UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Size: px
Start display at page:

Download "UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION"

Transcription

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Midwest Independent Transmission System ) Operator, Inc. ) Docket No. ER PROTEST TO COMPLIANCE FILING OF THE RETAIL ENERGY SUPPLY ASSOCIATION Pursuant to Rule 211 of the Federal Energy Regulatory Commission s ( Commission ) Rules of Practice and Procedure, 18 C.F.R , and the Commission s Notice issued on December 28, 2012, the Retail Energy Supply Association ( RESA ) 1 hereby files this Protest of the Midwest Independent Transmission System Operator, Inc. s ( MISO s ) compliance filing in the above-referenced proceeding. MISO s compliance filing is deficient and fails to protect LSEs from paying what could be excessive claimed administrative costs incurred by the provider of last resort ( POLR ) for procuring planning reserve margin requirement for any remaining demand under MISO s resource adequacy program. MISO must be directed to include in its Tariff the explicit requirement that any claimed administrative costs must be direct and verifiable costs that are incremental to what the POLR had to do for itself in performing its obligations under the RAR construct. In addition, costs should not be recoverable until MISO submits the costs for recovery under FPA Section 205. In support of this Protest, RESA submits as follows: 1 RESA s members include: Champion Energy Services, LLC; ConEdison Solutions; Constellation NewEnergy, Inc.; Direct Energy Services, LLC; GDF SUEZ Energy Resources NA, Inc.; Hess Corporation; Integrys Energy Services, Inc.; Just Energy; Liberty Power; MC Squared Energy Services, LLC; Mint Energy, LLC; NextEra Energy Services; Noble Americas Energy Solutions LLC; NRG, Inc.; PPL EnergyPlus, LLC; Stream Energy; TransCanada Power Marketing Ltd. and TriEagle Energy, L.P.. The comments expressed in this filing represent the position of RESA as an organization but may not represent the views of any particular member of RESA

2 - 2 - I. BACKGROUND As part of the Midwest ISO s efforts to design a voluntary capacity market, on July 20, 2011, Midwest ISO filed to develop Local Resource Zones to ensure that sufficient qualified Planning Resources can be relied upon to meet Load within each portion of the MISO region. 2 The Midwest ISO proposed to determine the geographic boundary of each Local Resource Zone. Midwest ISO then proposed to develop Local Resource Zone capacity requirements. LSEs serving load in a Local Resource Zone will meet the Planning Reserve Margin Requirements either through participation in a Planning Resource Auction process, through acquiring Planning Resources via bilateral contracts, or through opt-out procedures identified in the Tariff. Determination of an LSE s capacity requirement is based on a forecast of annual peak demand at the time of the Midwest ISO system peak (a Coincident Peak Demand forecast). When there is only one LSE in a distribution area (i.e., where there is no retail competition and the LSE is also the Electric Distribution Company ( EDC )), deriving a single Coincident Peak Demand forecast for the Planning Year is not controversial because the LSE/EDC will provide a forecast of its own peak demand. The capacity obligation will be known prior to the Planning Year. However, when the distribution area of an EDC comprises an area where there is retail competition meaning multiple LSEs and the EDC determining the Coincident Peak Demand for purposes of assigning a capacity obligation for the Planning Year (the Planning Reserve Margin Requirements ( PRMR )) is a critically important component of the price offered customers in the competitive market. 2 Midwest ISO July 20 Filing Letter at 7.

3 - 3 - MISO left all of the discretion for establishing retail load obligations in the hands of the EDC, requiring LSEs to work with the LDC to reach agreement as to the methodology to be used to develop Coincident Peak Demand forecasts for each of the LSEs within the EDC s service area. Midwest ISO is left to review the results. MISO uses the peak load contribution methodology - using individual customer peak load contribution ( PLC ) - as its default methodology for assigning capacity obligations to LSEs. If an EDC does not have the data to derive the peak load contribution, as some EDCs claimed, MISO will use the daily peak load method, and EDCs are required to provide to Midwest ISO the necessary daily peak load data. Over time, by collecting this historical data Midwest ISO will be able to utilize the peak load contribution methodology for LSEs in an EDC s area. See June 11 Order at P On September 28, 2012, MISO filed in Docket No. ER , tariff language to address two risks that it identified with its capacity allocation methodology applicable to retail access states: (1) that some Planning Resource Margin Requirement may not be sufficiently accounted for and modeled at the time of the Planning Resource Auction; and (2) that some Load may switch providers during the planning Year, which would result in an originally serving LSE having over-procured capacity and the LSE acquiring the new load having under-procured sufficient capacity. 3 MISO proposed to modify Section 69.A.1.1 of the Tariff to specify that an EDC must provide either Coincident Peak Demand or each retail customer s peak load contribution to both Midwest ISO and the LSEs by December 15. Any LSE that knows of any retail load switches for the upcoming Planning Year would be required to notify Midwest ISO. Midwest ISO will publish the calculation of transmission losses for each LBA by the first Business Day in December, rather than in January. 3 September 28 filing at 3.

4 - 4 - If there is a gap unassigned forecast demand once information from LSEs has been provided and the EDC has performed its coincident peak calculation, the POLR will procure that capacity for the service area, apparently via the annual auction. Specifically, In Section 69A a of its proposed Tariff revisions, the Midwest ISO proposal requires an LSE in a state that permits retail load switching to notify the Transmission Provider by January 15 regarding the LSE s proportion of the EDC s forecast Demand that it expects to serve on June 1 of the next Planning Year [emphasis added]. The EDC will add up the expects to serve forecasts and compare the total with the EDC s own area forecast. The so-called gap is the remaining Demand, which according to the proposed tariff will be allocated to the LSE that is the provider of last resort ( POLR ). In addition, Midwest ISO proposed changes to the provisions governing retail Load switching during the Planning Year. Midwest ISO proposed the amend Section 69.A.1.2 so that a daily rate will be applied to Load that switches during the Planning Year. If the relevant Load Zone applies the preferred default method costs will be allocated on a daily basis to LSEs by multiplying the peak load contributions for load served by the LSE by the Auction Clearing Price for the Local Resource Zone where the Load is located less any zonal delivery benefits. For LSEs that use the daily peak load default methodology, costs will be allocated on a daily basis to such LSEs by multiplying the load served by the LSE as a percentage of the EDC s load during the Hour of Midwest ISO s peak load, multiplied by the Planning Reserve Margin Requirement for the EDC s Coincident Peak Demand forecast times the Auction Clearing Price for the Local Resource Zone where the Load is located less any zonal deliverability benefits. 4 4 Id. at 6.

5 - 5 - On October 19, 2012, RESA filed a Protest of MISO s filing, arguing that MISO was overly complicating what should be a simple derivation of coincident peak demand each LSE should be permitted to derive its coincident peak demand and rely on its calculation to procure necessary resources under the MISO RAR construct. With respect to filling the gap noted above, RESA pointed out some of the logical and mechanical faults with this proposal, including noting that the proposal doesn t address what happens if the sum of the LSE forecasts is more than the EDC s forecast. In its November 27 Order, the Commission denied RESA s protest and accepted MISO s filing, subject to a compliance filing. As relevant here, FERC found that MISO did not specify how the POLR can recover the administrative cost of procuring the planning reserve margin requirement for any demand that it must obtain. See November 27 Order at P.27. FERC directed MISO to propose language to address the issue in its compliance filing. On December 27, 2012, RESA filed a request for rehearing, arguing that the Commission erred when it ordered MISO to include language to permit the POLR to recover undefined, unknown and likely non-existent costs. MISO also filed a request for rehearing on the same issue. Both RESA and MISO filed affidavits showing that there would be no administrative costs. These requests for rehearing remain pending. Also on December 27, 2012, and in purported compliance with the Commission s November 27 Order, MISO made its compliance filing. In its filing, MISO proposes to add language to Section 69.A.1.1.1a to provide that: the POLR may submit to the transmission Provider documentation of any administrative costs that it incurs related to procuring the PRMR for remaining demand. The Transmission Provider will review the reasonableness of any such administrative costs and will allocate the costs determined to be reasonably related to the PRMR procurement by the POLR to the LSEs that serve Demand in

6 - 6 - the POLR s service territory that benefitted from the POLR s PRMR procurement. The provision, as drafted, is unjust and unreasonable because it affords MISO unbridled discretion as to Commission-jurisdictional costs that would be recovered from LSEs. As will be shown in more detail below, MISO must revise the language (if it is not removed pursuant to RESA s and MISO s requests for rehearing) to require MISO to file any direct, verifiable costs claimed by a POLR (which may or may not be the EDC) with the Commission prior to collection from LSEs. II. ARGUMENT MISO s proposed Tariff language to provide a mechanism for a POLR to recover administrative costs associated with procuring the PRMR for remaining demand is unjust and unreasonable. MISO has not identified what sorts of administrative costs are recoverable and MISO has retained sole discretion to determine whether the costs are recoverable, with the right to assess LSEs to collect them. A MISO Must Specify that Any Costs That May Be Recoverable Are Limited to Verifiable, Direct Costs that Are Incremental to the Costs Incurred by the POLR in Procuring/Registering Its Own Load MISO has placed no limitation or description as to what types of charges are recoverable from LSEs under its provision. The POLR s only limitation appears to be whatever MISO thinks is appropriate. This unbridled discretion in MISO and the POLR renders the provision unjust and unreasonable. First, the Commission should require that any administrative costs are directly and solely related to the POLR s role in procuring the planning reserve margin requirement for remaining

7 - 7 - demand. The costs should be limited to costs that the POLR would not have incurred absent the minor administrative activity necessary. The POLR should not be permitted to submit as recoverable administrative costs, its overhead, capital and employee-related salary and pension costs, among other costs associated with its POLR obligations or other procurement functions. Second, the costs must be verifiable and documented with precision, with sufficient backup so that the Commission can assess whether the costs are permissible and recoverable administrative costs. LSEs must be able to understand and know any costs that they must bear, especially if they cannot avoid them. Third, the costs must be disclosed to all market participants. As noted in Argument B below, these costs must be filed with the Commission for approval under FPA Section 205. In addition, these costs, including the back-up, support and documentation must be reviewable by any market participant. Finally, the language proposed by MISO should be revised to reflect the fact that the POLR is not necessarily the EDC or local utility in the load zone. It is possible that any entity could act as a POLR under the MISO Tariff and relevant state laws and procedures. RESA has expressed, via the affidavit submitted with its Request for Rehearing, its view that there are no administrative costs associated with the limited function to be undertaken by the POLR. The action required by the POLR is a technical formality resulting from the voluntary nature of the capacity auction, that entails no work, no cost and no risk to the POLR. The POLR remains revenue neutral so that there is no financial risk associated with performing the limited function. However, MISO and the Commission must ensure that if there are any administrative costs claimed by a POLR, that these are verified, legitimate administrative costs solely

8 - 8 - associated with the POLR s performance of what is an extremely limited and minor administrative function. B. Any Costs Recovered from LSEs Associated with a POLR s Administration of the PRMR Procurement Process Must be Filed With and Approved By, the Commission RESA remains concerned that this administrative charge provision can be used by the POLR to collected unwarranted and unjustified costs. The Commission has improperly authorized collection of a rate, the level of which has not been determined. In order to collect a rate, Federal Power Act Section 205 requires that the rate be filed with the Commission for approval. Thus, MISO must not be permitted to give itself the discretion to determine what is and what is not a proper administrative cost that MISO can then collect from LSEs. If the Commission is going to require MISO to permit the POLR to recover a rate for administrative costs, that rate must be subject to review and approval by the Commission. LSEs must be provided the opportunity to review and comment/protest the rate, the level of costs, or the methodology used to determine the rate. To do otherwise would be to violate the filed rate doctrine. III. CONCLUSION RESA members are active participants in retail markets in MISO s footprint. RESA has raised a number of issues with respect to the capacity procurement processes in MISO. RESA, along with MISO, filed Requests for Rehearing of the Commission s November 27 Order, showing that: (1) the Commission erred when it imposed the requirement that the MISO allow POLRs to recover administrative costs; and (2) there are no administrative cost to

9 - 9 - recover. RESA now objects to MISO s filing in purported compliance with the November 27 Order. MISO s filing in compliance with the November 27 Order is unjust and unreasonable. Any rate for the recovery of those costs should be filed with the Commission prior to recovery from LSEs. The Commission must require that any administrative costs are directly and solely related to the POLR s role in procuring the planning reserve margin requirement for remaining demand. The costs should be limited to costs that the POLR would not have incurred absent the minor administrative activity necessary. The costs must be verified, documented and disclosed to all market participants in a filing to the Commission under FPA Section 205. Finally, the language proposed by MISO should be revised to reflect the fact that the POLR is not necessarily the EDC or local utility in the load zone. It is possible that any entity could act as a POLR under the MISO Tariff and relevant state laws and procedures. WHEREFORE, RESA respectfully requests that MISO s compliance filing be modified as described in this Protest. Respectfully submitted, Of Counsel: /s/elizabeth W. Whittle Elizabeth W. Whittle Counsel to The Retail Energy Supply Association Nixon Peabody, LLP 401 Ninth Street, N.W. Suite 900 Washington, DC ewhittle@nixonpeabody.com Dated: January 17, 2013

10 CERTIFICATE OF SERVICE I hereby certify that I have this day served the foregoing Motion to Intervene and Protest via on each person listed on the Commission s official service list. Dated in Washington, DC this 17 th day of January, /s/elizabeth Whittle Elizabeth W. Whittle

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C ) Docket Nos. ER17-211-000 Mid-Atlantic Interstate Transmission, LLC ) ER17-214-000 and ) ER17-216-000

More information

F I L E D :59 PM

F I L E D :59 PM BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program. Rulemaking

More information

153 FERC 61,248 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

153 FERC 61,248 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 153 FERC 61,248 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, and Tony Clark, Tilden Mining Company L.C. and Empire Iron

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket Nos. ER06-615-000 Operator Corporation ) ER07-613-000 ) ) (not consolidated) ) STATUS REPORT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION AES Huntington Beach, LLC ) Docket No. ER13-351-000 ANSWER OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION TO MOTION TO

More information

UNITED STATES OF AMERICA BERFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BERFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BERFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwestern Public Service Company, ) v. ) Docket No. EL13-15-000 Southwest Power Pool, Inc. ) ) Southwestern Public Service Company,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) PJM Interconnection, L.L.C. ) Docket No. ER )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) PJM Interconnection, L.L.C. ) Docket No. ER ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) Docket No. ER19-24-000 ) ANSWER OF PJM INTERCONNECTION, L.L.C. TO PROTEST AND COMMENTS ( PJM ), pursuant to Rule 213 of the

More information

Conectiv Energy to Liquidate Load Service Supply Contracts; Sells Generation to Calpine

Conectiv Energy to Liquidate Load Service Supply Contracts; Sells Generation to Calpine April 22, 2010 PPL Proposes Updated POR Discount Rates in Base Rate Case PPL Electric Utilities has requested to update its Purchase of Receivables discount rates in its current base rate case, to reflect

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION U.S. Department of Energy, Portsmouth/Paducah Project Office Docket No. RC08-5- REQUEST FOR REHEARING AND CLARIFICATION OF THE NORTH

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Midcontinent Independent System Operator, Inc. ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Midcontinent Independent System Operator, Inc. ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Midcontinent Independent System Operator, Inc. ) Docket No. ER--000 MOTION TO INTERVENE AND PROTEST OF THE RETAIL ENERGY SUPPLY

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-641-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION CXA La Paloma, LLC ) ) v. ) Docket No. EL18-177-001 ) California Independent System ) Operator Corporation ) MOTION FOR LEAVE TO

More information

IN THE SUPREME COURT OF OHIO

IN THE SUPREME COURT OF OHIO IN THE SUPREME COURT OF OHIO ^ In 'I'he Matter Of The Application To Modify, ) Case No. 2013-674 In Accordance With Section 4929.08, Revised ) Code, The Exemption Uranted Columbia Gas ) of Ohio, Inc.,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Complaint, ) ) Docket No. EL v. )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Complaint, ) ) Docket No. EL v. ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Coalition of MISO Transmission Customers, ) ) Complaint, ) ) Docket No. EL16-112-000 v. ) ) Midcontinent Independent System ) Operator,

More information

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, Tony Clark, Norman C. Bay, and Colette D. Honorable.

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New York Independent System Operator, Inc. ) Docket Nos. ER13-1380-000 ER14-500-000 EMERGENCY MOTION OF CENTRAL HUDSON GAS & ELECTRIC

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-1169-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act PJM Interconnection, L.L.C. 2750 Monroe Boulevard Audubon, PA 19403 March 30, 2018 Elizabeth P. Trinkle Counsel T: (610) 666-4707 F: (610) 666-8211 Elizabeth.Trinkle@pjm.com The Honorable Kimberly D. Bose

More information

161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. Midcontinent Independent System

More information

106 FERC 61,263 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

106 FERC 61,263 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 106 FERC 61,263 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell, and Joseph T. Kelliher. San Diego Gas & Electric Company

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Meridian Energy USA, Inc. ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Meridian Energy USA, Inc. ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Meridian Energy USA, Inc. ) Docket No. ER13-1333-000 MOTION TO INTERVENE AND PROTEST OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ISO New England Inc. ) Docket No. ER )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ISO New England Inc. ) Docket No. ER ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ISO New England Inc. ) Docket No. ER19-291-000 ) LIMITED PROTEST OF THE NEW ENGLAND STATES COMMITTEE ON ELECTRICITY Pursuant to

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER19-385-000 Operator Corporation ) COMMENTS OF THE DEPARTMENT OF MARKET MONITORING FOR

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. ) ) ) ISO New England Inc. ) Docket No. ER ) ) ) )

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. ) ) ) ISO New England Inc. ) Docket No. ER ) ) ) ) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ISO New England Inc. Docket No. ER19-444-000 MOTION TO INTERVENE AND LIMITED PROTEST OF THE NEW ENGLAND POWER GENERATORS ASSOCIATION, INC.

More information

September 21, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

September 21, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 DANIEL L. LARCAMP 202.274.2841 telephone 202.654.5616 facsimile daniel.larcamp@troutmansanders.com TROUTMAN SANDERS LLP Attorneys at Law 401 9th Street, N. W., Suite 1000 Washington, D.C. 20004-2134 202.274.2950

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) MOTION TO INTERVENE AND PROTEST OF ACCIONA WIND ENERGY USA LLC

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) MOTION TO INTERVENE AND PROTEST OF ACCIONA WIND ENERGY USA LLC UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) ) ) ) ) Docket No. ER14-781-000 MOTION TO INTERVENE AND PROTEST OF ACCIONA WIND ENERGY USA LLC In accordance

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Participating Transmission Owners ) Docket Nos. RT04-2-000 Administrative Committee ) ER09-1532-000 ) MOTION FOR LEAVE TO INTERVENE

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-756-3300 Fax: 202-756-3333 March 2, 2011 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019)

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

May 18, Black Hills Power, Inc. Docket Nos. ER and EL Compliance Filing Revising Attachment H Formula Rate Protocols

May 18, Black Hills Power, Inc. Docket Nos. ER and EL Compliance Filing Revising Attachment H Formula Rate Protocols Texas New York Washington, DC Connecticut Seattle Dubai London Blake R. Urban Attorney 202.828.5868 Office 800.404.3970 Fax Blake.Urban@bgllp.com Bracewell & Giuliani LLP 2000 K Street NW Suite 500 Washington,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION GenOn Energy Management. LLC ) Docket No. ER19-554-000 NRG California South LP ) MOTION TO INTERVENE AND COMMENTS OF THE DEPARTMENT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Trunkline Gas Company, LLC ) Docket No. CP12-5-000 Sea Robin Pipeline Company, LLC ) ) ANR Pipeline Company ) Docket No. CP11-543-000

More information

Statement of Chairman Cheryl A. LaFleur on Forward Capacity Auction 8 Results Proceeding

Statement of Chairman Cheryl A. LaFleur on Forward Capacity Auction 8 Results Proceeding September 16, 2014 Chairman Cheryl A. LaFleur Docket No. ER14-1409-000 Statement of Chairman Cheryl A. LaFleur on Forward Capacity Auction 8 Results Proceeding The ISO-New England (ISO-NE) Forward Capacity

More information

October 4, 2013 VIA ELECTRONIC FILING

October 4, 2013 VIA ELECTRONIC FILING VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: New York Independent System Operator, Inc. s, Report

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Calpine Corporation, Dynegy Inc., Eastern Generation, LLC, Homer City Generation, L.P., NRG Power Marketing LLC, GenOn Energy Management, LLC,

More information

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 March 7, 2012 Re: California Independent

More information

Energy Savings Income Fund, Universal Energy Enter Definitive Acquisition Agreement

Energy Savings Income Fund, Universal Energy Enter Definitive Acquisition Agreement April 23, 2009 Energy Savings Income Fund, Universal Energy Enter Definitive Acquisition Agreement Energy Savings Income Fund and Universal Energy Group have entered into a definitive agreement under which

More information

161 FERC 61,163 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

161 FERC 61,163 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 161 FERC 61,163 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. PJM Interconnection, L.L.C. Docket

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket No. ER99-3339-000 Operator Corporation ) ) REQUEST FOR REHEARING OF THE CALIFORNIA INDEPENDENT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation Docket No. ER14-1386- REQUEST FOR REHEARING OR, IN THE ALTERNATIVE, MOTION FOR

More information

July 15, 2015 VIA ELECTRONIC FILING

July 15, 2015 VIA ELECTRONIC FILING July 15, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20246 Re: Southwest Power Pool, Inc., Docket No.

More information

139 FERC 61,003 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

139 FERC 61,003 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 139 FERC 61,003 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. International Transmission

More information

December 7, Compliance with Order No. 844 Response to Deficiency Letter

December 7, Compliance with Order No. 844 Response to Deficiency Letter California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New York Independent System Operator, Inc. ) PJM Interconnection, L.L.C. ) Docket Nos. ER17-905-002 ) MOTION FOR LEAVE TO ANSWER

More information

RESA Wants Modification of D.C. Bill Error Reporting Rules

RESA Wants Modification of D.C. Bill Error Reporting Rules Calif. Draft Would Set Target of Jan. 1, 2010 for Novation of All DWR Contracts Novating current Department of Water Resources supply contracts to accelerate a return to direct access would be in the "public

More information

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015)

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015) 153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Southwest Power Pool,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION EDF Trading North America, LLC, on behalf of AES Alamitos, LLC AES Huntington Beach, LLC and AES Redondo Beach, LLC Docket No. ER19-458-000

More information

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company The Dayton Power and Light Company 1065 Woodman Drive, Dayton Ohio 45458 May 8, 2018 Via etariff Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

125 FERC 61,311 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

125 FERC 61,311 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 125 FERC 61,311 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G. Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.

More information

134 FERC 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

134 FERC 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 134 FERC 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. California

More information

ALSTON&BIRD LLP. The Atlantic Building 950 F Street, NW Washington, DC Fax:

ALSTON&BIRD LLP. The Atlantic Building 950 F Street, NW Washington, DC Fax: ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-756-3300 Fax: 202-756-3333 Bradley R. Miliauskas Direct Dial: 202-756-3405 Email: bradley.miliauskas@alston.com December

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION DC Energy, LLC ) Complainant, ) ) v. ) Docket No. EL18-170-000 ) PJM Interconnection, L.L.C., ) Respondent. ) ANSWER OF PJM INTERCONNECTION,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator ) Docket No. ER14-2824-000 Corporation ) ) MOTION TO INTERVENE, LIMITED PROTEST AND COMMENTS

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Nevada Power Company ) Docket No. ER15-2281-000 Sierra Pacific Power Company ) Docket No. ER15-2282-000 PacifiCorp ) Docket No.

More information

Southwestern Public Service Company Attachment O SPS Transmission Formula 2017 Projection Material Accounting Changes since January 1, 2016

Southwestern Public Service Company Attachment O SPS Transmission Formula 2017 Projection Material Accounting Changes since January 1, 2016 1 The Company has listed below any material changes that have taken effect since January 1, 2016. For additional information, please refer to the Southwestern Public Service Company FERC Form 1 for Q4

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Laclede Pipeline Company ) Docket No. ISO

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Laclede Pipeline Company ) Docket No. ISO UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Laclede Pipeline Company ) Docket No. ISO6-201-000 RESPONSE OF LACLEDE PIPELINE COMPANY TO MOTION TO INTERVENE AND PROTEST OF THE

More information

Re: PPL Electric Utilities Corporation Transmission Service Charge Effective June 1, 2011 Docket No. M

Re: PPL Electric Utilities Corporation Transmission Service Charge Effective June 1, 2011 Docket No. M PdE SCHELL,,; ArrOENETA Ar IMV Four Penn Center 1600 John F Kennedy Blvd. Philadelphia, PA 19103 215-587-1000 Main 215-587-1444 Main Fax www.postschell.com David B. MacGregor dmacgregor@postschell.com

More information

Pursuant to Rules 211, 213, and 214 of the Rules and Regulations of the Federal

Pursuant to Rules 211, 213, and 214 of the Rules and Regulations of the Federal UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Winding Creek Solar LLC ) ) ) Docket Nos. EL15-52-000 QF13-403-002 JOINT MOTION TO INTERVENE, PROTEST, AND ANSWER OF SOUTHERN CALIFORNIA

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION American Electric Power Service Corporation, ) Complainant ) v. ) Docket No. EL19-18-000 PJM Interconnection, L.L.C., ) Respondent

More information

STATE OF NEW YORK PUBLIC SERVICE COMMISSION

STATE OF NEW YORK PUBLIC SERVICE COMMISSION STATE OF NEW YORK PUBLIC SERVICE COMMISSION ---------------------------------------------------------------------------x CASE 00-M-0504 - Proceeding on Motion : of the Commission Regarding Provider of

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service Company ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service Company ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Arizona Public Service Company ) Docket No. ER16-1342- MOTION FOR CLARIFICATION OR, IN THE ALTERNATIVE, REQUEST FOR REHEARING OF

More information

ISO New England Inc. ) Docket Nos. ER ) EL

ISO New England Inc. ) Docket Nos. ER ) EL UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ISO New England Inc. ) Docket Nos. ER13-2149-000 ) EL13-72-000 COMMENTS AND ALTERNATIVE PROPOSAL OF THE NEW ENGLAND POWER POOL PARTICIPANTS

More information

123 FERC 61,016 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued April 4, 2008)

123 FERC 61,016 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE FILING. (Issued April 4, 2008) 123 FERC 61,016 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G. Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.

More information

Resource Adequacy Locational Reforms. August 2017

Resource Adequacy Locational Reforms. August 2017 Resource Adequacy Locational Reforms August 2017 1 Purpose & Key Takeaways Key Takeaways: Purpose: Discuss locational proposal and updated draft Tariff language, focusing on recent stakeholder feedback

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corp., Docket No. ER15-1229-000 MOTION TO INTERVENE AND COMMENTS OF Pursuant to Rules 211

More information

144 FERC 61,159 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C August 28, 2013

144 FERC 61,159 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C August 28, 2013 144 FERC 61,159 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426 August 28, 2013 In Reply Refer To: Kinetica Energy Express, LLC Docket No. RP13-1116-000 Crowell & Morning Attention: Jenifer

More information

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction

5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies LSE Participation in the ICAP Spot Market Auction 5.14 Installed Capacity Spot Market Auction and Installed Capacity Supplier Deficiencies 5.14.1 LSE Participation in the ICAP Spot Market Auction 5.14.1.1 ICAP Spot Market Auction When the ISO conducts

More information

DEFAULT SERVICE IN PENNSYLVANIA. David B. MacGregor, Esquire Anthony D. Kanagy, Esquire Post & Schell, P.C.

DEFAULT SERVICE IN PENNSYLVANIA. David B. MacGregor, Esquire Anthony D. Kanagy, Esquire Post & Schell, P.C. DEFAULT SERVICE IN PENNSYLVANIA David B. MacGregor, Esquire Anthony D. Kanagy, Esquire Post & Schell, P.C. Synopsis: This presentation provides an overview of default electric service in Pennsylvania beginning

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Cost Recovery Mechanisms for Modernization of Natural Gas Facilities Docket No. PL15-1- 000 REPLY COMMENTS OF THE NATURAL GAS SUPPLY

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Jaime Rose Gannon jrg@cpuc.ca.gov 415-846-4365 California Public Utilities Commission 3/11/2019 Please use this template to provide your

More information

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION 165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur and Richard Glick. California Independent System Operator

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Midcontinent Independent System ) Docket No. ER Operator, Inc.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Midcontinent Independent System ) Docket No. ER Operator, Inc. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Midcontinent Independent System ) Docket No. ER18-462-000 Operator, Inc. ) PROTEST OF THE NRG COMPANIES AND THE DYNEGY COMPANIES

More information

STATE OF CONNECTICUT WRITTEN EXCEPTIONS OF RETAIL ENERGY SUPPLY ASSOCIATION

STATE OF CONNECTICUT WRITTEN EXCEPTIONS OF RETAIL ENERGY SUPPLY ASSOCIATION STATE OF CONNECTICUT DEP ARTMENT OF PUBLIC UTILITY CONTROL DPUC INVESTIGATION INTO THE CONNECTICUT LIGHT AND POWER COMPANY'S BILLING ISSUES DOCKET NO. 08-02-06 JUL Y 7, 2008 WRITTEN EXCEPTIONS OF RETAIL

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER03-746-000 Operator Corporation ) ) ) San Diego Gas & Electric Company, ) Complainant,

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Curt Hébert, Jr., Chairman; William L. Massey, and Linda Breathitt. California Independent System Operator Corporation

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Credit and Capital Issues Affecting the ) Docket No. AD09-2-000 Electric Power Industry ) COMMENTS OF SOUTHERN CALIFORNIA EDISON

More information

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C August 1, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 700 Louisiana Street, Suite 700 Houston, Texas 77002-2700 John A. Roscher

More information

ORAL ARGUMENT NOT YET SCHEDULED UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT. Nos and

ORAL ARGUMENT NOT YET SCHEDULED UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT. Nos and USCA Case #12-1008 Document #1400702 Filed: 10/19/2012 Page 1 of 22 ORAL ARGUMENT NOT YET SCHEDULED UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT Nos. 12-1008 and 12-1081 TC RAVENSWOOD,

More information

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS 1. INTRODUCTION SCE shall calculate its Base Transmission Revenue Requirement ( Base TRR ), as defined in Section 3.6 of the main definitions section of

More information

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update Entergy Services, Inc. 101 Constitution Ave., N.W. Suite 200 East Washington, DC 20001 Tel: 202 530 7323 Fax: 202 530 7350 E-mail: mgriffe@entergy.com Michael C. Griffen Assistant General Counsel Federal

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Duke Energy South Bay, LLC ) Docket No. ER

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Duke Energy South Bay, LLC ) Docket No. ER UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Duke Energy South Bay, LLC ) Docket No. ER03-117-000 JOINT PROTEST OF CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION, CALIFORNIA ELECTRICITY

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Protest of Public Citizen, Inc.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Protest of Public Citizen, Inc. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Entergy Nuclear FitzPatrick, LLC Exelon Generation Company, LLC Docket No. EC16-169 Dated October 11, 2016 Protest of Public Citizen,

More information

February 23, 2015 VIA ELECTRONIC FILING

February 23, 2015 VIA ELECTRONIC FILING February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket

More information

Energy Bar Association

Energy Bar Association Energy Bar Association EBA Energizer: Section 205/206 Fundamentals and Insights November 17, 2016 David DesLauriers, Director Black & Veatch Management Consulting, LLC Jason T. Gray Esq., Shareholder Duncan,

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Transmission Planning and Cost Allocation ) by Transmission Owning and Operating ) Docket No. RM10-23- 000 Public Utilities ) Comments

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, and Nora Mead Brownell. California Power Exchange Corporation Docket No.

More information

Southwestern Public Service Company Attachment O SPS Transmission Formula Annual True-up for 2016 Material Accounting Changes since January 1, 2016

Southwestern Public Service Company Attachment O SPS Transmission Formula Annual True-up for 2016 Material Accounting Changes since January 1, 2016 1 The Company has listed below any material changes that have taken effect since January 1, 2016. For additional information, please refer to the Southwestern Public Service Company FERC Form 1 for Q4

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Pacific Gas and Electric Company ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Pacific Gas and Electric Company ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Pacific Gas and Electric Company ) Docket No. EL16-47-000 REQUEST FOR REHEARING OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR The

More information

American Electric Power Service Corporation Docket No. ER10- -

American Electric Power Service Corporation Docket No. ER10- - American Electric Power 801 Pennsylvania Avenue N.W. Suite 320 Washington, DC 20004 AEP.com May 3, 2010 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E.

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

SDG&E Applies to Default Small Non-Residential Customers to Critical Peak Pricing in 2013

SDG&E Applies to Default Small Non-Residential Customers to Critical Peak Pricing in 2013 UGI Utilities - Gas Division Files Unopposed POR Settlement UGI Utilities, Inc. - Gas Division has filed an unopposed settlement that would institute a Purchase of Receivables program for customers served

More information

161 FERC 61,010 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

161 FERC 61,010 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 161 FERC 61,010 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. Ad Hoc Renewable Energy Financing

More information

Mich. ALJ Recommends Implementation of Pooling at Consumers Energy

Mich. ALJ Recommends Implementation of Pooling at Consumers Energy March 25, 2010 Partial Settlement Filed in PECO Electric POR Case, Discount Rate Issue Reserved Parties have filed a partial settlement concerning PECO's revised electric purchase of receivables program

More information

August 9, 2010 Reliant Energy Seeking Pennsylvania Electric License to Serve Large, Mid-Merit Customers

August 9, 2010 Reliant Energy Seeking Pennsylvania Electric License to Serve Large, Mid-Merit Customers August 9, 2010 Reliant Energy Seeking Pennsylvania Electric License to Serve Large, Mid-Merit Customers Reliant Energy Northeast, LLC, a unit of NRG Energy, applied for a Pennsylvania electric generation

More information

FirstEnergy Files ESP Settlement With Many Nonbypassable Fees, but No Standby Charges

FirstEnergy Files ESP Settlement With Many Nonbypassable Fees, but No Standby Charges February 20, 2009 FirstEnergy Files ESP Settlement With Many Nonbypassable Fees, but No Standby Charges A proposed settlement among the FirstEnergy Ohio utilities, PUCO Staff, and industrial customers

More information