Water and Sewer Utility Rate Studies

Size: px
Start display at page:

Download "Water and Sewer Utility Rate Studies"

Transcription

1 Final Report Water and Sewer Utility Rate Studies July 2012 Prepared by: HDR Engineering, Inc.

2 July 27, 2012 Mr. Mark Brannigan Director of Utilities 591 Martin Street Lakeport, CA Subject: Comprehensive Water and Sewer Utility Rate Studies Final Report Dear Mr. Brannigan: HDR Engineering, Inc. (HDR) is pleased to present the final report on the comprehensive water and sewer rate studies conducted for the (City). A key objective the City s utility rate studies was to develop a financial plan and rates that generate sufficient revenue to fund the operating and capital needs of each utility. This report outlines the approach, methodology, findings, and conclusions of each utility s rate study. This report was developed utilizing the City s accounting, operating and management records. HDR has relied on this information to develop our analyses, from which we draw our findings, conclusions and recommendations. At the same time, this study was developed utilizing generally accepted utility rate setting principles. The conclusions and recommendations contained within this report are intended to provide a financial plan for each utility that meet each utility s operating and capital needs. Finally, this report provides to the City Council the basis for developing and implementing rates that are cost-based and defensible to the City s utility customers. We appreciate the assistance provided by the City staff in the development of this study. More importantly, we appreciate working with City s staff on this project. We look forward to opportunities to work serve the City in the future. Sincerely yours, HDR Engineering, Inc. Cil Pierce Senior Project Manager and Financial Analyst

3 Table of Contents Executive Summary Introduction... 1 Overview of the Rate Study Process... 1 Summary of Study Results... 1 Water Utility Specific Findings... 3 Sewer Utility Specific Findings... 6 Rate Comparison Summary Overview of Utility Rate Setting Process 1.1 Introduction Background and Context Overview of the Rate Study Process Generally Accepted Rate Setting Principles Prudent Financial Planning Determining the Revenue Requirement Cost of Service Analysis Designing Rates Summary Development of the Water Utility Rate Study 2.1 Introduction Determining the Water Utility Revenue Requirements Water Cost of Service Analysis Water Rate Design Analysis Summary of the Water Rate Study Development of the Sewer Utility Rate Study 3.1 Introduction Determining the Sewer Utility Revenue Requirement Sewer Cost of Service Analysis Sewer Rate Design Analysis Summary of the Sewer Rate Study Technical Appendices Appendix A Water Utility System Analyses Appendix B Sewer Utility System Analyses Appendix C Rate Affordability Water and Sewer Rate Study Contents i

4 This page intentionally left blank. Water and Sewer Rate Study Contents i

5 Executive Summary Introduction HDR Engineering (HDR) was retained by the (City) to conduct a comprehensive water and sewer rate study. The objective of the comprehensive rate study was to develop a financial plan and cost-based rates for each utility necessary to meet each utility s current and future operation and maintenance (O&M) and capital needs. This study also reviews the adequacy of existing water and sewer rates and provides the framework for any needed future adjustments. Overview of the Rate Study Process A comprehensive rate study consists of three interrelated analyses. They are a revenue requirement analysis, cost of service analysis and rate design analysis. Provided below in Figure ES-1 is a summary of these analyses. Figure ES 1 Overview of the Comprehensive of Rate Study Analyses Revenue Requirement Analysis Compares the sources of funds (revenue) to the expenses of the utility to determine the overall rate adjustment required Cost of Service Analysis Allocates the revenue requirements to the various customer classes of service in a fair and equitable" manner Rate Design Analysis Considers both the level and structure of the rate design to collect the target level of revenue Each of the utilities was evaluated on a stand-alone basis. That is, no subsidies between either utility or other City fund should occur. By viewing each utility on a stand-alone basis, the need to adequately fund both O&M and capital infrastructure must be balanced against the rate impacts to the utility s customers. Summary of Study Results In developing the revenue requirement, cost of service, and rate design analyses for each utility, several key assumptions and findings were made. These are as follows: The revenue requirements were developed for each utility for a six-year period of fiscal year, (FY) Water and Sewer Rate Study Executive Summary 1

6 The City s FY 2012 budgets were used as a starting point in developing the rate models, with 2011 actual revenue and expenses available for comparison and projection purposes. Customer growth was estimated to be 0.0% through FY 2014, and 0.5% through the remainder of the test period. All expenses are escalated for inflation, ranging between 3% and 5%. Items escalated at 5% include: benefits, chemicals, fuel, and electricity. Revenues at present rates were calculated for FY 2012 based on actual customer data from FY 2010 and FY 2011 and the current water and sewer rate schedules. The revenue requirements for each utility attempts to provide funding for the following types of reserves, as required by some of the funding sources the City plans to use for capital projects: Operating Reserve of 15% of operating expenses Equates to 55 days of operating expenses. The purpose of this reserve is to provide cash flow during times of low revenue flow. Rate Stabilization/Debt Service Reserves equaling 2 months of rate revenue, or required bond reserve levels This reserve is intended to eventually provide the equivalent of annual debt payment for long-term debt issues to guarantee principle and interest payments. R&R/CIP Reserve targeting 5% of net capital assets Given three measures for targeting a renewal and replacement reserve, this target is the lowest when compared with the other two measures: 1) 6-year average annual capital improvement expenditures, or 2) 1 2% of original asset value. The purpose of this reserve is to ensure funding for any infrastructure replacement emergencies. There are various financial planning measures a utility can employ to ensure funding for infrastructure replacement. HDR recommends targeting a minimum level of annual depreciation expense on an annual basis. This level of funding allows for a utility s infrastructure to be replaced as it is deteriorating over time. Depreciation expense does not reflect actual replacement costs, so depreciation expense should always be seen as a minimum level of funding for capital renewal and replacement projects. Funding depreciation expense through rates also helps the utilities to meet the debt service coverage ratio requirements of the bond and loan covenants. Four alternative funding scenarios were developed for each utility to review the impacts of various levels of depreciation funding. The final recommended rate transition plan results in neither utility achieving the minimum funding level of full depreciation expense, but the scenarios offer options to move in this direction. Each scenario has a different level of risk mitigation with regulators, the higher the scenarios, the less risk and more sustainable approach to funding O&M and capital. The City is working on grant funding opportunities with the USDA Rural Development program. Each utility is potentially eligible for a $1 million grant. Competition for these grants is very steep. Although the City qualifies under the small, economically disadvantaged community profile, less than $1 million is more likely, if any grant funding is provided at all. The funding under each scenario assumes only loan funding in order to make sure that enough funds are generated to fully cover costs. The City should know by November 2012 whether grant funds are available. Should the City be successful in obtaining grant funding, Water and Sewer Rate Study Executive Summary 2

7 the rate model(s) can be adjusted to reflect this funding, thereby reducing the level of rates needed in FY 2015 and beyond, by reducing debt service that is now assumed. The City Council held a public hearing at the July 17, 2012 City Council meeting where Scenario 3, Option 2 rates for the water utility and Scenario 2, Option 2 results and rates for the sewer utility were presented. The City has issued a Proposition 218 notice and will hold a public hearing September 18, 2012 for the final consideration of these rates. Water Utility Specific Findings Revenue Requirement Analysis Using two different sets of data provided by the City, the revenues at present rates were developed. The utility s rate revenue has come in close to budget projections and is on target to do so in FY 2012, Therefore, HDR used the total budgeted revenue as provided by the City, and allocated it to each customer class based on the portion of revenue calculated for each customer class within the revenues at present rates calculation. During FY 2012 through FY 2015 available reserves are used to help fund operating and capital funding deficiencies. By FY 2017 reserves achieve the minimum levels, as noted above. Scenarios 1 funds only operations, existing debt and the reserves described above. Scenario 2, 3, and 4 fund the USDA and SRF funded projects, plus additional projects that are projected within the Utility s latest Master Plan. These Scenarios differ by the level of depreciation expense they are able to fund, with Scenario 4 funding the largest amount, but still not total depreciation expense. An additional $600,000 of debt (low-interest loans) is needed in order to fully fund the Master Plan replacement projects in the latter part of the test period. HDR initially developed a 3-year phased-in rate implementation option. The City requested a 4-year implementation/phased-in approach to funding the total revenue requirement be developed to help lower and mitigate rate impacts. The three year implementation approach meets the 1.5% rate affordability test of the SRF and it results in lower long-term monthly rates, despite the higher increases needed in the second and third years of implementation. For the water utility, a $1 million dollar grant could reduce the average residential household rate by approximately $0.95. Therefore, each $100,000 of grant funding equates to approximately a $0.10/month savings for residential customers. Future year rates can be adjusted in the rate model, and reduced for any grant funding that the City may receive. A summary of the water revenue requirement analysis for Scenario 3 is provided below in Table ES-1. Water and Sewer Rate Study Executive Summary 3

8 Table ES-1 Summary of the Water Revenue Requirements Analysis (000 s) Actual Budget Projected FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 Revenues Rate Revenues $1,150 $1,174 $1,174 $1,174 $1,177 $1,180 $1,183 Miscellaneous Revenues Total Revenues $1,270 $1,281 $1,265 $1,266 $1,270 $1,274 $1,279 Expenses Operations & Maintenance $1,009 $1,145 $1,186 $1,229 $1,274 $1,321 $1,369 Transfers Capital Funded Through Rates Debt Service Change in Working Capital +/- (3) (215) (41) 29 (52) Total Expenses $1,269 $1,235 $1,489 $1,634 $1,940 $2,233 $2,372 Total Revenue Requirement $1,269 $1,235 $1,489 $1,634 $1,940 $2,233 $2,372 Balance/(Deficiency) of Funds $45 ($224) ($368) ($670) ($960) ($1,094) Plus: Bad Debt (4.0% of Rate Rev.) $46 $47 $47 $47 $47 $47 Balance/(Deficiency) with Bad Debt ($1) ($271) ($415) ($717) ($1,007) ($1,141) It should be noted that the balance or deficiencies in any single year are cumulative; any adjustments in the initial years will reduce the deficiency in the following years. Over the six-year period, rates need to be adjusted upwards in order to adequately and properly fund the water utility operations and capital improvements. The cumulative deficiency is $1.1 million, or nearly 100% of current rate revenue. This Scenario proposes the use of reserves, shown as negative values in the change in working capital line item, to help cover deficiencies through Then the reserves are replenished by FY Table ES-1 reflects Scenario 3, funding two-thirds of annual depreciation expense, rather than one-third, or almost fully funding depreciation, Scenarios 2 and 4 respectively. Scenario 3 also allows the utility to complete the USDA and SRF loan and grant funded improvements needed, along with other needed capital improvements later in the test period, as developed within the utility s latest Master Plan. There was a four-year and a three-year implementation approach developed. The four-year implementation period provides a more gradual transition to fully funding the utility s essential operating and capital needs. However, the three-year implementation option has slightly higher rate adjustments over a three year period, results in lower monthly rates overall, due to less use of reserves, so there is less need to replenish the reserves in the latter part of the test period. The three year implementation approach has a two dollar differential per month from the fouryear implementation approach, for the Option 2 rates by FY No rate adjustments are assumed for FY 2017 for either option. The figure below presents all four scenarios, with the three and four year implementation options for Scenario 3, Option 1 rates. Water and Sewer Rate Study Executive Summary 4

9 Because the four-year implementation approach mitigates rate impacts, the City Council determined that would be more acceptable to customers. For the water utility, either the three-year implementation option for Scenario 3 or Scenario 4 is needed to meet the SRF funding agency requirement of rates at 1.5% of median household income. Rate affordability tests were developed and provided to the City. They are provided in Appendix C at the end of this report. Rate Design Analysis The proposed rate designs were based on the results of the revenue requirement analysis. The water rates were designed to collect the targeted revenue as shown in the revenue requirement analysis. Rates were developed using generally accepted rate making methods and principles. While designing rates, it was important to incorporate resource conservation goals that the City had in mind. Therefore, two rate designs were developed. The first rate option simply takes the existing rates and applies the necessary adjustments across the board to all customer classes and rate components. Two rate designs were developed for the water utility. Option 1 applies the necessary adjustments to all rate components and all customer classes. Option 2 adjusts the water allotment available within Tier 1 for each customer class. It also develops a third consumption Tier for the residential customer class to encourage efficient usage. The existing and projected residential rate schedules are presented in Table ES-2. Rate schedules for other customer classes are presented in Section 2 of this report. Recommended Water Rates Option 2 rates for residential, and the Option 1 rates for other customer classes best meet the City s goals and objectives for the study. Option 2 residential rates appear to strengthen the conservation signal of the residential customers by providing a third consumption tier and rate, while providing lower cost Tier 1 rates such that low water users have the possibility of better managing their water bills. Allotments within each tier in each customer class were adjusted to Water and Sewer Rate Study Executive Summary 5

10 reflect average usage within those tiers for each customer class. Within both rate options, each customer class generates the appropriate level of revenue expected from that class of service, based on the revenue currently generated by each class of service. As noted previously, two rate transition plans were developed, a three-year and a four-year plan. At the July 17 th public hearing the City Council selected the four-year implementation plan. Those rates are presented below. Table ES-2 Present and Projected Residential Water Rates Options 1 and 2 for Scenario 3 4-year Implementation Approach Rates for Non-residential customers are provided in Section 2 of this report. Provided the growth, inflation and usage assumptions used to develop the revenue requirements remain the same, the rates presented above should generate the level of revenue required to meet the ongoing operational and capital needs of the water utility through FY Sewer Utility Specific Findings The sewer utility rate study process was very similar to the water utility rate process. Revenue Requirement Analysis The findings of the sewer revenue requirement analysis are provided below. Water and Sewer Rate Study Executive Summary 6

11 Using two different sets of data provided by the City, the revenues at present rates developed. Because year-to-date revenue is tracking close to the FY 2012 budgeted revenue, and this is close to the FY 2011 actual revenue, HDR used the FY 2012 budgeted revenue as a base for projections, and allocated it to each customer class based on the portion of revenue calculated for each customer class within the revenues at present rates. Similar to the water utility, between FY 2012 and FY 2015 operating reserves are used to help cover operating and capital funding deficiencies. By FY 2017 all reserves achieve the minimum levels, as described earlier. Scenarios 1 funds only operations, existing debt and the reserves described above. Scenario 2, 3, and 4 fund the USDA funded projects, plus additional projects that are projected within the utility s last Master Plan. These Scenarios differ by the level of depreciation expense they are able to fund, with Scenario 4 funding the largest amount, but still not total depreciation expense. FY 2011 depreciation was $627,000 and Scenario 4 gradually achieves approximately 50% of depreciation expense funding, or a maximum of $350,000 by FY Funding depreciation expense from rates also helps the utility to meet the debt service coverage ratio requirements. An additional $1.5 million of debt (assumed low-interest loans) is needed in order to complete the Master Plan capital projects. Similar to the water utility, if the City were successful in receiving a $1 million dollar grant this could reduce the average residential household sewer rate by approximately $1.15. Each $100,000 of grant funding equates to approximately a $0.10/month savings for residential customers. Future year rates (FY 2015 and beyond) can be adjusted in the rate model and reduced for any grant funding that the City may receive. The City s goal in designing rates is to have the same service charge throughout the City for each customer class. HDR developed a rate design (Option 2) that phases-in this goal over a three-year period. Initially, the revenue requirements for Scenario 3 were developed for consideration for the sewer utility. However, given the rate adjustments needed for the water utility, the regulatory requirements for both utilities, and in attempting to minimize rate impacts to customers as much as possible, the City requested that Scenario 2 be developed. Therefore, a summary of the sewer revenue requirement analysis for Scenario 2 is provided below in Table ES-3. Water and Sewer Rate Study Executive Summary 7

12 Table ES-3 Summary of the Sewer Revenue Requirements Analysis (000 s), Scenario 2 Budget Projected FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 Revenues Rate Revenues $1,505 $1,505 $1,505 $1,508 $1,512 $1,516 Miscellaneous Revenues Total Revenues $1,699 $1,698 $1,698 $1,703 $1,708 $1,712 Expenses Operations & Maintenance $1,473 $1,526 $1,582 $1,640 $1,701 $1,763 Transfers Capital Funded Through Rates Debt Service Change in Working Capital +/- (194) Total Expenses $1,641 $1,939 $2,102 $2,371 $2,550 $2,627 Total Revenue Requirement $1,641 $1,939 $2,102 $2,371 $2,550 $2,627 Balance/(Deficiency) of Funds $58 ($241) ($403) ($669) ($842) ($915) Plus: Bad Debt (4.0% of Rate Rev.) $58 $60 $60 $60 $60 $60 Balance/(Deficiency) with Bad Debt $0 ($301) ($463) ($729) ($903) ($976) Again, the deficiencies are cumulative. Any rate adjustments made in the earlier years reduce the overall deficiency. Over the six-year period, rates need to be adjusted upwards in order to adequately and properly fund the sewer utility operations and capital improvements. The cumulative deficiency is just under $1 million with the bad debt (unpaid bills) included. This Scenario 2 proposes the use of operating reserves to help cover deficiencies through FY Then the operating reserves are replenished by FY Through the entire test period, the other reserves are gradually funded. The primary difference between Scenario 2 and Scenario 3 for the sewer utility was an additional $300,000 of rate funding of capital improvements in Scenario 3, where in Scenario 2 these improvements are debt financed through assumed low-interest loans. Because debt is spread over a longer period of time, and potentially additional customers in the future, the rate impacts are less for Scenario 2 than for Scenario 3. The utility is still able to meet debt service coverage ratios on a stand-alone basis. Therefore, the City staff and management felt Scenario 2 would be more reasonable for City Council consideration. The results in Table ES-3 reflect Scenario 2, funding a portion of annual depreciation expense. This scenario also allows the utility to complete the USDA loan funded improvements needed, along with other needed capital improvements later in the test period, as developed within the utility s latest Master Plan. Rate Design Analysis Rate design, was therefore, based upon the results of the revenue requirement analysis. Cost- Water and Sewer Rate Study Executive Summary 8

13 based rates were designed to collect the targeted revenue as shown in the revenue requirement analysis. Rates were developed using generally accepted rate making methods and principles. The City s primary rate design goal was to bring customer throughout the City into the same rate schedule. This can ease customer understanding and rate administration. Therefore, two rate designs were developed. The first rate option simply takes the existing rates and applies the necessary adjustments across the board to all customer classes and rate components. Two rate designs were developed for the utility. Option 1 applies the necessary adjustments to all rate components and all customer classes Option 2 over a four year period rates move closer together for the north and south customers. By FY 2015 all customers within each customer class are paying the same rate as customers throughout the City s service area. The existing and Option 1 rate schedules are presented below. Both options apply the necessary adjustments to existing rates to generate adequate revenue from each customer class each year to fully fund sewer utility operations and capital needs. Table ES-4 Sewer Utility Present and Projected Option 1 Rates (Existing Rate Design) Four-year Implementation The rates in Table ES-5 below present Option 2 rates, showing the four-year transition of rates for the north and south areas gradually merging into the same rate City-wide, by customer class, by FY At the July 17, 2012 public hearing, City Council proposed the Option 2 rates with the four-year implementation approach for the Proposition 218 notice, as shown in Table ES-5. The final public hearing is scheduled for September 18, Water and Sewer Rate Study Executive Summary 9

14 Table ES-5 Sewer Utility Present and Projected Rates Option 2 Recommended Rates; Four-year Implementation The rates presented above in Table ES-5 should provide the sewer utility with adequate revenue to properly fund operations and capital needs through FY 2017, provided the underlying assumptions contained within the revenue requirement and rate design (growth, inflation, number of customers, etc.) remain the same. Rate Comparison A rate comparison was requested by the City. It is important to remember, when viewing bill comparisons with other utilities that rate comparisons are often like comparing apples and oranges. Each utility has different operating characteristics, procedures, customer mix, regulatory requirements, governing board decision making policies and practices, and so on. There is also no information collected about when these utilities last updated their rates. However, sometimes a view of rate comparisons can provide perspective of one utility s rates compared to others. The distinguishing operating and infrastructure condition factors must be considered as well. Provided below are comparisons of the City s current and proposed FY 2013 rates with FY 2012 rates of several surrounding utilities. Water and Sewer Rate Study Executive Summary 10

15 The rate comparison for sewer utilities is provided below, using Option 2 rates. Summary These rate studies were developed using generally accepted accounting and rate-setting principles and guidelines. The results of the rate studies for both utilities indicate that each utility is significantly deficient for the projected time period reviewed, through FY Rates are based on revenue requirement results. A cost of service analysis should be repeated in three to five years to determine if any interclass differences exist. All rate implementation scenarios, except Scenario 1, transition the utilities into a more sustainable operating environment of prudent management, where current rate revenue can Water and Sewer Rate Study Executive Summary 11

16 support current operations as well as certain levels of needed capital improvements. That level of support varies by Scenario. Scenarios 3 and 4 help the utilities move to a position where the utilities infrastructure can be maintained and managed in a prudent and proper way to allow the utilities to continue to provide the services into the future, by maintaining the infrastructure and facilities that provide these services in an on-going process. The implementation of the Scenario 3, Option 2 proposed rate adjustments for the water utility and Scenario 2, Option 2 rates for the sewer utility should generate the additional revenue needed to meet each utility s operating and capital needs, along with the financial test requirements of the capital project funding agencies. The proposed rate adjustments also bring equity to all customers in the sewer utility, and provide a stronger conservation signal for the water utility rates, along with the flexibility to manage ones utility bill. Water and Sewer Rate Study Executive Summary 12

17 1.1 Introduction HDR Engineering, Inc. (HDR) was retained by the (City) to perform comprehensive utility rate studies for the City s water and sewer utilities. A rate study determines the adequacy of the existing rates and provide the basis for adjustments for costbased rates. This section of the report describes the methodology applied to complete these utility rate studies for the City. 1.2 Background and Context Section 1 Overview of the Rate Setting Process It is important to describe the services the utilities provide in order to put the context of the rate study results into perspective. High-quality drinking water and sewer systems are essential to public health, business, and quality of life. When one considers everything that tap water delivers safe drinking water, fire protection, support for the economy, the quality of life we enjoy, it is easier to compare water and sewer utility costs with monthly cable bills and cell phone bills to get a perspective on what it costs to have these utility services we often take for granted. The American Water Works Association (AWWA), the water utility industry association, and other utility associations have documented the quantity of our water and sewer infrastructure that is aging and has determined that many communities must significantly increase their levels of investment in repair and rehabilitation of system components to protect public health and safety and to maintain environmental standards. In February, 2012, the AWWA released the most comprehensive-ever study on the need for re-investment in the nation's drinking water infrastructure, to address aging pipes and population shifts. Titled "Buried No Longer," the report evaluates drinking water infrastructure investment needs nationwide and covers the coming 25 to 40 year periods. Key findings include: The needs are large. The cost of replacing pipes at the end of their useful lives and addressing growth will total more than $1 trillion nationwide between 2011 and 2035 and exceed $1.7 trillion by Household water bills will go up. Although water bills will vary by community size and geographic region, for some communities the infrastructure costs alone could triple the size of a typical family's bill. There are import differences based on system size. As with many other costs, small communities with fewer people to share in the costs face the biggest challenge. The costs keep coming. Infrastructure renewal investments are likely to be incurred each year over several decades. For that reason, many utilities may choose to finance infrastructure replacement on a "pay-as-you-go" basis rather than through debt financing. Postponing investment only makes the problem worse. Postponing infrastructure investment in the near-term would raise the overall cost and increase the likelihood of water main breaks and other infrastructure failures. Water and sewer infrastructure is aging and costing more and more each year to maintain, as well as to replace. Where does a utility begin the process of rehabilitation and replacement of Water and Sewer Rate Study Overview of the Rate Study Process 13

18 an infrastructure system? One approach is to initiate and manage a modern, methodical, and sustainable asset renewal process for the City s utilities. The findings of the rate study move the utilities in this direction, while balancing these needs with the rate impacts necessary to provide for proper management of the utilities. These key findings of the AWWA study have also been determining factors in focusing the efforts in the utility rate study over the past year. The results of the analyses show that both the water and sewer utilities need rate adjustments, primarily to fully fund operations, infrastructure renewal and replacement, and to meet fire flow protection requirements. Lakeport is not alone in this reality. There are numerous utilities in California, and across the country, that need to adjust utility rates in order to properly fund and manage their systems in a prudent and responsible manner. A May 2011 Circle of Blue article noted that 30 major metropolitan areas within the U.S. had water rates that increased an average of 9% in Overview of the Rate Study Process A comprehensive study generally consists of three interrelated analyses performed for each utility. Figure 1-1 provides an overview of these analyses. Figure 1 1 Overview of the Comprehensive Rate Analyses Revenue Requirement Analysis Compares the sources of funds (revenues) to the expenses of the utility to determine the overall rate adjustment required Cost of Service Analysis Allocates the revenue requirements to the various customer classes of service in a fair and equitable" manner Rate Design Analysis Considers both the level and structure of the rate design to collect the target level of revenues Each of these technical analyses was conducted for the City s utilities. Each utility was reviewed on a stand-alone basis. At the same time HDR utilized generally accepted rate setting techniques and utility industry best practices in the development of each of the City s utility rate studies. 1.4 Generally Accepted Rate Setting Principles As a practical matter, utilities should consider setting their rates around some generally accepted or global principles and guidelines. Utility rates should be: Cost-based, equitable, and set at a level that meets the utility s full revenue requirement Easy to understand and administer Designed to conform with generally accepted rate setting techniques Water and Sewer Rate Study Overview of the Rate Study Process 14

19 Stable in their ability to provide adequate revenues for meeting the utility s financial, operating, and regulatory requirements Established at a level that is stable from year-to-year from a customer s perspective These principles and guidelines were applied, to the degree possible, in the development of the rate analyses developed for the City. 1.5 Prudent Financial Planning The establishment of financial planning and rate setting policies are intended to provide guidance in the financial planning and rate-setting process, and in the day-to-day financial management of the City s utilities. Adoption of financial policies provides a strong foundation for the long-term financial sustainability of the utilities and provides the outside financial community with a better understanding of the City s commitment to managing the utilities in a financially prudent manner. HDR also recommended some financial practices as part of developing the revenue requirement for each utility. These recommended financial policies and practices are summarized below. Adoption of financial policies provides a strong foundation for the long-term financial sustainability of the utilities... ESTABLISHING MINIMUM OPERATING RESERVE BALANCE The City strives to maintain a cash balance for each utility sufficient to meet the day-to-day cash flow requirements and operating expenses of that utility. A minimum balance equal to 15% of annual O&M expenses is the City s targeted fund balance for each utility, or the equivalent of approximately 55 days of O&M. This provides adequate revenue to maintain adequate levels of service even when cash flows run short or don t exactly track times of increased expenses. ESTABLISHING MINIMUM CAPITAL RESERVE FUNDS Capital reserves are established to fulfill the cash flow requirements of capital infrastructure construction costs, which vary significantly annually, depending on each year s projects and the funding sources available. Within the utility industry, capital reserves are generally established based on an average of projected annual capital expenditures, excluding unusually large one-time capital needs. For each utility, the City should attempt to maintain a capital reserve approximately equal to oneyear of renewal/replacement type projects, or a minimum of 5% of capital assets. This allows the utility to plan for renewal and replacement of the infrastructure. This reserve is also required in order to qualify for outside capital funding. RATE STABILIZATION AND DEBT SERVICE RESERVE This is another reserve to meet certain requirements of outside funding agencies. It is must meet a minimum of debt reserve requirements. Additionally, some revenue should be reserved to provide rate stabilization for future years. DEBT SERVICE COVERAGE TARGET RATIO The annual debt service coverage ratio (DSC) associated with each utility should be greater than or equal to a minimum 1.25 on all outstanding debt that carries a legal bond covenant. Targeting a higher DSC provides the City with greater flexibility in meeting this rate covenant (legal requirement) should revenues fluctuate from year to year. RATE FUNDING FOR RENEWAL AND REPLACEMENT CAPITAL PROJECTS The funding of on-going renewal and replacement capital projects should primarily be funded from rates. The use of long-term debt issues to fund renewal and replacement projects should be minimized Water and Sewer Rate Study Overview of the Rate Study Process 15

20 whenever possible. In order to adequately support this funding method, each utility should budget and fund, at a minimum, an amount equal to or greater than annual depreciation expense. It should be noted that depreciation expense is not the same as replacement cost, but by providing funding at an amount at least equal to annual depreciation expense should provide a steady funding source to help fund replacement capital infrastructure. HDR reviewed the funding of capital from rates for each utility and developed a gradual implementation plan of this prudent financial practice for each utility. This will help each utility to have a consistent funding source and a more sustainable funding approach. This concludes this brief summary of financial planning and rate setting policies related to reserves, funding of replacement capital projects, and debt service coverage ratios. 1.6 Determining the Revenue Requirement In developing the revenue requirements for each utility, each utility is analyzed on a stand alone basis. That is, no other utility or fund can subsidize utility services. The following paragraphs describe the general methodology and approach that HDR used to develop the City s rate studies Establishing a Projected Time Frame Reviewing a multi-year time period is recommended to identify any major expenses that may be on the horizon. The time frame for developing each revenue requirement analysis for this study, was a six-year projected time period, FY 2011/12 to 2016/ Establishing a Methodology and Approach The second step in determining the revenue requirement for the City was to decide on the basis of accumulating costs. For the City s revenue requirements, a cash basis approach was utilized. For municipal utilities, the cash basis approach is the most frequently used methodology. The actual revenue requirement developed for the City was customized to follow each utility s system of accounts (budget documents). Table 1-1 provides a summary of the cash basis approach used to develop the each of the utility s revenue requirements. Public utilities are... theoretically operated at zero profit. As a point of reference, the City s utilities are public utilities. Table 1 1 Overview of the Utility Cash Basis Revenue Requirements for Lakeport + Operations and Maintenance + Transfers + Capital Projects Funded from Rates + Debt Service (P + I); Existing and Future = Total Revenue Requirement Miscellaneous Revenues. = Net Revenue Requirement From Rates In addition, some utilities may include a component for a change in working capital which is a use of, or additional funding for, operating or capital reserves. This component is either used to help mitigate the need for a rate adjustment, or to replenish operating and capital reserves. The Change in Working Capital line item was included in the development of the City s revenue Water and Sewer Rate Study Overview of the Rate Study Process 16

21 requirement for each utility. 1.7 Cost of Service Analysis After the total revenue requirement is determined, it is allocated to the users of the service. The equitable allocation of a utility s costs is usually accomplished via a cost of service analysis. A cost of service analysis allocates costs in a manner that fairly reflects the cost relationships for producing and delivering services. A cost of service study requires three steps: 1. Costs are functionalized or grouped into the various cost categories related to providing service (for example, a water utility is often functionalized to source of supply, treatment, pumping, transmission, distribution, etc.). This step is largely accomplished by the utility s accounting system. 2. The functionalized costs are then classified to specific cost components. Classification refers to the arrangement of the functionalized data into cost components. For example, a water utility s costs are typically classified between average day needs, peak day needs, fire protection, and/or customer-related needs. Sewer utility costs are typically classified between volume of flow, strength of the wastewater, and customer related costs, etc. Solid waste or sanitation and landfill costs are allocated based on number of customers, trips, tonnage of waste, etc. 3. Once the costs are classified into components, they are allocated to the customer classes of service (residential, commercial, etc.). The allocation is based on each customer class relative contribution to the cost component. For example, customer-related costs are allocated to each class of service based on the total number of customers in that class of service. Once costs are allocated, the required revenues for achieving cost-based rates can be determined. Average unit costs (cost-based rates) are also determined within the cost of service and can be used as a starting point for establishing final proposed rate designs. 1.8 Designing Rates The final step of the comprehensive rate study process is the development of rates to collect the desired levels of revenues, based on the results of the revenue requirement and cost of service analysis. In reviewing rate designs, consideration is given to the level of the rates and the structure of the rates Rate Design Criteria and Considerations Prudent rate administration dictates that several criteria must be considered when setting utility rates. Some of these rate design criteria are listed below: Rates which are easy to understand from the customer s perspective Rates which are easy for the utility to administer Consideration of the customer s ability to pay Continuity, over time, of the rate making philosophy Policy considerations (encourage conservation, economic development, etc.) Yield the total revenue requirements Provide long-term revenue stability Promote efficient allocation of the resource Water and Sewer Rate Study Overview of the Rate Study Process 17

22 Equitable and non-discriminatory (cost-based) It is impossible to achieve all of these rate design goals and objectives in a single rate. Given that, these rate design goals and objectives need to be prioritized in order to be able to achieve the utility s overall rate design goals and objectives. For the most part, a major focus should be on establishing rates which are cost-based, equitable and generate sufficient revenues from year-to-year. 1.9 Summary This section of the report has provided a brief introduction to the general principles, techniques, and economic theory used to set water and sewer rates. These principles and methodologies are the basis for the City s analyses discussed herein. The next section of the report discusses the City s water utility rate study. Water and Sewer Rate Study Overview of the Rate Study Process 18

23 2.1 Introduction Section 2 Development of the Water Utility Rate Study A water utility rate study determines the adequacy of the existing water rates and provides the basis for adjustments to cost-based rates. This section describes the methodology, findings, and conclusions of the rate study process conducted for the City s water utility. 2.2 Determining the Water Utility Revenue Requirements The revenue requirement analysis is the first analytical step in the comprehensive rate study process. This analysis determines the overall adequacy of the City s water rates. From this analysis, a determination can be made as to the overall level of water rate adjustment needed to provide adequate and prudent funding for both operating and capital needs. Typically, the main objectives of a water rate study are to develop cost-based rates while attempting to minimize the impacts to the utility s customers. Provided below is a detailed discussion of the development of the revenue requirement analysis for the City s water utility Projecting Water Rate and Other Miscellaneous Revenues The first step in developing the revenue requirement was to develop a projection of water rate revenues, at present rate levels. In general, this process involves developing the projected consumption or billing units for each customer class or group. At the present time, single family residential customers account for approximately 58% of the total revenue. When including apartments, duplex, triplex and mobile home, the total residential accounts for 69% of total utility rate revenue. Commercial accounts for 24% and irrigation another 5%. There is an outside City rate differential for customers outside city limits of 60% above the base meter charge for in-city customers. The overall revenue derived from outside City customers is minimal and accounts for approximately 1% of total utility revenue. In total, at FY 2012 rates, the utility is projected to receive approximately $1.17 million in rate revenue. Over the planning horizon of this study, customer growth was conservatively projected to be relatively flat, at 0% through 2014 and 0.5% thereafter. This results in a projection of total rate revenues of slightly more than $1.18 million in FY In addition to rate revenues, the utility also receives a variety of miscellaneous revenues. These include miscellaneous fee revenue, investment interest, and connection fee revenue.. The utility is projected to receive approximately $106,000 in miscellaneous revenues in FY An assumed decrease in permit revenue reduces the projection of overall miscellaneous revenues to $96,000 by FY On a combined basis, taking into account the water rate revenues along with miscellaneous Water and Sewer Rate Study Water Utility Rate Study 19

24 revenues, the utility s total projected revenues, at present rate levels, are projected to be approximately $1.28 million by FY Projecting Operation and Maintenance Expenses Operation and maintenance (O&M) expenses are incurred by the water utility to operate and maintain the existing plant in service. The costs incurred in this area are expensed during the current year and are not capitalized or depreciated. HDR utilized the City s FY 2012 O&M expenses as a starting point and then escalated the expenses based on an appropriate cost escalation factors. Escalation factors range from 3% to 5%. Labor expenses and most miscellaneous materials and supplies are escalated at 3% per year. Staff benefits (medical) are escalated at 5%, along with chemicals, energy and transfers. Bad debt is assumed to be 4% per year. Total operation and maintenance expenses for the utility are projected to be approximately $1.14 million in FY O&M expenses are projected to increase to approximately $1.36 million by FY 2017, as a result of assumed inflation over that time period. No other extraordinary O&M expense increases or decreases were assumed during the planning period Transfers Each utility pays a transfer to the General Fund in recognition of services provided to the utilities from staff and personnel budgeted in the General Fund. These services include services from the Finance Department, Human Resources, Planning, etc. These expenses begin at $42,000 in FY 2012 and increase to $53,600 by FY 2017, due to inflationary assumptions Projecting Capital Improvement Projects Funded From Rate Revenue Utilities incur a variety of needs for capital improvements. There are three major types of improvements: regulatory driven, growth related, and renewal and replacement capital projects. The utility s capital improvements during the review period include a variety of needs but are primarily regulatory and replacement in nature. Capital improvements total $8.3 million through FY 17. The Capital improvements for the water utility are listed in detail in Exhibit 4 in Appendix A. There are a number of different methods which may be used to fund the water utility s capital improvement plan. The City has applied for a U.S.D.A. Rural Development grant and loan funding for $4.6 million in land purchase and lease and SCADA improvements for water system treatment. There are an additional $2.2 million in wellhead, new wells, pumping station and security improvements that the City applied to the State Revolving Fund (SRF) grant and loan program to fund. The financial plan (revenue requirement) assumes the funding will come in the form of a low-interest loan, or assumes the worst case scenario. This was done to be sure that adequate funding for the projects will be in place. If the City is successful in receiving a grant of up to $1 million, that can reduce future average residential household bills by approximately $0.95. Therefore, each $100,000 of grant funding equates to approximately a $0.10/month savings for residential customers. The City will have the rate models and can adjust future year rates for any grant funding that the City may receive. The remainder of the projects, primarily main replacements and wet well improvements, are funded by capital reserves, rates and an additional $600,000 in low-interest loans. These funding sources are identified for each project in A general financial guideline states that, at a minimum, a utility should fund an amount of capital replacement projects equal to or greater than annual depreciation through rates. Water and Sewer Rate Study Water Utility Rate Study 20

25 Exhibit 4 of Appendix A. A general financial guideline for funding renewal and replacement projects states that, at a minimum, a utility should fund from rates an amount equal to or greater than annual depreciation expense. Annual depreciation expense reflects the current investment in plant being depreciated or losing its useful life. Therefore, this portion of plant investment should be replaced, or put into reserves for future replacement to maintain the existing infrastructure. It must be kept in mind that, in theory, annual depreciation expense reflects an investment in infrastructure an average of 30 to 40 years ago, assuming a 60 to 80 year depreciable life. As a point of reference, the projected FY 2012 depreciation expense for the water utility is estimated to be greater than $250,000. It is assumed the utility s depreciation expense is greater than $250,000 because water main depreciation is not included in the current records available. The estimate of greater than depreciation is based on experience with similar sized utilities. At the present time, it appears that the City is funding approximately $9,000 of capital projects from rates. This is far below the suggested minimum funding level of annual depreciation expense. Therefore, the water revenue requirement Scenarios developed a gradual increase in this funding toward depreciation expense at varying levels for each Scenario, as described below. Scenario 1 Assumes no increase, only operations are funded. Scenario 2 Gradually implements approximately 1/ 3 rd of the estimated depreciation expense over the five year time period. Scenario 3 Gradually implements approximately 2/ 3 rds of the estimated depreciation expense over the five year time period. Scenario 4 Gradually implements approximately The gradual adjustment of rate funded capital, or of funding depreciation expense is done to help moderate rate impacts. In reviewing the various Scenarios with City staff and management, Scenario 3 was determined to be the best option in moving the utility into a more financially stable position, while funding the necessary capital improvements. This Scenario will allow the utility to begin to prepare for infrastructure replacements of pipe lines in poor condition that are necessary to maintain the current level of service, while also complying with various regulatory requirements. This scenario allows the utility to complete the USDA and SRF loan and grant funded improvements needed, along with other needed capital improvements later in the test period, as developed within the utility s 2006 Master Plan. It should also be noted that simply funding an amount equal to annual depreciation expense will not be sufficient to fully fund the replacement of the existing or depreciated facilities. Replacement costs typically are a minimum of twice depreciation expense. Scenario 3 allows the City to gradually move into a position of funding at least depreciation expense. It is important that the City continue to monitor the funding of capital replacements and increase the rate funding level whenever possible Projecting Debt Service The water utility currently has two debt obligations, a revenue bond and a low-interest loan, with an annual payment of approximately $255,000. By FY 2017, given the assumptions above of additional low-interest loans, there will be an additional $336,000 in loan repayments on an annual basis. As noted earlier, any grant funding the water utility receives will help to reduce this principal and interest payment. Water and Sewer Rate Study Water Utility Rate Study 21

26 Revenue bonds contain rate covenants requiring rates to be set at an adequate level to assure meeting specified minimum debt service coverage (DSC) ratio. This is a financial measure of the utility s ability to repay the debt. In general, the DSC is set at a level such that revenues less operating expenses should be at least 1.25 times greater than the maximum annual debt service on the outstanding debt. Given this minimum DSC, it is often prudent to plan or set rates at a level which exceeds this minimum. This guarantees meeting the minimum DSC, and at the same time, provides a slight cushion for unexpected changes. A higher DSC ratio can also strengthen the City s potential to receive a higher bond rating with lower interest on bonds in the future. Bond rating agencies would review the City s past financial strength and ability to repay the bonds. Within this study the minimum DSC ratio is 1.25 for all debt, including the lowinterest loans because City staff has stated that this level of DSC requirement is required within the loan documents. Total debt payments by FY 2017 would be $590,000. The water utility is projected to require a rate adjustment in 2012 to meet the minimum 1.25 requirement, and additional rate adjustments through FY 2015 in order to maintain the DSC ratio of Summary of the Revenue Requirements Given the above projections of revenues and expenses, a summary of the revenue requirement for the City s water utility can be developed. In developing the final water revenue requirement, consideration was given to the City s financial forecast and reserve policies. In particular, emphasis was placed on attempting to minimize rates, while maintaining adequate funds to support the operational activities, capital requirements, and minimum reserve levels throughout the projected time period. Presented in Table 2-1 is a summary of the water revenue requirement for Scenario 3. Detailed analysis can be found in Exhibit 3 of Appendix A. Water and Sewer Rate Study Water Utility Rate Study 22

27 Table 2-1 Summary of the Water Revenue Requirements Analysis (000 s), Scenario 3 Budget Projected FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 Revenues Rate Revenues $1,174 $1,174 $1,174 $1,177 $1,180 $1,183 Miscellaneous Revenues Total Revenues $1,281 $1,265 $1,266 $1,270 $1,274 $1,279 Expenses Operations & Maintenance $1,145 $1,186 $1,229 $1,274 $1,321 $1,369 Transfers Capital Funded Through Rates Debt Service Change in Working Capital +/- (215) (41) 29 (52) Total Expenses $1,235 $1,489 $1,634 $1,940 $2,233 $2,372 Total Revenue Requirement $1,235 $1,489 $1,634 $1,940 $2,233 $2,372 Balance/(Deficiency) of Funds $45 ($224) ($368) ($670) ($960) ($1,094) Plus: Bad Debt (4.0% of Rate Rev.) $46 $47 $47 $47 $47 $47 Balance/(Deficiency) with Bad Debt ($1) ($271) ($415) ($717) ($1,007) ($1,141) Debt Service Coverage Ratio Before Rate Adjustment After Proposed Rate Adjustment Table 2-1 reflects water utility Scenario 3, funding two-thirds of annual depreciation expense, rather than one-third, or almost fully funding depreciation, which are reflected in Scenarios 2 and 4 respectively. It should be noted that the balance or deficiencies in any single year are cumulative; any adjustments in the initial years will reduce the deficiency in the following years. Over the six-year period, rates need to be adjusted upwards in order to adequately and properly fund the water utility operations and capital improvements. The cumulative deficiency is $1.1 million, or nearly 100% of current rate revenue. This Scenario proposes the use of reserves, shown as negative values in the change in working capital line item, to help cover deficiencies through Then the reserves are replenished by FY As noted earlier, an indication of a utility s financial standing is the debt service coverage ratio. Table 2-2 shows that on a stand-alone basis, the water utility needs the proposed rate adjustments in order to meet the minimum DSC requirements of a minimum of There was a four-year and a three-year implementation approach developed. The four-year implementation period provides a more gradual transition to fully funding the utility s essential operating and capital needs. However, the three-year implementation option with slightly higher adjustments over a three year period, results in lower monthly rates overall, due to less use of reserves, so there is less need to replenish reserves in the latter part of the test period. The three year implementation approach has a two dollar differential per month from the four-year implementation approach, for the Option 2 rates by FY No rate adjustments are assumed Water and Sewer Rate Study Water Utility Rate Study 23

28 for FY 2017 for either option. The figure below presents all four scenarios, with the three and four year implementation options for Scenario 3, Option 1 rates. Because the four-year implementation approach mitigates rate impacts, the City Council determined that would be more acceptable to customers. For the water utility, either the three-year implementation option for Scenario 3 or Scenario 4 is needed to meet the SRF funding agency requirement of rates at 1.5% of median household income. Rate affordability tests were developed and provided to the City Review of the Reserve Levels Reserves are an important part of a utility s financial picture. There can be many different purposes for reserves, as described in Section 1 of this report. The water utility had an estimated balance of $615,000 at the beginning of FY For the water utility, the operating reserve runs below the minimum target through FY 2016, but reaches the target by the end of the review period in FY During the planning period the Rate Stabilization/Debt Service Reserve is maintained at the minimum level required for the bond reserve and to meet USDA and SRF requirements. Additionally, the R&R/CIP reserve is gradually increased to meet the funding agency requirements, meeting those requirements by FY Consultant Observations of the Revenue Requirement Scenario 3 will put the utility on the path toward sustaining the existing level of service by gradually funding more infrastructure replacement projects from rates. It will be important for the City to continue to monitor rate funding of capital replacement projects. As the utility s infrastructure continues to age, replacement costs will only continue to rise. Debt financing of facility replacements will not be possible on an on-going basis. It is important to move toward partial rate funding of replacement projects in order to maintain financial stability for the utility in the long-term. Scenario 3 is a reasonable approach toward gradual implementation of such a plan, while balancing rate impacts to customers at the same time. Water and Sewer Rate Study Water Utility Rate Study 24

29 2.3 Water Cost of Service Analysis While the revenue requirement analysis focused on the total level of funding needed to fully fund the utility s needs, a cost of service analysis is concerned with the equitable allocation of the total revenue requirement between the various customer classes of service (e.g., residential, commercial, etc.). The previously developed revenue requirement was utilized in the development of the cost of service analysis. Following the generallyaccepted guidelines and principles of a cost of service analysis will inherently lead to rates which are equitable, costbased, and not viewed as arbitrary or capricious in nature. In recent years, increasing emphasis has been placed on cost of service studies by government agencies, customers, utility regulatory commissions, and other interested parties. This interest has been generated in part by continued inflationary trends, increased operating and capital expenditures, and concerns of equity in rates among customers. Following the generally-accepted guidelines and principles of a cost of service analysis will inherently lead to rates which are equitable, cost-based, and not viewed as arbitrary or capricious in nature Objectives of a Cost of Service Study There are two primary objectives in conducting a cost of service study: Allocate the revenue requirement among the customer classes of service Derive average unit costs for subsequent rate designs The second rationale for conducting a cost of service analysis is to ensure that the rate is designed such that it properly reflects the costs incurred by the City. For example, a water utility incurs costs related to flow, both average day and peak day, fire protection, and customer cost components. A water utility must build sufficient capacity to meet summer peak capacity needs. Therefore, those customers creating this summer peak requirement should pay their fair share of the cost to meet this peak demand. Each of these types of costs may be collected in a slightly different manner as to allow for the development of rates that collect costs in the same manner as they are incurred. Terminology of a Water Cost of Service Analysis Functionalization The arrangement of the cost data by functional category (e.g. source of supply, treatment, etc.). Classification The assignment of functionalized costs to cost components (e.g. commodity, capacity, customer and fire protection related). Allocation Allocating the classified costs to each class of service based upon each class s proportional contribution to that specific cost component. Commodity Costs Costs that are classified as commodity related vary with the total flow of water (e.g. chemical use at a treatment plant). Capacity Costs Costs classified as capacity related vary with peak day or peak hour usage. Facilities are often designed and sized around meeting peak demands. Fire Protection Costs Costs that are related to fire protection services (e.g. hydrants). Customer Costs Costs classified as customer related vary with the number of customers on the system, e.g. metering costs. Direct Assignment Costs that can be clearly identified as belonging to a specific customer group or group of customers General Cost of Service Procedures In order to determine the cost to serve each customer class of service on the City s system, a Water and Sewer Rate Study Water Utility Rate Study 25

30 cost of service analysis is conducted. A cost of service study utilizes a three-step approach to review costs. These were previously discussed in our generic discussion in Section 1, and take the form of functionalization, classification, and allocation. Provided below is a detailed discussion of the water cost of service study conducted for the City, and the specific steps taken within the analysis Functionalization of Costs The first analytical step in the cost of service process is called functionalization. Functionalization is the arrangement of expenses and asset (plant) data by major operating functions within each utility. For example, treatment, pumping, distribution, etc. Within this study, the functionalization of the cost data was largely accomplished through the City s system of accounts Classification of Costs The second analytical task performed in a water cost of service study is the classification of the costs. Classification determines why the expenses were incurred or what type of need is being met. The City s plant accounts and revenue requirement were reviewed and classified using the following cost classifiers: Commodity Related Costs Capacity Related Costs Customer Related Costs Public Fire Protection Related Costs Revenue Related Costs Direct Assignments Key Cost of Service Assumptions A number of key assumptions were used within the City s cost of service study. Below is a brief discussion of the major assumptions used. The test period used for the cost of service analysis was FY 2013, for rate setting purposes. A cash basis approach was utilized which conforms to generally accepted water cost of service approaches and methodologies. The classification of plant in service was developed based upon generally accepted cost allocation techniques. Furthermore, they were developed using the City specific data, when available. When the City specific data was not available, HDR estimated the classification based upon its experience with previous water cost of service studies of a similar nature Summary of Cost of Service Results In summary form, the City s water cost of service analysis began by functionalizing the City s plant asset records and then the operating expenses. The functionalized plant and expense accounts were then classified into their various cost components. The individual classification totals were then allocated to the customer classes based upon the appropriate allocation factors. The allocated expenses for each class were then aggregated to determine each customer class s overall revenue responsibility. For the purposes of cost of service, all residential customer classifications were combined. A summary of the detailed cost responsibility developed by customer class is shown below. Water and Sewer Rate Study Water Utility Rate Study 26

31 When cost of service results by customer class are within 5%+ of the overall utility s need for a rate adjustments, the results are considered to be within cost of service. Based on the findings of the cost-of-service analyses conducted, all customer classes were within 5% of the overall results, with the exception of the motel/b&b customer class and irrigation customer class. With irrigation paying the same rates as other water customers, this would be expected. It is generally understood that irrigation customers contribute to peak demands on the system. Therefore, they are allocated costs based on usage and peaking factors. At the current time, given the level of rate adjustments required, the City s primary goal is to generate adequate revenue to fully fund operating and capital costs for the water utility. Given the necessary revenue adjustments, it is recommended that no cost of service adjustments be implemented at this time. When cost of service interclass adjustments are implemented, rate impacts can be much greater than the overall average adjustment for some customers. Additionally, this is the first comprehensive rate study HDR has completed for the City, and the first rate study for the City in a number of years. It will be important to repeat a cost of service analysis in three to five years to determine if results are consistent with these cost of service results. At that time, the City can determine if the results dictate that interclass differences do exist and whether to make interclass adjustments. Therefore rates were based on the results of the revenue requirement analysis. 2.4 Rate Design Analysis The proposed rate designs were based on the results of the revenue requirement analysis. The water rates were designed to collect the targeted revenue as shown in the revenue requirement analysis. Rates were developed using generally accepted rate making methods and principles. While designing rates, it was important to incorporate resource conservation goals that the City had in mind. Therefore, two rate designs were developed. The first rate option simply takes the existing rates and applies the necessary adjustments across the board to all customer classes and rate components. Option 2 adjusts the water allotment available within Tier 1 for each customer class. It also develops a third consumption Tier for the residential customer class to encourage efficient usage. The existing and projected rate schedules are presented in the following tables. Water and Sewer Rate Study Water Utility Rate Study 27

32 Table 2-2 Present and Projected Residential Water Rates Options 1 and 2 for Scenario 3 4-year Implementation Approach Meter charges are the same for both options, but for Option 2 residential, there are three consumption tiers. Water and Sewer Rate Study Water Utility Rate Study 28

33 Table 2-3 Present and Projected Multi-unit and Commercial Water Rates Scenario 3, 4-year Implementation Recommended Water Rates Option 2 rates for residential, and the Option 1 rates for other customer classes best meet the City s goals and objectives for the study. Option 2 residential rates appear to strengthen the conservation signal of the residential customers by providing a third consumption tier and rate, while providing lower cost Tier 1 rates such that low water users have the possibility of better managing their water bills. Allotments within each tier in each customer class were adjusted to reflect average usage within those tiers for each customer class. Within both rate options, each customer class generates the appropriate level of revenue expected from that class of service, based on the revenue currently generated by each class of service. As noted previously, two rate transition plans were developed, a three-year and a four-year plan. The three year meets the SRF financial affordability test sooner, and results in lower rates in the long-run. However, the City requested that a four-year implementation plan be developed. The City Council has elected to move forward with staff s recommendation for Option 2 rates for the Water and Sewer Rate Study Water Utility Rate Study 29

34 residential customer class. The rates for other customer classes: duplex, mobile home, apartments, motel, bed and breakfast and commercial are shown in the Table 2-3. For these customers, the existing rate structure is maintained, but the allotments for each tier are adjusted to reflect current average water usage by meter size. City Council also approved this Option 1 rate proposal for the other customer classes. Provided the growth, inflation and usage assumptions used to develop the revenue requirements remain the same, the rates presented above should generate the level of revenue required to meet the on-going operational and capital needs of the water utility through FY Rate Comparison A rate comparison was requested by the City. It is important to remember, when viewing bill comparisons with other utilities that rate comparisons are often like comparing apples and oranges. Each utility has different operating characteristics, procedures, customer mix, regulatory requirements, governing board decision making policies and practices, and so on. There is also no information collected about when these utilities last updated their rates or whether they may be under moratoriums or have regulatory compliance orders. However, sometimes a view of rate comparisons can provide perspective of one utility s rates compared to others. The distinguishing operating and infrastructure condition factors must be considered as well. Provided below are comparisons of the City s current and proposed FY 2013 rates with FY 2012 rates of several surrounding utilities. 2.5 Summary of the Water Rate Study The analyses completed for the water utility were completed using generally accepted rate setting principles and guidelines, based on the City s accounting records and utility billing data. The results of the revenue requirement indicate that the existing rate revenue is deficient for meeting future operating and capital needs of the utility. Provided the growth, inflation and usage assumptions used to develop the revenue requirements remain the same, the rates presented above should generate the level of revenue required to meet the on-going operational and capital needs of the water utility through FY Water and Sewer Rate Study Water Utility Rate Study 30

35 3.1 Introduction Section 3 Development of the Sewer Utility Rate Study This section describes the development of the sewer rate study for the City. Similar to the water rate study, a revenue requirement, cost of service and rate design analysis was conducted for the sewer utility. One of the main objectives of a sewer rate study is to develop cost-based rates while attempting to minimize the impacts to the utility s customers. Provided below is a detailed discussion of the technical analyses, along with our findings, conclusions and recommendations. 3.2 Determining the Sewer Utility Revenue Requirement Similar to the water utility, the sewer revenue requirement assumes the full and proper funding on a stand-alone basis needed to operate and maintain the system on a financially sound and prudent basis. The primary financial inputs in this process were the utility s historical billing records, current and projected operating budgets, and projected capital improvement plan. The sewer revenue requirement analysis was developed using the cash basis approach presented and discussed in Section 1 of this report Projecting Sewer Rate and Other Miscellaneous Revenues The first step in developing the sewer revenue requirement was to develop a projection of rate revenues, at present rate levels. In general, this process involved developing projected billing units for each customer group. The billing units for each customer group were then multiplied by the current applicable sewer rates. This method of independently calculating sewer rate revenues verifies that the projected revenues used within the analysis related directly to the projected billing units. The projected billing units by class of service were based on historical billing records. Currently, the City has three major sewer classes of service: residential, apartments and commercial. Based on the billing records, roughly 60% of the utility s rate revenues are derived from residential customers. In total, at present rates, the City is projected to receive approximately $1.5 million in rate revenue in FY With the same conservative annual growth estimates as estimated for the water utility (0% for through 2014, 0.5% FY 2015 though FY 2017) rate revenue is projected to total $1.51 million by FY In addition to rate revenues, the utility also receives a variety of miscellaneous revenues which include Basin 2000 revenue, County Service revenue, lease revenue, miscellaneous revenue and interest income. Other miscellaneous revenue averages $195,000 per year through the review period. On a combined basis, taking into account the rate revenues along with miscellaneous revenues, the utility s total projected revenues are expected to be approximately $1.69 million in FY 2012 and increasing to $1.71 million by FY Projecting Operation and Maintenance Expenses Operation and maintenance (O&M) expenses are incurred by the utility to operate the sewer utility and maintain the existing plant in service in a sustainable manner. The costs incurred in this area are expensed during the current year and are not capitalized or depreciated over time. Water and Sewer Rate Study Sewer Utility Rate Study 31

36 Escalation factors were developed for the basic types of expenses the sewer utility incurs: labor, benefits, materials and supplies, utilities, insurance, and miscellaneous expenses. Consistent with the water utility, the medical benefit escalation factor was assumed to be 5% per year over the planning horizon, along with chemicals, energy and transfers, the same factors as those used for the water utility. Bad debt is also assumed to be 4% per year. Most expense types used 3% per year escalation, including labor. Operation and maintenance (O&M) expenses are... costs incurred in this area are expensed during the current year and are not capitalized or depreciated over time HDR reviewed the utility s FY 2011 and 2012 budget and used them as the basis for projected expenses into future years. Given the FY O&M expenses, HDR then escalated the O&M expenses based on the escalation factors described above. Total operation and maintenance expenses for the utility are projected to be approximately $1.47 million in FY 2012 and are projected to increase to approximately $1.76 million by FY 2017, primarily as a result of assumed inflation over the time period. No other changes to sewer O&M expenses were assumed through FY Transfers Each utility pays transfers to the General Fund for services provided to the utilities from staff and personnel budgeted in the General Fund. These services include Management and Administration, services from Human Resources, Clerk s Office, the Finance Department, Planning, etc. These expenses begin at $45,000 in FY 2012 and increase to $57,000 by FY In addition, the sewer utility transfers Basin 2000 expenses to pay for debt associated with past improvements. This expense is offset by the Basin 2000 revenue that is received from North service area customers Projecting Capital Improvement Projects Funded From Rate Revenue The sewer utility has several replacement and improvement projects scheduled for the collection system as well as the treatment plant. Projects include sewer line replacements, life station replacements, Infiltration and Inflow (I&I) reduction program (which also includes pipe replacements), equipment replacement and repairs and modifications at the treatment plant. Specific projects include Martin Street, Main Street, Lakeshore Blvd. and North High Street parallel lines, Main Street sewer replacement, Clearlake lift station replacement, and several others. These improvements are needed to maintain the existing level of service, replace system components no longer functioning properly, and to meet regulatory requirements. In total, there is approximately $5.4 million in projected capital projects through FY Funding is assumed to be $3.2 million as a U.S.D.A. Rural Development low-interest loan. Another $1.7 million is assumed to be other future year low-interest loans, and $500,000 of rate funding over the next five years. As described in Section 1 and 2, a general financial guideline for financial stability states that, at a minimum, a utility should fund an amount equal to or greater than annual depreciation expense through rates. Annual depreciation expense reflects the current investment in plant being depreciated or losing its useful life. Therefore, this portion of plant investment needs to be replaced to maintain the existing level of infrastructure. Simply funding an amount A general financial guideline states that, at a minimum, a utility should fund an amount equal to or greater than annual depreciation through rates Water and Sewer Rate Study Sewer Utility Rate Study 32

37 equal to annual depreciation expense will not be sufficient to replace the existing or depreciated facility. The sewer utility s depreciation expense for FY 2011 was $627,000. As additional capital improvements are completed, depreciation expense will increase. Replacement cost, on average, is roughly two times annual depreciation. Therefore, consideration should be given to funding within rates some amount greater than annual depreciation expense for renewals and replacements. Similar to the water rate study, four funding scenarios were developed, adjusting the gradual level of rate funding of depreciation expense at varying levels for each Scenario, as described below. Scenario 1 Assumes no increase, only operations are funded. Scenario 2 Gradually implements approximately 1/ 3 rd of the estimated depreciation expense over the five year time period. Scenario 3 Gradually implements approximately 2/ 3 rds of the estimated depreciation expense over the five year time period. Scenario 4 Gradually implements approximately The gradual adjustment of rate funded capital, or of funding depreciation expense is done to help moderate rate impacts. In reviewing the various Scenarios with City staff and management, Scenario 2 was determined to be the best option in moving the utility into a more financially stable position, while funding the necessary capital improvements. This Scenario will allow the amount of capital improvements funded to increase gradually, from approximately $40,000 in FY 2012 to $125,000 over this planning horizon. The sewer utility achieves less rate funding of capital than the water utility, as staff and management felt that a lower level of rate funding for the sewer utility should be recommended to minimize the rate impacts to the degree possible. Whenever possible, the City should continue to increase rate funding of capital projects to move closer to funding the minimum of depreciation expense over time Projecting Debt Service The final component of the sewer revenue requirement is debt service. At the present time, the sewer utility has one outstanding debt issue, a 2007 revenue bond with debt payments of approximately $187,000 annually. There is new debt assumed for the U.S.D.A loan and other low-interest loans. The U.S.D.A. loan will have an annual payment of approximately $122,000 estimated to begin in FY The other low-interest loan payments are estimated to begin in FY 2015 at $4,000 per year and increase to $76,000 by FY In total, the annual debt payments are projected to be $387,000 by FY It is important to note that the City has applied for grant funding for a portion of the U.S.D.A. loan. If successful, the City could receive up to $1 million in grant funding, with the remainder of the total costs through the low-interest loan. This could potentially reduce debt payments by $37,000 per year, or the equivalent of approximately a 1.5% to 2% reduction in projected rates, or $1.15 reduction in the monthly payment for an average residential bill. This equates to approximately a $0.10 savings per month on average residential monthly bills per each $100,000 of grant funding that potentially replaces loan funding. The City is scheduled to find out in November 2012 the mix of loan and possible grant funding. The City will have the rate models and can update rate projections for future years depending on what financing becomes available. To meet requirements of the revenue bond and U.S.D.A. loans a utility must meet a debt service coverage requirement (DSC; a covenant of the revenue bonds) of That means that the Water and Sewer Rate Study Sewer Utility Rate Study 33

38 utility would have 25% more than the highest annual debt payment in all years, or 125% of the highest principal and interest payment over the term on the bond. The sewer utility is barely meeting this requirement in FY 2012 and a significant rate adjustment is needed to meet the requirement in FY In future years, additional rate increases are needed to continue to meet this financing requirement Summary of the Revenue Requirement Given the above projections of revenues and expenses, a summary of the revenue requirement for the sewer utility was developed. In developing the final revenue requirement, consideration was given to the financial planning considerations of the City. In particular, emphasis was placed on attempting to minimize rates, yet maintain adequate funds to support the operational activities and capital projects throughout the projected time period. As part of the rate study, Scenario 3 was initially developed and presented to the City for consideration. Upon review and further consideration the City determined that Scenario 2 would best meet the needs of the utility while maintaining rates as low as possible. Presented in Table 3-1 is a summary of the sewer revenue requirement for Scenario 2. Detailed analysis can be found in Exhibit 3 of Appendix B. Table 3-1 Summary of the Sewer Revenue Requirements Analysis (000 s), Scenario 2 Budget Projected FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 Rate Revenues $1,505 $1,505 $1,505 $1,508 $1,512 $1,516 Miscellaneous Revenues Total Revenues $1,699 $1,698 $1,698 $1,703 $1,708 $1,712 Expenses Operations & Maintenance $1,473 $1,526 $1,582 $1,640 $1,701 $1,763 Transfers Capital Funded Through Rates Debt Service Change in Working Capital +/- (194) Total Expenses $1,641 $1,939 $2,102 $2,371 $2,550 $2,627 Total Revenue Requirement $1,641 $1,939 $2,102 $2,371 $2,550 $2,627 Balance/(Deficiency) of Funds $58 ($241) ($403) ($669) ($842) ($915) Plus: Bad Debt (4.0% of Rate Rev.) $58 $60 $60 $60 $60 $60 Balance/(Deficiency) with Bad Debt $0 ($301) ($463) ($729) ($903) ($976) Debt Service Coverage Ratio Before Rate Adjustment After Proposed Rate Adjustment It is important to remember that the annual deficiencies in the Table 3-1 are cumulative. That is, any adjustments in the initial years will reduce the deficiency in the later years. Over the projected time period the deficiency in FY 2017 is $976,000. For the average residential bills Water and Sewer Rate Study Sewer Utility Rate Study 34

39 this equates to approximately $29.00/month over the five year period, or an average of approximately $6.00/year adjustment in the average monthly bills. These adjustments are necessary in order to maintain the existing level of service, adequately fund the utility s O&M and capital infrastructure needs, and to meet debt service financial requirements. These needed adjustments are primarily driven by the need to increase the funding of capital improvements from rates ( Capital Funding from Rates ), debt payments, and inflationary increases in O&M expenses. As discussed previously, funding of capital improvements from rates for renewal and replacement projects is an important financial concept. It also helps the utility to meet the DSC coverage requirement. With proper maintenance and rehabilitation of the City s sewer system, the useful life of the system can be maximized Review of the Reserve Levels A review of reserves was also completed. Reserves are an important part of a utility s financial picture. There are many different purposes for reserves, as described in Section 1 of this report. This section reviews each of the necessary reserves for the sewer utility. The sewer utility operation reserve, with a target of 15% of operating expenses, begins FY 2012 with approximately $525,000 and ends FY 2017 with a balance of $270,000. Operating reserves are used, as necessary, to meet expenses of the utility to aide in levelizing rate adjustments to the degree possible. This reserve provides cash flow for the utility s on-going expenses. In the mid-years of the review period the fund balance drops below this minimum requirement (FY ) but ends the review period at the minimum reserve level. During the review period the Rate Stabilization/Debt Service Reserve and the R&R/CIP Reserve are gradually built to meet the minimum level required for the bond reserve and to meet USDA requirements. By FY 2017 the utility is able to meet all reserve requirement minimum balances Consultant s Conclusions for Sewer Revenue Requirement Based on the Scenario 2 revenue requirement analysis, there is a deficiency of funds over the entire projected time period. Adjustments to the existing rates are necessary and recommended to adequately fund the operations, maintenance and capital needs of the utility. It will be important for the City to continue to monitor rate funding of capital replacement projects. As the utility s infrastructure continues to age, replacement costs will only continue to rise. Debt financing of facility replacements will not be possible on an on-going basis. It is important to continue to gradually increase rate funding of replacement projects in order to maintain financial stability for the utility and to meet debt service coverage requirements in the long-term. Scenario 2 is an approach toward gradual implementation of such a plan, while balancing rate impacts to customers at the same time. The next subsection discusses the allocation of the sewer revenue requirements to the various customer classes of service. Water and Sewer Rate Study Sewer Utility Rate Study 35

40 3.3 Sewer Cost of Service Analysis A cost of service analysis is a method to equity allocate the total revenue requirements to the various customer classes of service served by the utility. For the sewer cost of service study, the customer classes of service were defined as residential, commercial and apartments. The same generally accepted rate setting principles and methodologies, as used for the water utility, were applied to develop the sewer cost of service analysis. This process functionalized, classified and allocated the sewer revenue requirement to the customer classes in the manner in which the utility incurs the expense. When available, utility specific data was utilized. When the City specific data was not available, HDR estimated the classification based upon its experience with previous sewer cost of service studies of a similar nature Objectives of a Cost of Service Study There are two primary objectives in conducting a cost of service study: Allocate the revenue requirement among the customer classes of service Derive average unit costs for subsequent rate designs Classification of Costs The cost classifiers for the sewer utility differ from the water utility. Classification determines why the expenses were incurred or what type of need is being met. The City s plant accounts and revenue requirement were reviewed and classified using the following cost classifiers: Volume Related Costs Strength Related Costs Customer Related Costs Revenue Related Costs Direct Assignments Summary of the Cost of Service Results In summary form, this cost of service analysis began by functionalizing the utility s plant asset records and then the operating expenses. The functionalized plant and expense accounts were then classified into their various cost components. The individual classification totals were then allocated to the various customer groups based upon the appropriate allocation factors. The allocated expenses for each customer group were then aggregated to determine each Terminology of a Sewer Cost of Service Analysis Functionalization The arrangement of the cost data by functional category (e.g. treatment, collection etc.). Classification The assignment of functionalized costs to cost components (e.g. volume, strength, and customer related). Allocation Allocating the classified costs to each class of service based upon each class s proportional contribution to that specific cost component. Volume Costs Costs that are classified as volume related vary with the total flow of sewer (e.g. chemical use at a treatment plant). Strength Costs Costs classified as strength related refer to the wastewater treatment function. Typically, strength-related costs are further defined as biochemical oxygen demand (BOD) and suspended solids (SS). Different types of customers may have high wastewater strength characteristics and high strength wastewater costs more to treat. Facilities are often designed and sized around meeting these costs. Customer Costs Costs classified as customer related vary with the number of customers on the system, e.g. billing costs. Direct Assignment Costs that can be clearly identified as belonging to a specific customer group or group of customers. Water and Sewer Rate Study Sewer Utility Rate Study 36

41 customer group s overall revenue responsibility. A summary of the detailed cost responsibility developed by customer class is shown below. The allocation of costs attempted to equitably allocate facilities and costs to each customer class reflecting their respective benefit. The cost of service results indicated that some costs differences exist between the customer classes of service. A general rule of thumb that can be used as a guide when reviewing a cost of service analysis is if a class is within +/- 5% of the overall required adjustment the class is paying its fair share. The results are close to within this particular guideline, however, results also show an interclass cost differential. This analysis is completed on one year s data and customer information, and flow characteristics change over time. This is the first comprehensive rate study HDR has completed for the City, and that the City has had completed in several years. It would be appropriate to repeat the cost of service analysis during the next rate study and determine whether these findings are consistent over time, then adjust as appropriate Consultant s Conclusions and Recommendations Based upon the findings of the cost-of-service analyses conducted, the residential customer class is within 4% of the overall results. However there are interclass differences with the apartments and commercial customer classes. As noted earlier, there were discrepancies in the data when calculating the revenues at present rates. Therefore, these results could be skewed by incomplete data. Given the overall objective for the sewer utility to be financially stable and self sufficient, it is recommended the overall level of rates be adjusted to collect the revenue requirements over the test period. Therefore, all customer class rates are adjusted equally. A cost of service analysis should be completed a minimum of every five years to determine if revenue is received according to the impact each customer class has on the system. 3.4 Sewer Rate Design Analysis The final step of the sewer rate study process is the design of sewer rates to collect the desired levels of revenues, based on the results of the revenue requirement analysis. In reviewing sewer rate designs, consideration is given to the level and the structure of the rates Review of the Overall Rate Adjustments As indicated above, the priority for the sewer utility was to adjust and transition the overall level of the sewer rates to meet the overall financial needs of the utility for both operations and Water and Sewer Rate Study Sewer Utility Rate Study 37

42 capital replacement needs, while minimizing rate impacts to the degree possible Present and Proposed Sewer Rates In developing the proposed rate designs, the City s existing rate structures were reviewed. The existing rates are comprised of a monthly charge by class of service for residential and apartments, and for commercial there is an additional consumption charge per hundred cubic feet of usage. There are currently differing rates between the north and south service areas. This difference, in part, is related to the Basin 2000 charges. The City s primary rate design goal was to apply the same rate schedule to customers within each class of service, throughout the City. This can ease customer understanding and City administration. Therefore, two rate designs were developed. The first rate option simply takes the existing rates and applies the necessary adjustments across the board to all customer classes and rate components. Two rate designs were developed for the utility. Option 1 applies the necessary adjustments to all rate components and all customer classes Option 2 over a four year period, rates move closer together for the north and south customers. By FY 2015 all customers within each customer class are paying the same rate throughout the City s service area. The existing and Option 1 rate schedules are presented below. Table 3-2 Sewer Utility Present and Projected Option 1 Rates (Existing Rate Design) Four-year Implementation Both options apply the necessary adjustments to existing rates for each customer class to generate adequate revenue to fully fund sewer utility operations and capital needs each year. Water and Sewer Rate Study Sewer Utility Rate Study 38

43 The rates in Table 3-3 below present Option 2 rates, showing the four-year transition of rates for the north and south areas gradually merging into the same rate City-wide, by customer class, by FY Table 3-3 Sewer Utility Present and Projected Rates Option 2 Recommended Rates; Four-year Implementation The rates presented above in Table 3-3 should provide the sewer utility with adequate revenue to properly fund operations and capital needs through FY 2017, provided the underlying assumptions contained within the revenue requirement and rate design (growth, inflation, number of customers, etc.) remain the same. The City Council proposed these rates to be presented in Proposition 218 documents to the utility s customers and property owners Rate Affordability The is designated as an economically disadvantaged community. As such, it is eligible for more grant funding and lower interest loans for some capital projects, especially if rates begin to reach a level considered by funding agencies to be unaffordable. Various government funding agencies consider individual residential utility rates between 1.5% and 2.5% of the median household income to be an affordability issue. This level of rate typically qualifies a jurisdiction for lower cost capital project funding. For example, if the sewer utility monthly rate is 1.5% of the median household income, the City may qualify for the grant funding from the U.S.D.A. The affordability test was completed for Scenario 3 and Scenario 2 for the sewer utility, and had similar results. Results for Scenario 2 are provided in Appendix C at the end of this report. The utility s existing rates already fail the 1.5% affordability test. That is, they are considered less affordable, especially in a disadvantaged community. As the necessary rate adjustments are applied out in future years, this failed test status remains and increases to beyond the 2% affordability test by FY It should be noted that for this analysis, the City provided the Water and Sewer Rate Study Sewer Utility Rate Study 39

44 median household income and no adjustment or increase was made to the median household income in calculating the percentage of household income in future years Rate Comparison The City also requested a bill comparison for the sewer utility with other similar sized local utilities. It is important to remember, when viewing bill comparisons with other utilities that these comparisons are often like comparing apples and oranges. Each utility has different operating characteristics, procedures, customer mix, regulatory requirements, governing board decision making policies and practices, and so on. There is also no information collected about when these utilities last updated their rates. That said, sometimes a view of rate comparisons can provide perspective of one utility s rates compared to others. However, the distinguishing operating and infrastructure condition factors must be considered as well. Provided below are comparisons of the City s current and proposed FY 2013 rates with FY 2012 rates of several surrounding utilities. It does appear that the existing as well as proposed rates are higher than sewer rates of surrounding utilities. This is, in part, why City management looked toward Scenario 2 as a more reasonable option for the sewer utility. It is still imperative to remember that operating and capital costs must be fully funded fop the utility to continue to provide these services within the constraints of water quality regulations that are imposed on the City. It is not known how many other utilities are also considering adjustments to their rates. 3.5 Summary of the Sewer Rate Study This completes the analysis for the City s sewer utility. The rate adjustments and corresponding rate designs were developed using generally accepted rate setting methodologies and are based on accounting and budgeting information provided by the City. The proposed rates are intended to provide adequate revenue to maintain the sewer utility system in a sustainable manner. Water and Sewer Rate Study Sewer Utility Rate Study 40

Comprehensive Water Rate Study

Comprehensive Water Rate Study Final Report Dublin San Ramon Services District Comprehensive Water Rate Study January 213 Prepared by: HDR Engineering, Inc. January 1, 213 Ms. Lori Rose Financial Services Manager Dublin San Ramon Services

More information

The City of Sierra Madre

The City of Sierra Madre The City of Sierra Madre Comprehensive Water and Wastewater Cost of Service Study Report / December 24, 2018 24640 Jefferson Avenue Suite 207 Murrieta, CA 92562 Phone 951.698.0145 www.raftelis.com December

More information

City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY

City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY Summary of Findings October 2003 Financial Consulting Solutions Group, Inc. 8201 -- 164th Ave. NE, Suite 300, Redmond, WA

More information

WATER AND SEWER RATE STUDY

WATER AND SEWER RATE STUDY FINAL WATER AND SEWER RATE STUDY B&V PROJECT NO. 179322.0100 PREPARED FOR City of Lynwood, CA JANUARY 11, 2017 Black & Veatch Holding Company 2011. All rights reserved. City of Lynwood, CA WATER AND SEWER

More information

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013

MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013 MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT September 2013 10540 TALBERT AVENUE, SUITE 200 EAST FOUNTAIN VALLEY, CALIFORNIA 92708 P. 714.593.5100 F. 714.593.5101 MARINA

More information

YORK COUNTY, SOUTH CAROLINA

YORK COUNTY, SOUTH CAROLINA YORK COUNTY, SOUTH CAROLINA Water and Sewer Financial Planning and Rate Study Report October 25, 2017 1031 S. Caldwell Street Suite 100 Charlotte, NC 28203 Phone 704.373.1199 Fax 704.373.1113 www.raftelis.com

More information

Santa Clarita Water Division

Santa Clarita Water Division Santa Clarita Water Division Retail Water Rate Cost of Service Study Report September 2017 445 S Figueroa St Suite 2270 Los Angeles, CA 90039 Phone 213.262.9300 www.raftelis.com September 11, 2017 Mr.

More information

City of La Palma Agenda Item No. 5

City of La Palma Agenda Item No. 5 City of La Palma Agenda Item No. 5 MEETING DATE: January 19, 2016 TO: FROM: SUBMITTED BY: CITY COUNCIL CITY MANAGER Mike Belknap, Community Services Director AGENDA TITLE: Adopt a Resolution Approving

More information

Introduction to Water and Sewer Fund Needs August 11, 2017

Introduction to Water and Sewer Fund Needs August 11, 2017 Introduction to Water and Sewer Fund Needs August 11, 2017 A lot of good things are happening in Buffalo and we hope to make some exciting announcements in the months to come, especially about possible

More information

Squaw Valley PSD. Water & Sewer Rate and Connection Fee Study. Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc.

Squaw Valley PSD. Water & Sewer Rate and Connection Fee Study. Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc. Squaw Valley PSD Water & Sewer Rate and Connection Fee Study February 15, 2017 Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc. Purpose of the District s Study Provide sufficient

More information

CITY OF THOUSAND OAKS

CITY OF THOUSAND OAKS CITY OF THOUSAND OAKS 2018 Wastewater Financial Plan Update Final Report / June 23, 2017 445 S. Figueroa Street Suite #2270 Los Angeles, CA 90071 Phone 213.262.9300 Fax 213.262.9303 www.raftelis.com June

More information

City of Riverbank. Water Rate Study FINAL 6/18/2015

City of Riverbank. Water Rate Study FINAL 6/18/2015 Water Rate Study FINAL 6/18/2015 Bartle Wells Associates Independent Public Finance Consultants 1889 Alcatraz Avenue Berkeley, California 94703 www.bartlewells.com Tel: 510-653-3399 June 18, 2015 6707

More information

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by:

CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY. Prepared by: CITY OF REDLANDS WATER AND WASTEWATER RATE STUDY Prepared by: August 30, 2010 201 S. Lake Blvd, Suite 301 Pasadena CA 91101 Phone Fax 626 583 1894 626 583 1411 www.raftelis.com August 30, 2010 Mr. Chris

More information

La Cañada Irrigation District

La Cañada Irrigation District La Cañada Irrigation District Water Rate Study Report - 2009 March, 2009 201 S. Lake Blvd, Suite 803 Pasadena CA 91101 Phone Fax 626 583 1894 626 583 1411 www.raftelis.com March 30, 2009 Mr. Douglas M.

More information

City of Cocoa FY 2010 Utility Rate Study. Final Report. Water, Sewer & Reclaimed Water Rates, Fees & Charges Study. Prepared by:

City of Cocoa FY 2010 Utility Rate Study. Final Report. Water, Sewer & Reclaimed Water Rates, Fees & Charges Study. Prepared by: p FY 2010 Utility Rate Study Water, Sewer & Reclaimed Water Rates, Fees & Charges Study June 29, 2010 Prepared by: June 29, 2010 W.E. Mack Finance Director 65 Stone Street Cocoa, FL 32922 Re: FY 2010

More information

Water & Sewer Rate Study. Water & Sewer Cost of Service Rate Study. City of Norco, CA. Draft Report for

Water & Sewer Rate Study. Water & Sewer Cost of Service Rate Study. City of Norco, CA. Draft Report for Water & Sewer Cost of Service Rate Study for City of Norco, CA October 11, 2016 Table of Contents October 11, 2016 Chad Blais Director of Public Works City of Norco 2870 Clark Avenue Norco, CA 92860 Re:

More information

WATER AND WASTEWATER RATE STUDY

WATER AND WASTEWATER RATE STUDY WATER AND WASTEWATER RATE STUDY Draft July 3, 2013 Prepared by: Page 1 Page 2 201 S. Lake Avenue Suite 301 Pasadena, CA 91101 Phone 626. 583. 1894 Fax 626. 583. 1411 www.raftelis.com July 1, 2013 Mr. Don

More information

Sewer Rate Study CRESCENT CITY CALIFORNIA

Sewer Rate Study CRESCENT CITY CALIFORNIA CRESCENT CITY CALIFORNIA Sewer Rate Study 27368 Via Industria, Suite 110, Temecula, California 925904856 T 951.587.3500 800.755.6864 F 888.326.6864 www.willdan.com Mr. Eugene Palazzo City Manager City

More information

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 EXECUTIVE SUMMARY The functions and duties of the Oro Valley Water Utility Commission include reviewing and developing

More information

Notice of a public hearing

Notice of a public hearing Notice of a public hearing Dear Benicia Resident and/or Business Owner, You are receiving a revised Notice of a Public Hearing to increase the water and sewer rates and add water meter replacement fees.

More information

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS Black & Veatch Holding Company 2011. All rights reserved. COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 26 MAY 2015 B&V PROJECT NO.

More information

ES.1 Findings and Recommendations... ES Overview Current Rates Rate Making Objectives

ES.1 Findings and Recommendations... ES Overview Current Rates Rate Making Objectives Table of Contents Executive Summary ES.1 Findings and Recommendations... ES-1 Chapter 1. Introduction 1.1 Overview... 1-1 1.2 Current Rates... 1-1 1.3 Rate Making Objectives... 1-1 Chapter 2. Revenue Requirement

More information

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR Black & Veatch Holding Company 2011. All rights reserved. DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS San Antonio Water System PREPARED FOR San Antonio Water System 21 MAY 2015 B&V PROJECT

More information

Water Rate Study FINAL January 31, 2018

Water Rate Study FINAL January 31, 2018 Water Rate Study FINAL January 31, 2018 1889 Alcatraz Avenue Berkeley, CA 94703 Tel: 510 653 3399 www.bartlewells.com January 31, 2018 Joshua Basin Water District P.O. Box 675 / 61750 Chollita Road Joshua

More information

Temescal Valley Water District

Temescal Valley Water District Temescal Valley Water District Comprehensive Water, Recycled Water, and Wastewater Cost of Service Study Draft Report / December 7, 2016 24640 Jefferson Avenue Suite 207 Murrieta, CA 92562 Phone 951.698.0145

More information

SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3

SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3 01 April, 2014 SAN ANTONIO WATER SYSTEM (SAWS) RATE ADVISORY COMMITTEE: MEETING 3 Bill Zieburtz Richard Campbell Robert Chambers RATE SETTING PROCESS STUDY APPROACH RATE SETTING OBJECTIVES FINANCIAL PLAN

More information

RATE STUDY. Town of Midland. HEMSON C o n s u l t i n g L t d.

RATE STUDY. Town of Midland. HEMSON C o n s u l t i n g L t d. WATER AND WASTEWATER RATE STUDY Town of Midland C o n s u l t i n g L t d. December 2010 TABLE OF CONTENTS EXECUTIVE SUMMARY.........1 I BACKGROUND AND STUDY OBJECTIVES.........9 ll ASSOCIATED LEGISLATION.........13

More information

Water Rate Study Final Report

Water Rate Study Final Report Phelan Pinon Hills Community Services District March 6, 2013 Water Rate Study Final Report Corporate Office: Anaheim, California Temecula Office: 27368 Via Industria, Suite 110 Temecula, California 92590

More information

SQUAW VALLEY PUBLIC SERVICE DISTRICT

SQUAW VALLEY PUBLIC SERVICE DISTRICT EXHIBIT # F-4 21 pages SQUAW VALLEY PUBLIC SERVICE DISTRICT PROFESSIONAL SERVICES AGREEMENT WITH HDR ENGINEERING, INC. DATE: July 28, 2015 TO: FROM: SUBJECT: District Board Members Tom Campbell, Finance

More information

Public Hearing on Water and Sewer Rates. September 20, 2017

Public Hearing on Water and Sewer Rates. September 20, 2017 Public Hearing on Water and Sewer Rates September 20, 2017 Agenda Discuss Proposed Rates Impacts to Reserves and Financial Performance Rate Protest Comments Cost of Service and Rate Structure Study Recommendation

More information

WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016

WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016 WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016 The Financial Link Executive Summary - Water In May 2015, the City of Whitefish (City) retained AE2S to complete a Water and

More information

Cost Recovery Policy. Revised January Mount Pleasant Waterworks Cost Recovery Policy

Cost Recovery Policy. Revised January Mount Pleasant Waterworks Cost Recovery Policy Cost Recovery Policy Revised January 2016 VISION Through the unified and committed efforts of each and every employee, Mount Pleasant Waterworks will be a leader in our industry and community. MISSION

More information

MONROE CITY COUNCIL. Agenda Bill No

MONROE CITY COUNCIL. Agenda Bill No MONROE CITY COUNCIL Agenda Bill No. 15-145 TITLE: Discussion: Utility Rates (Postponed from August 18, 2015) 1 DATE: DEPT: CONTACT: PRESENTER: ITEM: 08/18/2015 Public Works Brad Feilberg Brad Feilberg

More information

Wastewater Rate Study. Villa Park, Illinois

Wastewater Rate Study. Villa Park, Illinois Wastewater Rate Study Villa Park, Illinois June 2013 Executive Summary General The Village of Villa Park s Wastewater Utility is responsible for operation and maintenance of the Village s separate sanitary

More information

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study Capital Region Water Water and Wastewater Rate Study Report November 22, 2017 Capital Region Water Water and Wastewater Rate Study TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 RATE STUDY SCOPE AND OBJECTIVES...1

More information

Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY

Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY Final Report COMPREHENSIVE WATER AND WASTEWATER COST OF SERVICE AND RATE STUDY Phase 2 Cost of Service and Rate Design BLACK & VEATCH PROJECT NO. 192366 Black & Veatch Holding Company 2017. All rights

More information

WATER USER RATES & FEE STUDY

WATER USER RATES & FEE STUDY WATER USER RATES & FEE STUDY FINAL REPORT February 2016 BARTLE WELLS ASSOCIATES Independent Public Finance Consultants 1889 Alcatraz Avenue Berkeley, California 94703 www.bartlewells.com Tel: 510/653-3399

More information

Goleta Water District

Goleta Water District 201 S Lake Ave. Suite 301 Pasadena CA 91101 Phone 626 583 1894 www.raftelis.com Water Rates and Cost of Service Study Final Report / June 11, 2015 Water Cost of Service & Rate Study Report 2015 201 S Lake

More information

LONG BEACH WATER DEPARTMENT COST OF SERVICE AND RATE STUDY

LONG BEACH WATER DEPARTMENT COST OF SERVICE AND RATE STUDY LONG BEACH WATER DEPARTMENT COST OF SERVICE AND RATE STUDY Final Report / February 1, 2017 445 S. Figueroa Street Suite 2270 Los Angeles, CA 90071 Phone Fax 213. 262. 9300 213. 262. 9303 www.raftelis.com

More information

CITY OF RAPID CITY. Financial and Rate Setting Policies for the Water and Water Reclamation Utilities

CITY OF RAPID CITY. Financial and Rate Setting Policies for the Water and Water Reclamation Utilities CITY OF RAPID CITY Financial and Rate Setting Policies for the Water and Water Reclamation Utilities Financial and Rate Setting Policies i City of Rapid City Financial/Rate Setting Policies for the Water

More information

FORT COLLINS- LOVELAND WATER DISTRICT

FORT COLLINS- LOVELAND WATER DISTRICT FORT COLLINS- LOVELAND WATER DISTRICT Water Financial Planning and Rate Study Report March 16, 2018 District of Thousand Oaks Water and Wastewater Financial Plan Study Report March 16, 2018 Board of Directors

More information

City of San Carlos Sewer Financial Plan & Rate Update

City of San Carlos Sewer Financial Plan & Rate Update City of San Carlos Sewer Financial Plan & Rate Update Revised 06/13/16 1889 Alcatraz Avenue Berkeley, CA 94703 Tel: 510 653 3399 www.bartlewells.com June 13, 2016 City of San Carlos Department of Public

More information

April 6, Katherine Godbey Director of Finance, Coachella Valley Water District Hovley Lane East Palm Desert, CA 92260

April 6, Katherine Godbey Director of Finance, Coachella Valley Water District Hovley Lane East Palm Desert, CA 92260 April 6, 2016 Katherine Godbey Director of Finance, Coachella Valley Water District 75515 Hovley Lane East Palm Desert, CA 92260 Dear Ms. Godbey: Hawksley Consulting (a subsidiary of MWH Global) is pleased

More information

STORM WATER USER RATE STUDY

STORM WATER USER RATE STUDY LY STORM WATER USER RATE STUDY STORM WATER UTILITY OREM CITY, UTAH JANUARY 2016 PREPARED BY LEWIS YOUNG ROBERTSON & BURNINGHAM, INC. TABLE OF CONTENTS SECTION I: EXECUTIVE SUMMARY... 3 SECTION II: OVERVIEW

More information

Water Services Rate Study

Water Services Rate Study Report on the Water Services Rate Study Town of Telluride, Colorado Project No. 72447 August 2013 Water Services Rate Study prepared for Town of Telluride, Colorado August 2013 Project No. 72447 prepared

More information

Study Workshops are designed to be both educational and to seek broad direction from the Board

Study Workshops are designed to be both educational and to seek broad direction from the Board Study Workshops are designed to be both educational and to seek broad direction from the Board Workshop #1 Financial Forecast & Cost of Service Water, recycled water, & sewer services Revenue requirement

More information

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY

WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY REPORT January 2017 WATER, WASTEWATER, STORMWATER, AND MUNICIPAL SOLID WASTE COST OF SERVICE AND RATE DESIGN STUDY PREPARED BY: ECONOMICS STRATEGY STAKEHOLDERS SUSTAINABILITY www.newgenstrategies.net 3420

More information

City of Norco WATER AND SEWER RATES Frequently Asked Questions

City of Norco WATER AND SEWER RATES Frequently Asked Questions Q. Where will I see the increase in my bill? A. Your utility bill will see changes in the Water Consumption, Irrigation Consumption, Fixed Monthly Water Charge and Sewer sections of the bill. If you have

More information

Water Rate Study for City of Lemoore

Water Rate Study for City of Lemoore Water Rate Study for City of Lemoore June 17, 2016 Prepared by: Dan Bergmann, Principal 15 Shasta Lane, Walnut Creek, CA 94597 Email: dan@igservice.com Office: 925-946-9090 Water Rate Study for City of

More information

YORBA LINDA WATER DISTRICT

YORBA LINDA WATER DISTRICT YORBA LINDA WATER DISTRICT 2015 Water and Sewer Rate Study Report FINAL August 25, 2015 City of Thousand Oaks Water and Wastewater Financial Plan Study Report 445 S. Figueroa Street Suite #227 Los Angeles,

More information

City Services Appendix

City Services Appendix Technical vices 1.0 Introduction... 1 1.1 The Capital Facilities Plan... 1 1.2 Utilities Plan... 2 1.3 Key Principles Guiding Bremerton s Capital Investments... 3 1.4 Capital Facilities and Utilities Addressed

More information

KC Water Cost of Service Task Force Meeting #6

KC Water Cost of Service Task Force Meeting #6 O C T O B E R 2 5, 2 0 1 6 KC Water Cost of Service Task Force Meeting #6 Agenda Review of Agreed Upon Guiding Principles Discussion Topics for now and future meetings Case Studies Expense Reduction Premised

More information

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415)

SAUSALITO-MARIN CITY SANITARY DISTRICT 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) Fax: (415) 1 EAST ROAD SAUSALITO, CALIFORNIA Telephone: (415) 332-0244 Fax: (415) 332-0453 Budget FY 2017/18 Adopted by Board on June 5, 2017 BUDGET EXECUTIVE SUMMARY FISCAL YEAR 2017/18 DISTRICT OVERVIEW The Sausalito-Marin

More information

City of Sanibel. Sewer Expansion Feasibility Study Update GAI #A

City of Sanibel. Sewer Expansion Feasibility Study Update GAI #A City of Sanibel Sewer Expansion Feasibility Study 2011 Update GAI # July 2011 July 12, 2011 GAI Proj. # Mr. Gates Castle Utility Director City of Sanibel 800 Dunlop Road Sanibel, FL 33957 Subject: Sewer

More information

1715 South Reserve Suite C Missoula, MT 59801

1715 South Reserve Suite C Missoula, MT 59801 ! 1715 South Reserve Suite C Missoula, MT 59801 March 9, 2007 Mayor Jessica Randazzo City of Hamilton, MT 223 S. Second Street Hamilton, MT 59840 Subject: Dear Mayor Randazzo: REVISED City of Hamilton,

More information

BODEGA BAY PUBLIC UTILITY DISTRICT Water and Wastewater Rate Study

BODEGA BAY PUBLIC UTILITY DISTRICT Water and Wastewater Rate Study BODEGA BAY PUBLIC UTILITY DISTRICT Water and Wastewater Rate Study FINAL REPORT March 22, 2018 BARTLE WELLS ASSOCIATES Independent Public Finance Advisors 1889 Alcatraz Avenue Berkeley, CA 94703-2714 Tel.

More information

2017 UTILITY RATE STUDY WORK SESSION #2: BACKGROUND, EDUCATIONAL/INFORMATIONAL

2017 UTILITY RATE STUDY WORK SESSION #2: BACKGROUND, EDUCATIONAL/INFORMATIONAL 2017 UTILITY RATE STUDY WORK SESSION #2: BACKGROUND, EDUCATIONAL/INFORMATIONAL Receive a presentation from Lewis Young Robertson & Burningham regarding the 2017 Utility Rate Study The purpose of the Council

More information

TOWNSHIP OF WEST LINCOLN

TOWNSHIP OF WEST LINCOLN TOWNSHIP OF WEST LINCOLN April 18, 2016 dfa DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 664-B Vine Street St. Catharines Ontario Canada L2M 7L8 Telephone: (905) 938-0965

More information

Town of Hillsborough. City Council Public Hearing. Water Rate Cost-of-Service Study. February 13, 2017

Town of Hillsborough. City Council Public Hearing. Water Rate Cost-of-Service Study. February 13, 2017 City Council Public Hearing February 13, 2017 Public Hearing on Proposed Water Rates PRESENTED BY Kelly J. Salt Partner 2016 Best Best & Krieger LLP Article X, section 2 (1928) The general welfare requires

More information

WATER VALIDATION, COST OF SERVICE & RATE DESIGN ANALYSIS WASTEWATER VALIDATION & RATE ANALYSIS MISCELLANEOUS FEES & OVERHEAD RATE ANALYSIS

WATER VALIDATION, COST OF SERVICE & RATE DESIGN ANALYSIS WASTEWATER VALIDATION & RATE ANALYSIS MISCELLANEOUS FEES & OVERHEAD RATE ANALYSIS WATER VALIDATION, COST OF SERVICE & RATE DESIGN ANALYSIS WASTEWATER VALIDATION & RATE ANALYSIS MISCELLANEOUS FEES & OVERHEAD RATE ANALYSIS B&V PROJECT NO. 179801.0100 PREPARED FOR Vallecitos Water District,

More information

City of Ann Arbor, MI Water and Sewer Cost of Service Study Final Draft Report

City of Ann Arbor, MI Water and Sewer Cost of Service Study Final Draft Report City of Ann Arbor, MI Water and Sewer Cost of Service Study Final Draft Report June 15, 2018 June 15, 2018 Ms. Lynne Chaimowitz Budget and Finance Supervisor City of Ann Arbor 301 E. Huron Street Ann Arbor,

More information

Great Lakes Water Authority/ Detroit Water and Sewerage Department Five-year Financial Forecast Cash Basis. July 1, 2015 through June 30, 2020

Great Lakes Water Authority/ Detroit Water and Sewerage Department Five-year Financial Forecast Cash Basis. July 1, 2015 through June 30, 2020 Great Lakes Water Authority/ Detroit Water and Sewerage Department Cash Basis July 1, 2015 through June 30, 2020 Table of Contents Report Letter... 1 Project Summary... 2-3 Executive Summary... 4 Financial

More information

COUNTY SANITATION. DISTRICTS OF LOS ANGELES COUNTY

COUNTY SANITATION. DISTRICTS OF LOS ANGELES COUNTY COUNTY SANITATION. DISTRICTS OF LOS ANGELES COUNTY 1955 Workman Mill Road, Whittier, CA 90601-1400 Mailing Address: P.O. Box 4998, Whittier, CA 90607-4998 Telephone: (562) 699-7411, FAX: (562) 699-5422

More information

Maurice Kaufman, Director of Public Works / City Engineer Bartle Wells Associates DATE: September 7, 2016 MEMORANDUM

Maurice Kaufman, Director of Public Works / City Engineer Bartle Wells Associates DATE: September 7, 2016 MEMORANDUM TO: FROM: Maurice Kaufman, Director of Public Works / City Engineer Bartle Wells Associates DATE: September 7, 2016 SUBJECT: - MEMORANDUM Introduction The (City) provides sewer sanitary collection services

More information

WATER AND SEWER UTILITIES RATE STUDY

WATER AND SEWER UTILITIES RATE STUDY WATER AND SEWER UTILITIES RATE STUDY RATE DESIGN WORKSHOP WITHCITYCOUNCIL / UTILITIES COMMISSION March 6, 2014 Agenda Overview of Rate Study Process Water / Sewer Developer Impact Fees Sewer Rates Water

More information

From: Lex Warmath and Elaine Conti, Raftelis Financial Consultants, Inc.

From: Lex Warmath and Elaine Conti, Raftelis Financial Consultants, Inc. 227 West Trade Street Phone 704 373 1199 www.raftelis.com Suite 1400 Fax 704 373 1113 Charlotte, NC 28202 Date: June 21, 2016 To: Mr. Bob Walker, Executive Director From: Lex Warmath and Elaine Conti,

More information

CASH RESERVE POLICY ADOPTED BY THE BOARD OF DIRECTORS ON DECEMBER 8, 2016

CASH RESERVE POLICY ADOPTED BY THE BOARD OF DIRECTORS ON DECEMBER 8, 2016 RANCHO CALIFORNIA WATER DISTRICT 42135 WINCHESTER ROAD/BOX 9017 TEMECULA, CA 92589-9017 CASH RESERVE POLICY ADOPTED BY THE BOARD OF DIRECTORS ON DECEMBER 8, 2016 TABLE OF CONTENTS I. BACKGROUND AND INTRODUCTION...

More information

Santa Ynez River Water Conservation District, ID No. 1. Water Rates & Finances. December 13, 2016

Santa Ynez River Water Conservation District, ID No. 1. Water Rates & Finances. December 13, 2016 Santa Ynez River Water Conservation District, ID No. 1 Water Rates & Finances December 13, 2016 Presentation Overview Objectives & Process District Finances Current & Projected Rates 2 Rate Study Objectives

More information

Utility Rate Study (A Case Study)

Utility Rate Study (A Case Study) Published on MTAS (http://www.mtas.tennessee.edu) January 06, 2019 Utility Rate Study (A Case Study) Dear Reader: The following document was created from the MTAS website (mtas.tennessee.edu). This website

More information

CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT

CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT CITY OF CALISTOGA WATER RATE STUDY FINAL REPORT February 2, 218 This page was intentionally left blank. City of Calistoga Water Rate Study Report Page 2 February 2, 218 Dylan Feik City Manager City of

More information

San Francisco Public Utilities Commission

San Francisco Public Utilities Commission San Francisco Public Utilities Commission Water & Wastewater Rate Study Report March 6, 2009 Prepared by: Table of Contents I. EXECUTIVE SUMMARY...1 A. Pricing Objectives...2 B. Review of Findings Water...2

More information

City of Benicia. Rate Study Update: Water & Wastewater Rates

City of Benicia. Rate Study Update: Water & Wastewater Rates City of Benicia Rate Study Update: Water & Wastewater Rates March 1, 2016 Prepared by: Karin Schnaider, Finance Director, City of Benicia Greg Clumpner, Director, NBS Carmen Narayanan, Consultant, NBS

More information

BOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS

BOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS BOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS Electric Utility Revenues, Revenue Requirements, Cost of Service, And Rates Draft Final Report (As Updated) February 2010 February 1, 2010 Kansas City Board

More information

M A N I T O B A ) Order No. 169/07 ) THE PUBLIC UTILITIES BOARD ACT ) December 28, 2007 THE CITY OF BRANDON REVISED WATER AND SEWER RATES

M A N I T O B A ) Order No. 169/07 ) THE PUBLIC UTILITIES BOARD ACT ) December 28, 2007 THE CITY OF BRANDON REVISED WATER AND SEWER RATES www.pub.gov.mb.ca M A N I T O B A ) ) THE PUBLIC UTILITIES BOARD ACT ) December 28, 2007 BEFORE: Graham F. J. Lane, CA, Chairman Monica Girouard, CGA, Member Susan Proven, P.H.Ec., Member THE CITY OF BRANDON

More information

Impact Fees for Wastewater Systems

Impact Fees for Wastewater Systems 2013 Impact Fees for Wastewater Systems Final Report City of Kalispell 12/13/2013 Contents Executive Summary... 4 2 Introduction... 4 Financial Objective of Impact Fees... 4 Impact Fee Criteria... 4 The

More information

TEN YEAR FINANCIAL FORECAST

TEN YEAR FINANCIAL FORECAST TEN YEAR FINANCIAL FORECAST The ability to ensure a reliable supply of high quality water for Metropolitan s 26 member agencies depends on Metropolitan s ongoing ability to fund operations and maintenance,

More information

Managing Financial Risk and Declining Demand. Presentation Outline

Managing Financial Risk and Declining Demand. Presentation Outline Managing Financial Risk and Declining Demand Washington Association of Sewer & Water Districts Spring Conference April 13, 2012 John Ghilarducci Presentation Outline 1. Why Consumption is Declining Potential

More information

The purpose and subject of the proposed local law is to adopt revised sewer rates per the report prepared and submitted by BST & Company, CPA s LLP.

The purpose and subject of the proposed local law is to adopt revised sewer rates per the report prepared and submitted by BST & Company, CPA s LLP. BOARD OF TRUSTEES VILLAGE OF GREENPORT NOTICE OF PUBLIC HEARING ON A PROPOSED LOCAL LAW OF 2017 AMENDING CHAPTER 105 (SEWERS) OF THE VILLAGE OF GREENPORT CODE PLEASE TAKE NOTICE that the Board of Trustees

More information

Commercial. Real Estate Stress Testing. by Mike Newett and Don Gilliam. The Loan

Commercial. Real Estate Stress Testing. by Mike Newett and Don Gilliam. The Loan Commercial Real Estate Commercial Real Estate Stress Testing Stress testing of commercial real estate portfolios has become an even more important risk management tool, especially since interest rates

More information

CITY OF COLDWATER BRANCH COUNTY, MICHIGAN FINANCIAL STATEMENTS JUNE 30, 2006

CITY OF COLDWATER BRANCH COUNTY, MICHIGAN FINANCIAL STATEMENTS JUNE 30, 2006 BRANCH COUNTY, MICHIGAN FINANCIAL STATEMENTS JUNE 30, 2006 CONTENTS Page Report Letter 1-2 Management s Discussion and Analysis 3-12 Basic Financial Statements Government-Wide Financial Statements: Statement

More information

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District

Water Consultancy. Montecito Sanitary District Wastewater Rate Study Report. Montecito Sanitary District 3585 Maple Street, Suite 250 Ventura, CA 93003 805-404-1467 Montecito Sanitary District Wastewater Rate Study Report March 2016 Montecito Sanitary District 1042 Monte Cristo Lane Santa Barbara CA 93108

More information

UTILITY RATE STUDY. Public Hearing

UTILITY RATE STUDY. Public Hearing UTILITY RATE STUDY Public Hearing. Public January 23, 2018 Resources Management Group, Inc. Utility, Rate, Financial, and Management Consultants Rate Guiding Principles Recognized Revenues Should Be Sufficient

More information

DECISION 2017 NSUARB 101 M07809 NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF THE PUBLIC UTILITIES ACT

DECISION 2017 NSUARB 101 M07809 NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF THE PUBLIC UTILITIES ACT DECISION 2017 NSUARB 101 M07809 NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF AN APPLICATION of the MUNICIPALITY OF THE COUNTY OF PICTOU, on behalf

More information

Regional Wastewater System Financial Assessment Technical Memorandum

Regional Wastewater System Financial Assessment Technical Memorandum Regional Wastewater System Financial Assessment Technical Memorandum To: From: CC: Project: Subject: Sarpy County Tom Gould - HDR David Dechant HDR Judy Dean HDR Joe Roberts HDR File Southern Sarpy County

More information

Making up 69% of the annual fixed costs is debt service for water system improvements by two

Making up 69% of the annual fixed costs is debt service for water system improvements by two METROPOLITAN DOMESTIC WATER IMPROVEMENT DISTRICT 2013 WATER RATES & REVENUE ANALYSIS AUGUST 12, 2013 Last August, an analysis was completed and provided to the Board of Directors that gave a detailed look

More information

West Valley Sanitation District FINANCIAL PLAN & RATE STUDY. January 2018

West Valley Sanitation District FINANCIAL PLAN & RATE STUDY. January 2018 West Valley Sanitation District FINANCIAL PLAN & RATE STUDY January 2018 BARTLE WELLS ASSOCIATES Independent Public Finance Consultants 1889 Alcatraz Avenue Berkeley, California 94703 www.bartlewells.com

More information

Table of Contents. Page Witness Background and Experience General Matters Major Wastewater Rate Changes Wastewater Revenue...

Table of Contents. Page Witness Background and Experience General Matters Major Wastewater Rate Changes Wastewater Revenue... MSD Exhibit No. MSD H 0 Rate Change Proceeding WILLIAM STANNARD Direct Testimony Metropolitan St. Louis Sewer District February, 0 Table of Contents Page Witness Background and Experience... General Matters...

More information

Final COST OF SERVICE STUDY SEPTEMBER City of San Clemente

Final COST OF SERVICE STUDY SEPTEMBER City of San Clemente Final COST OF SERVICE STUDY SEPTEMBER 2017 City of San Clemente Contents CONTENTS Executive Summary... 1 Study Goals and Drivers... 1 Water Rate Analysis & Adoption... 2 Recycled Water Rate Analysis &

More information

WASTEWATER FINANCIAL PLAN STUDY REPORT

WASTEWATER FINANCIAL PLAN STUDY REPORT WASTEWATER FINANCIAL PLAN STUDY REPORT FINAL October 7, 2013 Prepared by: Page 1 201 S. Lake Avenue Suite 301 Pasadena, CA 91101 Phone 626.583. 1894 Fax 626.583. 1411 www.raftelis.com October 7, 2013 Mr.

More information

The series 2008 Water & Sewer Revenue Bonds Feasibility Report recommended the City perform and implement a rate study for the following reasons:

The series 2008 Water & Sewer Revenue Bonds Feasibility Report recommended the City perform and implement a rate study for the following reasons: Additional Background Information Water and Wastewater The City of Fort Lauderdale supplies water and sewer services on a regional basis to over 250,000 residents of central Broward County. The areas serviced

More information

Notice of Public Hearing for Proposed Change to a Water Budget Rate Structure to be Held at Murrieta City Hall

Notice of Public Hearing for Proposed Change to a Water Budget Rate Structure to be Held at Murrieta City Hall May 20, 2011 Notice of Public Hearing for Proposed Change to a Water Budget Rate Structure to be Held at Murrieta City Hall Dear Western Municipal Water District customer, Every Western Municipal Water

More information

APPENDIX J. CIP Renewal and Replacement Process. Revision History

APPENDIX J. CIP Renewal and Replacement Process. Revision History APPENDIX J CIP Renewal and Replacement Process Revision History Revision Date Approval Reason 0 09/30/05 Original 1 05/25/11 2 09/27/12 3 03/26/14 4 11/14/16 E. Yong Updated Clearinghouse process and replaced

More information

Module 8 Rate Design Overview for Small Water Systems

Module 8 Rate Design Overview for Small Water Systems Module 8 Rate Design Overview for Small Water Systems Workbook Financial/Managerial Series This course includes content developed by the Pennsylvania Department of Environmental Protection in cooperation

More information

Table 2-2 Projected Water Production and Costs

Table 2-2 Projected Water Production and Costs Table 2-2 Projected Water Production and Costs Recorded Estimated Budget Forecast Description FY 2007-08 FY 2008-09 FY 2009-10 FY 2010-11 FY 2011-12 FY 2012-13 FY 2013-14 Well Production (OCWD, A-F, a)

More information

WATER RATE AND FINANCIAL POLICY TACOMA PUBLIC UTILITIES WATER DIVISION

WATER RATE AND FINANCIAL POLICY TACOMA PUBLIC UTILITIES WATER DIVISION WATER RATE AND FINANCIAL POLICY TACOMA PUBLIC UTILITIES WATER DIVISION March 2017 Adopted by Public Utility Board Resolution U-10910 on February 22, 2017 Adopted by City Council Ordinance No. 28413 on

More information

CITY OF FLORENCE, ALABAMA ELECTRICITY, GAS, AND WATER AND WASTEWATER DEPARTMENTS. FINANCIAL STATEMENTS JUNE 30, 2007 and 2006

CITY OF FLORENCE, ALABAMA ELECTRICITY, GAS, AND WATER AND WASTEWATER DEPARTMENTS. FINANCIAL STATEMENTS JUNE 30, 2007 and 2006 ELECTRICITY, GAS, AND WATER AND WASTEWATER DEPARTMENTS FINANCIAL STATEMENTS JUNE 30, 2007 and 2006 ELECTRICITY, GAS, AND WATER AND WASTEWATER DEPARTMENTS TABLE OF CONTENTS Independent Auditors Report 1

More information

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE

FINANCIAL PLAN WATER AND WASTEWATER LINES OF SERVICE UCS2018-0223 ATTACHMENT 1 FINANCIAL PLAN 2019-2022 WATER AND WASTEWATER LINES OF SERVICE 2018 MARCH 14 MAKING LIFE BETTER EVERY DAY UCS2018-0223 Financial Plan 2019-2022 - Water and Wastewater Lines of

More information

Strategic Plan of Work & Projections. Development of the Plan of Work

Strategic Plan of Work & Projections. Development of the Plan of Work Strategic Plan of Work & Projections The Strategic Plan of Work & Projections portion of this document provides a narrative discussion of the County s longterm planning process and links the policy making

More information

Comprehensive Rate Study & Cost Allocation Analysis. Public Workshop December 4, 2017

Comprehensive Rate Study & Cost Allocation Analysis. Public Workshop December 4, 2017 Comprehensive Rate Study & Cost Allocation Analysis Public Workshop December 4, 2017 Today s Workshop: Present findings and solicit Board input on rate design and fiscal policy considerations Financial

More information

Revenue Plan. August 12, Dennis Davies Deputy Director of Public Works 200 Civic Center Way El Cajon, CA 92020

Revenue Plan. August 12, Dennis Davies Deputy Director of Public Works 200 Civic Center Way El Cajon, CA 92020 1925 Palomar Oaks Way, Suite 3 Carlsbad, California 928 tel: 76 438 7755 fax: 76 438 7411 Dennis Davies Deputy Director of Public Works 2 Civic Center Way El Cajon, CA 922 Subject: Six Year Revenue Plan

More information