Independent Accountant s Report On Applying Agreed-Upon Procedures. Rock Springs Elementary School Replacement June 4, 2014

Size: px
Start display at page:

Download "Independent Accountant s Report On Applying Agreed-Upon Procedures. Rock Springs Elementary School Replacement June 4, 2014"

Transcription

1 Independent Accountant s Report On Applying Agreed-Upon Procedures Rock Springs Elementary School Replacement June 4, 2014 The School Board of Orange County, Florida Orlando, Florida We have performed the procedures enumerated below, which were agreed to by The School Board of Orange County, Florida ( OCPS ), solely to assist you in certifying the final contract value (contract dated March 28, 2011) to Turner Company (the Manager ), based upon the total costs of construction for the Rock Springs Elementary School Replacement (the Project ) and to certify certain other Project costs. This agreed-upon procedures engagement was conducted in accordance with attestation standards established by the American Institute of Certified Public Accountants. The sufficiency of these procedures is solely the responsibility of the party specified in this report. Consequently, we make no representation regarding the sufficiency of the procedures described below either for the purpose for which this report has been requested or for any other purpose. The procedures applied and the related findings are as follows: 1. We obtained copies of the contract documents between OCPS and the Manager and read the documents noting items of financial and attestation significance, including provisions relative to the cost of work, fee arrangements, bonds and insurance, owner direct purchases, and the owner controlled insurance program ( OCIP ). 2. We inquired of the contracting parties to determine if there were any disputed provisions relative to the Project, or if there were any other unresolved disputes, including disputes between the Manager and their subcontractors. There were none noted. 3. We requested from the Manager a reconciliation of the final pay application to the job cost detail; however, despite repeated attempts, none was provided. As a result, no evaluation could be performed on the differences between the job cost detail provided by the Manager and the amounts contained in the final pay application. As a result, we reduced the job costs to reflect agreement with the final pay application. Please see Exhibit A.

2 4. We reviewed the construction costs, as documented by the Manager for compliance with the contract documents, including the following: a. vouched all costs in excess of $50,000 (as determined by phase totals on the Manager s job cost). for subcontract costs that qualify, we examined the subcontract and all the change orders to the subcontract, comparing the adjusted contract amount to the amount in the Manager s job cost and the total of the Manager s payments to the subcontractor. We noted approximately $13,000 of executed subcontractor change orders for which there was no supporting pricing documentation retained by the Manager. Additionally, we traced owner direct purchase amounts per OCPS to deductive change orders to the subcontractor to ensure that such subcontracts had been reduced for the purchases. The owner direct purchase log submitted by OCPS did not properly categorize all invoices to the respective subcontractor correctly. Therefore, CRI reviewed the owner direct purchase detail, determined the proper categorization to the subcontractors, and reconciled this list to the subcontractor deductive change orders without exception. for reimbursable labor costs, we chose a sample from the payroll line items in the Manager s job cost and traced each line item selected to time sheets and pay rate authorizations. CRI noted that Manager personnel, performing rough carpentry work, were paid between $30.61 and $37.82 per hour, excluding labor burden. for other items that qualified, we traced the charge to vendor invoices and evidence of payment. We examined supporting documentation for bond and subguard charges. b. reviewed the costing of change orders between OCPS and the Manager for conformity to the contract documents. We reconciled the owner direct purchases, per the ODP Log to deductive change orders to the guaranteed maximum price. Also, obtained the summary of OCIP results from the insurance carrier and traced the OCIP credits to deductive change orders. c. reviewed Manager labor burden percentage, if applicable, for appropriateness as well as conformity to the contract documents. The labor burden was established in the contract documents at 35%, we noted the Manager charged burden in excess of this percentage for its selfperformed labor. Please see Exhibit A. d. reviewed and inquired of the Manager regarding related party charges to the Project. The Manager self-performed approximately $35,000 of rough carpentry work, and $10,500 of IT service. Both of these scopes of work were originally to be performed by others, and neither was approved in writing by the Owner prior to the commencement of the work, as is required by the Agreement in paragraph The Manager also utilized a related entity, Turner Surety and Insurance Brokerage, Inc., as the broker for the subguard policy. CRI removed the fees associated with this transaction, please see the subguard adjustment on Exhibit A. e. reviewed posting dates in the job cost for charges incurred prior to the commencement date set forth in the contract amendments.

3 f. reviewed Manager fees and general conditions for conformity to the contract documents. Additionally, we reviewed the Manager s actual compensation for a sample of general conditions labor (included in the lump sum general conditions) for accuracy of base salary, application of contracted labor burden percentage, and personnel appropriateness to the Project. We found instances where the base rates included in the general conditions were higher than the actual compensation, however, overall the rates in the contract were higher than the actual rates by approximately.5% for the sample. g. reviewed actual contingency costs, and reviewed the contingency log for proper authorization and resolution of final balances. h. recalculated the contract guaranteed maximum price and actual costs of construction based upon the Manager s records. The results are shown in Exhibit A Project Costs. 5. Regarding the completion of the Project, we performed the following: a. we inquired and examined support that the Project was completed within the time constraints stated in the contract. b. we examined the Certificate of Substantial Completion and the Certificate of Final Inspection, signed by the Architect, verifying that the Project was completed in accordance with the contract. We noted that the date of the Architect s sign off on the Certificate of Final Completion was May 1, 2013, which is 25 days after the contractually required date of final completion (120 days after the date of substantial completion). No provision was noted stating liquidated damages for non-compliance with the date of final completion. 6. We obtained evidence of the SAP/Purchase order reconciliation from OCPS and ensured the final contract value to the Manager was accurate and reflected final pre-attestation adjustments. 7. We obtained a representation from the Manager that the job cost is complete and represents properly reimbursable and paid costs under the terms of the contract. The Manager also represented that all related party transactions have been disclosed to us. We were not engaged to, and did not, conduct an audit, the objective of which would be the expression of an opinion on the specified elements, accounts, or items. Accordingly, we do not express such an opinion. Had we performed additional procedures, other matters might have come to our attention that would have been reported to you. This report is intended solely for the information and use of The School Board of Orange County, Florida, and is not intended to be and should not be used by anyone other than the specified party. Orlando, Florida June 4, 2014

4 Orange County Public Schools Rock Springs Elementary School Replacement Exhibit A - Project Costs Calculation of the construction cost plus fee: Manager job costs - Amendment #1 $ 8,136,507 Remove payments to associate partner (177,658) Remove non-billable items (27,802) Remove overage in self-performed rough carpentry work (10,522) Remove overage in general requirements (11,010) Subcontractor acceleration costs (15,000) Adjust labor burden to fixed rate on self performed labor (8,895) Adjust subguard calculation (13,388) Adjust subcontractor charges (3,488) Improper subcontractor charges (3,215) Subcontractor markups in excess of contractual limits (1,291) Remove repair items not properly backcharged (3,912) 7,860,326 Original lump sum general conditions - Amendment #1 540,000 Calculation of construction management fee: Original construction management fee - Amendment #1 569,996 Additional construction management fee through contingency 3,564 Reduction for material test failure and standby time (2,611) 570,949 cost plus fee $ 8,971,275 Calculation of adjusted guaranteed maximum price: Amendment #1 $ 13,449,810 Adjustments from change orders per the Manager (4,434,773) Adjusted guaranteed maximum price $ 9,015,037 cost, lesser of construction cost plus fee and adjusted guaranteed maximum price $ 8,971,275 Owner direct purchases 3,866,489 $ 12,837,764

5 Management Response to Audit Report for the Rock Spring ES Project ISSUES NOTED AREA MANAGEMENT RESPONSE Approximately $13,000 of executed subcontractor change orders for which there was no supporting pricing documentation retained by the construction manager. The $13,000 reference appears to be for changes between the CM and their subcontractors which were not presented to the owner for review and consideration. It will be stressed with all Contractors that their responsibility per their agreement is to maintain accurate and complete backup documentation of all invoicing from their sub-contractors. The owner direct purchase log submitted by OCPS did not properly categorize all invoices to the respective subcontractor. Manager personnel performing rough carpentry work were paid between $30.61 and $37.82 per hour, excluding labor burden. The labor burden was established in the contract documents at 35%, we noted the construction manager charged burden in excess of this percentage for its self-performed work. The construction manager selfperformed approximately $35,000 of rough carpentry work and $10,500 of IT service. Both of these scopes of work were originally to be performed by others and neither was approved in writing by the Owner prior to compliance will be summarized on an audit findings memo to Historically, the ODP information provided for project audit lists purchase order information by vendor with corresponding subcontractor name only. Comment noted. It is to be verified that selfperformed work is being performed by tradesman who are not over qualified for the task and thus avoiding labor rates that are higher than the norm for an item of work. compliance will be summarized in an audit findings memo to compliance will be summarized in an audit findings memo to In addition to what is stated in the contract agreement (Exhibit A Section 36.3), request for payment for self-performed work will be checked and verified against the allowed contract limits prior to approval of the relevant application for payment. 1

6 Management Response to Audit Report for the Rock Spring ES Project commencement of the work. The date of the Architect s sign off on the Certificate of Final Completion was May 1, 2013, which is 25 days after the contractually required date of final completion. Request for substituting subcontractors are to be vetted per Exhibit A Section 36.3 of the contract (per extract below). compliance will be summarized in an audit findings memo to The CM Agreement for Rock Springs ES does not allow for assessing liquidated damages relating to work during the final completion phase. Recent revisions to the agreement include the assessment of liquidated damages to the Management firm when failing to achieve final completion on the stipulated date. 2

Independent Accountant s Report On Applying Agreed Upon Procedures

Independent Accountant s Report On Applying Agreed Upon Procedures Independent Accountant s Report On Applying Agreed Upon Procedures The School Board of Orange County, Florida INDEPENDENT ACCOUNTANT S REPORT ON APPLYING AGREED UPON PROCEDURES December 10, 2015 The School

More information

Independent Accountant s Report On Applying Agreed Upon Procedures

Independent Accountant s Report On Applying Agreed Upon Procedures Independent Accountant s Report On Applying Agreed Upon Procedures The School Board of Orange County, Florida INDEPENDENT ACCOUNTANT S REPORT ON APPLYING AGREED UPON PROCEDURES The School Board of Orange

More information

Independent Accountant s Report On Applying Agreed-Upon Procedures. Sessions Property/Siplin Road Elementary School January 2, 2014

Independent Accountant s Report On Applying Agreed-Upon Procedures. Sessions Property/Siplin Road Elementary School January 2, 2014 Carr, Riggs & Ingram, LLC 1031 West Morse Blvd., Ste 200 Winter Park, Florida 32789 (407) 644-7455 (407) 628-5277 (fax) www.cricpa.com Independent Accountant s Report On Applying Agreed-Upon Procedures

More information

Independent Accountant s Report On Applying Agreed-Upon Procedures. Wheatley Elementary School Comprehensive Needs Project April 22, 2015

Independent Accountant s Report On Applying Agreed-Upon Procedures. Wheatley Elementary School Comprehensive Needs Project April 22, 2015 Independent Accountant s Report On Applying Agreed-Upon Procedures Wheatley Elementary School Comprehensive Needs Project April 22, 2015 The School Board of Orange County, Florida Orlando, Florida We have

More information

Independent Accountant s Report On Applying Agreed-Upon Procedures. Aloma Elementary School Comprehensive Needs February 3, 2015

Independent Accountant s Report On Applying Agreed-Upon Procedures. Aloma Elementary School Comprehensive Needs February 3, 2015 Independent Accountant s Report On Applying Agreed-Upon Procedures Aloma Elementary School Comprehensive Needs February 3, 2015 The School Board of Orange County, Florida Orlando, Florida We have performed

More information

Independent Accountant s Report On Applying Agreed Upon Procedures

Independent Accountant s Report On Applying Agreed Upon Procedures Independent Accountant s Report On Applying Agreed Upon Procedures The School Board of Orange County, Florida Comprehensive Needs Project at Apopka Elementary School INDEPENDENT ACCOUNTANT S REPORT ON

More information

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated: Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,

More information

The City of Tarpon Springs

The City of Tarpon Springs Prepared By: Carr, Riggs & Ingram August 29, 2018 The City of Tarpon Springs Contract Compliance Assessment of The Reverse Osmosis Water Treatment Facility Table of Contents Transmittal Letter... 1 Executive

More information

AIA Document A102 TM 2007

AIA Document A102 TM 2007 AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the

More information

Document A Exhibit A

Document A Exhibit A Design-Build Amendment Document A141 2014 Exhibit A This Amendment is incorporated into the accompanying AIA Document A141 2014, Standard Form of Agreement Between Owner and Design-Builder dated the day

More information

CONSTRUCTION CONTRACT ANALYSIS. Robert Zellmer, CCA Manager Baker Tilly

CONSTRUCTION CONTRACT ANALYSIS. Robert Zellmer, CCA Manager Baker Tilly CONSTRUCTION CONTRACT ANALYSIS Robert Zellmer, CCA Manager Baker Tilly OVERVIEW Today s topics: Contract Key Terms Documentation Requirements Red Flags LEARNING OBJECTIVE Deepen management s understanding

More information

Forsyth County Board of Education

Forsyth County Board of Education Forsyth County Board of Education Performance Audit on Special Purpose Local Option Sales Tax For The Year Ended June 30, 2014 200 Galleria Parkway, Suite 1700 Atlanta, Georgia 30339 Phone: (800) 277-0080

More information

Conformity with GAAP is essential for consistency and comparability in financial reporting.

Conformity with GAAP is essential for consistency and comparability in financial reporting. GENERALLY ACCEPTED ACCOUNTING PRINCIPLES (GAAP) & FINANCIAL ACCOUNTING STANDARD BOARD (FASB) The term generally accepted accounting principles refer to the standards, rules, and procedures that serve as

More information

Document A Exhibit A Determination of the Cost of the Work

Document A Exhibit A Determination of the Cost of the Work Document A121 2014 Exhibit A Determination of the Cost of the Work THE OWNER: (Name, legal status, address and other information) THE CONTRACTOR: (Name, legal status, address and other information) This

More information

INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES

INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES Lakefield Airport Authority 6177 State Route 219 Celina, Ohio 45822 We have performed the procedures enumerated below, with which the Authority

More information

DeKalb County Board of Education

DeKalb County Board of Education DeKalb County Board of Education Performance Audit on Education - Special Purpose Local Option Sales Tax For The Fiscal Year Ended June 30, 2017 200 Galleria Parkway, Suite 1700 Atlanta, Georgia 30339

More information

AIA Document A102 TM 2007

AIA Document A102 TM 2007 AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the

More information

Performing Contract Audits. Thomas A. Mock, CIA, CCA Director of Internal Audit Lake County Schools

Performing Contract Audits. Thomas A. Mock, CIA, CCA Director of Internal Audit Lake County Schools Performing Contract Audits Thomas A. Mock, CIA, CCA Director of Internal Audit Lake County Schools Overview of Session Types of Construction Contracts Architectural Agreement Contract Documents Bonds and

More information

Attachment D Program Specific Audit Requirements

Attachment D Program Specific Audit Requirements Attachment D Requirements The must encompass an audit of The Children s Trust Contracts in accordance with section P3: of this Contract. The comprehensive nature of auditing performed in accordance with

More information

AIA Document A102 TM 2007

AIA Document A102 TM 2007 AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the

More information

IC Chapter Guaranteed Savings Contracts; Energy Efficiency Programs Used by School Corporations

IC Chapter Guaranteed Savings Contracts; Energy Efficiency Programs Used by School Corporations IC 36-1-12.5 Chapter 12.5. Guaranteed Savings Contracts; Energy Efficiency Programs Used by School Corporations IC 36-1-12.5-0.5 "Actual savings" defined Sec. 0.5. As used in this chapter, "actual savings"

More information

AUDITING CONSTRUCTION CAPITAL PROJECTS 101

AUDITING CONSTRUCTION CAPITAL PROJECTS 101 AUDITING CONSTRUCTION CAPITAL PROJECTS 101 January 9, 2018 Adam Rouse Managing Consultant acrouse@bkd.com 1 TO RECEIVE CPE CREDIT Participate in entire webinar Answer polls when they are provided If you

More information

Agreed-Upon Procedures Report. Florida Court Clerks & Comptrollers and State of Florida Department of Revenue

Agreed-Upon Procedures Report. Florida Court Clerks & Comptrollers and State of Florida Department of Revenue Report and State of Florida Department of Revenue Thomas Howell Ferguson P.A. 2615 Centennial Blvd., Suite 200 Tallahassee, Florida 32308 Law, Redd, Crona & Munroe, P.A. 2075 Centre Pointe Blvd., Suite

More information

Orange County Public Schools. Audit of Citizen s Construction Oversight and Value Engineering (COVE) Reports

Orange County Public Schools. Audit of Citizen s Construction Oversight and Value Engineering (COVE) Reports 2014 Audit of Citizen s Construction Oversight and Value Engineering (COVE) Reports Orange County Public COVE Schools Report Audit Internal Audit Department April 21, 2014 Internal Audit Department - i

More information

! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information)

!  # $  % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information) ! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information) Wynne Public Schools P.O. Box 69 Wynne, AR 72396 Telephone

More information

WISCONSIN HOUSING AND ECONOMIC DEVELOPMENT AUTHORITY Low Income Housing Tax Credit (LIHTC) Program COST CERTIFICATION AUDIT GUIDE

WISCONSIN HOUSING AND ECONOMIC DEVELOPMENT AUTHORITY Low Income Housing Tax Credit (LIHTC) Program COST CERTIFICATION AUDIT GUIDE WISCONSIN HOUSING AND ECONOMIC DEVELOPMENT AUTHORITY Low Income Housing Tax Credit (LIHTC) Program COST CERTIFICATION AUDIT GUIDE REVISED NOVEMBER 13, 2007 BACKGROUND Owners of Projects consisting of more

More information

DRAFT COUNTY OF SACRAMENTO, CALIFORNIA

DRAFT COUNTY OF SACRAMENTO, CALIFORNIA COUNTY OF SACRAMENTO, CALIFORNIA Independent Accountant s Report on Applying Agreed-Upon Procedures on the Low and Moderate Income Housing Funds of the Former Redevelopment Agency of the County of Sacramento,

More information

Maryland Department of Commerce

Maryland Department of Commerce Maryland Department of Commerce Maryland Film Production Activity Tax Credit AGREED UPON PROCEDURES GUIDELINES An independent, third-party auditor s report on Agreed Upon Procedures is required as part

More information

Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form. McKee and Associates Architecture and Interior Design Addendum No. TWO Date: 12.21.18 Project: Re-Roofing Media Center/Classroom Building and Band Building at Valley High School for the Chambers County

More information

Certification of Financial Statements for ICT PSP projects

Certification of Financial Statements for ICT PSP projects DG INFORMATION SOCIETY AND MEDIA ICT Policy Support Programme Competitiveness and Innovation Framework Programme Certification of Financial Statements for ICT PSP projects Version 1.0 (03-03-2008) Certification

More information

CITY OF GLENDALE. Project: Project No.:

CITY OF GLENDALE. Project: Project No.: CITY OF GLENDALE CONSTRUCTION MANAGER AT RISK AGREEMENT Project: Project No.: TABLE OF CONTENTS SECTION PAGE Definitions... 1 Construction Services... 1 Representatives and Key Personnel.... 1 Documents...

More information

AIA Document A103 TM 2007

AIA Document A103 TM 2007 AIA Document A103 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work plus a fee without a Guaranteed Maximum Price AGREEMENT made as of the

More information

CONSTRUCTION AGREEMENT (Stipulated Sum) BY AND BETWEEN. NEW YORK UNIVERSITY SCHOOL OF MEDICINE, an administrative unit of NEW YORK UNIVERSITY

CONSTRUCTION AGREEMENT (Stipulated Sum) BY AND BETWEEN. NEW YORK UNIVERSITY SCHOOL OF MEDICINE, an administrative unit of NEW YORK UNIVERSITY CONSTRUCTION AGREEMENT (Stipulated Sum) BY AND BETWEEN NEW YORK UNIVERSITY SCHOOL OF MEDICINE, an administrative unit of NEW YORK UNIVERSITY - OWNER - AND [ ] - CONTRACTOR - --------- PROJECT Animal Imaging

More information

INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES

INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES 4215 County Road 23 Burgoon, Ohio 43407 We have performed the procedures enumerated below, which were agreed to by the Board of Trustees

More information

Accounting System Requirements

Accounting System Requirements Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily

More information

AIA Document A133 TM 2009

AIA Document A133 TM 2009 AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

More information

The Springs at Santa Rita Homeowners Association. Fiscal Policies and Procedures

The Springs at Santa Rita Homeowners Association. Fiscal Policies and Procedures The Springs at Santa Rita Homeowners Association Fiscal Policies and Procedures Table of Contents Accounting Procedures... 1 Basis of Accounting... 1 Journal Entries... 1 Bank Reconciliations... 1 Internal

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

EXTERIOR LIGHTING AND CONTROLS RETROFIT PHASE II PROJECT ENERGY SERVICES SADDLEBACK COLLEGE. April 25, Electricity Savings: 201,221 kwh/yr

EXTERIOR LIGHTING AND CONTROLS RETROFIT PHASE II PROJECT ENERGY SERVICES SADDLEBACK COLLEGE. April 25, Electricity Savings: 201,221 kwh/yr EXHIBIT A Page 1 of 1 EXTERIOR LIGHTING AND CONTROLS RETROFIT PHASE II PROJECT ENERGY SERVICES SADDLEBACK COLLEGE April 25, 2016 Based upon inspection form, site visit and rough savings calculation, San

More information

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner: Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AS MODIFIED BY OWNER AGREEMENT made as of the day of in the year (In words,

More information

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. Accounts Payable Obligations to pay for goods and services that have

More information

SECTION SUPPLEMENTARY CONDITIONS

SECTION SUPPLEMENTARY CONDITIONS SECTION 00800 SUPPLEMENTARY CONDITIONS PART 1 GENERAL 1.01 GENERAL CONDITIONS A. The Supplementary Conditions modify, delete and/or add to the General Conditions, AIA Document A201/Cma, Construction Management

More information

This Webcast Will Begin Shortly

This Webcast Will Begin Shortly This Webcast Will Begin Shortly If you have any technical problems with the Webcast or the streaming audio, please contact us via email at: splemoderator@smartpros.com Thank You! 1 KEY ISSUES IN NEGOTIATING

More information

METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS. Independent Accountants Report on Applying Agreed-Upon Procedures

METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS. Independent Accountants Report on Applying Agreed-Upon Procedures METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS Independent Accountants Report on Applying Agreed-Upon Procedures Year ended September 30, 2012 KPMG LLP 811 Main Street Houston, TX 77002 Independent

More information

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract

More information

For the Year Ended September 30, 2017

For the Year Ended September 30, 2017 Page 1 of 7 Report of Independent Certified Public Accountants on Applying Agreed-Upon Procedures for Federal Funding Allocation Data (IAS-FFA) Broward County, Florida - Transportation Department For the

More information

ROME TOWNSHIP ATHENS COUNTY DECEMBER 31, 2016 AND 2015 TABLE OF CONTENTS. Independent Accountants Report on Applying Agreed-Upon Procedures...

ROME TOWNSHIP ATHENS COUNTY DECEMBER 31, 2016 AND 2015 TABLE OF CONTENTS. Independent Accountants Report on Applying Agreed-Upon Procedures... ROME TOWNSHIP ATHENS COUNTY DECEMBER 31, 2016 AND 2015 TABLE OF CONTENTS TITLE PAGE Independent Accountants Report on Applying Agreed-Upon Procedures... 1 This page intentionally left blank. INDEPENDENT

More information

RICHLAND COUNTY, OHIO

RICHLAND COUNTY, OHIO SANDUSKY TOWNSHIP RICHLAND COUNTY, OHIO AGREED UPON PROCEDURES For the Years Ended December 31, 2016 and 2015 Board of Trustees 5201 Hook Road Crestline, Ohio 44827 We have reviewed the Independent Accountant

More information

MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT

MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT THE CONTRACT IS BETWEEN: OWNER: MARION COUNTY A political subdivision of the state of Oregon And TBD Contractor (referred

More information

OCIP Contract Language

OCIP Contract Language Page 1 of 12 7. Insurance Requirements OCIP Contract Language 7.1 COUNTY Provided Insurance. COUNTY will provide an Owner Controlled Insurance Program ( OCIP ) for the Project. The OCIP will be administered

More information

P&ERRY. Associates. d e. e C. MUHLENBERG TOWNSHIP PICKAWAY COUNTY Agreed-Upon Procedures For the Years Ended December 31, 2016 and 2015

P&ERRY. Associates. d e. e C. MUHLENBERG TOWNSHIP PICKAWAY COUNTY Agreed-Upon Procedures For the Years Ended December 31, 2016 and 2015 313 Second St. Marietta, OH 45750 740.373.0056 1907 Grand Central Ave. Vienna, WV 26105 304.422.2203 104 South Sugar St. St. Clairsville, OH 43950 740.695.1569 P&ERRY 1310 Market Street, Suite 300 Wheeling,

More information

Orange County Public Schools. Internal Audit Report. Liability Insurance Claims Process Audit

Orange County Public Schools. Internal Audit Report. Liability Insurance Claims Process Audit Orange County Public Schools Internal Audit Report Liability Insurance Claims Process Audit September 28, 2011 To: Rick Collins, Chief Financial Officer Leslie Komurke, Senior Administrator, Management

More information

Orlando-Orange County Expressway Authority

Orlando-Orange County Expressway Authority Orlando-Orange County Expressway Authority s Audit November 2012 2012 Protiviti Inc. All Rights Reserved. This document has been prepared for use by OOCEA s management, audit committee, and board of directors.

More information

PROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr.

PROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr. PROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr. (a) General. The Contractor is encouraged to develop, prepare, and submit

More information

Chapter 2 DESIGNER AGREEMENTS & PAYMENTS

Chapter 2 DESIGNER AGREEMENTS & PAYMENTS Chapter 2 DESIGNER AGREEMENTS & PAYMENTS 2.01 BASIC OWNER / DESIGNER AGREEMENT FORM A. Form 1. Document SBC-6 is the standard form authorized by the State Building Commission for a Basic Services agreement

More information

COWBOY JOE CLUB FINANCIAL REPORT JUNE 30, 2017

COWBOY JOE CLUB FINANCIAL REPORT JUNE 30, 2017 COWBOY JOE CLUB Report on the Application of Agreed-Upon Procedures to the Records of the University of Wyoming Cowboy Joe Club and to its System of Internal Accounting Control FINANCIAL REPORT JUNE 30,

More information

Exhibit. Owner Controlled Insurance Program. Insurance Requirements

Exhibit. Owner Controlled Insurance Program. Insurance Requirements Exhibit Owner Controlled Insurance Program Insurance Requirements 1. Owner Controlled Insurance Program. OWNER shall implement an Owner Controlled Insurance Program ( OCIP ) for the Project. The OCIP is

More information

CATTLEMEN S BEEF PROMOTION AND RESEARCH BOARD INDEPENDENT ACCOUNTANT S REPORT

CATTLEMEN S BEEF PROMOTION AND RESEARCH BOARD INDEPENDENT ACCOUNTANT S REPORT INDEPENDENT ACCOUNTANT S REPORT For Fiscal Years Ended September 30, 2008 and 2009 And for the Five Months Ended February 28, 2010 A1 Independent Accountant s Report on Applying Agreed-Upon Procedures

More information

AIA Document A133 TM 2009

AIA Document A133 TM 2009 AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

More information

WINROCK TOWN CENTER TAX INCREMENT DEVELOPMENT DISTRICT 1 REPORT OF INDEPENDENT ACCOUNTANTS ON THE APPLICATION OF AGREED UPON PROCEDURES

WINROCK TOWN CENTER TAX INCREMENT DEVELOPMENT DISTRICT 1 REPORT OF INDEPENDENT ACCOUNTANTS ON THE APPLICATION OF AGREED UPON PROCEDURES WINROCK TOWN CENTER TAX INCREMENT DEVELOPMENT DISTRICT 1 REPORT OF INDEPENDENT ACCOUNTANTS ON THE APPLICATION OF AGREED UPON PROCEDURES JUNE 30, 2015 TABLE OF CONTENTS WINROCK TOWN CENTER TAX INCREMENT

More information

Killer Contract Clauses. Presented by Ben Westcott Shareholder Andrews Myers, PC

Killer Contract Clauses. Presented by Ben Westcott Shareholder Andrews Myers, PC Killer Contract Clauses Presented by Ben Westcott Shareholder Andrews Myers, PC bwestcott@andrewsmyers.com Liability Considerations Design Defects Concealed Conditions Schedule Insurance Payment Terms

More information

Section: Major Maintenance and Repair Reserve Fund

Section: Major Maintenance and Repair Reserve Fund DEPARTMENT OF MANAGEMENT SERVICES ADMINISTRATIVE POLICY TITLE: Major Maintenance and Repair Reserve Fund Management EFFECTIVE: July 16, 2008 REVISED: February 19, 2018 POLICY NUMBER 08-101 Bureau of Private

More information

AIA CONTRACT DOCUMENTS

AIA CONTRACT DOCUMENTS AIA CONTRACT DOCUMENTS A101, A102 and A201 Sanjay Kurian Becker & Poliakoff, P.A. Forms of Documents AIA A101-2007 (Lump sum) AIA A102-2007 (Guaranteed Maximum Price) AIA A201-2007 (General Conditions)

More information

EXHIBIT A GENERAL ENGINEERING CONTRACT (GEC) - TRAFFIC AND REVENUE SCOPE OF SERVICES

EXHIBIT A GENERAL ENGINEERING CONTRACT (GEC) - TRAFFIC AND REVENUE SCOPE OF SERVICES EXHIBIT A GENERAL ENGINEERING CONTRACT (GEC) - TRAFFIC AND REVENUE SCOPE OF SERVICES Exhibit "A" SCOPE OF SERVICES General Engineering Contract - Traffic and Revenue FPN: TBD I. Purpose... A-1 II. Term

More information

Schedule A (Attached to Bill of Sale) (Contract Value includes all taxes, Description of Material, Description of Location)

Schedule A (Attached to Bill of Sale) (Contract Value includes all taxes, Description of Material, Description of Location) Form 633 9/11/08 PAYMENT CHECKLIST FOR STORED MATERIAL SUBCONTRACTOR DATE JOB NAME JOB # Executed Bill of Sale (with Subcontractor Corporate Seal) (Applicable if sub bought material from other vendors/suppliers)

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year «Two Thousand Fourteen» (In

More information

MISSOURI DEPARTMENT OF NATURAL RESOURCES SOIL AND WATER CONSERVATION DISTRICT - ENGAGEMENT PERIOD -

MISSOURI DEPARTMENT OF NATURAL RESOURCES SOIL AND WATER CONSERVATION DISTRICT - ENGAGEMENT PERIOD - OBJECTIVES 1. To determine that internal controls were adequate and functioning properly at the soil and water conservation district. 2. To determine that the soil and water conservation district was in

More information

CONSTRUCTION PROJECT EVALUATION CALIFORNIA STATE UNIVERSITY, FRESNO SAVE MART CENTER. September 26, 2005

CONSTRUCTION PROJECT EVALUATION CALIFORNIA STATE UNIVERSITY, FRESNO SAVE MART CENTER. September 26, 2005 CONSTRUCTION PROJECT EVALUATION CALIFORNIA STATE UNIVERSITY, FRESNO SAVE MART CENTER September 26, 2005 Prepared by: KPMG LLP 801 Second Avenue, Suite 900 Seattle, WA 98104 This report and all associated

More information

Owner-Contractor Construction Agreement For Owner Controlled Insurance Program

Owner-Contractor Construction Agreement For Owner Controlled Insurance Program Owner-Contractor Construction Agreement For Owner Controlled Insurance Program This agreement is entered into as of ( Effective Date ) between Lone Star College (the "College"), a public junior college

More information

DOCUMENT SUPPLEMENTARY CONDITIONS

DOCUMENT SUPPLEMENTARY CONDITIONS 1.1 GENERAL CONDITIONS DOCUMENT 007300 SUPPLEMENTARY CONDITIONS A. The Supplementary Conditions modify, delete and/or add to the General Conditions, AIA Document A201/Cma, Construction Management Edition,

More information

DRAFT FOR PUBLIC COMMENT

DRAFT FOR PUBLIC COMMENT CITY OF EL CENTRO SUCCESSOR AGENCY FOR THE FORMER REDEVELOPMENT AGENCY DUE DILIGENCE REVIEW PURSUANT TO AB1484 LOW AND MODERATE INCOME HOUSING FUND TABLE OF CONTENTS INDEPENDENT ACCOUNTANTS REPORT 3 ATTACHMENT

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION MODIFICATION PROCEDURES AND PRICING OF CHANGED WORK

DIVISION 1 GENERAL REQUIREMENTS SECTION MODIFICATION PROCEDURES AND PRICING OF CHANGED WORK DIVISION 1 GENERAL REQUIREMENTS SECTION 01 2600 MODIFICATION PROCEDURES AND PRICING OF CHANGED WORK PART 1 GENERAL 1.01 SUMMARY A. Section includes requirements that supplement the paragraphs of Document

More information

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents:

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: A101-2017: Standard Form of Agreement Between Owner and Contractor where

More information

APPENDIX B TO COMPREHENSIVE AGREEMENT UOSA CONTRACT VSS UOSA VEHICLE SERVICE STATION FORM OF STAGE 2: FINAL DESIGN AMENDMENT

APPENDIX B TO COMPREHENSIVE AGREEMENT UOSA CONTRACT VSS UOSA VEHICLE SERVICE STATION FORM OF STAGE 2: FINAL DESIGN AMENDMENT APPENDIX B TO COMPREHENSIVE AGREEMENT UOSA CONTRACT VSS UOSA VEHICLE SERVICE STATION FORM OF STAGE 2: This Stage 2: Final Design Amendment (Final Design Amendment) is an Amendment to the Comprehensive

More information

What Sureties Want To See In Financial Statements

What Sureties Want To See In Financial Statements What Sureties Want To See In Financial Statements October 28, 2010 John Reed, CPA, CCIFP Construction and Real Estate Group Principal, LarsonAllen LLP Nick Costa Account Executive, The Travelers Companies,

More information

To: Administration and Finance Committee Date: February 3, SUBJECT: Independent Auditor s Report on National Transit Database Report Form FFA-10

To: Administration and Finance Committee Date: February 3, SUBJECT: Independent Auditor s Report on National Transit Database Report Form FFA-10 To: Administration and Finance Committee Date: February 3, 2016 From: Erick Cheung Reviewed By: Director of Finance SUBJECT: Independent Auditor s Report on National Transit Database Report Form FFA-10

More information

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month and

More information

Metropolitan Nashville Airport Authority

Metropolitan Nashville Airport Authority Metropolitan Nashville Airport Authority MEMORANDUM TO: CC: FROM: Douglas E. Kreulen, Acting President and CEO Michael Lee, Chief Commercial Officer Davita Taylor, Chief of Staff, Bd. Liaison, Business

More information

Fiscal Guidelines For CSC Funded Programs FY 2016/2017

Fiscal Guidelines For CSC Funded Programs FY 2016/2017 Fiscal Guidelines For CSC Funded Programs FY 2016/2017 Effective Date: October 1, 2016 Table of Contents Introduction... 4 Goals of the Fiscal Guidelines... 4 Seeking CSC Budget Specialist Advice Technical

More information

Independent Accountants Report on Applying Agreed-Upon Procedures (Tier 4) For the Year Ended December 31, 2015

Independent Accountants Report on Applying Agreed-Upon Procedures (Tier 4) For the Year Ended December 31, 2015 EAST PECOS MUTUAL DOMESTIC WATER CONSUMERS ASSOCIATION Independent Accountants Report on Applying Agreed-Upon Procedures (Tier 4) For the Year Ended December 31, 2015 STATE OF NEW MEXICO East Pecos Mutual

More information

OSCEOLA COUNTY CLERK OF THE CIRCUIT COURT

OSCEOLA COUNTY CLERK OF THE CIRCUIT COURT OSCEOLA COUNTY CLERK OF THE CIRCUIT COURT FINANCIAL STATEMENTS Year Ended September 30, 2016 C O N T E N T S Page Number Financial Section Independent Auditor s Report 1 Financial Statements Balance Sheet

More information

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between SHORT FORM STANDARD SUBCONTRACT This Agreement is made this day of, 20, between (Contractor) and (Subcontractor). The work described in Section I below shall be performed in accordance with the prime contract

More information

CESSNA TOWNSHIP HARDIN COUNTY AGREED UPON PROCEDURES

CESSNA TOWNSHIP HARDIN COUNTY AGREED UPON PROCEDURES CESSNA TOWNSHIP HARDIN COUNTY AGREED UPON PROCEDURES FOR THE YEARS ENDED DECEMBER 31, 2012 AND 2011 INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES Cessna Township 7393 Township Road

More information

SPECIAL CONDITIONS OF CONTRACT

SPECIAL CONDITIONS OF CONTRACT SPECIAL CONDITIONS OF CONTRACT TABLE OF CONTENT PART A: STANDARD PROVISIONS... 95 A1 Scope of the System... 95 A2 Securities... 95 A2.1 Advance Payment Security... 95 A2.2 Performance Security... 95 A3

More information

BROWARD COUNTY TRANSIT DIVISION BROWARD COUNTY, FLORIDA INDEPENDENT ACCOUNTANTS' REPORT ON APPLYING AGREED-UPON PROCEDURES SEPTEMBER 30, 2016

BROWARD COUNTY TRANSIT DIVISION BROWARD COUNTY, FLORIDA INDEPENDENT ACCOUNTANTS' REPORT ON APPLYING AGREED-UPON PROCEDURES SEPTEMBER 30, 2016 Page 1 of 9 BROWARD COUNTY TRANSIT DIVISION BROWARD COUNTY, FLORIDA INDEPENDENT ACCOUNTANTS' REPORT ON APPLYING AGREED-UPON PROCEDURES SEPTEMBER 30, 2016 Page 2 of 9 One S.E. Third Avenue 110 East Broward

More information

APPENDIX A TO COMPREHENSIVE AGREEMENT UOSA CONTRACT S/1 BUILDING S/1 RENOVATIONS FORM OF STAGE 2: DESIGN-BUILD WORK AMENDMENT

APPENDIX A TO COMPREHENSIVE AGREEMENT UOSA CONTRACT S/1 BUILDING S/1 RENOVATIONS FORM OF STAGE 2: DESIGN-BUILD WORK AMENDMENT APPENDIX A TO COMPREHENSIVE AGREEMENT UOSA CONTRACT S/1 BUILDING S/1 RENOVATIONS FORM OF STAGE 2: DESIGN-BUILD WORK AMENDMENT This Stage 2: Design-Build Work Amendment ( DB Work Amendment) is an Amendment

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,

More information

The Harbor Science and Arts Charter School

The Harbor Science and Arts Charter School The Harbor Science and Arts Charter School Financial Statements and Supplemental Schedule Years Ended June 30, 2012 and 2011 The report accompanying these financial statements was issued by BDO USA, LLP,

More information

VILLAGE COMMUNITY DEVELOPMENT DISTRICT NO. 6. Basic Financial Statements. September 30, 2005

VILLAGE COMMUNITY DEVELOPMENT DISTRICT NO. 6. Basic Financial Statements. September 30, 2005 Basic Financial Statements (With Independent Auditors Report Thereon) Table of Contents Financial Section Independent Auditors Report on the Financial Statements 1 Management s Discussion and Analysis

More information

CONSTRUCTION PROJECT EVALUATION CALIFORNIA STATE UNIVERSITY, SACRAMENTO MODOC HALL PROJECT. September 26, 2005

CONSTRUCTION PROJECT EVALUATION CALIFORNIA STATE UNIVERSITY, SACRAMENTO MODOC HALL PROJECT. September 26, 2005 CONSTRUCTION PROJECT EVALUATION CALIFORNIA STATE UNIVERSITY, SACRAMENTO MODOC HALL PROJECT September 26, 2005 Prepared by: KPMG LLP 801 Second Avenue, Suite 900 Seattle, WA 98104 This report and all associated

More information

FISCAL POLICY MANUAL SUMMER 2018

FISCAL POLICY MANUAL SUMMER 2018 FISCAL POLICY MANUAL SUMMER 2018 Children s Services Council of St. Lucie County 546 NW University Boulevard, Suite 201 Port St. Lucie, Florida 34986 772.408.1100 (PHONE) 772.408.1111 (FAX) Web site: www.cscslc.org

More information

INSURANCE EXHIBIT TO CONSTRUCTION AGREEMENT Insurance Requirements Owner Controlled Insurance Program

INSURANCE EXHIBIT TO CONSTRUCTION AGREEMENT Insurance Requirements Owner Controlled Insurance Program *THIS INSURANCE EXHIBIT IS SUBJECT TO FINAL UPDATE BASED ON QUOTE NEGOTIATIONS AND DECISION BY OWNER TO IMPLEMENT THE OCIP PROGRAM FOR THIS PROJECT IT IS BEING PROVIDED FOR INFORMATION ONLY, TO PROSPECTIVE

More information

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS Section Page 8-1 BASIS AND MEASUREMENT OF PAYMENT QUANTITIES... 8.1 8-1.01 Unit Price Contracts... 8.1 8-1.02 Lump Sum or Job Contracts... 8.1 8-1.03

More information

Communication With Those Charged With Governance

Communication With Those Charged With Governance Communication With Those Charged With Governance Government Auditing Standards Report on the Financial Statements Management s Responsibility for the Financial Statements Auditor s Responsibility Government

More information

Department of Human Services Division of Medical Assistance and Health Services Transportation Broker Services Contract - Utilization

Department of Human Services Division of Medical Assistance and Health Services Transportation Broker Services Contract - Utilization New Jersey State Legislature Office of Legislative Services Office of the State Auditor Department of Human Services Division of Medical Assistance and Health Services Transportation Broker Services Contract

More information

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. Broad St., 4 th Floor, COLUMBUS, OHIO 43223

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. Broad St., 4 th Floor, COLUMBUS, OHIO 43223 RAILROAD AUDIT CIRCULAR No. 4V7-Draft OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. Broad St., 4 th Floor, COLUMBUS, OHIO 43223 SUBJECT: Subcontracted Costs (DRAFT FOR COMMENT PERIOD 2) Last

More information

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN THE DEKALB COUNTY BOARD OF EDUCATION AND THE CONSTRUCTION MANAGER Construction

More information

INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES

INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES 1398 South Fulton Street Port Clinton, Ohio 43452 We have performed the procedures enumerated below, which were agreed to by the Board

More information

DRAFT FOR PUBLIC COMMENT

DRAFT FOR PUBLIC COMMENT CITY OF IMPERIAL SUCCESSOR AGENCY FOR THE FORMER REDEVELOPMENT AGENCY DUE DILIGENCE REVIEW PURSUANT TO AB1484 LOW AND MODERATE INCOME HOUSING FUND TABLE OF CONTENTS INDEPENDENT ACCOUNTANTS REPORT 3 ATTACHMENT

More information