SMUD ANNUAL DISCLOSURE For the Year Ended 12/31/2017
|
|
- Marshall Hubbard
- 5 years ago
- Views:
Transcription
1 SMUD ANNUAL DISCLOSURE For the Year Ended 12/31/2017 POWER SUPPLY RESOURCES The following table sets forth information concerning SMUD s power supply resources as of April 30, Capacity availability reflects rated or nameplate capacities at SMUD s load center, as well as entitlement, firm allocations and contract amounts. Source: POWER SUPPLY RESOURCES (As of April 30, 2018) Capacity Available (MW) Generating Facilities: Upper American River Project Hydroelectric Solano 1, 2 & 3 Wind Projects Wind (2) Sub-total: Local Gas-Fired Plants: SFA (Cosumnes) CVFA (Carson-Ice) SCA (Procter & Gamble) 182 SPA (McClellan) SPA (Campbell Soup) Sub-total:... 1,012 Purchased Power: Western Area Power Administration (WAPA) (3) (4) Feed-in-Tarrif Photovoltaic Solar Recurrent Solar Rock Tenn (Simpson) Biomass Iberdrola (PPM) Wind Patua (Gradient/Vulcan) Geothermal CalGeo Geothermal... 9 Other Long-Term Contracts Firm Contract Reserves Committed Short-Term Purchases (5) Sub-total:... 1,483 Total... 3,253 Available capacity is the net capacity available to serve SMUD s system during the peak month of July. (2) Wind supply resources are intermittent and are shown at the average historical capacity over the past 3 years between 12:00 p.m. and 6:00 p.m. (3) Total includes SMUD s Base Resource share and WAPA Customer allocations. (4) Assumes firm reserves of 5% are included. (5) Committed Short-Term Purchases are primarily purchased on a year-ahead to season-ahead basis from various sources. Note: Totals may not add due to rounding.
2 AVERAGE CLASS RATES SMUD Rates (cents/kwh) PG&E Rates (cents/kwh) (2) Percent Below PG&E (3) Residential - Standard % Residential Low Income % All Residential % Small Commercial (Less than 20 kw) % Small Commercial (21 to 299 kw) % Medium Commercial (300 to 499 kw) % Medium Commercial (500 to 999 kw) % Large Commercial (Greater than 1,000 kw) % Lighting Traffic Signals % Lighting Street Lighting % Agriculture % System Average % Projected 2018 average prices for SMUD with rates effective January 1, (2) PG&E average prices in 2018 reflect rates effective March 1, 2018, per Advice Letter 5231-E dated February 16, (3) The rates in the Average Class Rates table are calculated by dividing the total revenue of each class by the total usage of that class in kwhs. The actual savings per customer will vary based on their actual electricity consumption.
3 ALLOCATION OF DISTRICT REVENUE BY CUSTOMER CLASS The following chart sets forth the forecast percentage of SMUD revenues from billed sales associated with each customer class Revenue Forecast Agriculture 0.7% Lighting 0.6% Large Commercial Medium 14.7% Commercial 5.1% Residential 47.5% Small Commercial 31.4%
4 OPERATING DATA Selected operating data of SMUD for the four years ended December 31, 2014 through 2017, and for the three months ended March 31, 2018 and March 31, 2017 are presented in the following table. SMUD SELECTED OPERATING DATA CUSTOMERS, SALES, SOURCES OF ENERGY AND REVENUES Three Months Ended March 31, Year Ended December 31, Customers at End of Period: Residential , , , , , ,899 Commercial and industrial... 67,304 67,072 67,260 67,037 66,777 66,427 Other... 7,491 7,519 7,491 7,533 7,560 7,569 Total , , , , , ,895 MWh Sales: Residential... 1,084,924 1,144,289 4,957,240 4,670,307 4,654,571 4,639,175 Commercial and industrial... 1,273,633 1,257,701 5,761,158 5,688,615 5,747,669 5,775,248 Other... 14,839 15,463 57,952 62,216 71,559 83,537 Total... 2,373,396 2,417,453 10,776,350 10,421,135 10,473,799 10,497,960 Surplus power/out of area sales , ,877 1,788,719 1,826,687 1,677,566 1,906,263 Total... 2,620,648 2,850,330 12,565,069 12,247,822 12,151,365 12,404,223 Sources of Energy Sold MWh: Generated by SMUD... 1,719,796 2,030,513 7,274,860 7,934,086 6,857,498 6,896,535 Purchased or exchanged , ,121 5,757,332 4,795,517 5,746,573 5,963,656 Total... 2,711,730 2,953,634 13,032,192 12,732,603 12,604,071 12,860,191 Less System losses and SMUD usage... 91, , , , , ,968 Total... 2,620,648 2,850,330 12,565,069 12,247,822 12,151,365 12,404,223 Gross System peak demand (kw)... 1,555,000 1,607,000 3,157,000 2,972,000 2,956,000 3,003,000 Average kwh sales per residential customer (2)... 1,953 2,071 8,969 8,495 8,522 8,545 Average Revenue per kwh Sold: Residential (2) (cents) Commercial & industrial (2) (cents) Peak system MW values are measured at the four SMUD interconnection points and exclude SMUD s generation losses. Historical values include the impacts of dispatchable, non-dispatchable, and energy efficiency program capacity savings. (2) The average kwh sales per residential customer and the average revenue per kwh sold are calculated based upon billed and unbilled sales. Source: SMUD
5 SMUD UNCONSOLIDATED FINANCIAL DATA (thousands of dollars) Three Months Ended March 31, Year Ended December 31, Summary of Income Operating Revenues (2)... $ 335,271 $ 336,758 $ 1,554,366 $1,490,522 $1,474,691 $1,523,798 Operating Expenses... (311,455) (285,252) (1,363,094) (1,282,597) (1,309,001) (1,362,758) Operating Income (Loss)... 23,816 51, , , , ,040 Interest and Other Income (Expense)... (12,080) 6,320 58,217 43, ,679 85,478 Interest Expense... (19,145) (19,651) (78,554) (82,465) (84,565) (88,717) Change in Net Position... $ (7,409) $ 38,175 $170,935 $168,480 $ 184,804 $ 157,801 Selected Statement of Net Position Information Net Plant in Service... $2,932,694 $2,951,673 $2,942,005 $2,976,674 $2,974,179 $2,995,607 Construction Work in Progress , , , , , ,794 Electric Utility Plant Net... $3,238,172 $3,178,147 $3,220,726 $3,182,460 $3,147,817 $3,104,401 Unrestricted Cash... $ 592,159 $ 629,641 $ 608,311 $ 622,657 $ 534,392 $ 621,562 Rate Stabilization Fund... $ 99,899 $ 35,154 $ 99,899 $ 35,154 $ 30,251 $ 45,306 Total Assets... $5,325,311 $5,172,147 $5,335,913 $5,183,326 $5,095,984 $5,095,463 Net Position... $1,502,957 $1,377,606 $1,510,366 $1,339,431 $1,170,952 $ 990,929 Long-Term Debt (3)... $1,997,016 $2,123,013 $2,001,767 $2,126,395 $2,224,376 $2,236,404 Debt Service Coverage Ratios Parity Debt Service Coverage Ratio... N/A N/A 2.75x 2.59x 2.57x 2.25x Parity and Subordinate Debt Service Coverage Ratio... N/A N/A 2.65x 2.53x 2.52x 2.24x The consolidated financial statements of SMUD comprise financial information of SMUD along with the consolidated component units, CVFA, SPA, SCA, SFA and NCGA. This table includes only unconsolidated financial information of SMUD. Net operating revenues and expenses and Electric Utility Plant and Capitalization of CVFA, SPA, SCA, SFA and NCGA are not included in this table, although amounts paid to or received from the Authorities by SMUD are included. (2) Operating Revenues reflect net transfers to (from) the Rate Stabilization Fund for each full year as follows: 2017 $64.7 million 2016 $4.9 million 2015 ($15.1 million) 2014 ($36.2 million) (3) Long-Term Debt includes Long-Term Debt due within one year and unamortized premiums.
6 DEBT SERVICE COVERAGE RATIOS Year Ended December 31, Parity Debt Service Coverage Ratio x 2.59x 2.57x 2.25x 2.41x Fixed Charge Ratio x 2.49x 2.48x 2.17x 2.31x Note: Previously shown figures have been updated to match current Accounting methodology. METHOD OF COMPUTATION OF DEBT SERVICE RATIOS For the Year Ended 12/31/2017 ($000) Debt Service Coverage Ratio (Parity Bond Basis) Fixed Charge Basis Operating Revenues $ 1,554,366 $ 1,554,366 Interest and Other Income 43,986 43,986 Adjustments: Build America Bonds rebate 9,135 Net receipts on Series K swap 6,727 CIAC (Cash Proceeds Only) 13,125 13,125 Extraordinary Income (Natural Gas and Power Settlement Proceeds) - - AFUDC-equity and borrowed funds 3,234 Grant Revenue Revenue From Ineffective Gas Swaps 699 SB-1 Revenue Recognition 10,124 10,124 AB-32 Revenue Recognition - - 1,642,271 1,622,476 Operating Expenses: Operations & Maintenance (less Rosa accretion and PP&L amortization) 1,187,411 1,192,606 GASB 68 (47,814) (47,814) NET REVENUES 502, ,684 Parity Bonds: Principal 95,155 95,155 Interest 87,475 71,613 Subordinated Bonds Principal and Interest 0 8,810 Commercial Paper Interest 0 4,715 Parity Revenue Bond Debt Service 182, ,293 Debt Service Coverage/Fixed Charge Ratio Notes: 1.) Includes transfer to the rate stabilization fund of: $64,744,000.
7 RANCHO SECO DECOMMISSIONING (As of 12/31/2017) $ Millions Total Decommissioning Cost Estimate (Excluding Site Restoration) Total Decommissioning Costs Incurred as of 12/31/ Amount Needed for Remaining Decommissioning Costs 5.2 Balance in Decommissioning Fund 8.4 Contribution to the Decommissioning Trust Fund in Estimate for Site Restoration Costs 13.1 Expected site restoration costs are not required to be funded per NRC requirements
8 ESTIMATED CAPITAL REQUIREMENTS (Dollars in Thousands) Service Area and Other System Improvements Including Distribution System Improvements to Existing Generation Plant General Plant Special Projects Total Capital Requirements 2018 $201,552 $63,491 $99,000 $102,633 $466, ,439 82,978 96,824 33, , ,562 54,845 88,604 83, , ,016 77,339 80, , , ,766 77,339 97, , ,667
Immediately following the SMUD Board meeting scheduled at 6:00 p.m.
Sacramento Cogeneration Authority Special Meeting (Procter & Gamble Cogeneration Project) Date: December 21, 2017 Time: Immediately following the SMUD Board meeting scheduled at 6:00 p.m. Location: SMUD
More informationVCE Board Meeting. May 10, 2018 Woodland City Council Chambers
VCE Board Meeting May 10, 2018 Woodland City Council Chambers Item 14 - Summary of Credit Agreement Revolving Line of Credit (RLOC) Up to $11 M RLOC Monthly Interest payments @ One-Month LIBOR + 1.75%
More informationCommunity Solar Rate Rider: Schedule No February 13, 2018
Community Solar Rate Rider: Schedule No. 500 February 13, 2018 1 Community Solar Agenda Design Principles Program Highlights Pricing Methodology Example Customer Impact Conclusion Next Steps 2 Design Principles
More informationReview of LADWP Feed-In-Tariff Proposal for City Council
Review of LADWP Feed-In-Tariff Proposal for City Council Frederick H. Pickel, Ph.D Office of Public Accountability / Ratepayer Advocate, City of Los Angeles opa@lacity.org tel. 213-482-6814 Jan 22, 2013
More information* SMUDm. Sacramento. Cogeneration Authority. Special Meeting. (Procter & Gamble Cogeneration Project)
Sacramento Cogeneration Authority Special Meeting (Procter & Gamble Cogeneration Project) Date: December 20, 2018 Time.- Immediately following the SMUD Board meeting scheduled at 6:00 p.m. Location: SMUD
More informationPortland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance
February 16, 2018 Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance Full-year 2017 financial results on target excluding the effects of the Tax Cuts and Jobs
More informationCondensed Consolidated Statements of Income (millions, except per share amounts) (unaudited)
Condensed Consolidated Statements of Income (millions, except per share amounts) Three Months Ended September 30, 2007 Group, Operating Revenues $ 3,445 $ 1,090 $ 40 $ 4,575 Operating Expenses Fuel, purchased
More informationInterim Financial Statements - Unaudited. For the Period Ended June 30, 2016
Interim Financial Statements - Unaudited For the Period Ended June 30, 2016 Financial Statements - Unaudited For the Period Ended June 30, 2016 Contents Overview and Basis of Accounting 2 Management s
More informationSchedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES
I. APPLICABILITY & AVAILABILITY This Schedule is applicable to any Cogenerator or Small Power Producer (Qualifying Facility), as defined in the Public Utility Regulatory Policies Act of 1978 (PURPA), which
More informationOREGON STANDARD AVOIDED COST RATES AVOIDED COST PURCHASES FROM ELIGIBLE QUALIFYING FACILITIES Page 1
S ELIGIBLE QUALIFYING FACILITIES Page 1 Available To owners of Qualifying Facilities making sales of electricity to the Company in the State of Oregon. Applicable For power purchased from Base Load and
More informationVoluntary Renewable Energy Markets 101
Voluntary Renewable Energy Markets 101 Jenny Heeter, NREL Renewable Energy Markets Conference 2013 Austin, Texas September 23, 2013 NREL is a national laboratory of the U.S. Department of Energy, Office
More informationMICRO-GENERATION REGULATION
Province of Alberta ELECTRIC UTILITIES ACT MICRO-GENERATION REGULATION Alberta Regulation 27/2008 With amendments up to and including Alberta Regulation 140/2017 Office Consolidation Published by Alberta
More informationMICRO-GENERATION REGULATION
Province of Alberta ELECTRIC UTILITIES ACT MICRO-GENERATION REGULATION Alberta Regulation 27/2008 With amendments up to and including Alberta Regulation 218/2016 Office Consolidation Published by Alberta
More informationSCHEDULE NEM-V-ST Sheet 1
Original Cal. P.U.C. Sheet o. 27703-E San Diego, California Canceling Cal. P.U.C. Sheet o. SCHEDULE EM-V-ST Sheet 1 VIRTUAL ET EERGY METERIG FOR MULTI-TEAT AD MULTI-METER PROPERTIES APPLICABILITY Optionally
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 58755-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 55676-E APPLICABILITY Schedule NEM-V Sheet 1 Applicable to Qualified Customers
More informationPortland General Electric Company Eighth Revision of Sheet No P.U.C. Oregon No. E-18 Canceling Seventh Revision of Sheet No.
Portland General Electric Company Eighth Revision of Sheet No. 215-1 P.U.C. Oregon No. E-18 Canceling Seventh Revision of Sheet No. 215-1 PURPOSE SCHEDULE 215 SOLAR PAYMENT OPTION PILOT SMALL SYSTEMS (10
More informationSchedule NEM-V Sheet 1 VIRTUAL NET ENERGY METERING FOR MULTI-TENANT AND MULTI-METER PROPERTIES
Southern California Edison Revised Cal. PUC Sheet No. 55676-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 54511-E* APPLICABILITY Schedule NEM-V Sheet 1 Applicable to Qualified
More informationSCHEDULE 85 COGENERATION AND SMALL POWER PRODUCTION STANDARD CONTRACT RATES
IDAHO POWER COMPANY FOURTH REVISED SHEET NO. 85-1 THIRD REVISED SHEET NO. 85-1 AVAILABILITY Service under this schedule is available for power delivered to the Company's control area within the State of
More informationPortland General Electric Company First Revision of Sheet No P.U.C. Oregon No. E-18 Canceling Original Sheet No
Portland General Electric Company First Revision of Sheet No. 216-1 P.U.C. Oregon No. E-18 Canceling Original Sheet No. 216-1 PURPOSE SCHEDULE 216 SOLAR PAYMENT OPTION PILOT MEDIUM SYSTEMS (GREATER THAN
More informationSCHEDULE LGS-RR LARGE GENERAL SERVICE RENEWABLE RIDER
Page 1 of 8 1. AVAILABILITY: 1.1 This Schedule LGS-RR ( Schedule LGS-RR ) is available only in conjunction with GRDA s Schedule LGS Large General Service ( Schedule LGS ) to customers connected to GRDA
More informationb. Benefitting Account(s), each of which:
Original 31546-E ELECTRC SCHEDULE NEMV Sheet 1 VRTUAL NET METERNG FOR A MULT-TENANT OR MULT-METER PROPERTY SERVED AT THE SAME SERVCE DELVERY PONT APPLCABLTY: This virtual net energy-metering schedule is
More informationOregon Public Utility Commission
Oregon Public Utility Commission 2012 Oregon Utility Statistics Susan Ackerman, Chair Steven Bloom, Commissioner John Savage, Commissioner Jason Eisdorfer, Director Utility Program Oregon Public Utility
More informationSCHEDULE 19 LARGE POWER SERVICE
Idaho Power Company First Revised Sheet No. 19-1 I.P.U.C. No. 29, Tariff No. 101 Original Sheet No. 19-1 PUBLIC UTILITIES COMMISSION Jan. 19, 2011 Jan. 1, 2011 Per O.N. 32132 AVAILABILITY Service under
More informationInterconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW
Interconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW A. APPLICANT INFORMATION *Person/Company Name: *OUC Account No.: *Mailing Address: *City, State & Zip: Street Address
More informationVALLEY CLEAN ENERGY ALLIANCE. Staff Report Agenda Item 11
VALLEY CLEAN ENERGY ALLIANCE Staff Report Agenda Item 11 TO: FROM: SUBJECT: Valley Clean Energy Alliance Board of Directors Mitch Sears, Interim General Manager Gary Lawson, Sacramento Municipal Utility
More informationCombining Financial Statements
Combining Financial Statements Years Ended September 30, 2003 and 2002 Community Power. Statewide Strength. This page intentionally left blank. Combining Financial Statements Years Ended September 30,
More informationPortland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION
Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and
More informationAdvice 4045-E Issued by Date Filed May 18, 2012 Decision ,
Revised Cal. P.U.C. Sheet No. 31625-E Cancelling Revised Cal. P.U.C. Sheet No. 30514-E ELECTRC SCHEDULE NEMVMASH Sheet 1 VRTUAL NET ENERGY METERNG FOR MULTFAMLY AFFORDABLE HOUSNG (MASH/NSHP) WTH SOLAR
More informationDraft Financial Statements - Unaudited. For the Year Ended September 30, 2016 DRAFT
Draft Financial Statements - Unaudited For the Year Ended September 30, 2016 Financial Statements - Unaudited For the Year Ended September 30, 2016 Contents Overview and Basis of Accounting 2 Management
More informationRate W: Applies to customers who were on Rate W as of May 1, A-6: Applies to customers who were on A-6 as of May 1, 2006.
Revised Cal. P.U.C. Sheet No. 36652-E Cancelling Revised Cal. P.U.C. Sheet No. 35782-E ELECTRC SCHEDULE A-6 Sheet 1 SMALL GENERAL TME-OF-USE SERVCE APPLCABLTY: This time-of-use schedule applies to single-phase
More informationISO Tariff Original Sheet No. 637 ISO TARIFF APPENDIX L. Rate Schedules
Original Sheet No. 637 ISO TARIFF APPENDIX L Rate Schedules Original Sheet No. 638 Schedule 1 Grid Management Charge The Grid Management Charge (ISO Tariff Section 8.0) is a formula rate designed to recover
More informationTNUoS Tariffs in 10 minutes March 2018
TNUoS s in 10 minutes March 2018 An overview of TNUoS tariffs This information paper provides an overview of National Grid s Transmission Network Use of System (TNUoS) tariffs, applicable to transmission
More information2018 Corporate Operating Plan
2018 Corporate Operating Plan 2018 CORPORATE OPERATING PLAN TABLE OF CONTENTS Page Management Letter... 1 Corporate Strategic Planning... 2 Executive Summary... 7 Assumptions... 9 2018 Corporate Operating
More informationNo. 47. An act relating to the Vermont Energy Act of (H.56) It is hereby enacted by the General Assembly of the State of Vermont:
No. 47. An act relating to the Vermont Energy Act of 2011. (H.56) It is hereby enacted by the General Assembly of the State of Vermont: * * * Net Metering * * * Sec. 1. 30 V.S.A. 219a is amended to read:
More informationFinal Application for New License for Major Water Power Project Existing Dam
Final Application for New License for Major Water Power Project Existing Dam Northfield Mountain Pumped Storage Project (FERC Project Number 2485) Turners Falls Hydroelectric Project (FERC Project Number
More informationMICRO-GENERATION REGULATION
Province of Alberta ELECTRIC UTILITIES ACT MICRO-GENERATION REGULATION Alberta Regulation 27/2008 With amendments up to and including Alberta Regulation 203/2015 Office Consolidation Published by Alberta
More informationFINANCIAL STATEMENTS CONNECTICUT NATURAL GAS CORPORATION (UNAUDITED)
FINANCIAL STATEMENTS OF CONNECTICUT NATURAL GAS CORPORATION AS OF MARCH 31, 2018 AND DECEMBER 31, 2017 AND FOR THE THREE MONTHS ENDED MARCH 31, 2018 AND 2017 (UNAUDITED) TABLE OF CONTENTS Financial Statements:
More informationGeorgia Power Company s Qualifying Facilities (QF) Fundamentals
Georgia Power Company s Qualifying Facilities (QF) Fundamentals Public Utilities Regulatory Policies Act ( PURPA ) Legislative Purpose: To combat the energy crisis of the 1970s To promote energy conservation
More informationMemorandum. Jennifer Cregar, Co-Division Chief, Sustainability, County of Santa Barbara
Memorandum To: Jennifer Cregar, Co-Division Chief, Sustainability, County of Santa Barbara From: Pacific Energy Advisors, Inc. Subject: Community Choice Aggregation Technical Study Date: May 25, 2018 Executive
More information2018 PROPOSED BUDGET
DRAFT BOARD FINANCE COMMITTEE REVIEW 2018 PROPOSED BUDGET SACRAMENTO MUNICIPAL UTILITY DISTRICT FINANCING AUTHORITY November, 2017 ~~ ~FA ~ CllAMENTO MUNICIPAL UTI~l!Y DISTRICT FINAN ONG AUTHORITY.,, {~
More informationCurrent State of the Voluntary Renewable Energy Market
Current State of the Voluntary Renewable Energy Market Jenny Heeter, NREL Renewable Energy Markets Conference 2013 Austin, Texas September 24, 2013 NREL is a national laboratory of the U.S. Department
More informationSchedule NEM-V-ST Sheet 1 VIRTUAL NET METERING FOR MULTI-TENANT AND MULTI-METER PROPERTIES SUCCESSOR TARIFF
Southern California Edison Revised Cal. PUC Sheet No. 60503-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58758-E Schedule NEM-V-ST Sheet 1 APPLICABILITY This Schedule is applicable
More informationSERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE
Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA The
More informationELECTRIC SCHEDULE NEM2VMSH Sheet 1 VIRTUAL NET ENERGY METERING FOR MULTIFAMILY AFFORDABLE HOUSING (MASH/NSHP) WITH SOLAR GENERATOR(S)
Original 37847-E ELECTRC SCHEDULE NEM2VMSH Sheet 1 VRTUAL NET ENERGY METERNG FOR MULTFAMLY AFFORDABLE HOUSNG (MASH/NSHP) WTH SOLAR GENERATOR(S) APPLCABLTY: This virtual net energy-metering schedule is
More informationELECTRIC UTILITY RATES
ELECTRIC UTILITY RATES Schedule 7 Schedule 20 Schedule 23 Schedule 24 Schedule 25 Schedule 36 Schedule 37 Schedule 38 Schedule 50 Schedule 80 Schedule 81 Schedule 82 Schedule 90 Schedule 200 Schedule 210
More information2017 COST OF SERVICE, RATE TRAJECTORIES AND BILLING DETERMINANTS. March 6, 2017
2017 COST OF SERVICE, RATE TRAJECTORIES AND BILLING DETERMINANTS March 6, 2017 AGENDA Cost of Service (COS), Trajectories, and Billing Determinants Overview Rate Trajectories & Cost of Service (COS) Results
More informationSan Francisco Public Utilites Commission. Retail Electric Rate Study
San Francisco Public Utilites Commission Retail Electric Rate Study December 30, 2010 TABLE OF CONTENTS EXECUTIVE SUMMARY... 2 OVERVIEW OF UTILITY RATE SETTING PRINCIPLES... 4 DEVELOPMENT OF THE REVENUE
More informationStandard Interconnection Agreement for Customer-Owned Renewable Generation System
Standard Interconnection Agreement for Customer-Owned Renewable Generation System This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at in,
More informationYukon Energy Corporation
Financial Statements December 31, 2016 Management s Responsibility for Financial Reporting Independent Auditor s Report Statement of Financial Position Statement of Operations and Other Comprehensive Income
More informationTariff and Business Rules. For Electric Service Provided by. Pedernales Electric Cooperative, Inc.
Tariff and Business Rules For Electric Service Provided by Pedernales Electric Cooperative, Inc. 201 South Avenue F P.O. Box 1 Johnson City, Texas 78636-0001 Adopted 6-15-09; Amended 8-16-10; 9-20-10;
More informationLAS Electricity Procurement Program Overview
LAS Electricity Procurement Program Overview Township of Huron-Kinloss Council Presentation Graham Proudley LAS Client Relations Specialist September 3, 2014 WHAT IS LAS? Affiliated with AMO Focus toward
More informationGREEN POWER PROVIDERS PROGRAM PARTICIPATION GUIDELINES (Effective April 1, 2018)
GREEN POWER PROVIDERS PROGRAM PARTICIPATION (Effective April 1, 2018) GUIDELINE 1 - PROGRAM PURPOSE AND DESCRIPTION The purpose of the Green Power Providers program ( Program ) is to continue to increase
More informationSchedule NEM-ST Sheet 1 NET ENERGY METERING SUCCESSOR TARIFF
Southern California Edison Revised Cal. PUC Sheet No. 60463-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58728-E Schedule NEM-ST Sheet 1 APPLICABILITY This Schedule is applicable
More informationGREEK RENEWABLES SUPPORT SCHEME PROPOSALS
BRIEFING GREEK RENEWABLES SUPPORT SCHEME PROPOSALS MARCH 2016 BRIEF OUTLINE OF THE SCHEME PHOTOVOLTAIC PROJECTS TRANSITIONAL PROVISIONS NON-INTERCONNECTED ISLANDS COMPETITIVE BIDDING PROCESS FROM 2017
More informationSTANDARD INTERCONNECTION AGREEMENT FOR TIER 1 RENEWABLE GENERATOR SYSTEMS
STANDARD INTERCONNECTION AGREEMENT FOR TIER 1 RENEWABLE GENERATOR SYSTEMS This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at in, Florida
More informationEugene Water & Electric Board. Annual Report for the year ended December 31, 2003
Eugene Water & Electric Board Annual Report for the year ended December 31, 2003 Eugene Water & Electric Board December 31, 2003 Board of Commissioners 500 East Fourth Avenue Eugene, Oregon 97401 Mr. Patrick
More informationSchedule NEM-ST Sheet 1 NET ENERGY METERING SUCCESSOR TARIFF
Southern California Edison Revised Cal. PUC Sheet No. 60463-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58728-E Schedule NEM-ST Sheet 1 APPLICABILITY This Schedule is applicable
More informationReport of Independent Auditors
Report of Independent Auditors To the Board of Commissioners Public Utility District No. 1 of Clark County Vancouver, Washington Report on the Financial Statements We have audited the accompanying individual
More information04/16/2014- AMENDED AND REPORTED OUT TO THE FLOOR 04/04/14-AMENDED AND REPORTED OUT TO THE COMMITTEE ON RULES AND JUDICIARY 09/13/13-NO ACTION TAKEN
COMMITTEE ON ENERGY AND ENVIRONMENTAL PROTECTION 0//0- AMENDED AND REPORTED OUT TO THE FLOOR 0/0/-AMENDED AND REPORTED OUT TO THE COMMITTEE ON RULES AND JUDICIARY 0//-NO ACTION TAKEN BILL NO. 0-000 Thirtieth
More informationRevenue Requirement Application 2004/05 and 2005/06. Volume 1. Chapter 2. Consolidated Revenue Requirements and Financial Schedules
Revenue Requirement Application 00/0 and 00/0 Volume 1 Chapter. Consolidated Revenue Requirements and Financial Schedules Table of Contents LIST OF FIGURES... -IV LIST OF TABLES... -IV LIST OF SCHEDULES...-V
More informationCCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer
CCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer Presentation Overview Growth of CCA Core Policy Issues Exit Fees and Non-Bypassable Charges Future of California s Energy Policies
More informationVillage of Lyndonville Electric Department (A Component Unit of the Village of Lyndonville, Vermont) FINANCIAL STATEMENTS.
FINANCIAL STATEMENTS TABLE OF CONTENTS Page INDEPENDENT AUDITOR S REPORT MANAGEMENT S DISCUSSION AND ANALYSIS FINANCIAL STATEMENTS Statements of Net Position 1 Statements of Revenues, Expenses and Changes
More informationUNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 10-Q
UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 10-Q [X] QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the quarterly period ended
More informationStandard Interconnection Agreement for Customer-Owned Renewable Generation System kw
Standard Interconnection Agreement for Customer-Owned Renewable Generation System kw This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at
More informationCH ENERGY GROUP, INC. & CENTRAL HUDSON GAS & ELECTRIC CORP. QUARTERLY FINANCIAL REPORT. for the period ended
CH ENERGY GROUP, INC. & CENTRAL HUDSON GAS & ELECTRIC CORP. QUARTERLY FINANCIAL REPORT for the period ended SEPTEMBER 30, 2017 FINANCIAL STATEMENTS (UNAUDITED) QUARTER ENDED SEPTEMBER 30, 2017 TABLE OF
More informationEconomic Impacts of New Jersey s Proposed Renewable Portfolio Standard Report Schedules
Economic Impacts of New Jersey s Proposed Renewable Portfolio Standard Report Schedules David E. Dismukes, Ph.D. Acadian Consulting Group 6455 Overton Street Baton Rouge, Louisiana 70808 December 16, 2005
More informationLarge Commercial Rate Simplification
Large Commercial Rate Simplification Presented to: Key Account Luncheon Red Lion Hotel Presented by: Mark Haddad Assistant Director/CFO October 19, 2017 Most Important Information First There is no rate
More information26 th Revision of Sheet No. 91 Canceling 25 th Revision WN U-60 of Sheet No. 91
26 th Revision of Sheet No. 91 Canceling 25 th Revision WN U-60 of Sheet No. 91 COGENERATON AND SMALL POWER PRODUCTON (T) AVALABLTY: 1. This schedule applies to any person or entity, hereinafter referred
More informationFPUA REVENUE SUFFICIENCY ANALYSIS Rate Study Update
FPUA REVENUE SUFFICIENCY ANALYSIS Rate Study Update Purpose: Summary of Observations: Special Considerations: Update Financial Forecast through Fiscal Year 2020 Estimate Sufficiency of the Utility Systems
More informationNON OFFICIAL VERSION ONLY ORIGINAL SPANISH VERSION SHOULD BE CONSIDERED LEGALLY VALID FOR INTERPRETATION
NON OFFICIAL VERSION ONLY ORIGINAL SPANISH VERSION SHOULD BE CONSIDERED LEGALLY VALID FOR INTERPRETATION ELECTRIC POWER Act 26 190 Legal Regulations on National Promotion for the Use of Sources of Renewable
More informationBALANCE SHEETS (thousands) Assets
BALANCE SHEETS Assets 2011 2010 (thousands) as of December 31, 2011 and 2010 Utility Plant - at cost Electric plant..................................... $ 4,943,363 $ 4,792,217 Less accumulated depreciation
More informationRevised Cal. P.U.C. Sheet No E Cancelling Revised Cal. P.U.C. Sheet No E. ELECTRIC SCHEDULE A-1 Sheet 1 SMALL GENERAL SERVICE
Revised Cal. P.U.C. Sheet No. 40709-E Cancelling Revised Cal. P.U.C. Sheet No. 35409-E ELECTRC SCHEDULE A-1 Sheet 1 SMALL GENERAL SERVCE APPLCABLTY: Schedule A-1 applies to single-phase and polyphase alternating-current
More informationFROZEN PUMP CURTAILMENT RIDER
Index No: 90 Replacing Sheet: 1 Sheet 1 of 5 Sheets PURPOSE The Pump Curtailment Rider (PCR) is an optional schedule that allows irrigation Customers to participate in a dispatchable load curtailment program.
More informationAppendix. Investor Conference April 4, 2007 New York, NY
Appendix Investor Conference April 4, 2007 New York, NY 1 Cautionary Statement Regarding Forward- Looking Information This presentation contains forward-looking statements regarding management s guidance
More informationHalifax Electric Membership Corporation
Rev. 1/1/18 Halifax Electric Membership Corporation Electric Rate Schedules NORTH CAROLINA 33, MARTIN ENFIELD, NORTH CAROLINA Electric Rate Schedules Table of Contents Schedule Description Page Effective
More information2017 Renewable Energy Plan Public Service Company of Colorado February Volume 1. Hearing Exhibit 101 Attachment RLK-1 Page 1 of 81
Hearing Exhibit 101 Page 1 of 81 2017 Renewable Energy Plan Public Service Company of Colorado February 2016 Volume 1 xcelenergy.com 2016 Xcel Energy Inc. Xcel Energy is a registered trademark of Xcel
More informationManagement s responsibility for financial reporting
Management s responsibility for financial reporting The accompanying consolidated financial statements of Energy Savings Income Fund and all the information in this annual report are the responsibility
More informationMC COOK PUBLIC POWER DISTRICT McCook, Nebraska. Board Policy No. 488
MC COOK PUBLIC POWER DISTRICT McCook, Nebraska Board Policy No. 488 SUBJECT Renewable Generator Net Metering OBJECTIVE To set forth a policy for the interconnection and net metering of renewable energy
More informationOVERTON POWER DISTRICT No North Moapa Valley Boulevard P O Box 395 Overton, Nevada
OVERTON POWER DISTRICT No. 5 615 North Moapa Valley Boulevard P O Box 395 Overton, Nevada 89040-0395 Date Approved: May 16, 2012 Regulation No. OPD-S-9.100 Approved By : A. PURPOSE: OVERTON POWER DISTRICT
More informationELECTRIC SCHEDULE E-SDL Sheet 1 SPLIT-WHEELING DEPARTING LOAD
Revised Cal. P.U.C. Sheet No. 28588-E Cancelling Revised Cal. P.U.C. Sheet No. 27455-E ELECTRIC SCHEDULE E-SDL Sheet 1 APPLICABILITY: TERRITORY: RATES: This schedule is applicable to customers that have
More informationSTANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM
STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM This Agreement is made and entered into this day of, 20, by and between, (hereinafter RGS Owner ), located at in, Florida, and Utility
More informationPlanned Actual Planned Adjusted
Section I: Program Overview A. Program Summary Program Description The Commercial Prescriptive Lighting Program is a contractor-driven program that provides financial incentives to commercial and industrial
More informationEnergex. Statement of expected price trends. 1 July 2016 to 30 June /15 Statement of expected price trends
Energex Statement of expected price trends 1 July 2016 to 30 June 2017-1- 2014/15 Statement of expected price trends Version control Version Date Description 1.0 3 June 2016 Published on Energex s website
More informationBoard Finance & Audit. Committee Meeting and Special SMUD Board of Directors Meeting
Board Finance & Audit Committee Meeting and Special SMUD Board of Directors Meeting Date: Tuesday, September 4, 2018 Time: 5:30 p. m. Location". SMUD Customer Service Center, Rubicon Room 6301 S Street,
More informationRenewable Energy Finance and Investment Panel: Iowa
Renewable Energy Finance and Investment Panel: Iowa Alternate Energy Revolving Loan Program (AERLP) William Haman, P.E. Minnesota Renewable Energy Roundtable Maple Grove, MN October 27, 2016 Who is the
More informationFor the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc.
DSM Economics For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc. DSM Economics - Overview Why? Basics of Economics Benefits Costs Economic Test Overviews Economics of Sample
More informationOPTIONAL LARGE GENERAL SERVICE - HIGH OFF-PEAK USE
6100 Neil Road, Reno, Nevada 68th Revised PUCN Sheet No. 79 Tariff No. Electric No. 1 Cancelling 67th Revised PUCN Sheet No. 79 APPLICABLE This schedule is available as an option to Schedule No. GS-3 for
More informationReport of Management. Auditors Report
Report of Management The consolidated financial statements and all the information in the 2007 annual report are the responsibility of management. The financial statements have been prepared in accordance
More informationM E M O R A N D U M. The remainder of this memorandum sets forth Q&As regarding the Dominion Agreement.
Virginia Energy Purchasing Governmental Association M E M O R A N D U M P.O. Box 71420 Richmond, VA 23255 TO: FROM: VEPGA MEMBERS Steve Sinclair, Chair of VEPGA DATE: SEPTEMBER 8, 2014 RE: Implementation
More informationROCKLAND ELECTRIC COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016
STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PROVISION OF BASIC GENERATION SERVICE FOR THE PERIOD BEGINNING JUNE 1, 2016 Docket No. ER15040482 ROCKLAND ELECTRIC COMPANY PROPOSAL FOR
More informationRENEWABLE FINANCING CONSIDERATIONS. Bond Buyer 2011 CA Public Finance Renewable Panel
RENEWABLE FINANCING CONSIDERATIONS Panel Federal and State Proposals and Regulations Issue Background and Status Effects Clean Water Act (CWA) Section 316(b) requires that the location, design, construction
More informationINTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS
INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS This Interconnection Agreement for Customer-Owned Renewable Generation Systems ( Interconnection Agreement ) is made this day of
More informationManagement Comments. February 12, 2015
Management Comments February 12, 2015 Average Bill, Not Average Cost of Service Court Rich: according to this Exhibit 6, 62.4 percent of the people in E-23 are paying less than the average cost of service,
More informationFINANCIAL STATEMENTS AND INDEPENDENT AUDITORS REPORT GAINESVILLE REGIONAL UTILITIES GAINESVILLE, FLORIDA SEPTEMBER 30, 2018 AND 2017
FINANCIAL STATEMENTS AND INDEPENDENT AUDITORS REPORT GAINESVILLE REGIONAL UTILITIES GAINESVILLE, FLORIDA SEPTEMBER 30, 2018 AND 2017 FINANCIAL STATEMENTS AND INDEPENDENT AUDITORS REPORT GAINESVILLE REGIONAL
More informationVolatility, risk, and risk-premium in German and Continental power markets. Stefan Judisch Supply & Trading GmbH 3 rd April 2014
Volatility, risk, and risk-premium in German and Continental power markets Stefan Judisch Supply & Trading GmbH 3 rd April 2014 RWE Supply & Trading 01/04/2014 PAGE 0 Agenda 1. What are the market fundamentals
More informationPlatte River Power Authority
Independent Auditor s Report and Financial Statements Financial Statements Years Ended Contents Independent Auditor s Report...1 Management s Discussion and Analysis (Unaudited)...3 Financial Statements
More informationOld Dominion Power Company 220 West Main Street Louisville, Kentucky ELECTRIC SERVICE VIRGINIA STATE CORPORATION COMMISSION
S.C.C. No. 15 Canceling S.C.C. No. 14 Old Dominion Power Company 220 West Main Street Louisville, Kentucky Rates, Terms and Conditions for Furnishing ELECTRIC SERVICE In Dickenson, Lee, Russell, Scott,
More informationTier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System
CITY OF MOUNT DORA, FLORIDA FIRST REVISED SHEET NO. 15.0 CANCELS ORIGINAL SHEET NO. 15.0 Tier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System This Agreement is made and
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 64409-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58722-E Schedule NEM Sheet 1 APPLICABILITY Applicable to Eligible Customer-Generators
More informationVolatility, risk, and risk-premium in German and Continental power markets
Volatility, risk, and risk-premium in German and Continental power markets Stefan Judisch Supply & Trading GmbH RWE Supply & Trading PAGE 0 Agenda 1. What are the market fundamentals telling us? 2. What
More information