1 Does the Northeast Need Additional Gas Infrastructure and if There is a Need, Can the Infrastructure be Financed, Constructed and Built? Valerie Green, Pierce Atwood LLP (Moderator) Boris Brevnov, Liberty Energy Trust James Daly, Eversource Energy Brian Schwabenbauer, TRC Michael Jacobs, Union of Concerned Scientists October 4, 2018 Boston, MA

2 State of the Energy Infrastructure Time for the Boston Tea Party? Our ships, freight trains, industrial transportation equipment, and power generation run on oil, while the country exports clean, efficient natural gas to overseas countries. Like the Boston Tea Party of old, the US is acting as a colonial state, effectively subsidizing other countries displacement of oil with its natural gas. Time line Tea Act of Parliament 1773 Whale Oil becomes largest fuel oil source 18 th century US drilled oil, Pennsylvania 1859 US becomes net importer 1945 Commercial shale production begins 2005 US becomes a net energy exporter 2022? 1

3 State of the Infrastructure and Environmental Impact Winter cold spike, along with an unplanned outages at Pilgrim, caused a large spike in demand for heavy oil burning electric generation. Pollution spiked across all major categories. 657% Increase in NOX 140% Increase in CO2 2721% Increase in SO2 Source NE ISO, SIemens 2 2

4 Renewable Generation Impact: Gas Plant decrease in utilization Source: NE ISO 3 3

5 Bloomberg New Energy Finance: Gas Plant installed capacity remains stable over time 4

6 Zero emission storage is a goal, but economics and resiliency requirements continue to favor gas as a storage medium 5

7 In addition to equity, Liberty has a wide variety of financing options and partners to provide capital for projects Private Activity Bonds (PABs) Payment in Lieu of Taxes (PILOT) 4(a)(2) Private Placement 144A / Reg S Bank Loan Investors: Mainly Life insurance companies in Primary buyers are retail investors, Primary buyers are retail investors, U.S. and some large European large bond funds, property and large bond funds, property and accounts Life Insurance companies (core Commercial bank lenders with project casualty insurance companies, and casualty insurance companies, and demand), Qualified Institutional Buyers crossover buyers that generally buy crossover buyers that generally buy Flexible marketing process, can precircle investors ahead of more formal finance lending programs ( QIBs ), and asset managers taxable bonds taxable bonds marketing Industrial applications, including Eligible Uses: seaports, intercity rail, transit, solid waste disposal, toll roads, airports, Related infrastructure water and wastewater treatment and Any Any Any low income housing Specific authorizations (special cases) Tax Status: Tax-Exempt (subject to the AMT) Tax-Exempt (not subject to the AMT) Taxable Taxable Taxable Maturity: Bridge Loans: month tenor As long as 40 years (with amortizing General preference for bullet maturity designed to backstop capital markets Longer maximum maturity Strong Longer maximum maturity Strong structures) up to 15-year Weighted (5 s, 10 s, 30 s) but will accommodate issuance market demand for 30 year and longer market demand for 30 year and longer Average Life ( WAL ) amortizers maturities maturities Term Loans or Mini-Perms : typically Greatest depth inside 30 years; some Certain private accounts would go to 3-7 years, deepest liquidity in the investors would go to years shorter tenors Pricing: Fixed rate Fixed rate Fixed rate Fixed rate Floating rate LIBOR (can swap to fixed) Delay Draws: Typically fully funded at close Typically fully funded at close Rate lock up to 9 months and spread lock up to 18 months No, fully funded at close Flexible to address delayed draw Disclosure Requirements: Advantages: Key Considerations: Formal disclosure required of all information pertinent to potential investors, including risk factors of the project Continuing disclosure requirements for ongoing communication to investors Lower interest rate cost Market acceptance of low and noninvestment grade project finance credits Longer maximum maturity Strong market demand for 30 year and longer maturities Tax-exempt bonds are typically callable at par beginning in ten years Market demands continuing disclosure of project status Restrictions on use of proceeds (e.g. reserve size limits) Restrictions on earnings rates for proceeds Formal disclosure required of all information pertinent to potential investors, including risk factors of the project Continuing disclosure requirements for ongoing communication to investors Lower interest rate cost Market acceptance of low and noninvestment grade project finance credits Longer maximum maturity Strong market demand for 30 year and longer maturities Tax-exempt bonds are typically callable at par beginning in ten years Tax analysis required to determine PILOT eligibility Market demands continuing disclosure of project status Restrictions on use of proceeds (e.g. reserve size limits) Restrictions on earnings rates for proceeds Bank Book style, periodic financial disclosures typically required Legal documents typically include a Note Purchase Agreement and Intercreditor Agreement, if applicable Marketing more limited to ~100 accounts on basis of information memorandum and data room Buy-and-hold investors less sensitive to market conditions/volatility. Limited disclosure streamlines documentation Allows for delayed drawdowns Investors do not charge premiums for reduced liquidity, structural complexity, or amortization Efficient marketing format for complex structures/ credits due to diligence period and access to consultants/counsel More limited investor base Asset managers and bond funds are traditionally not part of the investor universe due to the lack of secondary market liquidity More formal disclosure Not reviewed by the SEC, legal disclosure required (risk factors and 10(b)5 legal opinion); Documents to investor include Offering Memorandum, Indenture and Intercreditor Agreement, if applicable Marketing more broad to +5,000 accounts Access to broader investor base, where large 144A/Reg S accounts can drive significant demand and leverage over pricing and terms Ability to support amortizers and bullets Shorter execution period, particularly for more conventional projects (given limited diligence periods and access to consultants/counsel) Ideal for simpler, operational credits of large size Broader disclosure and 10(b)5 opinion required Pricing typically more sensitive to short-term market technicals/liquidity vs. 4(a)(2) or project bank market Premium required for amortized structures No delayed-draw feature; potential negative carry Bank Book style Not reviewed by the SEC, risk factors not required Fastest execution achievable for simpler, operational credits Low cost of unfunded commitment Pre-payable without call premium No ratings required Relatively short tenors Tighter maintenance covenants and more cumbersome documentation Heavily reliant upon relationships with banks 6 6

8 Massachusetts has the need and the opportunities to lead 7 7

9 Pierce Atwood Annual Energy Infrastructure Symposium James Daly Vice President Energy Supply October 4, 2018 Safety First and Always

10 New England s Vulnerability to High Gas and Electricity Prices 2013/14 Polar Vortex increased electricity costs by $3.2Bn 2017/18 winter cold snap increased electricity costs by $1.7Bn Spot prices drive forward market prices Retail electricity rates are about $1Bn/Year higher on average $100 $80 $60 $40 $20 New England vs Marcellus Gas Prices ($/MMBtu) $3.2B Incremental Costs $1.7B $2.5B $0 March-2013 March-2014 March-2015 March-2016 March-2017 March-2018 New England Natural Gas Price Marcellus Natural Gas Price Cold snap makes New England the world s priciest gas market Bloomberg yet nearby production areas remained one of the lowest cost gas markets Safety First and Always 2

11 Reliability at Risk Fuel-security risk is the foremost challenge to a reliable power grid in New England ISO-NE, Jan. 18, 2018 ISO-NE: Operational Fuel Security Analysis Despite aggressive renewable energy goals Region faces severe threats to reliability by of 23 of the scenarios evaluated resulted in emergency actions 19 of 23 of the scenarios evaluated resulted in rolling blackouts Mystic Power Plant Reliability Agreement Region s fuel security threats leads to Exelon announcing it will retire one of the largest power plants in New England absent a cost-of-service contract ISO-NE will charge electric customers hundreds of millions for this cost-ofservice contract Strategy is likely to be repeated with 1/3 of New England s generating capacity retiring No Long Term Solution In Sight 3 Safety First and Always

12 Environmental Impact of Cold Snap The incremental emissions from the lack of natural gas during the cold snap is an environmental disaster for meeting New England s GHG goals. +6MM - MA EEA Secretary, Matthew Beaton Jan. 24, MW 1 Million Tons of Additional Greenhouse Gas Emissions The incremental emissions from increased oil and coalfired power plants nearly exceeding annual emissions limits in 13 days Safety First and Always Equivalent to 6 Million Additional Vehicles The incremental emissions from the cold snap are equivalent to doubling the number of vehicles on our roads Negated the Benefits of 75% of the Solar Power in MA The additional greenhouse gas emissions during the cold snap offset the annual benefits of more than 1,500 MW solar power 4

13 Natural Gas Complementing Renewables Renewables will meet an increasing portion of our energy needs while natural gas responds to the fluctuations in renewable output and meets winter peak demand Natural Gas Backstops the Variable Output of Natural Gas Meets Winter Renewables Demand Until Storage Is Available At Scale Actual Output vs Plant Capacity (MWs) Winter Peak Demand (MWs) Plant Capacity Natural gas-fired power required Hourly Demand Peak power demand 6-7 PM Sunset at 4:31 PM Actual solar power generated DAYLIGHT HOURS Source: ISO-NE Safety First and Always AUGUST DAYLIGHT HOURS Source: National Renewable Energy Laboratory; randomly selected August day Solar power cannot resolve the region s winter peak demand 5

14 Paradox of Policies Clean Energy Resources Fluctuating wholesale prices are insufficient to support investment Investors require long-term, stable pricing commitments Cost are declining future prices will be lower cost than today s resources State policies support longterm fixed commitments Reliability Resources Fluctuating wholesale prices are insufficient to support investment Investors require long-term, stable pricing Costs are increasing future prices likely higher than today Policies don t support longterm commitments Safety First and Always 6

15 Risks to Gas Pipe Investment for Generators Mike Jacobs Union of Concerned Scientists October 4

16 Legal Framework 40 years of competition amongst generation State authority in policy Tension between state and federal authorities 2

17 Renewables in 2024 (ISO v States) State RPS laws require ~15% increase by State contracts for offshore wind currently 1430 MW. 3

18 4

19 Wind is greater in winter Windfarms are more productive in winter Annual capacity factor is 48 49%, but 50 60%+ winter The capacity credit of offshore wind in the NYISO and ISO NE markets is significantly higher in winter than in summer; Physics of heavier cold air; extreme cold described by ISO: winds were frequently stronger than average, which caused extended periods of wind chill temperatures. 5

20 Estimating the Value of Offshore Wind Along the U.S. Eastern Coast. LBNL

21 Second Annual Energy Infrastructure Symposium October 4, 2018 Boston, MA

WEEKLY MARKET UPDATE

WEEKLY MARKET UPDATE WEEKLY MARKET UPDATE Weekly Summary: The U.S. Energy Information Administration reported last week that natural gas storage decreased by 206 Bcf. The withdrawal for the same week last year was 76 Bcf while

More information

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...

More information

Annual Report on Bank of China s Green Bonds. Outstanding BOC Green Bonds

Annual Report on Bank of China s Green Bonds. Outstanding BOC Green Bonds Annual Report on Bank of China s Green Bonds Bank of China ( BOC ) Green Bonds enables BOC to support environment friendly projects and companies which are particularly active in terms of environment preservation,

More information

Q I N T E R I M R E P O R T. Brookfield Renewable Partners L.P.

Q I N T E R I M R E P O R T. Brookfield Renewable Partners L.P. Q2 2017 I N T E R I M R E P O R T Brookfield Renewable Partners L.P. OUR OPERATIONS We manage our facilities through operating platforms in North America, Colombia, Brazil, and Europe which are designed

More information

Bank of China Limited Green Bond Management Statement

Bank of China Limited Green Bond Management Statement Bank of China Limited Green Bond Management Statement Bank of China Limited, including all its branches globally ( BOC ) is responsible for the preparation and fair presentation of this Green Bond Management

More information

Trading Date. % Change from Last Week. 53 State Street 12 For further information contact: Jessie Hagger

Trading Date. % Change from Last Week. 53 State Street 12 For further information contact: Jessie Hagger $ / MMBtu WEEKLY MARKET UPDATE Weekly Summary: The U.S. Energy Information Administration reported last week that natural gas storage increased by 89 Bcf. The injection for the same week last year was

More information

Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance

Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance February 16, 2018 Portland General Electric Reports 2017 Financial Results and Initiates 2018 Earnings Guidance Full-year 2017 financial results on target excluding the effects of the Tax Cuts and Jobs

More information

ICForecast: Strategic Power Outlook. Q Sample

ICForecast: Strategic Power Outlook. Q Sample ICForecast: Strategic Power Outlook Q1 2015 - Sample 2015 ICF International, Inc. Any views or opinions expressed in this paper are solely those of the author(s) and do not necessarily represent those

More information

NEW YORK MEETINGS. January 28, 2015

NEW YORK MEETINGS. January 28, 2015 NEW YORK MEETINGS January 28, 2015 2 Safe Harbor This presentation includes statements concerning NU s expectations, beliefs, plans, objectives, goals, strategies, assumptions of future events, future

More information

Final Version October 19, ENERGY EFFICIENCY PLAN TERM SHEET

Final Version October 19, ENERGY EFFICIENCY PLAN TERM SHEET CORE PRINCIPLES ENERGY EFFICIENCY PLAN TERM SHEET Energy efficiency is a cornerstone of the Commonwealth s long term energy policy. The Plan ( Plan ) reflects this key role and builds upon the high level

More information

LGUGC Facts Brief History Vision & Mission

LGUGC Facts Brief History Vision & Mission LGUGC Facts Brief History Incorporated in March 1998 with 51% ownership by BAP member banks, and 49% DBP ownership Initially opened only to Local Government Units (LGUs) Essentially launched the Municipal

More information

EEI 2014 Financial Conference. November 11-14, 2014

EEI 2014 Financial Conference. November 11-14, 2014 EEI 2014 Financial Conference November 11-14, 2014 Safe Harbor This presentation includes statements concerning NU s expectations, beliefs, plans, objectives, goals, strategies, assumptions of future events,

More information

2017 Integrated Resource Plan. Portfolio Development Detail September 8, 2016

2017 Integrated Resource Plan. Portfolio Development Detail September 8, 2016 2017 Integrated Resource Plan Portfolio Development Detail September 8, 2016 1 2017 Portfolio Development Process Vol. III Analysis Core Portfolios (Targeted Resource Classes) Cost and Risk (Broader Range

More information

2017 Year-End Results Investor Call. February 23, 2018

2017 Year-End Results Investor Call. February 23, 2018 2017 Year-End Results Investor Call February 23, 2018 Safe Harbor Statement All per-share amounts in this presentation are reported on a diluted basis. The only common equity securities that are publicly

More information

Energy Ventures Analysis 1901 N. Moore St. Arlington, VA (703)

Energy Ventures Analysis 1901 N. Moore St. Arlington, VA (703) T H E I M P A C T O F E A R L Y C O A L R E T I R E M E N T S O N K E Y P O W E R M A R K E T S Prepared for: National Mining Association Washington, DC May 2014 Energy Ventures Analysis 1901 N. Moore

More information

DFW INTERNATIONAL AIRPORT ADMINISTRATIVE POLICY AND PROCEDURE

DFW INTERNATIONAL AIRPORT ADMINISTRATIVE POLICY AND PROCEDURE Title: Functional Category Finance Issuing Department: Treasury Management Resolution Number: Effective Date: 05/02/2013 1.0 PURPOSE 1.1 The purpose of the Dallas/Fort Worth International Airport Board

More information

STATEMENT ON SSE S APPROACH TO HEDGING 14 November 2018

STATEMENT ON SSE S APPROACH TO HEDGING 14 November 2018 STATEMENT ON SSE S APPROACH TO HEDGING 14 November 2018 INTRODUCTION SSE is working towards its vision of being a leading energy company in a low carbon world by focusing on core businesses of regulated

More information

ISO-NE s CASPR and State RPSs

ISO-NE s CASPR and State RPSs RPS Collaborative Webinar ISO-NE s CASPR and State RPSs Hosted by Warren Leon, Executive Director, CESA May 23, 2018 Housekeeping Join audio: Choose Mic & Speakers to use VoIP Choose Telephone and dial

More information

Renewing Ireland's Energy European Investment Bank

Renewing Ireland's Energy European Investment Bank Renewing Ireland's Energy European Investment Bank IWEA Autumn Conference 2013 Galway Thursday 3 rd October 08/10/2013 1 The European Investment Bank (EIB) Long-term finance promoting European objectives

More information

Associated Industries of Massachusetts (AIM) is pleased to provide the following comments to the above mentioned issue.

Associated Industries of Massachusetts (AIM) is pleased to provide the following comments to the above mentioned issue. March 13, 2017 By Email to marfp83c@gmail.com The Massachusetts Department of Energy Resources ( DOER ) The Massachusetts Office of the Attorney General ( AGO ) Fitchburg Gas & Electric Light Company d/b/a

More information

PG&E Corporation. Christopher P. Johns Senior Vice President and CFO. Lehman Brothers CEO Energy/Power Conference September 2-4, 2008 New York City

PG&E Corporation. Christopher P. Johns Senior Vice President and CFO. Lehman Brothers CEO Energy/Power Conference September 2-4, 2008 New York City PG&E Corporation Christopher P. Johns Senior Vice President and CFO Lehman Brothers CEO Energy/Power Conference September 2-4, 2008 New York City This presentation is not complete without the accompanying

More information

Swiss Re Corporate Solutions. Financial Risk Solutions in a changing Energy Market Juerg Trueb, 3. April 2017

Swiss Re Corporate Solutions. Financial Risk Solutions in a changing Energy Market Juerg Trueb, 3. April 2017 Swiss Re Corporate Solutions Financial Risk Solutions in a changing Energy Market Juerg Trueb, 3. April 2017 Swiss Re at a glance Group results in USD billions Over 150 years of experience in providing

More information

Macquarie Infrastructure Corporation Reports First Quarter 2016 Financial Results, Increased Dividend

Macquarie Infrastructure Corporation Reports First Quarter 2016 Financial Results, Increased Dividend May 2, 2016 Macquarie Infrastructure Corporation Reports First Quarter 2016 Financial Results, Increased Dividend Proportionately Combined Free Cash Flow increases 8.7% to $133.4 million $1.67 per share

More information

Wholesale Panel. A Tale of Three (Very Different) Markets

Wholesale Panel. A Tale of Three (Very Different) Markets Wholesale Panel A Tale of Three (Very Different) Markets Lee Davis President East Region John Ragan President Gulf Coast John Chillemi President West Region Chris Moser SVP Commercial Operations East Region:

More information

Investor Meetings August 4 12, 2014

Investor Meetings August 4 12, 2014 Investor Meetings August 4 12, 2014 Safe Harbor This presentation includes statements concerning NU s expectations, beliefs, plans, objectives, goals, strategies, assumptions of future events, future financial

More information

BMO 2015 Fixed Income Conference. Todd Stack VP & Treasurer

BMO 2015 Fixed Income Conference. Todd Stack VP & Treasurer BMO 2015 Fixed Income Conference Todd Stack VP & Treasurer 1 Forward Looking Statements This presentation may contain forward looking statements, including statements regarding the business and anticipated

More information

Building on strengths

Building on strengths Building on strengths CIBC World Markets 10 th Annual Whistler Institutional Investor Conference Steve Snyder, President & CEO February 23, 2007 Forward looking statements This presentation may contain

More information

Matthew F. Hilzinger Chief Financial Officer

Matthew F. Hilzinger Chief Financial Officer Matthew F. Hilzinger Chief Financial Officer Morgan Stanley Global Electricity & Energy Conference April 3, 2008 Forward-Looking Statements This presentation includes forward-looking statements within

More information

CDM Project Issues and Analysis

CDM Project Issues and Analysis CDM Project Issues and Analysis Carbon Finance Project Development Workshop Ulaanbaatar, Mongolia June 23-24, 2008 1 Project Cycle Pre-project implementation (one time) 1 Project Design Document preparation

More information

portfolio is located primarily in eastern Canada and Washington State.

portfolio is located primarily in eastern Canada and Washington State. March 30, 2010 Putting Canada s Renewable Energy Industry on the Map Steve Snyder, President & CEO Good morning. Thank you for the introduction and the opportunity to join you today. I also want to thank

More information

IN THE MATTER OF THE BOARD S INVESTIGATION OF CAPACITY PROCUREMENT AND TRANSMISSION PLANNING BPU - Docket No. EO

IN THE MATTER OF THE BOARD S INVESTIGATION OF CAPACITY PROCUREMENT AND TRANSMISSION PLANNING BPU - Docket No. EO IN THE MATTER OF THE BOARD S INVESTIGATION OF CAPACITY PROCUREMENT AND TRANSMISSION PLANNING BPU - Docket No. EO-11050309 Comments of NRG Energy, Inc. Before the New Jersey Board of Public Utilities June

More information

MUNICIPAL BONDS IN TEXAS and THE BOND SALE PROCESS

MUNICIPAL BONDS IN TEXAS and THE BOND SALE PROCESS MUNICIPAL BONDS IN TEXAS and THE BOND SALE PROCESS Government Treasurers Organization of Texas Winter Seminar December 5, 2017 9:30 AM 10:30 AM Robert W. Baird & Co. Incorporated ( Baird ) is providing

More information

Understanding Risk and Preparing the RFP

Understanding Risk and Preparing the RFP Understanding Risk and Preparing the RFP Table of Contents Excerpts from Risk Allocation Primer... A Sample term sheet... B Description of disasters... C Excerpts from Risk Allocation Primer Please note

More information

Northeast Utilities Board of Trustees

Northeast Utilities Board of Trustees Sustainability Northeast Utilities Board of Trustees EVERSOURCE AS A SUSTAINABLE INVESTMENT Analyst Investor Sustainability Safe Harbor This presentation includes statements concerning Eversource s expectations,

More information

This memo provides highlights of market performance in October and November.

This memo provides highlights of market performance in October and November. California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Executive Director, Market Monitoring Date: December 5, 2018 Re: Department of Market Monitoring

More information

Platte River Power Authority

Platte River Power Authority Independent Auditor s Report and Financial Statements Financial Statements Years Ended Contents Independent Auditor s Report...1 Management s Discussion and Analysis (Unaudited)...3 Financial Statements

More information

Opportunities in Bond Financing

Opportunities in Bond Financing Opportunities in Bond Financing Renewable Energy Sidebar Friday, June 1, 2012 Atlanta, Georgia John M. May Managing Director Head of the Alternative Energy Finance Group Stern Brothers & Co. St. Louis,

More information

Volatility, risk, and risk-premium in German and Continental power markets

Volatility, risk, and risk-premium in German and Continental power markets Volatility, risk, and risk-premium in German and Continental power markets Stefan Judisch Supply & Trading GmbH RWE Supply & Trading PAGE 0 Agenda 1. What are the market fundamentals telling us? 2. What

More information

Oil, Gas and Power Prices Have Fallen and Can t Get Up Implications for the Power Industry Municipal Power & Utilities Assembly

Oil, Gas and Power Prices Have Fallen and Can t Get Up Implications for the Power Industry Municipal Power & Utilities Assembly Oil, Gas and Power Prices Have Fallen and Can t Get Up Implications for the Power Industry Municipal Power & Utilities Assembly Mike Zenker, Managing Director of Research NextEra Energy Resources September

More information

Advanced Asset/Liability Management

Advanced Asset/Liability Management Advanced Asset/Liability Management WBA BOLT Summer Leadership Summit June 14, 2018 Presented by: Marc Gall, Vice President mgall@bokf.com 1 Agenda Asset/Liability Management Summary Developing Assumptions

More information

Climate Bonds Standard Version 3.0

Climate Bonds Standard Version 3.0 Climate Bonds Standard Version 3.0 Climate Bonds Initiative 1 Table of Contents The structure of the Climate Bonds Standard had been adjusted to better reflect its consistency and alignment with the Green

More information

Solar Gr G e r en n Bond n s s Webinar July 2016

Solar Gr G e r en n Bond n s s Webinar July 2016 Solar Green Bonds Solar Green Bonds Webinar July 2016 Topics covered in this webinar 1. CBI & the green bond market 2. Green bond labelling & the role of standards 3. Climate Bonds Standard & Certification

More information

Portland General Electric

Portland General Electric Portland General Electric Earnings Conference Call Fourth Quarter and Full-Year 2017 Cautionary Statement Information Current as of February 16, 2018 Except as expressly noted, the information in this

More information

THE DEPARTMENT OF ENERGY S GRID RESILIENCE PRICING PROPOSAL: A COST ANALYSIS

THE DEPARTMENT OF ENERGY S GRID RESILIENCE PRICING PROPOSAL: A COST ANALYSIS THE DEPARTMENT OF ENERGY S GRID RESILIENCE PRICING PROPOSAL: A COST ANALYSIS BY ROBBIE ORVIS, ANDREW GOGGINS, BRENDAN PIERPONT, MAREN WENZEL, LAURA SANCHEZ, AND DAVID POSNER OCTOBER 2017 The Department

More information

Generation Retirement Scenario

Generation Retirement Scenario Generation Retirement Scenario Special Reliability Assessment December 18, 2018 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... v Key Findings... vii Recommendations...

More information

EX22.2v REPORT FOR ACTION. TransformTO Short-term Strategies Financial Estimates SUMMARY

EX22.2v REPORT FOR ACTION. TransformTO Short-term Strategies Financial Estimates SUMMARY EX22.2v REPORT FOR ACTION TransformTO Short-term Strategies Financial s Date: January 9, 2017 To: Budget Committee From: Chief Corporate Officer Wards: All SUMMARY This report responds to City Council's

More information

Global Resilience Risk

Global Resilience Risk Global Resilience Risk An Insurers Perspective WEC Energy Summit 16 March 2016 Jamie Summons, Head of Weather Solutions, Asia Pacific Swiss Re Weather Market Capability Global presence, market leadership

More information

SCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS

SCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS SCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS The following is a summary of the key terms and conditions of the proposed standard form electricity

More information

Management recommends the following enhancements to these modifications to the provisions for commitment costs:

Management recommends the following enhancements to these modifications to the provisions for commitment costs: California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 9, 2012 Re: Decision on Commitment

More information

JOSEPH A. HOLTMAN - ELECTRIC. 1 Q. Please state your name, title, employer and business. 4 Electricity Supply for Consolidated Edison Company of

JOSEPH A. HOLTMAN - ELECTRIC. 1 Q. Please state your name, title, employer and business. 4 Electricity Supply for Consolidated Edison Company of 1 Q. Please state your name, title, employer and business 2 address. 3 A. My name is Joseph A. Holtman. I am Director - 4 Electricity Supply for Consolidated Edison Company of 5 New York, Inc. ("Con Edison"

More information

Estimating Capacity Benefits of the AC Transmission Public Policy Projects

Estimating Capacity Benefits of the AC Transmission Public Policy Projects Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second

More information

Invest in Public Transportation for a Stronger America

Invest in Public Transportation for a Stronger America Invest in Public Transportation for a Stronger America Appendix: Finance Recommendations The American Public Transportation Association Urges the Trump Administration and Congress to Dramatically Increase

More information

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2011 S 1 SENATE BILL 747. Short Title: Offshore Wind Jobs and Economic Development.

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2011 S 1 SENATE BILL 747. Short Title: Offshore Wind Jobs and Economic Development. GENERAL ASSEMBLY OF NORTH CAROLINA SESSION S 1 SENATE BILL Short Title: Offshore Wind Jobs and Economic Development. (Public) Sponsors: Referred to: Senators Hartsell, Stein, Bingham; Rouzer and Vaughan.

More information

Eversource Energy Reports Third Quarter 2017 Results

Eversource Energy Reports Third Quarter 2017 Results 56 Prospect St., Hartford, Connecticut 06103-2818 800 Boylston St., Boston, Massachusetts 02199 Eversource Energy Reports Third Quarter 2017 Results HARTFORD, Conn. and BOSTON, Mass. (November 1, 2017)

More information

MEMORANDUM OF UNDERSTANDING

MEMORANDUM OF UNDERSTANDING MEMORANDUM OF UNDERSTANDING This Memorandum of Understanding ( MOU ) is made effective as of January 30, 2019 among Central Maine Power Company, a Maine corporation with offices located at 83 Edison Drive,

More information

P3 Financing Stan Ladner, Butler Snow LLP Josh Evans, Bostonia Partners LLC

P3 Financing Stan Ladner, Butler Snow LLP Josh Evans, Bostonia Partners LLC P3 Financing Stan Ladner, Butler Snow LLP Josh Evans, Bostonia Partners LLC P3 Financing Options Capital Markets Debt (Bank debt, subordinate debt) Private Activity Bonds (PABs) Governmental Tax-Exempt

More information

Exelon Reports Second Quarter 2018 Results

Exelon Reports Second Quarter 2018 Results Investors Newsroom Suppliers Contact Us COMPANY THE CAREERS LOCATIONS SUSTAINABILITY COMMUNITY GRID NEWSROOM Exelon Reports Second Quarter 2018 Results AUGUST 2, 2018 Earnings Release Highlights GAAP Net

More information

Public Service Enterprise Group

Public Service Enterprise Group Public Service Enterprise Group PSEG Earnings Conference Call 1 st Quarter 2018 April 30, 2018 Forward-Looking Statements Certain of the matters discussed in this presentation about our and our subsidiaries

More information

Bank of China Limited Green Bond Management Statement

Bank of China Limited Green Bond Management Statement Bank of China Limited Green Bond Management Statement Bank of China Limited, including all its branches globally, ( BOC ) is responsible for the preparation and fair presentation of this Green Bond Management

More information

Ex post payoffs of a tolling agreement for natural-gas-fired generation in Texas

Ex post payoffs of a tolling agreement for natural-gas-fired generation in Texas Ex post payoffs of a tolling agreement for natural-gas-fired generation in Texas The 5th IAEE Asian Conference, University of Western Australia, Spring, 2016 Yun LIU, Ph.D. Candidate Department of Economics,

More information

Half Year Results 6 Months Ended 30 June July 2018

Half Year Results 6 Months Ended 30 June July 2018 Half Year Results 6 Months Ended 30 June 2018 24 July 2018 Agenda Operations and Business Review Will Gardiner, CEO Financial Review Den Jones, Interim CFO Delivering the Strategy Will Gardiner, CEO 2

More information

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION November 30, 2016 www.poweradvisoryllc.com To: Power Advisory Clients and Colleagues From: Kris Aksomitis, Jason Chee-Aloy, Brenda Marshall,

More information

GREEN BOND FRAMEWORK

GREEN BOND FRAMEWORK GREEN BOND FRAMEWORK November 2017 1 Contents 1. CDB Background... 3 2. CDB s Green Strategy... 3 3. Green Bond Framework... 4 4. Third Party Verification... 7 Disclaimer... 8 2 1. CDB Background China

More information

Value Driven. Exelon Corporation. Sanford C. Bernstein Conference CO2 Emissions Limits and the Power Sector: How Will Utilities Respond?

Value Driven. Exelon Corporation. Sanford C. Bernstein Conference CO2 Emissions Limits and the Power Sector: How Will Utilities Respond? Value Driven Exelon Corporation Sanford C. Bernstein Conference CO2 Emissions Limits and the Power Sector: How Will Utilities Respond? New York, New York June 14, 2007 Exelon Investor Relations Contacts

More information

Volatility, risk, and risk-premium in German and Continental power markets. Stefan Judisch Supply & Trading GmbH 3 rd April 2014

Volatility, risk, and risk-premium in German and Continental power markets. Stefan Judisch Supply & Trading GmbH 3 rd April 2014 Volatility, risk, and risk-premium in German and Continental power markets Stefan Judisch Supply & Trading GmbH 3 rd April 2014 RWE Supply & Trading 01/04/2014 PAGE 0 Agenda 1. What are the market fundamentals

More information

SURGING PIPELINE INFRASTRUCTURE:

SURGING PIPELINE INFRASTRUCTURE: INFRASTRUCTURE: SURGING PIPELINE Sergio Ronga, Managing Director at DC Advisory, spoke to us about the current status of the European infrastructure market. 56 Baker & McKenzie Global Private Equity Insights

More information

Centrica plc Interim Results. for the period ended 30 June 2017

Centrica plc Interim Results. for the period ended 30 June 2017 Centrica plc Interim Results for the period ended 30 June 2017 Disclaimer This presentation does not constitute an invitation to underwrite, subscribe for, or otherwise acquire or dispose of any Centrica

More information

SUMMARY PROSPECTUS. May 1, 2018

SUMMARY PROSPECTUS. May 1, 2018 SUMMARY PROSPECTUS May 1, 2018 REMS REAL ESTATE INCOME 50/50 FUND INSTITUTIONAL SHARES (Ticker: RREIX) PLATFORM SHARES (Ticker: RREFX) Z SHARES (Ticker: RREZX) Before you invest, you may want to review

More information

FirstEnergy Solutions Files Deactivation Notice for Three Competitive Nuclear Generating Plants in Ohio and Pennsylvania

FirstEnergy Solutions Files Deactivation Notice for Three Competitive Nuclear Generating Plants in Ohio and Pennsylvania 341 White Pond Drive Akron, OH 44320 FOR IMMEDIATE RELEAS E FirstEnergy Solutions Files Deactivation Notice for Three Competitive Nuclear Generating Plants in Ohio and Pennsylvania 4,048 Megawatts of Electricity

More information

FP FORESIGHT UK INFRASTRUCTURE INCOME FUND

FP FORESIGHT UK INFRASTRUCTURE INCOME FUND FP FORESIGHT UK INFRASTRUCTURE INCOME FUND Targeting annual income of 5% through active management of UK listed renewable energy and infrastructure investment companies. INVESTOR GUIDE This Investor Guide

More information

New Development Bank s 2016 Green Financial Bond Duration Assurance

New Development Bank s 2016 Green Financial Bond Duration Assurance Appendix I New Development Bank s 2016 Green Financial Bond Duration Assurance Description of the use of proceeds (Reporting Period: 1 January 2017 18 July 2018) In accordance with The Announcement on

More information

KEY ELEMENTS OF A SUCCESSFUL CLEAN ENERGY PROJECT: Project Finance. Scott Foster September 14, 2011

KEY ELEMENTS OF A SUCCESSFUL CLEAN ENERGY PROJECT: Project Finance. Scott Foster September 14, 2011 KEY ELEMENTS OF A SUCCESSFUL CLEAN ENERGY PROJECT: Project Finance Scott Foster September 14, 2011 Hannon Armstrong Experience Transactions across the United States Hannon Armstrong Capital, LLC is a 31-year-old,

More information

4 th Quarter 2008 Earnings Review and 2009 Outlook February 6, 2009

4 th Quarter 2008 Earnings Review and 2009 Outlook February 6, 2009 4 th Quarter 2008 Earnings Review and 2009 Outlook February 6, 2009 Safe Harbor Statement Some of the statements in this document concerning future company performance will be forward-looking within the

More information

Eversource Energy AGA Financial Forum May 15 17, 2016

Eversource Energy AGA Financial Forum May 15 17, 2016 Eversource Energy 2016 AGA Financial Forum May 15 17, 2016 Safe Harbor All per share amounts in this presentation are reported on a diluted basis. The only common equity securities that are publicly traded

More information

Bank of China Limited Sustainability Series Bonds Management Statement

Bank of China Limited Sustainability Series Bonds Management Statement Bank of China Limited Sustainability Series Bonds Management Statement Bank of China Limited, including all its branches globally ( BOC ) is responsible for the preparation and fair presentation of this

More information

City of Toronto: Issuer Presentation RBC Green Bond Conference, April 10

City of Toronto: Issuer Presentation RBC Green Bond Conference, April 10 City of Toronto: Issuer Presentation 2018 RBC Green Bond Conference, April 10 Presentation Highlights 1. City of Toronto Economic Profile 2. Fiscal Overview 3. Regulatory Environment 4. Additional Credit

More information

Advisory for Municipalities and Other Public Awarding Authorities Using Energy Broker Services

Advisory for Municipalities and Other Public Awarding Authorities Using Energy Broker Services Office of the Inspector General Commonwealth of Massachusetts Glenn A. Cunha Inspector General Advisory for Municipalities and Other Public Awarding Authorities Using Energy Broker Services October 20,

More information

P3 Financing. Barney Allison. Peter Luchetti. Alfonso Mendez. Partner, Nossaman LLP. Managing Partner, Table Rock Capital

P3 Financing. Barney Allison. Peter Luchetti. Alfonso Mendez. Partner, Nossaman LLP. Managing Partner, Table Rock Capital P3 Financing Barney Allison Partner, Nossaman LLP Peter Luchetti Managing Partner, Table Rock Capital Alfonso Mendez Senior Financial Advisor, Arup Typical P3 Financing Structure Project Company SPV P3

More information

Sanford C. Bernstein Strategic Decisions Conference AES CORPORATION. Paul Hanrahan President and Chief Executive Officer. May 31,

Sanford C. Bernstein Strategic Decisions Conference AES CORPORATION. Paul Hanrahan President and Chief Executive Officer. May 31, AES CORPORATION Sanford C. Bernstein Strategic Decisions Conference Paul Hanrahan President and Chief Executive Officer May 31, 2006 1 Safe Harbor Disclosure Certain statements in the following presentation

More information

NECA Fuels Conference Coralie Carter Sculley. September 28, 2016

NECA Fuels Conference Coralie Carter Sculley. September 28, 2016 NECA Fuels Conference Coralie Carter Sculley September 28, 2016 Forward-Looking Statements/ Non-GAAP Financial Measures Forward-Looking Statements / Non-GAAP Financial Measures This presentation includes

More information

Independent Auditors Report

Independent Auditors Report GenOn REMA, LLC KPMG LLP 811 Main Street Houston, TX 77002 Independent Auditors Report The Board of Directors and Member GenOn Northeast Generation, Inc., Sole Member of GenOn REMA, LLC: We have audited

More information

Second Quarter & Year-to-Date 2007 Results

Second Quarter & Year-to-Date 2007 Results Second Quarter & Year-to-Date 2007 Results Strong business model. Diversified generating assets. Technical and commercial expertise. Environmental leadership. Financial discipline. Forward looking statements

More information

SUMMARY PROSPECTUS. May 1, 2018

SUMMARY PROSPECTUS. May 1, 2018 SUMMARY PROSPECTUS May 1, 2018 REMS INTERNATIONAL REAL ESTATE VALUE-OPPORTUNITY FUND INSTITUTIONAL SHARES (Ticker: REIFX) PLATFORM SHARES (Ticker: REIYX) Z SHARES (Ticker: REIZX).Before you invest, you

More information

Green Impact Report. Formosa 1. Introduction. Green Impact: Forecast GIG CARBON RATING: AAA

Green Impact Report. Formosa 1. Introduction. Green Impact: Forecast GIG CARBON RATING: AAA Introduction The Green Investment Ratings (GIR) Team of Green Investment Group Limited ( GIG ) has prepared this report (the Report ) in connection with the Offshore Wind Farm (the Project or ). The GIR

More information

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 1 2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019 Agenda January 24 9:00am-9:30am pacific Capacity-Contribution Values for Energy-Limited Resources 9:30am-11:30am pacific Coal

More information

Sanford C. Bernstein Strategic Decisions Conference. May 29, 2014

Sanford C. Bernstein Strategic Decisions Conference. May 29, 2014 Sanford C. Bernstein Strategic Decisions Conference May 29, 2014 Cautionary Statements Regarding Forward-Looking Information This presentation contains certain forward-looking statements within the meaning

More information

Who Says Financing Has To Be Conventional

Who Says Financing Has To Be Conventional Who Says Financing Has To Be Conventional Ohio Hospital Association Annual Conference - Session #2 June 9, 2014 Kass Matt Managing Director Lancaster Pollard & Co. kmatt@lancasterpollard.com Offering Financial

More information

Securities-Backed Debt Financing US & Emerging Markets

Securities-Backed Debt Financing US & Emerging Markets Overview of: PRIINCETON TECHNOLOGIIES INTERNATIIONAL INC.. A Global Technology Company Securities-Backed Debt Financing US & Emerging Markets First Quarter - 2011 Overview of Securities-Backed Debt Financing

More information

MEMORANDUM. TO: Barry Fadden, Acting Purchasing Agent; Carl Spector, Executive Director, Boston Air Pollution Control Commission

MEMORANDUM. TO: Barry Fadden, Acting Purchasing Agent; Carl Spector, Executive Director, Boston Air Pollution Control Commission 6 Everett Street, 4th Floor Cambridge, MA, 02138 T: 617-496-2058 F: 617-384-7633 MEMORANDUM TO: Barry Fadden, Acting Purchasing Agent; Carl Spector, Executive Director, Boston Air Pollution Control Commission

More information

Fourth Quarter 2017 Update. February 27, 2018

Fourth Quarter 2017 Update. February 27, 2018 Fourth Quarter 2017 Update February 27, 2018 1 Agenda Overview Dan Greenwell, President and Chief Executive Officer Operations Review John Diesch, Executive Vice President, Chemical Manufacturing Financial

More information

The basics of energy trading. Edgar Wilton

The basics of energy trading. Edgar Wilton The basics of energy trading Edgar Wilton Overview I. Liberalized electricity markets II. OTC and exchange trading III. Pricing analysis IV. Risk management V. Trading strategies 2 About me MSc in Risk

More information

BROOKFIELD RENEWABLE POWER INC. MANAGEMENT S DISCUSSION AND ANALYSIS MARCH 31, 2008

BROOKFIELD RENEWABLE POWER INC. MANAGEMENT S DISCUSSION AND ANALYSIS MARCH 31, 2008 BROOKFIELD RENEWABLE POWER INC. MANAGEMENT S DISCUSSION AND ANALYSIS MARCH 31, 2008 Attached is management s discussion and analysis of Brookfield Renewable Power Inc. (formerly Brookfield Power Inc. and

More information

M&A Financing. Presentation to: FEI NE WI Chapter. April 19, 2016

M&A Financing. Presentation to: FEI NE WI Chapter. April 19, 2016 M&A Financing Presentation to: FEI NE WI Chapter April 19, 2016 Agenda Characteristics of Attractive M&A Targets Key Financial and Tax Considerations Typical M&A Financing Participants Typical Buyout Capital

More information

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG 14- Liberty Utilities (EnergyNorth Natural Gas) Corp.

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG 14- Liberty Utilities (EnergyNorth Natural Gas) Corp. STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION DIRECT TESTIMONY OF FRANCISCO C. DAFONTE Page of Q. Mr. DaFonte, please state your name, business address and position with Liberty Utilities

More information

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and

More information

New Jersey Reference Case and Policy Scenario Results

New Jersey Reference Case and Policy Scenario Results New Jersey Reference Case and Policy Scenario Results January 3, 219 Prepared by ICF for Rutgers University at the Request of the New Jersey Board of Public Utilities NJ Reference Case and Policy Scenario

More information

Third Quarter & Year-to-Date 2007 Results

Third Quarter & Year-to-Date 2007 Results Third Quarter & Year-to-Date 2007 Results Strong business model. Diversified generating assets. Technical and commercial expertise. Environmental leadership. Financial discipline. Forward looking statements

More information

UK ELECTRIC MARKET REFORM APPLICATION TO TEXAS POWER MARKET. Ingmar Sterzing CEIC Seminar April 10, 2013

UK ELECTRIC MARKET REFORM APPLICATION TO TEXAS POWER MARKET. Ingmar Sterzing CEIC Seminar April 10, 2013 UK ELECTRIC MARKET REFORM APPLICATION TO TEXAS POWER MARKET Ingmar Sterzing CEIC Seminar April 10, 2013 1 Ingmar Sterzing, Pittsburgh, PA, 2013 UK and ERCOT Strikingly Similar Similar generation infrastructure

More information

NYMEX - Annual Strips

NYMEX - Annual Strips Weekly Summary: This week s U.S. Energy Information Administration s natural gas storage reported natural gas storage in the U.S. fell by 211 billion cubic feet, more than expected reduction of 204-208

More information

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Advisory Service for Energy and Climate Change John Lambert Senior Business Development Manager Direct Energy

More information