IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA AND IDA-53970) ON A SERIES OF TWO CREDITS

Size: px
Start display at page:

Download "IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA AND IDA-53970) ON A SERIES OF TWO CREDITS"

Transcription

1 Public Disclosure Authorized Document of The World Bank Report No: ICR Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA AND IDA-53970) ON A SERIES OF TWO CREDITS IN THE TOTAL AMOUNT OF SDR MILLION (US$200 MILLION EQUIVALENT) TO THE UNITED REPUBLIC OF TANZANIA Public Disclosure Authorized FOR THE FIRST AND SECOND POWER AND GAS SECTOR DPO December 21, 2017 Public Disclosure Authorized

2 CURRENCY EQUIVALENTS (Exchange Rate Effective as of December 21, 2017) Currency Unit = Tanzania Shilling (T Sh) T Sh 2, = US$1.00 US$1.00 = SDR GOVERNMENT FISCAL YEAR July 1 June 30 TANESCO FINANCIAL YEAR Since July 1, 2015: July 1 June 30 Transition year: January 1, 2014 June 30, 2015 Until December 31, 2013: January 1 December 31 ABBREVIATIONS AND ACRONYMS AfDB CAS DP DPO EPP ESCBP EWURA FYDP GDP GHG IMF IPP IPTL ISR KPI LNG MEM MOF M&E NAO NDC NGUMP NNGIP PDO PPP PPRA PSMP REA SCF TANESCO TPDC USAID African Development Bank Country Assistance Strategy Development Partner Development Policy Operation Emergency Power Producer Energy Sector Capacity Building Project Energy and Water Utilities Regulatory Authority Five Year Development Plan Gross Domestic Product Greenhouse Gas International Monetary Fund Independent Power Producer Independent Power Tanzania Ltd. Implementation Status and Results Report Key Performance Indicator Liquefied Natural Gas Ministry of Energy and Minerals Ministry of Finance and Planning Monitoring and Evaluation National Audit Office Nationally Determined Contribution National Gas Utilization Master Plan National Natural Gas Infrastructure Project Program Development Objective Public Private Partnership Public Procurement Regulatory Authority Power System Master Plan Rural Energy Agency Standby Credit Facility Tanzania Electric Supply Company Tanzania Petroleum Development Corporation U.S. Agency for International Development ii

3 Senior Global Practice Director: Carlos Felipe Jaramillo Country Director: Bella Bird Practice Director: Paloma Anos Casero Task Team Leaders: Jacques Morisset, Yutaka Yoshino ICR Task Team Leader: Joern Huenteler ICR Primary Author: Nestor Ntungwanayo iii

4 CONTENTS Data Sheet A. Basic Information... v B. Key Dates... v C. Ratings Summary... vi D. Sector and Theme Codes... vii E. Bank Staff... viii F. Results Framework Analysis... x G. Ratings of Program Performance in ISRs... xiii H. Restructuring (if any)... xiii 1. Program Context, Development Objectives, and Design Key Factors Affecting Implementation and Outcomes Assessment of Outcomes Assessment of Risk to Development Outcome Assessment of Bank and Borrower Performance Lessons Learned Comments on Issues Raised by Borrower/Implementing Agencies/Partners Annex 1. Bank Lending and Implementation Support/Supervision Processes Annex 2. Beneficiary Survey Results Annex 3. Stakeholder Workshop Report and Results Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR Annex 5. Comments of Cofinanciers and Other Partners/Stakeholders Annex 6. Supporting Data Annex 7. List of Supporting Documents Annex 8. Map iv

5 A. Basic Information Program 1 Country Tanzania Program Name Program ID P L/C/TF Number(s) IDA ICR Date December 21, 2017 ICR Type Core ICR Lending Instrument Original Total Commitment Development Policy Lending Borrower TZ First Power and Gas Sector DPO Ministry of Finance and Planning SDR million Disbursed Amount SDR million Implementing Agency: Ministry of Finance and Planning Cofinanciers and Other External Partners: n.a. Program 2 Country Tanzania Program Name TZ Second Power and Gas Sector DPO Program ID P L/C/TF Number(s) IDA ICR Date December 21, 2017 ICR Type Core ICR Lending Instrument DPL Borrower Original Total Commitment Ministry of Finance and Planning SDR million Disbursed Amount SDR million Implementing Agency: Ministry of Finance and Planning Cofinanciers and Other External Partners: n.a. B. Key Dates TZ First Power and Gas Sector DPO - P Revised/Actual Process Date Process Original Date Date(s) Concept Review: 01/17/2013 Effectiveness: - 06/12/2013 Appraisal: 02/06/2013 Restructuring(s): - - Approval: 03/26/2013 Mid-term Review: 11/07/ /07/2013 Closing: 06/30/ /30/2014 v

6 TZ Second Power and Gas Sector DPO - P Process Date Process Original Date Revised/Actual Date(s) Concept Review: 11/07/2013 Effectiveness: - 06/09/2014 Appraisal: 02/03/2014 Restructuring(s): n.a. n.a. Approval: 03/21/2014 Mid-term Review: 11/07/ /07/2013 C. Ratings Summary Closing: 06/30/ /30/2015 C.1 Performance Rating by ICR Overall Program Rating Outcome Risk to Development Outcome Bank Performance Borrower Performance Moderately Unsatisfactory High Moderately Satisfactory Moderately Unsatisfactory C.2 Detailed Ratings of Bank and Borrower Performance (by ICR) Overall Program Rating Bank Ratings Borrower Ratings Quality at Entry Moderately Satisfactory Government: n.a. Quality of Implementing Moderately Satisfactory Supervision: Agency/Agencies: n.a. Overall Bank Performance Moderately Satisfactory Overall Borrower Performance Moderately Unsatisfactory C.3 Quality at Entry and Implementation Performance Indicators TZ First Power and Gas Sector DPO - P Implementation QAG Assessments Indicators Performance (if any) Potential Problem Program No Quality at Entry (QEA) None at any time (Yes/No): Problem Program at any Quality of Supervision No None time (Yes/No): (QSA) DO rating before Moderately Closing/Inactive status Satisfactory Rating: vi

7 TZ Second Power and Gas Sector DPO - P Implementation QAG Assessments Indicators Performance (if any) Potential Problem Program No Quality at Entry (QEA) None at any time (Yes/No): Problem Program at any Quality of Supervision No None time (Yes/No): (QSA) DO rating before Moderately Closing/Inactive status Satisfactory Rating: D. Sector and Theme Codes TZ First Power and Gas Sector DPO - P Major Sector Energy and Extractives Original Actual Other Energy and Extractives Oil and Gas Major Theme/Theme/Sub Theme Private Sector Development Business Enabling Environment Investment and Business Climate Jobs Job Creation Public Sector Management Public Administration Transparency, Accountability and Good Governance Public Finance Management Public Expenditure Management Urban and Rural Development Rural Development Rural Infrastructure and Service Delivery Urban Development Urban Infrastructure and Service Delivery vii

8 TZ Second Power and Gas Sector DPO - P Major Sector Energy and Extractives Original Actual Other Energy and Extractives Energy Transmission and Distribution Oil and Gas Major Theme/Theme/Sub Theme Private Sector Development Jobs Job Creation Public Private Partnerships Public Sector Management Public Administration Transparency, Accountability and Good Governance Public Finance Management Public Expenditure Management Urban and Rural Development Rural Development Rural Infrastructure and service delivery Urban Development Urban Infrastructure and Service Delivery E. Bank Staff TZ First Power and Gas Sector DPO - P Positions At ICR At Approval Vice President: Makhtar Diop Makhtar Diop Country Director: Bella Bird Philippe Dongier Practice Manager/Manager: Abebe Adugna Dadi Albert Zeufack Task Team Leader: Jacques Morisset Jacques Morisset ICR Team Leader: Joern Huenteler ICR Primary Author: Nestor Ntungwanayo TZ Second Power and Gas Sector DPO - P Positions At ICR At Approval Vice President: Makhtar Diop Makhtar Diop Country Director: Bella Bird Philippe Dongier viii

9 TZ Second Power and Gas Sector DPO - P Positions At ICR At Approval Practice Manager/Manager: Abebe Adugna Dadi Albert Zeufack Task Team Leader: Yutaka Yoshino Yutaka Yoshino ICR Team Leader: Joern Huenteler ICR Primary Author: Nestor Ntungwanayo ix

10 F. Results Framework Analysis Program Development Objective (from Program Document Loan and Program Summaries) The PDO of the program was to (a) strengthen the country s ability to bridge the financial gap in its power sector, (b) reduce the cost of power supply and promote private sector participation in the power sector, and (c) strengthen the policy and institutional framework for the management of the country s natural gas resources. Revised Program Development Objectives The PDO was not revised during the period of implementation of the two operations (DPO-1 and DPO-2). PDO Indicator(s) TZ First and Second Power and Gas Sector DPOs (P and P145254). Pillar 1 Indicator Indicator 1: Value (quantitative or qualitative) Date achieved Comments (including % achievement) Baseline Value Original Target Values (from approval documents) 1 Actual Value Achieved when the DPO program elapsed Actual Value Achieved at the time of the ICR Strengthening the country s ability to bridge the financial gap in its power sector TANESCO operating deficit (US$ million) a (80) b Year to December 31, Year to June 30, 2016 (profit) Year to June 30, 2017 Overachieved, albeit with delay. Improvements in the operating deficit of the Tanzania Electric Supply Company (TANESCO) were a result of (a) tariff reforms, (b) significant cost reductions (Indicator 5), and (c) significant reductions in technical and non-technical losses (Indicator 3). Results were achieved despite a major depreciation of the Tanzanian Shilling during FY2015 (8 percent) and FY2016 (24 percent), affecting TANESCO s fuel cost. Indicator 2: TANESCO accounts (trade and other) payable (T Sh billion) Value (quantitative ,187 a 1,331 b or qualitative) Date achieved June 30, 2016 June 30, 2017 Comments (including % achievement) Indicator 3: Not achieved, because of (a) pressure on TANESCO s cash flow as external financing is insufficient for TANESCO s investment program, including for new connections; (b) insufficient surplus cash generated from operations; and (c) a major depreciation of the T Sh (see Indicator 1) (TANESCO s arrears are mostly denominated in U.S. dollars but indicator is in Tanzania Shilling). TANESCO technical and non-technical losses in transmission and 1 Indicators and their targets were partially revised during the preparation and approval of the second DPO in February The DPO series assesses the Program against the revised indicators. x

11 TZ First and Second Power and Gas Sector DPOs (P and P145254). Indicator Baseline Value Original Target Values (from approval documents) 1 Actual Value Achieved when the DPO program elapsed Actual Value Achieved at the time of the ICR distribution (%) Value (quantitative c c or qualitative) Date achieved Year to June 30, 2016 Year to June 30, 2017 Comments (including % achievement) Achieved and subsequently exceeded, as a result of measures to enhance transparency in and accountability for TANESCO s operational performance, Pillar 2: as well as investments in grid strengthening. Reducing the cost of power supply and promoting private sector participation in the power sector Indicator 4: Amount of gas-fired power generation capacity commissioned after 2011 (MW) Value (quantitative d 255 d or qualitative) Date achieved March 20, 2016 June 30, 2017 Comments (including % achievement) Not achieved. The Kinyerezi I gas power plant (150 MW) was fully commissioned in 2016 and the first unit of Kinyerezi II is expected to be commissioned by the end of However, while construction of both power plants was delayed, the pressure to commission new capacity was less than anticipated as demand grew much slower than expected (actual sales in 2016 were 17% lower than projected in the Program Document of the first Development Policy Operation [DPO-1]) and hydrology conditions have been relatively favorable. However, TANESCO will need to secure additional capacity soon to be able to withstand another major drought. Indicator 5: Average unit cost of power sales (US$/kWh) Value (quantitative 0.18 f a 0.09 b or qualitative) Date achieved Year to June 30, Year to June 30, Comments (including % achievement) Achieved and significantly exceeded, as a result of (a) the phaseout of emergency power plants, made possible by relatively good hydrological years in 2015 and 2017, new gas-fired generation capacity, and relatively slow demand growth; (b) a shift from oil products to natural gas in the generation mix; and (c) significant reductions in technical and non-technical losses (Indicator 3). Indicator 6: Number of bids for gas IPP power plants launched on a competitive basis (count) Value (quantitative or qualitative) Date achieved March 20, 2016 June 30, 2017 Comments (including % achievement) Not achieved. The pressure to secure new capacity has not been as high as anticipated (see Indicator 4). In addition, a series of major sector governance controversies relating to independent power producers (IPPs) and emergency power producers (EPPs) slowed down plans for procurement of privately-owned xi

12 TZ First and Second Power and Gas Sector DPOs (P and P145254). Indicator Baseline Value Original Target Values (from approval documents) 1 Actual Value Achieved when the DPO program elapsed Actual Value Achieved at the time of the ICR generation capacity during the Program period. Indicator 7: Ministry of Energy and Minerals (MEM) 2 documents on sector reforms published for public knowledge (count) Value (quantitative or qualitative) Date achieved March 20, 2016 June 30, 2017 Comments (including % achievement) Achieved. The two major sector reform documents approved by MEM since 2012 are (a) the Electricity Supply Industry Reform Strategy and Roadmap (2014) and (b) the National Energy Policy (2015). Pillar 3 Strengthening the policy and institutional framework for the management of the country s natural gas resources Indicator 8: Volume of gas produced (mmscfd) Value (quantitative e 132 e or qualitative) Date achieved Year to December 31, 2015 Year to December 31, 2016 Comments (including % achievement) Not achieved. Growth in gas production has been much slower than anticipated at approval of the DPOs, largely due to (a) slow domestic demand growth (see Indicator 4); (b) the decline in global energy prices; and (c) slow reform progress in the upstream regulatory and policy framework. Indicator 9: Amount of onshore proven natural gas reserves (Tcf) Value (quantitative e e or qualitative) Date achieved April 1, 2015c December 31, 2016 Comments (including % achievement) Not achieved. Probable reserves are now estimated at 57 Tcf. However, investment exploration and production (which would probable reserves into proven reserves ) has been subdued, largely due to (a) slow domestic demand growth (see Indicator 4); (b) the decline in global energy prices; and (c) slow reform progress in the upstream regulatory and policy framework. Indicator 10: Annual monitoring under the Natural Resource Charter initiative Value (quantitative No Yes No No or qualitative) Date achieved March 20, 2016 June 30, 2017 Comments (including % achievement) Not achieved. Reform progress in the upstream regulatory and policy framework has been much slower than anticipated, as a result of a series of sector governance controversies in the energy and minerals sectors (details in the main text) in combination with a change in Government and policy priorities and the decline in global energy prices which made the development of Tanzania s 2 The ICR was prepared before the Ministry of Energy and Minerals was renamed the Ministry of Energy in late xii

13 TZ First and Second Power and Gas Sector DPOs (P and P145254). Indicator Baseline Value Original Target Values (from approval documents) 1 Actual Value Achieved when the DPO program elapsed Actual Value Achieved at the time of the ICR natural gas resources less lucrative. a. Source: Audited financial statements of TANESCO. b. Source: Draft unaudited financial statements of TANESCO. c. Source: TANESCO. d Source: TANESCO. e. Source: National Bureau of Statistics; Tanzania Petroleum Development Corporation. Note: f. Updated data suggest that the 2012 baseline was 0.16; the value in 2013 was G. Ratings of Program Performance in ISRs TZ First Power and Gas Sector DPO - P Date ISR Actual Disbursements No. DO IP Archived (US$, millions) 1 04/16/2014 Moderately Satisfactory Moderately Satisfactory TZ Second Power and Gas Sector DPO - P Date ISR Actual Disbursements No. DO IP Archived (US$, millions) 1 08/13/2015 Moderately Satisfactory Moderately Unsatisfactory H. Restructuring (if any) There were no program restructurings during the period of implementation of the two operations (DPO-1 and DPO-2). However, results indicators and triggers were revised during the appraisal of DPO-2. xiii

14 1. Program Context, Development Objectives, and Design 1. This Implementation Completion and Results Report (ICR) assesses the results of the programmatic series of two Development Policy Operations (DPOs) to the United Republic of Tanzania. The DPO series aimed to (a) strengthen the country s ability to bridge the financial gap in its power sector, (b) reduce the cost of power supply and promote private sector participation in the power sector, and (c) strengthen the policy and institutional framework for the management of the country s natural gas resources. The first operation (DPO-1) of SDR million was approved by the World Bank s Board of Directors on March 26, The second operation (DPO-2) of SDR million was approved on March 21, The series was originally set up to consist of three programmatic DPOs. However, because of a delay in implementing the prior actions for DPO-3, on March 20, 2016 the programmatic series was considered to have lapsed because no subsequent operation was presented to the Board within 24 months after the Board approval of the previous operation in the series. A concept review meeting for a follow-up series of two operations was held in July 2016, but preparation of the follow-up DPO series was cancelled at the time of this ICR. 1.1 Context at Appraisal 3. When the DPO reform program was initiated in 2013, only 16 percent of Tanzanians had access to electricity and the lack of access to affordable and reliable energy was viewed as a major constraint to Tanzania s economic growth and diversification. Based on the latest Household Budget Survey 2011/12 data, only 16 percent of the population had access to electricity. Tanzania had access rates that were higher than Malawi and Uganda (9 percent) but lower than Kenya and Zambia (over 20 percent) and far lower than developing countries of East Asia (more than 90 percent coverage) and South Asia (62 percent). Access to the national grid was particularly limited in rural areas and for the poor. Only 1.1 percent of the lowest income quintile in rural areas had access to electricity. 3 U.S. Agency for International Development (USAID) and World Bank studies 4 found that poor infrastructure, especially power and transport, was a key constraint to economic growth and diversification in Tanzania. Managers of firms and most Tanzanian enterprises considered routine load shedding and power outages to be the most serious constraint to doing business. The lack of access to cheap and reliable energy was costing local firms as much as 5 percent of sales and as much as 18 percent for manufacturing firms. This scale was consistent with other reports in Africa, which suggest that power outages result in significant losses equivalent to 6 16 percent of turnover. To promote electricity access, in early 2013, the Government reduced connection fees by 30 percent to 90 percent, and instructed the Tanzania Electric Supply Company (TANESCO) to increase its customers base to 1,500,000 by 2015 and target 250,000 new connections per year. 4. Reforms to modernize Tanzania s power sector had begun in the early 2000s but a significant sector reorganization, stipulated by the Electricity Act of 2008, still had to be implemented. TANESCO, the vertically integrated utility, was corporatized in 2002 under the Public Corporations Act, but is still fully government-owned. The company was under a private management contract between May 2002 and December 2006, which focused on financial and technical performance improvements. A Rural Electrification Agency was established through the Rural Energy Act of 2005, with the mission to promote and facilitate availability and access to modern energy services in rural 3 National Panel Survey, USAID Tanzania Growth Diagnostics, Partnership for Growth. and World Bank Investment Climate Assessment. 1

15 mainland Tanzania. An independent Energy and Water Utilities Regulatory Authority (EWURA) became operational in This was followed by the adoption of an Electricity Act in 2008, which established a stronger separation between ownership, policy, and regulatory functions and created a clearer framework for sector governance, licensing, and tariff regulation. The Act included a mandate for the Ministry of Energy and Minerals (MEM) to prepare and publish a policy for the reorganization of the electricity market. The Act also stipulated the strengthening of the governance of TANESCO, reforming its top management structure and creating a Board of Directors with public and private sector stakeholder representations. However, implementation of the Electricity Act of 2008 had yet to make significant progress by the time of the appraisal of DPO-1, and the Government retained strong influence over all decision-making in the sector. 5. Tanzania was facing a power supply crisis during the appraisal of DPO-1 and DPO-2, which threatened to derail the country s industrialization agenda, put severe financial strain on TANESCO and the Government, and endangered its electricity access targets. In the years leading up to the DPO series, Tanzania was experiencing declining reserve capacity, triggered by growing demand and years of underinvestment in new and diversified generation capacity. Out of total of 1,092 MW of installed capacity in 2010, hydropower represented 52 percent, natural gas 33 percent, oil products 13 percent and imports 1 percent. In FY2010/11, as a result of poor rainfall that reduced hydropower production, Tanzania started experiencing a series of supply deficit. At the peak of the crisis, in mid-2011, some parts of the country experienced daily load shedding of up to 12 hours. TANESCO entered into expensive, short-term contracts with private emergency power producers (EPPs) to provide a total of 317 MW of generation capacity. These steps eased supply shortages but significantly increased the cost of supply: In 2012, the share of electricity generation of the EPPs was 11 percent, but their share of costs was 43 percent, doubling the average unit cost of sales (from US$0.08 per kwh in 2010 to US$ per kwh in 2012). This turned the power supply crisis into a financial crisis when the regulator did not pass through the additional costs to consumers. In mid-2012, TANESCO s financial shortfall was running at more than US$40 million per month, as the hydrological condition continued to be below average, while electricity demand kept increasing, requiring continued engagement of the expensive EPPs. TANESCO accumulated arrears to the EPPs, independent power producers (IPPs), and fuel and other suppliers, as tariffs and Government transfers to the sector did not keep up with the rising cost of supply. By the end of 2014, the total cumulative financial gap of the energy sector was expected to be between US$760 million and US$1 billion (or between 2.9 percent and 3.8 percent of gross domestic product [GDP]). The reform program prepared by the Government in response to this power supply crisis (the Program ) was supported by the DPO series (envisioned as programmatic DPO series with three operations). The Program was also supported by the IMF and the AfDB. 6. To respond to the power sector crisis, the Government had prepared a Program of reforms that included (a) crisis-response measures to address the short-term fiscal risks; and (b) medium- to long-term reform measures to prevent a similar crisis from repeating in the future. The Program had support at the highest levels of the Government and had been developed in close collaboration with development partners (DPs). It consisted of prior actions under three, interlinked pillars. The short term, crisis-response elements of the Porgram included measures to close the financial gap in the power sector through a combination of tariff reforms, transparent Government transfers to TANESCO, and Government-guaranteed commercial borrowing by TANESCO (Pillar 1). The medium to long-term reform measures (crisis-prevention) aimed at ensuring that the power and the gas sectors are developed 5 At the time of appraisal, the estimate of the cost of supply in 2012 was US$0.18, which is reflected in the baseline of Results Indicator 5. However, more recent statistics indicate that the average cost of supply was US$0.16 in FY2012 and US$0.18 in FY

16 and operated in a more efficient, transparent, and financially sustainable manner. To reduce the cost of supply and mitigate the risk of supply shocks (such as droughts or oil price increases), the authorities intended to shift the energy mix away from the expensive emergency supply to more efficient, gas-fired generation, developed through the private sector (Pillar 2). To ensure sufficient gas supply to the power sector (and the economy overall), the authorities aimed to develop a framework to attract investment in upstream natural gas exploration and production (Pillar 3). 7. Increasing gas production in a relatively short period and at relatively low cost required an adequate investment framework that had the capacity to incentivize investment in gas production. During , the Government s strategy was to use existing nearshore gas reserves to supply new gas power plants through the construction of a new pipeline. In the longer term, the authorities planned to invest in renewable resources and possibly coal and hydroenergy. The development of offshore massive gas reserves was at the top of the Government s agenda, but the expected impact on economic growth and poverty was expected to occur only when production starts in about 7 10 years. The objective of the strategy was not only to increase power capacity but also to significantly reduce production costs by lowering the reliance of the energy network on expensive fuel power plants. It could also help diversify the risks associated with climatic shocks and variations in fuel prices on international markets. The DPO series was to support this medium-term vision. 8. The proposed series was to complement a larger World Bank portfolio supporting the energy sector of Tanzania directly or indirectly. Ongoing and planned complementary World Bank interventions cited in the Program documents included the following: (a) investment lending that intended to promote access to energy, strengthen the transmission and distribution network, and expand use of renewable energy 6 ; (b) the Energy Sector Capacity Building Project (ESCBP, P126875) 7 ; (c) nonlending analytical work and technical assistance on the multisector gas agenda; (d) a potential policy-based guarantee operation to increase the capacity of TANESCO to borrow commercially at attractive terms; and (e) ongoing and future general budget support aimed at improving effectiveness and transparency in public finance areas including revenue mobilization and public investment management. 9. The country s macroeconomic performance during the period covered by the DPO program was broadly positive (Table 1). The real GDP annual growth for Tanzania remained high during FY , averaging about 7.0 percent, driven by construction and services. In FY2016/17, the growth rate is projected to reach 6.6 percent. The inflation rate remained low and stable. The external balance improved, with the current account deficit falling from14.3 percent in FY2012/13 to an estimated 2.8 percent in FY2016/17. The fiscal deficit improved sharply after FY2012/13 from 6.8 percent of GDP to around 3 percent of GDP, and remained stable throughout the Program period. However, a looser monetary policy has yet to translate into a reduced cost of borrowing for the private sector or into increased private investment, partly because of the continued uncertainty. Going forward, fiscal and monetary policy challenges remain, with persistently high domestic payment arrears (at around 6 percent of GDP at the end of FY2016/17) and the low execution rate of the development budget (62 percent in FY2016/17) threatening the credibility of the budget. The growth outlook is favorable in the short- to medium-term, with key risks being both mostly domestic and under the Government s control. In the medium term, the main risks relate to a further deterioration in business sentiment as a result of increased policy uncertainty and to a decline in the execution rate of the development budget. The most significant 6 At the time of appraisal, the World Bank was supporting the Government s access agenda and renewable energy objectives (Tanzania Energy Development and Access Project [TEDAP], 2008; US$167 million) as well as investment in transmission grid expansion (Backbone Transmission Project 2010; US$150 million). 7 The ESCBP (2015; US$35 million) provides capacity building to the Government and its institutions. 3

17 external risks relate to potential rebounds in oil prices, volatile global financial conditions, and a decline in demand from Tanzania s main export partners. Table 1. Key Economic Indicators: FY2012/13 FY2016/17 (in percent unless otherwise indicated) Government Fiscal Years (July 1 June 30) 2013/ / / /17 e 2017/18 f 2018/19 f Real GDP growth, at constant market prices Private Consumption Government Consumption Gross Fixed Capital Investment Exports, Goods and Services Imports, Goods and Services Real GDP growth, at constant factor prices Agriculture Industry Services CPI Current Account Balance (% of GDP) Financial and Capital Account (% of GDP) Net Foreign Direct Investment (% of GDP) M3 growth (in FY) Private sector credit growth (in FY) Revenue (% of GDP) Expenditure (% of GDP) Fiscal Balance (% of GDP) Arrears (% of GDP, in FY) Debt (% of GDP) Notes: e = estimate, f = forecast. Source: International Monetary Fund (IMF) Report, World Bank Staff. Note: a. Net of treasury bills issued for liquidity management. b. Excludes interest payments due on external debt under negotiation for relief and domestic unpaid claims. 1.2 Original Program Development Objectives (PDO) and Key Indicators (as approved) 10. The PDO of the Program supported by DPO-1 and DPO-2 was to (a) strengthen the country s ability to bridge the financial gap in its power sector, (b) reduce the cost of power supply and promote private sector participation in the power sector, and (c) strengthen the policy and institutional framework for the management of the country s natural gas resources. 4

18 11. The Program s results indicators are shown in Table Revised PDO and Key Indicators, and Reasons/Justification 12. No changes were made to the PDO between DPO-1 and DPO DPO-2 made some changes to selected indicators with the aim to better align with the interpretation of the original objectives and capture progress toward them. It also added three new results indicators and revised the target year of all indicators from 2015 to Table 2 presents the two sets of indicators indicating the concordance between them. When referring to results indicators of the DPO series, this ICR refers to the numbering shown in Table 2 (for example, Results Indicator 1 is TANESCO s operating deficit). 14. The revised indicators are used in this ICR to evaluate the DPO series. When assessing the DPO series achievement of its PDOs, this ICR takes into account that the results indicators were designed for a series of three operations but only two out of three planned DPOs were approved. # Table 2. Original and Adjusted Results Indicators of the Program Indicator as Approved under DPO-1 Indicator as Approved under DPO-2 Baseline a (2012) Pillar 1: Strengthening the country s ability to bridge the financial gap in its power sector 1 TANESCO operating deficit (US$, millions) 2 Amount of accumulated arrears to suppliers by TANESCO (US$, millions) TANESCO operating deficit (US$, millions) TANESCO accounts (trade and other) payable (T Sh, billions) 240 (DPO-1: 244) T Sh 707 billion (DPO-1: US$276 million) Target a (2016) 50 T Sh 300 billion (DPO-1: US$50 million) Pillar 2: Reducing the cost of power supply and promoting private sector participation in the power sector 3 TANESCO technical and nontechnical losses in transmission and distribution (%) 4 New generation capacity added to the system, cumulative (MW) 5 Average unit cost of power sales (US$/kWh) 6 Number of bids for gas IPP power plants launched on a competitive basis Amount of gas-fired power generation capacity commissioned after 2011 (MW) Average unit cost of power sales (US$/kWh) Number of bids for gas IPP power plants launched on a competitive basis 7 MEM documents on sector reforms published for public knowledge (DPO-1: >600) 0.18 b (DPO-1: 0.20) (DPO-1: 0.13) Pillar 3: Strengthening the policy and institutional framework for the management of the country s natural gas resources 8 Volume of gas produced (mmscfd) Volume of gas produced (mmscfd) (DPO-1: >290) 5

19 # Indicator as Approved under DPO-1 9 Amount of onshore proven natural gas reserves (Tcf) Indicator as Approved under DPO-2 Amount of onshore proven natural gas reserves (Tcf) Baseline a (2012) Target a (2016) 10 Annual monitoring under the Natural Resource Charter initiative No Yes Note: MEM = Ministry of Energy and Mining; mmscfd = Million Standard Cubic Feet per Day; Tcf = Trillion Cubic Feet. a. Values in brackets are from DPO-1. b. Updated statistics indicate that the baseline cost was 0.16 in 2012 and 0.18 in Original Policy Areas Supported by the Program 15. The DPO series supported three main policy areas, which also formed the elements of the PDO: (a) strengthening the country s ability to bridge the financial gap in the power sector, (b) reducing the cost of power supply and promoting private sector participation in the power sector, and (c) strengthening the policy and institutional framework for the management of the country s natural gas resources. Below is a description of the expected outcome, the prior actions completed under the two first operations, and the triggers that were to set the stage for the third operation. Pillar 1: Strengthening the country s ability to bridge the financial gap in its power sector 16. Expected outcomes. Pillar 1 aimed to restore the financial sustainability of the sector by (a) raising TANESCO s collected revenues close to a cost-reflective 8 level and (b) arresting and eventually reversing the buildup of arrears. These outcomes, measured by the size of TANESCO s operating deficit and the level of its arrears, were expected to be affected by measures under Pillar 1 (which focused on the revenue side of TANESCO s income statement) as well as Pillars 2 and 3 (which tackled the cost of electricity supply). 17. Prior actions and triggers. Under DPO-1 and DPO-2, the Government implemented measures to (a) increase tariffs and improve bill collection, including from Government consumers and (b) ensure fiscal transfers to TANESCO are determined based on TANESCO s needs as well as transparent and consistent with an adequate macroeconomic policy framework. Triggers for DPO-3 (as approved under DPO-2) were a comprehensive national subsidy policy with principles for subsidizing the energy sector and a commitment to reduce the level of transfers to TANESCO in FY2014/15 to the level of not more than 2 percent of controlled total public expenditure. 9 Pillar 2: Reducing the cost of power supply and promoting private sector participation in the power sector 18. Expected outcomes. Pillar 2 aimed to reduce the cost and risks related to power supply by (a) reducing system losses; (b) promoting private investment to overcome the supply shortage and ending the dependence on EPPs; (c) replacing costly and polluting oil-fired power generation with natural gas-based 8 Cost-reflective revenues are understood for this ICR as revenues that are sufficient to cover TANESCO s cost. The cost incurred by the Government of servicing debt on behalf of TANESCO is not included in this definition. 9 Controlled total expenditure = total expenditure consolidated funds service wage foreign development expenditure. 6

20 generation in Tanzania s power mix; and (d) enhancing sector governance and performance through closer monitoring, enhanced access to information for all stakeholders, and the adoption of a participative and consultative approach to problem solving and policy formulation. These outcomes were to be measured by newly installed generation capacity, loss reduction, unit cost of power sales; launched tenders for private sector-owned generation capacity; and sector reform documents published by the MEM. Expected outcomes of Pillar 2 were interlinked with those of Pillars 1 and 3, in two main ways: First, as mentioned earlier, prior actions under this pillar were also expected to contribute to the outcomes of Pillar 1. Second, the additional upstream gas investments required for additional gas-fired power plants (Results Indicator 2) were to be enabled through measures under Pillar Prior actions and triggers. Under DPO-1 and DPO-2, the Government adopted, and took measures to implement, a new strategic power sector policy. Implementation measures included (a) a performance contract between TANESCO and the MEM; (b) period publication of performance reports, financial audits, and procurement audits; and (c) launching a capacity-building program. The Government also prepared a road map for structural reforms, which was to be approved under DPO-3. Triggers for DPO-3 (as approved under DPO-2) were for (a) TANESCO to continue improving and reporting publicly on collection performance and on operational losses, (b) the Government to phase out 150 MW of EPPs, (c) TANESCO to implement the 2013 policy to promote private sector participation in power generation by launching at least one competitive bidding process for new gas-based generation capacity to diversify power generation sources in the country toward lower cost structure of the power sector, and (d) the Government to approve the road map for structural reforms of the energy sector (including the power and gas subsectors). Pillar 3: Strengthening the policy and institutional framework for the management of the country s natural gas resources 20. Expected outcomes. Pillar 3 aimed to expand gas supply to the sector by strengthening the policy and institutional framework of the upstream gas sector. This expected outcome was likely to contribute to the objectives of the other two pillars, as secure gas supply for its planned gas-fired generation capacity was critical to reduce costs (Pillar 2) and restore the balance of revenues and costs in the sector (Pillar 1). 21. Prior actions and triggers. Under DPO-1 and DPO-2, the Government has put in place the first building blocks of the policy and institutional framework. The Government (a) adopted a Natural Gas Policy, based on a consultative process; (b) launched a program to adopt a Tanzania Natural Resource Charter; (c) elevated the natural gas agenda by including natural gas development in the mandate of the Cabinet committee on economic affairs and creating an interministerial senior task force; (d) cleared arrears with gas developers; (e) verified the amount of natural gas reserves in the United Republic of Tanzania s territory; and (f) mandated the Tanzania Petroleum Development Company (TPDC) to publish its audited financial statements; its latest procurement audit reports, and its key performance indicators (KPIs). Triggers for DPO-3 (as approved under DPO-2) foresaw the completion of the major building blocks of the policy and institutional framework by (a) adopting a National Gas Utilization Master Plan, (b) preparing new natural gas legislation, and (c) and adopting a Petroleum Policy. Distinction between crisis response elements and medium- to long-term reform elements of the Policy and Results Matrix in this ICR 22. In the narrative and assessment, this ICR distinguishes crisis-response elements of the Policy and Results Matrix on the one side and medium- to long-term reform elements on the other. The three pillars group prior actions of the DPO series according to the objectives. However, for the purpose of the assessment carried out in this ICR it was considered useful to distinguish between shortterm (crisis response) measures that yielded immediate results and reforms to the energy sector structure, 7

21 sector policy framework, and sector institutions that could be expected to translate into tangible outcomes only in the medium to long term. The former includes measures on tariffs, arrears clearance, and fiscal transfers under Pillar 1 and also measures relating to performance contracts and performance audits under Pillar 2 and arrears clearance under Pillar 3. The latter includes most reform measures under both Pillar 2 and Pillar 3. This distinction was made because as laid out in sections 2 6 of this ICR, the assessment of adequacy of design and objectives of the DPO series was found to differ significantly between these two elements of the Policy and Results Matrix. 1.5 Revised Policy Areas 23. The policy areas for the PDO program were not revised. The Policy and Results Matrix approved with DPO-2 included only relatively small changes to the prior actions of DPO-2 compared to the triggers approved with DPO-1, as summarized in Table 5 in section Other Significant Changes 24. The Government and IDA did not proceed with the proposed third operation in the series because of delays in the implementation of the Program. On March 20, 2016, the programmatic series was considered lapsed because no subsequent operation was presented to the Board within 24 months after the Board approval of the previous operation in the series (in this case, DPO-2). A concept review meeting for a follow-up series of two operations (DPO-3 and DPO-4) was held in July 2016, but preparation of the follow-up DPO series was cancelled at the time of the ICR. Details on the reasons for the delays and the status of triggers for DPO-3 are provided in section Key Factors Affecting Implementation and Outcomes 2.1 Program Performance 25. The programmatic series consisted of two single-tranche DPOs, disbursed in full upon effectiveness, in the total amount of SDR million. Key dates of the two operations are provided in Table 3. Table 3. Key Dates of the DPO Series Operation Disbursed Amount Approval Effectiveness Date Closing DPO-1 SDR 64.9 million March 26, 2013 June 12, 2013 June 30, 2014 DPO-2 SDR 65.2 million March 21, 2014 June 9, 2014 June 30, All prior actions were completed by the Government before the Board presentation of DPO-1 and DPO-2. Table 4 shows the key objectives pursued and all prior actions completed ahead of the approval of each operation. None of the prior actions was reversed after Board approval. However, progress on some reform areas tackled by the prior actions either slowed down or was partially reversed in subsequent years (see section 3.2 for details). Table 4. Policy Matrix and Status of Prior Actions Prior Action Status Pillar 1: Strengthening the country s ability to bridge the financial gap in its power sector Prior action #1.1: TANESCO has increased its collection of revenues by 30% between Completed 8

22 Prior Action Status CY2011 and CY2012, through tariff increase and improved collections of bills. Prior action #1.2: To improve the financial conditions of TANESCO in FY2013, (a) EWURA reviewed the current electricity tariffs; (b) the Government has identified the amount of subsidies to be transferred from the Government budget to TANESCO based on, among others, the abovementioned tariff review; and (c) the Government has paid T Sh 67 billion by June 2012 to clear its arrears to TANESCO for electricity consumed by governmental entities. Prior action #2.1: TANESCO has implemented new tariffs, approved by EWURA in December 2013 in order to increase its revenue. Prior action #2.2: The Government had created in its approved FY2013/14 budget a specific code with funds for transfers to TANESCO to improve fiscal transparency. Prior action #2.3: The Government has taken actions to reduce the level of transfers to TANESCO from the level of FY2012/13 and has committed that the level will not exceed 2.5 percent of controlled total expenditure in FY2013/14. ahead of DPO-1 Completed ahead of DPO-2 Pillar 2: Reducing the cost of power supply and promoting private sector participation in the power sector Prior action #1.3: The Government adopted a policy aiming to reduce the cost of power supply, improve the operational efficiency of the power sector, and promote the participation of the private sector in power generation through a competitive and transparent bidding process that respects the national laws and the best practices of international environmental and social standards. Prior action #1.4: TANESCO and the Ministry of Energy and Mining signed a performance contract, which includes measurable key performance indicators for TANESCO to enhance its efficiency in CY2013. Prior action #1.5: TANESCO published (a) periodic performance reports prepared by TANESCO against the key performance indicators set out in the abovementioned performance contract between TANESCO and MEM; (b) its latest annual audit report issued by NAO; and (c) its latest annual performance report issued by PPRA. Prior action #2.4: The Government and TANESCO have implemented the initial phase of the 2013 Policy for Private Sector Participation in Power Generation through Competitive Processes by launching PPP capacity-building programs for (a) screening and conducting due diligence; (b) financial structuring; (c) structuring processes for selecting developers and implementing transactions; (d) preparing legal and regulatory documents; and (e) managing government and public corporation fiscal risks. Prior action #2.5: The Government has adopted the recommendations of the Presidential Big Results Now (BRN) Initiative to develop a road map for structural reforms of the energy sector and has established a Ministry Delivery Unit within MEM to oversee the implementation of the recommendations. Completed ahead of DPO-1 Completed ahead of DPO-2 Pillar 3: Strengthening the policy and institutional framework for the management of the country s natural gas resources Prior action #1.6: The Government completed a nationwide public consultation process for adopting its Natural Gas Policy. Prior action #1.7: The Government adopted measures, including clearing arrears with gas developers by paying them US$106.9 million by December 2012 and verifying the amount of natural gas reserves in the United Republic of Tanzania s territory, which will enable higher production of natural gas and its use in power generation after CY2014. Prior action #2.6: The Government has adopted the Natural Gas Policy. Completed ahead of DPO-1 Completed 9

23 Prior Action Status Prior action #2.7: The Government has launched a program to adopt a Tanzania Natural Resource Charter and has established an expert panel to oversee the program. Prior action #2.8: The Government has established a top-level institutional mechanism to enhance interministerial coordination by mandating the Cabinet committee on economic affairs to handle the natural gas agenda and creating an interministerial senior task force on natural gas. ahead of DPO-2 Prior action #2.9: TPDC has published on its website its latest audited financial statement, latest procurement audit report, and key performance indicators. Note: EWURA = Energy and Water Utilities Regulatory Authority; NAO = National Audit Office; PPP = Public- Private Partnership; PPRA = Public Procurement Regulatory Authority. 27. Minor adjustments were made to the DPO series Policy and Results Matrix during preparation and appraisal of DPO-2. The Government had made progress on all results indicators approved with DPO-1 (listed in Table 2), and showed continued resolve to address the crisis in the power sector. Reflecting the continuity of the implementation of the Program, the Policy and Results Matrix approved with DPO-2 included only relatively small changes to the prior actions of DPO-2 compared to the triggers approved with DPO-1, as summarized in Table 5 below. Changes to the results indicators were summarized in Table 2 above. # Table 5. Prior Actions for DPO-2 Compared to Triggers for DPO-2 as Approved under DPO-1 Trigger for DPO-2, as Approved under DPO-1 Prior Action for DPO-2 Comment Pillar 1: Strengthening the country s ability to bridge the financial gap in its power sector 2.1 TANESCO to increase revenues through a combination of better bills collection, reduction in losses, and, if necessary, requesting EWURA to adjust tariffs. 2.2 To improve fiscal transparency, the Government has provisioned in the FY2014 budget contingency funds that can be used to address the financing gap in TANESCO. 2.3 In FY2014, Government shall use a combination of tariff increases, commercial borrowing, and government subsidies to cover the financing gap in TANESCO. Government subsidies shall not exceed 2.5 percent of total expenditures (excluding consolidated funds services, wages, and development foreign). TANESCO has implemented new tariffs, approved by EWURA in December 2013 in order to increase its revenue. The Government had created in its approved FY2013/14 budget a specific code with funds for transfers to TANESCO to improve fiscal transparency. The Government has taken actions to reduce the level of transfers to TANESCO from the level of FY2012/13 and has committed that the level will not exceed 2.5 percent of controlled total expenditure in FY2013/14. Trigger modified to capture the stronger action taken by the Government (approved tariff increase) and edited for clarity. Substance strengthened (specific budget line instead of contingency fund) and trigger language edited for clarity. Substance maintained, but trigger language edited for clarity. Pillar 2: Reducing the cost of power supply and promoting private sector participation in the power sector 10

24 # Trigger for DPO-2, as Approved under DPO The Government, and TANESCO as appropriate, have adopted concrete measures (including training, hiring transaction advisers if necessary, and completing necessary studies) to improve its technical and commercial capacity to develop PPP projects in the energy sector through transparent and competitive process, as well as to evaluate unsolicited proposals (where they have merits), including subjecting them to a competitive process. 2.5 The Government has completed an Energy Sector Review whose objective is to recommend structural reforms aimed at improving power sector performance (including efficiency and accountability), to comply with the Electricity Act (2008, including part viii), and has approved its recommendations. Prior Action for DPO-2 The Government and TANESCO have implemented the initial phase of the 2013 Policy for Private Sector Participation in Power Generation through Competitive Processes by launching PPP capacitybuilding programs for (a) screening and conducting due diligence; (b) financial structuring; (c) structuring processes for selecting developers and implementing transactions; (d) preparing legal and regulatory documents; and (e) managing government and public corporation fiscal risks. The Government has adopted the recommendations of the Presidential Big Results Now (BRN) Initiative to develop a road map for structural reforms of the energy sector and has established a Ministry Delivery Unit within MEM to oversee the implementation of the recommendations. Comment Substance maintained, but trigger language edited for clarity. Substance maintained and strengthened (establishment of delivery unit) and trigger language edited for clarity. Pillar 3: Strengthening the policy and institutional framework for the management of the country s natural gas resources 2.6 The Government approves the Natural Gas Policy. 2.7 Gas Act to be submitted to Parliament after participative public consultations, including (a) transparent and participative regulatory practices and (b) access to information and participative monitoring by stakeholders. The Government has adopted the Natural Gas Policy. The Government has launched a program to adopt a Tanzania Natural Resource Charter and has established an expert panel to oversee the program. Trigger language edited for clarity. Trigger was replaced. The Gas Act was moved to DPO- 3 because by the time of DPO-2 it had not been submitted to the Parliament as an extended period was required to conduct public consultations. At the same time, the Government implemented an equally significant action in strengthening the policy and institutional framework for the management of the natural gas resources by 11

25 # Trigger for DPO-2, as Approved under DPO The Government establishes a top-level institutional mechanism to enhance intersectoral cooperation on the gas policy agenda. 2.9 TPDC publishes (on its website and in print) its internal periodic performance reports, latest audit annual report of the NAO and latest annual performance report of the PPRA. Prior Action for DPO-2 The Government has established a top-level institutional mechanism to enhance interministerial coordination by mandating the Cabinet committee on economic affairs to handle the natural gas agenda and creating an interministerial senior task force on natural gas. TPDC has published on its website its latest audited financial statement, latest procurement audit report, and key performance indicators. Comment launching the Natural Resource Charter initiative. This replacement was to accommodate those latest developments while maintaining the strength of the overall program under DPO-2. Trigger edited for clarity. Trigger edited for clarity. 28. Progress toward implementing triggers for DPO-3 was delayed during and fell short of the expectations in some areas, causing the series to lapse in early Completion of all triggers and Board approval of DPO-3 was originally envisioned by early However, only one trigger (#3.2) was met by then. Several others were met during 2015 and 2016, as summarized in Table 6, while four triggers were not met by the time of the ICR. Consequently, the series lapsed 24 months after Board approval of DPO-2, on March 24, Table 6. Status of Triggers of DPO-3 (as approved with DPO-2) at the time of the ICR Trigger for DPO-3 Trigger #3.1: The Government adopts a comprehensive national subsidy policy, which defines principles for providing subsidies in the energy sector. Trigger #3.2: The Government has committed to reduce the level of transfers to TANESCO in FY2014/15 to the level not more than 2 percent of controlled total public expenditure. Trigger #3.3: TANESCO continues to improve and report publicly on collection performance and on Status Not met. No national subsidy policy has been adopted. Meanwhile, the Government has eliminated subsidies for capacity charges, fuels, and other operating expenses but continues to fund TANESCO s capital expenses. Met, without delay. In FY2014/15 the Government provided transfers of US$33 million (net of taxes) to TANESCO, which is equivalent to around 1 percent of controlled total public expenditures. Net transfers in FY2015/16 and FY2016/17 were US$7 and US$3 million, respectively. Met, albeit with delay. Bill collection increased from 90% in FY2014/15 to 101% in FY2015/16 and 96% in FY2016/17. Technical and non-technical losses in the distribution grid fell from 12

26 Trigger for DPO-3 Status operational losses and develops a plan to meet the targets set by the EWURA order in December Trigger #3.4: The Government phases out Emergency Power Projects by 150 MW without lowering the reliability of power supply delivery. Trigger #3.5: TANESCO implements the 2013 policy to promote private sector participation in power generation by launching at least one competitive bidding process for new gas-based power project(s) to diversify power generation sources in the country toward lower cost structure of the power sector. Trigger #3.6: The Government approves the road map for structural reforms of the energy sector (including the power and gas subsectors), which includes specific structural measures aimed at improving its governance and overall efficiency and time-bound implementation schedule, and initiates its implementation. Trigger #3.7: The Government adopts a National Gas Utilization Master Plan (NGUMP). Trigger #3.8: The Government prepares a Gas Bill to the Parliament. Trigger #3.9: The Government prepares and adopts a Petroleum Policy. 2.2 Major Factors Affecting Implementation Design Factors Affecting Program Implementation and Outcomes 19% in 2012 to 12.3% in FY2015/16 and 10.4% in FY2016/17, meeting the 2013 EWURA order target of 15.1%. Met, albeit with delay. EPP capacity in use declined from 317 MW in 2012 and 2013 to 162 in FY2015/16 and 0 in FY2016/17. This has been achieved without lowering the reliability of power supply delivery but the sector remains highly exposed to supply shortages in the case of technical failures or a major drought. Not met. The Government chose to implement Kinyerezi I (including extension) and Kinyerezi II as public projects. The Government s policy toward private sector participation in future generation projects is unclear. Partially met. The MEM adopted and published on its website the Electricity Supply Industry Reform Strategy and Roadmap in June 2014, which is consistent with recommendations of the energy lab of Big Results Now. However, it excludes the natural gas subsector and implementation of the road map has not proceeded as per the envisioned implementation schedule. The Government s policy toward implementation of the road map is unclear. Not met. The Government has prepared the draft NGUMP that has not been shared widely by energy sector stakeholders. Met, albeit with delay. The Oil and Gas Revenue Management Act 2015 and the Petroleum Act were passed by the Parliament in June 2015 following the adoption of the Natural Gas Revenue Management Policy adopted by the Cabinet in May Met, albeit with delay. The Petroleum Policy was adopted by the Cabinet in Following the adoption of the Petroleum Policy, the Petroleum Act 2015 was passed by the Parliament in June 2015, signed by the President in October 2015, and gazetted thereafter. The substance of the act still needs to be supplemented with the establishment of an effective sector institutional framework and the gradual introduction of an internationally benchmarked, prioritized body of regulations to implement the act. The act was amended in July 2017 following the parliamentary inquiry into mining contracts. 29. The Government was highly committed to resolve the electricity supply crisis and associated financial difficulties of TANESCO, leading to strong implementation performance up to Board approval of DPO-2. The objectives, prior actions, and results indicators were very closely 13

27 aligned with the Government s response to the electricity supply crisis. Major tariff hikes, which raised per-unit revenues of TANESCO by 35 percent in 2012 and 30 percent in , underscored the Government s commitment to implement difficult reforms. 30. The World Bank s DPO series was part of a concerted donor effort to support the Government s response to the fiscal and macroeconomic implications of the electricity supply crisis, reducing the risk of reform slippage, especially during The Government s reform response was developed in close consultation with stakeholders including the energy sector donor consultation group. A Standby Credit Facility (SCF) arrangement of the IMF ( ; SDR 149 million) included structural benchmarks on TANESCO s financial recovery complementary to the DPO series and closely monitored fiscal transfers and domestic borrowing for the electricity sector. While overall program performance was mixed, the third and final SCF review noted that [s]ignificant progress was achieved in addressing financial difficulties of the energy sector (p. 9). The Government s power sector reform program also received support from the African Development Bank (AfDB) in the form of a three-phase budget support operation ( ; SDR 100 million in total). 31. The crisis-response elements of the Policy and Results Matrix was informed by recent analytical work and global experience and had a clear line of sight between prior actions and results indicators. The short-term reform elements supported by the DPO series, which included tariff reforms, fiscal transfers, and performance agreements between the MEM and TANESCO, were informed by extensive, up-to-date analysis, and lessons learned from the World Bank s reform and crisis-response experience in the power sector. Relevant analytical work included (a) the Power System Master Plan (PSMP 2012), (b) a short-term financial assessment ( ) of TANESCO, (c) the Big Results Now Energy Lab Report (2013), and (d) the Government of Tanzania-Energy Development Partner Group Joint Energy Sector Review (2013). Prior actions and objectives were clearly aligned and there was a clear line of sight between prior actions and results indicators. 32. In contrast, the medium- to long-term reform elements of the Policy and Results Matrix carried high implementation risks because they were backloaded, heavy on commitments and light on implementation, and missed a clear line of sight between prior actions and results indicators. Prior actions and triggers under Pillars 2 and 3 called for fundamental reforms to the power and gas sectors but envisioned that the analytical foundations and buy-in of stakeholders would be established, to a large extent, during implementation. The program also envisioned that Government commitments in the form of policies, plans, and road maps would be followed by reform implementation measures above and beyond the measures laid out in the DPO Policy and Results Matrix. As outlined in more detail in section 3, Program progress stalled on several fronts after the immediate pressure of the crisis eased in The World Bank took an informed risk by engaging with the Government on natural gas reforms (supported by Pillar 3) without significant prior sector dialogue, because of the strategic importance of a strong upstream natural gas policy framework for the development of Tanzania s energy sector. Unlike in the power sector pillars, Pillar 3 of the DPO series could not build on solid analytical foundations and an established sector dialogue. Only after initiation of the preparation of the DPO series did the World Bank engage in deeper sector dialogue through a natural gas scoping mission, 10 EWURA s tariff orders refer to increases of percent and percent in 2012 and 2014, respectively. Relative changes in per-unit revenues differ from relative changes in tariffs because of changes in the composition of consumption and parallel changes in fixed charges for consumers. Data on per-unit revenues was taken from TANESCO s financial statements. 14

28 co-led by the World Bank and including six other DPs, which developed the policy and institutional actions to be undertaken by the authorities. However, the World Bank s senior management assessed the risk of not engaging on such an important sector as higher than the Program s risks. 34. The technical risk assessment was adequate but important governance risks were missed; the political economy of power sector reform in particular was poorly reflected in the design of the medium- to long-term reform measures in the Program. The most important technical risks that materialized had been correctly identified, including hydrology, global energy prices, and exchange rate volatility, and the appraisal documents rightly noted that these risks could not be fully mitigated within the Program. However, risks relating to the governance of the Program and the political economy of power sector reform could have been better reflected in the length, scope and ambition of the DPO series. Specifically, these risks included (a) the Government s reform commitment beyond the immediate crisis, (b) insufficient stakeholder consensus on structural sector reforms (the exact nature of which was to be determined under the Program), and (c) the risks associated with designing a reform program that spans election cycles. External Factors Affecting Program Implementation and Outcomes 35. During implementation, progress toward the envisioned outcomes was affected by a number of external factors, including major macroeconomic and governance risks that materialized. The main external factors of the Program that affected implementation are summarized in Table 7, grouped by (a) sector developments outside of the Program, (b) governance factors, and (c) macroeconomic factors. Table 7. Major External Factors of the Program Affecting Implementation Factors Sector developments outside of the Program Access agenda becoming priority: To promote access, in early 2013, the Government reduced connection fees by 30% to 90%, and instructed TANESCO to increase its customers base to 1,500,000 by 2015 and target 250,000 new connections per year. Electricity demand growth slowdown: Slower than expected, demand growth in FY averaged 7.6%, below the 10% growth per year estimated during appraisal of DPO-1. Hydrology improvements. Hydrology improved after drought in FY and was above average in FY2015 and FY2017. FY2016 hydrology was at similar level as FY Global energy price decline. Global oil and liquefied natural gas (LNG) prices declined after mid-2014, subsequently remained subdued through the end of Impact on Program Implementation Investments in new connections and related distribution grid strengthening were financed mainly from TANESCO s internal cash funds, limiting the company s ability to pay off arrears (thus affecting Results Indicator 2) Improved balance between demand and supply and lessened pressure to commission new gas power plants (Results Indicator 4) Decrease in TANESCO s generation cost during FY2015 and FY2017 (Results Indicator 5) Improved balance between demand and supply and lessened pressure to commission new gas power plants (Results Indicator 4) Slowdown in investor interest in natural gas exploration and production, especially offshore (Results Indicator 8) Impact on TANESCO s generation cost was favorable but more than cancelled out by exchange rate depreciation from FY2015 onwards (Results Indicators 1 and 5) 15

29 Factors Gas pipeline delay. Completion of the National Natural Gas Infrastructure Project (NNGIP), a core element of the Government strategy to increase natural gas-fired power generation, was delayed by one year (completed October 2015) Governance factors Legal controversies. The inquiry into the sale of the Independent Power Tanzania Ltd (IPTL) plant in 2014, controversies surrounding the structure of payments to IPPs and EPPs, and the mining sector inquiry in 2017 both led to removal or suspension of prolonged periods of time of MEM officials including key leadership positions election. Parliamentary and presidential elections held in October 2015 led to change in the Government. Macroeconomic factors Growth and inflation: GDP growth remained favorable at around 7 percent throughout the implementation period. Inflation declined after FY2012 and remained around 5 6 percent in FY2013 FY2016/17. Exchange rate depreciation: Major exchange rate depreciation during FY2015 (8 percent) and FY2016 (24 percent). Relatively stable before and after. Fiscal consolidation: The Central Government s overall fiscal consolidation, as a result of lower-thanexpected domestic revenue collection, diminishing aid disbursements, and higher investment in infrastructure projects, posed a challenge for the energy sector in receiving sufficient public funds to scale up necessary investments. Arrears to contractors, suppliers and pension funds by the Government reached over 6 percent of GDP at the end of FY2015/16. Impact on Program Implementation Delay in the availability of gas for new power plants (especially Kinyerezi I) and fuel switching of existing power plants (Results Indicator 4) Delay in implementation of sector reform program under Pillar 2 (especially Results Indicators 6 and 7) as well as difficulties in maintaining the strategic policy dialogue for DPO-3 in the absence of the MEM leadership team Reorientation of priorities for sector reform program under Pillar 2 (especially Results Indicators 6 and 7) Improvements in households available income, cushioning the impact of tariff increases (indirectly affecting Results Indicator 1) Increase in value of TANESCO s arrears to suppliers (which are mostly denominated in U.S. dollars) by around 30 percent (Results Indicator 2) Impact on TANESCO s generation cost was unfavorable and only partially cancelled out by decline in global energy prices from FY2015 onwards (Results Indicators 1 and 5) The Central Government s fiscal consolidation slowed down investment financing from the Ministry of Finance and Planning (MOF) for TANESCO s capital investment program Phaseout of direct budget transfers to TANESCO even though TANESCO s net income remained negative. 2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization 36. M&E design: Results Framework. The Program s results indicators and target values, identified at appraisal of DPO-1 and revised at DPO-2, were adequately linked to the PDO. The Results Framework included more outcome indicators (for example, Results Indicators 1 5 and 8 9) than output indicators (Results Indicators 6, 7, and 10). The focus on outcomes was adequate for the crisis-response elements of the Program (for example, tariff reforms and 16

30 phase-out of EPPs) but less appropriate for the medium- to long-term elements of the Program. In the case of the latter, the emphasis on outcomes blurred the line of sight between prior actions and results indicators (for example, the link between the natural gas policy framework and the volumes of proven gas reserves and gas produced). Output indicators would have been more adequate for these prior actions. Results indicators were appropriately defined, 11 measurable, and did not require data collection efforts beyond the financial and performance reporting of the MEM and TANESCO, ensuring that (a) monitoring of the indicators relied on and further built capacity of country systems (b) it could continue beyond the Program period, and (c) this ICR had access to reliable information on all results indicators. Roles and responsibilities. The MOF was notionally responsible for overseeing the M&E of the Program, but was to draw on the assistance of the MEM, TANESCO, and the energy sector regulator, EWURA. This setup was adequate in view of the selected results indicators. Key Program results indicators were also included in (a) the budget support framework used by the Government and DPs over the past decade in Tanzania, (b) the IMF program, and (c) the World Bank-led annual Public Expenditure Review process. This close integration of M&E efforts across the World Bank s and other DPs engagement benefited M&E implementation. 37. M&E implementation: Results monitoring. The Government and the World Bank continuously monitored progress against the main financial and performance indicators of the power sector, which included the results indicators of the DPO series, although information on reform progress is not always reflected on time. Financial monitoring of TANESCO in particular still needs to become more timely. On the World Bank side, two Implementation Status and Results Reports (ISRs) were filed, in April 2014 and August 2015, but they did not give a thorough account of the reasons for delays and postponement of the DPO-3, in part reflecting the fact that the M&E framework s choice of outcome indicators over output indicators was inadequate for monitoring the progress of medium- to long-term reforms (see above). However, overall, monitoring of the Results Framework was implemented adequately and at the time of ICR, data on all indicators were readily available. Change in financial year affecting M&E implementation. The M&E framework was set up to measure progress in TANESCO s financial years, which were equal to calendar years at the time of appraisal. However, TANESCO soon switched to a new financial year from July 1 to June 30 to align with the Government s fiscal year, starting in FY2015/16. The transition year FY2014/15 was an 18-month period. This ICR adopts TANESCO s financial years for the measurement of the results indicators. 38. M&E utilization. The M&E framework was used in the implementation of the Program and decisions on the World Bank s DPO series in an adequate manner. On the Government side, financial indicators informed Government decisions, including tariff reforms. On the World Bank side, a midterm review in June 2015 came to the conclusion that at that time only three out of the nine triggers were 11 The results indicators included two minor errors the unit of Results Indicator 5 should have been listed as US /kwh and Results Indicator 6 should have referred to tenders, rather than bids but these were inconsequential for the quality of the M&E framework. 17

31 met (#3.2, #3.8 and #3.9), leading to the decision of not proceeding with DPO-3 until after the general elections in October Expected Next Phase/Follow-up Operation 39. For IDA18 (FY ), the Government and the World Bank are in dialogue on a followup operation to continue support in specific policy areas of the Program, in particular TANESCO s financial recovery, complemented by lending in other areas of the Government s energy sector development program. As of November 2017, a particular emphasis of the operation will be on resolving the problem of the legacy payment arrears. Other ongoing and pipeline operations of IDA in the sector include financing for access, transmission (including interconnections with neighboring countries), and capacity building. 3. Assessment of Outcomes 3.1 Relevance of Objectives, Design and Implementation Overall Rating: Substantial (a) Relevance of Objectives: Substantial 40. The objectives of the crisis-response elements of the Policy and Results Matrix to restore TANESCO s financial viability and reduce fiscal risks were core to the Government s and the World Bank s strategy in the energy sector. From initial approval through to closing of the series, the objectives of improving the financial situation of the power sector and phasing out EPPs to reduce the cost of energy supply (that is, Pillar 1 and parts of Pillar 2) were closely aligned with (a) Tanzania s National Strategy for Growth and Poverty Reduction 2025 (Mkakati wa Kukuza Uchumi na Kupunguza Umaskini Tanzania [MKUKUTA] II), (b) Tanzania s five-year development plans (FYDP I 2011/ /16 and FYDP II 2015/ /21), (c) the World Bank s Country Assistance Strategy (CAS) for FY2012 FY2015, 12 and (d) the World Bank s energy sector strategy Initially, the objectives of the medium- to long-term reform elements of the Policy and Results Matrix reflected shared priorities between the Government and the World Bank, but their relevance to the Government was less clear at the time of the ICR. At the time of appraisal, there was strong Government commitment to the objectives of promoting private sector participation in power generation (Pillar 2) and strengthening the policy and institutional framework for natural gas utilization (Pillar 3). These objectives were translated into concrete policy commitments and action plans with the Electricity Supply Industry Reform Strategy and Roadmap of 2014 and the National Energy Policy of However, reform implementation toward these two objectives slowed down after 2014 in part due to the IPTL inquiry, skepticism within the Government about the structure of payments to IPPs and EPPs 14, and preparations for the election of 2015 and has not picked up since then. FYDP II, prepared by the new Government, strongly emphasizes energy infrastructure development and includes certain elements of the Electricity Supply Industry Reform Strategy and Roadmap , but puts 12 The objectives are also aligned with the draft CPF for FY2017 FY2022, which is currently under preparation. 13 As captured in the World Bank Toward a Sustainable Energy Future for All: Directions for the World Bank Group s Energy Sector. Washington, DC. 14 Specifically, there is skepticism within the Government about the adequacy of capacity payments to IPPs and EPPs (fixed annual payments to cover capital costs). 18

32 less emphasis on the objectives of private sector participation and strengthening the policy and institutional framework for natural gas. At the time of the ICR, new controversies surrounding the IPTL power plant and contracts in the mining industry have introduced additional uncertainty about the ways in which the Government handles contracts with private investors on large investments, including in the power and natural gas sectors, thus potentially affecting the relevance of the DPO series objectives relating to the private sector. 42. The DPO series objectives were aligned with Tanzania s Nationally Determined Contribution (NDC) to the Paris Agreement. Tanzania s NDC, submitted in 2015, builds on the reform directions of the Program, including in the following two priority mitigation measures specified in the NDC: (a) investing in energy diversification to ensure overall energy security for economic development through enhanced availability, affordability, and reliability while contributing toward energy emissions intensity reduction over time and (b) expanding the use of natural gas for power production, cooking, transport, and thermal services through improvement of natural gas supply systems throughout the country. 43. Acceleration of TANESCO s electrification program became a core objective for the Government in the power sector from 2013 onwards and would have to be part of any comprehensive energy sector reform program initiated at the time of the ICR, but was not reflected in the objectives and design of the evaluated DPO series. To promote electricity access, in early 2013, the Government reduced connection fees by 30 percent to 90 percent, and instructed TANESCO to increase its customers base to 1,500,000 by 2015 and target 250,000 new connections per year. While the Rural Energy Agency (REA) was to finance rural and peri-urban connections; a substantial share of new connections was to be financed from TANESCO s own funds. This put pressure on TANESCO s cash flow and limited the company s ability to pay back arrears. However, this scale-up in access investment was not sufficiently considered in the design of the DPO, especially its measures and targets relating to arrears. (b) Relevance of Design: Substantial 44. The choice of a programmatic DPO series and the selection of prior actions were adequate for the crisis-response elements of the Program. The electricity supply crisis required the Government to take difficult decisions in a short time and follow up and avoid reversal over a period of several years. The programmatic DPO was the right instrument to support such reforms. 45. Through careful design of the prior actions, the DPO series enabled the Government to internalize difficult policy trade-offs. Enough flexibility was built into the design of the Policy and Results Matrix to allow the Government s deliberation on important but difficult policy decisions to follow due course. This was achieved by agreeing with the Government on the objective and desired outcomes of the prior actions and triggers, while leaving the resolution of policy trade-offs to the Government. For instance, the Triggers for DPO-2 under Pillar 1 specified the fiscal reform objective (a cap on transfers to TANESCO), which but left the exact nature of policy actions. During preparation of DPO-2 the language of Prior Action 2.1 was then adjusted to account for the outcomes of the Government s deliberation. 46. However, the DPO series approach to bringing arrears under control would be inadequate at the time of the ICR. The design of the DPO series was based on a careful analysis of TANESCO s profitability (net income) under different scenarios. Beyond immediate measures (for example, clearance of Government arrears to TANESCO), less attention was paid in the analysis and the design of the Policy and Results Matrix to TANESCO s cash flow and potential impacts on arrears from reduced Government transfers, the changes in Government subsidies for connections and connection targets (see above), or 19

33 policy slippage in the shift toward private sector-owned generation. While there was consistent logic behind the Program s strategy to reduce arrears, the DPO series would have benefited from separate analysis and risk mitigation measures in this regard. More careful analysis of TANESCO s cash flow under different scenarios would be needed to inform renewed support by DPs to resolve TANESCO s arrears. 47. The medium- to long-term reform elements of the Program would have benefited from less backloading and a clearer line of sight between prior actions and results indicators. As outlined in more detail in section 3, Program progress stalled on several fronts after the immediate pressure of the crisis eased in This hindered achievement of the Program s results indicators even where outputs of the prior actions were achieved. 48. The design of the DPO series could have been more resilient to changes in the Government priorities if the PDO of the series had solely focused on ends (for example, security of supply or financial sustainability), rather than means (for example, private sector participation). Reference in the PDO to private sector participation in particular limited the World Bank s ability to adjust to changes in the Government s priorities after the completion of the second DPO. (c) Relevance of Implementation: High 49. Implementation arrangements were highly relevant in that they emphasized ongoing dialogue and the mobilization of technical support, which were critical in view of the complexity of attempted power sector and natural gas upstream reforms. The ongoing technical assistance engagement, including several activities for which the World Bank team raised trust fund resources, helped maintain the technical dialogue despite a transition in Government and several changes in sector leadership during the implementation of the DPO series. 50. The decision not to proceed with the third operation in the series within the two years after Board approval of DPO-2 was adequate. The decision reflected an adequate adjustment to changing context and Government priorities. 51. Close alignment of the DPO series with DPs programs was critical for the success achieved during implementation and parallel technical assistance by the World Bank provided much-needed capacity-building support to implement the Program. The close alignment with the parallel IMF program ( ) and the World Bank s ESCBP were essential for achieving the results of the Program. 3.2 Achievement of Program Development Objectives Rating: Modest 52. Achievement of the PDO is assessed as Moderately Unsatisfactory on the basis of the progress on key indicators. The PDO of the program was to (a) strengthen the country s ability to bridge the financial gap in its power sector, (b) reduce the cost of power supply and promote private sector participation in the power sector, and (c) strengthen the policy and institutional framework for the management of the country s natural gas resources. As laid out below in detail and summarized in Table 8, the DPO series performed well on Results Indicators 1, 3, and 5, which relate to TANESCO s operating deficit, technical losses, and cost of supply. The DPO series also achieved Results Indicator 7 (documents published on sector reforms). However, the series only made partial progress toward Indicators 4, 8, and 9, and did not make any progress (or even reversed progress) on Results indicators 2, 6, and

34 21

35 Table 8. Performance of Program against DPO Target Indicators # Indicator 1 TANESCO operating deficit/(profit) (US$ million) 2 TANESCO accounts (trade and other) payable (T Sh billion) 3 TANESCO technical and non-technical losses in transmission and distribution 4 Amount (in MW) of gasfired power generation capacity commissioned 5 Average unit cost of power sales (US$/MWh) 6 Number of bids for gas IPP power plants launched on a competitive basis 7 MEM documents on sector reforms published for public knowledge 2012 (Baseline) Target set in 2013 Target set in 2014 Actual FY2015/16 Actual FY2016/ (82) a ,187 1,331 a > a Volume of gas produced (mmscfd) 9 Amount of onshore proven natural gas reserves (Tcf) 78 > b 132 c d 1.2 e 10 Annual monitoring under the Natural Resource Charter initiative No Yes No No Note: In 2014, TANESCO s financial year was changed from January December (until FY2013) to June June. (starting FY2016). The transition fiscal year had 18 months (January 2014 to June 2015). a Based on unaudited draft financial statements of TANESCO. b year to December 31, 2015; d year to December 31, 2016; d as of April 2015; e as of December 31, An ex post analysis of the results chain of the Program is presented in Table 9. The table presents, for each pillar, a summary of the implemented prior actions and their immediate outputs; other factors affecting the results indicators; and the Program s performance toward the results indicators. The results chain for each pillar is discussed below in details. 22

36 Prior Actions and Outputs (DPO-1 and DPO-2) Table 9: Efficacy and Causal Chain of the Series Reform Program Other Factors Affecting Results Indicators Performance toward Results Indicators Objective 1: Strengthening the country s ability to bridge the financial gap in its power sector (Efficacy Rating: Modest) Two tariff increases in January 2012 and January 2014 Improvements in bill collection from conventional meters and increased use of prepaid meters Reduction of Government arrears to TANESCO Improved transparency and reduction of Government transfers to TANESCO During the Program period, the Government pursued fiscal consolidation amid lower-thanexpected domestic revenues and slow aid disbursements, reducing the fiscal resources available to support TANESCO s investment program Major exchange rate depreciation during FY2015 (8 percent) and FY2016 (24 percent) increased the value of TANESCO s arrears to suppliers (which are mostly denominated in U.S. dollars) and its fuel cost Hydrology improved after the drought in FY2011 FY2013 and was above average in FY2015 and FY2017 (FY2016 hydrology was poor again), leading to decrease in TANESCO s generation cost Access agenda became priority after 2013 for the Government, which reduced connection fees and instructed TANESCO to increase its customers base to 1,500,000 by 2015 and target 250,000 new connections per year, to be financed mainly from TANESCO s internal cash funds, limiting the company s ability to pay off arrears TANESCO turned around its operating results, improving its operating margin from 21% in FY2012 and 41% in FY2013 to 13% in FY2015, 14% in FY2016, and 12% in FY2017 Arrears continued to increase: trade and other payables surged from a total of T Sh 472 billion (US$298 million at that time) at the end of FY2011 to T Sh 980 billion (US$565 million) in FY2015, T Sh 1,187 billion (US$538 million) in FY2016, and T Sh 1,331 billion (US$605 million) at the end of FY2017 Objective 2: Reducing the cost of power supply and promoting private sector participation in the power sector (Efficacy Rating: Modest) New strategic power sector policy Road map for structural reforms Capacity-building program Performance contract between TANESCO and the MEM Regular publication of performance reports (including bill collection and technical/nontechnical losses), financial audits, and procurement audits Parliamentary and presidential elections held in October 2015 led to change in Government, reorientation of priorities and delay in implementation of sector reform program under Pillar 2 The inquiry into the sale of IPTL private power plant in 2014 and the mining sector inquiry in 2017 both led to removal or suspension of prolonged periods of time of MEM officials including key leadership positions, causing delays in implementation of sector reform program under Pillars 2 and 3 Completion of the NNGIP pipeline, a Technical and non-technical losses in transmission and distribution fell from 22.4%in FY2011 and 24.7% in FY2013 to 16.4% in FY2017 Installed gas-fired generation capacity increased by 150 MW in 2016 and another 425 MW are under construction, out of which 30MW are expected to be commissioned by the end of 2017 Average cost of supply has 23

37 Prior Actions and Outputs (DPO-1 and DPO-2) Other Factors Affecting Results Indicators core element of the Government strategy to increase natural gas-fired power generation, was delayed by about one year, which delayed the availability of gas for new power plants (especially Kinyerezi I) and fuel switching of existing power plants Good hydrology in FY2015 and FY2017 as well as slower-thanexpected demand growth (7.6% compared to estimated 10% per year]) improved balance between demand and supply and lessened pressure to commission new gas power plants Performance toward Results Indicators fallen back at pre-crisis level (US 9.2 per kwh in FY2017 compared to US 8.4 per kwh in FY2010 and US 18.4 per kwh in FY2013) No new tenders for private sector-owned generation capacity were issued Objective 3: Strengthening the policy and institutional framework for the management of the country s natural gas resources (Efficacy Rating: Modest) Adoption of Natural Gas Policy Launch of a program to adopt a Tanzania Natural Resource Charter Inclusion of natural gas in the mandate of the Cabinet committee on economic affairs and creation of an interministerial senior task force Clearing of arrears with gas developers Verification of the amount of natural gas reserves Publication of TPDC s audited financial statements, its latest procurement audit reports, and its key performance indicators New natural gas legislation New Petroleum Policy and legislation Global oil and LNG prices declined after mid-2014, subsequently remained subdued through the end of 2017, leading to a slowdown in investor interest in natural gas exploration and production, especially offshore The inquiry into the sale of IPTL private power plant in 2014 and the mining sector inquiry in 2017 both led to removal or suspension of prolonged periods of time of MEM officials including key leadership positions, causing delays in implementation of sector reform program under Pillars 2 and 3 Source: Data from TANESCO, TPDC, and MEM; analysis by World Bank staff. Volume of gas produced increased from 78 mmscfd in 2012 to 102 mmscfd in 2015 and 132 mmscfd in 2016 Amount of onshore proven natural gas reserves increased from 1.0 Tcf in 2012 to 1.4 Tcf in 2015 and 1.2 Tcf in 2016 Annual monitoring under the Natural Resource Charter initiative was not implemented Objective 1: Strengthen the country s ability to bridge the financial gap in its power sector Rating: Modest 54. TANESCO s profitability recovered from the crisis, buoyed by tariff increases, improved hydrology, and the phase-out of EPPs. As a result of the measures taken under the DPO 24

38 series, average tariff per unit sold increased from T Sh 136 per kwh in FY2011 to T Sh 249 per kwh in FY2016 and T Sh 238 per kwh in FY2017. GDP growth remained favorable during the same period, at around 7 percent and inflation declined after to around 5 6 percent in FY2013 FY2016/17, cushioning the impact of tariff increases and avoiding erosion of tariffs in real terms. In parallel, changes in the fuel mix (discussed under Pillar 2 below) and the phase-out of 317 MW of expensive EPPs reduced the cost of power generation. 55. Results Indicator 1 was achieved and TANESCO reached operating cost recovery despite the phase-out of operating subsidies from the Government and a major depreciation in FY2015/16. As a result, TANESCO s profitability improved significantly, as shown in Figure 1, turning its operating deficit of US$239 million in FY2013 into an operating surplus of US$149 million in FY2014/15 and US$80 million in FY2016/17 (FY2015/16 showed an operating deficit of US$92 million because of poor hydrology conditions). This was achieved amid a period of fiscal consolidation and reduction of budget transfers to TANESCO as well as major exchange rate depreciation during FY2015 (8 percent) and FY2016 (24 percent), which translated into higher fuel cost. Figure 1. Gross Profit Margin (before Government subsidies and other cost and revenues) and Operating Profit Margin a of TANESCO during FY2008 FY2016/ % 10.00% 0.00% % % % % % % TANESCO profitability Gross profit margin % Operating profit margin (EBIT) % /15* 2015/ /17** Note: a The operating profit margin is defined here as income before financing cost and taxes; * 18- month period; ** based on TANESCO s unaudited draft financial statements. Source: TANESCO. 56. Government subsidies to cover TANESCO s operating expenses were phased out as profitability improved. TANESCO had since the mid-2000s benefited from Government subsidies to cover its operating expenses. These subsidies escalated during the crisis of , reaching US$139 million in FY2013. As a result of the measures taken under the DPO series, Government transfers (net of taxes) to cover operating costs of TANESCO became more transparent and decreased from US$117 million in FY2012 and US$139 million in FY2013 to US$3 million in FY2016 and 0 in FY2017. The Government continues to contribute to financing investment projects in the sector (capital expenses), consistent with the subsidy policies adopted in the National Energy Policy

39 No. of annual connections TANESCO's self-financed investments (financed from cash flow and borrowing) in T Sh million TzSh billion Days of cost of sales Figure 2. Development of TANESCO s Trade and Other Payables 1,400,000 1,200,000 1,000, , , , ,000 - TANESCO trade & other payables (FY2015 adjusted for longer period) Trade and other payables TSh million Creditor days Source: World Bank staff estimates based on TANESCO data; 2017 data based on unaudited draft financial statements. 57. Cash collected per year by TANESCO more than doubled between FY2011 and FY2015/16 as a result of measures taken under the DPO series. Between FY2011 and FY2015/16, revenues per kwh increased by 82 percent. Average bill collection increased from 82 percent in FY2012 to 101 percent in FY2016 and 96 percent in FY2017. Figure 3: Impact of acceleration of electrification program on TANESCO s cash needs for investment 600, , , , , ,000 - TANESCO's self-financed investments compared to growth in new connections /15* 2015/16 * 18-month period 350, , , , , ,000 50,000 - Source: World Bank staff estimates based on TANESCO data. 58. Arrears continued to climb, however, as measures taken under the DPO series were insufficient to counterbalance other factors that put pressure on TANESCO s arrears balance. These factors included in particular the acceleration of the electrification program, insufficient Government transfers for investment, and the exchange rate depreciation: The sharp depreciation of the local currency between 2015 and 2016 raised the nominal value of TANESCO arrears to suppliers by almost 30 percent in local currency. 26

40 Government support for TANESCO s investment program fell short of cash needs as the Government underwent a period of expenditure consolidation in 2014/15 and 2015/16 to maintain its fiscal deficit target. Except for two small commercial loans in the total amount of around T Sh 60 billion, TANESCO s access to commercial borrowing to repay arrears was restricted by the Government after FY2014/15. After the 2015 election, the new Government put a strong emphasis on a rigorous verification process before clearing outstanding payments/arrears to the private sector, which slowed down payment of outstanding arrears across the public sector. At the same time, TANESCO s cash used for investment increased sharply after the Government in January 2013 reduced the cost of new connections by 29 percent to 75 percent and instructed TANESCO to increase its customers base to 1,500,000 by 2015 and target 250,000 new connections per year (see Figure 3). 59. Results indicator 2 (trade and other payables) was therefore missed by a wide margin, despite the significant increase in cash collected. As shown in Figure 2, trade and other payables surged from a total of T Sh 472 billion (US$298 million) at the end of FY2011 to T Sh 980 billion (US$565 million) in FY2015, T Sh 1,187 billion (US$538 million) in FY2016, and T Sh 1,331 billion (US$605 million) at the end of FY2017. If measured in creditor days, trade and other payables fell in FY2012 and FY2013 but increased thereafter. That is, while operational performance of TANESCO significantly improved, the burden of the historical payment arrears has gotten worse. Most of these payables are due to the electricity and fuel suppliers and some are interest carrying. Resolving them is of critical importance for TANESCO s financial sustainability, supply security, and investment environment. Objective 2: Reduce the cost of power supply and promote private sector participation in the power sector Rating: Modest 60. Measures to improve transparency and accountability on TANESCO's operational performance contributed to reducing system losses and improving bill collection. Technical and nontechnical losses in transmission and distribution fell from 22.4 percent in FY2011 and 24.7 percent in FY2013 to 16.4 percent in FY2017 (compared to a target of 18 percent under Results Indicator 3, see Figure 4). Average bill collection increased from 82 percent in FY2012 to 101 percent 15 in FY2016 and 96 percent in FY2017. Prior actions under the DPO series contributed to this improvement, including the performance contract between TANESCO and the MEM and the publication of performance reports, financial audits, and procurement audits, which enhanced transparency and accountability at TANESCO. 15 The collection rate exceeded 100 percent because the Government made two large, one-off payments to TANESCO to pay off outstanding arrears, and as a result the total cash collected during the year exceeded the total amount billed. 27

41 GWh Figure 4. Decline in Technical and Non-Technical Losses during FY2009 FY2016/17 30% Total transmission & distribution losses (%) 25% 20% 15% 10% 5% 0% /15* 2015/ /17** Note: * 18-month period; ** based on TANESCO s management accounts. Source: TANESCO. 61. Newly commissioned gas-fired generation capacity improved supply security and helped phase out oil-fired generation and EPPs. The target of Results Indicator 4, the commissioning of 400 MW of new gas-fired generation capacity, was not met but significant progress has been made as of the time of the ICR. The Kinyerezi I gas power plant (150 MW) was fully commissioned in 2016 and the first unit of Kinyerezi II is expected to be commissioned by the end of As a result, the share of liquid fuels (diesel and heavy fuel oil) in the generation mix fell from 18 percent in FY2013 to 4 percent in FY2017 (see Figure 5), leading to lower costs and lower per unit emissions. Together with improved hydrology and lower-than-expected demand growth (see below) allowed TANESCO to phase-out 317 MW of oil-fired EPPs. Figure 5. Tanzania s Power Generation Mix 8,000 7,000 Power generation by source ( ) Hydro Gas Diesel HFO Biomass Imports 6,000 5,000 4,000 3,000 1,402 1,572 1,982 2,356 2,568 2,802 3,172 2,723 3,664 4,178 2,000 1,000-2,502 2,635 2,626 2,687 Source: TANESCO. 1,977 2,040 1, Delays in the commissioning of gas-fired generation capacity (Results Indicator 4) can be explained by infrastructure bottlenecks as well as a lower-than-anticipated need for additional capacity. Completion of the NNGIP pipeline, a core element of the Government strategy to increase natural gas-fired power generation, was delayed by about one year, which delayed the availability of gas for new power plants (especially Kinyerezi I) and fuel switching of existing power plants. At the same time, good hydrology in FY2015 and FY2017 as well as slower-than-expected demand growth (7.6 2,587 1,273 1,321 2,025 2,428 Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Jun Jul-Jun Jul-Jun * 2015/ /17 28

42 US$/kWh percent compared to an estimated 10 percent per year) improved balance between demand and supply and lessened pressure to commission new gas power plants. Figure 6. Revenues and Cost of Supply of TANESCO FY2009 FY2016/ Revenues and cost of supply (per kwh) /15* 2015/ /17** Own generation US$/kWh Purchased electricity US$/kWh Depreciation US$/kWh Transmission US$/kWh Distribution expenses US$/kWh Revenues from electricity sales US$/kWh Note: * 18-month period; ** based on TANESCO s unaudited draft financial statements. Source: World Bank staff estimates based on TANESCO data. 63. The switch from oil to gas-fired generation and the phaseout of EPPs contributed to a sharp reduction in the cost of supply, leading to overachievement on Results Indicator 5. The average cost of supply (Results Indicator 5; see Figure 6) fell by half and returned to pre-crisis levels (US 9.2 per kwh in FY2017, which compares to US 8.4 per kwh in FY2010 and US 18.4 per kwh in FY2013). The main factors were better hydrology (about one-third of the reduction) and the replacement of oil-fired generation and EPPs with natural gas (two-thirds of the reduction). 64. Implementation of the reform policy and road map developed under the Program stalled soon after they were published, and the private sector participation agenda did not advance under the DPO series. Results Indicator 7 was met when the MEM published a road map for structural reforms and a new strategic power sector policy. 16 Both documents strongly emphasized the need to attract private sector investment into the sector. To facilitate implementation, the Government initiated a capacitybuilding program. However, the inquiry into the sale of the IPTL private power plant in 2014 led to removal or suspension for prolonged periods of MEM officials including key leadership positions, putting reform implementation on hold. The preparation for the parliamentary and presidential elections held in October 2015 further stalled implementation and under the new Government the reform agenda laid out in did not pick up significant momentum again, despite the issuance in October 2016 of The Electricity (Market Re-organization and Promotion of Competition) Regulations, , pursuant to the Electricity Act of The regulations stipulated that the power sector would be unbundled along the functional lines (generation, transmission, distribution), market liberalized, and procurement of generation projects competitively done. The regulations also established an Electricity Infrastructure Procurement Committee. The FYDP-II, too, calls for a more significant role for the private sector in generation and emphasizes the need for independence in decision-making in determining power purchasing tariffs, management of the power master plan, and power transmission. However, the October 2016 regulations are yet to be implemented, the Government however retains strong influence over decision-making in the sector, and its medium- to long-term vision for sector reforms remains to be articulated. Results 16 These documents are the (a) the Electricity Supply Industry Reform Strategy and Roadmap (2014) and (b) the National Energy Policy (2015). 29

43 Indicator 6, which aimed to capture the first competitive auction for private sector-owned generation capacity, was not met as the Government is yet to proceed with such a tender. Objective 3: Strengthen the policy and institutional framework for the management of the country s natural gas resources Rating: Modest 65. Under Pillar 3 of the Program, the Government established a policy framework for the upstream natural gas sector and laid the groundwork for subsequent legislative reforms. Under DPO-1 and DPO-2, the Government (a) approved a Natural Gas Policy and a Petroleum Policy in 2014; (b) cleared arrears with developers; (c) initiated an independent verification of Tanzania s natural gas reserves; (d) took measures to make TPDC more transparent and improve accountability, and (e) established a top-level institutional mechanism to enhance policy coordination by mandating the Cabinet committee on economic affairs to handle the natural gas agenda and creating an interministerial senior task force on natural gas. These measures in particular the two policies and the coordination mechanism laid the foundations for subsequent legislative reforms (see below). The Government also initiated a benchmarking exercise of the natural gas sector in close partnership with the Natural Resource Charter. 66. The Government maintained the reform momentum in the natural gas sector after approval of DPO-2 and implemented legislation that reformed sector governance. The Parliament passed the Petroleum Act of 2015, the Oil & Gas Revenue Management Act of 2015, and the Tanzania Extractive Industries Transparency Initiative Act of Taken together, these measures established a unified legal framework for investment in upstream natural gas in Tanzania, by (a) tasking two agencies to regulate the upstream and midstream,/downstream segments (the Petroleum Upstream Regulatory Agency and the Energy and Water Utilities Regulatory Agency); (b) mandating the regulatory agencies to establish and maintain a transparent licensing and contracting framework; (c) tasking the Government to establish a transparent fiscal regime; and (d) mandating the establishment of an Oil and Gas Fund for maintaining fiscal and macroeconomic stability, enhancing social and economic development, and safeguarding resources for future generations. However, the legal framework suffered from a series of conceptual contradictions on the one hand introducing a regulatory structure and regulatory procedures favoring free market principles, transparency and competition, while on the other opening space for Government interference in due process and introduced elements in its institutional framework that may discourage prospective investors. Further, follow-up on the legislative reforms has been slower than anticipated, in part due to a slump in global energy prices and the resulting downturn in global capital investment in the oil and gas industry. The Natural Resource Charter initiative has not yet been implemented (Results Indicator 10). 67. Investments in gas production by established private sector partners increased but fell short of expected levels. The gas-to-power investment program is a core in the FYDP II and in the Electricity Supply Industry Reform Strategy and Roadmap, which establish ambitious targets for the expansion of power generation capacity. During the Program period, the volume of gas produced increased from 78 mmscfd in 2012 to 102 mmscfd in 2015 and 132 mmscfd in 2016 (Results Indicator 8). Information provided by the private sector suggests that these numbers underestimate investment as additional production capacity is ready for ramp-up (possibly up to 200 mmscfd). However, even when accounting for these uncounted investments, private sector interest fell short of expected levels, and may lead to shortages in gas supply if gas-fired generation capacity is scaled up rapidly (current Government plans calling for the trebling of gas-based generation capacity by FY2020/21 will require an equally ambitious expansion of natural gas production to over 300 mmscfd). 30

44 68. Investments in new exploration also fell short of expectations, at least partially because of the decline in global energy prices. Global oil and LNG prices declined after mid-2014 and subsequently remained subdued through the end of 2017, leading to a slowdown in investor interest in natural gas exploration. As a result, the amount of onshore proven natural gas reserves increased only slightly, from 1.0 Tcf in 2012 to 1.4 Tcf in 2015 and 1.2 Tcf in 2016 (Results Indicator 9). 17 In consequence, the development of Tanzania s offshore resources is also unlikely to proceed in the short to medium term. 3.3 Justification of Overall Outcome Rating Rating: Moderately Unsatisfactory 69. The DPO series is rated Moderately Unsatisfactory because, despite significant achievements in the crisis-response elements of the Policy and Results Matrix, the Program did not make sufficient progress towards its objectives (efficacy). The relevance of objectives was Substantial but efficacy was Modest (4 out of 10 results indicators were achieved). The outcome rating compares to a rating of Moderately Satisfactory in the latest ISR for Progress toward achievement of PDO. The rating s justification is that measures taken under the DPO series: Enabled the Program to achieve 4 out of 10 indicators (and overachieve on two of them), even though the results indicators were designed for a series of three operations but only two out of three planned DPOs were approved; Led to major rebalancing of cost and revenues in the power sector, bringing TANESCO s profitability back to pre-crisis levels (Results Indicators 1 and 5); Contributed to significant improvements in TANESCO s operational performance, including a one-fourth reduction in technical and non-technical losses and achievement of good practice benchmark levels of bill collection; Scaled up the power-to-gas supply chain in Tanzania and established a legislative framework for upstream natural gas development, but did not achieve the envisioned medium-term supply security of natural gas and gas-fired power; Laid the conceptual groundwork for a power sector reform policy and road map, but could not facilitate significant progress toward reform implementation. 3.4 Overarching Themes, Other Outcomes and Impacts (a) Poverty Impacts, Gender Aspects, and Social Development 70. Poverty impacts of the electricity tariff reforms under the Program were mitigated through cross-subsidies between consumer groups. As shown in the tariff schedule in annex 6, electricity tariffs in Tanzania are differentiated by consumer groups. Small household consumers (category D1; defined as average consumption below 75 kwh per month) have been and continue to be subsidized. As of FY2017, the tariff applied to this consumer group is T Sh 100 per kwh, compared to a general use tariff of T Sh 17 The Government statistic of 57 Tcf of natural gas reserves corresponds to a gross approximation of gas in place, which has not been independently assessed and does not correspond to the internationally recognized meaning of reserves. 31

45 292 per kwh (category T1). In relative terms, tariffs for D1 increased by 67 percent between FY (28 percent in real terms), the highest value among the five categories, but in absolute terms the increase of D1 tariffs (T Sh 40 per kwh) was the second lowest among the categories (see annex 6). Thus, cross-subsidies mitigated the poverty impact of the reforms under the DPO series. 71. Growth in real household income from strong GDP growth and contained inflation also mitigated the poverty impacts of the tariff reforms under the DPO series. GDP growth remained favorable at around 7 percent throughout the implementation period. Inflation declined after FY2012 and remained around 5 6 percent in FY2013 FY2016/ A review of household spending on electricity tariffs in over 20 Sub-Saharan African countries found that, after the tariff reforms, the share of household spending on electricity in Tanzania was still not above average in the region ( percent among the poor and percent among all households). 18 This is in line with the finding that the tariff reforms under the Program did not have significant negative impacts on poverty in Tanzania. 73. The tariff increases enabled TANESCO to significantly expand its electrification program from 2013 onward, with the associated positive social and gender impacts. Providing households, social institutions, and enterprises with new energy access and improved energy services has the potential to promote gender equality, create employment and business opportunities, and contribute to a broad range of human development outcomes. As shown in Figure 7, TANESCO and REA accelerated the implementation of Tanzania s electrification program. Between them, the two institutions more than tripled the number of new connections completed per year between FY2012 and FY2015/16. TANESCO s contribution to this expansion was largely financed from its own resources and thus benefited significantly from increased revenues due to the tariff reforms under the Program. Figure 7. New Electricity Connections Completed by TANESCO and REA in FY2004 FY2016/17 350,000 New connections per year (incl. REA) 300, , , , ,000 50, * Source: TANESCO. 74. Reduced budget transfers to the power sector contributed to fiscal consolidation and provided fiscal space for spending on other priorities, including spending on social development. 18 Kojima, M., X. Zhou, J. J. Han, J. de Wit, R. Bacon, and C. Trimble Who Uses Electricity in Sub-Saharan Africa? World Bank Policy Research Working Paper World Bank, Washington, DC. 32

46 During the Program period, fiscal consolidation remained a major challenge for the Government due to lower-than-expected domestic revenue collection, diminishing aid disbursements, and higher investment in infrastructure projects. As a result of the Program, Government transfers to the power sector (net of taxes) decreased from US$117 million in FY2012 and US$139 million in FY2013 to US$3 million in FY2016 and 0 in FY2017. This provided fiscal space and reduced the pressure on fiscal consolidation in other sectors. (b) Institutional Change/Strengthening 75. TANESCO and the MEM took several measures under the Program to strengthen TANESCO s governance and operational capacity, but the long-term impact of these measures has been marginal. The key institutional change brought in by the DPO program was the signing of a performance contract for FY2013 between TANESCO and the MEM, which included measurable KPIs for TANESCO. However, follow-up on areas of underperformance has been limited. TANESCO s institutional independence and its accountability for performance have not changed significantly since the beginning of the Program. Other governance measures included the publication of financial reports and performance audits, but publication of these documents has since been irregular and the scope of reporting could be improved. 76. The Government has put in place a comprehensive reform road map for institutional restructuring and strengthening in the power sector, but implementation of the road map has been limited. Under the Program, the Government adopted the recommendations of the Presidential Big Results Now Initiative to develop a road map for structural reforms of the energy sector, developed the Electricity Supply Industry Reform Strategy and Roadmap in 2014, and established a Ministry Delivery Unit within the MEM to oversee the implementation of the road map. However, implementation of the roadmap has been limited Significant institutional reforms in the natural gas sector were initiated with the adoption of new gas sector legislation in The legislative reforms under the Program established the basic elements of its legal and institutional framework for the proper development of its natural gas sector. (c) Other Unintended Outcomes and Impacts (positive or negative) 78. Implementation of the Program halted the increase in specific greenhouse gas (GHG) emissions of Tanzania s power sector. Per unit GHG emissions in the sector increased by 78 percent, from 228 gco 2 /kwh to 408 gco 2 /kwh, between 2008 and This trend was due to increased reliance on oil-fired generation while hydropower output remained stable and was expected to continue in the absence of larger utilization of natural gas. By promoting hydropower and natural gas over oil-fired generation, the Program reversed this trend and specific emissions fell to an average of 361 gco 2 /kwh during FY2014 FY2016/ Reforms envisioned in the roadmap to be completed by the end of FY2017/18 included the unbundling of generation from transmission and distribution; direct trading between generators and bulk off-takers; the creation of a designated independent market operator; and a mechanism and rules for the operation of a retail market for electricity by the regulator. None of these reforms were under way at the time of the ICR, and whether or not they will be implemented in the future was uncertain. 33

47 gco2/kwh Figure 8. Impact of the Program on GHG Emissions in the Sector 500 Specific GHG emissions of the power sector in Tanzania FY2008- FY2016/ Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Dec Jan-Jun Jul-Jun Jul-Jun Source: World Bank staff estimates based on TANESCO data. 79. The ICR identified no other unintended outcomes or impacts. 3.5 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops 80. No beneficiary survey or stakeholder workshop was held. 4. Assessment of Risk to Development Outcome Overall Rating: High / / The risk to the development outcome is assessed as High, for six main reasons: (a) the tight balance between supply and demand in the power sector; (b) continued pressure on TANESCO s cash flow; (c) changes in the priorities and reform direction of the new Government in the power sector; (d) recent reforms in the upstream natural gas policy framework and potential impacts on the investment climate; (e) there is a risk that the Government is learning the wrong lessons from private sector investments in the power sector; and (f) macroeconomic risks, including exchange rate risks, constraints on fiscal space limiting the Government s ability to contribute to TANESCO s investment program and arrears repayment, and global energy price volatility. 82. First, the supply-demand balance in Tanzania s power sector is still precarious and TANESCO may fall back into financial difficulties e.g., in case of a drought or power plant failure before additional gas-fired generation capacity comes online and the interconnection to Ethiopia is commissioned. Tanzania has experienced periodic financial crises in the power sector (last in ), largely due to a lack of sufficient supply capacity to withstand droughts. As of end-2017, the supply-demand balance remains tight, even at the current level of connectivity, as evidenced by the major 10-hour power outage in late October Two major gas power plant investments (Kinyerezi I Extension and Kinyerezi II) are expected to be completed in 2018/19, adding 425 MW in total 20. In addition, a new grid interconnection with Kenya/Ethiopia is expected to be completed in phases starting in 2019, eventually allowing up to 400 MW of imports. However, utilizing the new gas plants will require 20 Kinyerezi II (240 MW) will be gradually commissioned by August The Kinyerezi I Extension (185 MW) is expected to be fully operational by the beginning of

48 securing gas supplies, which are at risk of falling short of quantities needed for the new gas-fired generation plants; and until the investments are completed, the system remains vulnerable to outages in case of failures of individual power plants. Improved system expansion planning and execution, including supply diversification by utilizing Tanzania s solar and wind resources, will be important to further reduce vulnerability to droughts and other supply side risks. 83. Second, plans for major public investment in the power sector will continue to put pressure on cash flow, limiting TANESCO s ability to repay its arrears. The 2016 PSMP update implies major public investment in generation and transmission. The same is true for the Government s access targets (connecting 50 percent of the population by 2020 and over 75 percent by 2030, up from 33 percent in 2016), which imply a major scale-up of investment in new connections. World Bank estimates suggest that achieving the targets would require 600, ,000 new household connections per year, up from around 250,000 per year in recent years. TANESCO is already at the limits of its financing capacity and access to commercial borrowing is restricted. Pressure on TANESCO s liquidity is therefore expected to continue. 84. Third, the Government has at least partially shifted direction in the reform program in the power sector, potentially reversing or stalling some of the outputs and outcomes under the Program. The new Government has charted out a new course of action with regard to key economic policy directions, but its priorities in the energy sector are still being worked out. An ongoing consulting assignment on the financial situation of TANESCO is an illustration of the Government s intent to understand the prevailing situation before embarking on a new reform program. Whether or not the Government intends to continue implementation of the reform program laid out under Pillar 2 including the reform road map laid out in the documents that contributed to Results Indicator 7 is currently unclear. Nonetheless, it is clear that the current Government is putting less emphasis on private sectorfunded infrastructure development in the energy sector than the Program laid out under this DPO series, meaning that some of the outputs and outcomes of the Program may be reversed or stalled in the future. The Government also retains strong direct influence over decision-making in the sector and has weakened EWURA s ability to make independent regulatory decisions Fourth, there is a risk that the Government is learning the wrong lessons from past private sector investments in the power sector. While the Government and TANESCO implemented the initial phase of the 2013 Policy for Private Sector Participation in Power Generation through Competitive Processes by launching PPP capacity-building programs, the DPO series was not able to demonstrate the benefits of well-executed private sector investments in the power sector. Therefore, a small number of controversial and poorly executed contracts continue to cast a shadow on the outlook for privately-owned generation in Tanzania in general. In the absence of a clearly articulated rationale and shared vision among sector stakeholders, the Government s policy toward private sector participation in future generation projects is unclear. The risk to the development outcome is that the Government concludes from these poorly executed investments that private sector investments are not worth pursuing at all, rather than that private sector investments have to be done right. 86. Fifth, recent amendments to the Petroleum Act in mid-2017, passed in response to the outcomes of a parliamentary inquiry into mining contracts with the private sector, may affect the natural gas investment framework. Shortly before the ICR was prepared, in July 2017, the Government amended the Petroleum Act of Potential impacts of the reforms include (a) negatively affecting the 21 In December 2016, the Minister of Energy and Minerals suspended EWURA tariff order. In June 2017, the Prime Minister suspended the Director General of EWURA after EWURA initiated the license renewal process for IPTL. EWURA then declined to renew the operating license for IPTL in August

49 stability of existing Production Sharing Agreements; and (b) clouding the prospects for future private investment in the sector. Therefore, although the impact of the amendments on the attractiveness of investment in natural gas exploration and production was not fully clear at the time of the ICR, the amendments increased the risks to the development outcome. 87. Sixth, while the macroeconomic outlook is relatively stable, macroeconomic risks to the development outcome include TANESCO s exposure to exchange rate risks; constrained fiscal space limiting the Government s ability to adequately fund TANESCO s investment program or contribute to repayment of arrears; and global energy price volatility. Tanzania s economy remains one of the highest performers in the region, exceeded in 2016 only by Côte D Ivoire and Ethiopia. Real GDP expanded at a slower rate of 6.8 percent in the first half of 2017 compared to 7.7 percent over the same period in The inflation rate has remained low and stable and reserves are at a healthy level. The outlook remains favorable with the main downside risks of a domestic nature and largely under Government control. However, TANESCO s arrears remain exposed to exchange rate risks as much of it is denominated in US$. Furthermore, in view of continued fiscal constraints for the Central Government, such as persistently high arrears 22 and underexecution of the development budget, it is unclear to what extent the Government can contribute to funding TANESCO s investment program or the repayment of arrears. Lastly, macroeconomic risks to the sustainability to the development outcome also include global energy price volatility, especially the potential negative impact of sustained low energy prices on investments in the development of Tanzania s natural gas resources. 5. Assessment of Bank and Borrower Performance 5.1 Bank Performance (a) Bank Performance in Ensuring Quality at Entry Rating: Moderately Satisfactory 88. World Bank performance in ensuring quality at entry is rated Moderately Satisfactory for the following reasons: The World Bank ensured that the DPO series was part of a concerted donor effort to support the Government s response to the fiscal and macroeconomic implications of the electricity supply crisis during The objectives of the crisis-response elements of the Policy and Results Matrix to restore TANESCO s financial viability and reduce fiscal risks were core to the Government s and the World Bank s strategy in the energy sector. The crisis-response elements of the Policy and Results Matrix was informed by recent analytical work and global experience and had a clear line of sight between prior actions and results indicators. Enough flexibility was built into the design of the Policy and Results Matrix to allow the Government s deliberation on important but difficult policy decisions to follow due course. For instance, the Triggers for DPO-2 under Pillar 1 specified the fiscal reform objective (a 22 Arrears to contractors, suppliers, and pension funds by the Government reached over 6 percent of GDP at the end of FY2015/16. 36

50 cap on transfers to TANESCO), but left the exact nature of policy actions open. During preparation of DPO-2 the language of Prior Action 2.1 was then adjusted to account for the outcomes of the Government s deliberation. The medium- to long-term reform elements of the Policy and Results Matrix were risky because they were backloaded; heavy on commitments and light on implementation; and missed a clear line of sight between prior actions and results indicators. Some of these risks were informed risks and thus do not represent shortcomings in the performance of the World Bank, but important governance risks were missed; the political economy of power sector reform in particular was poorly reflected in the design of the medium- to long-term reform measures in the Program. (b) Quality of Supervision Rating: Moderately Satisfactory 89. World Bank performance in ensuring quality at supervision is rated Moderately Satisfactory for the following reasons. Continued close alignment of the DPO series with DPs programs was critical for the success achieved during implementation. Throughout the implementation of the Program, the World Bank provided close implementation support by an experienced core team as part of regular supervision missions and additional support missions as needed. The parallel technical assistance under the World Bank s ESCBP provided much-needed capacity-building support to implement the Program. The World Bank continuously monitored progress against the main financial and performance indicators of the power sector and the M&E framework was used in the implementation of the Program and decisions on the World Bank s DPO series in an adequate manner. The decision not to proceed with the third operation in the series within the two years after Board approval of DPO-2 reflected an adequate adjustment to changing context and Government priorities and was based on in-depth dialogue with the Government during three missions in September and then in November and December However, the World Bank s implementation support is considered to have had moderate shortcomings, because it did not reflect a complete understanding of the political economy of power sector reform in Tanzania and the World Bank team was not always able to respond to implementation challenges on time. For instance: i. The major change in the Government s policy for connection charges in early 2013 and its impact on TANESCO s finances were not recognized in the preparation of DPO-2 and thus not reflected in the design of the operation. ii. The fact that arrears continued to mount in FY2014/15 despite positive income could have led the Bank team to adjust course in the reform dialogue. 37

51 iii. In hindsight, more could have been done to disseminate global best practices in structuring and executing private-sector participation in the power sector, and the potential benefits for Tanzania s development. iv. The DPO series results framework was not adjusted when it became clear that the third DPO would not be not approved within 24 months. (c) Justification of Rating for Overall Bank Performance Rating: Moderately Satisfactory 90. This rating combines the ratings for Quality at Entry and Quality of Supervision. 5.2 Borrower Performance Rating: Moderately Unsatisfactory 91. While the MOF was the official implementing agency of DPO series, the ICR considers the MOF and the MEM as the key implementers of the program, as both represented the Government in the implementation of the Program. Government performance is rated Moderately Unsatisfactory because of significant shortcomings despite strong performance in some areas of the Policy and Results Matrix: Government commitment to and leadership in the crisis-response elements of the Policy and Results Matrix was strong and the Government successfully managed the fiscal impacts of the power sector crisis in Service and performance improvements facilitated under the leadership of the MEM contributed to the social acceptability of tariff reforms. The MOF, in coordination with the MEM, TANESCO, and EWURA took ownership in selecting and implementing the prior actions and the borrower commitment was reflected in the timely approval of DPO-1 and DPO-2. The Government established a policy framework for upstream natural gas development, maintained momentum after approval of DPO-2 and adopted legislation that reformed natural gas sector governance. Government commitment to the medium- to long-term power sector reforms including private sector participation, structural reforms of the power sector, good governance and financial sustainability of TANESCO and an independent regulatory function in the Policy and Results Matrix was less clear from the start. The Government s reform efforts in the energy sector and engagement with the World Bank lost momentum when the IPTL controversy led to removal or suspension of prolonged periods of time of MEM officials including key leadership positions. Despite progress in some areas, reform efforts are yet to regain momentum, causing major delays in implementation of the Program. DPO-3 was cancelled as a result. Insufficient Government funding for TANESCO s investment program after approval of DPO-2 led to a cash shortfall at TANESCO and contributed to the buildup of arrears. Under DPO-2, the Government and TANESCO committed to finance any remaining financing gap in the power sector (after tariff reforms) from Government subsidies and commercial 38

52 6. Lessons Learned borrowing. However, actual Government measures fell short of this commitment, especially with regard to cash needs for investment. Rating: Moderately Unsatisfactory 92. A sectoral DPO series can be an effective crisis response when it is closely aligned with an IMF program, complements fiscal consolidation with service improvements, and has a clear line of sight between prior actions and expected outcomes. The Power and Gas Sector DPO series was successful in the first two years and in (most of) the crisis-response elements relating to financial sustainability and fiscal risks of the power sector, for three main reasons. First, close coordination and parallel support by several DPs, especially the IMF, was critical for sustained implementation of these difficult reforms. Second, the major tariff reforms between FY2011 and FY2014/15 which, cumulatively, more than doubled tariffs for some categories, were acceptable to consumers only because they were accompanied by significant reductions in outages and improvements in quality of service. This further underpins recent global experience, which suggests that consumers are willing to pay more if they in turn receive better service. Third, the crisis-response elements of the Policy and Results Matrix especially measures relating to TANESCO s revenues and costs such as tariff reforms and the phase-out of EPPs had a clear line of sight between prior actions and expected outcomes. 93. Improving liquidity and profitability of utilities are related objectives but require separate analyses and risk mitigation measures. The DPO series implicitly assumed that achieving profitability and reducing arrears the two subobjectives under Pillar 1 could be achieved largely through the same measures (the term financing gap in the PDO was meant to capture both cash needs and net income). However, trends in profitability and arrears diverged widely during the Program period because TANESCO s investment program was inadequately funded, underscoring the need for separate analyses and risk mitigation measures in the design of operations targeting both. 94. Engaging in the natural gas agenda was a risk worth taking, even if outcomes as measured by the results indicators were only Modest. The Bank used this DPO series as an opportunity to establish an engagement with the Government in the natural gas sector, which was and remains critical for the development of Tanzania s energy sector. This decision enabled the DPO series to support a comprehensive reform program that tackled the whole energy supply chain. While the reform momentum in the natural gas sector slowed down when global energy prices declined in 2015, significant progress was made towards a modern upstream natural gas policy framework that would not have been possible without the DPO series. Thus, despite weak performance on indicators under Pillar 3, engagement in the gas sector reform proved to be risk worth taking. 95. World Bank-supported power sector reform programs in Sub-Saharan Africa need to take into account the full breadth of utility investment obligations including investments to deliver on the electricity access agenda and their impacts on sector fundamentals. The Government s efforts to expand electricity access were recognized in the design of the Program, but not fully integrated into the financial modeling that underpinned the Program s Results Framework. The impact of the access agenda on sector financials was therefore not anticipated, even in DPO-2, which was approved after the Government significantly expanded financial obligations for TANESCO in financing new connections (because of the delays in TANESCO s financial reporting, the full impact of these reforms was not yet visible in the performance indicators by the time of appraisal of DPO-2). As a result, TANESCO s arrears continued to rise despite significant improvement and, in fact, overachievement, on TANESCO s income statement (see section 3.2 for more details). In view of the prominence of the access agenda in the Sustainable Development Goals and the sector development programs of Sub-Saharan African 39

53 governments, the lesson from this DPO series is that future energy DPOs in Sub-Saharan Africa including in Tanzania need to take access investments and related policy frameworks more explicitly into account into the design of the operation. 96. Where the promotion of private sector participation is part of a World Bank-supported reform program, program design needs to be informed by a political economy analysis and global best-practices as well as associated benefits need to be clearly articulated. The series was underpinned by comprehensive economic and financial analysis and informed by the World Bank s global experience with energy sector reform. However, no systematic stakeholder mapping and political economy analysis were undertaken. Therefore, the political economy risks of power sector reform in Tanzania were insufficiently reflected in the design and implementation of the program, which contributed to the underperformance of the DPO series (see sections 2 and 3 for details). For instance, in hindsight, the DPO series expectations about the pace and momentum of reforms (beyond immediate crisis-response measures) appear overambitious, and the results framework should have been adjusted once it became clear that DPO-3 would not be approved. Further, more could have been done to articulate and share with the Government global best practices in structuring and executing private-sector participation in the power sector (e.g., best practice in risk sharing in PPP models), and the potential benefits for Tanzania s development. In the absence of a clearly articulated rationale and shared vision among sector stakeholders, a small number of controversial and poorly executed contracts cast a shadow on the outlook for PPPs in Tanzania s power sector in general. This lesson learned is in line with emerging findings from a currently ongoing review of the global power sector reform agenda by the World Bank s Energy and Extractives Global Practice ( Rethinking Power Sector Reform ; P157376), which will lay out an agenda for more closely integrating political economy considerations into power sector reform programs. 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners (a) Borrower/Implementing agencies 97. Not applicable. (b) Cofinanciers 98. Not applicable. (c) Other partners and stakeholders (for example, NGOs/private sector/civil society) 99. Not applicable. 40

54 Annex 1. Bank Lending and Implementation Support/Supervision Processes (a) Task Team Members P TZ First Power and Gas Sector DPO Names Title Unit Responsibility/ Specialty Lending Jacques Morisset Program Leader AFCF2 Task Team Leader Vladislav Vucetic Lead Energy Specialist GEE01 Team Member Nazaneen Ismail Ali Senior Procurement Specialist GGO05 Procurement Mona El-Chami Senior Financial Management Specialist GGO23 Financial Management Mustafa Zakir Hussain Operations Adviser: OPSPQ Team Member Robert Schlotterer Lead Infrastructure Finance Specialist GEEFS Team Member Yutaka Yoshino Program Leader AFCE1 Team Member Emmanuel Mungunasi Senior Economist GMF07 Team Member Sanjeev Ahluwalia n.a. n.a. Team Member Zhengjia Meng Young Professional GEEFS Team Member Alexander Huurdeman Senior Gas Specialist GEEX1 Team Member Goodluck Mosha n.a. n.a. Team Member Waly Wane Senior Economist GED07 Team Member Chiara Bronchi Practice Manager GGO13 Team Member Katherine Bain Consultant GGODR Team Member Victoria Cunningham n.a. n.a. Team Member Agnes Mganga Program Assistant AFCE1 Team Member Leah Mukuta n.a. n.a. Team Member Mercy Sabai Sr Financial Management Specialist GGO31 Team Member Donald Mneney Consultant GGO01 Team Member Ann Jeannette Glauber Lead Environmental Specialist GEN2A Team Member Charles Feinstein n.a. n.a. Peer reviewer Francisco Carneiro Program Leader LCC3C Peer reviewer P TZ Second Power and Gas Sector DPO Names Title Unit Responsibility/ Specialty Lending Yutaka Yoshino Program Leader AFCE1 Task Team leader Vladislav Vucetic Lead Energy Specialist GEE01 Team Member Natalyia Kulichenko Senior Energy Specialist GEE07 Team Member Mustafa Zakir Hussain Operations Adviser: OPSPQ Team Member Jacques Morisset Program Leader AFCF2 Team Member Emmanuel Mungunasi Senior Economist GMF07 Team Member Victoria Cunningham n.a. n.a. Team Member Nicola Woodroffe n.a. n.a. Team Member Lydie Ahodehou Program Assistant GMF07 Team Member Zhengjia Meng Young Professional GEEFS Team Member Alexander Huurdeman Senior Gas Specialist GEEX1 Team Member Justina Kajange Operations Analyst GTI11 Team Member Zoe Kolovou Lead Counsel LEGAM Team Member 41

55 P TZ Second Power and Gas Sector DPO Names Title Unit Responsibility/ Specialty Luis Schwarz Senior Finance Specialist WFALN Team Member Roy Sudharshan Canagarajah Manager ECADE Team Member Hilda Emeruwa Operations Analyst GMFDR Team Member Oliver Braedt Program Leader LCC6C Team Member Ann Jeannette Glauber Lead Environmental Specialist GEN2A Team Member Amy Faust Consultant GSU13 Team Member Helen Shahriari Senior Social Scientist GSU05 Team Member Alexandra C. Bezeredi Lead Social Development Specialist GSU01 Team Member Hanneke Van Tilburg Senior Social Development Specialist OPSPF Team Member Leah Mukuta n.a. n.a. Team Member Isis Gaddis Senior Economist GCGDR Team Member Nadia Belhaj Hassine Senior Economist GPV01 Team Member Mercy Sabai Senior Financial Management Specialist GGO31 Financial Management Donald Mneney Consultant GGO01 Team Member Milan Brahmbhatt n.a. n.a. Peer reviewer Charles Feinstein n.a. n.a. Peer reviewer Havard Halland Senior Economist GGOPS Peer reviewer (b) Staff Time and Cost P Tanzania First Power and Gas Sector DPO Staff Time and Cost (Bank Budget Only) Stage No. of Staff Weeks US$, thousands (including travel and consultant costs) Lending and Supervision FY , TOTAL , P Tanzania Second Power and Gas Sector DPO Staff Time and Cost (Bank Budget Only) Stage US$, thousands (including travel and No. of Staff Weeks consultant costs) Lending and Supervision FY , TOTAL ,

56 Annex 2. Beneficiary Survey Results Not applicable. 43

57 Annex 3. Stakeholder Workshop Report and Results Not applicable. 44

58 Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR No comments from the Borrower were received by the time of the submission of this ICR. 45

59 Annex 5. Comments of Cofinanciers and Other Partners/Stakeholders Not applicable. 46

60 Annex 6. Supporting Data Table 6.1. Results Indicators No. Pillar 1 Unit TANESCO operating deficit US$ million (3) (20) (3) (149) 92 (80) 2 TANESCO accounts (trade and other) T Sh 428,9 472,21 824,0 979,9 1,187, 1,330, 202, , ,012 payable million TANESCO technical and non-technical losses in transmission and distribution (%) % Pillar 2 Unit Amount of gas-fired power generation capacity commissioned after 2011 (MW) MW n.a. n.a. n.a. n.a Average unit cost of power sales (US$/MWh) US /kwh Number of bids for gas IPP power plants launched on a competitive basis (count) n.a. n.a. n.a. n.a. n.a. n.a MEM documents on sector reforms published for public knowledge (count) n.a. n.a. n.a. n.a. n.a. n.a Pillar 3 Unit Volume of gas produced (mmscfd) mmscfd n.a. n.a. n.a. n.a. 78 n.a n.a. 9 Amount of onshore proven natural gas reserves (Tcf) Tcf n.a. n.a. n.a. n.a n.a n.a. 10 Annual monitoring under the Natural Resource Charter initiative n.a. No No No No No No No No No 47

61 D1 T1 T2 Table 6.2. Electricity Tariffs by Category FY2008 FY2017 Electricity Tariffs Category Unit FY2008 FY2009 FY2010 FY2011 FY2012 FY2013 FY2015 FY2016 FY2017 Consumers who consume on average below 75 kwh General usage tariff Consumers at 400 V and above and >7,500 kwh/month T3 Medium voltage T5 High voltage Service charge T Sh/Month Energy charge (0 75 kwh) Energy charge (>75 kwh) Change FY2012 FY2017 T Sh/kWh % T Sh/kWh % Service charge T Sh/Month 2,303 2,303 2,303 2,738 3,841 3,841 5, % Energy charge T Sh/kWh % Maximum demand charge T Sh/kVA/Month Service charge T Sh/Month 8,534 8,534 8,534 10,146 14,233 14,233 14,233 14,233 14,233 0% Energy charge T Sh/kWh % Maximum demand charge T Sh/kVA/Month 9,347 9,347 9,347 12,078 16,944 16,944 15,004 15,004 15,004 11% Service charge T Sh/Month 8,534 8,534 8,534 10,146 14,233 13,233 16,769 16,769 16,769 18% Energy charge T Sh/kWh % Maximum demand charge T Sh/kVA/Month 8,669 10,350 14,520 13,200 13,200 13,200 28% Service charge T Sh/Month 8,534 8,534 8,534 10,146 14,233 15, % Energy charge T Sh/kWh % Maximum demand charge T Sh/kVA/Month 4,775 4,775 4,775 8,610 12,079 12,079 16,550 16,550 16,550 37% 48

62 Annex 7. List of Supporting Documents Title Date Reference Number 2016 Power System Master Plan Update December 2016 n.a. AfDB Power Sector Reforms and Governance 2015, 2016 n.a. Support Program (PSRGSP) Phases I III Aide Memoires for the Project s Supervision Missions Multiple Multiple Development of Electricity Tariff-Setting August 2012 n.a. Methodology and Carrying Out Cost of Service Study (Mercados Study) DPO Program Documents February 2013, TZ, TZ February 2014 Electricity Supply Industry Reform Strategy and June 2014 n.a. Roadmap IMF Staff Reports on Article IV Consultations and Multiple Reviews under the Standby Credit Facility Arrangement Program Implementation Status and Results Reports Multiple Multiple (ISRs) TANESCO Audited Financial Statements and n.a. Management Accounts TANESCO Short-term Financial Assessment 2012 June, 2012 n.a TANESCO Tariff Applications n.a. TANESCO Turnaround Study (MCC) 2016 n.a. Tanzania Development Vision n.a. Tanzania Economic Update 10: Managing Water November 2017 n.a. Wisely Tanzania National Energy Policy December, 2015 n.a. Tanzania Rural Electrification Expansion Program May, TZ Program for Results Tanzania: Intended Nationally Determined September 2015 n.a. Contribution (INDC) under the UNFCCC The Tanzania Five-Year Development Plan 2011/12 June 2011 n.a. 2015/16 The Tanzania Five-Year Development Plan 2016/17 June 2016 n.a. 2020/21 World Bank Tanzania CAS for FY2012/15 May, TZ Note: MCC = Millennium Challenge Corporation; UNFCCC = United Nations Framework Convention on Climate Change. 49

63 Annex 8. Map Source: The World Bank. 50

Japanese ODA Loan. Ex-ante Evaluation

Japanese ODA Loan. Ex-ante Evaluation Japanese ODA Loan Ex-ante Evaluation 1. Name of the Program Country: The Islamic Republic of Pakistan Project: Energy Sector Reform Program Loan Agreement Signed: June 4, 2014 Loan Amount: 5,000 million

More information

Power Sector Reform: Second Development Policy Credit Region

Power Sector Reform: Second Development Policy Credit Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROGRAM INFORMATION DOCUMENT (PID) APPRAISAL STAGE April 2, 2015 Report No.: 99908 (The

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING ELECTRICITY SECTOR EFFICIENCY ENHANCEMENT PROJECT CR SE. April 25, 2005 TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING ELECTRICITY SECTOR EFFICIENCY ENHANCEMENT PROJECT CR SE. April 25, 2005 TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0021272 Public Disclosure Authorized Public Disclosure Authorized Operation ID P159774 Country Fiji Operation Name Fiji Post-Cyclone Winston

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80480) ON A LOAN IN THE AMOUNT OF US$ 100 MILLION TO TO THE THE REPUBLIC OF EL SALVADOR FOR A

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80480) ON A LOAN IN THE AMOUNT OF US$ 100 MILLION TO TO THE THE REPUBLIC OF EL SALVADOR FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR2743 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

The World Bank Kenya Infrastructure Finance/PPP project (P121019)

The World Bank Kenya Infrastructure Finance/PPP project (P121019) Public Disclosure Authorized AFRICA Kenya Financial Systems Practice Global Practice IBRD/IDA Adaptable Program Loan FY 2013 Seq No: 4 ARCHIVED on 22-Dec-2014 ISR17114 Implementing Agencies: Public Private

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2620) (IDA-4520) (IDA-46610) (IDA-47750) ON A GRANT AND THREE CREDITS

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2620) (IDA-4520) (IDA-46610) (IDA-47750) ON A GRANT AND THREE CREDITS Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2620) (IDA-4520)

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) TF Dec ,580,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) TF Dec ,580,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020620 Public Disclosure Authorized Public Disclosure Authorized Operation ID P147166 Country Haiti

More information

Project Costs (US$M):

Project Costs (US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted: 10/05/2015 Report Number: ICRR14849 Public Disclosure Authorized Public Disclosure Authorized Public

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H6200) ON A GRANT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H6200) ON A GRANT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002334 IMPLEMENTATION COMPLETION AND RESULTS

More information

Actual Project Name : Tanzania Emergency Power Supply Country: Tanzania. Project Costs (US$M US$M):

Actual Project Name : Tanzania Emergency Power Supply Country: Tanzania. Project Costs (US$M US$M): IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted : 09/24/2007 Report Number : ICRR12725 PROJ ID : P074624 Appraisal Actual Project Name : Tanzania Emergency Project Costs (US$M

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-81900) ON A SERIES OF LOANS IN THE AMOUNT OF $21.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-81900) ON A SERIES OF LOANS IN THE AMOUNT OF $21. Public Disclosure Authorized Document of The World Bank Report No: ICR00003839 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-81900) ON A SERIES OF LOANS IN THE AMOUNT

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H8510) ON A GRANT IN THE AMOUNT OF SDR 3.4 MILLION (US$5.0 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H8510) ON A GRANT IN THE AMOUNT OF SDR 3.4 MILLION (US$5.0 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Document of The World Bank Report No: ICR00004097 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H8510) ON A GRANT

More information

Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL CREDIT DOCUMENT INTERNATIONAL DEVELOPMENT ASSOCIATION

Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL CREDIT DOCUMENT INTERNATIONAL DEVELOPMENT ASSOCIATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Water and Urban I1 Africa Region Document of The World Bank FOR OFFICIAL USE ONLY SUPPLEMENTAL

More information

Assessment of reallocation warrants in Tanzania

Assessment of reallocation warrants in Tanzania ANALYSIS OF REALLOCATION WARRANTS Final report: Assessment of reallocation warrants in Tanzania July 2014 Scanteam: Team leader Torun Reite and team member Erlend Nordby ANALYSIS OF REALLOCATION WARRANTS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002035 IMPLEMENTATION COMPLETION AND RESULTS

More information

The World Bank NEITI Reporting Compliance (P162344)

The World Bank NEITI Reporting Compliance (P162344) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF NEITI REPORTING COMPLIANCE APPROVED ON DECEMBER 7, 2016 TO FEDERAL MINISTRY

More information

2015 Development Policy Financing Retrospective: Preliminary Findings

2015 Development Policy Financing Retrospective: Preliminary Findings 2015 Development Policy Financing Retrospective: Preliminary Findings Purpose of this Consultation Meeting on the DPF Retrospective The 2015 Retrospective will focus on the Bank s experience with Development

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H9370 AND IDA-D0830) FOR AN ECONOMIC GOVERNANCE REFORM OPERATION

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H9370 AND IDA-D0830) FOR AN ECONOMIC GOVERNANCE REFORM OPERATION Public Disclosure Authorized Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Report No: ICR00004366 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H9370 AND IDA-D0830)

More information

Islamic Republic of Pakistan: Update on Energy Sector Plan

Islamic Republic of Pakistan: Update on Energy Sector Plan Technical Assistance Report Project Number: 50081-001 Knowledge and Support Technical Assistance (KSTA) August 2017 Islamic Republic of Pakistan: Update on Energy Sector Plan This The views document expressed

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA & IDA-57400) ON A SERIES OF CREDITS

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA & IDA-57400) ON A SERIES OF CREDITS Public Disclosure Authorized Document of The World Bank Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-54360 & IDA-57400) ON A Report No: ICR00004110 SERIES OF CREDITS Public

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD IDA-47520) ON A LOAN/CREDIT IN THE AMOUNT OF US$4 MILLION / US$8 MILLION ST.

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD IDA-47520) ON A LOAN/CREDIT IN THE AMOUNT OF US$4 MILLION / US$8 MILLION ST. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-79190 IDA-47520)

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) TF-A Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) TF-A Jun ,000,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020814 Public Disclosure Authorized Public Disclosure Authorized Operation ID P156865 Country West Bank

More information

Country Practice Area(Lead) Additional Financing Croatia Finance & Markets P129220

Country Practice Area(Lead) Additional Financing Croatia Finance & Markets P129220 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020731 Public Disclosure Authorized Public Disclosure Authorized Project ID P116080 Project Name EXPORT

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-51970) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$ 440 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-51970) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$ 440 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-51970) ON

More information

Program Information Document (PID)

Program Information Document (PID) Program Information Document (PID) Appraisal Stage Date Prepared/Updated: 17-May-2018 Report No: PIDA24962 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80400) FOR A

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80400) FOR A Public Disclosure Authorized Document of The World Bank Report No: ICR00003828 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80400) FOR A

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 104604 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Document of The World Bank

Document of The World Bank Document of The World Bank PROJECT COMPLETION NOTE OF A LEARNING AND INNOVATION LOAN IN THE AMOUNT OF SDR 2.7 MILLION (US$4 MILLION EQUIVALENT) TO THE REPUBLIC OF MALAWI FOR A DEVELOPMENT LEARNING CENTER

More information

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection Technical Assistance Report Project Number: 47042-001 Policy and Advisory Technical Assistance (PATA) October 2013 People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

More information

Report No: ICR IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-81270) ON A SERIES OF TWO LOANS IN THE AMOUNT OF US$ 500 MILLION TO THE

Report No: ICR IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-81270) ON A SERIES OF TWO LOANS IN THE AMOUNT OF US$ 500 MILLION TO THE Public Disclosure Authorized Document of The World Bank Report No: ICR00004058 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-81270) ON A SERIES OF TWO LOANS Public Disclosure

More information

Document of The World Bank

Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-44000, TF-99140)

More information

Jordan Country Brief 2011

Jordan Country Brief 2011 Jordan Country Brief 2011 CONTEXT The Hashemite Kingdom of Jordan is an upper middle income country with a population of 6 million and a per-capita GNI of US $4,390. Jordan s natural resources are potash

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1.Name of the Project Country: Ukraine Project: Economic Reform Development Policy Loan (Ⅱ) Loan Agreement: December 4, 2015 Loan Amount: JPY

More information

TANZANIA DIAGNOSTIC TRADE INTEGRATION STUDY (DTIS) UPDATE: EXTRACTIVE INDUSTRIES. 07 November, 20016

TANZANIA DIAGNOSTIC TRADE INTEGRATION STUDY (DTIS) UPDATE: EXTRACTIVE INDUSTRIES. 07 November, 20016 TANZANIA DIAGNOSTIC TRADE INTEGRATION STUDY (DTIS) UPDATE: EXTRACTIVE INDUSTRIES 07 November, 20016 1 Extractive Industries strategic importance The Extractive Industries (EI) sector is made up of Large-scale

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: NEP 37196 TECHNICAL ASSISTANCE TO THE KINGDOM OF NEPAL FOR RESTRUCTURING OF NEPAL ELECTRICITY AUTHORITY December 2004 CURRENCY EQUIVALENTS (as of 3 November 2004) Currency Unit

More information

Vietnam: IMF-World Bank Relations *

Vietnam: IMF-World Bank Relations * -1- Vietnam: IMF-World Bank Relations * Partnership in Vietnam s Development Strategy The government of Vietnam s development strategy is set forth in its Comprehensive Poverty Reduction and Growth Strategy

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE APPROACH (SWAP) DEVELOPMENT PROJECT Public Disclosure Authorized The World Bank REPORT NO.: RES30161 RESTRUCTURING PAPER Public Disclosure Authorized ON A PROPOSED PROJECT RESTRUCTURING OF RWANDA ELECTRICITY ACCESS SCALE-UP AND SECTOR WIDE

More information

Implementation Status & Results Lebanon LB-EMERGENCY POWER SECTOR REFORM CAPACITY REINFORCEMENT (P104774)

Implementation Status & Results Lebanon LB-EMERGENCY POWER SECTOR REFORM CAPACITY REINFORCEMENT (P104774) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Lebanon LB-EMERGENCY POWER SECTOR REFORM CAPACITY REINFORCEMENT (P104774) Operation Name: LB-EMERGENCY

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Haiti Energy & Extractives Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 7 ARCHIVED on 28-Jun-2017 ISR27403 Implementing Agencies:

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Mar ,450,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Mar ,450,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021097 Public Disclosure Authorized Public Disclosure Authorized Project ID P111598 Country Tanzania

More information

EN 1 EN. Annex. Sector Policy Support Programme: Sector budget support (centralised management) DAC-code Sector Trade related adjustments

EN 1 EN. Annex. Sector Policy Support Programme: Sector budget support (centralised management) DAC-code Sector Trade related adjustments Annex 1. Identification Title/Number Trinidad and Tobago Annual Action Programme 2010 on Accompanying Measures on Sugar; CRIS reference: DCI- SUCRE/2009/21900 Total cost EU contribution : EUR 16 551 000

More information

Kenya s IMF Standby Facility, & Cytonn Weekly #31/2018

Kenya s IMF Standby Facility, & Cytonn Weekly #31/2018 Kenya s IMF, & Cytonn Weekly #31/2018 Focus of the Week The International Monetary Fund (IMF) recently concluded their visit to Kenya where they were holding discussions with the Kenyan Government on the

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT

More information

Cofinancing (US$M): c. Policy Areas: The policy areas included into the Program Document of the FIRM DPL were the following:

Cofinancing (US$M): c. Policy Areas: The policy areas included into the Program Document of the FIRM DPL were the following: Public Disclosure Authorized IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted: 03/25/2015 Report Number: ICRR14675 Public Disclosure Authorized Public Disclosure Authorized Public

More information

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) Sector Performance, Problems, and Opportunities Improving Public Expenditure Quality Program, SP1 (RRP VIE 50051-001) SECTOR ASSESSMENT (SUMMARY): PUBLIC SECTOR MANAGEMENT (PUBLIC EXPENDITURE AND FISCAL MANAGEMENT) 1 Sector Road Map 1. Sector Performance,

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: 87961

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: 87961 Project Name Region Country Sector(s) Theme(s) Lending Instrument Project ID Borrower Implementing Agency Environmental Category PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: 87961 IMPROVING

More information

Armenia: Infrastructure Sustainability Support Program

Armenia: Infrastructure Sustainability Support Program Technical Assistance Report Project Number: 46220 Policy and Advisory Technical Assistance (PATA) December 2012 Armenia: Infrastructure Sustainability Support Program The views expressed herein are those

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON A MULTI DONOR TRUST FUND TF IN THE AMOUNT OF US$ MILLION EQUIVALENT TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON A MULTI DONOR TRUST FUND TF IN THE AMOUNT OF US$ MILLION EQUIVALENT TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF056601) ON

More information

DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING HONDURAS AND NICARAGUA CATASTROPHE RISK INSURANCE PROJECT

DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING HONDURAS AND NICARAGUA CATASTROPHE RISK INSURANCE PROJECT Public Disclosure Authorized The World Bank DOCUMENT OF THE WORLD BANK REPORT NO.: RES24760 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00003680 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF-92396 TF-96083)

More information

Central government administration (80%); Sub-national government administration (20%) Operation ID

Central government administration (80%); Sub-national government administration (20%) Operation ID Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROGRAM INFORMATION DOCUMENT (PID) APPRAISAL STAGE 31 March 2016 Report No.: AB7818 (The

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) A GRANT IN THE AMOUNT OF SDR 10 MILLION (US$15.00 MILLION EQUIVALENT),

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) A GRANT IN THE AMOUNT OF SDR 10 MILLION (US$15.00 MILLION EQUIVALENT), Public Disclosure Authorized Document of The World Bank Report No: ICR00003583 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) ON A GRANT IN

More information

PROGRAM INFORMATION DOCUMENT (PID) CONCEPT STAGE. First Governance and Competitiveness Development Policy Operation (DPO1) Region

PROGRAM INFORMATION DOCUMENT (PID) CONCEPT STAGE. First Governance and Competitiveness Development Policy Operation (DPO1) Region PROGRAM INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6864 Operation Name First Governance and Competitiveness Development Policy Operation (DPO1) Region AFRICA Sector Central government administration

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA IDA-H0400) ON A CREDIT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA IDA-H0400) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-37720 IDA-37721

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Report No. PID7125 Project Name Argentina-Special Structural Adjustment... Loan (SSAL)

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-92619) ON A FOOD CRISIS RESPONSE DEVELOPMENT POLICY GRANT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-92619) ON A FOOD CRISIS RESPONSE DEVELOPMENT POLICY GRANT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001189 IMPLEMENTATION COMPLETION AND RESULTS

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (SLIDF TF-13246) ON AN IDA GRANT FROM THE SIERRA LEONE INFRASTRUCTURE DEVELOPMENT FUND

IMPLEMENTATION COMPLETION AND RESULTS REPORT (SLIDF TF-13246) ON AN IDA GRANT FROM THE SIERRA LEONE INFRASTRUCTURE DEVELOPMENT FUND Public Disclosure Authorized Document of The World Bank Report No: ICR00004215 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (SLIDF TF-13246) ON AN IDA GRANT FROM THE SIERRA

More information

IRAQ: SECOND EXPENDITURE RATIONALIZATION, ENERGY EFFICIENCY AND STATE-OWNED ENTERPRISE GOVERNANCE PROGRAMMATIC DPF (P161

IRAQ: SECOND EXPENDITURE RATIONALIZATION, ENERGY EFFICIENCY AND STATE-OWNED ENTERPRISE GOVERNANCE PROGRAMMATIC DPF (P161 Public Disclosure Authorized IRAQ: SECOND EXPENDITURE RATIONALIZATION, ENERGY EFFICIENCY AND STATE-OWNED ENTERPRISE MIDDLE EAST AND NORTH AFRICA Iraq Macroeconomics, Trade and Investment Global Practice

More information

FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (LOAN NO 7829-MK, GRANT NO TF096329) FOR

FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (LOAN NO 7829-MK, GRANT NO TF096329) FOR Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00001958 IMPLEMENTATION

More information

State Owned Financial Institutions Reform Project (P156837)

State Owned Financial Institutions Reform Project (P156837) EUROPE AND CENTRAL ASIA Serbia Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2018 Seq No: 2 ARCHIVED on 12-Dec-2018 ISR34752 Implementing Agencies: Republic

More information

Evaluation Approach Paper Project Performance Evaluation Report: Economic Recovery Program in the Maldives (Loans 2597/2598-MLD) August 2017

Evaluation Approach Paper Project Performance Evaluation Report: Economic Recovery Program in the Maldives (Loans 2597/2598-MLD) August 2017 Asian Development Bank. 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org; www.adb.org/evaluation Evaluation Approach Paper Project

More information

Implementation Status & Results Philippines National Program Support for Tax Administration Reform. (P101964)

Implementation Status & Results Philippines National Program Support for Tax Administration Reform. (P101964) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Philippines National Program Support for Tax Administration Reform. (P101964) Operation Name: National

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3279A) ON A CREDIT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3279A) ON A CREDIT Public Disclosure Authorized Document of The World Bank Report No: ICR0000505 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-32790 IDA-3279A)

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 2 ARCHIVED on 18-Nov-2016 ISR25624 Implementing Agencies: National Bank

More information

PROGRAM INFORMATION DOCUMENT (PID) CONCEPT STAGE July 21, 2017 Report No.: MG Public Finance Sustainability and Investment II DPO

PROGRAM INFORMATION DOCUMENT (PID) CONCEPT STAGE July 21, 2017 Report No.: MG Public Finance Sustainability and Investment II DPO Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROGRAM INFORMATION DOCUMENT (PID) CONCEPT STAGE July 21, 2017 Report No.: 120763 Operation

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-4456 and IDA-4994) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$ MILLION EQUIVALENT)

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-4456 and IDA-4994) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$ MILLION EQUIVALENT) Public Disclosure Authorized Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Report No: ICR00003524 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-4456 and IDA-4994)

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650)

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021115 Public Disclosure Authorized Public Disclosure Authorized Project ID P118737 Project Name ENERGY

More information

Document of The World Bank. Report No: ICR IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-83840, IBRD-85220) ON A SERIES OF TWO LOANS

Document of The World Bank. Report No: ICR IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-83840, IBRD-85220) ON A SERIES OF TWO LOANS Public Disclosure Authorized Document of The World Bank Report No: ICR00004253 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-83840, IBRD-85220)

More information

Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions

Key Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions Public Disclosure Authorized AFRICA Africa Water Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 3 ARCHIVED on 27-Jun-2016 ISR22945 Implementing Agencies: Zambezi River Authority

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Project Name Region Sector Project ID Borrower Beneficiaries Implementing Agency Report No. PID10910 India-Andhra Pradesh Economic Reform... Loan/Credit South Asia Poverty Reduction and Economic Management

More information

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL FINANCING LOAN TO THE WITH THE GUARANTEE OF

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL FINANCING LOAN TO THE WITH THE GUARANTEE OF Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

STAFF REPORT FOR THE 2018 ARTICLE IV CONSULTATION DEBT SUSTAINABILITY ANALYSIS. Risk of external debt distress:

STAFF REPORT FOR THE 2018 ARTICLE IV CONSULTATION DEBT SUSTAINABILITY ANALYSIS. Risk of external debt distress: May 24, 218 STAFF REPORT FOR THE 218 ARTICLE IV CONSULTATION DEBT SUSTAINABILITY ANALYSIS Risk of external debt distress: Augmented by significant risks stemming from domestic public and/or private external

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-48290) ON A CREDIT IN THE AMOUNT OF SDR 49.6 MILLION (US$ 74.7 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-48290) ON A CREDIT IN THE AMOUNT OF SDR 49.6 MILLION (US$ 74.7 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-48290) Poverty

More information

Implementation Status & Results Nigeria Nigeria Edo State First Development Policy Operation (P123353)

Implementation Status & Results Nigeria Nigeria Edo State First Development Policy Operation (P123353) Public Disclosure Authorized Public Disclosure Authorized Project Name: Implementation Status & Results Nigeria Nigeria Edo State First Development Policy Operation (P123353) Nigeria Edo State First Development

More information

Energy ACCOUNTABILITY STATEMENT MINISTRY OVERVIEW

Energy ACCOUNTABILITY STATEMENT MINISTRY OVERVIEW Energy ACCOUNTABILITY STATEMENT This business plan was prepared under my direction, taking into consideration the government s policy decisions as of March 3, 2017. original signed by Margaret McCuaig-Boyd,

More information

Mongolia The SCD-CPF Engagement meeting with development partners September 1 and 22, 2017

Mongolia The SCD-CPF Engagement meeting with development partners September 1 and 22, 2017 Mongolia The SCD-CPF Engagement meeting with development partners September 1 and, 17 This is a brief, informal summary of the issues raised during the meeting. If you were present and wish to make a correction

More information

Tariffs and Tariff Design Promoting Access to the Poor

Tariffs and Tariff Design Promoting Access to the Poor Regulation for Practitioners Building Capacity through Participation Tariffs and Tariff Design Promoting Access to the Poor Gloria Magombo Energy Advisor gmagombo@satradehub.org July 27-31, Eskom Convention

More information

Document of The World Bank. IMPLEMENTATION COMPLETION RESULTS REPORT (IDA and IDA-56810) ON TWO DEVELOPMENT POLICY CREDITS

Document of The World Bank. IMPLEMENTATION COMPLETION RESULTS REPORT (IDA and IDA-56810) ON TWO DEVELOPMENT POLICY CREDITS Public Disclosure Authorized Document of The World Bank Report No: ICR00003972 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION RESULTS REPORT (IDA 54180 and IDA-56810)

More information

CALENDAR OF IMPORTANT MONETARY AND ECONOMIC POLICY EVENTS

CALENDAR OF IMPORTANT MONETARY AND ECONOMIC POLICY EVENTS CALENDAR OF IMPORTANT MONETARY AND ECONOMIC POLICY EVENTS 1995 Jan: Effective January 2, the Statutory Minimum Reserve (SMR) Requirement was increased from 12.0 percent to 15.0 percent for all deposit

More information

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report Public Disclosure Authorized AFRICA Africa Environment & Natural Resources Global Practice IBRD/IDA Adaptable Program Loan FY 2009 Seq No: 13 ARCHIVED on 29-Dec-2016 ISR26629 Implementing Agencies: Ministry

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE TRANSPARENCY AND ACCOUNTABILITY CAPACITY BUILDING PROJECT (CREDIT NO.

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE TRANSPARENCY AND ACCOUNTABILITY CAPACITY BUILDING PROJECT (CREDIT NO. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

Document of The World Bank

Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-35380 IDA-35381)

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Public Disclosure Authorized Document of The World Bank Document of The World Bank Public Disclosure Authorized FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Report No: RES22488 Public Disclosure Authorized

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-58084) ON A GRANT IN THE AMOUNT OF US$ 5 MILLION TO THE LEBANESE REPUBLIC FOR THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-58084) ON A GRANT IN THE AMOUNT OF US$ 5 MILLION TO THE LEBANESE REPUBLIC FOR THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR2675 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

PROGRAM-FOR-RESULTS INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.:

PROGRAM-FOR-RESULTS INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROGRAM-FOR-RESULTS INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: 113653 Program

More information

AFRICAN DEVELOPMENT BANK GROUP MADAGASCAR: HIPC APPROVAL DOCUMENT COMPLETION POINT UNDER THE ENHANCED FRAMEWORK

AFRICAN DEVELOPMENT BANK GROUP MADAGASCAR: HIPC APPROVAL DOCUMENT COMPLETION POINT UNDER THE ENHANCED FRAMEWORK AFRICAN DEVELOPMENT BANK GROUP MADAGASCAR: HIPC APPROVAL DOCUMENT COMPLETION POINT UNDER THE ENHANCED FRAMEWORK March 2005 TABLE OF CONTENTS Page I Introduction... 1 II Madagascar s Qualification for the

More information

Annex A. Country Partnership Framework Template. Document of The World Bank Group FOR OFFICIAL USE ONLY

Annex A. Country Partnership Framework Template. Document of The World Bank Group FOR OFFICIAL USE ONLY Annex A. Country Partnership Framework Template Document of The World Bank Group FOR OFFICIAL USE ONLY INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT [AND/OR INTERNATIONAL DEVELOPMENT ASSOCIATION]

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 40280 September 2007 Islamic Republic of Afghanistan: Technical Assistance for Support for Economic Policy Management (Cofinanced by the Government of Australia

More information

Mongolia: Development of State Audit Capacity

Mongolia: Development of State Audit Capacity Technical Assistance Report Project Number: 47198-001 Capacity Development Technical Assistance (CDTA) November 2013 Mongolia: Development of State Audit Capacity The views expressed herein are those of

More information

Draft Terms of Reference. Mozambique Climate Change Technical Assistance Project

Draft Terms of Reference. Mozambique Climate Change Technical Assistance Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 1. Background Context Draft Terms of Reference Mozambique Climate Change Technical Assistance

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Lebanon Social Protection & Labor Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 09-Jan-2017

More information

REQUEST FOR A THREE-YEAR ARRANGEMENT UNDER THE EXTENDED CREDIT FACILITY DEBT SUSTAINABILITY ANALYSIS

REQUEST FOR A THREE-YEAR ARRANGEMENT UNDER THE EXTENDED CREDIT FACILITY DEBT SUSTAINABILITY ANALYSIS May 18, 217 REQUEST FOR A THREE-YEAR ARRANGEMENT UNDER THE EXTENDED CREDIT FACILITY DEBT SUSTAINABILITY ANALYSIS Approved By Dominique Desruelle and Andrea Richter Hume (IMF) and Paloma Anos-Casero (IDA)

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H5770) ON A GRANT

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H5770) ON A GRANT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H5770) ON

More information

January Brunei Darussalam: Development Status

January Brunei Darussalam: Development Status January 213 Brunei Darussalam: Development Status ABBREVIATIONS ADB Asian Development Bank ADF Asian Development Fund GDP gross domestic product GNI gross national income IMF International Monetary Fund

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80640) ON A LOAN IN THE AMOUNT OF US$200 MILLION TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80640) ON A LOAN IN THE AMOUNT OF US$200 MILLION TO THE Public Disclosure Authorized Document of The World Bank Report No: ICR00004191 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80640) ON A LOAN

More information