T2S User Testing and Migration DCA Holder view

Size: px
Start display at page:

Download "T2S User Testing and Migration DCA Holder view"

Transcription

1 T2S User Testing and Migration DCA Holder view Information event for future DCA Holders: Euro liquidity management in view of T2S ECB, 16 December 2013 T2S Programme Office European Central Bank 1

2 T2S User Testing and Migration DCA Holder view Agenda 1 Declaration procedure for DCPs/DCA Holders 2 T2S User Testing 3 T2S Migration 2

3 T2S User Testing and Migration DCA Holder view Agenda 1 Declaration procedure for DCPs/DCA Holders 2 T2S User Testing 3 T2S Migration 3

4 Declaration procedure for DCA Holders Timing The institutions intending to become directly connected DCA holders should inform the Eurosystem (in a binding manner) at the latest: - for A2A mode, 1 year before the start of the Community testing stage of the respective migration wave with which they first time migrate to T2S - for U2A mode, 3 months before the start of the Community testing stage of the respective migration wave with which they first time migrate to T2S A2A mode U2A mode Wave 1 3 March December 2014 Wave 2 19 September June 2015 Wave 3 16 February November 2015 Wave 4 09 October July 2016 NCBs can define earlier deadlines towards its communities due to adaptation/operational aspects Declaration is the precondition for certification 4

5 T2S User Testing and Migration DCA Holder view Agenda 1 Declaration procedure for DCPs/DCA Holders 2 T2S User Testing 3 T2S Migration 5

6 T2S User Testing Introduction general principles The User Testing Subgroup (UTSG) prepares and monitors the execution of the T2S User Testing - A PMG substructure - UTSG members are CSDs, Central Banks and Eurosystem - CSD participants and payment banks are involved through observers and their relevant CSDs and Central Banks The CSDs and Central Banks are responsible for coordinating the User Testing preparation and execution of its community (ICP as well as DCPs) CSD participants and DCA Holders participate in the User Testing execution according to the testing plan of the relevant CSDs and Central Banks 6

7 T2S User Testing DCA Holder s mandatory testing stages Connectivity Bilateral Interoperability Multilateral Interoperability Community Business Day 7

8 T2S User Testing DCA Holder s mandatory testing stages 2-3 months before the start of the Community testing of the wave with which the DCA Holder will first time test T2S Connectivity DCP Validate the proper setup and configuration of all connectivity related aspects, to ensure that the actor s systems and T2S can communicate via A2A and/or U2A Community CSDs, CBs, communities Test the adaptation of participants internal systems to T2S and the updated systems of the CSDs/CBs upon involvement by the CSDs and CBs Business Day CSDs, CBs, communities Test the adaptation of participants internal systems to T2S based on the production schedule and similar to the day-to-day business 8

9 T2S User Testing DCA Holder s testing activities on T2S test environments Test Environment Usage Q Q Q Q Q Q Q Q Q Q Q Q Connectivity Set-up & Testing WAVE I Testing Community/Business Day Community WAVE 2 Testing Community/Business Day WAVE 3 Testing Community/Business Day/Stabilisation WAVE 4 Testing Community/Business Day/Stabilisation Pre-Prod Connectivity Set-up & Testing Pre-Production tests WAVE 2 Community - Cycle 2* 01 Aug 30 Sep Wave 1 Go-Live Wave 2 Go-Live Wave 3 Go-Live Wave 4 Go-Live * Phased-in connectivity set-up and connectivity testing for waves 2, 3 & 4 With Liquidity Transfer Utility (i.e. without T2CUST) 9

10 T2S User Testing DCA Holder s certification testing Objective: to provide evidence that an institution connecting to T2S via A2A or U2A can interact with T2S Scope: a limited number of predefined test cases to be executes as a technical sender of the messages - The maximum number of DCA Holder certification test cases is 6 - The tests that a DCA Holder shall execute will depend on the connectivity mode, the communication mode and the functionalities the DCA Holder will use in production Timing: during the Community testing stage of the first wave the DCA Holder would like to migrate to T2S Support: the Central Bank of the respective DCA Holder will support and communicate with the DCA Holder Issuance of certification: In case an institution executes certification testing as a DCA Holder, the respective Central Bank will issue the certificate; in case the institution executes certification testing also as a DCP participant, the T2S PO will issue the certificate covering both business areas 10

11 T2S User Testing DCA Holder s authorisation Objective: to verify whether the DCA Holder complies with the Central Bank s rules, procedures and requirements to go-live in T2S Scope: common set of authorisation test cases defined by the Eurosystem Central Banks Timing: during the Community testing stage of the respective Central Bank (exact timing to be defined by the Eurosystem Central Banks) Support: the Central Bank of the respective DCA Holder will support and communicate with the DCA Holder Issuance of authorisation: the Central Bank of the respective DCA Holder 11

12 T2S User Testing DCA Holders familiarisation phase The CSDs and Central Banks have decided that before the start of the Community testing stage of all waves, the waves perform - The Pre-Migration Dress Rehearsal followed by - The Migration Weekend Dress Rehearsal on the weekend preceding to the start of the Community testing stage of this wave and followed by - The communities testing with T2S based on the fine tuned static data configuration build up during the Migration Weekend Dress Rehearsal Some Central Banks plan to give certain rights and privileges to their DCA Holders to perform some tasks during the Pre-Migration Phase. Therefore, they have informed the UTSG that their DCA Holders may require a period before their participation in the Pre-Migration Dress Rehearsal in order to familiarise with T2S - The only dependency between a DCA Holder activity and the subsequent Central Bank activity is about setting up the secondary CMBs for client-collateralisation The UTSG will consider planning such DCA Holders familiarisation period once the DCA Holders confirm the need for such period and detail their requirements 12

13 T2S User Testing and Migration DCA Holder view Agenda 1 Declaration procedure for DCPs/DCA Holders 2 T2S User Testing 3 T2S Migration 13

14 T2S Migration Introduction general principles The Migration Subgroup (MSG) coordinates the preparation and the execution of the migration to T2S - A PMG substructure - MSG members are CSDs, Central Banks and Eurosystem - CSD participants and payment banks are involved through observers and their relevant CSDs and Central Banks The CSDs and Central Banks are responsible for coordinating the migration preparation and execution of its community (ICP as well as DCPs) CSD participants and DCA Holders participate in the migration execution according to the pre-migration schedule and migration weekend playbook applicable to the relevant CSDs and Central Banks 14

15 T2S Migration Pre-Migration phase - DCA Holder s involvement DCA Holder s static data is set-up during the Pre- Migration phase of each Migration wave Scope: - Access Rights: Users roles and privileges - Dedicated Cash Accounts and Credit Memorandum Balance: Liquidity Transfer Orders, Client collateralisation - Messaging and Reporting: Message subscription, Report configuration Practicality: the respective Central Bank will define which static data will be set-up centrally by the central bank and which static data will be set-up directly by the DCA Holder, as well as the timing for both activities 15

16 T2S Migration Migration weekend - DCA Holder s involvement DCA Holder can be involved in limited activities during the migration weekend - Maintain any remaining static data - Send CMS feeds to T2S (Securities prices, securities eligibility for collateralisation) and Reconcile - Initiate liquidity transfers (LTs) via T2 system - Reconcile settled LTs - Query T2S system Practicality: The extent of DCA Holders access to T2S may be defined by the respective Central Banks 16

17 Thank you for your attention 17

CLASSIFICATION DIRECTLY CONNECTED PARTIES IN T2S

CLASSIFICATION DIRECTLY CONNECTED PARTIES IN T2S T2S PROGRAMME OFFICE ECB-UNRESTRICTED 11 June 2013 Item 4.2 09.04.01/2013/006583 CLASSIFICATION DIRECTLY CONNECTED PARTIES IN T2S Background The T2S Advisory Group (AG) in February 2013 invited the T2S

More information

Registration to T2S. 07 May Patrick Heyvaert

Registration to T2S. 07 May Patrick Heyvaert 07 May 2015 Patrick Heyvaert Registration Ordering T2S services via VAN Only for directly connected Procedure SWIFT or SIA-Colt Static data test environment (T2S community and pre-production environments)

More information

DCA Info session. 9 December 2014

DCA Info session. 9 December 2014 DCA Info session 9 December 2014 DCA Info session Peter Lagaert 9 December 2014 Overview T2-T2S CENTRAL BANK MONEY 3 Introduction 01-10-14 Bilateral Testing 30-04-15 Multilateral Testing wave 2 16-09-15

More information

Likely obsolete topics from the potential Change Requests for T2S Release 2 May ECB T2S Programme Office European Central Bank

Likely obsolete topics from the potential Change Requests for T2S Release 2 May ECB T2S Programme Office European Central Bank Requests for T2S Release 2 May 2015 ECB T2S Programme Office European Central Bank 1 Requests Background ECB has been keeping a log of changes that have been considered as potential candidates for a future

More information

T2S: Settling without borders in Europe

T2S: Settling without borders in Europe T2S: Settling without borders in Europe T2S DCP Infosession Paris, 11 October 2011 T2S Programme Office European Central Bank Table of Contents 1 Status Update 2 What is a DCP? 3 What are the implications

More information

T2S Guide for Payment Banks

T2S Guide for Payment Banks T2S Guide for Payment Banks June 2016 updated version T2S Programme Office European Central Bank ECB-PUBLIC 0 1 T2S Guide for Payment Banks An Introduction A Payment Bank is an important entity in T2S

More information

Collection of additional requirements for the T2S cash forecast

Collection of additional requirements for the T2S cash forecast Collection of additional requirements for the T2S cash forecast Workshop on T2S cash forecast and message output optimisation 23 February 2016 European Central Bank 0 Introduction Recently many requests

More information

T2S: Planning Pricing - Harmonisation

T2S: Planning Pricing - Harmonisation 0 T2S: Planning Pricing - Harmonisation NBB-SSS, 23 April 2012 Annemieke Bax - T2S Programme Office European Central Bank 1 T2S Introduction Purpose and Benefits of T2S A Service offered to CSDs for Settlement

More information

Liquidity Management in T2S

Liquidity Management in T2S Liquidity Management in T2S Info Session T2S Project Team European Central Bank 1 Outline 1. Liquidity Management in T2S Principles and Definitions Setup 2. Liquidity Management - Scenarios Liquidity Transfers

More information

Tasks related to the support of T2S auto-collateralisation procedure

Tasks related to the support of T2S auto-collateralisation procedure Tasks related to the support of T2S auto-collateralisation procedure Open tickets as of 22 nd May 2015 1. INC159759 opened on 16 th March: Issue with the upload of valuation coefficients in T2S. The cutoff

More information

Business Case. Setup of a Credit Memorandum Balance

Business Case. Setup of a Credit Memorandum Balance Business Case Setup of a Credit Memorandum Balance 5 GUI Workshop Frankfurt March 31 th, 2011 1 Business Case: U2A configuration of all the necessary Static Data to setup a Credit Memorandum Balance (CMB)

More information

Answering the DCP Questionnaire - CSD's Common Answers and KELER's individual answers

Answering the DCP Questionnaire - CSD's Common Answers and KELER's individual answers SD's ommon Answers and KELER's individual answers 1 2013.06.07 Answering the DP Questionnaire - SD's ommon Answers and KELER's individual answers Dear DPs, with this document you receive the common answers

More information

TARGET2-BE User Group. 15 June 2017

TARGET2-BE User Group. 15 June 2017 TARGET2-BE User Group 15 June 2017 Agenda T2-T2S consolidation High level overview Future RTGS services High level overview URD Releases and testing Release 11.0 November 2017 Release 12.0 November 2018

More information

SCHEDULE OF A SETTLEMENT DAY IN T2S DETAILED DESCRIPTION

SCHEDULE OF A SETTLEMENT DAY IN T2S DETAILED DESCRIPTION SCHEDULE OF A SETTLEMENT DAY IN TS DETAILED DESCRIPTION 4 5 TS Project Office Reference: 09.04.0/00/009600 Date: 0 November 00 Version:.4 Status: Final 6 TABLE OF CONTENTS 4 5 6 7 8 9 0 4 5 6 7 8 9 0 4

More information

T2S features and functionalities

T2S features and functionalities T2S features and functionalities Conference at Narodowy Bank Polski 23 June 2009 T2S Project Team European Central Bank 09.04.01/2009/005409 T2S settles CSD instructions Notary function Custody and assetservicing

More information

2017 Cash management in TARGET2-Securities with the Banque de France Blueprint Version 4 March 2017

2017 Cash management in TARGET2-Securities with the Banque de France Blueprint Version 4 March 2017 2017 Cash management in TARGET2-Securities with the Banque de France Blueprint Version 4 March 2017 Banque de France Version 4 March 2017 1 C O N T E N T S 1. INTRODUCTION... 5 2. CASH ACCOUNTS... 6 2.1.

More information

TARGET2-Securities (T2S) Functional Design at a Glance. An introduction to T2S for CBF customers October TARGET2- Securities (T2S)

TARGET2-Securities (T2S) Functional Design at a Glance. An introduction to T2S for CBF customers October TARGET2- Securities (T2S) TARGET2-Securities (T2S) Functional Design at a Glance An introduction to T2S for CBF customers October 2013 TARGET2- Securities (T2S) TARGET2-Securities (T2S) Functional Design at a Glance An introduction

More information

T2S Auto-collateralisation. 19 November 2013

T2S Auto-collateralisation. 19 November 2013 T2S Auto-collateralisation Additional background information after the date of the workshop A Eurosystem workshop entitled "Set-up for autocollateralisation/client collateralisation in T2S was held on

More information

T2-T2S CONSOLIDATION USER REQUIREMENTS DOCUMENT T2 - CENTRAL LIQUIDITY MANAGEMENT COMPONENT FOR

T2-T2S CONSOLIDATION USER REQUIREMENTS DOCUMENT T2 - CENTRAL LIQUIDITY MANAGEMENT COMPONENT FOR T2-T2S CONSOLIDATION USER REQUIREMENTS DOCUMENT FOR T2 - CENTRAL LIQUIDITY MANAGEMENT COMPONENT Version: 1.2 Status: Final Date: 30/11/2018 Contents 1 CENTRAL LIQUIDITY MANAGEMENT (CLM)... 4 1.1 Overview...

More information

Liquidity Management - Functional overview (Features in T2 and T2S to manage liquidity incl. T2S Interface in T2)

Liquidity Management - Functional overview (Features in T2 and T2S to manage liquidity incl. T2S Interface in T2) Liquidity Management - Functional overview (Features in T2 and T2S to manage liquidity incl. T2S Interface in T2) Information event for future DCA holders, 16 Dec 2013 Siegfried Vonderau, 3CB/4CB 1 Features

More information

CORPORATE ACTIONS BUSINESS PROCESS DESCRIPTION

CORPORATE ACTIONS BUSINESS PROCESS DESCRIPTION CORPORATE ACTIONS BUSINESS PROCESS DESCRIPTION TS Programme Office Reference: 0.0.0/0/000 Date: 0 April 0 Version:. Status: Draft 0 TABLE OF CONTENTS 0 0 0 Introduction. Objective and Scope. Structure

More information

BOGS Feasibility Assessment towards T2S

BOGS Feasibility Assessment towards T2S BOGS Feasibility Assessment towards T2S v 1.0 Athens, April 2012 Table of Contents 1. EXECUTIVE SUMMARY... 3 2. IMPACT ANALYSIS/ADAPTATION APPROACH... 3 2.1 LEGAL/REGULATORY... 4 2.1.1 Compliance with

More information

AMIPAY NSG TIPS infosession 11/01/2018

AMIPAY NSG TIPS infosession 11/01/2018 AMIPAY NSG TIPS infosession 11/01/2018 Agenda TIPS and ASI6 RT TIPS functioning T2 in view of TIPS Role of the NBB Conclusions 2 / 67 AMIPAY NSG TIPS Infosession - Introduction TIPS and ASI6 RT Axelle

More information

Insight Session: T2S Auto-collateralisation

Insight Session: T2S Auto-collateralisation Insight Session: T2S Auto-collateralisation T2S Info Session Vienna, 5 October 2012 T2S Programme Office European Central Bank ECB-PUBLIC 0 Table of Contents T2S Auto-collateralisation 1 Why is auto-collateralisation

More information

ECB-UNRESTRICTED. T2-T2S Consolidation. ECB DG-MIP T2-T2S Consolidation Project Team. Outcome of the market consultation.

ECB-UNRESTRICTED. T2-T2S Consolidation. ECB DG-MIP T2-T2S Consolidation Project Team. Outcome of the market consultation. ECB DG-MIP Project Team Outcome of the market consultation AMI-Pay meeting 29 September 2017 Rubric Outcome of the market consultation Statistics URD Institutions Comments CLM 62 831 RTGS 59 646 SHRD 56

More information

1. General Information CR Raised by: T2S Project Team Institute: ECB Date Raised: 21/04/09

1. General Information CR Raised by: T2S Project Team Institute: ECB Date Raised: 21/04/09 1. General Information CR Raised by: T2S Project Team Institute: ECB Date Raised: 21/04/09 Change Request Title: Life Cycle of a Liquidity Transfer Order CR Ref.: T2S URD 152 Change Request Classification:

More information

T2S Harmonisation workstream update

T2S Harmonisation workstream update T2S Harmonisation workstream update T2S Advisory Group meeting, Malta Stock Exchange, Malta, 19 June 2013 HSG/T2S Programme Office European Central Bank AG Agenda Item 5.1 0 Outline 1 CSDR update HSG Outcome

More information

Test plan general view

Test plan general view T2S COMMUNITY TEST Test plan general view 22 nd 17 th April 2015 Formatted: Superscript Version 2.01 Content 1.0 INTRODUCTION 4 2.0 TEST APPLICABILITY 4 3.0 TEST SUPPORT 6 4.0 TESTING OUTCOME 7 5.0 SET-UP

More information

Central Depository AD

Central Depository AD Central Depository AD FEASIBILITY STUDY Target 2 Securities (T2S) Project Central Depository AD June 2012 1 P a g e Feasibility Study Authorization Memorandum I have assessed the Feasibility Study for

More information

T2/T2S CONSOLIDATION HIGH LEVEL BUSINESS CHANGES DOCUMENT

T2/T2S CONSOLIDATION HIGH LEVEL BUSINESS CHANGES DOCUMENT T2/T2S CONSOLIDATION HIGH LEVEL BUSINESS CHANGES DOCUMENT Version: 0.0.03 Status: Draft Date: 20/03/2017 Table of Contents 1 INTRODUCTION... 3 2 MODULAR APPROACH... 4 2.1. Requirements... 4 2.2. Shared

More information

1. General Information CR Raised by: T2S Project Team Institute: ECB Date Raised: 21/04/09

1. General Information CR Raised by: T2S Project Team Institute: ECB Date Raised: 21/04/09 1. General Information CR Raised by: T2S Project Team Institute: ECB Date Raised: 21/04/09 Change Request Title: Life Cycle of a Liquidity Transfer Order CR Ref.: T2S URD 152 Change Request Classification:

More information

Operational Aspects on the Cash Side. T2S Info Session Ljubljana, 10 March 2013 Patrick Papsdorf DG-P European Central Bank

Operational Aspects on the Cash Side. T2S Info Session Ljubljana, 10 March 2013 Patrick Papsdorf DG-P European Central Bank Operational Aspects on the Cash Side T2S Info Session Ljubljana, 10 March 2013 Patrick Papsdorf DG-P European Central Bank 1 Table of Contents 2 1 2 3 4 5 Introduction Fundamentals Procedures in normal

More information

TARGET2-BE User Group. 5 April 2017

TARGET2-BE User Group. 5 April 2017 TARGET2-BE User Group 5 April 2017 Agenda Future RTGS High level business domains CLM and accounts Central bank operations Payments Liquidity transfers Reference data Management minimum reserves Eurosystem

More information

CROSS-BORDER MARKET PRACTICE SUB-GROUP (XMAP) REPORT ON CROSS-CSD ACTIVITY

CROSS-BORDER MARKET PRACTICE SUB-GROUP (XMAP) REPORT ON CROSS-CSD ACTIVITY ADVISORY GROUP ON MARKET INFRASTRUCTURES FOR SECURITIES AND COLLATERAL (AMI-SECO) 17 NOVEMBER 2017 CROSS-BORDER MARKET PRACTICE SUB-GROUP (XMAP) REPORT ON CROSS-CSD ACTIVITY Executive Summary The purpose

More information

Service description for KDD members in T2S environment

Service description for KDD members in T2S environment Service description for KDD members in T2S environment Version 3, September 2016 CONTENTS A. GENERAL INFORMATION... 3 B. BUSINESS AND OPERATIONAL ASPECTS OF KDD S SERVICES IN T2S ENVIRONMENT... 4 1. STATIC

More information

T2-T2S CONSOLIDATION HIGH-LEVEL SUMMARY OF BUSINESS CHANGES

T2-T2S CONSOLIDATION HIGH-LEVEL SUMMARY OF BUSINESS CHANGES T2-T2S CONSOLIDATION HIGH-LEVEL SUMMARY OF BUSINESS CHANGES Version: 0.70.6 Status: DRAFT Date: 22/06/201717/05 /2017 Contents 1 INTRODUCTION... 4 2 MODULAR APPROACH... 6 2.1 Requirements... 6 2.2 Central

More information

DATA MODEL DOCUMENTATION. Version 1.0

DATA MODEL DOCUMENTATION. Version 1.0 DATA MODEL DOCUMENTATION Version 1.0 1 CLASS DIAGRAMS... 6 1.1 GFS 00 - GENERIC AUDIT TRAIL AND REVISIONS... 6 1.2 GFS 01 - HIGH LEVEL STATIC DATA... 7 1.3 GFS 02 - PARTY DATA MANAGEMENT... 8 1.4 GFS 03

More information

Change Requests 559 and 560 resulting from the CSG s Task Force (TF) on Insolvency Proceedings

Change Requests 559 and 560 resulting from the CSG s Task Force (TF) on Insolvency Proceedings Change Requests 559 and 560 resulting from the CSG s Task Force (TF) on Insolvency Proceedings CRG teleconference on 22 January 2016 T2S Programme Office European Central Bank 1 Change Requests resulting

More information

Status Update of Change Requests from the CSG s Task Force (TF) on Insolvency Proceedings

Status Update of Change Requests from the CSG s Task Force (TF) on Insolvency Proceedings Status Update of Change Requests from the CSG s Task Force (TF) on Insolvency Proceedings CRG meeting on 10 March 2016 T2S Programme Office European Central Bank 1 Background The CSG in the meeting on

More information

TESTING ACTIVITIES FOR THE SSP RELEASE V12.0 (2 ND REV)

TESTING ACTIVITIES FOR THE SSP RELEASE V12.0 (2 ND REV) ECB-Public 20 26 June July 2018 TESTING ACTIVITIES FOR THE SSP RELEASE V12.0 (2 ND REV) 1. Introduction With reference to the Eurosystem communication on the Final content of the SSP release 12.0 as published

More information

TARGET2-BE User Group 9/11/2016

TARGET2-BE User Group 9/11/2016 TARGET2-BE User Group 9/11/2016 TARGET2-BE User Group Agenda TARGET2 consultation Eurosystem vision for the future RTGS services T2S and TARGET2 Internal liquidty transfers in T2S Privileges for auto-collateralisation

More information

TESTING ACTIVITIES FOR THE SSP RELEASE V11.0

TESTING ACTIVITIES FOR THE SSP RELEASE V11.0 ECB-Public 18 May 2017 TESTING ACTIVITIES FOR THE SSP RELEASE V11.0 Introduction With reference to the Eurosystem communication on the content of the SSP release 11.0 as published on the ECB/TARGET2 Website

More information

ICP Account Application Form for T2S

ICP Account Application Form for T2S ICP Account Application Form for T2S We, the undersigned, representing, hereby request LuxCSD S.A. ( LuxCSD ) to open an account in our name with the Account name following specifications: 1 Registered

More information

Outcome of the Change Review Group (CRG) meeting 15 December 2017

Outcome of the Change Review Group (CRG) meeting 15 December 2017 T2S Change Review Group ECB-PUBLIC Final 12 January 2018 of the Change Review Group (CRG) meeting 15 December 2017 1. Introductory session The acting chairperson, Ignacio Terol, informed that the ECB Governing

More information

NASDAQ CSD SERVICE DESCRIPTION

NASDAQ CSD SERVICE DESCRIPTION NASDAQ CSD SERVICE DESCRIPTION Please note that the service description is provided to the stakeholders of the Nasdaq CSD for information purposes and document does not establish the procedures of the

More information

Summary Meeting of the Change Review Group (CRG)

Summary Meeting of the Change Review Group (CRG) T2S PROGRAMME OFFICE 22 November 2016 V1.1 Contact person: Alejandro del Campo Roiz de la Parra Phone: +49 69 1344 7910 E-mail: T2S.CRG@ecb.int Summary Meeting of the Change Review Group (CRG) 26 October

More information

T2-T2S CONSOLIDATION BUSINESS DESCRIPTION DOCUMENT

T2-T2S CONSOLIDATION BUSINESS DESCRIPTION DOCUMENT T2-T2S CONSOLIDATION BUSINESS DESCRIPTION DOCUMENT Version: 1.0.0 Status: Final Date: 04/10/2018 Table of contents 1 INTRODUCTION... 4 1.1 Purpose of the document... 5 1.2 Structure of the document...

More information

T2/T2S Consolidation. Ancillary Systems Settlement Services. ECB DG-MIP T2/T2S Consolidation Project Team. Task Force on Future RTGS Services

T2/T2S Consolidation. Ancillary Systems Settlement Services. ECB DG-MIP T2/T2S Consolidation Project Team. Task Force on Future RTGS Services ECB DG-MIP Project Team Ancillary Systems Settlement Services Task Force on Future RTGS Services 2 nd TF meeting, 25-26 January 2017 Rubric AS Settlement 1 Objectives and scope 2 Overview of AS Settlement

More information

T2S GUI Workshop Change Summary of GUI BFD V1.6 & Outstanding Issues

T2S GUI Workshop Change Summary of GUI BFD V1.6 & Outstanding Issues 09.04.01/2011/000611 T2S GUI Workshop Change Summary of GUI BFD V1.6 & Outstanding Issues Frankfurt, 24th January 2011 T2S Project Team European Central Bank GUI BFD V1.6 Change Summary Business Object

More information

Information Guide. for TARGET2 users

Information Guide. for TARGET2 users Information Guide for TARGET2 users Version 9.0 November 2015 Information Guide for TARGET2 Users - version 9.0 1 Table of Contents INFORMATION GUIDE FOR TARGET2 USERS Information Guide for TARGET2 Users

More information

T2S financial statements for the fiscal year 2015

T2S financial statements for the fiscal year 2015 T2S financial statements for the fiscal year 2015 April 2017 T2S operating statement (in ) Notes 2015 1 Revenues 2,223,942 T2S fees charged to customers 1 2,223,942 Expenses (49,876,136) Services provided

More information

FOURTH PROGRESS REPORT ON TARGET2

FOURTH PROGRESS REPORT ON TARGET2 FOURTH PROGRESS REPORT ON TARGET2 On 20 November 2006, the Eurosystem published the third progress report on TARGET2. The report provided details of a number of pricing and legal issues (the pricing of

More information

Institute: Central Bank Date raised: 11/09/2015

Institute: Central Bank Date raised: 11/09/2015 General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: Working Group on TARGET2 (WGT2) Institute: Central Bank Date raised:

More information

T2S Penalty Mechanism

T2S Penalty Mechanism CRG meeting 28 February 2017, Frankfurt DG-Market Infrastructure and Payments European Central Bank ECB-PUBLIC 1 Table of contents 1 What is the T2S penalty mechanism? Introduction Scope/Out of scope 2

More information

Bank of Greece Securities Settlement System (BOGS)

Bank of Greece Securities Settlement System (BOGS) February 2015 Bank of Greece Securities System () T2S - Community and Business Day testing 1. INTRODUCTION This document intends to provide all participants with the necessary information required, in

More information

SETTLEMENT DAY IN T2S FOR SETTLEMENT IN NON-EURO

SETTLEMENT DAY IN T2S FOR SETTLEMENT IN NON-EURO AMI-SeCo Harmonisation Steering Group 20 June 2017 SETTLEMENT DAY IN T2S FOR SETTLEMENT IN NON-EURO 1. Background The use of a single schedule for the T2S settlement day is established by the T2S User

More information

1. Legal/business importance parameter: Critical 2. Market implementation efforts parameter: Low

1. Legal/business importance parameter: Critical 2. Market implementation efforts parameter: Low General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: CSD Steering Group (CSG) Request title: T2S should maintain and

More information

CBF Customer Simulation Period April and May 2018 Guideline

CBF Customer Simulation Period April and May 2018 Guideline CBF Customer Simulation Period April and May 2018 Guideline CBF Customer Simulation Period April and May 2018 Guideline March 2018 Document Number: 7202 This document is the property of Clearstream Banking

More information

Guideline Settlement and Securities Account Administration

Guideline Settlement and Securities Account Administration Annex 8 to the GTC of OeKB CSD Guideline Settlement and Securities Account Administration Version 1.4 June 2018 2 Table of Contents Table of Figures 6 Revision History 7 1 Introduction 8 1.1 Objective

More information

ECB-UNRESTRICTED T2/T2S CONSOLIDATION HIGH LEVEL BUSINESS CHANGES DOCUMENT

ECB-UNRESTRICTED T2/T2S CONSOLIDATION HIGH LEVEL BUSINESS CHANGES DOCUMENT T2/T2S CONSOLIDATION HIGH LEVEL BUSINESS CHANGES DOCUMENT Version: 0.0.01 Status: INITIAL BASELINE Date: 17/02/2017 Table of Contents 1 INTRODUCTION... 3 2 MODULAR APPROACH... 3 2.1 Requirements... 3 2.2

More information

Integrated central bank collateral management services

Integrated central bank collateral management services Integrated central bank collateral management services Alessandro Bonara (ECB) Richard Derksen (CCBM2 Project) Amsterdam, 21 October 2010 Table of contents 1. The Eurosystem collateral framework II. Move

More information

T2-T2S CONSOLIDATION BUSINESS DESCRIPTION DOCUMENT

T2-T2S CONSOLIDATION BUSINESS DESCRIPTION DOCUMENT T2-T2S CONSOLIDATION BUSINESS DESCRIPTION DOCUMENT Version: 0.1 Status: DRAFT Date: 16/04/2018 Table of contents 1 INTRODUCTION... 4 1.1 Purpose of the document... 5 1.2 Structure of the document... 5

More information

Target2 Securities. Monte Titoli User Requirements

Target2 Securities. Monte Titoli User Requirements Target2 Securities Monte Titoli User Requirements Contents Click here to enter text. 1. Document Management 6 1.1 Document History 6 1.2 Definitions, Acronyms and Abbreviations 6 1.3 References 7 1.4

More information

Having regard to the Treaty on the Functioning of the European Union, and in particular the first and fourth indents of Article 127(2) thereof,

Having regard to the Treaty on the Functioning of the European Union, and in particular the first and fourth indents of Article 127(2) thereof, 14.11.2017 L 295/89 DECISION (EU) 2017/2081 OF THE EUROPEAN CTRAL BANK of 10 October 2017 amending Decision ECB/2007/7 concerning the terms and conditions of TARGET2-ECB (ECB/2017/30) THE EXECUTIVE BOARD

More information

Target2- Securities Graphical User Interface. Demo Version User Guide. Version 0.1

Target2- Securities Graphical User Interface. Demo Version User Guide. Version 0.1 Target2- Securities Graphical User Interface Demo Version User Guide Version 0.1 Table of Content 1. Introduction... 1 2. T2S Demo... 2 2.1 Screen Structure...2 2.2 Menu Structure...4 2.3 Demo Scope...5

More information

DECISION (EU) [2017/XXX] OF THE EUROPEAN CENTRAL BANK. of 10 October 2017

DECISION (EU) [2017/XXX] OF THE EUROPEAN CENTRAL BANK. of 10 October 2017 EN ECB-PUBLIC DECISION (EU) [2017/XXX] OF THE EUROPEAN CENTRAL BANK of 10 October 2017 amending Decision ECB/2007/7 concerning the terms and conditions of TARGET2-ECB (ECB/2017/30) THE EXECUTIVE BOARD

More information

NBB-SSS adaptation plan to T2S First Q&A session - Intro

NBB-SSS adaptation plan to T2S First Q&A session - Intro NBB-SSS adaptation plan to T2S First Q&A session - Intro Brussels June 28 th, 2012 Luc JANSSENS Securities Unit Intro & Agenda News user committee T2S Community (see next slide) Cash side - what's new/important

More information

T2S Settlement day for non-euro

T2S Settlement day for non-euro T2S Settlement day for non-euro 2 nd AMI-SeCo meeting, agenda item 2.2 4-5 July 2017, Frankfurt George Kalogeropoulos ECB/DG-MIP/Market Integration Division 0 1 Single schedule for a settlement day in

More information

Le banquier luxembourgeois dépositaire de titres

Le banquier luxembourgeois dépositaire de titres Le banquier luxembourgeois dépositaire de titres ALJB - Michel Barbancey Clearstream Banking Executive Director Relationship Management Europe ICSD s role The International Central Securities Depositories

More information

DRAFT WORKING DOCUMENT ON TARGET2-SECURITIES THE FUNCTIONAL ARCHITECTURE

DRAFT WORKING DOCUMENT ON TARGET2-SECURITIES THE FUNCTIONAL ARCHITECTURE DG PAYMENT SYSTEMS AND MARKET INFRASTRUCTURE 19 December 2006 DRAFT WORKING DOCUMENT ON TARGET2-SECURITIES THE FUNCTIONAL ARCHITECTURE This draft working document on TARGET2-Securities (T2S) has been prepared

More information

T2S Special Series I Issue No 1 I April 2012 I T2S benefits: much more than fee reductions

T2S Special Series I Issue No 1 I April 2012 I T2S benefits: much more than fee reductions T2S Special Series I Issue No 1 I April 2012 I T2S benefits: much more than fee reductions T2S Special Series Issue No 3 January 2014 Corporate actions in T2S Author: Rosen Ivanov, T2S Programme Office,

More information

T2S AG INPUT ON THE ESMA DISCUSSION PAPER. (CSDR, Art. 6 & 7) Contents

T2S AG INPUT ON THE ESMA DISCUSSION PAPER. (CSDR, Art. 6 & 7) Contents T2S AG INPUT ON THE ESMA DISCUSSION PAPER (CSDR, Art. 6 & 7) 22 May 2014 09.04.01/2014/006159 Contents 1. General Comments... 2 2. RTS related to Settlement Discipline... 4 2.1 Measures to prevent settlement

More information

Focus Session. 13 December 2017 Paris, France

Focus Session. 13 December 2017 Paris, France Focus Session 13 December 2017 Paris, France TARGET2 and T2S consolidation - securities (T2S) perspective Mehdi Manna European Central Bank Table of contents 1 2 3 T2S governance T2S functionalities and

More information

Change Requests Backlog

Change Requests Backlog Change Requests Backlog 4CB Preliminary Assessment of Change Requests in Batch#0 CRG Meeting Agenda Topic #4 6 September 2016 Madrid 4CB Preliminary Assessment The CRG requested in its meeting on 6&7 July

More information

The participants have the possibility to determine the execution time of their transactions, through From Time and either Till Time or Reject Time.

The participants have the possibility to determine the execution time of their transactions, through From Time and either Till Time or Reject Time. RTGS UDFS Deviations from the URD Section in UDFS Section in URD URD ID URD Text Deviation Reason for deviation 5.1.3 1.2.3.3 RTGS.TR.HVP.PAYT.3 RTGS.TR.HVP.PAYT.3.2 SHRD.UR.BDD.1 The participants have

More information

Information guide. for TARGET2 users

Information guide. for TARGET2 users Information guide for TARGET2 users Version 5.0 November 2011 1 WGT2/2011/095rev2; PSSC/2011/448 Table of contents Information guide for TARGET2 users Table of contents 1. INTRODUCTION... 6 1.1. WHAT IS

More information

Infosession TIPS: Target Instant Payments Settlement. 3 February Infosession TIPS: Target Instant Payments Settlement 3.02.

Infosession TIPS: Target Instant Payments Settlement. 3 February Infosession TIPS: Target Instant Payments Settlement 3.02. Infosession : Target Instant Payments Settlement 3 February 2017 Infosession : Target Instant Payments Settlement 3.02.2017 1 On the agenda for today 10:00-10:15 Introduction : Target Instant Payments

More information

1. Legal/business importance parameter: Medium 2. Market implementation efforts parameter: Medium

1. Legal/business importance parameter: Medium 2. Market implementation efforts parameter: Medium General Information (Origin of Request) User Requirements (URD) Other User Functional or Technical Documentation (SYS) Request raised by: NBB-SSS Institute: CSD Date raised: 03/03/2016 Request title: T2S

More information

Reform of the registration, clearing and settlement system and its adaptation to Target 2 Securities.

Reform of the registration, clearing and settlement system and its adaptation to Target 2 Securities. Reform of the registration, clearing and settlement system and its adaptation to Target 2 Securities. AGENDA 1. CURRENT STATUS 2. PRINCIPLES OF THE REFORM 3. PRINCIPLES OF T2S 4. FINAL SETUP 5. TIMETABLE

More information

T2-T2S CONSOLIDATION USER REQUIREMENTS DOCUMENT T2 - RTGS COMPONENTFUTURE RTGS (RTGS) FOR

T2-T2S CONSOLIDATION USER REQUIREMENTS DOCUMENT T2 - RTGS COMPONENTFUTURE RTGS (RTGS) FOR T2-T2S CONSOLIDATION USER REQUIREMENTS DOCUMENT FOR T2 - RTGS COMPONENTFUTURE RTGS (RTGS) Version: 1.1.2 Status: DRAFT Date: xx/xx/2018 Contents 1 HIGH VALUE PAYMENTS SETTLEMENT (HVP)... 4 1.1 Overview...

More information

USER REQUIREMENTS CHAPTER 5 LIFECYCLE MANAGEMENT AND MATCHING REQUIREMENTS

USER REQUIREMENTS CHAPTER 5 LIFECYCLE MANAGEMENT AND MATCHING REQUIREMENTS USER REQUIREMENTS CHAPTER 5 LIFECYCLE MANAGEMENT AND MATCHING REQUIREMENTS T2S project Team Reference: T2S-07-0355 Date: 15 November 2007 Version: 1 Status: Final TABLE OF CONTENT 5 Lifecycle Management

More information

TARGET2- Suomen Pankki

TARGET2- Suomen Pankki RULES ON AUTO-COLLATERALISATION OPERATIONS Definitions For the purposes of these Rules the following definitions apply: 1. auto-collateralisation means intraday credit granted by the euro area national

More information

Final Migration Weekend Dress Rehearsal (MWDR) Process Description & Overview on Reports

Final Migration Weekend Dress Rehearsal (MWDR) Process Description & Overview on Reports Final Migration Weekend Dress Rehearsal (MWDR) 1 Introduction In preparation of the introduction of T2S wave 4 in February 2017, Eurex Clearing will participate in the final migration weekend dress rehearsal

More information

Gergely Koczan Potential benefits and challenges of taking collateral for Eurosystem credit operations in T2S

Gergely Koczan Potential benefits and challenges of taking collateral for Eurosystem credit operations in T2S Gergely Koczan Potential benefits and challenges of taking collateral for Eurosystem credit operations in T2S AMI-SeCo Workshop on Eurosystem deliberations on taking collateral 11 May 2017, Madrid Rubric

More information

NEWSLETTERMAY FOR MEMBERS OF CDCP. Significant Changes in the Certification of Members!

NEWSLETTERMAY FOR MEMBERS OF CDCP. Significant Changes in the Certification of Members! NEWSLETTERMAY FOR MEMBERS OF CDCP www.cdcp.sk 216 Significant Changes in the Certification of Members! With regard to transition to Target 2-Securities (T2S) system the Central Securities Depository of

More information

Integrated central bank collateral management services

Integrated central bank collateral management services Integrated central bank collateral management services Alessandro Bonara (ECB) Richard Derksen (DNB/CCBM2 Project) Cogesi, 22 November 2010 1 What s coming up Move towards integrated collateral management

More information

T2S financial statements for the fiscal year 2016

T2S financial statements for the fiscal year 2016 T2S financial statements for the fiscal year 2016 December 2017 (updated in May 2018) T2S operating statement (amounts in ) Notes 2016 2015 1 Revenues 1 15,316,323 2,223,942 T2S fees charged to customers

More information

DIRECTIVE NO 6. in terms of the CENTRAL BANK OF MALTA ACT (CAP. 204)

DIRECTIVE NO 6. in terms of the CENTRAL BANK OF MALTA ACT (CAP. 204) CENTRAL BANK OF MALTA DIRECTIVE NO 6 in terms of the CENTRAL BANK OF MALTA ACT (CAP. 204) HARMONISED CONDITIONS FOR OPENING AND OPERATING PAYMENTS MODULE ACCOUNTS AND DEDICATED CASH ACCOUNTS IN TARGET2-MALTA

More information

Migration to TARGET2-BE : introduction

Migration to TARGET2-BE : introduction Migration to TARGET2-BE : introduction May 2016 Sophie HELBIG Payments and securities Agenda TARGET 2 : basics Current situation Future situation Steps to open a PM account Timeline of the project Decisions

More information

CR raised by: T2S Project Team Institute: ECB Date raised: 15/09/08

CR raised by: T2S Project Team Institute: ECB Date raised: 15/09/08 09.04.01/2009/001863 CR raised by: T2S Project Team Institute: ECB Date raised: 15/09/08 Change Request title: Unmatched messages No further information CR ref. no: T2S URD 0007 (T2S-URD V4-CLA-07) Change

More information

TARGET2-Securities The Pre-project Phase

TARGET2-Securities The Pre-project Phase TARGET2-Securities The Pre-project Phase Jean-Michel Godeffroy ECB, Director General Payment Systems and Market Infrastructure Meeting with representatives of market participants and market infrastructures

More information

DECISION OF THE EUROPEAN CENTRAL BANK

DECISION OF THE EUROPEAN CENTRAL BANK L 134/22 Official Journal of the European Union 21.5.2011 DECISIONS DECISION OF THE EUROPEAN CENTRAL BANK of 20 April 2011 on the selection of TARGET2-Securities network service providers (ECB/2011/5)

More information

T2S auto-collateralisation

T2S auto-collateralisation T2S auto-collateralisation Brussels, 7 June 2012 Yvan TIMMERMANS T2S BENUG Chairman What is auto-collateralisation? Intraday credit operation triggered when a buyer lacks funds for settling a securities

More information

AMENDMENTS THE CENTRAL SECURITIES DEPOSITORY RULES AND CORRESPONDING INSTRUCTIONS

AMENDMENTS THE CENTRAL SECURITIES DEPOSITORY RULES AND CORRESPONDING INSTRUCTIONS AMENDMENTS THE CENTRAL SECURITIES DEPOSITORY RULES AND CORRESPONDING INSTRUCTIONS By resolution n. 19606 of the 11 th May 2016 CONSOB approved in agreement with Banca d Italia the amendments to the Rules

More information

Service Description in connection with the Introduction of TCS BaNCS System

Service Description in connection with the Introduction of TCS BaNCS System Service Description in connection with the Introduction of TCS BaNCS System V11.00.01-250826/09051/2017 INTRODUCTION... 5 1. MASTER DATA... 7 1.1. CLIENTS... 7 1.1.1. KELER code... 7 1.1.2. Access to T2S

More information

Minutes from the Joint Nordic-Baltic T2S NUG meeting hosted by the Riksbank in Stockholm 19 January 2010

Minutes from the Joint Nordic-Baltic T2S NUG meeting hosted by the Riksbank in Stockholm 19 January 2010 2010-02-05/BG Minutes from the Joint Nordic-Baltic T2S NUG meeting hosted by the Riksbank in Stockholm 19 January 2010 1) Chairman's introduction (Mats Wallinder) The chairman welcomed all participants

More information

T2S Migration Workshop

T2S Migration Workshop T2S Migration Workshop February 3, 2016 INTERBOLSA. All Rights Reserved. Agenda 1. T2S Project Status 2. Interbolsa Migration Plan Overview Pre-Migration Migration Weekend 3. Contingency Plan 4. Communication

More information

The future of market infrastructure: what s on the ECB agenda?

The future of market infrastructure: what s on the ECB agenda? Marc Bayle de Jessé Director General Market Infrastructure & Payments The future of market infrastructure: what s on the ECB agenda? ESCB Social Dialogue Frankfurt, 16 March 2017 Rubric Introduction The

More information

DCP AUTHORIZATION TEST CASES T2S PROJECT

DCP AUTHORIZATION TEST CASES T2S PROJECT DCP AUTHORIZATION TEST CASES T2S PROJECT Version 4.1 REVIEW dated 6 th July 2015 1 Target2 Securities - DCP AUTHORIZATION TEST v. 4.1 Review [T2S 208] Contents 1 DOCUMENT MANAGEMENT 5 1.1 Document History

More information

Collateral Management Harmonisation Activities (CMHAs)

Collateral Management Harmonisation Activities (CMHAs) Agenda item 3 Collateral Management Harmonisation Activities (CMHAs) Proposal for CMHAs of AMI-SECO. CMH TF meeting of 24 August 2017 Rubric Proposal for Collateral Management Harmonisation Activities

More information