PRE-BID QUERIES AND REPLIES

Size: px
Start display at page:

Download "PRE-BID QUERIES AND REPLIES"

Transcription

1 PRE-BID QUERIES AND REPLIES NIT NO: PNMM/PC54/E/001 PROJECT NAME: CLIENT: GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LIMITED, BHARUCH, GUJARAT (INDIA) SCOPE OF WORK: Supply of Process License, Basic Design and Detailed Engineering, Procurement, Supply, Fabrication, Inspection by Third Party Inspection Agency (TPI) as applicable by Llyods/BV/TUV, Expediting, Route Survey for ODCs, Insurance, Transportation of all Equipments / Materials to work site including Loading and Un-loading, Storage, Construction and Erection of all civil, mechanical, electrical and instrumentation works, assembly and Installation, Temporary Site facility required for execution of Project, obtaining all necessary statutory approvals from concerned government authorities, as applicable, Testing, Mechanical Completion, Pre-Commissioning, Commissioning, Sustained Load Test Performance Guarantee Test Run Including total Project Management and handing over of Ammonia & Urea Plants of Capacity 2500 MTPD & 3850 MTPD respectively along with Associated Offsite & Utilities Facilities at GNFC s existing complex in Bharuch, duly completed in all respects, on single point responsibility basis.

2 Page 1. LETTER INVITING BID [EMD] The value of EMD specified, USD 2 Million is very high. Bidder requests Owner to reduce the EMD Amount of of [Defect Liability Period] [Inspector] However, extended DEFECTS LIABILITY PERIOD shall have an upper limit of 36 months for extended DEFECTS LIABILITY PERIOD, starting from the ACCEPTANCE OF PLANT. However, extended DEFECTS LIABILITY PERIOD shall have an upper limit of 24 months for extended DEFECTS LIABILITY PERIOD, starting from the ACCEPTANCE OF PLANT Comment:- Who shall bear all the costs and/or expenses associated with the appointment of such Inspector? Owner shall bear the cost as per Clause of 4. 8 of [Mutually Agreed Damages] MUTUALLY AGREED DAMAGES (MAD) means the pre-defined mutually agreed rates between OWNER and CONTRACTOR as detailed in NIT representing the CONTRACTOR s liability without possibility to recourse at Law) for the delay in achieving ACCEPTANCE OF PLANT for reasons attributable to the CONTRACTOR and / or for the failure to meet WORKS COST and performance guarantees provided under clause 5.2 of NIT. MUTUALLY AGREED DAMAGES (MAD) means the pre-defined mutually agreed rates between OWNER and CONTRACTOR as detailed in NIT representing the CONTRACTOR s liability for the delay in achieving ACCEPTANCE OF PLANT for reasons attributable to the CONTRACTOR and/or for the failure to meet WORKS COST and performance guarantees provided under clause 5.2 of NIT. PC54-PNCOM-PBQR RK MN RRK 2 of 31

3 Page of /44 9 of [Sub-Contractor and Sub Supplier] [TEST] SUB-CONTRACTOR shall mean any or all persons, firms or companies selected by CONTRACTOR with approval in WRITING by OWNER from whom a portion of SCOPE OF CONTRACT are procured by the CONTRACTOR. SUB-SUPPLIER shall mean any or all persons, firms or companies selected by CONTRACTOR with approval in RITING, by OWNER from whom EQUIPMENT are procured by CONTRACTOR. TEST shall mean such process or processes to be carried out by the CONTRACTOR as are prescribed in the CONTRACT or considered necessary by CONTRACTOR and/or OWNER or their representative in order to ascertain quality, workmanship, performance and efficiency of EQUIPMENT or part SUB-CONTRACTOR shall mean any or all persons, firms or companies selected by CONTRACTOR with approval in WRITING by OWNER, which shall not be unreasonably denied, withheld or delayed, from whom a portion of SCOPE OF CONTRACT are procured by the CONTRACTOR. SUB-SUPPLIER shall mean any or all persons, firms or companies selected by CONTRACTOR with approval in WRITING, by OWNER, which shall not be unreasonably denied, withheld or delayed, from whom EQUIPMENT are procured by CONTRACTOR.. TEST shall mean such process or processes to be carried out by the CONTRACTOR as are prescribed in the CONTRACT or considered necessary by CONTRACTOR and OWNER in order to ascertain PC54-PNCOM-PBQR RK MN RRK 3 of 31

4 Page of ( g) [Scope Contract] 12 of [Contractors General Responsibility] of thereof. In the event that there is any of the EQUIPMENT or WORK of the type, which is not specifically mentioned in the SPECIFICATIONS or drawings set out in CONTRACT, but which is necessary for normal, safe, and continuous operation of PLANT with guaranteed capacity and quality of product and quality and quantity of effluents on continuous basis throughout the year, CONTRACTOR shall supply such items of EQUIPMENT or WORK or perform such WORK that are required tobe done within PLANT, free of cost to OWNER, as if the same had been originally included in CONTRACT. quality, workmanship, performance and efficiency of EQUIPMENT or part thereof. Comment:- Need clarification on the insurance to be taken for ALOP and Delayed Start Up In the event that there is any of the EQUIPMENT or WORK of the type, which is not specifically mentioned in the SPECIFICATIONS or drawings set out in CONTRACT, but which is necessary or normal, safe, and continuous operation of PLANT with guaranteed capacity and quality of product and quality and quantity of effluents on continuous basis throughout the year, CONTRACTOR shall supply such items of EQUIPMENT or WORK or perform such WORK that are required to be done within PLANT, at price, to be agreed mutually by the PARTIES. Insurance for ALOP and DS (Delayed Start up) will be taken by GNFC as per Clause of [Statutory Comment:- Need clarification on the approval to be obtained from the Electrical Inspectorate. Bidder may note that only such approvals PC54-PNCOM-PBQR RK MN RRK 4 of 31

5 Page Approvals] are under its responsibility that are related to Bidder performance and execution of the Scope of Work of [Statutory Approvals] Comment:-Need clarification on the list of approvals to be obtained by the contractors in its name. Owner indicates that except for Environment Clearance all other work related permits are the responsibility of Contractor and Owner is in no way responsible for obtaining the permits except facilitate the Contractor by way of necessary authorization. For example Boiler Inspection Certificate is issued in the name of Owner but the full responsibility is to be taken by Contractor in getting the certificate from Boiler Inspector of [Inspection, All TESTs trials in general of EQUIPMENT and materials shall be witnessed by the INSPECTOR. The Bidder propose to amend the following:- as definition of INSPECTOR itself PC54-PNCOM-PBQR RK MN RRK 5 of 31

6 Page 12. Testing Expediting] 20 of [Inspection, Testing Expediting] and and Therefore, CONTRACTOR shall confirm with OWNER by or Fax about the exact date of inspection with at least 30 DAYS notice. CONTRACTOR shall specify the items and quantities ready for testing and indicate whether a Preliminary or Final Test is to be carried out. If on receipt of this notice, OWNER decides to waive the right to witness the test, timely information will be given to CONTRACTOR accordingly. All TESTs trials in general of EQUIPMENT and materials shall be witnessed by the INSPECTOR/ OWNER or its representative. Therefore, CONTRACTOR shall confirm with OWNER by or Fax about the exact date of clarifies inspection with at least 7 DAYS notice. CONTRACTOR shall specify the items and quantities ready for testing and indicate whether a Preliminary or Final Test is to be carried out. (a) If on receipt of this notice, OWNER decides to waive the right to witness the test, timely information will be given to CONTRACTOR accordingly. The Bidder propose to add the following after the above clause as (b):- (b) Notwithstanding anything contained in this Clause , any delay/failure by the Inspector/OWNER or its REPRESENTATIVE to carry out such inspection and/or witness shall entitle the Contractor to carry out such inspection by itself, and shall send certified copy of such results to the Owner, which shall be final and binding on Owner. PC54-PNCOM-PBQR RK MN RRK 6 of 31

7 Page of [Inspection, Testing and Expediting] 20 of [Inspection, Testing and Expediting] 22 of [Construction] 26 of [Progress Monitoring and Reporting /Network Schedule] Should the CONTRACTOR fail to comply with such notice within the period considered reasonable by OWNER and specified in such note, the OWNER shall have the option and be at liberty to take the CONTRACT wholly or in part at the CONTRACTOR'S risk and cost and recover from the CONTRACTOR, all extra costs incurred by the OWNER on this account. Comment:-What shall be the time frame within which the information shall be given by the Owner? Comment:- Need clarification about the qualified laboratories. Comment:- Need clarification/identification about the construction activities to be performed by the Contractor Should the CONTRACTOR fail to comply with such notice within the period as mutually agreed and specified in such note, the OWNER shall have the option and be at liberty to take the CONTRACT wholly or in part at the CONTRACTOR'S risk and cost and recover from the CONTRACTOR, all extra costs, limited to 10% of cost which the CONTRACTOR could have expended, incurred by the OWNER on this account. 27 of Last paragraph [after (e)] Two days before scheduled inspection date Qualified laboratory means approved by NABL, as this clause is self explanatory. Specific query, if any to be raised separately. PC54-PNCOM-PBQR RK MN RRK 7 of 31

8 Page Co- [Project ordination] 27 of [Technical Information] 28 of of [Technical Information] [Packing] In the event OWNER requests CONTRACTOR to make any alteration to the program, scope or responsibility under CONTRACT, CONTRACTOR shall do the same. CONTRACTOR will grant to OWNER an irrevocable, non transferable, perpetual and non exclusive right to use all technical information and knowhow and shall further advise OWNER. CONTRACTOR. The packing, markings and documentation within and outside the packages shall comply strictly with the CONTRACT and subject to any subsequent instructions ordered by the OWNER. In the event OWNER requests CONTRACTOR to make any alteration, to the program, scope or responsibility under CONTRACT, CONTRACTOR shall do the same subject to adjustment in TIME SCHEDULE and CONTRACT PRICE, if applicable, which shall be agreed by the PARTIES, mutually. Comment:_ Need clarity on the concept of Clause is self LOAN. explanatory which states that such documents are property of OWNER and subject to recall by OWNER. The bidder propose to amend as as the first sentence itself CONTRACTOR will grant to OWNER an clarifies the purpose. irrevocable, non-transferable, perpetual and non-exclusive right to use all technical information and know-how for the purpose of the operation of the PLANT and shall further advise OWNER. CONTRACTOR. The packing, markings and documentation within and outside the packages shall comply strictly with the CONTRACT and subject to any PC54-PNCOM-PBQR RK MN RRK 8 of 31

9 Page of of [Insurance] [Dispatch, Transportation / Shipping] CONTRACTOR shall take in the joint name of CONTRACTOR and OWNER comprehensive insurance.. The consignment shall be dispatched after inspection and acceptance by the OWNER...beha lf shall continue till ACCEPTANCE OF PLANT. subsequent instructions ordered by the OWNER, provided such instructions does not incur additional costs and/or expenses not included in the Contract Price. Suggested clause : Except in case of Global Policies, the CONTRACTOR shall take joint name of CONTRACTOR and OWNER comprehensive insurance.. Comment:- Article provides for exception for Global Policy. In view of this, Joint Name of the Owner in the existing Policy needs to be confirmed. Comment:- Who shall bear the cost associated with such inspection by the Owner? The following to be added : The Contractor shall provide notice for inspection 7 days prior to the date of inspection. In case of any delay beyond 7 days, from the date of inspection, both to carry out inspection by the Owner and/or issuance of acceptance thereof, the Contractor may dispatch the consignment and such delay shall be deemed to be extension of TIME SCHEDULE. Inspection cost shall be included in CONTRACT PRICE. However, personnel expense such as travelling and living, for OWNER s appointed inspector shall be borne by OWNER. Addition to this clause as suggested is not acceptable. PC54-PNCOM-PBQR RK MN RRK 9 of 31

10 Page of [Basic Design Conditions] Basic Design Conditions are provided at technical SPECIFICATION attached at PART-II TECHNICAL. OWNER shall furnish any additional information concerning the basic design conditions requested by CONTRACTOR as soon as practicable, but in any event not later than as per the requirements of CONTRACTOR'S engineering schedule established and made available to OWNER during the early stages of WORK. CONTRACTOR shall rely upon the correctness of the information given by OWNER satisfying the consistency and adequacy of such information. The bidder proposes to amend the following:- Basic Design Conditions are provided at technical SPECIFICATION attached at PART-II TECHNICAL. OWNER shall furnish any additional information concerning the basic design conditions requested by CONTRACTOR as soon as practicable, but in any event not later than as per the requirements of CONTRACTOR'S engineering schedule established and made available to OWNER during the early stages of WORK and delay, if any, shall be subject to adjustment in TIME SCHEDULE. Further, the CONTRACTOR shall rely upon the correctness of the information given by OWNER satisfying the consistency and adequacy of such information of d) [Monitor, Review approval WORK] and of d) Time period for approval of DRAWINGS by OWNER shall be finalized during PROJECT Coordination Procedure. d) Time period for approval of DRAWINGS, and other documents connected with basic and detailed engineering design and PC54-PNCOM-PBQR RK MN RRK 10 of 31

11 Page of [Warranties and Guarantees] This warranty shall be valid for 12 MONTHS from the date of ACCEPTANCE OF PLANT for all the EQUIPMENT (except otherwise specified / for Catalysts, Adsorbent, Resin). SPECIFICATIONS for EQUIPMENT, lists of spare parts and special maintenance tools, and lists of special construction aids, tools, tackles, and fixtures by OWNER shall be finalized during PROJECT Co-ordination Procedure. This warranty shall be valid for 12 MONTHS from the date of ACCEPTANCE OF PLANT or 18 MONTHS from the date of last major delivery ( WARRANTY PERIOD ), whichever is earlier; for all the EQUIPMENT (except otherwise specified / for Catalysts, Adsorbent, Resin) of [Warranties and Guarantees] If the CONTRACTOR fails to take proper corrective action to repair/replace DEFECT satisfactorily within a reasonable period, OWNER shall be free to take such corrective action as may be deemed necessary at CONTRACTOR'S risk and cost, after giving notice to the CONTRACTOR. Comment:- Need clarity as to what shall be the warranty period for Catalysts, Adsorbent, Resin. If the CONTRACTOR fails to take proper corrective action to repair/replace DEFECT satisfactorily within reasonable period, mutually agreed by the PARTIES, OWNER shall be free to take such corrective action as may be deemed necessary at CONTRACTOR'S risk and PC54-PNCOM-PBQR RK MN RRK 11 of 31

12 Page cost, after giving notice to the CONTRACTOR of c. 39 of [Warranties and Guarantees] [Warranties and Guarantees] c. Plant is not operated as per the specifications of raw material and utilities mentioned in the contract/agreement. EQUIPMENT or part thereof so repaired or replaced shall have further warranty for a period of 12 MONTHS from the date of such repair or c. Plant is not operated as per the specifications of raw material and utilities mentioned in the contract/agreement and the operating manual as provided by the Contractor The Bidder proposes to delete this clause as this is circular obligation and have no end to Warranty Period, as defined. OWNER may accept with modification as under: and instructions of the operating manual. replacement and the Bank Guarantee (value acceptable to OWNER) of the affected EQUIPMENT shall be suitably extended. PC54-PNCOM-PBQR RK MN RRK 12 of 31

13 Page of [Warranties and Guarantees] 43 of a), b) [Delay in Contractors performance] If the CONTRACTOR fails to meet its obligation to repair or replace defective EQUIPMENT within a reasonable period of time, if CONTRACTOR refuses to carry out the WORK under the guarantee Article, if danger is anticipated or in case of severe urgency, OWNER shall be entitled to carry out at CONTRACTOR'S cost and risk, repair WORK or replacement deliveries or have the same carried out by a third party. Taxes and duties of any kind whatsoever imposed by the authorities of the country of CONTRACTOR or his SUB- CONTRACTOR until delivery, shall be borne by CONTRACTOR. a) Terminate the CONTRACT wholly or partially and complete it by the OWNER or reassign it to others after giving 30 days notice in WRITING to the CONTRACTOR to remedy the cause complained of. b) Make any modifications, deletions, additions to the CONTRACT as the OWNER may consider necessary to ensure its satisfactory execution after giving 7 days notice to CONTRACTOR to remedy the cause complained of. The Bidder proposes to delete the BOLD PORTION of the Article since the same is covered adequately under the heading TAX & DUTIES (ARTICLE 6.2) a) Terminate the CONTRACT wholly or partially and complete it by the OWNER or reassign it to others after giving 60 days notice in WRITING to the CONTRACTOR to remedy the cause complained of. b) Make any modifications, deletions, additions to the CONTRACT as the OWNER may consider necessary to ensure its satisfactory execution after giving 30 days notice to CONTRACTOR. PC54-PNCOM-PBQR RK MN RRK 13 of 31

14 Page of of of [Rejections of EQUIPMENT, Removal of Rejected EQUIPMENT and Replacement] [Rejections of EQUIPMENT, Removal of Rejected EQUIPMENT and Replacement] [Rejections of EQUIPMENT, Removal of Rejected If the EQUIPMENT are not as per SPECIFICATION or fail to perform as per the specified performance guarantees, the OWNER shall be entitled to reject the EQUIPMENT or part thereof and ask for repair or replacement within reasonable time, failing which, OWNER shall procure its requirements from elsewhere at CONTRACTOR'S cost and risk. In the event of such rejection, the OWNER shall be entitled to use of the EQUIPMENT in a reasonable and proper manner for a time reasonably sufficient to enable him to obtain replacement. In case of rejection of EQUIPMENT, OWNER shall have the right to recover the amounts, if any, paid from any of his invoice pending with OWNER or by alternative method. to remedy the cause complained of. If the EQUIPMENT are not as per SPECIFICATION or fail to perform as per the specified performance guarantees, the OWNER shall be entitled to reject the EQUIPMENT or part thereof and the CONTRACTOR shall, at its option, undertake repair or replacement within reasonable time, as may be mutually agreed by the PARTIES, failing which, OWNER shall procure its requirements from elsewhere at CONTRACTOR'S cost. In the event of such rejection, the OWNER shall at mutually agreed terms with the Contractor, be entitled to use of the EQUIPMENT in a reasonable and proper manner for a time reasonably sufficient to enable him to obtain replacement. In case of rejection of EQUIPMENT, OWNER shall have the right to recover the amounts paid for the rejected Can be accepted for rejected equipment only PC54-PNCOM-PBQR RK MN RRK 14 of 31

15 Page EQUIPMENT and Replacement] 44 of of of [Corrective Measures and MUTUALLY AGREED DAMAGES] [Mutually Agreed Damages] [Statement about Corrective Measures] CONTRACTOR shall before start-up certify that PLANT is constructed in accordance with the drawings and SPECIFICATIONS furnished by CONTRACTOR provided that the performance guarantees pursuant to Article 5.3 are not met during a GUARANTEE TEST RUN pursuant to Article 8.5.4,,..due to reasons attributable to CONTRACTOR, the OWNER shall, without prejudice to its other remedies under the CONTRACT, deduct from the CONTRACT PRICE, as MUTUALLY AGREED DAMAGES for the respective defaults, a sum calculated as per Article 5.9.1, 5.9.2/5.9.3 hereunder. In the event that after modifications pursuant to Article the performance guarantees of PLANT are not met within 30 (thirty) DAYs from the beginning of the first GUARANTEE TEST RUN, OWNER may request CONTRACTOR to give a full and detailed statement in WRITING to OWNER within 10 (ten) DAYs of notice EQUIPMENT, if any, from any of invoice pending with OWNER or by alternative method. Comment : The Article referred in the said Article does not exist. Please suggest the provisions, which said clause deals with...due to reasons attributable to CONTRACTOR, the OWNER shall, as a sole and exclusive remedy under the CONTRACT, deduct from the CONTRACT PRICE, as MUTUALLY AGREED DAMAGES for the respective defaults, a sum calculated as per Article 5.9.1, 5.9.2/5.9.3 hereunder. The Bidder proposes to replace 30 days with 180 days Article 8.5 is to be referred instead of Article PC54-PNCOM-PBQR RK MN RRK 15 of 31

16 Page to do so of [Design Guarantees] 48 of [Faulty EQUIPMENT caused by the Contractor] CONTRACTOR shall be responsible to.e defective under normal operating conditions within 12 (twelve) MONTHS from the date of start-up of PLANT. In case a DEFECT in EQUIPMENT is due to an error in SPECIFICATIONS prepared by CONTRACTOR, CONTRACTOR shall undertake engineering, procurement, inspection, supply and installation etc at its own cost In the event that as a result of faulty EQUIPMENT installed in PLANT due to CONTRACTOR'S faulty SPECIFICATIONS, PLANT does not during the one year period after ACCEPTANCE OF PLANT operate within the ranges specified in Article to be demonstrated by a GUARANTEE TEST RUN conducted by OWNER in accordance with the provisions of the CONTRACT, CONTRACTOR shall be responsible to.. defective under normal operating conditions within 12 (twelve) MONTHS from the date of MECHANICAL COMPLETION of the PLANT. Comment:- Once the performance guarantees are achieved as specified in Article or in case of any failure to the achieve the same on payment of MUTUALLY AGREED DAMAGES, the ACCEPTANCE OF PLANT take place in line with Article 9 and therefore the only liability of the Contractor extends only to the Mechanical Warranty for repair and/or replacement. Or This said Article shall be subject to Article PC54-PNCOM-PBQR RK MN RRK 16 of 31

17 Page CONTRACTOR will have responsibility for replacing at its own cost the item or items of EQUIPMENT that caused the prime deficiency in performance of PLANT of of [Enforcement of VENDOR'S Guarantees] [Limitation Liability] of CONTRACTOR. 12 (twelve) MONTHS period of operation from the date of start-up of PLANT Notwithstanding the provisions of sub- Article , CONTRACTOR'S liability shall be unlimited for the following cases: CONTRACTOR. 12 (twelve) MONTHS from the date of MECHANICAL COMPLETION of the PLANT. The bidder proposes to delete the sub clause: a) Quantity and Quality of products from PLANT is not achieved as guaranteed as per Article 5.3. a. As the damage cap is already provided b) The WORKS COST is higher than 102.5% of the guaranteed WORKS COST. c) For providing immunity against Patent infringement pursuant to Article d) For providing immunity against indemnification pursuant to Article b. As the damage cap is already provided (e) As the damage cap is already provided and (f) from the exclusion lists. PC54-PNCOM-PBQR RK MN RRK 17 of 31

18 Page e) The Pollution level and Noise level Guarantees as per Articles 5.3 have not been met of k), o) [Contract Price] f) SUSTAINED LOAD TEST is not successfully conducted within 90 DAYS from MECHANICAL COMPLETION for reasons attributable to CONTRACTOR. k) Insurance including ALOP and DS, o) All other costs, expenses and outgoing of the CONTRACTOR not otherwise expressly set forth herein necessary, required or incidental to the full, complete and proper performance and discharge of the CONTRACTOR s obligations under and in accordance with the CONTRACT including completion of the PLANT in all respects and overheads of the CONTRACTOR. k) Insurance excluding ALOP and DS, (Comments As the ALOP and DS is the responsibility of OWNER, as per Article 3.8.9) o) All other costs, expenses and outgoing of the CONTRACTOR not otherwise expressly set forth herein necessary, required or incidental, in the opinion of CONTRACTOR, to the full, complete and proper performance and discharge of the CONTRACTOR s obligations under and in accordance with the CONTRACT including completion of the PLANT in all respects and overheads of the CONTRACTOR. Only Insurance premium for ALOP and DS shall be to OWNER s account. Bidder s responsibility is as per Article Any cost in this relation shall be included. PC54-PNCOM-PBQR RK MN RRK 18 of 31

19 Page of [Contract Price] The CONTRACT PRICE is fixed and firm and not subject to any escalation during the contract period unless otherwise stated elsewhere in the CONTRACT. The CONTRACT PRICE is fixed and firm and not subject to any escalation during the contract period unless otherwise stated elsewhere in the CONTRACT and except in case of :- Clause is self explanatory i. Force Majeure ii. Suspension ordered by the Owner iii. Delay and/or any default of the Owner iv. Extension of contract period due to reason not attributable to the CONTRACTOR of [Contract Price] Price Variation in CONTRACT PRICE shall be permitted as hereunder up to placement of LOI: Price Variation in CONTRACT PRICE shall be permitted from the date of the price bid submission by the CONTRACTOR till the ACCEPTANCE OF THE PLANT PC54-PNCOM-PBQR RK MN RRK 19 of 31

20 Page of [Taxes Duties ] 56 of & 11 [Taxes Duties ] 58 of [Advance Payment] 62 of [Bank and and Accordingly, the CONTRACT Price will, without extra price and/or extension of time, be held to include everything implicitly or otherwise required or necessary for the proper and timely completion of the Works including acceptance of PLANT in accordance with the CONTRACT. Accordingly, the CONTRACT Price will, without extra price and/or extension of time, except as set forth in the CONTRACT, be held to include everything as required or necessary for the proper and timely completion of the Works including acceptance of PLANT in accordance with the CONTRACT. - The said Article and are similar to Article and 6.1.6, which are appropriately placed and hence Bidder suggests for deletion to ensure clarity and avoid ambiguity. Advance payment shall be made on furnishing the following which shall be adjusted in all subsequent payments till MECHANICAL COMPLETION; Original bank guarantee in the prescribed proforma of the amount equal to the advance payment in one(l) copy valid up to ACCEPTANCE OF PLANT plus claim period of three months... If required, the above Security Bond The Bidder proposes as under, in relation to validity of the ABG till the period of MC than Acceptance of Plant since the Advance is being adjusted till MC only:- Original Bank Guarantee for Performance of Contract in the prescribed performa attached at ANNEXURE-1.16A for 10% of the CONTRACT PRICE valid up to the MECHANICAL COMPLETION plus claim period of three months in the form of Bank Guarantee. The Bidder proposes to amend as Article and are same. PC54-PNCOM-PBQR RK MN RRK 20 of 31

21 Page Guarantee Warranty Obligations] for for Performance Guarantee shall be further extended until fulfillment of CONTRACTOR's warranty obligations as per Article If required on account of any reasons attributable to the Contractor, the above Security Bond for Performance Guarantee shall be further extended until fulfilment of CONTRACTOR's warranty obligations as per Article a - NEW [Interest Delayed Payment] on The Bidder proposes the include the following clause : In case any payment, which is due in accordance with the CONTRACT, the OWNER shall pay interest to the CONTRACTOR at the rate SBI BR + 5.5% for the period of delay. Further, the CONTRACTOR shall reserve all other rights under the CONTRACT including common laws to seek further remedies. Not agreed to bidder request. Further, if the due payment is delayed for more than 30 days, the CONTRACT, at its option, reserve the right for (a) slow down the progress of the Project, (b) cause to pay the damages, cost or any other consequence which may arise for delayed payment to SUB CONTRACTORS and/or VENDORS including failing its own obligation under the CONTRACT; terminate the CONTRACT, which shall be construed as PC54-PNCOM-PBQR RK MN RRK 21 of 31

22 Page termination of contract at convenience of OWNER of of [Pre Commissioning] [Permits and Clearances] As soon as MECHANICAL COMPLETION has been achieved, CONTRACTOR shall present PLANT for inspection and on being satisfied about its completion, OWNER shall issue a certificate to CONTRACTOR within 7 DAYS indicating the date of MECHANICAL COMPLETION, provided PLANT can continue to receive feed leading to production of Ammonia and Urea. The Bidder proposes to amend as As soon as MECHANICAL COMPLETION has been achieved, CONTRACTOR shall present PLANT for inspection, OWNER shall issue a certificate to CONTRACTOR within 7 DAYS indicating the date of MECHANICAL COMPLETION, however, if the OWNER fails to inspect and/or issue the certificate within time stipulated above, the date of scheduled inspection shall be construed as MECHANICAL COMPLETION date ( DEEMED MECHANICAL COMPLETION ) Comment:- Need clarity on the licenses/permits and clearances to be obtained by the Contractor. Owner indicates that except for Environment Clearance all other work related permits are the responsibility of Contractor and Owner is in no way responsible for obtaining the permits except facilitate the Contractor by way of necessary authorization. For example Boiler PC54-PNCOM-PBQR RK MN RRK 22 of 31

23 Page Inspection Certificate is issued in the name of Owner but the full responsibility is to be taken by Contractor in getting the certificate from Boiler Inspector of [Acceptance of Plant] Within 30 (thirty) DAYs from the discharge of CONTRACTOR from liability for performance guarantees, OWNER shall send to CONTRACTOR a signed Certificate for ACCEPTANCE OF PLANT. On issue of this Certificate of Acceptance by OWNER, CONTRACTOR shall become entitled to receive payment of all unpaid amounts due to CONTRACTOR subject to CONTRACTOR'S fulfilling the obligations stipulated under the CONTRACT. The Bidder suggest the following modification : Within 30 (thirty) DAYs from the discharge of CONTRACTOR from liability for performance guarantees, OWNER shall send to CONTRACTOR a signed Certificate for ACCEPTANCE OF PLANT. In case OWNER fails to issue the certificate for ACCEPTANCE OF PLANT, within said stipulated time of 30 days, the 31 st day shall be the date of issuance of certificate for ACCEPTANCE OF PLANT ( DEEMED ACCEPTANCE OF PLANT ). On issue of this Certificate of Acceptance by OWNER including Deemed Acceptance of Plant, CONTRACTOR shall become entitled to receive payment of all unpaid amounts due to CONTRACTOR subject to CONTRACTOR'S fulfilling the obligations stipulated under the CONTRACT. PC54-PNCOM-PBQR RK MN RRK 23 of 31

24 Page of of [Acceptance of Plant] [Effective Date of Contract ] 70 of b) 70 of [Change Scope Contract] [Change Scope Contract] in of in of In the event of CONTRACTOR'S liability for performance guarantees has been discharged under paragraphs (a) through (g) of Article , The CONTRACT between CONTRACTOR and OWNER shall become effective upon issue of Letter of Intent to CONTRACTOR by OWNER. b) Changes in CONTRACTOR'S which in the opinion of OWNER/CONTRACTOR is necessary for the normal safe and continuous operation of PLANT as referred to in Article Any change in codes, standards, SPECIFICATIONS or practice in the SPECIFICATIONS including changes in pollution control and environmental norms, etc. whether related or arising out of statutory regulations/requirements or otherwise Comment:- Reference to the Article given in the said clause needs clarification. The Bidder proposes to amend as The CONTRACT between CONTRACTOR and OWNER shall become effective upon signing of the CONTRACT by and between the CONTRACTOR and the OWNER. The Bidder proposes to amend as b) Changes in CONTRACTOR'S.which in the opinion of OWNER and CONTRACTOR is necessary for the normal safe and continuous operation of PLANT as referred to in Article The Bidder proposed to bring the said clause in similar concept as envisaged under Article in relation to extension of contractual period. Here is our suggestion i.e. addition after the Article 10.9: In the event of CONTRACTOR'S liability for performance guarantees has been discharged under paragraphs (a) through (f) of Article , PC54-PNCOM-PBQR RK MN RRK 24 of 31

25 Page taking place on or after the EFFECTIVE DATE OF CONTRACT but within the contractual period, which entails additional costs, shall be to the account of OWNER. However, any additional cost beyond contractual period shall be in the CONTRACTOR s account provided the delay is solely attributable to CONTRACTOR of of [Bank Guarantee for Performance of CONTRACT] [Bank Guarantee for Performance of CONTRACT] 73 of [Bank Guarantee for Performance of CONTRACT] 73 of a. [Bank If scheduled date of ACCEPTANCE OF PLANT is delayed for any reason, CONTRACTOR shall extend the Bank Guarantee for Performance of CONTRACT without any cost to OWNER. The Bank Guarantee for Performance of CONTRACT will be discharged by the OWNER not later than 15 DAYS following the date of completion of the CONTRACTOR'S performance obligations under the CONTRACT. a. If the CONTRACTOR fails to supply the EQUIPMENT to meet the ACCEPTANCE OF PLANT schedule The Bidder proposes to amend as If scheduled date of ACCEPTANCE OF PLANT is delayed for reasons attributable to the Contractor, CONTRACTOR shall extend the Bank Guarantee for Performance of CONTRACT without any cost to OWNER. The Bidder proposes to amend as The Bank Guarantee for Performance of CONTRACT will be discharged by the OWNER not later than 15 DAYS following its expiry date under the CONTRACT. The Bidder proposes to replace 30 days with 180 days The Bidder proposes to amend as PC54-PNCOM-PBQR RK MN RRK 25 of 31

26 Page Guarantee for Performance of CONTRACT] 74 of and [Termination on Breach and Insolvency] 74 of [Termination for Convenience] and/or The EQUIPMENT that are complete and ready for shipment within 30 DAYS after the CONTRACTOR'S receipt of notice of termination shall be purchased by OWNER from the CONTRACTOR at the CONTRACT terms and prices. For remaining EQUIPMENT, the OWNER may opt: a) to have any portion completed and delivered at the CONTRACT terms and prices and/or a. If the CONTRACTOR fails to supply the EQUIPMENT to meet the ACCEPTANCE OF PLANT schedule (after period covered by MUTUALLY AGREED DAMAGES) and/or The Bidder requests for the termination payment clarity in case of termination due to reason (a) Material Breach by the Contractor and (b) termination for insolvency. F IDIC EPC (edition) would be acceptable to the Bidder. The Bidder proposes to amend as b) to cancel the remainder and pay to the CONTRACTOR an agreed amount for partially completed EQUIPMENT and for equipment/materials and parts previously procured by the CONTRACTOR or of which the Contractor is liable to accept delivery: this EQUIPMENT shall become the property of (and be at the risk of) the Owner when paid for the by the Owner, and the Contractor shall place the same at the Owner s disposal; b) to cancel the remainder and pay to the CONTRACTOR an agreed amount The Bidder proposes to add the following:- d) Any other cost or liability which in the PC54-PNCOM-PBQR RK MN RRK 26 of 31

27 Page for partially completed EQUIPMENT and for materials and parts previously procured by the CONTRACTOR. circumstances was reasonably incurred by the contractor in the expectation of completing the work; plus c) Plus pay to the CONTRACTOR any other commitment cost that may be necessary due to such termination, provided such a claim is supported by documentary evidence from the CONTRACTOR. e) The reasonable costs incurred by Contractor as a result of such termination, including but not limited to costs of demobilisation and any cancellation charges that Contractor must pay Subcontractors and / or Suppliers as a result of such termination plus reasonable overhead, reasonable profit on unexpired portion of Work and any other cost or liability which in the circumstances was reasonably incurred by the contractor in the expectation of completing the work and any loss or damage sustained by the contactor as a result of the termination. f) The amount of any loss of profit or other Losses or damage sustained by the Contractor as a result of termination; g) The cost of removal temporary works and Contractor s equipment from the Site and the return of these items to the Contractor s at its choice of location; plus h) Return of the Bank guarantee or any bond and/or deposits or any sum retained thereof to the Contractor PC54-PNCOM-PBQR RK MN RRK 27 of 31

28 Page of of of [Termination of Contract] [Force majeure] [Force majeure] Notwithstanding anything elsewhere provided in the CONTRACT documents, all advances made by the OWNER to the CONTRACTOR shall forthwith become repayable to the OWNER in the event of the CONTRACT being terminated for any cause. In such event of termination the advance shall be recoverable with SBI BR + 5.5% from CONTRACTOR. The Bidder suggests as under, subject to OWNER agrees for the same interest payment in case of delayed payment to the CONTRACTOR. Notwithstanding anything elsewhere provided in the CONTRACT documents, all advances made by the OWNER to the CONTRACTOR shall forthwith become repayable to the OWNER in the event of the CONTRACT being terminated as per Article (Termination for Default). In such event of termination, the unadjusted advance shall be recoverable with SBI BR + 5.5% from CONTRACTOR. For removal of doubt it is clarified that unadjusted advance shall mean balance of advance money after CONTRACTOR s adjustment against obligations completed and towards dues arising out of termination. Comment:- The local chamber of commerce does not provide for authorisation/countersignature and hence the bidder requests to waive off such provision. Comment:- There is no provision for extension of time in case of force majeure and hence a provision entitling the Contractor to claim for extension of time for such period during which such force PC54-PNCOM-PBQR RK MN RRK 28 of 31

29 Page of [Legal Construction] 75 of [Venue] 77 of [Recovery of sums/dues] 77 of [Cut off dates] 22 OF [VALIDITY OF BID].jurisdiction of the Bharuch Court. venue Bharuch All cost, damages or expenses CONTRACTOR under this CONTRACT or other CONTRACTS and/or may be recovered by action at law or otherwise. No claims or correspondence on this CONTRACT shall be entertained by the OWNER after 3 MONTHS after issue of Certificate of ACCEPTANCE OF PLANT by the OWNER. majeure event lasts shall be incorporated. Comment : The Bidder suggests the jurisdiction to be with AHMEDABAD COURTS due to availability of eminent lawyers and save time and efforts. Comment : The Bidder suggests the place of arbitration as AHMEDABAD being the neutral venue. The Bidder proposes to amend as All cost, damages or expenses CONTRACTOR under this CONTRACT and/or may be recovered by action at law or otherwise. Comment:- The bidder proposes to amend the period of 3 months and replace the same with till the expiry of the warranty period. Considering the volatility of prices of commodities and much shorter bid validity provided by our sub-vendors/subcontractors, it is impossible to provide a bid validity of 9 months. Bidder requests Owenr to reduce the bid validity to maximum 3 months from the date of bid submision. Any extension of bid validity beyond this period needs to be checked at a later date and confirmed by the PC54-PNCOM-PBQR RK MN RRK 29 of 31

30 Page Sheet 24 of 28 Sheet 30 of 78 Sheet 12 of 28 Sheet 58 of The evaluated CONTRACT PRICE will be discounted, as per the billing schedule submitted by the Bidder for the implementation period [Insurance] 10.3 The EMD of unsuccessful Bidders will be returned by OWNER to the unsuccessful Bidders as promptly as possible on acceptance of Bid of the successful Bidder or when the Bidding process is cancelled by OWNER, whichever is later. 7.0 [Advance Payment] Bidder based on specific request from Owner. Please clarify what % discounting will be applied The Insurance coverage mentioned in this clause appears to be very high. Please confirm Bidder propose change as below: The EMD of unsuccessful Bidders will be returned by OWNER as promptly as possible on acceptance of Bid of the successful Bidder or when the Bidding process is cancelled by OWNER, whichever is earlier. As per Article 7.0, 10% Advance shall be paid to the CONTRACTOR on presentation of following documents: a) CONTRACT copy duly signed by PARTIES b) Commercial invoice c) Bank guarantee equal to 110% the amount of advance as per performa at ANNEXURE-1.17 Agreed Note 4 shall be amended accordingly Annex- 1.2 Sheet 55 of 58 Note-4 Contrary to this, Note 4 of Annex-1.2 states : Owner is intending to pay 10% mobilization advance in two installments PC54-PNCOM-PBQR RK MN RRK 30 of 31

31 Page of (first installment of upto 6% and balance in the second installment). The second installment would be paid only after 3 months subject to satisfactory utilization of the 1st advance. Kindly clarify Advance payment will be done as per Article 7.0 PC54-PNCOM-PBQR RK MN RRK 31 of 31

AN ISO 9001 & ISO COMPANY TENDER DOCUMENT. NIT No.: NRO/CON/738/667 date : FOR

AN ISO 9001 & ISO COMPANY TENDER DOCUMENT. NIT No.: NRO/CON/738/667 date : FOR AN ISO 9001 & ISO 14001 COMPANY TENDER DOCUMENT NIT No.: NRO/CON/738/667 date : 12.10.2018 FOR Supply, Installation, Testing, Commissioning & Handing- over of Medical equipments (Group-7F) for Government

More information

General Conditions for Purchase (CG-2)

General Conditions for Purchase (CG-2) Page: 2 of 5 1 Definitions - CLIENT means the party placing an order, being the legal entity as mentioned in the Purchase Order, as well as his legal successors in title; - VENDOR means the party who delivers

More information

7/14/16. Hendry County Purchase Order Terms and Conditions

7/14/16. Hendry County Purchase Order Terms and Conditions Hendry County Purchase Order Terms and Conditions 1. Offer The order set forth in the Purchase Order is subject to cancellation by HENDRY COUNTY without notice if not accepted by VENDOR within fourteen

More information

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS 1. DEFINITIONS AND INTERPRETATION 1.1 Definitions In this Contract (as hereinafter defined)

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Nutreco General Purchase Terms and Conditions

Nutreco General Purchase Terms and Conditions Nutreco General Purchase Terms and Conditions Article 1 - Definitions Agreement Conditions Contract Nutreco Order Products Seller : The purchase agreement between Nutreco and the Seller : The General Purchase

More information

Bidding Documents. Procurement of Goods Laboratory Equipment- Industrial & Management Engineering Department

Bidding Documents. Procurement of Goods Laboratory Equipment- Industrial & Management Engineering Department P a g e 1 Bidding Documents For National Competitive Bidding Pakistan Procurement of Goods Laboratory Equipment- Industrial & Management Engineering Department PART ONE (FIXED) Instructions to Bidders

More information

GENERAL TERMS AND CONDITIONS OF PURCHASE GENERAL TERMS AND CONDITIONS OF PURCHASE

GENERAL TERMS AND CONDITIONS OF PURCHASE GENERAL TERMS AND CONDITIONS OF PURCHASE 1 of 8 1. DEFINITIONS : 1.1. PURCHASER GENERAL TERMS AND CONDITIONS OF PURCHASE The Purchaser means LANKA IOC PLC with its office at Level 20, West Tower, World Trade Centre, Echelon Square, Colmbo 01,

More information

SUPPLIER - TERMS AND CONDITIONS Materials and Goods

SUPPLIER - TERMS AND CONDITIONS Materials and Goods SUPPLIER - TERMS AND CONDITIONS Materials and Goods 1. BINDING EFFECT; ACCEPTANCE. This purchase order and all subsequent purchase orders delivered by Buyer to Seller (each, an "order"), shall be governed

More information

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR CONTRACTOR S COPY SUBCONTRACT NO. Alberta Standard Construction Subcontract THIS AGREEMENT made this day of, A.D. 20 BETWEEN name (hereinafter called the

More information

FATIGUE TECHNOLOGY INC. PURCHASE ORDER TERMS AND CONDITIONS DATED JANUARY 4, 2006

FATIGUE TECHNOLOGY INC. PURCHASE ORDER TERMS AND CONDITIONS DATED JANUARY 4, 2006 FATIGUE TECHNOLOGY INC. PURCHASE ORDER TERMS AND CONDITIONS DATED JANUARY 4, 2006 1. CONTRACT. Fatigue Technology Inc. s, hereinafter called FTI, purchase order, or change order to a purchase order, collectively

More information

DRAWINGS AND DESCRIPTIONS GENERAL CONDITIONS CONCLUSION OF THE CONTRACT, MINIMUM ORDER VALUE & PURCHASE ORDER CHANGES/CANCELLATION DEFINITIONS

DRAWINGS AND DESCRIPTIONS GENERAL CONDITIONS CONCLUSION OF THE CONTRACT, MINIMUM ORDER VALUE & PURCHASE ORDER CHANGES/CANCELLATION DEFINITIONS GENERAL CONDITIONS PREAMBLE 1. The General Conditions, which can also be found on the Supplier s website www.cet-power.com, shall apply to all offers, Purchase Orders, invoices and other documents produced

More information

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE 1. SCOPE ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE 1.1 These general conditions of purchase published at www.zanon.com -shall be deemed as an integral part of any order issued by Ettore Zanon

More information

TRIPURA NATURAL GAS COMPANY LIMITED

TRIPURA NATURAL GAS COMPANY LIMITED TRIPURA NATURAL GAS COMPANY LIMITED GENERAL PURCHASE CONDITIONS (GPC) 1. Consignee: C&P In-charge, TNGC Ltd, Shilpa, Nigam Bhawan, Khejur Bagan, Agartala, Tripura West Any expenditure and/or demurrage

More information

STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES

STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES Definitions Term Contract Meaning the contract formed between Client and Contractor for the supply by Contractor of the Scope of Supply. Contractor 7

More information

UNITED STATES AND CANADA TERMS AND CONDITIONS OF SALE NOVEMBER 2006

UNITED STATES AND CANADA TERMS AND CONDITIONS OF SALE NOVEMBER 2006 UNITED STATES AND CANADA TERMS AND CONDITIONS OF SALE NOVEMBER 2006 1 Definitions Invoice means the invoice issued by the Supplier which described the Products purchased by the Purchaser and which includes,

More information

DOUKPSC04 Rev Feb 2013

DOUKPSC04 Rev Feb 2013 DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby

More information

Town of Whitby Terms and Conditions

Town of Whitby Terms and Conditions Town of Whitby Terms and Conditions Part B - Standard Terms and Conditions 1. Definitions Town - The Corporation of the Town of Whitby, its successors and assigns. Bidder - The person, firm or corporation

More information

GENERAL CONDITIONS for the SUPPLY AND INSTALLATION OF MECHANICAL, ELECTRICAL AND ELECTRONIC PRODUCTS. Brussels, January 2014

GENERAL CONDITIONS for the SUPPLY AND INSTALLATION OF MECHANICAL, ELECTRICAL AND ELECTRONIC PRODUCTS. Brussels, January 2014 ORGALIME SI 14 Lenntech info@lenntech.com Tel. +31-152-610-900 www.lenntech.com Fax. +31-152-616-289 GENERAL CONDITIONS for the SUPPLY AND INSTALLATION OF MECHANICAL, ELECTRICAL AND ELECTRONIC PRODUCTS

More information

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1 COMPLIANCE TO CONDITIONS OF CONTRACT - SCC.1(Renovation) Please indicate clearly below your compliance to each clause of the Conditions of Contract. Where you are not in agreement, you should give your

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

CONDITIONS OF CONTRACT FOR QUOTATION

CONDITIONS OF CONTRACT FOR QUOTATION CONDITIONS OF CONTRACT FOR QUOTATION Version 6.0 Page 1 of 18 CONTENTS Clause Subject matter 1 Definitions and Interpretation 2 Scope of Contract 3 Delivery 4 Removal and Replacement 5 Financial Provisions

More information

PURCHASING TERMS AND CONDITIONS DOMESTIC FLEET

PURCHASING TERMS AND CONDITIONS DOMESTIC FLEET PURCHASING TERMS AND CONDITIONS DOMESTIC FLEET GENERAL Agreement means, collectively, these terms and conditions and the Order to which they apply. CSL means The CSL Group Inc., acting through its Canada

More information

FIXTURE TERMS & CONDITIONS Materials & Goods

FIXTURE TERMS & CONDITIONS Materials & Goods FIXTURE TERMS & CONDITIONS Materials & Goods 1. BINDING EFFECT; ACCEPTANCE. This purchase order and all subsequent purchase orders delivered by Supplier to The Pep Boys Manny, Moe & Jack, and its affiliates,

More information

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M. Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project

More information

ANNEX A Standard Special Conditions For The Salvation Army

ANNEX A Standard Special Conditions For The Salvation Army ANNEX A Standard Special Conditions For The Salvation Army TO BE ATTACHED TO AIA B101-2007 EDITION ABBREVIATED STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT 1. Contract Documents. This Annex supplements,

More information

General Terms and Conditions of Sale of DSM Resins (Far East) Co., Ltd.

General Terms and Conditions of Sale of DSM Resins (Far East) Co., Ltd. GENERAL TERMS AND CONDITIONS OF SALE OF DSM Resins (Far East) Co., Ltd. Seller (as defined below) hereby expressly rejects the applicability of any general conditions of the Customer (as defined below).

More information

Dickinson College Purchase Order Terms and Conditions

Dickinson College Purchase Order Terms and Conditions Dickinson College Purchase Order Terms and Conditions Policy/Procedure This policy covers: A. Introduction B. Terms and Conditions A. Introduction Financial Operations does not require the use of a purchase

More information

PURCHASE ORDER TERMS AND CONDITIONS

PURCHASE ORDER TERMS AND CONDITIONS PURCHASE ORDER TERMS AND CONDITIONS 1. SUPPLY OF GOODS AND/OR SERVICES 1.1 In consideration or payment of the Price by the Company, the Contractor must supply the Goods and/or provide the Services to the

More information

General Conditions of Sale

General Conditions of Sale General Conditions of Sale These are the terms and conditions of sale which apply to all goods sold by the seller to the customer. These terms and conditions shall take precedence over any terms and conditions

More information

SPECIAL CONDITIONS OF CONTRACT

SPECIAL CONDITIONS OF CONTRACT SPECIAL CONDITIONS OF CONTRACT TABLE OF CONTENT PART A: STANDARD PROVISIONS... 95 A1 Scope of the System... 95 A2 Securities... 95 A2.1 Advance Payment Security... 95 A2.2 Performance Security... 95 A3

More information

APPENDIX [ ] TO PURCHASE CONTRACT STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS FOR THE ARLA FOODS GROUP OF COMPANIES.

APPENDIX [ ] TO PURCHASE CONTRACT STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS FOR THE ARLA FOODS GROUP OF COMPANIES. Version 2.2 APPENDIX [ ] TO PURCHASE CONTRACT STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS FOR THE ARLA FOODS GROUP OF COMPANIES between Arla Foods amba VAT No.: 25313763 and [Supplier] VAT

More information

TERMS AND CONDITIONS OF PURCHASE

TERMS AND CONDITIONS OF PURCHASE TERMS AND CONDITIONS OF PURCHASE 1. GENERAL: For purposes of these Terms and Conditions of Purchase, the term Talbots shall mean The Talbots, Inc. The term Order shall mean, collectively: (i) a written

More information

SECTION - IX FORMS AND PROCEDURES

SECTION - IX FORMS AND PROCEDURES SECTION - IX FORMS AND PROCEDURES Kenya Power and Lighting Company IX - 1 Contract A39 Table of Forms NOTIFICATION OF AWARD - LETTER OF ACCEPTANCE... 2 CONTRACT AGREEMENT... 3 APPENDIX 1. TERMS AND PROCEDURES

More information

Purchase Order Terms and Conditions

Purchase Order Terms and Conditions Purchase Order Terms and Conditions Policy/Procedure Financial Operations does not require the use of a Purchase Order (PO) to procure goods or services through the Banner system. However, departments

More information

EMN Europe Purchase Agreement / Sample

EMN Europe Purchase Agreement / Sample EMN Europe Purchase Agreement / Sample The Agreement between Supplier and the ordering division Buyer. (Commercial Terms Contracts. / CTC ). 1. Supply of Products 1.1. The Supplier shall supply to the

More information

Purchasing Terms and Conditions of Schunk Sintermetalltechnik GmbH, Thale, Germany (hereafter SST)

Purchasing Terms and Conditions of Schunk Sintermetalltechnik GmbH, Thale, Germany (hereafter SST) 1. General Purchasing Terms and Conditions of Schunk Sintermetalltechnik GmbH, Thale, Germany (hereafter SST) For all purchasing processes of SST, these Purchasing Terms and Conditions shall apply exclusively.

More information

PURCHASE ORDER ACKNOWLEDGEMENT

PURCHASE ORDER ACKNOWLEDGEMENT PURCHASE ORDER These Terms and Conditions shall apply to this Purchase Order attached hereto as Exhibit A and to all subsequent transactions (whether or not a Purchase Order is used) between Marquette

More information

SECTION GCC GENERAL TERMS AND CONDITIONS OF CONTRACT A. INTRODUCTION

SECTION GCC GENERAL TERMS AND CONDITIONS OF CONTRACT A. INTRODUCTION SECTION GCC GENERAL TERMS AND CONDITIONS OF CONTRACT A. INTRODUCTION 1.0 DEFINITION OF TERMS 1.1 The Contract means the agreement entered into between Owner and Contractor as per the Contract Agreement

More information

AIRPORT AUTHORITY HONG KONG

AIRPORT AUTHORITY HONG KONG AIRPORT AUTHORITY HONG KONG GENERAL CONDITIONS OF CONTRACT BUILDING AND CIVIL WORKS ISSUE NO. 10 August 2011 [this page not used] GENERAL CONDITIONS OF CONTRACT FOR BUILDING AND CIVIL WORKS TABLE OF CONTENTS

More information

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN THE DEKALB COUNTY BOARD OF EDUCATION AND THE CONSTRUCTION MANAGER Construction

More information

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT This Equipment Purchase Agreement ( Agreement ) is entered into this day of, 20, by and between the Western Riverside Council of Governments,

More information

GENERAL CONDITIONS FOR THE SUPPLY OF WORKS

GENERAL CONDITIONS FOR THE SUPPLY OF WORKS VDP_ZoD/2014 GENERAL CONDITIONS FOR THE SUPPLY OF WORKS PREAMBLE 1. These General Conditions (hereinafter referred to as VDP_ZoD ) regulate the conditions in performing a Works between the company ABB,

More information

These Standard Terms and Conditions form a contract between the Company and the Supplier. SUPPLY OF GOODS / SERVICES QUALITY PRICE AND PAYMENT

These Standard Terms and Conditions form a contract between the Company and the Supplier. SUPPLY OF GOODS / SERVICES QUALITY PRICE AND PAYMENT These Standard Terms and Conditions form a contract between the Company and the Supplier. SUPPLY OF GOODS / SERVICES 1. The Supplier shall supply and deliver to the Company all the goods/services set out

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT made by and between, hereinafter called the Owner, and SITESCOMMERCIAL, LLC 185 WIND CHIME COURT, SUITE

More information

PALL INDIA PVT LTD PURCHASE ORDER TERMS AND CONDITIONS

PALL INDIA PVT LTD PURCHASE ORDER TERMS AND CONDITIONS PALL INDIA PVT LTD PURCHASE ORDER TERMS AND CONDITIONS [BETWEEN PALL INDIA AND SUPPLIER INCORPORATED IN INDIA] 1. ACKNOWLEDGEMENT AND ACCEPTANCE 1.1 Supplier shall acknowledge receipt of Pall India Pvt

More information

2.1 UNICEF wishes to procure items in the quantities and with the specifications outlined in the schedules contained in this Solicitation Document.

2.1 UNICEF wishes to procure items in the quantities and with the specifications outlined in the schedules contained in this Solicitation Document. PART I PURPOSE OF THIS INVITATION TO BID 1. BACKGROUND 1.1 UNICEF promotes the rights and wellbeing of every child, in everything we do. Together with our partners, we work in 190 countries and territories

More information

ADVANCED TECHNICAL TRAINING

ADVANCED TECHNICAL TRAINING ADVANCED TECHNICAL TRAINING CENTRE AN ISO 9001:2008 CERTIFIED INSTITUTE BARDANG, SINGTAM, EAST SIKKIM - 737134 Telephones: (03592) 233482/9002735427/9434035381 Email: attc.skmpoly@gmail.com COMPETITIVE

More information

General Terms and Conditions of Sale of DMS Enterprise GmbH

General Terms and Conditions of Sale of DMS Enterprise GmbH General Terms and Conditions of Sale of DMS Enterprise GmbH These General Terms and Conditions have been prepared in English only for information purposes. When in doubt about meaning and intention of

More information

Department of Mechanic, Electronic and Hi-Tech Industry Ministry of Commerce, P.R.C 2008

Department of Mechanic, Electronic and Hi-Tech Industry Ministry of Commerce, P.R.C 2008 Department of Mechanic, Electronic and Hi-Tech Industry Ministry of Commerce, P.R.C 2008 Department of Mechanic, Electronic and Hi-Tech Industry Ministry of Commerce, P.R.C 2008 The Bidding Documents for

More information

THE NATIONAL TREASURY. Republic of South Africa

THE NATIONAL TREASURY. Republic of South Africa THE NATIONAL TREASURY Republic of South Africa GOVERNMENT PROCUREMENT: GENERAL CONDITIONS OF CONTRACT July 2010 THE NATIONAL TREASURY: Republic of South Africa 2 TABLE OF CLAUSES 1. Definitions 2. Application

More information

Annexure - C to TENDER STANDARD COMMERCIAL TERMS & CONDITIONS [FORMAT TO BE FILLED-UP BY THE SUPPLIER]

Annexure - C to TENDER STANDARD COMMERCIAL TERMS & CONDITIONS [FORMAT TO BE FILLED-UP BY THE SUPPLIER] S No. BHEL Standard Terms Supplier Confirmation Deviation 01 Price: Supplier shall be quoted on "FIRM PRICE" basis only. No price variation clause will be entertained. 02 Terms of Delivery: (a) Indigenous

More information

PRONAT INDUSTRIES LTD. ("PRONAT") TERMS AND CONDITIONS OF PRODUCTS SALE AND PROCUREMENT OF SERVICES

PRONAT INDUSTRIES LTD. (PRONAT) TERMS AND CONDITIONS OF PRODUCTS SALE AND PROCUREMENT OF SERVICES PRONAT INDUSTRIES LTD. ("PRONAT") TERMS AND CONDITIONS OF PRODUCTS SALE AND PROCUREMENT OF SERVICES PRONAT'S TERMS AND CONDITIONS OF SALE OF PRODUCTS AND PROCUREMENT OF SERVICES ARE LIMITED TO THOSE CONTAINED

More information

INTERNATIONAL GRAND INVESTMENT CORPORATION TERMS AND CONDITIONS

INTERNATIONAL GRAND INVESTMENT CORPORATION TERMS AND CONDITIONS INTERNATIONAL GRAND INVESTMENT CORPORATION TERMS AND CONDITIONS Except as otherwise provided on the face of this Purchase Order or Supply Contract (the Order ) which is attached hereto, the parties agree

More information

SECTION GCC GENERAL TERMS & CONDITIONS OF CONTRACT A. INTRODUCTION

SECTION GCC GENERAL TERMS & CONDITIONS OF CONTRACT A. INTRODUCTION SECTION GCC GENERAL TERMS & CONDITIONS OF CONTRACT A. INTRODUCTION 1.0 DEFINITION OF TERMS 1.1 The Contract means the agreement entered into between the Owner and the Contractor as per the Contract Agreement

More information

496, Udyog Vihar, Phase-III, Gurgaon Phone:

496, Udyog Vihar, Phase-III, Gurgaon Phone: 496, Udyog Vihar, Phase-III, Gurgaon 122016 Phone: +91-124-2876431 THSTI/NIQ/33/14-15 20 th Aug, 2014 Notice Inviting Quotations On behalf of the Executive Director, THSTI, Gurgaon, Haryana, INDIA, sealed

More information

MODIFICATIONS OR AMENDMENTS:

MODIFICATIONS OR AMENDMENTS: 1. GENERAL: These terms and conditions ("Terms") shall be applicable to any accompanying purchase order received by you ("Supplier") from Advanced Engineering, Inc. ("Purchaser"). The term "Goods and Services"

More information

Imperial Plastics, Incorporated. PURCHAS E ORDER STANDARD TERMS AND CONDITIONS (1/2016 version)

Imperial Plastics, Incorporated. PURCHAS E ORDER STANDARD TERMS AND CONDITIONS (1/2016 version) Imperial Plastics, Incorporated PURCHAS E ORDER STANDARD TERMS AND CONDITIONS (1/2016 version) 1- Definitions. The following definitions apply unless otherwise indicated: (a) the Customer means Imperial

More information

a. Article(s) Goods and/or services described on the face of the Purchase Order

a. Article(s) Goods and/or services described on the face of the Purchase Order TERMS AND CONDITIONS LIBERTY MUTUAL STANDARD TERMS AND CONDITIONS V. 5.0 1. DEFINITIONS a. Article(s) Goods and/or services described on the face of the Purchase Order b. Customer Liberty Mutual Insurance

More information

GENERAL TERMS AND CONDITIONS OF SALE

GENERAL TERMS AND CONDITIONS OF SALE GENERAL TERMS AND CONDITIONS OF SALE 1. PRICES FACILIS prices are exclusive of taxes, shipping, and insurance. Domestic prices apply only to products purchased for use in the United States. Export prices

More information

AGREEMENT No... FOR THE SUPPLY, FABRICATION AND DELIVERY OF... BETWEEN

AGREEMENT No... FOR THE SUPPLY, FABRICATION AND DELIVERY OF... BETWEEN AGREEMENT No.... FOR THE SUPPLY, FABRICATION AND DELIVERY OF... BETWEEN LEND LEASE PROJECT MANAGEMENT & CONSTRUCTION (AUSTRALIA) PTY LIMITED ABN 97 000 098 162 AND... ABN... PROJECT: BARANGAROO PROJECT

More information

United Tool & Mold, Inc. Jungwoo USA, LLC Terms and Conditions of Sale

United Tool & Mold, Inc. Jungwoo USA, LLC Terms and Conditions of Sale United Tool & Mold, Inc. Jungwoo USA, LLC Terms and Conditions of Sale Unless United Tool & Mold, Inc. or Jungwoo USA, LLC (as the case may be, we or similar references) has entered into a written agreement

More information

General Conditions for Consultancy Services Agreements

General Conditions for Consultancy Services Agreements Tebodin Middle East Ltd. P.O. Box 2652, Abu Dhabi, United Arab Emirates General Conditions for Consultancy Services Agreements 6 01.08.2016 Effective date definition changed and Vendor Declaration added

More information

Article 1. Definitions Article 2 Applicability Article 3 Offers Article 4 Prices

Article 1. Definitions Article 2 Applicability Article 3 Offers Article 4 Prices GENERAL TERMS AND CONDITIONS OF SALE AND DELIVERY OF THE VERENIGING PLATFORM PROMOTIONAL PRODUCTS HAVING ITS REGISTERED OFFICE IN AMSTERDAM AND PLACE OF BUSINESS IN (2585 EV) THE HAGUE AT BANKAPLEIN 1A

More information

SECTION III (VOLUME - I) GENERAL TERMS & CONDITIONS OF CONTRACT (GCC)

SECTION III (VOLUME - I) GENERAL TERMS & CONDITIONS OF CONTRACT (GCC) SECTION III (VOLUME - I) GENERAL TERMS & CONDITIONS OF CONTRACT (GCC) GCC percentage tender - 1 - Section-III-GCC GENERAL TERMS & CONDITIONS OF CONTRACT, CONTENTS C1. No. Description A. INTRODUCTION 1.0

More information

Terms & Conditions of Sale Flintec Sweden. 1. Validity of these standard terms and conditions of business

Terms & Conditions of Sale Flintec Sweden. 1. Validity of these standard terms and conditions of business Terms & Conditions of Sale Flintec Sweden 1. Validity of these standard terms and conditions of business (a) The following conditions apply excluding any other terms inconsistent herewith that the buyer

More information

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE

More information

General conditions of contract 2016 for the supply of spare parts

General conditions of contract 2016 for the supply of spare parts General conditions of contract 2016 for the supply of spare parts AMT AG, Badstrasse 34, 5312 Döttingen (Switzerland) 1 General 1.1 The contract shall be deemed to have been entered into upon receipt of

More information

AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal status and address)

AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal status and address) Document A134 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee without a Guaranteed Maximum Price AGREEMENT

More information

STANDARD CONSTRUCTION CONTRACT. THESE ARTICLES OF AGREEMENT made in duplicate and effective the day of 2017: NEW BRUNSWICK POWER CORPORATION

STANDARD CONSTRUCTION CONTRACT. THESE ARTICLES OF AGREEMENT made in duplicate and effective the day of 2017: NEW BRUNSWICK POWER CORPORATION STANDARD CONSTRUCTION CONTRACT THESE ARTICLES OF AGREEMENT made in duplicate and effective the day of 2017: BETWEEN: NEW BRUNSWICK POWER CORPORATION (referred to herein as the Owner) AND (referred to herein

More information

4. QUALITY AND INSPECTION All parts, materials, assemblies and tooling ( Products ) must

4. QUALITY AND INSPECTION All parts, materials, assemblies and tooling ( Products ) must (Form PO-TC 03-11 Revision E1) TENNECO S STANDARD TERMS AND CONDITIONS GOVERNING PURCHASE ORDERS 1. ACCEPTANCE In order to become a valid and binding contract between Supplier and Buyer, this purchase

More information

The Colt General Conditions of Purchase

The Colt General Conditions of Purchase Article 1 Applicability 1. Unless the parties have agreed otherwise in writing, these conditions shall apply to all contracts (for professional services), hereinafter referred to each time as the Contract,

More information

West Bengal Renewable Energy Development Agency. Draft General Terms & Conditions of the Tender

West Bengal Renewable Energy Development Agency. Draft General Terms & Conditions of the Tender West Bengal Renewable Energy Development Agency Draft General Terms & Conditions of the Tender (1) (a) The Tender shall be submitted in triplicate in 3 (three) separate Sealed Covers (COVER-I, II & III)

More information

CONTRACT TERMS AND CONDITIONS: PURCHASE OF MATERIALS (NOT TO EXCEED $300,000 VALUE)

CONTRACT TERMS AND CONDITIONS: PURCHASE OF MATERIALS (NOT TO EXCEED $300,000 VALUE) CONTRACT TERMS AND CONDITIONS: PURCHASE OF MATERIALS (NOT TO EXCEED $300,000 VALUE) 1. DELIVERABLES Contractor agrees to provide the goods, equipment, or items ( Materials ) detailed in the work scope

More information

General Conditions of Sale and Delivery (Germany/Other Countries) (based on the conditions recommended by the German Engineering Federation (VDMA))

General Conditions of Sale and Delivery (Germany/Other Countries) (based on the conditions recommended by the German Engineering Federation (VDMA)) &*UNATE Excellence in Cleaning General Conditions of Sale and Delivery (Germany/Other Countries) (based on the conditions recommended by the German Engineering Federation (VDMA)) Position at December 2012

More information

Vendor Contract TERMS AND CONDITIONS OF PURCHASE. 2. Payment Terms. Payment to Seller is subject to compliance with the following requirements:

Vendor Contract TERMS AND CONDITIONS OF PURCHASE. 2. Payment Terms. Payment to Seller is subject to compliance with the following requirements: Vendor Contract TERMS AND CONDITIONS OF PURCHASE 1. Acceptance. This Contract is conditional upon, and can be accepted only upon, the terms and conditions specified in this Contract. If Seller has previously

More information

PURCHASE ORDER TERMS AND CONDITIONS

PURCHASE ORDER TERMS AND CONDITIONS PURCHASE ORDER TERMS AND CONDITIONS 1. AGREEMENT TO SUPPLY GOODS 1.1 These Terms and Conditions shall apply to all Purchase Orders issued by the Purchaser. The Supplier by its written acceptance of the

More information

PERMIT TO ENTER YOU ARE REQUIRED TO COMPLY WITH THE ENDORSEMENTS AND DETAILS SHOWN ON THIS PERMIT

PERMIT TO ENTER YOU ARE REQUIRED TO COMPLY WITH THE ENDORSEMENTS AND DETAILS SHOWN ON THIS PERMIT PERMIT TO ENTER PERMIT NO: YOU ARE REQUIRED TO COMPLY WITH THE ENDORSEMENTS AND DETAILS SHOWN ON THIS PERMIT KIWIRAIL OFFICE DETAILS OFFICE: Area Office, KiwiRail Network, CONTACT: PHONE NO: Mob Fax PROTECTION

More information

THE UNIVERSITY OF THE WEST INDIES, MONA CAMPUS Procurement Policies and Procedures Manual. Appendices APPENDICES

THE UNIVERSITY OF THE WEST INDIES, MONA CAMPUS Procurement Policies and Procedures Manual. Appendices APPENDICES APPENDICES 53 Appendix 1-1 Agreement Form This Agreement made the...day of...20...between...of...hereinafter called the Employer and...of...hereinafter called the Contractor of the other part. Whereas

More information

CS ENERGY LIMITED SERVICE CONDITIONS

CS ENERGY LIMITED SERVICE CONDITIONS CS ENERGY LIMITED SERVICE CONDITIONS 1. DEFINITIONS In these Conditions: Agreement means the agreement between CS Energy and the Contractor for the provision of Services and comprises the relevant Service

More information

Tel: Fax:

Tel: Fax: Alatas Americas Inc Houston Office 22015 South Frwy. Manvel, Texas 77578 USA Tel: +1 281 431 0707 Fax: +1 281 431 0799 Email: houston@alatas.us Web: www.alatas.com GENERAL TERMS AND CONDITIONS OF SALE

More information

General Terms and Conditions of Business and Deliveries

General Terms and Conditions of Business and Deliveries General Terms and Conditions of Business and Deliveries For the Company RICO GmbH Ferdinand-Porsche-Str. 5 73479 Ellwangen 1 Validity 1. The following conditions are only valid for all offers submitted

More information

Union College Schenectady, NY General Purchasing Terms & Conditions

Union College Schenectady, NY General Purchasing Terms & Conditions Union College Schenectady, NY 12308 General Purchasing Terms & Conditions 1. DEFINITIONS. a. UNION COLLEGE represents the Trustees of Union College, is the purchaser of goods specified in the Purchase

More information

ALL INDIA INSTITUTE OF SPEECH AND HEARING, Naimisham Campus, Manasagangothri, Mysore Global Tender Document. Purchase of Technical Equipment

ALL INDIA INSTITUTE OF SPEECH AND HEARING, Naimisham Campus, Manasagangothri, Mysore Global Tender Document. Purchase of Technical Equipment ; ALL INDIA INSTITUTE OF SPEECH AND HEARING, Naimisham Campus, Manasagangothri, Mysore 570 006 Global Tender Document Purchase of Technical Equipment INDEX Sl. No. Contents Page No. 1. Global Tender Notification

More information

MT WELD MINING PTY LTD ACN Purchase Order Terms and Conditions for the Supply Of Goods and/or Services

MT WELD MINING PTY LTD ACN Purchase Order Terms and Conditions for the Supply Of Goods and/or Services MT WELD MINING PTY LTD ACN 053 160 400 Purchase Order Terms and Conditions for the Supply Of Goods and/or Services 1. GENERAL 1.1 Subject to clause 1.3, these terms and conditions (Terms & Conditions)

More information

NORDSON MEDICAL Standard Terms and Conditions of Purchase Revised March 11, 2015

NORDSON MEDICAL Standard Terms and Conditions of Purchase Revised March 11, 2015 NORDSON MEDICAL Standard Terms and Conditions of Purchase Revised March 11, 2015 1. ORDER APPLICABILITY AND ACCEPTANCE. (A) This purchase order is an offer by Micromedics (dba Nordson MEDICAL ) for the

More information

FleetPride, Inc. Standard Terms and Conditions of Purchase

FleetPride, Inc. Standard Terms and Conditions of Purchase FleetPride, Inc. 1. Terms of Agreement: The following terms and conditions of sale (these Standard Terms and Conditions ) contain general provisions applicable to all FleetPride, Inc. ( FleetPride ) supply

More information

NOTICE INVITING TENDER. Ten No. TEN/004/UPS/AO

NOTICE INVITING TENDER. Ten No. TEN/004/UPS/AO ADMINISTRATIVE OFFICE, BALAJI NAGAR, SIRIPURAM, VISAKHAPATNAM-530003. Phone: 0891-2747383, Fax: 2746061 E mail : cmgb.aovis@sbi.co.in NOTICE INVITING TENDER Ten No. TEN/004/UPS/AO State Bank of India invites

More information

STRATEDGE CORPORATION TERMS AND AGREEMENT OF SALE

STRATEDGE CORPORATION TERMS AND AGREEMENT OF SALE STRATEDGE CORPORATION TERMS AND AGREEMENT OF SALE StratEdge Corporation and Purchaser hereby agree to the following terms and conditions: 1) CONTROLLING DOCUMENT The acceptance by StratEdge Corporation

More information

W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES

W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES INVITATION FOR QUOTATIONS FOR CONSTRUCTION OF CIVIL WORKS UNDER SHOPPING PROCEDURES To Dear Sirs, Sub : INVITATION FOR QUOTATIONS FOR CONSTRUCTION

More information

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition Document A232 2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address) THE CONSTRUCTION MANAGER: (Name,

More information

(i) Draw special attention to certain general conditions applicable to government bids, contracts and orders; and

(i) Draw special attention to certain general conditions applicable to government bids, contracts and orders; and INDEPENDENT REGULATORY BOARD OF AUDITORS PROCUREMENT GENERAL CONDITIONS OF CONTRACT NOTES The purpose of this document is to: (i) Draw special attention to certain general conditions applicable to government

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS 11/21/2011 HENNEPIN COUNTY PURCHASING INSTRUCTIONS TO BIDDERS TABLE OF CONTENTS 1. DEFINITIONS...1 2. BIDDER'S PREBID DOCUMENT REVIEW...2 2.1. Availability of Documents 2 2.2. Interpretation or Correction

More information

General Terms and Conditions of Purchase (edition )

General Terms and Conditions of Purchase (edition ) General Terms and Conditions of Purchase (edition 03.05.2010) 1. Scope of validity 1.1. Orders placed by the Buyer (hereinafter referred to as Buyer ) shall be subject exclusively to these conditions,

More information

City of Miami Blanket Purchase Order Department of Purchasing P.O. Box Miami, Florida (305) Fax - (305)

City of Miami Blanket Purchase Order Department of Purchasing P.O. Box Miami, Florida (305) Fax - (305) Visit our website for business opportunities at: www.miamigov.com/procurement PURCHASE ORDER/RELEASE NUMBER 14537 Show this number on all packages, invoices, and shipping papers. Page No. City of Miami

More information

ProMinent Verder B.V.

ProMinent Verder B.V. Terms & Conditions ProMinent Verder B.V. (30100444) Filed at the Chamber of Commerce on 29-01-2015 1. General 1.1 These terms and conditions use the following terms and definitions: Product: items, as

More information

Standard Terms and Conditions of Sale

Standard Terms and Conditions of Sale 1. Interpretation and Applicability Standard Terms and Conditions of Sale 1.1 The following terms and conditions are to be read in conjunction with the Long Term Supply Agreement, if any. In the event

More information

Byte Paradigm General Conditions ( Design version)

Byte Paradigm General Conditions ( Design version) Byte Paradigm General Conditions ( Design version) Article I General 1. When these General Conditions for Delivery are part of tenders and agreements concerning the performance of deliveries and/or services

More information

General conditions of the V.I.V. (part A) for the sale and supply of products and services.

General conditions of the V.I.V. (part A) for the sale and supply of products and services. General conditions of the V.I.V. (part A) for the sale and supply of products and services. (Association of Importers of Combustion Engines) TRANSLATION of the "Algemene voorwaarden van de V.I.V voor de

More information

PURCHASE ORDER TERMS AND CONDITIONS

PURCHASE ORDER TERMS AND CONDITIONS PURCHASE ORDER TERMS AND CONDITIONS 1. Entire Agreement: (a) This Purchase Order including any addenda, sets forth the entire agreement relating to the purchased products or services and merges all prior

More information