PF Coils Manufacturing and Cold test contract (MFR) Face to face meetings July 2014 Kevin SMITH Pierre GAVOUYERE LASSERRE

Size: px
Start display at page:

Download "PF Coils Manufacturing and Cold test contract (MFR) Face to face meetings July 2014 Kevin SMITH Pierre GAVOUYERE LASSERRE"

Transcription

1 PF Coils Manufacturing and Cold test contract (MFR) Face to face meetings July 2014 Kevin SMITH Pierre GAVOUYERE LASSERRE 1

2 Summary of the presentation PF Coils Project PF Coils Schedule PF Coil Manufacturing Process (general presentation) MFR Scope of Supply (WBS) Contractual Arrangements Definition of the contract type main features Contractual liability and Interface Agreement Main inputs provided by F4E Main outputs expected from the candidate (offer) 2

3 PF Coils Project PF6 Manufacture : done by ASIPP PF2 to 5 Manufacture : 6 main contracts 1. Engineering Integrator (ASG) 2. Winding Tooling (SEA ALP) Russian Domestic Agency 3. Impregnation/Additional Tooling 4. Site & Infrastructure 5. PF Coils Manufacturing & Cold Test ASIPP 6. Cold Test Facility 3

4 PF Coils Schedule Contracts Call for tender Publication Expected Contract signature Duration Procurement procedure Engineering Jan 2013 Aug years Negotiated Integrator Winding Tools Jul 2013 Apr years Negotiated Contract signed Site & Infrastructure Impregnation and Additional Tools Manufacturer (MFR) May 2014 Oct years Open Market Survey Completed June 2014 Dec years Open Market Survey Completed Jul 2014 Apr years Negotiated Market Survey Completed Cold Test facility Sep 2014 Apr years Restricted PF6 ASIPP Oct years Co operation Agreement 4

5 PF Coils Manufacturing Process Superconductor (supplied by IO) Winding & Insulation Double Pancake (DP) Preparation (insulation, joint box & termination) Double pancake (DP) Impregnation Cold Test Final Coil Assembly Winding pack (WP) Impregnation DP Stacking & Winding Pack (WP) Ground Insulation 5

6 PF Coils Manufacturing Process Workflow goes from left to right : WP Impregnation DP Preparation & Impregnation DP Stacking & WP Insulation Storage area Winding & Insulation Conductor spool Storage Cold Test Clean Areas (ISO Class 9) PF Coil working stations 6

7 MFR Scope of Supply (WBS) Level 1 Level 2 Level 3 Manufacturing & Cold Testing Contract Components Qualification Dummy DP Fabrication PF Coils Manufacturing PF Cold Testing Logistics Management & Administration Staff training Access & EHS Management Procurement for component qualification Component fabrication QC Tests, QC reports, recommendations for modifications Procurement for dummy DP s PF4 & PF5 dummy DP fabrication Winding Pack mock up fabrication QC Tests, QC reports, recommendations for modifications Procurement for PF coils PF coils fabrication QC Tests, QC reports, final acceptance tests at room temperature Procurement for cold testing PF coils Cold testing QC Tests, QC reports, final acceptance tests at 80K Preparation for transportation to Tokamak site Takeover of the PF facility Witness installation and commissioning of special tooling Procurement, installation and commissioning of standard tooling Day by day maintenance of special tooling Storehouse procurement and management Working areas cleaning Handover: dismantling of standard tooling Workshop coordination Cost control / procurement activities Reporting to EI and to F4E / Participation to coordination meetings Administration staff Participation to the EI training courses Participation to the Tooling Contractors training courses Participation to the EHS training courses MFR Training for his staff Access control formalities OHS risk analysis Monitoring of the EHS regulations & standards 7

8 Contractual Arrangements Main aims (Reminder Info Days, Cadarache, April 2014): Appropriate allocation of risks Reasonable final price Alignment of contractor s and F4E s interests Possibility to adjust the resources estimate following the learning curve Definition of the contractual arrangements: Firm Price defined by the MFR contractor for: Tools (based on the Technical specifications provided by EI) Materials (based on the BoM provided by EI) Productive staff (based on EI s estimate) Non productive staff (supervision, workshop coordination, management, administration ) entirely defined by MFR Bonus for the completion of the first 2 coils based on milestone achievement Re assessment of the manpower estimate at the end of (or during) the manufacturing of the 2 nd coil MFR's performance measured during the manufacturing of PF2 is used as a basis to define a Final Price Liquidated damages related to the manufacturing of the last two coils (PF4 and PF3) 8

9 Contractual Arrangements Re assessment of the manpower estimate Main tools: MFR s Reporting (e.g. monthly meetings): Actual progress vs. Manufacturing Schedule Actual resources vs. EI s estimates Non productive time Ways to adjust/improve performance (workshop coordination, reorganization, trainings ) Lower threshold: Re assessment to be considered if the productive working hours exceed x% (e.g. 10%) of the ASG's estimate. An estimation of a "normal" non productive time (machine setting, waiting time during conductor handling, machine downtime ) will have to be agreed during the negotiation phase. Relationships" between the PF coils (coefficients): Estimation of the working hours needed for the last two coils (PF4 and 3) by extrapolating from the working hours needed to manufacture 2 nd coil (PF2). 9

10 Contractual Arrangements Interface Agreement The Interface Agreement regulates cooperation between the contractors during the project execution. EI drives the project and gives instructions to the contractors Project Coordination Committee conducts a regular follow up of the Project Interface obligations: definition of the scope of work and the responsibilities of each contractor Dispute resolution procedure: 1.EI 2.F4E 3.Mediator 4.Competent court CEAR Insurance: Cover: material damages (e.g. coils) arising from any causes (unless excluded) Contractor s exposure: 1.deductibles 2.what is not covered For example damage to a coil during impregnation: Insurance? MFR correctly followed procedures? Tools functioned correctly? Procedure provided by EI correct? External cause? 10

11 Main inputs provided by F4E Drawings, BoM, Technical Specifications Control Plans, Manufacturing methods, QC procedures Manufacturing schedule (from components' qualification to the acceptance tests of the last coil) Definition of Worker profiles using International and European standard frameworks: ISCO International Standard Classification of Occupations ESCO European classification of Skills/Competences, Qualifications and Occupations EQF European Qualifications Framework Manpower estimate (productive staff) for each manufacturing phase and each profile of worker (mechanical fitters, electricians, TIG welders, etc ) Manpower estimate = Task duration + Number of workers Example for station A (winding): Winding of 1 DP = 5 weeks Workers = 2.7 Mechanical Fitters + 2 Winders TIG welder 11

12 Main outputs expected from the candidate (offer) Main content of the candidate s Technical Offer: Structure of the MFR s organization: Productive staff (including Logistics) Management and Administration (including EHS management) Strategy and plan to resource the facility during the whole manufacturing process (according to the EI s schedule) Structure of the MFR s supply chain Tools which will be provided by MFR 12

13 Follow us on: for energy

"Manufacturing and Cold Test" Contract (MFR) Questions / Answers

Manufacturing and Cold Test Contract (MFR) Questions / Answers Questions from companies Should potential tenderers (s) responses to all for ender be fully compliant but with a list of issues raised, or can exclusions or nonconformities be raised in the response? Will

More information

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction

More information

Technical Summary. Contract for Cooling Water Plant Installation Works in Building 61

Technical Summary. Contract for Cooling Water Plant Installation Works in Building 61 Contract for Cooling Water Plant Installation Works in Building 61 1 Purpose The purpose of this Call for Nomination is to establish a contract for early cooling water plant installation in the Site Services

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

Call for Nomination for the Tokamak Complex Contract TCC1 & TCC2 PROCUREMENT SUMMARY

Call for Nomination for the Tokamak Complex Contract TCC1 & TCC2 PROCUREMENT SUMMARY Call for Nomination for the Tokamak Complex Contract TCC1 & TCC2 PROCUREMENT SUMMARY 1 Introduction The Call for Nomination subject of the present document is the first step of the Procurement process

More information

Key IRS Interest Rates After PPA

Key IRS Interest Rates After PPA Key IRS Rates - After PPA - thru 2011 Page 1 of 10 Key IRS Interest Rates After PPA (updated upon release of figures in IRS Notice usually by the end of the first full business week of the month) Below

More information

DALLAS COUNTY DISTRICT COURT ADMINISTRATION

DALLAS COUNTY DISTRICT COURT ADMINISTRATION DALLAS COUNTY DISTRICT COURT ADMINISTRATION April 14, 2009 BRIEFING MEMORANDUM TO: FROM: Honorable Commissioners Court Duane Allen Gallup ADR Coordinator SUBJECT: ADR Program & Dispute Mediation Services

More information

Large Commercial Rate Simplification

Large Commercial Rate Simplification Large Commercial Rate Simplification Presented to: Key Account Luncheon Red Lion Hotel Presented by: Mark Haddad Assistant Director/CFO October 19, 2017 Most Important Information First There is no rate

More information

Business & Financial Services December 2017

Business & Financial Services December 2017 Business & Financial Services December 217 Completed Procurement Transactions by Month 2 4 175 15 125 1 75 5 2 1 Business Days to Complete 25 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 217 Procurement

More information

MANAGING FOR RESULTS: An Implementation Plan for the City of Portland

MANAGING FOR RESULTS: An Implementation Plan for the City of Portland MANAGING FOR RESULTS: An Implementation Plan for the City of Portland Office of Management and Finance City Auditor s Office Bureau of Planning City of Portland, Oregon June, 2003 Managing for Results

More information

Practical Cost Control Handbook for Project Managers

Practical Cost Control Handbook for Project Managers JEREMIE AVEROUS Practical Cost Control Handbook for Project Managers A Practical Guide to Enable Consistent and Predictable Forecasting for Large, Complex Projects We can Customize this Handbook for your

More information

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016 October 2017 The Charities Regulator, in accordance with the provisions of section 14 of the Charities Act 2009, carried

More information

NORTHROP GRUMMAN SYSTEMS CORPORATION

NORTHROP GRUMMAN SYSTEMS CORPORATION NORTHROP GRUMMAN SYSTEMS CORPORATION ADDENDUM TO COMMERCIAL TERMS AND CONDITIONS FOR SUBCONTRACTS IN SUPPORT OF THE ADVANCED MISSION PROGRAM (AMP) PRIME CONTRACT 04-C-3045 All of the additional terms and

More information

The First Steps in Implementing a Simplified Earned Value Management System

The First Steps in Implementing a Simplified Earned Value Management System 2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface

More information

Housing Operations. Housing Division Re-Organization. Rent Supplement Deficit 2016 Audit Results 2018 Operating Budget(s) Next Steps

Housing Operations. Housing Division Re-Organization. Rent Supplement Deficit 2016 Audit Results 2018 Operating Budget(s) Next Steps Housing Operations Housing Operations Housing Division Re-Organization Robert Lee s retirement Rent Supplement Deficit 2016 Audit Results 2018 Operating Budget(s) Next Steps Housing Division Re-Org Principles

More information

L3 Technologies, Inc.

L3 Technologies, Inc. 1. When the materials or products furnished are for use in connection with a U.S. Government contract or subcontract, in addition to the L3 General Terms and Conditions for Supply and Services Subcontracts,

More information

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: June 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - June 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800 Dec 2015

More information

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: September 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - September 2018 (Single Computation) 11400 - Yorktown Funds 11200 11000 10800 10600

More information

SUPPLIER PRE QUALIFICATIONS QUESTIONAIRE SECTION 1: COMPANY IDENTITY

SUPPLIER PRE QUALIFICATIONS QUESTIONAIRE SECTION 1: COMPANY IDENTITY SUPPLIER PRE QUALIFICATIONS QUESTIONAIRE SECTION 1: COMPANY IDENTITY Company Name Office Address Factory Address Warehouse Address Primary Contact Position Phone Fax Email Website Mailing Address Trade

More information

Property Handling Process

Property Handling Process Property Handling Process Insert Picture of Defect or Process Project Start: 10 / 2009 Project Revision: 8 / 2010 Project Champion: Diannia Jackson Black/Green Belt: Jimmy Toler 1 Define Phase 1. Select

More information

Change Order Guidelines: Quick Reference

Change Order Guidelines: Quick Reference ELECTRI International The Foundation for Electrical Construction, Inc. PRODUCTIVITY ENHANCEMENT Change Order Guidelines: Quick Reference ELECTRI International 3 Bethesda Metro Center, Suite 1100 Bethesda,

More information

SCHEDULE 10 INDEX FACTOR

SCHEDULE 10 INDEX FACTOR SCHEDULE 10 INDEX FACTOR SCHEDULE 10 INDEX FACTOR 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance and

More information

SCHEDULE 10 INDEX FACTOR

SCHEDULE 10 INDEX FACTOR DRAFT SCHEDULE 10 INDEX FACTOR SCHEDULE 10 INDEX FACTOR 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance

More information

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017)

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017) LCCI International Qualifications Cost Accounting Level 3 Model Answers Series 3 2009 (3017) For further information contact us: Tel. +44 (0) 8707 202909 Email. enquiries@ediplc.com www.lcci.org.uk Cost

More information

NHS Pensions Re-Procurement Programme

NHS Pensions Re-Procurement Programme NHS Pensions Re-Procurement Programme Pensioner Payroll Supplier Boot Camp 7 th October 2015 Introduction to NHS Business Services Authority Steven Pink Director of Change and Commercial Delivery Project

More information

SOCIAL SECURITY PREMIUMS

SOCIAL SECURITY PREMIUMS SOCIAL SECURITY PREMIUMS PAYABLE BY CONTRACTORS DayaRahyaft Audit & Management Services Firm www.dayarahyaft.com Social Security Organization has just made a revision of its regulations and circulars concerning

More information

An ISO 9001:2015 & ISO 29990:2010 Certified Company TRAINING CALENDAR. Quality Assured Training 15-NOV-16

An ISO 9001:2015 & ISO 29990:2010 Certified Company TRAINING CALENDAR. Quality Assured Training 15-NOV-16 An ISO 9001:2015 & ISO 29990:2010 Certified Company TRAINING CALENDAR 2017 Quality Assured Training 15-NOV-16 An ISO 9001:2015 & ISO 29990:2010 Certified Company ABOUT US A High Impact, Quality Assured

More information

QUARTERLY FINANCIAL REPORT March 31, 2018

QUARTERLY FINANCIAL REPORT March 31, 2018 California Independent System Operator QUARTERLY FINANCIAL REPORT March 31, 2018 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

1 Long Term Debt $ 9,298,554 $ (250,000) $ 9,048, Preferred Stock 30,450 30, % 5 Common Equity 250, %

1 Long Term Debt $ 9,298,554 $ (250,000) $ 9,048, Preferred Stock 30,450 30, % 5 Common Equity 250, % SUMMARY SCHEDULE ($000'S) Schedule 1 Page 1 of 1 Line Capitalization HISTORICAL YEAR ENDED 12/31/16 Hybrid Percent Equity Adjusted of Total Cost of Cost of Amount Adjustment Amount Capitalization Capital

More information

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy?

QUESTION 2. QUESTION 3 Which one of the following is most indicative of a flexible short-term financial policy? QUESTION 1 Compute the cash cycle based on the following information: Average Collection Period = 47 Accounts Payable Period = 40 Average Age of Inventory = 55 QUESTION 2 Jan 41,700 July 39,182 Feb 18,921

More information

Department of Market Monitoring White Paper. Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources

Department of Market Monitoring White Paper. Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources Department of Market Monitoring White Paper Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources Revised: November 21, 2011 Table of Contents 1 Executive

More information

1. Background General information on the initiative... 3

1. Background General information on the initiative... 3 Contents 1. Background... 3 1.1 General information on the initiative... 3 1.2 Implementation modalities... 4 2. Project Budget and funds utilization... 4 2.1 Budget components and utilization... 4 2.2

More information

Program Reporting. Contents. Integral planning forecast Capgemini. All rights reserved. 1

Program Reporting. Contents. Integral planning forecast Capgemini. All rights reserved. 1 Program Reporting Integral planning forecast Reporting week: 30 Contents 1. Introduction 2. Forecast delivery planning 6 weeks 3. Delivery planning changes 4. Program consolidated status 5. Project delivery

More information

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017.

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for August 2018 Date: October 10, 2018 I. Summary CTA s financial results are favorable to budget for

More information

QUARTERLY FINANCIAL REPORT June 30, 2017

QUARTERLY FINANCIAL REPORT June 30, 2017 California Independent System Operator QUARTERLY FINANCIAL REPORT June 30, 2017 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

Construction of the #7 Line Subway Extension Project New York September 17, 2018

Construction of the #7 Line Subway Extension Project New York September 17, 2018 Construction of the #7 Line Subway Extension Project New York September 17, 2018 Saibal Basuroy, PMP Project Controls Director, Hill International Inc. Disclaimer This presentation is protected by US and

More information

Spheria Australian Smaller Companies Fund

Spheria Australian Smaller Companies Fund 29-Jun-18 $ 2.7686 $ 2.7603 $ 2.7520 28-Jun-18 $ 2.7764 $ 2.7681 $ 2.7598 27-Jun-18 $ 2.7804 $ 2.7721 $ 2.7638 26-Jun-18 $ 2.7857 $ 2.7774 $ 2.7690 25-Jun-18 $ 2.7931 $ 2.7848 $ 2.7764 22-Jun-18 $ 2.7771

More information

Pareto Securities Oil & Offshore Conference

Pareto Securities Oil & Offshore Conference Pareto Securities Oil & Offshore Conference September 2-3, 2015 Oslo, Norway www.paragonoffshore.com Safe Harbor Statement This material contains statements that are forward looking statements about Paragon

More information

Financial Accounting s Conceptual Foundations

Financial Accounting s Conceptual Foundations Economics /Management 4 Financial Accounting Financial Accounting s Conceptual Foundations L-2 A highly-stylized Information System Basic Functions (all info systems): 1. Collection of transactions data

More information

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett (RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford

More information

SCHEDULE 10 INDEX FACTOR

SCHEDULE 10 INDEX FACTOR SCHEDULE 10 INDEX FACTOR 1. GENERAL 1.1 Capitalized Terms Capitalized terms used in this Schedule have the definitions as set out in the Agreement to Design, Build, Finance and Maintain Nine New Schools

More information

Section 9 : GOVERNMENT CONTRACT REQUIREMENTS

Section 9 : GOVERNMENT CONTRACT REQUIREMENTS Section 9 : GOVERNMENT CONTRACT REQUIREMENTS CLAUSE 90J (1/10/00) F04701-96-C-0025 GLOBAL POSITIONING SYSTEMS (GPS-IIF) GOVERNMENT CONTRACT REQUIREMENTS (a) The following contract clauses are incorporated

More information

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Management Proposal

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Management Proposal ARTES Competitiveness & Growth Full Proposal Requirements for the Content of the Management Proposal Part 5B Work Definition, Organisation and Schedule Statement of Applicability and Proposal Submission

More information

VIIl. Agency Financial Plans and 12-Month Allocations

VIIl. Agency Financial Plans and 12-Month Allocations VIIl. Agency Financial Plans and 12-Month Allocations New York City Transit MTA NEW YORK CITY TRANSIT FEBRUARY FINANCIAL PLAN FOR 2006-2009 2005 FINAL ESTIMATE AND ADOPTED BUDGET FOR 2006 In accordance

More information

HOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics

HOPE NOW. Snapshot Industry Extrapolations and HAMP Metrics Snapshot Industry Extrapolations and HAMP Metrics Three Month Q2-215 Q3-215 Q4-215 Q1-216 Q2-216 Jun-16 Jul-16 Aug-16 Total Completed Modifications 119,658 97,773 84,798 86,167 1,198 41,872 34,815 36,6

More information

Cherry Hill Board of Education

Cherry Hill Board of Education Cherry Hill Board of Education ENERGY SAVINGS PLAN (ESP) PRESENTATION JANUARY 15, 2013 Presented By: Tom Xenakis, PE - Vice President, Commercial John Marchiafava, PE - Engineering Manager, Commercial

More information

UNICEF s Strategic Planning Processes

UNICEF s Strategic Planning Processes UNICEF s Strategic Planning Processes Outline of the Presentation Overview The Strategic Plan: The (current) Strategic Plan 2014-2017 Findings from the Mid Term review of the Strategic Plan 2014-2017 Preparing

More information

Work Program Integration Initiative (WPII)

Work Program Integration Initiative (WPII) Florida Department of TRANSPORTATION Work Program Integration Initiative (WPII) Florida PALM Executive Steering Committee Meeting February 27, 2019 Florida Department of Transportation Agenda Overview

More information

PASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA. 24 th April 2018

PASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA. 24 th April 2018 PASSENGER REJECTION REDUCTION INITIATIVE KIRK PEREIRA 24 th April 2018 WHAT IS THIS PROJECT ABOUT? Well we are not going into that again this year! Nearly everyone in this room knows about the project

More information

Invitation for Pre-Qualification of Bidders for 1X600 MT Mounded Pressurized Storage Vessel at Lucknow LPG Plant.

Invitation for Pre-Qualification of Bidders for 1X600 MT Mounded Pressurized Storage Vessel at Lucknow LPG Plant. Invitation for Pre-Qualification of Bidders for 1X600 MT Mounded Pressurized Storage Vessel at Lucknow LPG Plant. TENDER NO. : E&P:PQR:MSV/12-13/ 01 DATED 13-07-2012 Bharat Petroleum Corporation Ltd.,

More information

THE B E A CH TO WN S O F P ALM B EA CH

THE B E A CH TO WN S O F P ALM B EA CH THE B E A CH TO WN S O F P ALM B EA CH C OU N T Y F LO R I D A August www.luxuryhomemarketing.com PALM BEACH TOWNS SINGLE-FAMILY HOMES LUXURY INVENTORY VS. SALES JULY Sales Luxury Benchmark Price : 7,

More information

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date:

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date: DATA ITEM DESCRIPTION Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT Number: Approval Date: 20091026 AMSC Number: N9105 Limitation: DTIC Applicable: N/A GIDEP Applicable: N/A Office

More information

SALT RSS-NIR MID-TERM REVIEW MAY 20 & 21, 2009 SCHEDULE AND BUDGET

SALT RSS-NIR MID-TERM REVIEW MAY 20 & 21, 2009 SCHEDULE AND BUDGET SALT RSS-NIR MID-TERM REVIEW MAY 20 & 21, 2009 SCHEDULE AND BUDGET MARK MULLIGAN UNIVERSITY OF WISCONSIN Overview Work Breakdown Structure Development Flow Schedule - Critical Path Phases & Key Milestones

More information

Fleet Status Report. ENSCO 8505 and ENSCO 8503 Contracted into 3Q April 2018 ENSCO 8505

Fleet Status Report. ENSCO 8505 and ENSCO 8503 Contracted into 3Q April 2018 ENSCO 8505 ENSCO 8505 ENSCO 8505 and ENSCO 8503 ed into 3Q18 Recently, ENSCO 8505 was awarded two contracts for a total of three wells and ENSCO 8503 was contracted for two wells. Both rigs are capable of operating

More information

Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization

Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization Completion Report Project Number: 46-01 Technical Assistance Number: 7857 April 016 Lao People's Democratic Republic: Strengthening the Capacity of the State Audit Organization This document is being disclosed

More information

The Development Agreement. Long-Term Care Home Renewal Branch October 2016

The Development Agreement. Long-Term Care Home Renewal Branch October 2016 The Development Agreement Long-Term Care Home Renewal Branch October 2016 Learning Objectives By the end of this session, you will have a solid understanding of: The description and purpose of a Development

More information

Project Connect Connect January 11, 2012

Project Connect Connect January 11, 2012 Project Connect January 11, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next

More information

Questions to Consider When You Implement Oracle Assets

Questions to Consider When You Implement Oracle Assets Questions to Consider When You Implement Oracle Assets Cindy Cline Cline Consulting and Training Solutions, LLC During the implementation of Oracle Assets, several issues will arise and numerous decisions

More information

Redwood Empire Quilters Guild Job Description Rev. 08/2010

Redwood Empire Quilters Guild Job Description Rev. 08/2010 Redwood Empire Quilters Guild Job Description Rev. 08/2010 Job Title Treasurer Voting Board Member Yes Key Responsibilities Responsible for all financial transactions and financial records of the guild.

More information

E.1E RS. DE I(o J -1 E NERGY. p -J. February 28, By Electronic Deliveiy & Hand Delivery

E.1E RS. DE I(o J -1 E NERGY. p -J. February 28, By Electronic Deliveiy & Hand Delivery p -J DE I(o J -1 E.1E RS w 78() N. Commercial Street, Nfanehester, NH 03101 E ersource Energy E NERGY P.O. I3ox 330 Manchester, NH 03105-0330 (603) 634-2701 Christopher J. Goulding Manager. NH Revenue

More information

SUPPLIER PREQUALIFICATION QUESTIONNAIRE

SUPPLIER PREQUALIFICATION QUESTIONNAIRE As a prerequisite to being considered to provide services for West White Rose Project (WWRP), all potential suppliers must complete and submit the attached questionnaire for evaluation. The information

More information

BC HYDRO SITE C CLEAN ENERGY PROJECT SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT. for the Site C Clean Energy Project

BC HYDRO SITE C CLEAN ENERGY PROJECT SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT. for the Site C Clean Energy Project BC HYDRO SITE C CLEAN ENERGY PROJECT SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT for the Site C Clean Energy Project British Columbia Hydro and Power Authority and Voith Hydro Inc. Dated:

More information

Updates & Milestones re: Peak Demand Reduction. EEAC Consultants (with PA contributions) (Revised, 3/13/17)

Updates & Milestones re: Peak Demand Reduction. EEAC Consultants (with PA contributions) (Revised, 3/13/17) Updates & Milestones re: Peak Demand Reduction EEAC Consultants (with PA contributions) (Revised, 3/13/17) Key Work Streams in 2016-2018 Following the Analytical Framework Cost-Effectiveness Framework

More information

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program HUD NSP-1 Reporting Apr 2010 Grantee Report - State Program State Program NSP-1 Grant Amount is $19,600,000 $9,355,381 (47.7%) has been committed $4,010,874 (20.5%) has been expended Grant Number HUD Region

More information

How To Reduce Transfer Pricing Compliance Costs?

How To Reduce Transfer Pricing Compliance Costs? How To Reduce Transfer Pricing Compliance Costs? Margie van der Valk and Maria Grigoryeva TPA Global, Amsterdam (The Netherlands) 5 April 2018 1 Increased work burden What will the tax inspector receive

More information

Key IRS Interest Rates After PPA

Key IRS Interest Rates After PPA Key IRS Interest After PPA (updated upon release of figures in IRS Notice usually by the end of the first full business week of the month) Below are Tables I, II, and III showing official interest rates

More information

Document A Exhibit A Determination of the Cost of the Work

Document A Exhibit A Determination of the Cost of the Work Document A121 2014 Exhibit A Determination of the Cost of the Work THE OWNER: (Name, legal status, address and other information) THE CONTRACTOR: (Name, legal status, address and other information) This

More information

Text. New gtld Auctions #ICANN49

Text. New gtld Auctions #ICANN49 Text Text New gtld Auctions Agenda Auction Summary Text Public Comment Recap Auction Logistics Looking Ahead Q &A Auctions Summary Auctions Method of Last Resort per Applicant Text Guidebook 4.3 o Ascending

More information

EXHIBIT A GOVERNMENT PROVISIONS APPLICABLE TO PRIME CONTRACT FA D-2451

EXHIBIT A GOVERNMENT PROVISIONS APPLICABLE TO PRIME CONTRACT FA D-2451 EXHIBIT A GOVERNMENT PROVISIONS APPLICABLE TO PRIME CONTRACT FA8632-05-D-2451 The clauses contained in the following Government regulations are incorporated by reference. Where necessary or appropriate

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL For Construction Manager as Constructor for Tri-North Middle School Response Due: April 2, 2018, 1:00 pm MCCSC Service Building 560 E. Miller Drive Bloomington, IN 47401. REQUEST FOR

More information

CIRB Guidelines: Conversion of Paper Studies into ishare Studies

CIRB Guidelines: Conversion of Paper Studies into ishare Studies CIRB Guidelines: Conversion of Paper Studies into ishare Studies 1. Introduction ishare e-cirb was rolled out in September 2014. The ishare was fully developed in December 2016. CIRB has processed more

More information

Energy Yield Reconciliation in Monthly O&M Reports

Energy Yield Reconciliation in Monthly O&M Reports Energy Yield Reconciliation in Monthly O&M Reports Claire Puttock, Lee Cameron & Alex Clerc April 15, 2016 EWEA Technology Workshop, Bilbao Contents Introduction to variance explanation Motivation Key

More information

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017.

Cash & Liquidity The chart below highlights CTA s cash position at January 2018 compared to January 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for January 2018 Date: March 14, 2018 I. Summary CTA s financial results are $1.7 million unfavorable

More information

AIA Document A103 TM 2007

AIA Document A103 TM 2007 AIA Document A103 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work plus a fee without a Guaranteed Maximum Price AGREEMENT made as of the

More information

Management Reports. June for PREPARED BY POWERED BY

Management Reports. June for PREPARED BY POWERED BY Management Reports for June 217 PREPARED BY POWERED BY Contents 1. Management Reports Cashflow Forecast Actual vs Budget P&L Forecast Where Did Our Money Go? Net Worth 2. Understanding your Reports 3.

More information

Goldman Sachs Global Energy Conference January 5, Rob Saltiel President & CEO

Goldman Sachs Global Energy Conference January 5, Rob Saltiel President & CEO Goldman Sachs Global Energy Conference January 5, 2017 Rob Saltiel President & CEO 1 Forward-Looking Statements Statements contained in this report with respect to the future are forward-looking statements.

More information

Effective January 1st, 2013, the following promotional payments will be available to appropriate independent distributors:

Effective January 1st, 2013, the following promotional payments will be available to appropriate independent distributors: Topics Effective January 1st, 2013, the following promotional payments will be available to appropriate independent distributors: At the level of and above 1) Title Incentive 2) Group Awards 3) Rising

More information

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017.

Cash & Liquidity The chart below highlights CTA s cash position at June 2018 compared to June 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for June 2018 Date: August 15, 2018 I. Summary CTA s financial results are unfavorable to budget for

More information

Beginning Date: January 2016 End Date: February Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Beginning Date: January 2016 End Date: February Managers in Zephyr: Benchmark: Morningstar Short-Term Bond Beginning Date: January 2016 End Date: February 2018 Managers in Zephyr: Benchmark: Manager Performance January 2016 - February 2018 (Single Computation) 11200 11000 10800 10600 10400 10200 10000 9800

More information

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 Technical Assistance Report Project Number: 40345 April 2008 Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 The views expressed herein are those

More information

Distribution Group Study Process. August 26, 2014

Distribution Group Study Process. August 26, 2014 Distribution Group Study Process August 26, 2014 Agenda Overview Applying for DGSP DGSP Interconnection Process Applicability and Utility Contacts Questions 2 Process Overview Open Window Period Evaluation

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE C&T:JTL 1 of 6 C&T:APPR:JDC:PAL:07-24-02 FHWA:APPR:06-01-11 a. Description. In addition to the progress

More information

(WEBSITE ONLY) EMPLOYEE SHARE PLANS

(WEBSITE ONLY) EMPLOYEE SHARE PLANS (WEBSITE ONLY) EMPLOYEE SHARE PLANS 31 December HIGHLY RESTRICTED Employee Share Plans In accordance with the terms of a waiver granted by the Hong Kong Stock Exchange on 24 December 2010, full details

More information

Kuwait National Petroleum Company

Kuwait National Petroleum Company Kuwait National Petroleum Company Clean Fuels Project 2020 Cost & Budgeting of a Mega Project, Oct. 2018 Presenter: Eng. Wael Al-Jasem Former Team Leader Project Management KNPC Now Team Leader Mega Projects

More information

Operating Reserves Educational Session Part B

Operating Reserves Educational Session Part B Operating Reserves Educational Session Part B Energy Market Uplift Senior Task Force September 17, 2013 Joseph Bowring Joel Romero Luna Operating Reserves Operating reserves can be grouped into five categories:

More information

Big Walnut Local School District

Big Walnut Local School District Big Walnut Local School District Monthly Financial Report for the month ended September 30, 2012 Prepared By: Felicia Drummey Treasurer BIG WALNUT LOCAL SCHOOL DISTRICT SUMMARY OF YEAR-TO-DATE FINANCIAL

More information

Contract Management Training

Contract Management Training Contract Management Training Everyone working on Projects must be familiar with Contracts. To this end, I have developed a very practical 2 day training: Hands-On Contract Management This presentation

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

Trade Finance, Letters of Credit and Bank Guarantees

Trade Finance, Letters of Credit and Bank Guarantees Trade Finance, Letters of Credit and Bank Guarantees Page 1 of 10 Why Attend Securing company s assets while transacting with local and international customers is critical for the success and sustainability

More information

After the Rate Increase, What Then?

After the Rate Increase, What Then? After the Rate Increase, What Then? Robert Eisenbeis, Ph.D. Vice Chairman & Chief Monetary Economist Bob.Eisenbeis@Cumber.com What the FOMC Did At Dec Meeting The Fed made the first step towards normalization

More information

2019 Budget and Grid Management Charge Initial Stakeholder Meeting

2019 Budget and Grid Management Charge Initial Stakeholder Meeting 2019 Budget and Grid Management Charge Initial Stakeholder Meeting July 24, 2018 Agenda Topic: Welcome and Introductions Presenter: Kristina Osborne 2019 Budget Process & GMC Rate Outlook April Gordon

More information

Update on the Financial Framework Review. Informal Consultation 25 July 2016

Update on the Financial Framework Review. Informal Consultation 25 July 2016 Update on the Financial Framework Review Informal Consultation 25 July 2016 Integrated Roadmap: Alignment of Strategic Plan, Country Strategic Plan, Corporate Results Framework and Financial Framework

More information

CONSULTANT TEAM DRAFT WORK PLAN AND BUDGET

CONSULTANT TEAM DRAFT WORK PLAN AND BUDGET CONSULTANT TEAM DRAFT 2017-2018 WORK PLAN AND BUDGET August 16, 2017 CONTEXT Incorporates EEAC priorities, Councilor input, and experience from previous work plans Covers a 16 month period from Sep 2017

More information

Draft Design and Monitoring Framework

Draft Design and Monitoring Framework Draft Design and Monitoring Framework Project Number: 42394-022 August 2011 TON : Nuku'alofa Urban Development Sector Project A design and monitoring framework is an active document, progressively updated

More information

Review of Membership Developments

Review of Membership Developments RIPE Network Coordination Centre Review of Membership Developments 7 October 2009/ GM / Lisbon http://www.ripe.net 1 Applications development RIPE Network Coordination Centre 140 120 100 80 60 2007 2008

More information

PimaCountyCommunityCollegeDistrict Board of Governors 4905C East Broadway/Tucson, Arizona INFORMATION REPORT

PimaCountyCommunityCollegeDistrict Board of Governors 4905C East Broadway/Tucson, Arizona INFORMATION REPORT PimaCountyCommunityCollegeDistrict Board of Governors 4905C East Broadway/Tucson, Arizona 85709-1010 INFORMATION REPORT Meeting Date: 9/14/16 Item Number: 2.1 Item Title Financial Report July 2016 Financial

More information

Blanket Purchase Agreement Attachment 1 FAR/DFARS Clauses

Blanket Purchase Agreement Attachment 1 FAR/DFARS Clauses Orders issued against this Blanket Purchase Agreement (BPA) are subject to the clauses included in the underlying General Services Administration (GSA) Federal Supply Schedule (FSS) Contract and the additional

More information

Government Bond Market Development in Myanmar

Government Bond Market Development in Myanmar Government Bond Market Development in Myanmar Daw Si Si Pyone Deputy Director General Treasury Department 11-8-2017 Ministry of Planning and Finance 1 Outlines I. Key Milestones in Development of Treasury

More information

«Kekava Bypass» Case Study

«Kekava Bypass» Case Study «Kekava Bypass» Case Study 28 September, 2017 Contents Introduction 3 Project details 6 Legal aspects Procurement procedure 15 Legal aspects PPP Agreement 22 Finance aspects 26 Off balance sheet treatment

More information

Simplo Technology Co.,Ltd Company Profile

Simplo Technology Co.,Ltd Company Profile Simplo Technology Co.,Ltd Company Profile Jeanie Wei 2018 December http://www.simplo.com.tw Taiex ticker:6121 Milestones Apr 1992 Company founded Jul 1998 Nov 2001 Feb 2002 Mar 2002 Oct 2002 Nov 2002 Oct

More information