasi, Michael J. Ryan School of Engineering and Information Technology, University of New South Wales (UNSW Australia), Canberra Abstract - Controlling the progress and performance of a project is pivotal to achieve its planned goals. Schedule and cost are often used to make a baseline for managing projects progress, but there are always uncertainties in planning and estimating the schedule and cost of projects. Therefore, a contingency reserve is needed to manage uncertainties and risks. In this paper, we present a new cost contingency management method. To show the benefit of our new proposed method, it is applied to a real-life bridge maintenance project, and then it is compared with an existing cost contingency management method. The comparison shows that our new method can help the project manager obtain more detailed information about the financial status of the project. Keywords - Contingency Allocation, Contingency Management, Cost Contingency, Project Management. I. INTRODUCTION AND BACKGROUND There are many uncertainties and risks involved in all phases of construction projects [1]. These uncertainties can be classified as predictable (known unknowns) and unpredictable (unknown unknowns). Contingency reserve is a managerial tool to control such identifiable (and unidentifiable) uncertainties/risks. Contingency reserve is more precisely defined as the amount of funds, budget, or time needed above the estimate to reduce the risk of overruns of project objectives to a level acceptable to the organisation [2]. Construction participants including owners, contractors, and designers add cost contingency reserve to cover unpredicted costs from changes in the base cost estimate. Research has shown that one of the main factors that contribute to the projects success is the improvements in the cost estimation techniques including cost contingency estimation [3]. The contingency budget is not established to cover changes in scope; rather, its purpose is to cope with cost increases resulting from the uncertain nature of some construction activities. So, for example, if in a bridge construction project the asset manager decides to add a new ladder or paint a new pier, this constitutes a change of scope and its cost or duration impact cannot be absorbed by contingency reserve. Allocation of low amounts of contingency for projects with high risks may result in significant losses. On the other hand, high amounts of contingency may decrease the chances of being awarded a contract. Expert judgment is generally used to determine the bidding contingency reserve. Expert decision is mainly based on the previous experiences with similar projects. Subjectivity is the main disadvantage of this technique as the skill, knowledge, and motivation of the experts may vary widely or the nature of the project might be very different from the ones the expert has experienced [4]. The research topic of project cost contingency consists of contingency estimation, contingency allocation and contingency management. Cost contingency estimation is about calculating the estimated amount of total cost contingency for a project. Contingency allocation involves assigning the total cost contingency to individual activities based on the activity s contribution to the overall variance of the project. Contingency management is a list of processes to monitor and track the status of the contingency for each activity and the entire project. Most of the papers found in the literature were about estimating cost contingency ([5], [6], [7]), and very few about managing and controlling estimated contingency. Among the very few works on cost contingency management, Eldosouky [8] presented a method to manage contingency on a project which requires data collection from previous projects (e.g., interviews with project managers and collecting data about cost and duration of the project) and also the use of some subjective opinion. More recently, Barraza and Bueno [9] presented a methodology for using Monte Carlo Simulation (MCS) for cost contingency estimation, which also includes heuristics for contingency assignment allocation among project activities. They stated that if independent performance is assumed among the project activities and a probability distribution is assigned to each activity, all possible project costs will be normally distributed with a mean cost similar in value to the one that is calculated by the addition of the activities mean costs, and the variance of the possible project cost results to be equal to the accumulation of all activities cost variances [9]. Their proposed methodology provided performance status classification which can be used as a practical guide for management decision making. This research, extending their approach, presents a new cost contingency management method by developing new metrics to calculate the current remaining contingency on a project and compare it with the expected remaining contingency. The new proposed method also updates the contingency for each activity at the end of each reporting period, giving the project manager an early warning sign. A comparison among the two methods is provided by applying both to a real-life bridge maintenance project. The similarities and differences between the two cost contingency management methods are also discussed in detail. The aim of this paper is to introduce an improved cost contingency tracking method that would allow the project
2 manager to manage the project more efficiently, as well as presenting a practical method without the use of complex mathematical equations. II. REVIEWING THE PROPOSED COST CONTINGENCY MANAGEMENT METHOD In the approach proposed in this paper, a probabilistic method is adopted to determine the cost contingency of the project. This involves assigning a probability distribution function to each activity in the project, and through a summative process, developing a probability distribution function for the overall project cost. Subsequently, Monte Carlo Simulation (MCS) is applied which essentially represents repeating construction of the project through a very large number of trials (e.g., 10,000 trials). For any given trial, all of the chosen values for the individual cost components can be mathematically combined to get a (total) project cost. The process is then repeated for the remaining trials and a probability distribution based upon the overall project cost is generated. The cost contingency is then allocated to each activity and are managed with the proposed method in this paper. The remaining contingency for each activity (and for the total project) calculated at the end of each reporting period allows comparison between the actual remaining contingency and the expected (planned) remaining contingency. The proposed method controls the actual costs for a project, as well as the individual activity, to be under the target cost value. If an activity is completed, any remaining contingency reserve will be used as a cushion for future risks. The similar indices between the proposed cost contingency management and the original cost contingency method presented by Barraza and Bueno [9] are: Approved Budget (AB), is the maximum amount of money assigned to each activity without contingency. Work Performed (WP), is the percentage complete for each activity. Planned Value (PV), otherwise known as budgeted cost of work performed (BCWP), is calculated by multiplying AB with WP. PV = AB * WP (1) Cost Variance (CV), which is the difference between PV and actual cost (AC), also known as actual cost of work performed (ACWP). CV = PV AC (2) Cost Contingency of Work Performed (CCWP), which is calculated by multiplying the cost contingency (CC) by WP. CCWP = CC * WP (3) Cost Underrun (CU), which is calculated by subtracting AC from PV and then added to CCWP. CU = PV AC + CCWP (4) Status, which classifies each activity as well as the total project into either A, B or C. Status A shows that the CV is nonnegative and the project has not used any of the contingency assigned to it, status B shows that the CV is negative but below the CCWP, and status C shows that the CV is negative and above (in absolute value) the CCWP and is presenting a cost overrun. The following new parameters are introduced in our proposed method providing more information about future remaining contingencies: Expected Remaining Contingency (ERC), which shows the amount of cost contingency that is expected (planned) to remain at the end of the reporting period. It is calculated by subtracting CCWP from CC. ERC = CC CCWP (5) Actual Remaining Contingency (ARC), which shows the amount of contingency that is actually remaining at the end of the reporting period. This is calculated by dividing the ERPV of each activity over the ERPV of the total project, multiplied by the project s CU and then added to ERC. ARC = (ERPV / ERPV) * CU + ERC (6) When an activity is 100% complete, then the ARC is assumed to be zero. This is because when the activity is complete, it is expected to spend the entire contingency allocated to it. The difference between the ERC and ARC shows the amount of contingency saved/spent. Expected Remaining Planned Value (ERPV), this shows only the remaining PV for each activity and for the total project at the end of the reporting period. ERPV = (1 - WP) * PV (7) Remaining Contingency (RC), informs the project manager about the remaining cost contingency of each activity in real terms. This means that the contingency is not restricted to the percentage complete of an activity, i.e. if an activity is 60% complete then it does not necessarily need to use up to 60 % of the contingency, the activity can use as much of the allocated contingency as needed. This time a negative RC means that the entire contingency allocated to the activity is consumed, and the project manager should take immediate action to stop this. RC is calculated by adding CC to CV. RC = CC + CV (8)
3 Cost Balance (CB), which shows the total remaining cost for each activity including contingency. This shows the project manager if the remaining budget is enough to complete the activity (or the project). CB can be compared against ERPV to determine whether the project has enough funds to be completed. CB is calculated by subtracting PV from AB and then added to RC. CB = RC + (AB PV) (9) III. APPLICATION OF THE PROPOSED COST CONTINGENCY MANAGEMENT METHOD In order to demonstrate the use of our proposed method and compare it with the existing cost contingency management method, both methodologies have been applied to a real life bridge maintenance project. The project is a recently completed Roads & Maritime Services (RMS) maintenance project in the Australian state of New South Wales. To preserve the identity of the project, all activities have been replaced with WBS numbers. The bridge project lasted for 110 days (22 weeks) with a budget of $156,850 and the reporting period is chosen to be every 30 working days (every six weeks). The cost contingency management method proposed by Barraza and Bueno [9] ends at giving the project manager a status about the project while our method continues to provide more information to the project manager about the project using the following five indices (also discussed above) to reinforce the results about the status of the project (ERPV, ERC, ARC, RC and CB). Table I shows the assigned budget and contingency for each activity. The CC is the amount of money used to cover the unforeseeable cost, also known as known unknown. The method used to obtain CC and allocate them to each activity is outside the scope of this paper. TABLE I. Project information Task Name AB CC 1 $151,500 $5, $4,500 $ $68,000 $2, $60,000 $2, $1,000 $ $7,000 $ $79,000 $2, $21,000 $ $15,000 $ $21,000 $ $15,000 $ $7,000 $201 Table II shows all the indices used in both methods for the first reporting period, after 30 days. As seen, the Cost Variance (CV) of the project is $-2,700. This means that the actual costs of the project exceeded the planned cost. The Status of the project is C which means that the project has made use of more than the allowed contingency for the work performed and is therefore presenting a cost overrun. The Expected Remaining Contingency (ERC) of the project is $2,897 and the Actual Updated Remaining Contingency (ARC) is $2,650, this means that the total remaining cost contingency for the project is expected to be $2,897 out of the total $5,350 but in fact the project had $2,650 remaining. The Remaining Contingency (RC) for ongoing and completed activities is $99. The Cost Balance (CB) of project is $97,450 (remaining PV and remaining CC). To know more about ongoing activities, the next level in WBS (1.1, 1.2 and 1.3) should be examined. For instance, the CV of task 1.2 is $-2,700 and the status is C showing that sub-activities under 1.2 used more than the allowed contingency for the work performed. The RC is -$35, while ERC and ARC are $585 and $544 respectively. This shows that the activity is doing worse than expected. The CB for activities under 1.2 is $16,003. For the second reporting period (Table III), after 60 days, the result of the project are as follows- the CV is $- 4,400 which means that the project is still spending more money than planned. The status of the project is B which is an improvement from the previous reporting period, this shows that the entire contingency have not been consumed, the RC is $252. The ERC is $709 while the ARC is $950 showing that the entire project has more cost contingency remaining; the CB is $25,350. For the third reporting period (Table IV), after 90 days, the CV of the project is $-4,450 while the status of the project is B that is the same as the previous reporting period, the RC of the project is $815. The project s ERC is $150 and the ARC is $900 showing that the project is doing better financially than the previous reporting period, while the CB of the project is $6,150. For the fourth and last reporting period (Table V), after 110 days, the CV of the project is $-5,100 and the remaining contingency is $250 as seen on the RC and CB. The ERC and ARC are both zero because the project is expected to consume the entire cost contingency at the end of the project.
4 TABLE II. Results for first reporting period (after 30 days) 1 $56,700 33% $59,400 $2,453 $-2,700 $-247 C $2,897 $2,650 $94,800 $99 $97, $52,200 69% $54,900 $2,318 $-2,700 $-382 C $585 $544 $15,800 $-35 $16, $52,200 87% $54,900 $2,318 $-2,700 $-382 C $346 $326 $7,800 $-35 $7, % $29 $26 $1,000 - $1, % $210 $192 $7,000 - $7, % $2,312 $2,106 $79,000 - $81, % $612 $557 $21,000 - $21, % $438 $399 $15,000 - $15, % $621 $566 $21,000 - $21, % $440 $400 $15,000 - $15, % $201 $183 $7,000 - $7,201 TABLE III. Results for the second reporting period (after 60 days) 1 $127,100 $118,100 $4,641 $-4,400 $241 B $709 $950 $24,400 $252 $25, $54,600 55% $42,200 $1,603 $-1,000 $603 B $709 $950 $24,400 $615 $25, $18,600 83% $18,100 $552 $500 $1,052 A $69 $93 $2,400 $1,064 $3, % $440 $587 $15,000 - $15, % $201 $270 $7,000 - $7,201 TABLE IV. Results from the third reporting period (after 90 days) 1 $146,250 91% $137,300 $5,200 $-4,450 $750 B $150 $900 $5,250 $815 $6, $73,750 85% $61,400 $2,162 $-1,050 $1,112 B $150 $900 $5,250 $1,177 $6, $21, % $19,900 $621 $1,100 $1,721 A $1,721 $1, $13,800 90% $13,800 $405 - $405 A $34 $206 $1,200 $440 $1, $2,950 40% $3,600 $85 $-650 $-565 C $116 $694 $4,050 $-534 $3,601 TABLE V. Results from the third reporting period (after 110 days) 1 $151, % $143,200 $5,350 $-5,100 $250 B $250 $ $79, % $67,300 $2,312 $-1,700 $612 B $612 $ $21, % $19,900 $621 $1,100 $1,721 A $1,721 $1, $15, % $14,800 $440 $200 $640 A $640 $ $7, % $8,500 $201 $ -1,500 $-1,299 C $-1,299 $-1,299
5 IV. DISCUSSION AND CONCLUSION There are several types of uncertainties in the construction industry, the most important being the uncertainty in the estimated cost of project activities. No budget estimate can be correct in every detail. Also, it is very difficult to decide on the appropriate level of detail to include in a cost estimate. Therefore, cost contingency not only should be properly calculated but also wisely controlled during project execution. The main aim of this article is to provide a simple heuristic approach to cost contingency management that provides the project manager with different depth of information. The cost contingency management approach allows controlling the actual cost of each activity, by keeping it below the target cost. The new cost contingency management method proposed in this paper is an improvement to the method presented by Barraza and Bueno [9]. They classify each activity in the project based on the contingency expenditure: status A is when no contingency is used; status B is when some but not the entire contingency is used; and status C is when the entire contingency is used. This is a simple and effective approach and as stated by Barraza and Bueno [9] complex models would not be the solution either for a contingency management approach, as if a model is found conceptually too complex, or if it takes a lot of time for decision maker to analyse the information obtained from it, such a model will have no value for practice. We extended the management method to provide more information to the project manager, while at the same time preserving the method s simplicity. After showing the status of each activity, as well as for the total project, we provide the decision maker with the actual remaining contingency at the end of the reporting period to compare it with the expected remaining contingency. The expected remaining contingency is calculated by assuming that the amount of contingency spent is directly proportional to the percentage complete of each activity, for example if an activity is 60% complete then we assume the activity has 40% contingency remaining. In summary, we extend the management method after showing the status of each activity and the total project. We then show a comparison between the expected remaining contingency and the actual remaining contingency. In addition, we compare between the contingency remaining (with respect to the percentage complete) and the actual contingency remaining, this is only for ongoing and completed activities. This paper has proved that cost contingency can be managed when placed to individual activities and not placed at the end of the project. We have also found that the proposed method provides a warning system and clearly identifies the activity(s) that is causing the cost overrun. This means the project manager can always find the activities that are causing problems in the project. It is very difficult to claim that this is the best and the only method for managing contingency available, and there is no one manual to manage cost contingency during project execution. But what we need to have in the construction industry is a simple to understand, clear and easy to use method that allows the decision maker to select the level of information required to be known. The proposed method works at different levels within the WBS. A couple of assumptions have been used in this paper including, that the PV (BCWP) of the activity can never increase unless there is an increase in scope, therefore, any increase in actual cost that is not associated with an increase in scope results in spending contingency. Another assumption is that the rate at which the cost contingency is used is directly proportional to the percentage complete in an activity, for example if an activity is 60% complete then the assumption is that 60% of the cost contingency is spent. We recommend for future research, that the method incorporates schedule contingency as well. We also suggest applying the proposed cost contingency management method to different types of projects (i.e. software projects). REFERENCES [1] Lhee, S.C., Flood, I. & Issa, R. 2014, "Development of a two-step neural network-based model to predict construction cost contingency", Journal of Information Technology in Construction, vol. 19, pp J. U. Duncombe, Infrared navigation Part I: An assessment of feasibility, IEEE Trans. Electron Devices, vol. ED-11, pp , Jan [2] Project Management Institute 2013, A Guide to the Project Management Body of Knowledge (PMBOK Guide). Project Management Institute, Incorporated.. [3] Uzzafer, M. 2013, "A contingency estimation model for software projects", International Journal of Project Management, vol. 31, no. 7, pp W.-K. Chen, Linear Networks and Systems, Belmont, CA: Wadsworth, 1993, pp [4] Burroughs, S. & Juntima, G. 2004, "Exploring techniques for contingency setting", AACE International Transactions,, pp. EST3. 1-EST3. 6.R. A. Scholtz, The Spread Spectrum Concept, in Multiple Access, N. Abramson, Ed. Piscataway, NJ: IEEE Press, 1993, ch. 3, pp [5] Touran, A. 2003, "Probabilistic model for cost contingency", Journal of Construction Engineering and Management, vol. 129, no. 3, pp [6] Idrus, A., Fadhil Nuruddin, M. & Rohman, M.A. 2011, "Development of project cost contingency estimation model using risk analysis and fuzzy expert system", Expert Systems with Applications, vol. 38, no. 3, pp [7] Xiong, B. & Xia, B. 2014, "Examining the Effects of Early Cost Drivers on Contingencies", In Castro-Lacouture, Daniel, Irizarry, Javier,& Ashuri, Baabak (Eds.) Construction Research Congress 2014, American Society of Civil Engineers (ASCE), Atlanta, Georgia, USA, pp J. Williams, Narrow-band analyzer, Ph.D. dissertation, Dept. Elect. Eng., Harvard Univ., Cambridge, MA, [8] Eldosouky, I.A., Ibrahim, A.H. & Mohammed, H.E. 2014, "Management of construction cost contingency covering upside and downside risks", Alexandria Engineering Journal, vol. 53, no. 4, pp [9] Barraza, G.A. & Bueno, R.A. 2007, "Cost contingency management", Journal of Management in Engineering, vol. 23, no. 3, pp
Allocation and Management of Cost Contingency in Projects
The University of New South Wales From the SelectedWorks of Alireza Abbasi 2016 Allocation and Management of Cost Contingency in Projects Mohammed W. Hammad, UNSW Australia Alireza Abbasi, UNSW Australia
More informationStochastic Risk Analysis and Cost Contingency Allocation Approach for Construction Projects Applying Monte Carlo Simulation
, July 5-7, 2017, London, U.K. Stochastic Risk Analysis and Cost Contingency Allocation Approach for Construction Projects Applying Monte Carlo Simulation Fahimeh Allahi, Lucia Cassettari, Marco Mosca
More informationEarned Value Management - EVM
Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the
More informationMohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators
Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience
More informationCONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationAnalysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh
Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS
More informationSTOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS
Full citation: Connor, A.M., & MacDonell, S.G. (25) Stochastic cost estimation and risk analysis in managing software projects, in Proceedings of the ISCA 14th International Conference on Intelligent and
More informationA Study on Risk Analysis in Construction Project
A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------
More informationCOST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING
ISSN: 0976-3104 Lou et al. ARTICLE OPEN ACCESS COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING Ashkan Khoda Bandeh Lou *, Alireza Parvishi, Ebrahim Javidi Faculty Of Engineering,
More informationSTOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS
STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS Dr A.M. Connor Software Engineering Research Lab Auckland University of Technology Auckland, New Zealand andrew.connor@aut.ac.nz
More informationThe Cost Monitoring of Construction Projects Through Earned Value Analysis
211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi
More informationEarned Value Management. Danielle Kellogg. Hodges University
Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level
More informationDeveloping a Novel Framework to Manage Schedule Contingency Using Theory of Constraints and Earned Schedule Method
The University of New South Wales From the SelectedWorks of Alireza Abbasi 2016 Developing a Novel Framework to Manage Schedule Contingency Using Theory of Constraints and Earned Schedule Method Mohammed
More informationApplication of Earned Value Management (EVM) for Effective Project Control
Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge
More informationPlanning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique
Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,
More informationRISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT. Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E.
RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E. Texas Research and Development Inc. 2602 Dellana Lane,
More informationManaging Project Risk DHY
Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationApplication of Data Mining Tools to Predicate Completion Time of a Project
Application of Data Mining Tools to Predicate Completion Time of a Project Seyed Hossein Iranmanesh, and Zahra Mokhtari Abstract Estimation time and cost of work completion in a project and follow up them
More informationApplication of Earned Value Analysis in Analysing Project Performance
Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant
More informationEarned Value Management An Overview March 2014
Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process
More informationLesson 7 The Project Budget
MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget
More informationPerformance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods
EPPM, Singapore, 20-21 Sep 2011 Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic Meghdad Attarzadeh 1 and David K H Chua 2 Abstract Estimation and
More informationAn overview of budget contingency calculation methods in construction industry
Creative Construction Conference 2014 An overview of budget contingency calculation methods in construction industry Payam Bakhshi a*, Ali Touran b a Assistant Professor, Wentworth Institute of Technology,
More informationAvailable online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 574 580 Creative Construction Conference 2015 (CCC2015) A method for estimating contingency based on project complexity
More informationProbabilistic Model Development for Project Performance Forecasting Milad Eghtedari Naeini, and Gholamreza Heravi
Probabilistic Model Development for Project Performance Forecasting Milad Eghtedari Naeini, and Gholamreza Heravi Abstract In this paper, based on the past project cost and time performance, a model for
More informationCost Estimate at Completion Methods in Construction Projects
2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Cost Estimate at Completion Methods in Construction Projects Timur Narbaev 1
More informationEarned Value Management Guide
1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress
More informationFebruary 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE)
U.S. ARMY COST ANALYSIS HANDBOOK SECTION 12 COST RISK AND UNCERTAINTY ANALYSIS February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE) TABLE OF CONTENTS 12.1
More informationEARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION
EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY Dr David Hillson PMP FAPM FIRM, Director, Risk Doctor & Partners david@risk-doctor.com www.risk-doctor.com INTRODUCTION In today s uncertain
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More informationPresented at the 2012 SCEA/ISPA Joint Annual Conference and Training Workshop -
Applying the Pareto Principle to Distribution Assignment in Cost Risk and Uncertainty Analysis James Glenn, Computer Sciences Corporation Christian Smart, Missile Defense Agency Hetal Patel, Missile Defense
More informationeurope GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors
eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationFundamentals of Project Risk Management
Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on
More informationTime and Cost Optimization Techniques in Construction Project Management
Time and Cost Optimization Techniques in Construction Project Management Mr.Bhushan V 1. Tatar and Prof.Rahul S.Patil 2 1. INTRODUCTION In the field of Construction the term project refers as a temporary
More informationEquitable Financial Evaluation Method for Public-Private Partnership Projects *
TSINGHUA SCIENCE AND TECHNOLOGY ISSN 1007-0214 20/25 pp702-707 Volume 13, Number 5, October 2008 Equitable Financial Evaluation Method for Public-Private Partnership Projects * KE Yongjian ( ), LIU Xinping
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationUnderstanding the Differences. Accounting Practice for Measuring. Supertech Project Management
Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James
More informationMonitoring and Controlling RCC Work in Delayed Construction Projects
Monitoring and Controlling RCC Work in Delayed Construction s Nimesh Gujarati, Dr. B S Balapgol Post Graduate Student (Construction and Management), DYPCOE, Akurdi, Pune-44, Maharashtra, India Principal,
More informationHow to Satisfy GAO Schedule Best Practices
By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals
More informationTHE PMP EXAM PREP COURSE
THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45
More informationUse of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule
Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,
More informationWhite Paper. Risk Assessment
Risk Assessment The assessment of risk is a very personal process, what is acceptable to one person may be far too risky for another to consider. The appreciation and assessment of risk and a person's
More information9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.
Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control
More informationA Framework for Risk Assessment in Egyptian Real Estate Projects using Fuzzy Approach
A Framework for Risk Assessment in Egyptian Real Estate Projects using Fuzzy Approach By Ahmed Magdi Ibrahim Aboshady A Thesis Submitted to the Faculty of Engineering at Cairo University In Partial Fulfillment
More informationProbabilistic Benefit Cost Ratio A Case Study
Australasian Transport Research Forum 2015 Proceedings 30 September - 2 October 2015, Sydney, Australia Publication website: http://www.atrf.info/papers/index.aspx Probabilistic Benefit Cost Ratio A Case
More informationA MATHEMATICAL PROGRAMMING APPROACH TO ANALYZE THE ACTIVITY-BASED COSTING PRODUCT-MIX DECISION WITH CAPACITY EXPANSIONS
A MATHEMATICAL PROGRAMMING APPROACH TO ANALYZE THE ACTIVITY-BASED COSTING PRODUCT-MIX DECISION WITH CAPACITY EXPANSIONS Wen-Hsien Tsai and Thomas W. Lin ABSTRACT In recent years, Activity-Based Costing
More informationRISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS
RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS Identify, Quantify, and 237 217 200 237 217 200 Manage 237 217 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 80 119 27 252 174.59 110 135 120 112
More informationFinancial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany
1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance
More informationEARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE
EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE Mr. Divyesh Joshi 1, Mr. Vyom B. Pathak 2, Ms. Neetu B. Yadav 3 M.E. Student, Civil Eng. Dept., SNPIT &RC, Umrakh
More informationProject Management and Resource Constrained Scheduling Using An Integer Programming Approach
Project Management and Resource Constrained Scheduling Using An Integer Programming Approach Héctor R. Sandino and Viviana I. Cesaní Department of Industrial Engineering University of Puerto Rico Mayagüez,
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT Planning DETERMINE BUDGET PROCESSES BY PROCESS GROUP Monitoring and Controlling 7.1 Plan Costs Management 7.4 Control Costs 7.2 Estimate Costs 7.3 Determine Budget DETERMINE BUDGET
More informationJefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7
Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,
More informationOptimizing Modular Expansions in an Industrial Setting Using Real Options
Optimizing Modular Expansions in an Industrial Setting Using Real Options Abstract Matt Davison Yuri Lawryshyn Biyun Zhang The optimization of a modular expansion strategy, while extremely relevant in
More informationOptimizing the Incremental Delivery of Software Features under Uncertainty
Optimizing the Incremental Delivery of Software Features under Uncertainty Olawole Oni, Emmanuel Letier Department of Computer Science, University College London, United Kingdom. {olawole.oni.14, e.letier}@ucl.ac.uk
More informationFor the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.
For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com
More informationProject Risk Management
Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management
More informationTHE VALUE OF EARNED VALUE MANAGEMENT
THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs
More informationRISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA
RISK MANAGEMENT 11.1 Plan Risk Management: The process of DEFINING HOW to conduct risk management activities for a project. In Plan Risk Management, the remaining FIVE risk management processes are PLANNED
More informationEarned Value Management
Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards
More informationLikelihood-based Optimization of Threat Operation Timeline Estimation
12th International Conference on Information Fusion Seattle, WA, USA, July 6-9, 2009 Likelihood-based Optimization of Threat Operation Timeline Estimation Gregory A. Godfrey Advanced Mathematics Applications
More informationRunning head: VALUE ANALYSIS REPORTING 1
Running head: VALUE ANALYSIS REPORTING 1 Value Analysis Reporting Benjamin Srock Embry-Riddle Aeronautical University Worldwide Campus Effective Communication for Managing Projects PMGT-502 Ki-Young Jeong,
More informationRISK MITIGATION IN FAST TRACKING PROJECTS
Voorbeeld paper CCE certificering RISK MITIGATION IN FAST TRACKING PROJECTS Author ID # 4396 June 2002 G:\DACE\certificering\AACEI\presentation 2003 page 1 of 17 Table of Contents Abstract...3 Introduction...4
More informationRISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management
AACE International Recommended Practice No. 44R-08 RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management Acknowledgments: John K. Hollmann, PE CCE CEP (Author)
More informationEarning Value From Risk
Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned
More informationAdministration. Course Aim. Introductions
Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may
More informationIran s Stock Market Prediction By Neural Networks and GA
Iran s Stock Market Prediction By Neural Networks and GA Mahmood Khatibi MS. in Control Engineering mahmood.khatibi@gmail.com Habib Rajabi Mashhadi Associate Professor h_mashhadi@ferdowsi.um.ac.ir Electrical
More informationRISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS
N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...
More informationA Literature Review Fuzzy Pay-Off-Method A Modern Approach in Valuation
Journal of Economics and Business Research, ISSN: 2068-3537, E ISSN (online) 2069 9476, ISSN L = 2068 3537 Year XXI, No. 1, 2015, pp. 98-107 A Literature Review Fuzzy Pay-Off-Method A Modern Approach in
More informationRisk Video #1. Video 1 Recap
Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive
More informationUnit 9: Risk Management (PMBOK Guide, Chapter 11)
(PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should
More informationThree Numbers to Measure Project Performance
Dr. Thomas Liedtke Alcatel D 70435 Stuttgart (Germany) Peter Paetzold Alcatel D 70435 Stuttgart (Germany) e_mail: TLiedtke@alcatel.de phone: +49 711 821 40346 fax.: +49 711 821 42230 e_mail: Peter.Paetzold@alcatel.de
More informationThe calculation of optimal premium in pricing ADR as an insurance product
icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) The calculation of optimal premium in pricing ADR as
More informationCost Overrun Assessment Model in Fuzzy Environment
American Journal of Engineering Research (AJER) e-issn : 2320-0847 p-issn : 2320-0936 Volume-03, Issue-07, pp-44-53 www.ajer.org Research Paper Open Access Cost Overrun Assessment Model in Fuzzy Environment
More informationRetirement Villages An Institutional Asset Class?
Author Affiliations University of Technology Sydney, Sydney, Australia Abstract Globally the world is facing an ageing trend and while this trend has been global, seniors housing has remained a local asset
More informationLONG INTERNATIONAL. Rod C. Carter, CCP, PSP and Richard J. Long, P.E.
Rod C. Carter, CCP, PSP and Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
More informationDetailed Project Scheduling and Cost Management
Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute
More informationMonte Carlo for selecting risk response strategies
Australasian Transport Research Forum 2017 Proceedings 27 29 November 2017, Auckland, New Zealand Publication website: http://www.atrf.info Monte Carlo for selecting risk response strategies Surya Prakash
More informationProject Performance Evaluation By Earned Value Method
Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *
More informationMeasures for Cost Escalation in Bridge
Measures for Cost Escalation in Bridge Rahul Munde PG student, M.E.(C&M) Dept. of Civil Engineering DYPSOET, Pune Maharashtra, India rahul.munde77@gmail.com Prof. Ashish Waghmare Assistant Professor Dept.
More information4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring
More informationDecision Support Methods for Climate Change Adaption
Decision Support Methods for Climate Change Adaption 5 Summary of Methods and Case Study Examples from the MEDIATION Project Key Messages There is increasing interest in the appraisal of options, as adaptation
More informationA Scenario-Based Method (SBM) for Cost Risk Analysis
A Scenario-Based Method (SBM) for Cost Risk Analysis Cost Risk Analysis Without Statistics!! September 2008 Paul R Garvey Chief Scientist, Center for Acquisition and Systems Analysis 2008 The MITRE Corporation
More informationMMZG 523 PROJECT MANAGEMENT
MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationThe Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management
The Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management H. Zheng Department of Mathematics, Imperial College London SW7 2BZ, UK h.zheng@ic.ac.uk L. C. Thomas School
More informationIntegrating Contract Risk with Schedule and Cost Estimates
Integrating Contract Risk with Schedule and Cost Estimates Breakout Session # B01 Donald E. Shannon, Owner, The Contract Coach December 14, 2015 2:15pm 3:30pm 1 1 The Importance of Estimates Estimates
More information(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett
(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford
More informationStudy of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun
Study of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun A.G.D.Premalal 1, R.K.P.C.B. Mudalige 1 and S.N.Malkanthi 1 1 Department of Civil and Environmental
More informationEarned Value Management (EVM) and the Acquisition Program
American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.
More informationAn Enhancement of Earthquake Vulnerability Models for Australian Residential Buildings Using Historical Building Damage
An Enhancement of Earthquake Vulnerability Models for Australian Residential Buildings Using Historical Building Damage Hyeuk Ryu 1, Martin Wehner 2, Tariq Maqsood 3 and Mark Edwards 4 1. Corresponding
More informationA Probabilistic Approach to Determining the Number of Widgets to Build in a Yield-Constrained Process
A Probabilistic Approach to Determining the Number of Widgets to Build in a Yield-Constrained Process Introduction Timothy P. Anderson The Aerospace Corporation Many cost estimating problems involve determining
More informationCalifornia Department of Transportation(Caltrans)
California Department of Transportation(Caltrans) Probabilistic Cost Estimating using Crystal Ball Software "You cannot exactly predict an uncertain future" Presented By: Jack Young California Department
More informationPresenting Earned Value
Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What
More informationPrioritization of Climate Change Adaptation Options. The Role of Cost-Benefit Analysis. Session 8: Conducting CBA Step 7
Prioritization of Climate Change Adaptation Options The Role of Cost-Benefit Analysis Session 8: Conducting CBA Step 7 Accra (or nearby), Ghana October 25 to 28, 2016 8 steps Step 1: Define the scope of
More informationStochastic Budget Simulation
PERGAMON International Journal of Project Management 18 (2000) 139±147 www.elsevier.com/locate/ijproman Stochastic Budget Simulation Martin Elkjaer Grundfos A/S, Thorsgade 19C, Itv., 5000 Odense C, Denmark
More information