Item. Metro Contingency and Risk Management

Size: px
Start display at page:

Download "Item. Metro Contingency and Risk Management"

Transcription

1 Item Metro Contingency and Risk Management April 19, 2012

2 Background SAFETEA-LU requires in Section 5309(d)4(A)i: The proposed [Grantee] project plan provides for the availability of contingency amounts that FTA determines to be reasonable to cover unanticipated cost increases 2

3 Metro Contingency and Risk Management Policies Applies to all Metro capital projects Consistent with Federal Guidelines Has been successfully used on Metro projects Contingency policy last presented to Construction Committee in June

4 Project Risk Project risk is the likelihood that a project outcome will vary from its original goal Goals are usually categorized as scope, cost and time Rarely does a project conclude with meeting all of its original goals; this indicates that risk exists in all projects Project risk is the sum of virtually an infinite number of possible events 4

5 Types of Risk DESIGN RISK Associated with the performance and variability of design-related activities MARKET RISK Effects of open market pricing of goods and services, as well as contract packaging strategies CONSTRUCTION RISK Related to the inevitable variability of project environment, including items such as weather, subsurface conditions and contractor performance 5

6 Elements of Risk Examples Include: Complexity of Project Completeness of Design Constructability Geotechnical Conditions Schedule System Integration Third Party Approvals Acts of God

7 Risk Mitigation Strategies Risk Avoidance Risk Transfer Risk Reduction Risk Acceptance 7

8 Risk Management Process Identifying risk situations for which outcomes are likely to vary in amounts that may significantly affect the project s goals Assessing the likelihood and magnitude of such variance Responding by developing plans for minimizing hazard and maximizing gain Managing the execution of those plans 8

9 Certainty and Uncertainty No Information Partial Information Complete Information Unknown unknowns Known Unknowns Knowns Scope of project risk assessment Total Uncertainty General Uncertainty Specific Uncertainty Total Certainty 9

10 Risk Review Project is re-evaluated at various phases of development to forecast potential risk reduction Alternatives Analysis Preliminary Engineering Final Design Procurement Construction Testing & Start-up Pre-revenue Operations Project Development Project Construction Operations Arrows indicate when a major risk review may occur 10

11 Cost Contingency Targets Percent Preliminary Engineering Phase Final Design Phase FFGA Award 100% Bid 50% Construction 11

12 Schedule Contingency FTA has established criteria for suggested minimum schedule contingency levels The targeted amount of schedule contingency, for the project as a whole, is 20% of the time from the start of final design to the start of revenue operations 12

13 Crenshaw/LAX Project Risk Management Geotechnical Risks for Design-Build Procurement Metro undertakes extensive soil boring program Metro establishes detailed performance requirements with well established monitoring and instrumentation procedures Independent evaluation by Tunnel Advisory Panel PE design development phase carries geotechnical analysis to a greater level compared to other disciplines. Metro establishes base line for assumptions and assumes responsibility for changed conditions 13

14 Crenshaw/LAX Project Other Risk Management Techniques Conduct formal risk assessments at prescribed intervals throughout design and construction phases Prepare a Risk Contingency Management Plan updated monthly Contractors participate in risk assessments during construction phase Integrated Project Management Office with colocation of key personnel Resolution of issues at lowest level of organizations with escalation ladder 14

Federal Transit Administration United States Department of Transportation Washington, DC 20590

Federal Transit Administration United States Department of Transportation Washington, DC 20590 Discrete Distributions Probability 0.3 0.25 0.2 0.15 0.1 0.05 0 1 2 3 4 5 Time (mos) (days) or Costs ($000) Project Cost, Mitigated and Opportunities Realized PROBABILITY Project Cost, Unmitigated PROJECT

More information

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS Identify, Quantify, and 237 217 200 237 217 200 Manage 237 217 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 80 119 27 252 174.59 110 135 120 112

More information

Risk Management for Tunnel Planning, Design and Construction

Risk Management for Tunnel Planning, Design and Construction ALDEA SERVICES Risk Management for Tunnel Planning, Design and Construction Robert J F Goodfellow, P.E. Senior Vice President August 14, 2017 UNIVERSAL LAWS OF TUNNELING Major Tunnel Project? DON T TAKE

More information

Major Projects Advisory Project Leadership Series

Major Projects Advisory Project Leadership Series KPMG GLOBAL ENERGY INSTITUTE Major Projects Advisory Project Leadership Series February 7, 2013 Disclaimer The information contained herein is of a general nature and is not intended to address the circumstances

More information

A Study on Risk Analysis in Construction Project

A Study on Risk Analysis in Construction Project A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------

More information

KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects

KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects KPMG Global Energy Institute KPMG International KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects Construction projects

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER. Pre-Construction and Construction Phase Services

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER. Pre-Construction and Construction Phase Services AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER Pre-Construction and Construction Phase Services FP&M Project No, CP00Error! Bookmark not defined. AGREEMENT made by and between the Board of Regents, State

More information

Differing Site Conditions: Problems in Hiding Scott Lowe, Trauner Consulting Services, Inc.

Differing Site Conditions: Problems in Hiding Scott Lowe, Trauner Consulting Services, Inc. Differing Site Conditions: Problems in Hiding Scott Lowe, Trauner Consulting Services, Inc. August 10, 2015 Scott Lowe, P.E. Principal, Trauner Consulting Services 30 years experience Professional Engineer

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany RISK MANAGEMENT LECTURE 5 Ahmed Elyamany 1 RISK SECTION OBJECTIVES Introduce the students to the concepts of risk management and the different tools to analyze risk and estimate time and cost contingencies.

More information

DURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017

DURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017 DURHAM-ORANGE LIGHT RAIL TRANSIT PROJECT FINANCIAL RISKS AND MITIGATION STRATEGIES APRIL 2017 There are several financial risks to the 2017 County Transit Plans (Plans) that could arise at different times

More information

APPROVE REVISIONS TO TRANSIT PROJECT CONTINGENCY POLICY

APPROVE REVISIONS TO TRANSIT PROJECT CONTINGENCY POLICY One Gateway Plaza 213.922.2000 Los Angeles. CA 90012-2952 metro.net 8 FINANCE, BUDGET AND AUDIT COMMITTEE SEPTEMBER 19, 2012 CONSTRUCTION COMMITTEE SEPTEMBER 20, 2012 SUBJECT: ACTION: TRANSIT PROJECT CONTINGENCY

More information

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.) Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

INTRODUCTION TO RISK MANAGEMENT FOR CONSTRUCTION PROJECTS. Prof. Reda Abdulaal Vice Presidency for Projects

INTRODUCTION TO RISK MANAGEMENT FOR CONSTRUCTION PROJECTS. Prof. Reda Abdulaal Vice Presidency for Projects INTRODUCTION TO RISK MANAGEMENT FOR CONSTRUCTION PROJECTS Prof. Reda Abdulaal Vice Presidency for Projects December 2009 Objectives & Outcomes of this Presentation December 2009 Introduction to Risk Managment

More information

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk

More information

CEVP Cost Estimate Validation Process

CEVP Cost Estimate Validation Process CEVP Cost Estimate Validation Process CSVA Conference 2004 Monica Bielenberg, P.E. Program Manager Why an Estimate is Not a Number Estimates are uncertain... Ultimate project cost and schedule cannot be

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

6 th September not protectively marked 1

6 th September not protectively marked 1 Establishing Risk Management processes in UK Nuclear New Build - (inc Enterprise Risk Management & Probabilistic Cost & Schedule Risk Analysis processes) 6 th September 2016 not protectively marked 1 Introductions

More information

Metropolitan Council. May 30, 2018

Metropolitan Council. May 30, 2018 Metropolitan Council May 30, 2018 1 Today s Topics Revised Project Budget and Schedule Third Amendment to Cooperative Funding Agreement with HCRRA Fourth Amendment to 2017 CTIB Capital Grant Agreement

More information

USF System Compliance & Ethics Program. Risk Assessment Process. Enterprise-Wide Risk Assessment

USF System Compliance & Ethics Program. Risk Assessment Process. Enterprise-Wide Risk Assessment USF System Compliance & Ethics Program Risk Assessment Process Enterprise-Wide Risk Assessment Risk Assessment Process Risk Assessment: A disciplined, documented, and ongoing process of identifying and

More information

PN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS

PN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS PN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS 101.01 On page 1, Add the following: NOTE: The fact that the bid items for this Design-Build project are general rather than

More information

MANITOBA HYDRO 2017/18 & 2018/19 GENERAL RATE APPLICATION PUB INFORMATION REQUESTS MGF'S RESPONSES

MANITOBA HYDRO 2017/18 & 2018/19 GENERAL RATE APPLICATION PUB INFORMATION REQUESTS MGF'S RESPONSES MGF'S RESPONSES PUB/MGF - 1 Reference: MGF Report Page 1 Please identify and explain the factors that have resulted in productivity not meeting the assumptions in the original General Civil Contract The

More information

Project Management. A Practitioner s Guide. Steven M. Bragg

Project Management. A Practitioner s Guide. Steven M. Bragg Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project

More information

Risk Allocation in Underground Construction and the Benefits of the ECI/Portland Model Approach

Risk Allocation in Underground Construction and the Benefits of the ECI/Portland Model Approach Risk Allocation in Underground Construction and the Benefits of the ECI/Portland Model Approach Matt Swinton David A. Hecker Kiewit Infrastructure Group David A. Hecker Kiewit Corporation Group General

More information

AIA Document A133 TM 2009

AIA Document A133 TM 2009 AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

More information

Project Change Management. The Origins of Change

Project Change Management. The Origins of Change Project Change Management The Origins of Change The Reality Despite the best of intentions, thoughtful planning, and early recognition of and mitigation of risks to a project change will occur. This change

More information

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE 602-778-7324 brian.bombardier@hdrinc.com 2015 HDR, Inc., all rights reserved. Addressing Cost and

More information

Chapter 9 Financial Considerations. 9.1 Introduction

Chapter 9 Financial Considerations. 9.1 Introduction 9.1 Introduction Chapter 9 This chapter presents anticipated costs, revenues, and funding for the NEPA BART Extension Alternative. A summary of VTA s financial plan for the BART Extension Alternative is

More information

Procurement models for District Energy System Projects

Procurement models for District Energy System Projects Procurement models for District Energy System Projects IDEA Conference Presented by Tomasz Smetny-Sowa, Senior Director Energy Services Acquisition Program June 13, 2018 Real Property Services Branch Public

More information

The Foreseeability of Unforeseen Geologic Conditions

The Foreseeability of Unforeseen Geologic Conditions The Foreseeability of Unforeseen Geologic Conditions by Benjamin T. Benumof, Ph.D., Associate* Despite the growing sophistication of construction contracts, unforeseen or differing site conditions disputes

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 42 Program Management Project Budget and Schedule Status October 20 2011 Project Schedules* Project 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Expo Phase I Orange Line Extension

More information

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual

Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Project No. 9574-2018 Issued 7/19/2017 Washington State University Facility Services, Capital Terre View Research

More information

The Engineers Joint Contract Documents Committee Releases 2013 editions of the EJCDC Construction Series (C-Series) documents

The Engineers Joint Contract Documents Committee Releases 2013 editions of the EJCDC Construction Series (C-Series) documents FOR IMMEDIATE RELEASE The Engineers Joint Contract Documents Committee Releases 2013 editions of the EJCDC Construction Series (C-Series) documents ALEXANDRIA, Va., March 25, 2013 The Engineers Joint Contract

More information

Metropolitan Transportation Authority: East Side Access Cost Overruns

Metropolitan Transportation Authority: East Side Access Cost Overruns Metropolitan Transportation Authority: East Side Access Cost Overruns Thomas P. DiNapoli New York State Comptroller Kenneth B. Bleiwas Deputy Comptroller Report 12-2013 March 2013 Highlights East Side

More information

CITY OF SASKATOON COUNCIL POLICY

CITY OF SASKATOON COUNCIL POLICY ORIGIN/AUTHORITY Clause F1, Administrative Report No. 15-2001; Clause B1, Legislative Report No. 16-2004; Item 5b), Matters Requiring Public Notice December 3, 2007; Item 4a), Matters Requiring Public

More information

RISK MANAGEMENT for Public-Private Partnership Projects

RISK MANAGEMENT for Public-Private Partnership Projects Lenders Technical Advisor s Role in and Approach to RISK MANAGEMENT for Public-Private Partnership Projects CONTENTS 3 Introduction 4 Risk Identification 6 Risk Management and Mitigation 7 Risk Allocation

More information

Risk Assessment of the Niagara Tunnel Project

Risk Assessment of the Niagara Tunnel Project Canadian Society of Value Analysis October 24, 2006 Risk Assessment of the Presented by: David Eden, P. Eng., Ontario Power Generation Susan Sherman, P.Eng.,URS Canada Inc Overview Qualitative Risk Analysis

More information

Risk Management Guideline July, 2017

Risk Management Guideline July, 2017 Risk Management Guideline July, 2017 Check the Capital Project Delivery website to ensure this is the current version. Table of Contents PREFACE... 1 SECTION OVERVIEW... 1 SECTION 1 - INTRODUCTION... 2

More information

Corridor Management Committee. May 6, 2015

Corridor Management Committee. May 6, 2015 Corridor Management Committee May 6, 2015 1 Today s Topics Project Budget and Schedule Update Project Options Work Plan Upcoming Meeting Schedule 2 Project Budget and Schedule Update 3 Project Updates:

More information

What Lies Underneath: A Guide to Differing Site Conditions. Ryan Klein (719)

What Lies Underneath: A Guide to Differing Site Conditions. Ryan Klein (719) What Lies Underneath: A Guide to Differing Site Conditions Ryan Klein rklein@shermanhoward.com (719) 448-4028 What are Differing Site Conditions? Photo: Raiders of the Lost Ark (1981) Definition of Differing

More information

Constellation Energy Comments on Proposed OTC Reforms

Constellation Energy Comments on Proposed OTC Reforms Constellation Energy Comments on Proposed OTC Reforms Constellation Energy Key Facts Constellation Energy is a Fortune 500 company (#125 on the 2009 list). Over 26,500 MW 2008 peak load served to retail

More information

Finance Committee. Inquiry into methods of funding capital investment projects. Submission from PPP Forum

Finance Committee. Inquiry into methods of funding capital investment projects. Submission from PPP Forum About Finance Committee Inquiry into methods of funding capital investment projects Submission from Established in 2001, the is an industry body representing over 110 private sector companies involved

More information

UPDATED IAA EDUCATION SYLLABUS

UPDATED IAA EDUCATION SYLLABUS II. UPDATED IAA EDUCATION SYLLABUS A. Supporting Learning Areas 1. STATISTICS Aim: To enable students to apply core statistical techniques to actuarial applications in insurance, pensions and emerging

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

Document C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser

Document C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser Document C132 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Adviser AGREEMENT made as of the 14th day of July in the year 2014 (In words, indicate day, month and year.) BETWEEN

More information

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner: Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT - PRELIMINARY ENGINEERING OPTION II

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT - PRELIMINARY ENGINEERING OPTION II One Gateway Plaza Los Angeles. CA 90012-295; 16 MEASURE R PROJECT DELIVERY COMMITTEE SEPTEMBER 16, 2010 SUBJECT: ACTION: CRENSHAW/LAX TRANSIT CORRIDOR PROJECT - PRELIMINARY ENGINEERING OPTION II APPROVE

More information

Improving the Procurement Process Unbalanced Bids

Improving the Procurement Process Unbalanced Bids STAFF REPORT ACTION REQUIRED Improving the Procurement Process Unbalanced Bids Date: January 10, 2007 To: From: Wards: Audit Committee Jeff Griffiths, Auditor General All Reference Number: SUMMARY During

More information

Risk Analysis and Strategic Evaluation of Procurement Process in Construction

Risk Analysis and Strategic Evaluation of Procurement Process in Construction Risk Analysis and Strategic Evaluation of Procurement Process in Construction Sharayu P. Pawar 1, Dr. M.N.Bajad 2, Prof. Mr. R.D. Shinde 3 1PG Student (Construction Management), RMD Sinhgad College of

More information

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Consultant s Report Project Number: 49166-001 People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Public Private Partnerships: Management

More information

BEST PRACTICE IN COST ESTIMATION. Presentation by : Dr.-Ing Chris Mbatha

BEST PRACTICE IN COST ESTIMATION. Presentation by : Dr.-Ing Chris Mbatha BEST PRACTICE IN COST ESTIMATION Presentation by : Dr.-Ing Chris Mbatha OBJECTIVE The attendee will be able to: Describe a unit price bid Decide when and where the different types of estimates are used

More information

DENVER BOARD OF WATER COMMISSIONERS. Briefing Paper for Gross Reservoir Expansion 2018 Budget Update

DENVER BOARD OF WATER COMMISSIONERS. Briefing Paper for Gross Reservoir Expansion 2018 Budget Update DENVER BOARD OF WATER COMMISSIONERS Meeting Date: December 13, 2017 Board Item: V-A-2 Briefing Paper for Gross Reservoir Expansion 2018 Budget Update Strategic Plan Alignment Lenses: Customer Centric Industry

More information

STOCKTON UNIVERSITY POLICY. Employees Covered All University financing activities.

STOCKTON UNIVERSITY POLICY. Employees Covered All University financing activities. STOCKTON UNIVERSITY POLICY Debt Management Policy Policy Administrator: Associate Vice President for Administration and Finance Authority: N.J.S.A. 18A:64-6 Effective Date: February 15, 2006; November

More information

Budget Discussion. July 2009 Citizens Advisory Committee

Budget Discussion. July 2009 Citizens Advisory Committee Budget Discussion July 2009 Citizens Advisory Committee Budget presentation How did TriMet arrive at the LPA budget How are estimates developed How are we tracking changes How are we doing with the budget

More information

Canacol Energy Ltd. Announces Conventional Natural Gas Prospective Resources

Canacol Energy Ltd. Announces Conventional Natural Gas Prospective Resources Canacol Energy Ltd. Announces Conventional Natural Gas Prospective Resources CALGARY, ALBERTA (April 11, 2017) Canacol Energy Ltd. ( Canacol or the Corporation ) (TSX: CNE; OTCQX: CNNEF; BVC: CNEC) is

More information

Risk Management Policy

Risk Management Policy Risk Management Policy April 2017 1 Introduction 1.1 The primary objective of risk management is to ensure that the risks facing the business are appropriately managed. 1.2 Force is committed to ensuring

More information

Executive Change Control Board. January 15, 2016

Executive Change Control Board. January 15, 2016 Executive Change Control Board January 15, 2016 1 Today s Topics Review In Kind Land Transfer (Action) Review Project Schedule Review Project Cost Estimate at 60% Design Review Project Scope (Action) Next

More information

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk Management Preconstruction & Construction Managing Construction

More information

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2009 SESSION LAW SENATE BILL 836

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2009 SESSION LAW SENATE BILL 836 GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2009 SESSION LAW 2010-179 SENATE BILL 836 AN ACT TO: (1) CLARIFY LIABILITY FOR DAMAGES CAUSED BY THE DISCHARGE OF NATURAL GAS, OIL, OR DRILLING WASTE INTO STATE

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

Joint Report of the Transportation and Management Committees For the Special Metropolitan Council meeting of May 30, 2018

Joint Report of the Transportation and Management Committees For the Special Metropolitan Council meeting of May 30, 2018 Committee Report Business Item No. 2018-127 Joint Report of the Transportation and Management Committees For the Special Metropolitan Council meeting of May 30, 2018 Subject: Southwest Light Rail Transit

More information

Policy 3-205: Remodeling and Construction Policy

Policy 3-205: Remodeling and Construction Policy Policy 3-205: Remodeling and Construction Policy I. Purpose To provide for the planning, funding, approval, design and completion of remodeling and construction projects. These policies and Procedures

More information

Ms. Laurel Ross, Acting Commission Secretary and Director

Ms. Laurel Ross, Acting Commission Secretary and Director Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

IFRS Fair Value Measurement. Credibility. Professionalism. AccountAbility

IFRS Fair Value Measurement. Credibility. Professionalism. AccountAbility IFRS 13 13 Fair Value Measurement Credibility. Professionalism. AccountAbility Agenda Objective Scope Definitions Measurement Disclosure Objective of IFRS 13 The IFRS applies to IFRSs that require or permit

More information

Purchasing Policy. Jefferson Transit Authority. January 1, Replacing JTA Procurement Policy (Resolution#15-06) Jefferson Transit Authority

Purchasing Policy. Jefferson Transit Authority. January 1, Replacing JTA Procurement Policy (Resolution#15-06) Jefferson Transit Authority January 1, 2017 Replacing JTA Procurement Policy (Resolution#15-06) Effective Date 1/1/2017 Table of Contents Procurement Policy Overview and Purpose... 1 Section 1: Objectives... 1 Section 2: Scope...

More information

Memorandum. Date: RE: Citizens Advisory Committee

Memorandum. Date: RE: Citizens Advisory Committee Memorandum Date: 03.04.2010 RE: Citizens Advisory Committee March 10, 2010 To: From: Subject: Summary Citizens Advisory Committee Maria Lombardo Chief Deputy Director for Policy and Programming Lee Saage

More information

COSTING AND PROJECT EVALUATION USING NODOC

COSTING AND PROJECT EVALUATION USING NODOC COSTING AND PROJECT EVALUATION USING NODOC Three types of Capital cost estimates 1- Preliminary (approximate) estimates 2- Authorization (Budgeting) estimates 3- Detailed (Quotation) estimates 1- Preliminary

More information

AIA Document A133 TM 2009

AIA Document A133 TM 2009 AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

More information

Document C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser

Document C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser Document C132 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Adviser AGREEMENT made as of the day of in the year Two Thousand Sixteen (In words, indicate day, month and year.)

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

Risk Analysis and Management. May 2011 ISO 14971

Risk Analysis and Management. May 2011 ISO 14971 Risk Analysis and Management Qsite May 2011 ISO 14971 1 Agenda Definitions Risk Management Development Phases Process Hazards Evaluation Residual Risk 2 Why Do We Need Risk Analysis 1. Quantify the risk

More information

Banca IMI Securities Corp.

Banca IMI Securities Corp. Statement of Financial Condition December 31, 2015 Filed as PUBLIC information pursuant to Rule 17a-5(d) under the Securities Exchange Act of 1934. Contents Report of Independent Registered Public Accounting

More information

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP Project Management for the Professional Professional Part 3 - Risk Analysis Michael Bevis, JD CPPO, CPSM, PMP What is a Risk? A risk is an uncertain event or condition that, if it occurs, has a positive

More information

8. FINANCIAL ANALYSIS

8. FINANCIAL ANALYSIS 8. FINANCIAL ANALYSIS This chapter presents the financial analysis conducted for the Locally Preferred Alternative (LPA) selected by the Metropolitan Transit Authority of Harris County (METRO) for the.

More information

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc. Value for Money Analysis: Choosing the Best Project Delivery Method Ken L. Smith, PE, CVS -HDR Engineering, Inc. 1 Overview What is a VfM analysis Why is it used Key VfM components and principles Life

More information

AIA Document A133 TM 2009

AIA Document A133 TM 2009 AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

More information

THE CORPORATION OF THE CITY OF WINDSOR POLICY

THE CORPORATION OF THE CITY OF WINDSOR POLICY THE CORPORATION OF THE CITY OF WINDSOR POLICY Service Area: Office of the Chief Administrative Officer Policy No.: CR252/2014 Department: Approval Date: October 6, 2014 Division: Corporate Initiatives

More information

CONSTRUCTION MANAGER AGREEMENT BETWEEN THE UNIVERSITY OF ROCHESTER AND. Insert CM Firm. Insert Name of Project. Insert Project Number

CONSTRUCTION MANAGER AGREEMENT BETWEEN THE UNIVERSITY OF ROCHESTER AND. Insert CM Firm. Insert Name of Project. Insert Project Number CONSTRUCTION MANAGER AGREEMENT BETWEEN THE UNIVERSITY OF ROCHESTER AND Insert CM Firm Insert Name of Project Insert Project Number University of Rochester Planning and Project Management 271 East River

More information

Virginia Department of Transportation. Midtown Tunnel Project. Updated Finance Plan Supplement. February 2013

Virginia Department of Transportation. Midtown Tunnel Project. Updated Finance Plan Supplement. February 2013 Virginia Department of Transportation Midtown Tunnel Project Updated Finance Plan Supplement February 2013 1. Project Overview The Downtown Tunnel/Midtown Tunnel/MLK Extension Project located in the cities

More information

Request for Proposal For Design Engineering Services. Northwest Lansing Relief Sewer Project

Request for Proposal For Design Engineering Services. Northwest Lansing Relief Sewer Project Request for Proposal For Design Engineering Services City of Lansing, Kansas Wastewater Utility Department 800 First Terrace Lansing, Kansas 66043 February 14, 2018 Page 1 of 14 A. INTRODUCTION The City

More information

SOUND TRANSIT STAFF REPORT RESOLUTION NO. R NE 40th Street Overlake Transit Center/Park-and-Ride Lot Project Budget Amendment

SOUND TRANSIT STAFF REPORT RESOLUTION NO. R NE 40th Street Overlake Transit Center/Park-and-Ride Lot Project Budget Amendment SOUND TRANSIT STAFF REPORT RESOLUTION NO. R2002-01 NE 40th Street Overlake Transit Center/Park-and-Ride Lot Project Budget Amendment Meeting: Date: Type of Action: Staff Contact: Phone: Board 2/14/02 Discussion/Possible

More information

Measuring the Amount of Asymmetric Information in the Foreign Exchange Market

Measuring the Amount of Asymmetric Information in the Foreign Exchange Market Measuring the Amount of Asymmetric Information in the Foreign Exchange Market Esen Onur 1 and Ufuk Devrim Demirel 2 September 2009 VERY PRELIMINARY & INCOMPLETE PLEASE DO NOT CITE WITHOUT AUTHORS PERMISSION

More information

Construction Project Management from the Owner s Perspective

Construction Project Management from the Owner s Perspective Construction Project Management from the Owner s Perspective Presented at: IMUA 2013 Annual Meeting May 21, 2013 Page 1 Agenda Introduction to Risk Management Risk through the Project Life Cycle Project

More information

Toronto Transit Projects April 25, Jack Collins Vice President, Rapid Transit Implementation

Toronto Transit Projects April 25, Jack Collins Vice President, Rapid Transit Implementation Toronto Transit Projects April 25, 2012 Jack Collins Vice President, Rapid Transit Implementation 1 Outline Overall Direction Evaluation Principles City Council Motions Toronto Plan Evaluation against

More information

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved. Addressing Cost and Schedule Concerns Usual Questions Analysis Needs

More information

The Edna McConnell Clark Foundation. Consolidated Financial Report September 30, 2015 and 2014

The Edna McConnell Clark Foundation. Consolidated Financial Report September 30, 2015 and 2014 The Edna McConnell Clark Foundation Consolidated Financial Report September 30, 2015 and 2014 Contents Independent auditor s report 1-2 Financial statements Consolidated statements of financial position

More information

Updated Financial Analysis Final Draft

Updated Financial Analysis Final Draft Solar Market Pathways: San Francisco Solar and Storage for Resilience Project December 2017 Final Draft Important Notice This report was prepared by Arup North America Ltd. ( Arup ) in its capacity as

More information

Presented By: Steve Cohen, Executive VP Sabadell United Bank

Presented By: Steve Cohen, Executive VP Sabadell United Bank Presented By: Steve Cohen, Executive VP Sabadell United Bank Plentiful Cheap Loose? Commercial Bank failures 465 during The Great Recession Primary cause Real Estate sector ADC considered the most risky

More information

CONSISTENCY IN CONTRACT DEFAULT PROCESS

CONSISTENCY IN CONTRACT DEFAULT PROCESS CONSISTENCY IN CONTRACT DEFAULT PROCESS Joe S. Graff, P.E., Director Construction Section, CST 10/10/17 Presentation Outline 1 2 Defaults A Necessary evil. Default Considerations 3 Default Process 4 5

More information

ADDENDUM NO. 1 TO CONTRACT DOCUMENTS

ADDENDUM NO. 1 TO CONTRACT DOCUMENTS ADDENDUM NO. 1 TO CONTRACT DOCUMENTS Project: Owner: Contract No.: RFP NO. 199 CENTRAL LANDFILL PUMP STATION #3 RETROFIT PROJECT RHODE ISLAND RESOURCE RECOVERY CORPORATION Project No.: 11119271 Date: MAY

More information

PUBLIC-PRIVATE PARTNERSHIPS. ACEC Risk Management Committee

PUBLIC-PRIVATE PARTNERSHIPS. ACEC Risk Management Committee PUBLIC-PRIVATE PARTNERSHIPS A LOOK FROM THE INSIDE AT THE RISK MANAGEMENT ISSUES ACEC Risk Management Committee The Risk Management Committee of the American Council of Engineering Companies (ACEC) believes

More information

Renville County Purchasing Procedures (Procurement Policy)

Renville County Purchasing Procedures (Procurement Policy) Renville County Purchasing Procedures (Procurement Policy) Board approved 11-15-2016 1 RENVILLE COUNTY PURCHASING PROCEDURES I. Purchasing/Procurement Approval Requirements All employees authorized to

More information

Executive Change Control Board. March 30, 2016

Executive Change Control Board. March 30, 2016 Executive Change Control Board March 30, 2016 1 Today s Topics Review Civil Cost Estimate at 90% Next Steps 2 Review Civil Cost Estimate at 90% 3 Requested City/County Scope Elements Adjusted 60% cost

More information

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project Document B108 2009 Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project AGREEMENT made as of the in the year (In words, indicate day, month and year.)

More information

PRIME DEALER SERVICES CORP. STATEMENT OF FINANCIAL CONDITION AS OF NOVEMBER 30, 2008 AND INDEPENDENT AUDITORS REPORT

PRIME DEALER SERVICES CORP. STATEMENT OF FINANCIAL CONDITION AS OF NOVEMBER 30, 2008 AND INDEPENDENT AUDITORS REPORT PRIME DEALER SERVICES CORP. STATEMENT OF FINANCIAL CONDITION AS OF NOVEMBER 30, 2008 AND INDEPENDENT AUDITORS REPORT ******** INDEPENDENT AUDITORS REPORT To the Board of Directors of Prime Dealer Services

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

CMGC Interim Pricing (OPCC) Milestone Process

CMGC Interim Pricing (OPCC) Milestone Process CMGC Interim Pricing (OPCC) Milestone Process Introduction and Purpose of this Document The purpose of this document is to outline MnDOT s process for validating CMGC pricing submitted by the CMGC Contractor

More information

Infrastructure Ontario TRACK RECORD 2017 REPORT

Infrastructure Ontario TRACK RECORD 2017 REPORT Infrastructure Ontario TRACK RECORD 2017 REPORT CONTENTS EXECUTIVE SUMMARY A. BACKGROUND INFORMATION A1 Background of Infrastructure Ontario...4 A2 Background of Third-Party Consultant - Hanscomb...5 B.

More information