1 DATE: August 2, 2011 ADDENDUM NUMBER: 2 MODIFYING: PROJECT: DUE DATE AND TIME: FROM: TO: RFQ 963A SHUTDOWN CONTRACTOR SPECIALISTS August 18, 2011, 2:00 p.m. THE METROPOLITAN WATER DISTRICT OF SOUTHERN CALIFORNIA 700 North Alameda Street, Third Floor Los Angeles, California (213) All prospective bidders This addendum forms a part of the Request for Qualifications, RFQ 963A. Use RFQ 963A as originally issued to submit Statements of Qualifications and acknowledge receipt of this addendum and all previously issued addenda by completing Part 8, Acknowledgment of Addenda, of the Prequalification Questionnaire. This addendum consists of 2 pages of text and 47 pages of attachments. CHANGES TO PRIOR ADDENDA: 1. In Addendum 1, delete the paragraph below the heading TO: All prospective bidders, and replace with the following: This addendum forms a part of the Request for Qualifications, RFQ 963A. Use RFQ 963A as originally issued to submit Statements of Qualifications and acknowledge receipt of this addendum by completing Part 8, Acknowledgment of Addenda, of the Prequalification Questionnaire. 2. In Addendum 1, eliminate the response to Question and Answer No. 1 due to the re-issuance of the Prequalification Questionnaires (Prime Contractor and Subcontractor) in this addendum. Refer to the revised response under Question and Answer No. 1 in this addendum. CHANGES TO PREQUALIFICATION REQUIREMENTS: 3. In Section 1, Prime Contractor/Subcontractor Qualifications Paragraph 1.3A, change $5,000,000 and above to read: a minimum of $1,000,000 each 4. In Section 1, Prime Contractor/Subcontractor Qualifications Paragraph 1.3B, change $500,000 and above to read: a minimum of $500,000 each QUESTIONS AND CLARIFICATIONS: Requests for clarification of details on the provisions of the prequalification documents have been identified. The questions with the appropriate Metropolitan responses are as follows: (1) Question: Can Respondents who submitted the Statements of Qualifications (SOQs) under RFQ 963 use the same submittals for the re-advertised RFQ 963A? Answer: No. Respondents to RFQ963A shall use the revised Prequalification Questionnaire (Prime Contractor and Subcontractor) as issued in this addendum. Revisions made to the questionnaires are marked with a heavy line on the left hand margin for easier reference. (2) Question: Would Metropolitan consider lowering the currently required $5,000,000 for Prime Contractors threshold to a lower amount? August RFQ 963A

2 Addendum Number 2 Answer: Yes. The required minimum construction value for each project has been revised in this addendum. (3) Question: Please clarify if the three projects must all be a minimum of $5,000,000 each or if the three projects combined must total a minimum of $5,000,000? Answer: Each of the three projects shall have a minimum value of at least $1,000,000 as revised in this addendum. (4) Question: In reference to Question 3, must all three projects include a shutdown component or can these three projects involve water/wastewater treatment plant that does not include shutdown work? Answer: Metropolitan is prequalifying contractors that are capable of handling repair works during shutdown conditions, thus, the experience required calls for each project to include a shutdown component. (5) Question: In Section 1, Paragraphs 1.3A and 1.3B, Respondents are required to have completed at least three projects of certain values. However, in the Prequalification Questionnaires (Prime Contractor and Subcontractor), under Part 6 (A, B, and C), Respondents are required to list five projects. Please clarify. Answer: Part of the minimum requirements for the first phase of the evaluation (Part 1A) is for Respondents to have completed at least three shutdown related projects meeting the minimum values as revised in this addendum. For the second phase of the evaluation for the applicable category, Respondents shall list up to five projects completed in the last five years (Parts 6A and 6B) or ten years (Part 6C). The first three projects shall be the shutdown related projects meeting the minimum values specified, while the other two projects shall be shutdown related projects of any size. END OF ADDENDUM August RFQ 963A

3 RFQ NO. 963A SHUTDOWN CONTRACTOR SPECIALIST PREQUALIFICATION QUESTIONNAIRE (PRIME CONTRACTOR) Prequalifying under the following category/ies: Pipeline Repairs Mechanical and Rotating Equipment Repairs Electrical and Power Generation Repairs COMPANY INFORMATION: RESPONDENT/COMPANY NAME: ADDRESS: PRINCIPAL OFFICE: PHONE: FAX: CONTACT PERSON: PHONE: FAX: ADDRESS: -1-

4 PART 1: MINIMUM REQUIREMENTS A. Respondents will be immediately rated fail if the answer to any of questions 1 through 5 is No. 1. Does the Respondent possess a valid and current California Contractor s license for the types of projects, for which it intends to submit a bid? Yes -2- No 2. Has the respondent completed at least three projects involving repairs/new construction valued at $1,000,000 each or more under the qualifying category in shutdown conditions requiring 24/7 operations within the last five (5) years? Yes No 3. Does the Respondent have a liability insurance policy with a policy limit of at least $2,000,000 per occurrence and $2,000,000 aggregate (will vary dependent upon project size)? Yes No 4. Does the Respondent have a current workers compensation insurance policy as required by the Labor Code or is legally self-insured pursuant to Labor Code section 3700 et. seq.? Yes No 5. Have you attached a letter of bond-ability confirming name, address and telephone number of a contact for a California admitted surety? The letter must include both single and aggregate bonding capacity totals. Yes No B. Respondents will be immediately rated fail if the answer to any of questions 6 through 10 is Yes 6. In the last five years, has your firm had its Contractors license suspended? Yes No 7. In the last five years, has your firm, or any officer, been convicted of a crime involving the awarding of a contract of a government (local, state or federal) construction project, or the bidding or performance of a government contract? Yes No 8. In the last five years, has your firm been defaulted or terminated by an owner (other than for convenience of the project owner) or has your surety completed a contract for your firm? Yes No 9. At the time of submitting this pre-qualification form, is your firm ineligible to bid on or be awarded any public works contract, or perform as a subcontractor on a public works contract? Yes No 10. Has your firm, or any person, ever been found guilty in a criminal action, for making any false claim or material misrepresentation to any public agency or entity? Yes No

5 PART 2 - CURRENT ORGANIZATION AND BUSINESS STRUCTURE 1. Please check appropriate organizational structure: Corporation Partnership Other 2. If a corporation, answer the following: a. Date of incorporation: b. State of incorporation: c. List Board of Directors and Titles: Sole Proprietorship Joint Venture 3. If a sole proprietorship or partnership, answer the following: a. Date of organization: b. Name and address of all partners: c. If partnership (state whether general or limited): 4. If a joint venture, answer the following: a. Date of commencement of joint venture: b. Names and addresses of members of the joint venture: 5. How many years has your organization been in business as a General Contractor? 6. How many years has your organization been in business under its present business name? 7. Under what other or former names has your organization operated? 8. If other than a corporation, sole proprietorship, or partnership, describe organization and name principals: 9. List states and categories in which your organization is legally qualified to do business. Indicate registration or license numbers and expiration dates, as applicable. 10. List the work normally performed by your work forces: -3-

6 PART 3: FINANCIAL INFORMATION 1. State your firm s gross revenues for the last three years: 2. Name of Bonding Company(ies) and name(s) and address(es) of agent(s) for the last five years: 3. Maximum bonding capacity (in dollars) $ 4. In the last five years, has any surety made any payments, on your firm s behalf to satisfy any claims made against a performance or payment bond issued in connection with a construction project, either public or private? If yes, on separate signed pages, provide a list of all demands placed on the bid bond, payment and/or performance bond of the firm during the preceding fiveyear period. Details should include date, project, dollar amount, and an explanation of circumstances. 5. If required, will you be able to provide a liability insurance policy with a policy limit of at least $2,000,000 per occurrence and $2,000,000 aggregate? -4-

7 PART 4: DISPUTES AND NON-COMPLIANCE RFQ 963A For responses to Part 4, provide separate signed pages as necessary. Write Part 4, Question No. on the top right hand corner and sign at the bottom of each page. 1. Have you ever failed to complete any construction contract awarded to you? If so, note when, where, and why. 2. In the last five years, has your license been suspended or revoked for failure to comply with substantive licensing requirements? If so, note when, and why. 3. In the last five years, has your firm been assessed and paid liquidated damages after completion of a project under construction contract with either a public or private owner because of a delay in completing the project? If yes, describe the circumstances that lead to the assessment of liquidated damages, provide the name of the owner, project name, amount of liquidated damages paid, and when. 4. In the last five years, have any complaints been filed in court against your firm concerning your firm s work on a construction project? If yes, identify the complaint(s) by providing the project name, date of the complaint, name of the plaintiff, a brief description of the nature of the complaint, the court in which the case was filed, and a brief description of the status of the complaint pending, or, if resolved, of the resolution. 5. In the last five years, have any complaints been filed in court against your firm for failure to comply with labor laws and regulations and worker s compensation law, or failure to provide timely payment of all obligations to subcontractors, vendors, or suppliers? If yes, identify the complaint(s) by providing the project name, date of the complaint, name of the entity (or entities), a brief description of the nature of the complaint, the court in which the case was filed, and a brief description of the status of the complaint pending, or if resolved, of the resolution. -5-

8 6. In the last five years, has your firm filed a complaint in court against a project owner concerning work on a project or payment for a contract and filed that claim in court or arbitration? If yes, identify the complaint(s) by providing the project name, date of the complaint, name of the entity (or entities), a brief description of the nature of the complaint, the court in which the case was filed, and a brief description of the status of the complaint pending, or, if resolved, of the resolution. 7. Using your firm s OSHA No. 300 Logs (Work-Related Injuries and Illnesses) for the last 3 years, provide the following information: a. Number of lost workday cases (injuries involving days away from work) b. Number of restricted workday cases c. Number of cases with medical treatment d. Number of fatalities e. Incident rate lost workdays f. Incidence rate OSHA recordables g. OSHA citations -6-

9 PART 5: ON-GOING PROJECTS RFQ 963A Provide all the required information on all projects the Respondent currently has under contract within Southern California. The names, references and phone numbers must be current and verifiable. Use additional sheets as necessary. (1) Project Name: Owner: Description of Project, Scope of Work: Performing Work as Prime Contractor: Subcontractor: Total Value of Contract Awarded: Start Date: Percent Completed: Extension Time Granted: (2) Project Name: Owner: Description of Project, Scope of Work: Performing Work as Prime Contractor: Subcontractor: Total Value of Contract Awarded: Start Date: Percent Completed: Extension Time Granted: -7-

10 (3) Project Name: Owner: Description of Project, Scope of Work: Performing Work as Prime Contractor: Subcontractor: Total Value of Contract Awarded: Start Date: Percent Completed: Extension Time Granted: -8-

11 PART 6A: COMPLETED PROJECTS (PIPELINE REPAIRS) RFQ 963A NOTE: Complete and submit only the applicable version of Part 6 (A, B, or C) for the category that the Respondent is qualifying for. List up to five urgent construction projects completed in the last five years involving water pipelines ranging in sizes between 36 inches and 201 inches. The list shall only include public works projects that are located within Southern California. Metropolitan encourages Respondents to list projects that meet the following criteria: larger diameter pipeline repairs; more complex traffic control; shorter duration shutdown windows relative to the work required which utilized more complex construction methods such as shoring or groundwater control. The first three projects shall meet the minimum required value of $1,000,000 each and the next two projects may be of any value. (Names, references, and phone numbers must be current and verifiable): (1) Project Name: Owner: Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Number of Pipeline Sections Repaired: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No Performed Work as Prime Contractor: Subcontractor: -9-

12 (2) Project Name: Owner: Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Number of Pipeline Sections Repaired: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No Performed Work as Prime Contractor: Subcontractor: (3) Project Name: Owner: -10-

13 Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Number of Pipeline Sections Repaired: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No Performed Work as Prime Contractor: (4) Project Name: Owner: Subcontractor: RFQ 963A Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Number of Pipeline Sections Repaired: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No Performed Work as Prime Contractor: Subcontractor: -11-

14 (5) Project Name: Owner: Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Number of Pipeline Sections Repaired: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No Performed Work as Prime Contractor: Subcontractor: -12-

15 PART 6B: COMPLETED PROJECTS (MECHANICAL AND ROTATING EQUIPMENT REPAIRS) RFQ 963A NOTE: Complete and submit only the applicable version of Part 6 (A, B, or C) for the category that the Respondent is qualifying for. List up to five urgent construction projects completed in the last five years involving repair or rebuilding of turbines, pumps, valves, or compressors, or dynamic balancing of rotating apparatus. The list shall only include public works projects that are located within Southern California. Metropolitan encourages Respondents to list projects that meet the following criteria: combination of repair, refurbishment, or rebuilding of various mechanical equipment in any one project completed within shorter duration shutdown windows relative to the work required which utilized more complex construction methods. The first three projects shall meet the minimum required value of $1,000,000 each and the next two projects may be of any value. (Names, references, and phone numbers must be current and verifiable): (1) Project Name: Owner: Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No Performed Work as Prime Contractor: Subcontractor: -13-

16 (2) Project Name: Owner: Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No Performed Work as Prime Contractor: Subcontractor: (3) Project Name: Owner: -14-

17 Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No Performed Work as Prime Contractor: Subcontractor: (4) Project Name: Owner: Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No -15-

18 Warranty claims by Owner on installed equipment Yes No Performed Work as Prime Contractor: (5) Project Name: Owner: Subcontractor: RFQ 963A Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No Performed Work as Prime Contractor: Subcontractor: -16-

19 PART 6C: COMPLETED PROJECTS (ELECTRICAL AND POWER GENERATION REPAIRS) RFQ 963A NOTE: Complete and submit only the applicable version of Part 6 (A, B, or C) for the category that the Respondent is qualifying for. List up to five urgent construction projects completed in the last ten years involving electrical and power generation repairs of the highest voltage installed. The list shall only include public works projects that are located within Southern California. Metropolitan encourages Respondents to list projects that meet the following criteria: repair or retrofit of 230 kv circuit breakers, disconnect switches, power transmission lines, switchgears, and substations of similar voltage, repair/rewinding/testing of power transformers, reactors, and generator switchgears, electrical field testing, connections or tie-ins completed within shorter duration shutdown windows relative to the work required which utilized more complex construction methods. The first three projects shall meet the minimum required value of $1,000,000 each and the next two projects may be of any value. (Names, references, and phone numbers must be current and verifiable): (1) Project Name: Owner: Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No -17-

20 Performed Work as Prime Contractor: Subcontractor: (2) Project Name: Owner: Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No Performed Work as Prime Contractor: Subcontractor: (3) Project Name: Owner: -18-

21 Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No Performed Work as Prime Contractor: Subcontractor: (4) Project Name: Owner: Voltage Requirement: -19-

22 Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No RFQ 963A Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes Performed Work as Prime Contractor: (5) Project Name: Owner: Subcontractor: No Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No -20-

23 Performed Work as Prime Contractor: Subcontractor: -21-

24 PART 7: ADDITIONAL DOCUMENTATION RFQ 963A 1. Firm Qualifications / Staffing Plan: Submit resumes for the Project Manager and any key personnel who will participate in these services. Resumes shall highlight education, licenses, relevant experience, and specific responsibilities for services described herein. 2. List of Available Equipment for Use: Submit a list of all equipment owned and intended for use if issued a contract in connection with this RFQ. The list shall include the equipment size and capacity. 3. Provide a letter from your surety or an authorized agent indicating your firm s bond-ability. The letter shall include the amount of your firm s single bond limit and aggregate amount. A letter from an authorized agent must include a power of attorney and notary acknowledgment. 4. Provide a notarized letter from a California admitted insurance carrier stating that Respondent is able to obtain insurance if awarded a construction contract. -22-

25 PART 8: ACKNOWLEDGMENT OF ADDENDA I hereby acknowledge the receipt, understanding and full consideration of Addenda to the Request for Statements of Qualifications for Metropolitan s RFQ No. 963A. Date: Respondent s Name: By: Title: (Acknowledgment of Addenda must be signed by a corporate official) -23-

26 PART 9: PREQUALIFICATION CERTIFICATION The undersigned swears that the foregoing statements and attachments, which include pages, are true and correct and includes all material information necessary to identify and explain the operations of (Name of Organization) as well as the ownership thereof. It is recognized and acknowledged that all information contained herein and submitted concurrently or in supplemental documents with this Application is complete, current, and true. I further acknowledge that any false, deceptive or fraudulent statements on the Application will result in denial of prequalification and may cause the said firm from participating in future contracts with Metropolitan. Signature of Owner, Officer, President, or Chief Executive Officer Name/Title Date COUNTY OF STATE OF: Subscribed and sworn to before me this day of, 20 SIGNED (Notary Public) (Address of Notary) My Commission Expires -24-

27 RFQ NO. 963A SHUTDOWN CONTRACTOR SPECIALIST PREQUALIFICATION QUESTIONNAIRE (SUBCONTRACTOR) Prequalifying under the following category/ies: Pipeline Repairs Mechanical and Rotating Equipment Repairs Electrical and Power Generation Repairs COMPANY INFORMATION: RESPONDENT/COMPANY NAME: ADDRESS: PRINCIPAL OFFICE: PHONE: FAX: CONTACT PERSON: PHONE: FAX: ADDRESS: -1-

28 PART 1: MINIMUM REQUIREMENTS A. Respondents will be immediately rated fail if the answer to any of questions 1 and 2 is No. 1. Does the Respondent possess a valid and current California Contractor s license for the types of projects, for which it intends to submit a bid? Yes No 2. Has the respondent completed at least three projects involving repairs/new construction valued at $500,000 each or more under the qualifying category in shutdown conditions requiring 24/7 operations within the last five (5) years? Yes No B. Respondents will be immediately rated fail if the answer to any of questions 3 through 7 is Yes 3. In the last five years, has your firm had its Contractors license suspended? Yes No 4. In the last five years, has your firm, or any officer, been convicted of a crime involving the awarding of a contract of a government (local, state or federal) construction project, or the bidding or performance of a government contract? Yes No 5. In the last five years, has your firm been defaulted or terminated by a Prime Contractor (other than for convenience of the project owner) or has your surety completed a contract for your firm? Yes No 6. At the time of submitting this pre-qualification form, is your firm ineligible to bid on or be awarded any public works contract, or perform as a subcontractor on a public works contract? Yes No 7. Has your firm, or any person, ever been found guilty in a criminal action, for making any false claim or material misrepresentation to any public agency or entity? Yes No -2-

29 PART 2 - CURRENT ORGANIZATION AND BUSINESS STRUCTURE 1. Please check appropriate organizational structure: Corporation Partnership Other 2. If a corporation, answer the following: a. Date of incorporation: b. State of incorporation: c. List Board of Directors and Titles: Sole Proprietorship Joint Venture 3. If a sole proprietorship or partnership, answer the following: a. Date of organization: b. Name and address of all partners: c. If partnership (state whether general or limited): 4. If a joint venture, answer the following: a. Date of commencement of joint venture: b. Names and addresses of members of the joint venture: 5. How many years has your organization been in business as a General Contractor? 6. How many years has your organization been in business under its present business name? 7. Under what other or former names has your organization operated? 8. If other than a corporation, sole proprietorship, or partnership, describe organization and name principals: 9. List states and categories in which your organization is legally qualified to do business. Indicate registration or license numbers and expiration dates, as applicable. 10. List the work normally performed by your work forces: -3-

30 PART 3: FINANCIAL INFORMATION 1. State your firm s gross revenues for the last three years: 2. Name of Bonding Company(ies) and name(s) and address(es) of agent(s) for the last five years: 3. Maximum bonding capacity (in dollars) $ 4. In the last five years, has any surety made any payments, on your firm s behalf to satisfy any claims made against a performance or payment bond issued in connection with a construction project, either public or private? If yes, on separate signed pages, provide a list of all demands placed on the bid bond, payment and/or performance bond of the firm during the preceding fiveyear period. Details should include date, project, dollar amount, and an explanation of circumstances. -4-

31 PART 4: DISPUTES AND NON-COMPLIANCE RFQ 963A For responses to Part 4, provide separate signed pages as necessary. Write Part 4, Question No. on the top right hand corner and sign at the bottom of each page. 1. Have you ever failed to complete any construction contract awarded to you? If so, note when, where, and why. 2. In the last five years, has your license been suspended or revoked for failure to comply with substantive licensing requirements? If so, note when, and why. 3. In the last five years, has your firm been assessed and paid liquidated damages after completion of a project under construction contract with either a public or private owner because of a delay in completing the project? If yes, describe the circumstances that lead to the assessment of liquidated damages, provide the name of the owner, project name, amount of liquidated damages paid, and when. 4. In the last five years, have any complaints been filed in court against your firm concerning your firm s work on a construction project? If yes, identify the complaint(s) by providing the project name, date of the complaint, name of the plaintiff, a brief description of the nature of the complaint, the court in which the case was filed, and a brief description of the status of the complaint pending, or, if resolved, of the resolution. 5. In the last five years, have any complaints been filed in court against your firm for failure to comply with labor laws and regulations and worker s compensation law, or failure to provide timely payment of all obligations to subcontractors, vendors, or suppliers? If yes, identify the complaint(s) by providing the project name, date of the complaint, name of the entity (or entities), a brief description of the nature of the complaint, the court in which the case was filed, and a brief description of the status of the complaint pending, or if resolved, of the resolution. -5-

32 6. In the last five years, has your firm filed a complaint in court against a project owner concerning work on a project or payment for a contract and filed that claim in court or arbitration? If yes, identify the complaint(s) by providing the project name, date of the complaint, name of the entity (or entities), a brief description of the nature of the complaint, the court in which the case was filed, and a brief description of the status of the complaint pending, or, if resolved, of the resolution. 7. Using your firm s OSHA No. 300 Logs (Work-Related Injuries and Illnesses) for the last 3 years, provide the following information: a. Number of lost workday cases (injuries involving days away from work) b. Number of restricted workday cases c. Number of cases with medical treatment d. Number of fatalities e. Incident rate lost workdays f. Incidence rate OSHA recordables g. OSHA citations -6-

33 PART 5: ON-GOING PROJECTS RFQ 963A Provide all the required information on all projects the Respondent currently has under contract within Southern California. The names, references and phone numbers must be current and verifiable. Use additional sheets as necessary. (1) Project Name: Owner/Prime Contractor: Description of Project, Scope of Work: Total Value of Contract Awarded: Start Date: Percent Completed: Extension Time Granted: (2) Project Name: Owner/Prime Contractor: Description of Project, Scope of Work: Total Value of Contract Awarded: Start Date: Percent Completed: Extension Time Granted: -7-

34 (3) Project Name: Owner/Prime Contractor: Description of Project, Scope of Work: Total Value of Contract Awarded: Start Date: Percent Completed: Extension Time Granted: -8-

35 PART 6A: COMPLETED PROJECTS (PIPELINE REPAIRS) RFQ 963A NOTE: Complete and submit only the applicable version of Part 6 (A, B, or C) for the category that the Respondent is qualifying for. List up to five urgent construction projects completed in the last five years involving water pipelines ranging in sizes between 36 inches and 201 inches. The list shall only include public works projects that are located within Southern California. Metropolitan encourages Respondents to list projects that meet the following criteria: larger diameter pipeline repairs; more complex traffic control; shorter duration shutdown windows relative to the work required which utilized more complex construction methods such as shoring or groundwater control. The first three projects shall meet the minimum required value of $500,000 each and the next two projects may be of any value. (Names, references, and phone numbers must be current and verifiable): (1) Project Name: Owner/Prime Contractor: Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No -9-

36 (2) Project Name: Owner/Prime Contractor: Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No (3) Project Name: Owner/Prime Contractor: -10-

37 Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No RFQ 963A (4) Project Name: Owner/Prime Contractor: Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No -11-

38 (5) Project Name: Owner/Prime Contractor: Pipe Sizes: Pipe Types: Depths of Excavation: Method of shoring used: Traffic Control Condition: Complex Simple None Groundwater Control: Yes No -12-

39 PART 6B: COMPLETED PROJECTS (MECHANICAL AND ROTATING EQUIPMENT REPAIRS) RFQ 963A NOTE: Complete and submit only the applicable version of Part 6 (A, B, or C) for the category that the Respondent is qualifying for. List up to five urgent construction projects completed in the last five years involving repair or rebuilding of turbines, pumps, valves, or compressors, or dynamic balancing of rotating apparatus. The list shall only include public works projects that are located within Southern California. Metropolitan encourages Respondents to list projects that meet the following criteria: combination of repair, refurbishment, or rebuilding of various mechanical equipment in any one project completed within shorter duration shutdown windows relative to the work required which utilized more complex construction methods. The first three projects shall meet the minimum required value of $500,000 each and the next two projects may be of any value. (Names, references, and phone numbers must be current and verifiable): (1) Project Name: Owner/Prime Contractor: Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No -13-

40 (2) Project Name: Owner/Prime Contractor: Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No (3) Project Name: Owner/Prime Contractor: -14-

41 Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No (4) Project Name: Owner/Prime Contractor: RFQ 963A Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No -15-

42 (5) Project Name: Owner/Prime Contractor: Type of equipment repaired or refurbished: Did the project involve equipment design? Yes No Functional testing of repaired or refurbished equipment Yes No Equipment adjustments made due to functional testing failure Yes No Warranty claims by Owner on installed equipment Yes No -16-

43 PART 6C: COMPLETED PROJECTS (ELECTRICAL AND POWER GENERATION REPAIRS) RFQ 963A NOTE: Complete and submit only the applicable version of Part 6 (A, B, or C) for the category that the Respondent is qualifying for. List up to five urgent construction projects completed in the last ten years involving electrical and power generation repairs of the highest voltage installed. The list shall only include public works projects that are located within Southern California. Metropolitan encourages Respondents to list projects that meet the following criteria: repair or retrofit of 230 kv circuit breakers, disconnect switches, power transmission lines, switchgears, and substations of similar voltage, repair/rewinding/testing of power transformers, reactors, and generator switchgears, electrical field testing, connections or tie-ins completed within shorter duration shutdown windows relative to the work required which utilized more complex construction methods. The first three projects shall meet the minimum required value of $500,000 each and the next two projects may be of any value. (Names, references, and phone numbers must be current and verifiable): (1) Project Name: Owner/Prime Contractor: Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No -17-

44 (2) Project Name: Owner/Prime Contractor: Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No (3) Project Name: Owner/Prime Contractor: -18-

45 Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No (4) Project Name: Owner/Prime Contractor: Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No -19-

46 Were adjustments to the system needed or any re-testing required? Yes No (5) Project Name: Owner/Prime Contractor: Voltage Requirement: Electrical Field Testing Required: Complex Simple None Any damaged equipment during testing? Yes No Failure by Owner-provided Testing Agency to start or complete testing due to Respondent s inability to provide testing plan or documentation requirement Yes No Were adjustments to the system needed or any re-testing required? Yes No -20-

47 PART 7: ADDITIONAL DOCUMENTATION RFQ 963A 1. Firm Qualifications / Staffing Plan: Submit resumes for the Project Manager and any key personnel who will participate in these services. Resumes shall highlight education, licenses, relevant experience, and specific responsibilities for services described herein. 2. List of Available Equipment for Use: Submit a list of all equipment owned and intended for use if issued a contract in connection with this RFQ. The list shall include the equipment size and capacity. -21-

48 PART 8: ACKNOWLEDGMENT OF ADDENDA I hereby acknowledge the receipt, understanding and full consideration of Addenda to the Request for Statements of Qualifications for Metropolitan s RFQ No. 963A. Date: Respondent s Name: By: Title: (Acknowledgment of Addenda must be signed by a corporate official) -22-

49 PART 9: PREQUALIFICATION CERTIFICATION The undersigned swears that the foregoing statements and attachments, which include pages, are true and correct and includes all material information necessary to identify and explain the operations of (Name of Organization) as well as the ownership thereof. It is recognized and acknowledged that all information contained herein and submitted concurrently or in supplemental documents with this Application is complete, current, and true. I further acknowledge that any false, deceptive or fraudulent statements on the Application will result in denial of prequalification and may cause the said firm from participating in future contracts with Metropolitan. Signature of Owner, Officer, President, or Chief Executive Officer Name/Title Date COUNTY OF STATE OF: Subscribed and sworn to before me this day of, 20 SIGNED (Notary Public) (Address of Notary) My Commission Expires -23-

STATEMENT OF BIDDER S QUALIFICATIONS (GENERAL CONTRACTOR)

STATEMENT OF BIDDER S QUALIFICATIONS (GENERAL CONTRACTOR) HOUSING AUTHORITY OF THE COUNTY OF SAN BERNARDINO CAPITAL FUND PROGRAM 715 E. BRIER DRIVE SAN BERNARDINO, CA 92408-2841 (909) 890-0644 FAX (909) 915-1831 STATEMENT OF BIDDER S QUALIFICATIONS (GENERAL CONTRACTOR)

More information

CONTRACTORS AND SUBCONTRACTORS PRE-QUALIFICATION APPLICATION for MEASURE M BOND PROJECTS

CONTRACTORS AND SUBCONTRACTORS PRE-QUALIFICATION APPLICATION for MEASURE M BOND PROJECTS CONTRACTORS AND SUBCONTRACTORS PRE-QUALIFICATION APPLICATION for MEASURE M BOND PROJECTS Hollister School District will be soliciting bids for reconstruction and new construction on Measure M Bond Projects.

More information

PREQUALIFICATION FOR GENERAL CONTRACTORS

PREQUALIFICATION FOR GENERAL CONTRACTORS PREQUALIFICATION FOR GENERAL CONTRACTORS Central Union School District Admiral Akers Elementary School Page 0 of 17 CONTACT INFORMATION Firm Name: Check One: Corporation (As it appears on license) Partnership

More information

EL CENTRO ELEMENTARY SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE AND CERTIFICATION FOR GENERAL CONTRACTORS FOR MULTIPLE PROJECTS

EL CENTRO ELEMENTARY SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE AND CERTIFICATION FOR GENERAL CONTRACTORS FOR MULTIPLE PROJECTS EL CENTRO ELEMENTARY SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE AND CERTIFICATION FOR GENERAL CONTRACTORS FOR MULTIPLE PROJECTS Due 2:00pm, January 11, 2018 Pursuant to Public Contract Code section

More information

ATTACHMENT 6 PREQUALIFICATION QUESTIONNAIRE. Firm Name: Check One: Corporation (as it appears on license) Sole Prop.

ATTACHMENT 6 PREQUALIFICATION QUESTIONNAIRE. Firm Name: Check One: Corporation (as it appears on license) Sole Prop. ATTACHMENT 6 PREQUALIFICATION QUESTIONNAIRE CONTACT INFORMATION Firm Name: Check One: Corporation (as it appears on license) Partnership Sole Prop. Contact Person: Address: Phone: Fax: If Firm is a sole

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2019 PRE-QUALIFICATION QUESTIONNAIRE

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2019 PRE-QUALIFICATION QUESTIONNAIRE PART B. 2019 QUESTIONNAIRE PREQUALIFICATION FOR GENERAL CONTRACTORS AND MECHANICAL, ELECTRICAL AND PLUMBING SUBCONTRACTORS CONTACT INFORMATION Firm Name: Check One: (As it appears on license) Corporation

More information

PREQUALIFICATION QUESTIONAIRE

PREQUALIFICATION QUESTIONAIRE CITY HALL FIRST FLOOR COMMUNITY DEVELOPMENT REMODEL PREQUALIFICATION QUESTIONAIRE PROJECT DESCRIPTION Beverly Hills Community Development Facility was last remodeled in 2007, and contains approximately

More information

Request for Qualifications

Request for Qualifications Request for Qualifications Issued: December 2, 2016 City Auditorium Bathroom Remodel Project Design-Build Project STATEMENTS OF QUALIFICATIONS ARE DUE BY 3:00 P.M. TUESDAY, JANUARY 10, 2017 1.0 REQUEST

More information

ADDENDUM NO. 1. Date: March 7, Accessible Ramp at Saddleback College. Bid No South Orange County Community College District

ADDENDUM NO. 1. Date: March 7, Accessible Ramp at Saddleback College. Bid No South Orange County Community College District ADDENDUM NO. 1 Date: March 7, 2018 Accessible Ramp at Saddleback College Bid. 2071 South Orange County Community College District General-All project documents including contract documents, drawings, and

More information

Prequalification Questionnaire

Prequalification Questionnaire Prequalification Questionnaire MODESTO CITY SCHOOLS PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE MEP SUBCONTRACTORS (Date) Pursuant to Public Contract Code section 20111.6, each prospective contractor

More information

Attachment A Application for Prequalification of Hazardous Material and Building Removal Contractors

Attachment A Application for Prequalification of Hazardous Material and Building Removal Contractors Attachment A Application for Prequalification of Hazardous Material and Building Removal Contractors S201-RFQ3 Request for Qualifications Page 1 of 23 APPLICATION FOR PRE-QUALIFICATION OF HAZARDOUS MATERIAL

More information

Madera Unified School District

Madera Unified School District Madera Unified School District Contractor Prequalification Procedures Prequalification Application PREQUALIFICATION PROCEDURES tice is hereby given by Madera Unified School District ( District ) that general

More information

C740 (13002F) REQUEST FOR PRE-QUALIFICATION BIDDERS

C740 (13002F) REQUEST FOR PRE-QUALIFICATION BIDDERS SILICON VALLEY BERRYESSA EXTENSION PROJECT C740 (13002F) REQUEST FOR PRE-QUALIFICATION OF BIDDERS Milpitas Station Surface Parking and Roadway Issued September 25, 2014 REQUEST FOR PRE-QUALIFICATION OF

More information

2018 GENERAL CONTRACTOR PREQUALIFICATION APPLICATION FOR NON STATE FUNDED PROJECTS > $1 MILLION. December 12, 2017

2018 GENERAL CONTRACTOR PREQUALIFICATION APPLICATION FOR NON STATE FUNDED PROJECTS > $1 MILLION. December 12, 2017 2018 GENERAL CONTRACTOR PREQUALIFICATION APPLICATION FOR NON STATE FUNDED PROJECTS > $1 MILLION PART A 2018 Instructions; Appeals Process PART B 2018 Questionnaire PART C 2018 Questionnaire Scoring PART

More information

PRE-QUALIFICATION SUBMITTAL PACKAGE FOR GENERAL CONTRACTOR PRE-QUALIFICATION FOR THE VETERANS SPORTS PARK AT TUSTIN LEGACY, CIP NO.

PRE-QUALIFICATION SUBMITTAL PACKAGE FOR GENERAL CONTRACTOR PRE-QUALIFICATION FOR THE VETERANS SPORTS PARK AT TUSTIN LEGACY, CIP NO. PRE-QUALIFICATION SUBMITTAL PACKAGE FOR GENERAL CONTRACTOR PRE-QUALIFICATION FOR THE VETERANS SPORTS PARK AT TUSTIN LEGACY, CIP NO. 20043 IN THE CITY OF TUSTIN 300 CENTENNIAL WAY TUSTIN, CALIFORNIA 92780

More information

PREQUALIFICATION PACKAGE FOR

PREQUALIFICATION PACKAGE FOR PREQUALIFICATION PACKAGE FOR THERMAL ENERGY STORAGE TANK REHABILITATION (REVISED) PROJECT 17-59 Due Date and Location for Submittal: 2:00 pm on Monday, December 18, 2017 City Clerk City of Beverly Hills

More information

Exhibit B-1 MEP Subcontractor Questionnaire

Exhibit B-1 MEP Subcontractor Questionnaire Exhibit B-1 MEP Subcontractor Questionnaire SAN RAFAEL CITY SCHOOLS PREQUALIFICATION QUESTIONNAIRE AND CERTIFICATION FOR PROSPECTIVE MEP SUBCONTRACTORS Due before 2:00pm, day,, 2017 Pursuant to Public

More information

Acknowledgment Form - page 1 of 2

Acknowledgment Form - page 1 of 2 Acknowledgment Form - page 1 of 2 RFQu - Construction Services for Josiah Henson Park The Proposer must include this signed acknowledgment that the Proposer has reviewed all the terms and conditions of

More information

GUADALUPE RIVER PARK AND GARDENS IDENTIFICATION, INTERPRETIVE AND WAY FINDING SYSTEMS SINGAGE PROJECT CITY OF SAN JOSE REDEVELOPMENT AGENCY

GUADALUPE RIVER PARK AND GARDENS IDENTIFICATION, INTERPRETIVE AND WAY FINDING SYSTEMS SINGAGE PROJECT CITY OF SAN JOSE REDEVELOPMENT AGENCY CITY OF SAN JOSE REDEVELOPMENT AGENCY REQUEST FOR PRE-QUALIFICATION OF EXTERIOR SIGN FABRICATION BIDDERS GUADALUPE RIVER PARK AND GARDENS IDENTIFICATION, INTERPRETIVE AND WAY FINDING SYSTEMS SINGAGE PROJECT

More information

CITY OF SAN MATEO PUBLIC WORKS APRIL

CITY OF SAN MATEO PUBLIC WORKS APRIL REQUEST FOR PROPOSAL PRE-QUALIFICATION OF CONTRACTORS SEEKING TO BID ON THE CITY OF SAN MATEO S WASTEWATER TREATMENT PLANT DIGESTER GAS TO COMPRESSED NATURAL GAS INFRASTRUCTURE AND VEHICLE FUELING SYSTEM

More information

PREQUALIFICATION QUESTIONNAIRE

PREQUALIFICATION QUESTIONNAIRE PREQUALIFICATION QUESTIONNAIRE FOR THE LANDSCAPE MAINTENANCE OF VARIOUS CITY PARKS, MEDIANS, COMMUNITY FACILITIES DISTRICTS, A WATERWAYS ASSESSMENT DISTRICT LANDSCAPE MAINTENANCE DISTRICTS AND OTHER CITY

More information

WHEREAS, the District desires to adopt the Prequalification Process, including the Questionnaire, Rating System, and Appeal Process.

WHEREAS, the District desires to adopt the Prequalification Process, including the Questionnaire, Rating System, and Appeal Process. RESOLUTION NO. 18-009 OF THE BERKELEY UNIFIED SCHOOL DISTRICT ADOPTING PREQUALIFICATION PROCESS FOR PRIME CONTRACTORS PURSUANT TO PUBLIC CONTRACT CODE SECTION 20111.6 WHEREAS, the Berkeley Unified School

More information

APPLICATION FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS FOR NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT

APPLICATION FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS FOR NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT APPLICATION FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS FOR NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT NORTH ORANGE COUNTY COMMUNICTION COLLEGE DISTRICT PURCHASING DEPARTMENT 1830 WEST ROMNEYA DR.

More information

Qualifications Statement Prime Contractor Subcontractor. Cover Sheet DGS Project Name DGS Project Number

Qualifications Statement Prime Contractor Subcontractor. Cover Sheet DGS Project Name DGS Project Number Cover Sheet DGS Project Name DGS Project Number Check One: Corporation, Partnership*, Individual, Joint Venture*, Other* * If more than one entity, file a separate Qualifications Statement for each entity.

More information

EL RANCHO UNIFIED DISTRICT PREQUALIFICATION QUESTIONNAIRE PACKET

EL RANCHO UNIFIED DISTRICT PREQUALIFICATION QUESTIONNAIRE PACKET EL RANCHO UNIFIED DISTRICT PREQUALIFICATION QUESTIONNAIRE PACKET In accordance with California Public Contract Code section 20111.6, all prime or general contractors and mechanical, electrical and plumbing

More information

APPLICATION FOR PRE-QUALIFICATION of GENERAL CONTRACTORS and PRIME CONTRACTORS

APPLICATION FOR PRE-QUALIFICATION of GENERAL CONTRACTORS and PRIME CONTRACTORS Name of Prequalifying Contractor: FYE2017Prequalification APPLICATION FOR PRE-QUALIFICATION of GENERAL CONTRACTORS and PRIME CONTRACTORS (For construction contracts valued at more than $500,000) For SAN

More information

CONTRACTORS AND SUBCONTRACTORS PRE-QUALIFICATION APPLICATION

CONTRACTORS AND SUBCONTRACTORS PRE-QUALIFICATION APPLICATION Purchasing Services 1830 South Nogales Street Rowland Heights CA 91748 Phone: (626) 854-8387 Fax: (626) 854-8587 www.rowlandschools.org Governing Board Cary C. Chen Lynne Ebenkamp Donna Freedman David

More information

LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES CONSTRUCTION CONTRACTS

LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES CONSTRUCTION CONTRACTS LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES CONSTRUCTION CONTRACTS PRIME CONTRACTOR PREQUALIFICATION QUESTIONNAIRE OVERVIEW By submitting this Prime Contractor Prequalification Questionnaire to the

More information

State of North Carolina Prequalification for Single Prime Contractors

State of North Carolina Prequalification for Single Prime Contractors Failure to answer all of the following questions may result in disqualification. If general contractor has any questions, contact the person listed below under Submitted to. Completing this questionnaire

More information

APPLICATION FOR RENEWAL VENDOR PREQUALIFICATION

APPLICATION FOR RENEWAL VENDOR PREQUALIFICATION THE SCHOOL DISTRICT OF PALM BEACH COUNTY, FLORIDA APPLICATION FOR RENEWAL VENDOR PREQUALIFICATION Construction Purchasing Department 3661 Interstate Park Rd. N., 2 nd Floor Riviera Beach, FL 33404 Phone:

More information

CONTRA COSTA COMMUNITY COLLEGE DISTRICT 500 Court St, Martinez, CA CONTRACTOR INFORMATION

CONTRA COSTA COMMUNITY COLLEGE DISTRICT 500 Court St, Martinez, CA CONTRACTOR INFORMATION 500 Court St, Martinez, CA 94553 CONTRACTOR PREQUALIFICATION APPLICATION FORM (CUPCCAA, PCC 22000) INFORMAL BIDDING PROCEDURES (PCC 22030) CONTRACTOR INFORMATION Firm / Company Name: (as it appears on

More information

State of North Carolina Prequalification for Single Prime Contractors

State of North Carolina Prequalification for Single Prime Contractors Failure to answer all of the following questions may result in disqualification. If general contractor has any questions, contact Dan Fields, the Project Principal at dfields@bjac.com. Completing this

More information

THE SCHOOL DISTRICT OF PALM BEACH COUNTY, FLORIDA RENEWAL VENDOR PREQUALIFICATION PROGRAM

THE SCHOOL DISTRICT OF PALM BEACH COUNTY, FLORIDA RENEWAL VENDOR PREQUALIFICATION PROGRAM THE SCHOOL DISTRICT OF PALM BEACH COUNTY, FLORIDA RENEWAL VENDOR PREQUALIFICATION PROGRAM Pursuant to State Requirements for Educational Facilities, Chapter 4, Section 4.1 Prequalification of Contractors

More information

PREQUALIFICATION OF PROSPECTIVE BIDDERS

PREQUALIFICATION OF PROSPECTIVE BIDDERS SUBCONTRACTOR S STATEMENTS OF EXPERIENCE Company Name: Contact Person: Email: Address: City/State/Zip: Website Address: Telephone: Contractor License.: Fax: Type(s): Business Type: Corporation Partnership

More information

CONTRACTORS AND SUBCONTRACTORS PRE-QUALIFICATION APPLICATION

CONTRACTORS AND SUBCONTRACTORS PRE-QUALIFICATION APPLICATION 501 N. Crescent Way Anaheim CA 92801 Phone: (714) 999-3511 www.auhsd.us www..org Office of the Superintendent Governing Board Annemarie Randle-Trejo Anna L. Piercy Katherine H. Smith Brian O'Neal Al Jabbar

More information

INVITATION TO BID U Directional Boring Utility Department

INVITATION TO BID U Directional Boring Utility Department INVITATION TO BID U-06-06 Directional Boring Utility Department Purpose: The City of Palm Coast, Utility Department is soliciting proposals from qualified contractors to perform directional drilling to

More information

TOWN OF PEMBROKE PARK REQUEST FOR QUALIFICATIONS. To Provide Solid Waste Franchise Financial Auditor Services for the Town of Pembroke Park

TOWN OF PEMBROKE PARK REQUEST FOR QUALIFICATIONS. To Provide Solid Waste Franchise Financial Auditor Services for the Town of Pembroke Park TOWN OF PEMBROKE PARK REQUEST FOR QUALIFICATIONS To Provide Solid Waste Franchise Financial Auditor Services for the Town of Pembroke Park Issued By: Town Manager 3150 Southwest 52 nd Avenue Pembroke Park,

More information

Invitation to Bid-B Annual Contract for Mowing of Vacant Lots/Fire Mitigation Ordinance

Invitation to Bid-B Annual Contract for Mowing of Vacant Lots/Fire Mitigation Ordinance Invitation to Bid-B-05-01 Annual Contract for Mowing of Vacant Lots/Fire Mitigation Ordinance Purpose: The City of Palm Coast, Flagler County, Florida is accepting proposals to provide underbrush mowing

More information

RENEWABLE WATER RESOURCES

RENEWABLE WATER RESOURCES RENEWABLE WATER RESOURCES Purchasing Department 561 Mauldin Road Greenville, South Carolina 29607 REQUEST FOR QUALIFICATION For Indefinite Delivery Contract Construction Services For Process (WRRFs) and

More information

PART 1: COMPANY DETAILS

PART 1: COMPANY DETAILS PART 1: COMPANY DETAILS Legal Name of Company (per your W-9): Legal Parent Company: Federal Employee Identification Number: Website: Year Company Started *: Date of Incorporation: State of Incorporation:

More information

INVITATION FOR STATEMENT OF QUALIFICATIONS

INVITATION FOR STATEMENT OF QUALIFICATIONS INVITATION FOR PROJECT NAME: WWTP HEADWORKS AND CLARIFIER PROJECT RFQ NUMBER: 2015-017 Statement of Qualifications Due Date: Thursday, May 14, 2015 Time: 2:00 PM CITY OF NORTHGLENN PUBLIC WORKS DEPARTMENT

More information

Responsibility Determination for General Contractors Who May Desire to Submit Bid Proposals for the Construction of [PROJECT TITLE]

Responsibility Determination for General Contractors Who May Desire to Submit Bid Proposals for the Construction of [PROJECT TITLE] Responsibility Statement and Questionnaire CITY OF NAPA PUBLIC WORKS DEPARTMENT NAPA, CALIFORNIA [DATE] Responsibility Determination for General Contractors Who May Desire to Submit Bid Proposals for the

More information

Subcontractor / Vendor Prequalification Statement Company Name:

Subcontractor / Vendor Prequalification Statement Company Name: Subcontractor / Vendor Prequalification Statement Company Name: Type of Work Company Performs: State of Incorporation: Date of Incorporation: Street Address (No PO Boxes): City State Zip: Office Number:

More information

REQUEST FOR QUALIFICATIONS FOR PIPELINE CONTRACTORS FOR 2019

REQUEST FOR QUALIFICATIONS FOR PIPELINE CONTRACTORS FOR 2019 ADDENDUM NO. 1 Item 1. PREQUALIFICATION QUESTIONNAIRE INSTRUCTIONS Second sentence should read Contractors must receive a passing score in each of the three categories to be considered. Item 2. PREQUALIFICATION

More information

OFFEROR S STATEMENT OF QUALIFICATIONS

OFFEROR S STATEMENT OF QUALIFICATIONS RBHA.ORG 804-819-4000 107 SOUTH FIFTH STREET, RICHMOND, VA 23219 OFFEROR S STATEMENT OF QUALIFICATIONS CAMPUS PHASE II CONSTRUCTION MANAGEMENT AT RISK 2016-AD-0004 TO BE COMPLETED BY OFFERORS IN RESPONSE

More information

REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS

REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS 1. INTRODUCTION Van Dyke Public Schools is requesting proposals from Energy Services Companies (ESCOs)

More information

SUBCONTRACTOR PREQUALIFICATION APPLICATION GENERAL INFORMATION

SUBCONTRACTOR PREQUALIFICATION APPLICATION GENERAL INFORMATION Date of Response: Company name: SUBCONTRACTOR PREQUALIFICATION APPLICATION GENERAL INFORMATION DBA: Phone: E-mail: Main Office Address: State: ZIP Code: Website: Sole Proprietorship: Partnership: Corporation:

More information

RENEWABLE WATER RESOURCES

RENEWABLE WATER RESOURCES RENEWABLE WATER RESOURCES Purchasing Department 561 Mauldin Road Greenville, South Carolina 29607 REQUEST FOR QUALIFICATION For Reedy River Basin Sewer Tunnel REQUEST FOR QUALIFICATION Renewable Water

More information

EXPERIENCE AND QUALIFICATION STATEMENT OF

EXPERIENCE AND QUALIFICATION STATEMENT OF EXPERIENCE AND QUALIFICATION STATEMENT OF (Legal Name of Bidder) SUBMITTED TO: Oakland County Water Resources Commissioner Building 95 West One Public Works Drive Waterford, Michigan 48328-1907 REGARDING:

More information

Greenville-Spartanburg Airport District 2000 GSP Drive, Suite 1 Greer, SC CONTRACTOR PREQUALIFICATION APPLICATION

Greenville-Spartanburg Airport District 2000 GSP Drive, Suite 1 Greer, SC CONTRACTOR PREQUALIFICATION APPLICATION Greenville-Spartanburg Airport District 2000 GSP Drive, Suite 1 Greer, SC 29651 CONTRACTOR PREQUALIFICATION APPLICATION Terminal Drop-off Improvements August 15, 2018 REQUEST FOR QUALIFICATIONS FOR LANDSCAPE

More information

Charlotte-Mecklenburg Schools. Request for Qualifications

Charlotte-Mecklenburg Schools. Request for Qualifications Charlotte-Mecklenburg Schools Request for Qualifications Move Management Services December 2, 2018 Table of Contents Section 1 - ADVERTISEMENT...3 Section 2 INTRODUCTION/OVERVIEW/GENERAL INFORMATION...4

More information

REQUEST FOR PRE-QUALIFICATION OF GENERAL ENGINEERING CONTRACTORS SITE UTILITIES AND INFRASTRUCTURE PROJECT ADVANCED TECHNOLOGY & EDUCATION PARK

REQUEST FOR PRE-QUALIFICATION OF GENERAL ENGINEERING CONTRACTORS SITE UTILITIES AND INFRASTRUCTURE PROJECT ADVANCED TECHNOLOGY & EDUCATION PARK REQUEST FOR PRE-QUALIFICATION OF GENERAL ENGINEERING CONTRACTORS FOR SITE UTILITIES AND INFRASTRUCTURE PROJECT AT ADVANCED TECHNOLOGY & EDUCATION PARK SOCCCD PROJECT NO. 20 June 2, 2016 South Orange County

More information

Contractor s Qualification Statement

Contractor s Qualification Statement THE AMERICAN INSTITUTE OF ARCHITECTS AIA Document A305 Contractor s Qualification Statement 1986 EDITION This form is approved and recommended by The American Institute of Architects (AIA) and The Associated

More information

MARGUERITE AQUATICS COMPLEX RENOVATION CONTRACTOR PRE-QUALIFICATION RFQ

MARGUERITE AQUATICS COMPLEX RENOVATION CONTRACTOR PRE-QUALIFICATION RFQ 1 Page: 1 of 1 CITY OF MISSION VIEJO ADDENDUM NO. 1 MARGUERITE AQUATICS COMPLEX RENOVATION CONTRACTOR PRE-QUALIFICATION RFQ DATE: 4/30/16 BY: Jon Hughes Project Manager TO: ALL INTERESTED PARTIES The following

More information

DISADVANTAGED BUSINESS ENTERPRISE

DISADVANTAGED BUSINESS ENTERPRISE DISADVANTAGED BUSINESS ENTERPRISE I. Policy It is the policy of the City of Gardena that Disadvantaged Business Enterprises (DBEs) shall have the maximum opportunity to participate in contracts and subcontracts.

More information

BID INSTRUCTIONS / BID FORMS. For DSA REQUIRED ADA IMPROVEMENTS LEONARDO DA VINCI K-8 SCHOOL

BID INSTRUCTIONS / BID FORMS. For DSA REQUIRED ADA IMPROVEMENTS LEONARDO DA VINCI K-8 SCHOOL Business Services Contracts Office 5735 47th Avenue Sacramento, CA 95824 (916) 643-2464 Gerardo Castillo, Chief Business Officer Kimberly Teague, Contract Specialist BID INSTRUCTIONS / BID FORMS For DSA

More information

SUBCONTRACTOR PRE-QUALIFICATION APPLICATION Please submit by to:

SUBCONTRACTOR PRE-QUALIFICATION APPLICATION Please submit by  to: I. General Information SUBCONTRACTOR PRE-QUALIFICATION APPLICATION Please submit by email to: ChristinaL@Citnalta.com A. Name and address of your business: This Company and address is the: Main Office

More information

Contractor s Qualification Statement

Contractor s Qualification Statement THE AMERICAN INSTITUTE OF ARCHITECTS AIA Document A305 Contractor s Qualification Statement 1986 EDITION This form is approved and recommended by The American Institute of Architects (AIA) and The Associated

More information

DOCUMENT MOUNTAIN VIEW-WHISMAN SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS. December 1, 2018

DOCUMENT MOUNTAIN VIEW-WHISMAN SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS. December 1, 2018 DOCUMENT 00 45 13 FOR PROSPECTIVE BIDDERS December 1, 2018 The Mountain View-Whisman School District ( District ) has determined that contractors ( Contractor(s) or Firm(s) ) on projects during the calendar

More information

APPLICATION FOR AUBURN UNIVERSITY S REGISTERED CONTRACTOR'S LIST For Projects $50,000 and Greater

APPLICATION FOR AUBURN UNIVERSITY S REGISTERED CONTRACTOR'S LIST For Projects $50,000 and Greater 2016-2018 APPLICATION FOR AUBURN UNIVERSITY S REGISTERED CONTRACTOR'S LIST For Projects $50,000 and Greater THIS IS NOT PRE-QUALIFICATION TO BID A SPECIFIC PROJECT. AFTER ADDITION TO THE AU REGISTERED

More information

(City) (State) (Zip) (City) (State) (Zip) Contact : Phone: Cell Phone: Contact Phone: Cell Phone: Contact Phone: Cell Phone:

(City) (State) (Zip) (City) (State) (Zip) Contact : Phone: Cell Phone:   Contact Phone: Cell Phone:   Contact Phone: Cell Phone: Thank you for your interest in Environmental Design & Construction, LLC. In order to develop a more complete knowledge of your Company and better match future EDC opportunities to your Company s capabilities

More information

Denver Public Schools Facility Management / Purchasing S. Acoma St. Denver, Colorado S. Acoma St. Denver, Colorado 80223

Denver Public Schools Facility Management / Purchasing S. Acoma St. Denver, Colorado S. Acoma St. Denver, Colorado 80223 Denver Public Schools Facility Management / Purchasing 1617 S. Acoma St. Denver, Colorado 80223 Date: March 4, 2014 RFQ Number: RFQ Title: RFQ will be received: 2014 DPS Contractor RFQ RFQ Construction

More information

Glenwood/Bell Street Well Pump and Piping Construction

Glenwood/Bell Street Well Pump and Piping Construction SPECIFICATIONS BID 1-16 Glenwood/Bell Street Well Pump and Piping Construction THE CITY OF AVON PARK FLORIDA December 21 th, 2015 NOTICE TO BIDDERS INVITATION TO BID -- BID # 1-16 The City of Avon Park

More information

Responsible Bidder Supplemental Questionnaire

Responsible Bidder Supplemental Questionnaire Responsible Bidder Supplemental Questionnaire 1. How many years has your organization been in business in California as a contractor under your present business name and license number? Years 2. Is your

More information

COWLEY COUNTY, KANSAS REQUEST FOR PROPOSAL. SALARY STUDY SUBMITTAL DEADLINE June 1, 2012 RFP NUMBER

COWLEY COUNTY, KANSAS REQUEST FOR PROPOSAL. SALARY STUDY SUBMITTAL DEADLINE June 1, 2012 RFP NUMBER REQUEST FOR PROPOSAL SALARY STUDY SUBMITTAL DEADLINE June 1, 2012 RFP NUMBER 12-001 1. BACKGROUND INFORMATION: COWLEY COUNTY, KANSAS SCOPE OF SERVICES Cowley County, a municipal corporation existing under

More information

IRFQ #R15-04: FRIDAY NIGHT LIVE

IRFQ #R15-04: FRIDAY NIGHT LIVE IRFQ #R15-04: FRIDAY NIGHT LIVE INSTRUCTIONS: The Fillable Forms Template must be submitted in total with all required ATTACHMENTS and documents. Bidders that do not comply with the requirements, and/or

More information

GWINNETT COUNTY DEPARTMENT OF WATER RESOURCES

GWINNETT COUNTY DEPARTMENT OF WATER RESOURCES October 18, 2011 NOTICE OF PRE-QUALIFICATION OF CONTRACTORS FOR THE INSTALLATION, REPLACEMENT AND/OR RELOCATION OF PRESSURIZED WATER MAINS AND SEWER FORCE MAINS AND APPURTENANCES Gwinnett County is soliciting

More information

GUILFORD COUNTY SCHOOLS Invitation for Bids

GUILFORD COUNTY SCHOOLS Invitation for Bids GUILFORD COUNTY SCHOOLS Invitation for Bids Purchasing Department 501 W. Washington Street Greensboro, NC 27401 Direct all inquiries to: Invitation for Bids.: 6105 Joe Farrar farrarj@gcsnc.com (336) 370-3236

More information

PRIME CONTRACTOR PREQUALIFICATION APPLICATION

PRIME CONTRACTOR PREQUALIFICATION APPLICATION PRIME CONTRACTOR PREQUALIFICATION APPLICATION Director of Purchasing Services 3401 Walnut Street Suite 421 A Philadelphia, Pennsylvania 19104-6228 Issue Date 01/01/99 Revision 7 01/07/05 INSTRUCTIONS ON

More information

3B 72) 1.0 INTRODUCTION

3B 72) 1.0 INTRODUCTION 1.0 INTRODUCTION Peace River Manasota Regional Water Supply Authority Request for Statement of Qualifications From s For Regional Integrated Loop System Phase 3B Interconnect Project (Preymore Interconnect

More information

Venture General Contracting, LLC Pre-Qualification Form

Venture General Contracting, LLC Pre-Qualification Form Thank you for your interest in Venture General Contracting, LLC. In order to develop a more complete knowledge of your Company and better match future Company opportunities to your Company s capabilities

More information

ADDENDUM TO INVITATION FOR BIDS Fortuna Union High School District Proposition 39 LED Lighting Retrofit Bid No Addendum #2 February 23, 2017

ADDENDUM TO INVITATION FOR BIDS Fortuna Union High School District Proposition 39 LED Lighting Retrofit Bid No Addendum #2 February 23, 2017 ADDENDUM TO INVITATION FOR BIDS Fortuna Union High School District Proposition 39 LED Lighting Retrofit Bid No. 17-001 Addendum #2 February 23, 2017 To All Prospective Bidders: The Fortuna Union High School

More information

State of North Carolina Prequalification for First Tier Subcontractors under CM at Risk

State of North Carolina Prequalification for First Tier Subcontractors under CM at Risk NC General Statute 143.128.1.c states, The construction manager at risk shall contract directly with the public entity for all construction; shall publicly advertise as prescribed in G.S. 143-129; and

More information

REQUEST FOR ANNUAL PRE-QUALIFICATION OF PUBLIC WORKS CONTRACTORS

REQUEST FOR ANNUAL PRE-QUALIFICATION OF PUBLIC WORKS CONTRACTORS STANISLAUS COUNTY OFFICE OF EDUCATION 1100 H STREET MODESTO, CA 95354 REQUEST FOR ANNUAL PRE-QUALIFICATION OF PUBLIC WORKS CONTRACTORS Requested for Pre-Qualification Issued: December 8, 2017 Responses

More information

DOCUMENT TABLE OF CONTENTS

DOCUMENT TABLE OF CONTENTS DOCUMENT 00 0110 TABLE OF CONTENTS Division Section Title INTRODUCTORY INFORMATION BIDDING REQUIREMENTS 00 0101 Title Page 00 0110 Table of Contents 00 0115 Drawing List 00 1113 Notice Inviting Bids 00

More information

INVITATION TO BID-R Frieda Zamba Pool Renovations

INVITATION TO BID-R Frieda Zamba Pool Renovations INVITATION TO BID-R-06-01 Frieda Zamba Pool Renovations Purpose: The City of Palm Coast is requesting bids from general contractors for the renovations of the Frieda Zamba Pool. The outdoor, unsheltered

More information

PRE-QUALIFICATION REQUIREMENTS FOR BIDDERS Qualification Criteria

PRE-QUALIFICATION REQUIREMENTS FOR BIDDERS Qualification Criteria PRE-QUALIFICATION REQUIREMENTS FOR BIDDERS Qualification Criteria Contractors desiring to bid are required to complete the attached BIDDER QUALIFICATION QUESTIONNAIRE. These forms will be used to determine

More information

Webcor/Obayashi Joint Venture Request for Qualifications (RFQ) TG16.2 Tile/Flooring/Base

Webcor/Obayashi Joint Venture Request for Qualifications (RFQ) TG16.2 Tile/Flooring/Base For The Transbay Transit Center San Francisco, California Job No. 30100 Table of Contents I. PROJECT DESCRIPTION 2 II. SCOPE OF CONSTRUCTION SERVICES 3 III. COMMUNICATION WITH WEBCOR/OBAYASHI JOINT VENTURE

More information

BIDDER S QUALIFICATION AND EXPERIENCE STATEMENT

BIDDER S QUALIFICATION AND EXPERIENCE STATEMENT BIDDER S QUALIFICATION AND EXPERIENCE STATEMENT The OWNER will require supporting evidence regarding Bidder s Qualifications and competency. The Bidder will be required to furnish all of the applicable

More information

ITB ADDENDUM NO. 1. Addendum No. 1 to ITB MEDART LIFT STATION BYPASS Issued January 18, 2018

ITB ADDENDUM NO. 1. Addendum No. 1 to ITB MEDART LIFT STATION BYPASS Issued January 18, 2018 ITB 2018-02 ADDENDUM NO. 1 Addendum No. 1 to ITB 2018-02 MEDART LIFT STATION BYPASS Issued January 18, 2018 SECTION 2.0 SCHEDULE OF EVENTS See dates added in RED below Failure to comply with this or any

More information

CONTRACTOR PRE-QUALIFICATION APPLICATION FORM

CONTRACTOR PRE-QUALIFICATION APPLICATION FORM The School Board of Broward County, Florida Abby M. Freedman, Chair Nora Rupert, Vice Chair Robin Bartleman Heather P. Brinkworth Patricia Good Donna P. Korn Laurie Rich Levinson Ann Murray Dr. Rosalind

More information

REQUEST FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS DESIGN BID BUILD HEALTH CENTER CONCESSIONS BUILDING AND PARKING LOT PHASE 1A

REQUEST FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS DESIGN BID BUILD HEALTH CENTER CONCESSIONS BUILDING AND PARKING LOT PHASE 1A REQUEST FOR PRE-QUALIFICATION OF GENERAL CONTRACTORS DESIGN BID BUILD FOR HEALTH CENTER CONCESSIONS BUILDING AND PARKING LOT PHASE 1A AT IRVINE VALLEY COLLEGE SOCCCD PROJECT NO. 350 June 5, 2018 South

More information

Contractor Qualification Statement

Contractor Qualification Statement Contractor Qualification Statement PART I OPERATIONAL INFORMATION Date: A. GENERAL Legal Name of Business: Principal Office Street Address: Zip Code: City State: Principal Office Mailing Address: Zip Code:

More information

Addendum #1 RFQ #MM MCCD Measure MM Bond Program DSA Inspector of Record (IOR) Multiple Award MSA March 19, 2019

Addendum #1 RFQ #MM MCCD Measure MM Bond Program DSA Inspector of Record (IOR) Multiple Award MSA March 19, 2019 RFQ #MM-19-013 MCCD Measure MM Bond Program DSA Inspector of Record (IOR) Multiple Award MSA March 19, 2019 This to RFQ #MM-19-013, unless otherwise noted herein, makes changes to and/or clarifies the

More information

Charlotte-Mecklenburg Schools Capital Program Services. Request for Qualifications Architectural Design Services

Charlotte-Mecklenburg Schools Capital Program Services. Request for Qualifications Architectural Design Services Charlotte-Mecklenburg Schools Capital Program Services Request for Qualifications Architectural Design Services February 25, 2019 Contents Section 1 - ADVERTISEMENT...1 Section 2 - INTRODUCTION AND OVERVIEW...1

More information

PREDETERMINATION OF RESPONSIBILITY UNIVERSITY OF PITTSBURGH {SALK HALL RENOVATION PHASE II} DGS PROJECT NO. { }

PREDETERMINATION OF RESPONSIBILITY UNIVERSITY OF PITTSBURGH {SALK HALL RENOVATION PHASE II} DGS PROJECT NO. { } PREDETERMINATION OF RESPONSIBILITY UNIVERSITY OF PITTSBURGH {SALK HALL RENOVATION PHASE II} DGS PROJECT NO. {1103-385.4} BID PACKAGE {ELECTRICAL CONSTRUCTION} STATEMENT OF BIDDERS QUALIFICATIONS (Predetermination

More information

1.0 INTRODUCTION. Request for Qualifications Phase 1 Interconnect Project Directional Drill Subcontractor Page 1 of 21

1.0 INTRODUCTION. Request for Qualifications Phase 1 Interconnect Project Directional Drill Subcontractor Page 1 of 21 1.0 INTRODUCTION Peace River Manasota Regional Water Supply Authority Request for Statement of Qualifications From s For Regional Integrated Loop System Phase 1 Interconnect Project (U.S. 17 to Punta Gorda)

More information

In addition to completing our Subcontractor Qualification, you will need to submit the following documents:

In addition to completing our Subcontractor Qualification, you will need to submit the following documents: EXEMPLARY BUSINESS RELATIONSHIPS EXCEPTIONAL PERFORMANCE SUSTAINED EMPLOYEE OWNERSHIP Dear Sir/Madam, Exemplary business relationships and exceptional performance are not possible without highly qualified

More information

APPLICATION FOR CHANGE OF STATUS Lee County Contractor Licensing P.O. Box 398, Fort Myers, Florida (239)

APPLICATION FOR CHANGE OF STATUS Lee County Contractor Licensing P.O. Box 398, Fort Myers, Florida (239) APPLICATION FOR CHANGE OF STATUS Lee County Contractor Licensing P.O. Box 398, Fort Myers, Florida 33902 (239) 533-8895 Contractorlicensing@leegov.com Please place a check next to the change you are requesting:

More information

Home Address. Street City State Zip. Address. Street City State Zip. Home Phone ( ) Office Phone ( ) Fax ( )

Home Address. Street City State Zip.  Address. Street City State Zip. Home Phone ( ) Office Phone ( ) Fax ( ) APPLICATION FOR LEE COUNTY CERTIFICATE OF COMPETENCY Lee County Contractor Licensing P.O. Box 398, Fort Myers, Florida 33902 (239) 533-8895 Contractorlicensing@leegov.com I Applicant=s Name Type of Certificate

More information

Shook Subcontractor Prequalification Form

Shook Subcontractor Prequalification Form Email info@shookconstruction.com with any questions. The undersigned certifies under oath that the information provided herein is true and sufficiently complete so as not to be misleading. Section 1 -

More information

D. Type of work or services performed:

D. Type of work or services performed: RED+F SUBCONTRACTOR QUALIFICATION QUESTIONNAIRE INFORMATION TO BE FURNISHED BY A CONTRACTOR (Note: The term Contractor also refers to Subcontractors.) All questions on this questionnaire must be answered;

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS NO. 964-5378 COUNTY OF FRESNO POLYGRAPH TESTING SERVICES SUBMITTALS: ADDRESSED TO: MAILING ADDRESS: OFFICE ADDRESS: MARK ENVELOPE: COST LIMIT FOR AGREEMENT(S): Three (3) paper

More information

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract.

In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public construction contract. State of Oklahoma Capital Assets Management Construction and Properties Bid Affidavits In accordance with 61 O.S. 108 and 115, a sworn statement shall accompany any competitive bid submitted for a public

More information

PROPOSER'S QUALIFICATIONS STATEMENT

PROPOSER'S QUALIFICATIONS STATEMENT PROPOSER'S QUALIFICATIONS STATEMENT PROJECT TITLE: High Pressure Loop Transmission Line Phase 1 PROPOSAL SUBMITTED BY: (Print or Type Name of Bidder) The undersigned certifies the truth and correctness

More information

City of Forest Park Request for Proposals. Secure Access Control Systems

City of Forest Park Request for Proposals. Secure Access Control Systems City of Forest Park Request for Proposals Secure Access Control Systems Mandatory Pre-Proposal Conference March 9, 2016 at 10 am Bid Deadline March 25, 2016, at 2pm Purpose: The City of Forest Park is

More information

QUOTATION REQUEST Board of County Commissioners, Broward County, Florida

QUOTATION REQUEST Board of County Commissioners, Broward County, Florida Page: 1 of 19 Quotations for furnishing items or services stated below subject to terms and conditions provided, will be received by the Director of Purchasing, attention of the purchasing agent stated

More information

CONTRACTOR SURETY QUESTIONNAIRE

CONTRACTOR SURETY QUESTIONNAIRE CONTRACTOR SURETY QUESTIONNAIRE Federal Tax ID #: Date: Name Phone Address Fax Email I. ORGANIZATION AND BACKGROUND C-Corporation S-Corporation Partnership Limited Partnership Proprietorship A. Date business

More information

IMPORTANT GENERAL INSTRUCTIONS

IMPORTANT GENERAL INSTRUCTIONS IMPORTANT GENERAL INSTRUCTIONS 1. Each prospective bidder is required to file a prequalification questionnaire consisting of an Experience Record, Financial Statement, and Equipment Schedule, on a form