1 IMPLEMENTATION AGREEMENT FOR HYDRO POWER PROJECT (From 2 to 100 MW Capacity) This Implementation Agreement (the Agreement) made on this day of the month of of BETWEEN The Jammu & Kashmir State Power Development Corporation Limited registered under the Companies Act, 1956 having its registered office at Srinagar, through Shri, Managing Director, J&K State Power Development Corporation, at (herein after referred to as Corporation which expression unless repugnant to the context or meaning thereof, shall include its successors, administrators or permitted assigns), of the FIRST PART; AND M/s. having its registered office at (hereinafter referred to as the Independent Power Producer (IPP) which expression shall unless repugnant to the context or meaning thereof, include its successors, administrators or permitted assigns), through who has been duly authorized by the IPP vide their resolution dated. to execute the Agreement, of the SECOND PART. WHEREAS A. JKSPDC is the State's nodal agency for the development of hydro power for projects above 2 MWs in the State of Jammu & Kashmir; B. The IPP has been allotted the Project through a competitive bidding process. C. The IPP shall carry out the necessary detailed investigations and confirmatory surveys, prepare and submit the Detailed Project Report (DPR) for Techno Economic Clearance (TEC) leading to the implementation of the Project by the IPP. The IPP shall satisfy itself about the techno-economic viability of the Project and obtain all statutory clearances and approvals from the concerned authorities; and shall implement the project as per the schedule/milestones indicated in the RfQ Bid documents/tec and this agreement. D. The IPP is now desirous of undertaking the implementation of the project in accordance with the conditions set forth in this Agreement. NOW THEREFORE IN CONSIDERATION OF THE PREMISES AND MUTUAL COVENANTS AND CONDITIONS SET FORTH HEREIN, THE AGREEMENT WITNESSETH AS FOLLOWS: 29

2 ARTICLE-1 DEFINITIONS & INTERPRETATIONS 1.1 DEFINITIONS In this Agreement, the following words and expressions shall have the respective, meanings set forth below, unless the context otherwise requires: "Agreement" shall mean this Agreement together with all its annexes and any amendments thereto made in accordance with the provisions contained herein "Agreement Period" shall have the meaning as specified in Article "Applicable Laws" shall mean all laws as are in force for the time being and applicable in the state of Jammu & Kashmir including rules and regulations made thereunder, and judgments, decrees, injunctions, writs and orders of any court of record, during the subsistence of this Agreement Applicable Permits" shall mean all clearances, permits, authorizations, consents and approvals required to be obtained or maintained under Applicable Laws in connection with the design, engineering, financing, procurement, construction, operation and maintenance of the Project /Site during the subsistence of this Agreement Arbitration Act" means the Jammu & Kashmir Arbitration and Conciliation Act, 1997 and the rules made thereunder BOOT shall mean Build, Own, Operate and Transfer CEA/Authority" shall mean the Central Electricity Authority constituted under Indian Electricity Act, 2003 or its successors CERC shall mean Central Electricity Regulatory Commission "Commercial Operation" shall mean the state of unit/project when unit /Project is capable of delivering Active Power and Reactive Power on a regular basis after having successfully completed the commissioning tests as per Prudent Utility Practices "Commercial Operation Date (COD)" shall mean the date on which the Commercial Operation of Unit /Project as the case may be is achieved by the IPP Committed Power shall mean the power to be procured by J&K from the Project as per the quantum specified in the bidding document on the tariff determined through the bidding process. 30

3 Concession Period shall mean 35 years of operation of the project by the IPP from scheduled COD "Contractor" shall mean any person, firm or body corporate engaged by the IPP for the implementation/operation of the Project "Control Centre" or "State Load Dispatch Centre" or "SLDC" shall mean the J&KPDD's Load Dispatch Centre located at Bemina Srinagar/Gladni Jammu or such other control centre designated by J&KPDD from time to time (but not more than one at a time) wherefrom Dispatch Instructions shall be issued by J&KPDD to the IPP / Station. The control centre/sldc will work in close coordination with Northern Regional Load Dispatch Centre (NRLDC) "Debt" shall mean the amount of any loan, non-convertible debenture or other financial facility, raised and received by the IPP under the Financing Agreements, and actually expended (or to be expended) for the Project and which shall not be greater than the principal amount of debt specified in the applicable currency in the estimate of Project Cost as per the DPR "Deliverable Energy" shall mean the electrical energy generated at the Station, as measured at generator(s) terminals less the summation of the following:- i) Actual auxiliary consumption for the bonafide use of auxiliaries, lighting and ventilation in the Power Station and intake works and the transformation losses (from generation voltage to transmission voltage) of the step up transformers at the power house switchyard; ii) Transmission losses at actual, which shall be the difference of the electrical energy measured at sending and receiving ends of the transmission line (i.e. the station end and the interconnection point). For this purpose and subject to above, the energy meter reading shall be taken on monthly basis at the Inter Connection Point "Dispatch" means to schedule and control the generation of the Project in order to commence, increase, decrease or cease the electrical output as delivered to the Grid System in accordance with J&KPDD's instructions from the Control Centre in conformity with the Agreement and Prudent Utility Practices "Dispatch Instruction" shall mean an instruction issued by the Control Centre to the IPP for the Dispatch of power by message to be confirmed in writing / fax by Control Centre in accordance with the operating procedure developed by the Parties to operate the Project in accordance with the terms of this Agreement, technical limits and Prudent Utility Practices including: 31

4 a. An instruction to target active / reactive power output to be maintained by the Project; b. An instruction to synchronize or desynchronize a unit at a particular time; c. An instruction to defer or cancel a scheduled outage or maintenance outage; d. An instruction for backing down the active / reactive power due to Grid conditions. ' "Detailed Project Report" shall mean the Project Report submitted by the IPP after carrying out necessary detailed investigations and confirmatory surveys in the form as prescribed in the Bid Document "Dispute" shall have the meaning as specified in Article Distribution System means the system of wires and associated facilities between the delivery points on the transmission lines or the generating station connecting and the point of connection to the installation of the consumer Effective Date" shall mean the date of signing of this Agreement Energy means the electrical energy in kilowatt hours (Kwhs) "Equity" shall mean the aggregate of all subscribed and paid up share capital of the IPP in different currencies as converted to Rupees, by application of the procedure approved by the applicable Authority/Government of J&K, as invested in the Project and held by one or more shareholders in the IPP, which shall be in accordance with the financial plan "Financial Closure" shall mean the date on which the Financing Documents providing for funding by the Lenders have become effective and the IPP has immediate access to such funding under the Financing Documents "Financing Documents" means the documents executed by the IPP in respect of financial assistance to be provided by the Lenders by way of loans, guarantees, subscription to non-convertible debentures and other debt instruments including loan agreements, guarantees, notes, debentures, bonds and other debt instruments, security agreements, and other documents relating to the financing (including refinancing) of the Project and includes amendments or modifications made from time to time "Financing Package" means the financing package of the Project indicating the Project Cost and the means of financing thereof as per the DPR "Force Majeure" shall have the meaning as ascribed thereto in Article 9. 32

5 Free Energy shall mean the energy available to the Corporation free of charges from the project based on the offer of the IPP during bidding process Free Power shall mean the free capacity available to the Corporation from the project without any charges as per the offer given by IPP during bidding process. The free capacity shall be more than the minimum capacity prescribed in the bidding document "GoI" shall mean the Government of India GoJK/Government shall mean the Government of Jammu & Kashmir "Grid/Grid System" means the interconnected electrical transmission and distribution system of the state of Jammu & Kashmir including the Interconnection Facility and all other transmission lines and other equipment in the State of Jammu & Kashmir on the J&KPDD's side of the Interconnection point "Interconnection Facilities" shall mean all the facilities which shall include without limitation, switching equipment, communication, protection, control and metering devices etc. at the Interconnection Point(s) to be installed and maintained at the cost of the IPP to enable evacuation of power output from the Project in accordance with this Agreement "Interconnection Point(s)" shall mean the physical touch point at Sub- Station(s) of J&KPDD/ local grid/rural power distribution entities where the Project's transmission line for evacuating the power from the Project is connected to the Grid/ local grid/ rural power distribution entities "IPP" means M/s... having its registered office at... may be in the form of a single firm/corporation, partnership firm, of Indian or foreign origin or consortium or joint venture of such entities who may individually or jointly commit to implement the project, and shall, unless repugnant to the context or meaning thereof, also include their successors, administrators or permitted assigns LC means irrevocable letter(s) of credit Month means English calendar month "MoEF" shall mean Ministry of Environment & Forests, GoI or its successor authority/agency "NRLDC" shall mean "Northern Regional Load Dispatch Centre" or its successor entity. 33

6 "Net Saleable Energy" means the electrical energy in kwhr, delivered by the IPP at the Interconnection Point, less the free energy Open Access charges shall be defined as per the JKSERC, Regulations "Parties" shall refer to the Corporation and the IPP collectively "Party" shall refer to the Corporation and/or the IPP individually "Permanent Works" shall mean the permanent works forming part of the Project that are required to be constructed/installed and maintained as such for the implementation/operation of the Project for at least the Agreement Period and shall also include housing facilities for staff to be engaged for operation and maintenance of the Project Person shall include any IPP or body corporate or association or body of individuals, whether incorporated or not, artificial juridical person "Premium" shall mean the following: a. Premium" shall mean an amount not less than Rs.4,00,000/- (Four lacs only) per MW for 2-25 MW Projects, not less than Rs.6,00,000/- (Six Lacs only) per MW for projects above 25MW and upto 50MW and not less than Rs 8,00,000/-(Eight Lacs only) per MW for projects above 50 MW and upto 100 MW paid to Corporation after award of work as detailed in Article "Project" shall mean the small hydro electric project having an installed capacity of. MW as per Detailed Project Report and proposed to be established on.stream/nallah/river, a tributary of.. River of Basin in the.. District in the State of Jammu & Kashmir, India including complete hydroelectric power generating facility covering all components such as diversion, intake works, water conductor system, power station, generating units, project roads, bridges, offices, residential facilities, stores, guest houses and other connected facilities including the switchyard transmission line Interconnection Facilities "Prudent Utility Practices" shall mean those practices, methods, techniques and standards, as changed from time to time, that are generally accepted internationally by electric utilities for the purpose of ensuring safe, efficient and economic design, engineering, construction, commissioning, testing, operation and maintenance of various components of the Project of the type specified in this Agreement and which practices, methods and standards shall be adjusted as necessary to take into account: i) installation, operation and maintenance guidelines recommended by the manufacturers of plant and equipment to be incorporated in the Project; ii) the requirements of Indian Law as applicable in J&K State; 34

7 iii) iv) conditions affecting the Grid System; and Physical conditions at the Site Power means the electrical power in MWs RfQ Bid Documents shall mean the Bid Document (Request for qualification) issued by the Corporation for participation of private developers in hydro power sector in the state of J&K issued by the J&K State Power Dev. Corporation in pursuance of which the IPP was declared technically and financially qualified to participate in the RfP process RfP bid documents shall mean the Bid document (Request for Proposal) issued by the Corporation to qualified bidders for submission of their proposal/offer based on which the award of the project was made to the eligible bidder RMU means renovation, modernization and uprating "Scheduled Commercial Operation Date" shall mean the date by which IPP shall have achieved the Commercial Operation of the Project which shall be fixed by the corporation while according TEC SERC means the State Electricity Regulatory Commission "SPCB" means the State Pollution Control Board "Site" shall mean the site of Project appurtenances, generating plant including land, waterways, roads and any rights acquired or to be acquired by IPP for the purposes of the Project "State" shall mean Jammu & Kashmir "Station" shall mean the designated hydel power station of the IPP SLDC shall mean the State Load Dispatch Centre, an apex body to ensure integrated operation of the power system in the State TEC shall mean Techno Economic Clearance "Temporary Works" shall mean all temporary works of any kind required in connection with the implementation of the Project and that are incidental and ancillary to the design, engineering and construction of the Project and are constructed/installed and maintained till the Commercial Operation Date for the Project, and not forming part of Permanent Works Terminal Price shall mean the cost to be paid by the Corporation to the IPP after expiry of concession period at the time of handing over of the project which shall not be more than 10% of the tentative estimated cost of the project indicated in the bidding document 35

8 TOD means the time of the day for purpose of metering Transmission line means all high pressure cables and overhead lines ( not being an essential part of the distribution system of a licensee) transmitting electricity from generating station to another generating station or a substation, together with any step up and step down transformers, switchgear and other works necessary to and used for the control of such cables or overhead lines, and such buildings or part thereof as may be required to accommodate such transformers, switchgear and other works "J&KSERC" means Jammu & Kashmir State Electricity Regulatory Commission or its successor or its legal assignee "Unit" shall mean one hydro turbine generator including ancillary equipment and facilities thereto "J&KPDD" means Jammu & Kashmir Power Development Department or its successor or its legal assignee Wheeling means the operation whereby the distribution system and associated facilities of a transmission utility/ licensee or distribution utility/licensee, as the case maybe, are used by another person for the conveyance of electricity on payment of charges "Works" shall mean all works of civil, electrical, mechanical, control and instrumentation in nature and including design, engineering, services, supplies and other work activities required and necessary for the implementation of the Project and shall also include the Permanent Works and the Temporary Works Year shall mean financial year commencing on 1 st April and ending 31 st March

9 1.2 INTERPRETATIONS In this Agreement, unless the context otherwise requires: Any reference to a statutory provision shall include such provision as is from time to time modified or re-enacted or consolidated so far as such modification or re- enactment or consolidation applies or is capable of applying to any transactions entered into hereunder The references to persons and words denoting natural persons shall include bodies corporate and partnerships, joint ventures and statutory and other authorities and entities The nomenclature of the Agreement, headings and paragraph numbers are for the convenience of reference and shall be ignored in construing or interpreting the Agreement Any reference at any time to any agreement, deed, instrument, license or document of any description shall be construed as reference to that agreement, deed, instrument, license or other document as amended, varied, supplemented, modified or suspended at the time of such reference provided that this Clause shall not operate so as to increase the liability or obligations of any Party hereunder or pursuant hereto in any manner whatsoever Any reference to any period commencing "from" a specified day or date and "till" or "until" a specified day or date shall include both such days or dates Unless otherwise expressly provided in this Agreement, any Documentation required to be provided or furnished by the IPP to GOJK and/or Corporation shall be provided free of cost and in three copies and if GOJK or Corporation are required to return any such Documentation with their comments and/or approval, they shall be entitled to retain two copies thereof The words / expressions used in this Agreement but not defined herein, unless repugnant to the context, shall have the same meaning as assigned to them in the RfQ bid document and /or other agreements drawn between the parties of the project in respect as amended from time to time. The words / expressions used in this Agreement shall bear the same meaning as assigned to them in the context in which these have been used in this Agreement provided that their irrespective meaning, if any, assigned to such undefined word / expressions in the J&K Electricity Act 2010, as in force, shall also be taken into consideration for harmonious interpretation of the Agreement

10 ARTICLE Effectiveness TERMS OF THE AGREEMENT The Agreement shall come into force with effect from the Effective Date. 2.2 Agreement Period The Agreement shall remain in force up to a period of Thirty Five (35) years from the Scheduled Commercial Operation Date fixed while according TEC, unless terminated earlier in accordance with the provisions of this Agreement. 2.3 Renewals The IPP may request the Corporation for extension of the Agreement Period, at least one (I) year prior to the expiry of the Agreement Period; the term of this Agreement could be extended on such terms and conditions as are mutually agreed between the Parties. 2.4 a. Transfer of Project At the end of the Concession Period, the projects shall be ordinarily transferred to JKSPDCL on payment of terminal value without any encumbrances. The concession period may, however be, extended beyond 35 years on mutually agreed terms and conditions. b. Maintenance of the Project The Project assets would be maintained by the IPP in a condition that would ensure residual life of the project at the rated capacity for at least 20 years at any point of time including the time of transfer of the project to the State by the IPP. JKSPDCL or its authorized agencies would carry out mandatory inspections on regular basis to ensure the same. The IPP shall provide unhindered access to JKSPDCL to the project. If such inspections reveal that the plant capacity and/or residual life of the project are being undermined due to inadequate maintenance or insufficient capital infusion, JKSPDCL shall order remedial measures to be taken by the IPP. If the IPP fails to comply with these directions, the JKSPDCL shall be at liberty, after providing due opportunity of being heard to the IPP, to terminate the concession period. While doing so, a termination compensation value shall be determined on the basis of estimated net cash flows to equity shareholders for the next ten years or residual period of concession, whichever is less, discounted at a suitable rate. Both, the assessment of cash flows as well as the discount rate, would be as per the approval of JKSERC which will also factor in the costs of recapitalization, refurbishment, 38

11 renovation, repairs, etc. required to bring the project to the necessary standards. 2.5 Project Cost / Implementation The actual expenditure incurred on the project as approved by JKSERC shall be a criterion for firming up of the tariff. The GoJK/Corporation will monitor the project implementation with the right to advice the IPP to develop a cost effective project

12 ARTICLE 3 PROJECT AWARD The Project has been awarded to the IPP on the following terms & conditions. Project Premium: 3.1 Premium" shall mean an amount not less than Rs.4,00,000/- (Four lacs only) per MW for 2-25 MW Projects, not less than Rs.6,00,000/-(Six Lacs only) per MW for projects above 25MW and upto 50MW and not less than Rs 8,00,000/-(Eight Lacs only) per MW for projects above 50 MW and upto 100 MW paid to Corporation after award of work. 3.2 The Bank Guarantee provided as mentioned in the preceding paragraph shall be valid at least upto the time of Financial Closure and shall be encashable at the time of Scheduled Financial Closure whichever is earlier or the Actual Financial closure of the Project or failure of the IPP to reach any of the mile stone indicated in the RFQ document, whichever is earlier. 3.3 The IPP shall be responsible for the payment of any taxes, charges and fees in connection with the Project Premium and Bank Guarantee. Free Power: 3.4 The IPP shall provide free power to J&K at the rate of % (minimum of 15 % apart from 1 % for LADF). Terminal Value: 3.5 The Terminal value to be paid to the IPP at the end of Concession Period shall be Rs

13 ARTICLE 4 SALE OF POWER AND ROYALTY ENERGY 4.1 Disposal of Power : IPP shall supply % of power to J&K after netting off free power and LADF. (In respect of Projects upto 25 MWs the quantum of this power shall be 30 % and in respect of projects above 25 MWs its quantum shall not be less than 30 %). The IPP shall supply this power at a levelised tariff of Rs per unit for 35 years (for Projects above 25 MW).In case of Projects upto 25 MW the tariff for the power procured by J&K shall be determined by the Regulator. The IPP shall, after allowing for J&K s share of power including free power, be free to sell the balance power as it deems fit, within or outside the State. In case of sale to the State, its supply shall be metered at interconnection point. For supply of balance power (other than committed power to J&K), the State Transmission/Distribution networks of transmission/distribution Utility, can be utilized for which open access charges shall be borne by the IPP as per JKSERC regulations. T&D losses will also be borne by the IPP, as per JKSERC regulations All the sales of the energy generated by the Project would be approved, as may be required, by the J&KSERC. 4.2 Free Energy Free energy shall be as per the offer made by the IPP during the bidding process and shall be due from the scheduled COD % free power for LADF also shall be applicable and due from the developer immediately on Scheduled COD. The free power on account of LADF shall be utilized as per the provisions of Hydro Policy Free Power for Royalty, LADF will be calculated as per actual generation for projects commissioned as per schedule or earlier. However, in case of projects which are commissioned beyond scheduled date the same shall be applicable from the date of scheduled COD, except in case of the delay on an account of force majeure and reasons beyond the control of the developer

14 ARTICLE-5 OBLIGATIONS 5.1 Obligations of the IPP (i) Timelines for execution of a project allotted to an IPP shall be as follows:- Activity Indicative Timelines *(in months) 2-25 MWs MWs Letter of Award T 0 T 0 Payment of Upfront Premium along T T with Performance Guarantee (@ Rs 10 lac per MW) by the IPP. Investigation & submission of DPR by T T the IPP TEC of DPR by JKSPDCL after T T submission of all the necessary documents and clarifications by the IPP Signing of Implementation T T Agreement between the IPP & JKSPDCL Obtaining of all Clearances and T T achieving Financial Closure by the IPP Scheduled COD of the Project Shall be fixed by Shall be fixed by JKSPDCL while JKSPDCL while according TEC according TEC * The timelines indicated in this Table generally give the maximum period required for a particular step in execution of a project. The timelines may be specifically stated for particular projects on considerations of availability of the DPR, clearances, site suitability, etc. (ii) The IPP shall submit quarterly progress reports in respect of obtaining statutory clearances/approvals and achieving Financial Closure of the Project. The IPP shall also provide two copies each of the statutory clearances/approvals, as and when the same are obtained. (iii) The IPP shall submit to the Corporation two copies each of the Project related Agreements including in particular the Construction Contracts / EPC Contract, if any, the Financing Documents and the O&M Contract, if any. The IPP shall ensure that these Project related Agreements do not in 42

15 any way hold the Corporation /GoJK liable to the IPP or any Contractor in any manner whatsoever and shall be without prejudice to the rights of GoJK/ Corporation hereunder Commercial Operation Date (COD) The IPP shall achieve COD as specified by the Corporation in TEC document Incentives for Early Commercial Operation of the Project:- If COD is achieved earlier than scheduled COD, IPP will not be required to provide free power/royalty up to the scheduled COD from the actual COD Monitoring and Supervision of the Project i) The IPP shall furnish to the Corporation quarterly progress reports of actual progress of the Construction Works comprised in the Project and shall give all such other relevant information as may be required by the Corporation. ii) During the Construction Period, the IPP shall provide videography to Corporation every calendar quarter, covering the construction of the Project in that quarter. Such video recording shall be provided no later than fifteen days after the close of each quarter. iii) Corporation may inspect the Construction Works and the Project. The IPP shall, at all times, afford access to the Site to the authorised representatives of the Corporation and to the persons duly authorised by any Government agency having jurisdiction over the Project, including those concerned with safety, security or environmental protection to inspect the Project Site and to investigate any matter within their authority and upon reasonable notice, the IPP shall provide to such persons reasonable assistance/necessary information to carry out their respective duties and functions with minimum disruption to the construction, operation and maintenance of the Project consistent with the purpose for which such persons have gained such access to the Site Rights and Title Over the Site i) The IPP shall have exclusive rights to the use of the Site in accordance with the provisions of the Agreement and for this purpose it may regulate the entry and use of the Project by third parties. ii) The IPP shall not sublet any part or the whole of the Site save and except as may be expressly set forth in the Agreement, provided however that nothing contained herein shall be construed or interpreted as restricting the right of the IPP to appoint contractors for the performance of its obligations hereunder including for operation and maintenance of all or any part of the Project including the Project Facilities Execution of Upstream and Downstream Projects. 43

16 The IPP shall not have any objection to the development of upstream or downstream hydro power projects including development / diversion of water for irrigation, flood control/ water supply etc. projects being/ to be developed by the GoJK or any of its agencies, provided however, the GoJK will ensure uninterrupted flow of water discharge to the extent as must have been earmarked and indicated in the design discharge by the GoJK and/or as may be permitted under clearances to be issued by the concerned Government departments Rehabilitation and Resettlement Plan The IPP shall execute the Rehabilitation and Resettlement Plan prepared in consultation with the GoJK, duly vetted by the latter at its own cost and the cost so incurred shall form part of the Project Cost Safety Measures The IPP shall ensure proper safety measures during implementation of the Project including any geological study, construction and testing at the Site. The Corporation shall have the right to institute an appropriate mechanism to ensure compliance by the IPP in this regard Alternative Facilities In case any existing facilities including, but not limited to, irrigation systems, water supplies, roads, bridges, buildings, communication system(s) power systems and water mills are adversely affected because of the implementation of the Project, the IPP shall be responsible and bear the cost of for taking remedial measures to mitigate such adverse effects. The cost of the above remedial measures shall become part of the Project Cost. Such facilities shall be as mutually identified and agreed upon between the IPP and the Corporation. The IPP shall not interfere with any of the existing facilities till an alternate facility, as identified, is created Usage of Forest Land The IPP shall ensure that the land is used only for the Project. Use of Forest land, in case other alternative land is not available, shall be allowed strictly as per provisions of J&K Forest Conservation Act, 1997 and the IPP shall have to fulfill all the conditions mentioned in the order issued by the competent authority in this behalf before taking up the work. However, use of Forest land under Wildlife Protected areas shall be as per J&K Wildlife (Protection) Act, 2002 and Hon ble Supreme Court orders in this behalf Compensatory Afforestation The IPP shall pay to the GOJK the cost of raising compensatory afforestation and its maintenance for a period and the extent of area, as may be determined by Ministry of Environment and Forests (MoEF), GoI and or the concerned department of the GoJK Environment Clearance 44

17 The IPP shall be liable to obtain Environment clearance as required under the Environment (Protection) Act, 1986 and as per Environment Impact Assessment (EIA) Notification dated 14 th Sept Catchment Area Treatment Plans The IPP shall make suitable financial provisions in the Project Cost for the catchment area treatment plans, as may be determined by the concerned department of the GoJK and if need be by MoEF, GOI. The cost involved on this account shall be paid by the IPP to the Forest Department of the GoJK as per Forest and Environment Clearance accorded by the GoI/and or the concerned department of the GoJK Ensuring Flow of Water The IPP shall ensure such minimum flow of water immediately downstream of the weir/barrage/dam for downstream requirements as specified in the environmental clearance issued by the GoJK or as may be directed by any other department of the GoJK or SPCB Protection of Fish culture The IPP shall take appropriate steps, as may be required, for the protection of fish fauna in the project area. The IPP shall enter into a separate agreement with the Fisheries Department in this regard on case to case basis Environment Impact Assessment The IPP shall be liable to carry out Environmental Impact Assessment as required under the Environmental (Protection) Act, 1986 through consultant(s) drawn from a reputed organization and obtain the consent of State Pollution Control Board (SPCB) under the Water (Prevention and Control of Pollution) Act, 1974 or any other environment law(s) as may be applicable Fishing, Recreational and Navigational Rights The fishing, recreational and navigational rights in the river, water, channels, reservoirs, lakes shall remain vested with the Government/Fisheries Deptt. subject only to such restrictions as may be necessary for the operational requirements, safety and security of the Project. Opening and closing of the water body shall be undertaken with prior information and in close coordination with the Fisheries Department Maintaining Ecological Balance The IPP shall be responsible for maintaining the ecological balance by preventing deforestation, water pollution and defacement of natural landscape in the vicinity of Works. The IPP shall take all reasonable measures to prevent any, unnecessary destruction, scarring or defacement of the natural surroundings in the vicinity of the Works Dumping of Excavated Material 45

18 The IPP shall ensure that the material excavated from the site shall be dumped in the area duly approved by the Corporation Use of Facilities Subject to availability, security, safety, law, order, and operational factors being met, the IPP shall permit free use, by the GoJK and the general public, of all service roads constructed and maintained by it for the Project after the project has been commissioned Trees in the Land transferred to the IPP The IPP shall pay compensation of the trees, on the Forest land, which are to be felled or damaged during the execution of the project as per orders to be issued by the Competent Authority. Trees shall be felled/removed by the Forest Department/J&K State Forest Corporation and IPP shall not be entitled to its sale proceeds. Regarding felling of trees on the other GoJK lands and private land the same shall be as per the existing law in vogue. However, GoJK shall provide necessary assistance to the IPP in obtaining the permission of competent authority for removal of trees on the acquired land Archaeological Findings, Treasures etc. All fossils, coins, articles of value or antiquity and structures and other remains or things of geological or archaeological interest discovered on the Site shall be deemed to be the absolute property of the GoJK. The IPP shall take reasonable precautions to prevent his workmen or any other persons from damaging any such article or thing. The IPP shall arrange to hand over the same to the GoJK free of cost, provided that, in case any precious or semi-precious material is located, the IPP shall inform the GoJK immediately and abide by the directives of the GoJK which would stand communicated within a period of two (2) months from the date of receipt of such intimation from the IPP Labour and compliance with labour /Industrial and other laws. IPP shall at its expenses, ensure due compliance with all applicable and governing laws industrial and labour laws and regulations and by-laws both of the GoI and GoJK and all other local authorities and shall keep the GoJK indemnified in respect thereof. The IPP shall ensure due compliance with the provisions of the minimum wages Act, payment of wages Act, contract labour (regulations and abolition) Act, workman s compensation Act, EPF Act and other labour/industrial laws in force Promoter s Equity in the IPP 46

19 The IPP shall be permitted to incorporate a new public/private limited IPP for the implementation of the Project with its Registered Office within Jammu & Kashmir. All rights and obligations under this Agreement shall thereafter be transferred to the new IPP. Unless otherwise permitted by the Corporation, the aggregate equity contribution of the IPP/promoters of the allottee IPP/Consortium to which the Project was initially allotted shall not be less than 51 % (fifty one percent) during the Construction Period and until 2 (two) years following the commencement of Commercial Operations Surrender of allotment. The IPP may surrender the allotment if on formulation of the DPR within the stipulated time-frame, it establishes, to the entire satisfaction of JKSPDCL, that the project is techno-economically unviable. On such surrender, the bank guarantee provided by the IPP in lieu of upfront premium as well as the performance guarantee would be released and the premium amount would be refunded to the IPP. 5.2 Obligations of the GoJK and Corporation Assistance in Obtaining Clearances The Corporation shall assist the IPP in obtaining the various statutory clearances and approvals required for the implementation of the Project, from various competent authorities of the GoJK /GoI on best effort basis. The responsibility of obtaining these approvals/clearances shall, however, rest with the IPP only Use of materials The GOJK shall permit the IPP, in accordance with the Law to collect and use boulders, stones, shingles, limestone and other building materials, except precious and semi-precious materials, from the river beds, and/or from the land acquired for or transferred to or leased out the IPP for the Project on payment of royalty in accordance with the GOJK rules/rates in force from time to time. However, IPP shall obtain NOC from Fisheries Department for collection of such materials in all the cases and NOC from Forest Department in case of collection of such material from river beds falling in forest areas Lease of land for Permanent Works Upon the request of the IPP and subject to the provisions of laws in force, GOJK shall, on such terms and conditions and rates prescribed by the GOJK from time to time, provide for, on a long term lease, for maximum period of 40 years the GOJK land required for Permanent Works, as may be necessary for the construction, operation and maintenance of the Project. The private land will be acquired by the GOJK and then leased out to a non state subject IPP in accordance with Law on the subject Lease of Land for Temporary Works Upon the request of the IPP and subject to the provisions of laws in force, the GOJK shall provide, on such terms and conditions and rates as may be 47

20 prescribed by the GOJK from time to time, on a short term lease for a maximum period of not exceeding 7 years, such GOJK land required for Temporary Works, as is considered reasonably necessary by the GOJK. In case the IPP desires, in addition to GOJK land, private land may also be acquired by the GOJK and leased out to the IPP on a short term basis for a maximum period of not exceeding 7 years for temporary works, as is considered reasonable/ necessary by the Corporation Acquisition of Land JKSPDC will take necessary action to acquire land and also lease the same, as per applicable law strictly as per component wise project requirement of the IPPs on payment of premium/rentals to be determined by the Government till the expiry of Concession Period Lease hold assignment The GOJK shall permit mortgaging of land acquired/diverted for the Project as per rules and laws in force in favour of the Lenders Upgradation of Roads and Bridges GOJK shall, at the request and cost of the IPP, construct, widen and strengthen such roads or bridges within the State of Jammu & Kashmir, as are considered reasonably necessary by the GOJK. The GOJK shall permit the IPP to construct roads, bridges, culverts as considered necessary for the Project in the Project lands in consultation with State Public Works Department at the cost of the IPP. The GOJK/ Corporation may also construct roads, bridges, culverts as are considered reasonably necessary by the GOJK in the interest of the Project on a case-to-case basis Evacuation of Power The Corporation shall provide necessary assistance to the IPP in tying up the transmission system for evacuation of power from the Project out of Jammu & Kashmir through the transmission system of the J&KPDD, Power Grid Corporation of India Limited (PGCIL) or any other such utility(ies) Levies, Taxes and Charges i. No entry tax will be levied by the State Government on power generation, transmission equipment and building material and construction equipment for Power projects awarded under this policy. ii. Exemption from Income tax on account of income accruing from micro-hydel power projects shall be governed as per the Government of India policy in vogue. iii. IPP may pursue CDM benefits from the project at its own risk and responsibility. Sharing of the CDM benefits between IPP and JKSPDCL will be as per CERC/SERC regulations. iv. Projects awarded under this policy shall be exempted from water usage charges imposed under the J&K Water Resource Regulation 48

21 and Management Act 2010 for the first 10 years of operation reckoned from Scheduled Commercial Operation Date. v. The projects up to 25 MW can avail incentives from MNRE as per the National Policy

22 ARTICLE 6 PLANT OPERATION AND MAINTENANCE 6.1 Subject to the Provisions of the Agreement, the IPP shall operate and maintain, and if required, effect improvement (within the overall scope of the Project Implementation) in the Project in accordance with: i) Prudent Utility Practices; ii) All applicable laws and directive; iii) The manuals, instructions, manufacturers' guidelines supplied by construction contractors, manufacturers of equipments/ suppliers etc.; iv) The Grid Code; v) Dispatch instructions; and vi) Rated capacity subject to normal derating /deterioration. 6.2 The Project Unit(s) shall be capable of meeting the load dispatch requirements. The IPP shall follow the directive of the Control Centre/ NRLDC in the interest of integrated grid operation. 6.3 Any Dispute with reference to the directive of the Control Centre /NRLDC shall be referred to JKSERC whose decision in such a matter shall be final. Pending the decision of JKSERC, Control Centre's /NRLDC's directives shall prevail in the interest of smooth operation of the grid

23 ARTICLE 7 REPRESENTATI0NS AND WARRANTIES 7.1 Representations and Warranties of the IPP The IPP represents and warrants that as of the date hereof: a. The IPP is a IPP duly registered and validly existing under the laws of India and has all requisite legal power and authority to execute this Agreement and carry out the terms, conditions and provisions hereof; b. It has the financial/technical standing and capacity to undertake the Project; c. It is subject to civil and commercial laws of India with respect to this Agreement and it hereby expressly and irrevocably waives any immunity in any jurisdiction in respect thereof; d. It has complied with all Applicable Laws and has not been subject to any fines, penalties, injunctive relief or any other civil or criminal liabilities which in the aggregate have or may have Material Adverse Effect on its financial condition or its ability to perform its obligations and duties under this Agreement; e. There are no actions, suits or proceedings pending or, to the IPP's knowledge, threatened, against or affecting the IPP before any Court or administrative body or arbitral tribunal that might materially or adversely affect the ability of the IPP to meet and carry out its obligations under this Agreement; f. The IPP has duly paid all rents, royalties and all public demands, including provident fund dues, gratuity dues, employees State Insurance dues, income tax, sales tax, Corporation tax and all other taxes and revenues due and outstanding and that no attachments or warrants have been served on the IPP in respect of sales tax, income tax, GOJK / GOI revenue and other taxes; g. The execution and delivery by the IPP of this Agreement has been duly authorised by all requisite corporate or partnership action, and will not contravene any provision of, or constitute a default under any other agreement or instrument to which it is a party or by which it or its property may be bound; and h. Representations or warranties by the IPP contained herein or in any other document furnished by it to any Government Agency in relation to clearances and approvals shall not contain any untrue statement of 51

24 material fact. The IPP shall not omit to state a material fact necessary to make such representation or warranty not misleading. 7.2 Representations and Warranties of the Corporation. a. The Corporation is validly existing under the Laws of India and has all requisite legal power and authority to execute this Agreement and to carry out the terms, conditions and provisions hereof; and b. The execution and delivery of this Agreement by the Corporation does not violate the provision of any existing law or notification or regulation or order or decree of any court, government authority, or of agency or of any contract, undertaking or agreement, to which the Corporation is a party or which is binding on Corporation and any of the above does not result in the imposition or creation of any lien, charge or encumbrance on the assets of the IPP or part thereof

25 ARTICLE 8 UNDERTAKINGS 8.1 The IPP hereby covenants to and agrees with the Corporation to: a. Make all efforts to collect required information and file necessary applications to the concerned authorities for obtaining the statutory clearances and approvals. b. Use all reasonable efforts to obtain financing for construction and operation of the Project as contemplated in this Agreement; c. Use all reasonable efforts to negotiate and execute financing documents in, accordance with the terms and provisions of this Agreement; d. Work with and co-operate in good faith with the Corporation with respect to all of the obligations and rights hereunder; e. Use all reasonable efforts to obtain all GOJK/Corporation Authorisations / Applicable Permits; f. Engage advisors, representatives and experts as are experienced in the development, construction and financing of power stations similar to the Project; g. Design, construct and complete the Project in a good workman-like manner, 'only with the materials and equipment that are new and of international utility-grade quality, in such a manner that useful life of the Project will be at least equal to the Agreement period and in accordance with i. All applicable laws, rules, regulations, permits and licenses; and ii. Sound engineering and construction practices, and prudent utility practices. h. Engage contractors of repute that are recognized nationally or at state level and that have significant experience in the engineering, procurement and construction of hydel power generating stations of similar capacities; i. Operate and maintain the Project in accordance with the dispatch instructions and prudent utility practices; j. Provide Government / Corporation with copies of all publicly filed financial statements and reports; 53

26 k. Pay all amounts due to the Government (including penalty) in accordance with the provisions of this Agreement; l. The IPP shall be responsible for laying lines for connectivity to the nearest grid sub-station at the appropriate voltage which will normally be 132 KV or 33 KV depending on the capacity of the power station and distance from the Power station to the Grid substation. On specific request from the IPP, the J&K PDD will carry out the implementation of evacuation facilities at charges to be mutually negotiated. m. At the end of the Agreement period, transfer the Project in good, working condition to the Corporation as per provisions of this Agreement; And n. Not to transfer/dispose off or otherwise alienate any asset of the IPP without prior approval of the Corporation. 8.2 Undertakings of the Corporation The Corporation hereby covenants to and agrees with the IPP to: a. Provide such assistance and support as the IPP may reasonably require in identifying and preparing the applications for GOJK authorisations and in interfacing with Government Authorities in connection with obtaining the same for the construction, completion and operation of the Project; b. Provide adequate construction power subject to availability, to the Project work site at the cost of the IPP. The Corporation shall not be liable to pay any damages/compensation to the IPP in the event of non-supply of construction power beyond J&KPDD's control. c. Make arrangements for establishing (by themselves/other agencies) suitable transmission system for transmission of power beyond the interconnection point at least three months prior to the scheduled COD; And d. Work with and co-operate in good faith with the IPP with respect to all of the IPP's obligations and rights hereunder

JAMMU & KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED

JAMMU & KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED JAMMU & KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED NOTICE INVITING BIDS FOR IPP PROJECT NIT NO 02 of 2013 Dated 07-02-2013 1. Jammu & Kashmir State Power Development Corporation (JKSPDC) invites

More information

GOVERNMENT OF KERALA

GOVERNMENT OF KERALA 183 GOVERNMENT OF KERALA Kerala Small Hydro Power Policy 2012 1. Order G.O.(P) 25/2012/PD Dated: Thiruvananthapuram, 03.10.2012 2. Title Kerala Small Hydro Power Policy 2012 3. Objective To increase the

More information

STANDARD IMPLEMENTATION AND SERVICE AGREEMENT FOR DEVELOPMENT AND OPERATION OF INTRA-STATE TRANSMISSION SYSTEM

STANDARD IMPLEMENTATION AND SERVICE AGREEMENT FOR DEVELOPMENT AND OPERATION OF INTRA-STATE TRANSMISSION SYSTEM STANDARD IMPLEMENTATION AND SERVICE AGREEMENT FOR DEVELOPMENT AND OPERATION OF INTRA-STATE TRANSMISSION SYSTEM FOR TRANSMISSION OF ELECTRICITY THROUGH TARIFF BASED COMPETITIVE BIDDING FOR. [INSERT THE

More information

Bhopal: Dated 5 th May 2006

Bhopal: Dated 5 th May 2006 Bhopal: Dated 5 th May 2006 No. 1192/MPERC/2006. In exercise of the powers conferred by section 181 (g) read with section 32(3) of the Electricity Act, 2003 enacted by the parliament, the Madhya Pradesh

More information

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT Energy Department Government of Bihar 2012 ( 1 ) Table of Content 1. Objective 2. Title and Enforcement 3. Scope and Coverage 4. Nodal Agency 5. Classification

More information

GRANT THORNTON DRAFT CONCESSION AGREEMENT

GRANT THORNTON DRAFT CONCESSION AGREEMENT GRANT THORNTON DRAFT CONCESSION AGREEMENT For Establishment of Technical Education Institutes based on PPP mode in the state of Uttar Pradesh Engineering Institutes, Polytechnics and ITIs ( Project ) 12/02/2009

More information

CHAPTER I: PRELIMINARY Short title, commencement and interpretation

CHAPTER I: PRELIMINARY Short title, commencement and interpretation Notification dated 20.2.2009 Bhopal: dated 31 st January, 2009 No. 254-MPERC-2009. In exercise of the powers conferred by Section 181 read with Subsection (b) of Section 86 of the Electricity Act 2003

More information

Maharashtra State Electricity Distribution Company Limited

Maharashtra State Electricity Distribution Company Limited Maharashtra State Electricity Distribution Company Limited Model Power Purchase Agreement for Tariff Based Bidding Process for Procurement of Power on Long Term Basis from Power Stations where location,

More information

PIMPRI CHINCHWAD NEW TOWN DEVELOPMENT AUTHORITY (PCNTDA)

PIMPRI CHINCHWAD NEW TOWN DEVELOPMENT AUTHORITY (PCNTDA) PIMPRI CHINCHWAD NEW TOWN DEVELOPMENT AUTHORITY (PCNTDA) Common Set of Deviation (CSD) Issued Post Pre-Bid Meeting Held on 23 rd April 2013, for the Project Consultancy Services for the Work of Construction

More information

GOVERNMENT OF MADHYA PRADESH

GOVERNMENT OF MADHYA PRADESH 206 Compendium of State Government Policies on Renewable Energy Sector in India GOVERNMENT OF MADHYA PRADESH Wind Power Project Policy of Madhya Pradesh, 2012 (As Amended on 21 st February 2013) 1. Order

More information

Standard Power Purchase Agreement. For

Standard Power Purchase Agreement. For Standard Power Purchase Agreement For Procurement of Power on a Long-Term basis from the (insert capacity in MW) Ultra Mega Power Project to be set up at (specify location, district and State) sourcing

More information

[ ] - AND - [ ] POWER PURCHASE AGREEMENT RELATING TO DATED [ ]

[ ] - AND - [ ] POWER PURCHASE AGREEMENT RELATING TO DATED [ ] This document has been prepared for the purposes of the PPP IN INFRASTRUCTURE RESOURCE CENTER FOR CONTRACTS, LAWS AND REGULATIONS (PPPIRC) website. It is a sample document FOR REFERENCE PURPOSES ONLY and

More information

Compendium of State Government Policies on Renewable Energy Sector in India ARUNACHAL PRADESH

Compendium of State Government Policies on Renewable Energy Sector in India ARUNACHAL PRADESH 85 ARUNACHAL PRADESH Small Hydro Power Policy- 2007 Dated 24 th January, 2008 & Amendment Dated 13 th Oct. 2008 1. Order PWRS/HPD/W-1305/2005 dated 24 th January, 2008. And Amendment order No: PWRS/W-1305/2005/

More information

MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT

MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT APPENDIX A (insert date) MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT This Interconnection Agreement ( Agreement ) is

More information

APPLICATION FOR STANDARD CONTRACT BY A QUALIFYING COGENERATOR OR SMALL POWER PRODUCER

APPLICATION FOR STANDARD CONTRACT BY A QUALIFYING COGENERATOR OR SMALL POWER PRODUCER APPLICATION FOR STANDARD CONTRACT BY A QUALIFYING COGENERATOR OR SMALL POWER PRODUCER 1. The undersigned, hereinafter called "Seller," hereby requests that North Carolina Eastern Municipal Power Agency,

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission Notification no. UPERC / Secy / CNCE Regulation, 2009/ 696 Dated: 22.3.2010 In exercise of powers conferred under section 181 read with section 9, 61, 86

More information

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT [This contract has been approved by the California Public Utilities Commission in Decision 13-05-034. Modification of the terms and conditions of this contract will result in the need to obtain additional

More information

Implementation of Solar Based Projects in MP Dated 20 July, 2012

Implementation of Solar Based Projects in MP Dated 20 July, 2012 86 Compendium of Policies, Regulations, Technical Standards & Financing Norms for Solar Power Projects GOVERNMENT OF MADHYA PRADESH Implementation of Solar Based Projects in MP Dated 20 July, 2012 1. Title

More information

LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER] DATED AS OF [DATE OF LOAN CLOSING]

LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER] DATED AS OF [DATE OF LOAN CLOSING] [SFY 2017 DIRECT LOAN - MASTER TRUST LOAN AGREEMENT - PRINCIPAL FORGIVENESS/NANO - PRIVATE FORM] LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER] DATED

More information

JAMMU AND KASHMIR STATE ELECTRICITY REGULATORY COMMISSION

JAMMU AND KASHMIR STATE ELECTRICITY REGULATORY COMMISSION JAMMU AND KASHMIR STATE ELECTRICITY REGULATORY COMMISSION Notification No. 5/JKSERC/2005 Jammu dated 23 Sept. 2005 In exercise of powers conferred under section 36 read with section 8(1) (c) of the Jammu

More information

New and Renewable Energy Department Vallabh Bhavan, Bhopal

New and Renewable Energy Department Vallabh Bhavan, Bhopal New and Renewable Energy Department Vallabh Bhavan, Bhopal English Translation of Policy for implementation of Small Hydel-Power based Electricity Projects in Madhya Pradesh, 2011 (As Amended on 15th February

More information

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46)) GOVERNMENT NOTICE NO. 77 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 18(5), 45 and 46)) THE ELECTRICITY (DEVELOPMENT OF SMALL POWER PROJECTS) RULES, 2018 1. Citation

More information

AGREEMENT FOR SYNCHRONOUS OPERATION OF CAPTIVE POWER PLANTS OF.. WITH JHARKHAND STATE ELECTRICITY BOARD SYSTEM

AGREEMENT FOR SYNCHRONOUS OPERATION OF CAPTIVE POWER PLANTS OF.. WITH JHARKHAND STATE ELECTRICITY BOARD SYSTEM AGREEMENT FOR SYNCHRONOUS OPERATION OF CAPTIVE POWER PLANTS OF.. WITH JHARKHAND STATE ELECTRICITY BOARD SYSTEM AN AGREEMENT FOR SYNCHRONOUS OPERATION OF Captive Power Plant of M/s.. of.. MW is made on

More information

OPTION TENDER RULES. 3. A Tender Offer must be made in a Tender Offer Notice in the form set out on the Create Bids Screen in Gemini.

OPTION TENDER RULES. 3. A Tender Offer must be made in a Tender Offer Notice in the form set out on the Create Bids Screen in Gemini. Reference Number: 1.48 OPTION TENDER RULES INTRODUCTION 1. These Option Tender Rules ( Option Tender Rules ) detail the procedure by which a Tendering User may offer and National Grid may accept and exercise

More information

Interconnection of Electric Generators

Interconnection of Electric Generators Interconnection of Electric Generators (GENERATING CAPACITY OF NOT MORE THAN 25 KILOWATTS) Public Utility #1 of Ferry County Republic Washington November 15, 2007 Table of Contents Chapter 1 Purpose and

More information

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION Idaho Power Company Second Revised Sheet No. 72-1 I.P.U.C. No. 29, Tariff No. 101 First Revised Sheet No. 72-1 PUBLIC UTILITIES COMMISSION AVAILABILITY Service under this schedule is available throughout

More information

POWER PURCHASE AGREEMENT BETWEEN

POWER PURCHASE AGREEMENT BETWEEN POWER PURCHASE AGREEMENT BETWEEN SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED / NORTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED (insert as applicable depending on the interconnection

More information

Tier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System

Tier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System CITY OF MOUNT DORA, FLORIDA FIRST REVISED SHEET NO. 15.0 CANCELS ORIGINAL SHEET NO. 15.0 Tier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System This Agreement is made and

More information

TOWN OF DEEP RIVER AND TOWN OF CHESTER INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT

TOWN OF DEEP RIVER AND TOWN OF CHESTER INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT TOWN OF DEEP RIVER AND TOWN OF CHESTER INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT This INTERMUNICIPAL WASTEWATER TREATMENT AGREEMENT ( Agreement ), dated as of August 19, 2005, is made and entered into

More information

INTERCONNECTION AND OPERATING AGREEMENT

INTERCONNECTION AND OPERATING AGREEMENT INTERCONNECTION AND OPERATING AGREEMENT This Interconnection and Operating Agreement ( Agreement ) for the facility located at, in the City of, Michigan, is entered into this day of, 200 by and between

More information

AGREEMENT BETWEEN THE COMTRACK PARTICIPANT AND THE PERSON SEEKING TO OPEN AN ACCOUNT WITH THE COMTRACK PARTICIPANT

AGREEMENT BETWEEN THE COMTRACK PARTICIPANT AND THE PERSON SEEKING TO OPEN AN ACCOUNT WITH THE COMTRACK PARTICIPANT AGREEMENT BETWEEN THE COMTRACK PARTICIPANT AND THE PERSON SEEKING TO OPEN AN ACCOUNT WITH THE COMTRACK PARTICIPANT This agreement made and entered and executed at. on this day of.. between, a /firm/ company

More information

STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM

STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM This Agreement is made and entered into this day of, 20, by and between, (hereinafter RGS Owner ), located at in, Florida, and Utility

More information

AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION

AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION This Interconnection Agreement ( Agreement ) is made and entered into this day of, 20, by Egyptian Electric Cooperative Association,

More information

POWER PURCHASE AGREEMENT FOR SUPPLY OF ---- MW SOLAR POWER FROM GRID CONNECT SOLAR PV POWER PLANT FOR 12 YEARS

POWER PURCHASE AGREEMENT FOR SUPPLY OF ---- MW SOLAR POWER FROM GRID CONNECT SOLAR PV POWER PLANT FOR 12 YEARS POWER PURCHASE AGREEMENT FOR SUPPLY OF ---- MW SOLAR POWER FROM GRID CONNECT SOLAR PV POWER PLANT FOR 12 YEARS By [--------------------------------------------------------------] With Uttar Pradesh Power

More information

Terms and Conditions.

Terms and Conditions. Terms and Conditions 1. Interpretation 1.1 In these terms and conditions ( Conditions ) the following words have the following meanings. 1.1.2 Collection Service a Service whereby M&WR Ltd collects Waste

More information

M.P. Electricity Regulatory Commission Bhopal

M.P. Electricity Regulatory Commission Bhopal SMP-20/2010 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Wind Electric Generators 1. LEGISLATIVE PROVISIONS 1.1 Section 86(1) (e) of the Electricity Act 2003

More information

Electricity (Net-Metering) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 45 and 46) THE ELECTRICITY (NET-METERING) RULES, 2018

Electricity (Net-Metering) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 45 and 46) THE ELECTRICITY (NET-METERING) RULES, 2018 GOVERNMENT NOTICE NO. 76 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 45 and 46) THE ELECTRICITY (NET-METERING) RULES, 2018 1. Citation 2. Application 3. Interpretation

More information

Carolina Power & Light Company 61 d/b/a Progress Energy Carolinas, Inc. TERMS AND CONDITIONS FOR THE PURCHASE OF ELECTRIC POWER

Carolina Power & Light Company 61 d/b/a Progress Energy Carolinas, Inc. TERMS AND CONDITIONS FOR THE PURCHASE OF ELECTRIC POWER Carolina Power & Light Company 61 d/b/a Progress Energy Carolinas, Inc. TERMS AND CONDITIONS FOR THE PURCHASE OF ELECTRIC POWER l. PURCHASE AGREEMENT These Terms and Conditions" provide a mechanism through

More information

DATED and CHATTEL MORTGAGE

DATED and CHATTEL MORTGAGE Draft 20.06.2011 DATED 2011 BORROWER: MOTORHOLME LIMITED (1) and LENDER: AS SPECIFIED IN SCHEDULE 1 (2) CHATTEL MORTGAGE 8272934v3 1 THIS CHATTEL MORTGAGE is dated 2011 PARTIES 1 MOTORHOLME LIMITED a company

More information

Rate Code: L L-16 SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (SANTEE COOPER) LARGE LIGHT AND POWER SCHEDULE L-16

Rate Code: L L-16 SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (SANTEE COOPER) LARGE LIGHT AND POWER SCHEDULE L-16 SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (SANTEE COOPER) LARGE LIGHT AND POWER SCHEDULE L-16 Section 1. Availability: (A) Service hereunder is available at Delivery Points on or near the transmission facilities

More information

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE 1. SCOPE ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE 1.1 These general conditions of purchase published at www.zanon.com -shall be deemed as an integral part of any order issued by Ettore Zanon

More information

Bhopal Dated : 5th October 2004

Bhopal Dated : 5th October 2004 Bhopal Dated : 5th October 2004 No.2680/MPERC/2004. In exercise of powers conferred under Section 52 read with section 181(1) and 181(2) (z) and section 16 read with section 181(2) (d) of the Electricity

More information

Overview of the framework

Overview of the framework Overview of the framework To meet the infrastructure deficit, the Twelfth Five Year Plan envisages a renewed thrust on investment in infrastructure, particularly in the power sector. The additional thermal

More information

The Government of the Republic of South Africa and the Government of the Kingdom of Lesotho (hereinafter called "the Parties");

The Government of the Republic of South Africa and the Government of the Kingdom of Lesotho (hereinafter called the Parties); TREATY ON THE LESOTHO HIGHLANDS WATER PROJECT BETWEEN THE GOVERNMENT OF THE REPUBLIC OF SOUTH AFRICA AND THE GOVERNMENT OF THE KINGDOM OF LESOTHO SYLLABUS OF THE TREATY PREAMBLE ARTICLE 1: Definitions

More information

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office and

More information

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties.

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties. SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office

More information

ESCROW/SPECIAL ACCOUNT AGREEMENT

ESCROW/SPECIAL ACCOUNT AGREEMENT FORM NO.SEC/L/AGR-4/1 ESCROW/SPECIAL ACCOUNT AGREEMENT THIS AGREEMENT made this day of, between M/s Indian Renewable Energy Development Agency Limited (IREDA), a Public Company incorporated under the Companies

More information

J&K State Power Development Corporation Limited PARNAI HYDROELECTRIC PROJECT. (3x12.5 MW) BIDDING DOCUMENT FOR

J&K State Power Development Corporation Limited PARNAI HYDROELECTRIC PROJECT. (3x12.5 MW) BIDDING DOCUMENT FOR J&K State Power Development Corporation Limited PARNAI HYDROELECTRIC PROJECT (3x12.5 MW) BIDDING DOCUMENT FOR "ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC) CONTRACT" SECTION I OF TENDER DOCUMENTS INVITATION

More information

To be franked for Rs 300 and Notarized

To be franked for Rs 300 and Notarized To be franked for Rs 300 and Notarized MCX - TMs CLEARING MEMBER - TRADING MEMBER AGREEMENT ( CMTM Agreement ) This Agreement is made on this day of, 20 at Between M/s ISSL SETTLEMENT & TRANSACTION SERVICES

More information

2011 All Source RFP Exhibit I

2011 All Source RFP Exhibit I Prototype Natural Gas Tolling Agreement Term Sheet Background: This Prototype Natural Gas Tolling Agreement Term Sheet ( Term Sheet ) sets forth the current requirements that PSE wants the Respondent to

More information

WHITBY HYDRO CONNECTION AGREEMENT FOR A GENERATOR WITH MOMENTARY CLOSED TRANSITION OPERATION

WHITBY HYDRO CONNECTION AGREEMENT FOR A GENERATOR WITH MOMENTARY CLOSED TRANSITION OPERATION WHITBY HYDRO CONNECTION AGREEMENT FOR A GENERATOR WITH MOMENTARY CLOSED TRANSITION OPERATION This Connection Agreement ( Agreement ) is made and entered into this day of, 20, by Whitby Hydro ( the Distributor

More information

JAPAN INTERNATIONAL COOPERATION AGENCY. General Terms and Conditions for Japanese ODA Loans

JAPAN INTERNATIONAL COOPERATION AGENCY. General Terms and Conditions for Japanese ODA Loans JAPAN INTERNATIONAL COOPERATION AGENCY General Terms and Conditions for Japanese ODA Loans April 2012 General Terms and Conditions for Japanese ODA Loans Table of Contents Article Number Heading Page Article

More information

Commercial Terms and Conditions

Commercial Terms and Conditions Renewable energy buyback Commercial Terms and Conditions For purchase of Renewable Source Electricity Between Horizon Power and Customer North West Integrated System and Regional Non-Interconnected Systems

More information

Title Page Southern California Edison Company Tariff Title: Rate Schedule Tariff Record Title: Rate Schedule FERC No. 425 FERC FPA Electric Tariff AMENDED AND RESTATED ELDORADO SYSTEM OPERATINGAGREEMENT

More information

ELECTRICITY ACT, 2005

ELECTRICITY ACT, 2005 ELECTRICITY ACT, 2005 ARRANGEMENTOF SECTIONS Section PART 1 PRELIMINARY 1. Short title 2. Interpretation 3. Objectives PART II FUNCTIONS OF THE DEPARTMENT OF STATE 4. Functions of the Department of State

More information

CONSTRUCTION AND DEVELOPMENT OF ASHIANA-E-QUAID, LAHORE ON PUBLIC PRIVATE PARTNERSHIP (PPP) DEVELOPMENT AGREEMENT [DRAFT]

CONSTRUCTION AND DEVELOPMENT OF ASHIANA-E-QUAID, LAHORE ON PUBLIC PRIVATE PARTNERSHIP (PPP) DEVELOPMENT AGREEMENT [DRAFT] CONSTRUCTION AND DEVELOPMENT OF ASHIANA-E-QUAID, LAHORE ON PUBLIC PRIVATE PARTNERSHIP (PPP) DEVELOPMENT AGREEMENT [DRAFT] DEVELOPMENT AGREEMENT This Development Agreement is entered into at Lahore on this

More information

[MASTER TRUST LOAN AGREEMENT - AUTHORITY FORM] LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER]

[MASTER TRUST LOAN AGREEMENT - AUTHORITY FORM] LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER] Resolution No 14-64, Exhibit A2 [MASTER TRUST LOAN AGREEMENT - AUTHORITY FORM] LOAN AGREEMENT BY AND BETWEEN NEW JERSEY ENVIRONMENTAL INFRASTRUCTURE TRUST AND [NAME OF BORROWER] DATED AS OF MAY 1, 2015

More information

ANNEX A Standard Special Conditions For The Salvation Army

ANNEX A Standard Special Conditions For The Salvation Army ANNEX A Standard Special Conditions For The Salvation Army TO BE ATTACHED TO AIA B101-2007 EDITION ABBREVIATED STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT 1. Contract Documents. This Annex supplements,

More information

WHOLESALE BROKER/CONTRACTOR AGREEMENT

WHOLESALE BROKER/CONTRACTOR AGREEMENT WHOLESALE BROKER/CONTRACTOR AGREEMENT THIS WHOLESALE BROKER/CONTRACTOR AGREEMENT is entered into as of by and between Bondcorp Realty Services, Inc. ("Lender"), and, A CORPORATION ( Broker/Contractor ),

More information

Meghalaya State Electricity Regulatory Commission

Meghalaya State Electricity Regulatory Commission Meghalaya State Electricity Regulatory Commission SHILLONG Notification Dated: 12 th March, 2015 No.MSERC/RPO/2015/02: In exercise of power conferred under section 61, 66, 86(1)(e) and 181 of the Electricity

More information

NATIONAL COMMODITY CLEARING LIMITED

NATIONAL COMMODITY CLEARING LIMITED NATIONAL COMMODITY CLEARING LIMITED Circular to all Members of the Clearing Corporation Circular No. : NCCL/MEMBERSHIP-002/2018 Date : September 26, 2018 Subject : NCCL Membership - Submission of Undertaking

More information

Standard Form Project Agreement (hub DBFM Projects)

Standard Form Project Agreement (hub DBFM Projects) Standard Form Project Agreement (hub DBFM Projects) Version 2: June 20122.1: October 2013 . THIS STANDARD FORM PROJECT AGREEMENT MUST BE USED IN CONJUNCTION WITH THE STANDARD PROJECT AGREEMENTS USER S

More information

POWER PURCHASE and INTERCONNECTION AGREEMENT FOR SNAP GENERATION

POWER PURCHASE and INTERCONNECTION AGREEMENT FOR SNAP GENERATION POWER PURCHASE and INTERCONNECTION AGREEMENT FOR SNAP GENERATION This Agreement, effective the day of, 20 by and between PUBLIC UTILITY DISTRICT NO. 1 OF Chelan COUNTY, WASHINGTON, herein referred to as

More information

DRAFT PRE BID (MoU) (Rev-1) Memorandum of Understanding

DRAFT PRE BID (MoU) (Rev-1) Memorandum of Understanding DRAFT PRE BID (Rev-1) Memorandum of Understanding This Memorandum of Understanding (hereinafter referred to as MOU ) is made on the [Insert day] of Insert month] of Two Thousand and [Insert Year] at [Place].

More information

VKP WAREHOUSING (PTY) LTD

VKP WAREHOUSING (PTY) LTD VKP WAREHOUSING (PTY) LTD STANDARD TERMS AND CONDITIONS OF TRADE SOLE CONDITIONS VKP Warehousing ( the Company ) undertakes all services subject solely to the following Conditions which can be varied only

More information

GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010

GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010 GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010 No. 1/17/09-EB(PR)/450.- Whereas the State of Punjab is presently facing acute power shortages. And therefore,

More information

State Policy on Chhattisgarh Special Economic Zone. Government of Chhattisgarh. Department of Commerce and Industries

State Policy on Chhattisgarh Special Economic Zone. Government of Chhattisgarh. Department of Commerce and Industries (1) State Policy on Chhattisgarh Special Economic Zone Government of Chhattisgarh Department of Commerce and Industries 1.0 Preamble 1.1 Where as for augmenting infrastructure facilities for export production

More information

STANDARD TRADING TERMS AND CONDITIONS

STANDARD TRADING TERMS AND CONDITIONS STANDARD TRADING TERMS AND CONDITIONS The Customer s attention is drawn to the clauses of these Standard Trading Terms and Conditions which exclude or limit the Company s liability and those which require

More information

BE it enacted by Parliament in the Fifty-sixth Year of the Republic of India as follows:-

BE it enacted by Parliament in the Fifty-sixth Year of the Republic of India as follows:- ~ THE CREDIT INFORMATION COMPANIES (REGULATION) ACT, 2005 # NO. 30 OF 2005 $ [23rd June 2005.] + An Act to provide for regulation of credit information companies and to facilitate efficient distribution

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK SPECIAL OPERATIONS LOAN REGULATIONS Applicable to Loans Made by ADB from its Special Funds Resources DATED 1 JANUARY 2006 ASIAN DEVELOPMENT BANK SPECIAL OPERATIONS LOAN REGULATIONS

More information

EPC (ENGINEERING, PROCUREMENT AND CONSTRUCTION) AGREEMENT FOR

EPC (ENGINEERING, PROCUREMENT AND CONSTRUCTION) AGREEMENT FOR EPC (ENGINEERING, PROCUREMENT AND CONSTRUCTION) AGREEMENT FOR Design, Construction, Operation and Maintenance of Raw water Pumping Station and Raw water Transmission Main from Pipli Pumping Station (Pariyej

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Maharashtra Electricity Regulatory Commission (Standards of Performance of Distribution Licensees, Period for Giving Supply and Determination of Compensation)

More information

Expression of Interest. Procurement of Renewable Energy Under Short Term basis. Reliance Industries Limited In Gujarat and Maharashtra

Expression of Interest. Procurement of Renewable Energy Under Short Term basis. Reliance Industries Limited In Gujarat and Maharashtra Expression of Interest for Procurement of Renewable Energy Under Short Term basis To Reliance Industries Limited In Gujarat and Maharashtra Reliance Industries Limited Reliance Corporate Park, Thane-Belapur

More information

Town of Highlands Board Approved as of May 17, 2012

Town of Highlands Board Approved as of May 17, 2012 TOWN OF HIGHLANDS INTERCONNECTION AGREEMENT FOR SMALL PHOTOVOLTAIC GENERATION FACILITY OF 10 kw OR LESS This PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR SMALL GENERATION 10 kw or less (the Agreement ),

More information

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows: LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 100 KW AND LESS THAN OR EQUAL TO 1 MW TIER 3 This Interconnection Agreement

More information

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY No. 419 9 Shrawan, 1932(s) Ranchi, Saturday 31th July, 2010 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION, RANCHI (RENEWABLE PURCHASE OBLIGATION

More information

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

FEED-IN TARIFF CONTRACT (FIT CONTRACT) FEED-IN TARIFF CONTRACT (FIT CONTRACT) Version 2.1.1 March 22, 2013 SUPPLIER INFORMATION & ADDRESS 1. 2. SUPPLIER S ADDRESS COMPANY REPRESENTATIVE Fax: Phone: E-mail: 3. SUPPLIER INFORMATION Not a Non-Resident

More information

First Revised Sheet No. 448 Canceling Original WN U-60 Sheet No. 448 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 448 POWER SUPPLIER CHOICE

First Revised Sheet No. 448 Canceling Original WN U-60 Sheet No. 448 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 448 POWER SUPPLIER CHOICE First Revised Sheet No. 448 Canceling Original WN U-60 Sheet No. 448 1. ELIGIBILITY FOR SERVICE POWER SUPPLIER CHOICE All Special Contract Customers, and all Schedule 48 Customers as of March 9, 2001,

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized CONFORMED COPY

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized CONFORMED COPY Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 3239 IN Public Disclosure Authorized Public Disclosure Authorized (Private Power Utilities (TEC) Project) between INTERNATIONAL BANK FOR RECONSTRUCTION

More information

Prototype Wind PPA Term Sheet

Prototype Wind PPA Term Sheet Prototype Wind PPA Term Sheet Background: This Prototype Wind PPA Term Sheet ( Term Sheet ) sets forth the current requirements that PSE wants the Respondent to address or incorporate into any proposal

More information

OPERATION SERVICES AGREEMENT. Operation & Management of India International Convention & Expo Centre

OPERATION SERVICES AGREEMENT. Operation & Management of India International Convention & Expo Centre OPERATION SERVICES AGREEMENT Operation & Management of India International Convention & Expo Centre TABLE OF CONTENTS ARTICLE 1: DEFINITIONS AND INTERPRETATION... 3 1.1 DEFINITIONS...3 1.2 INTERPRETATION...3

More information

This agreement is made and executed at on this day of 20

This agreement is made and executed at on this day of 20 This agreement is made and executed at on this day of 20 Between: M/s. KUNVARJI FINSTOCK PVT. LTD. a body corporate, registered / incorporated under the provisions of Companies Act, 1956, having its registered

More information

SUBORDINATED NOTE PURCHASE AGREEMENT 1. DESCRIPTION OF SUBORDINATED NOTE AND COMMITMENT

SUBORDINATED NOTE PURCHASE AGREEMENT 1. DESCRIPTION OF SUBORDINATED NOTE AND COMMITMENT SUBORDINATED NOTE PURCHASE AGREEMENT This SUBORDINATED NOTE PURCHASE AGREEMENT (this Agreement ), dated as of the date it is electronically signed, is by and between Matchbox Food Group, LLC, a District

More information

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

FEED-IN TARIFF CONTRACT (FIT CONTRACT) FEED-IN TARIFF CONTRACT (FIT CONTRACT) Version 1.5.1 (July 15, 2011) CONTRACT IDENTIFICATION # FIT REFERENCE # FIT- FIT- CONTRACT DATE SUPPLIER SUPPLIER S ADDRESS SUPPLIER INFORMATION GROSS NAMEPLATE CAPACITY

More information

DRAFT (To be signed on Non-judicial stamp paper of Rs.100/-)

DRAFT (To be signed on Non-judicial stamp paper of Rs.100/-) DRAFT (To be signed on Non-judicial stamp paper of Rs.100/-) Memorandum of Understanding between NTPC Vidyut Vyapar Nigam Limited and solar power developer willing to migrate to National Solar Mission

More information

FIRM FIXED PRICE TERMS AND CONDITIONS AES-1 Applicable to Architect-Engineering Services Contracts INDEX CLAUSE NUMBER TITLE PAGE

FIRM FIXED PRICE TERMS AND CONDITIONS AES-1 Applicable to Architect-Engineering Services Contracts INDEX CLAUSE NUMBER TITLE PAGE Applicable to Architect-Engineering Services Contracts INDEX CLAUSE NUMBER TITLE PAGE 1. DEFINITIONS 1 2. COMPOSITION OF THE ARCHITECT-ENGINEER 1 3. INDEPENDENT CONTRACTOR 1 4. RESPONSIBILITY OF THE ARCHETECT-ENGINEER

More information

STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission

STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission This STANDARD INTERCONNECTION AGREEMENT, (the Agreement ), is entered into this day of, 20 by and between, hereinafter called Customer

More information

Agreement for Sale of Shares of a Private Limited Company

Agreement for Sale of Shares of a Private Limited Company Agreement for Sale of Shares of a Private Limited Company THIS AGREEMENT made at this day of 200 BETWEEN (1) ABC (2) DEF and (3) GHI, all having their address at, hereinafter jointly referred to as THE

More information

MISSOURI SERVICE AREA

MISSOURI SERVICE AREA MO.P.S.C. SCHEDULE NO. 6 1 st Revised 94 PURPOSE RIDER RC RENEWABLE CHOICE PROGRAM The purpose of the Renewable Choice Program ( Program ) is to offer eligible Customers an opportunity to subscribe to

More information

Taunton Municipal Lighting Plant. This INTERCONNECTION & NET METERING AGREEMENT 1. CUSTOMER ELECTRIC GENERATING SYSTEM

Taunton Municipal Lighting Plant. This INTERCONNECTION & NET METERING AGREEMENT 1. CUSTOMER ELECTRIC GENERATING SYSTEM Taunton Municipal Lighting Plant INTERCONNECTION & NET METERING AGREEMENT For Customer-Owned, Grid-Connected Electric Generating Systems of 60kW or Less This INTERCONNECTION & NET METERING AGREEMENT (

More information

Renewable Generation (Category 1-20 kw and less):

Renewable Generation (Category 1-20 kw and less): Renewable Generation (Category 1-20 kw and less): Net Metering Program Interconnection Program Application Parallel Operating Agreement Net Metering Program What is net metering? Net metering is a tool

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010 UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION No. UPERC/Secy/Regulation/10-787 Lucknow : Dated, 17 th August, 2010 In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity

More information

INTERCONNECTION GENERATION AND NET METERING POLICY

INTERCONNECTION GENERATION AND NET METERING POLICY INTERCONNECTION GENERATION AND NET METERING POLICY Manual for Member Owned Interconnection Generation Facilities Equal to 100 kw or Less Revised: May 11, 2015 Approved: August 25, 2014 Effective: August

More information

HOUSING CHAPTER 199 HOUSING

HOUSING CHAPTER 199 HOUSING [CH.199 1 CHAPTER 199 LIST OF AUTHORISED PAGES 1 8 LRO 1/2010 9 12 Original Service 13 14 LRO 1/2010 15 16 Original Service 17 18 LRO 1/2010 19 20 Original Service 21 22 LRO 1/2010 23 28 Original Service

More information

Electro Optic Systems Holdings Limited Share Plan Trust

Electro Optic Systems Holdings Limited Share Plan Trust Electro Optic Systems Holdings Limited Share Plan Trust Trust Deed Electro Optic Systems Holdings Limited (Company) Electro Optic Systems Holdings Limited (Trustee) Level 40 Governor Macquarie Tower 1

More information

Invoice. GPM Realty Group LLC 2 Progress Drive #4398 Clifton Park, NY 12065

Invoice. GPM Realty Group LLC 2 Progress Drive #4398 Clifton Park, NY 12065 Invoice GPM Realty Group LLC 2 Progress Drive #4398 Clifton Park, NY 12065 Billing Address Redburn Development-South Lake Apartments South Lake Ave Assoc., LLC 255 Washington Ave Ext. Suite 103 Albany,

More information

CONSULTING AGREEMENT STANDARD TERMS AND CONDITIONS

CONSULTING AGREEMENT STANDARD TERMS AND CONDITIONS CONSULTING AGREEMENT STANDARD TERMS AND CONDITIONS The following Standard Terms and Conditions, together with the attached scope of services constitute the terms of the Agreement between ("Consultant")

More information

Holden Municipal Light Department Interconnection Agreement for Net Metering Service

Holden Municipal Light Department Interconnection Agreement for Net Metering Service This agreement dated the day of, 20, ( Agreement ) is by and between Holden Municipal Light Department ( Department ), and, ( Customer ) (Department and Customer referred to as Parties ). Whereas, Customer

More information

Clearing Member Trading Member Agreement. This Agreement is made on this day of, 20, 20 between :

Clearing Member Trading Member Agreement. This Agreement is made on this day of, 20, 20 between : Clearing Member Trading Member Agreement This Agreement is made on this day of, 20, 20 between : IL&FS SECURITIES SERVICES LIMITED, a Company having its registered office at IL&FS House, Raheja Vihar,

More information

Renewable Generation (Category 1 20 kw and less):

Renewable Generation (Category 1 20 kw and less): Renewable Generation (Category 1 20 kw and less): Net Metering Program Interconnection Program Application Parallel Operating Agreement Net Metering Program What is net metering? Net metering is a tool

More information