Capital Cost Overrun and Operational Performance in Mining Industry. Management and Economics Society, CIM Toronto
|
|
- Chester Simpson
- 6 years ago
- Views:
Transcription
1 Capital Cost Overrun and Operational Performance in Mining Industry Management and Economics Society, CIM Toronto Tin Lwin Jose Lazo Technical Advisory Services Export Development Canada May 25, 2016
2 OVERVIEW Project Cost Overruns Operational Performance Production performance Operating cost performance Performance index 2
3 CAPITAL COST OVERRUNS 3
4 BACKGROUND Capital cost overruns (CO) have been endemic and significant. EDC has a significant lending portfolio in mining and metals. As a lender, EDC faced the issue which drove the desire to identify and mitigate potential CO s study identified sources of CO using internal data from 12 projects study characterized attributes of 78 projects with CO using internal and external data. Findings from the studies used to address CO risk. 4
5 2012 STUDY SOURCES OF COST OVERRUNS 8 Frequency (Count of Occurences) Owner's Labour Other Indirects Material Direct Labour Equipment EPCM Labour External Escalation Schedule Scope Changes FX 5 Note: 2012 and 2015 studies use different data sets
6 TAKE AWAYS STUDY Owner s and indirect costs tend to be significantly underestimated. Costs under EPCM scope on average tend to be more or less within expected accuracy level for a feasibility study (i.e. within 15%). Evidence of correlation between capex overruns and commodity prices, but not at the rate of increase in commodity prices. Significant cost overruns are a more recent phenomena. Capex estimates are carried out to feasibility level (AACE 1 Class 3), but stated accuracy levels are higher than AACE s expected accuracy of -20% to +40%. 6 1 AACE International, an industry association for advancement of cost engineering
7 2015 STUDY Purpose: Analyze capital cost overruns in mining projects and relationship to various variables. To compliment the 2012 study on sources of cost overruns. Discover other factors to consider in sizing cost overrun facility. Scope: Study limited to 78 projects: Capex > $ 50 M Started within last 20 years 7
8 CAPEX COST OVERRUNS (CO) 300% Cost Overrruns 250% 200% 150% 100% CO: 37% Budgeted Capex: $1.2 B Actual Capex: $1.6 B Financing: Debt: 57% Equity: 43% 50% 0% % Source: TAS analysis Bubble Size represents Project Size (Capex) Red buble represents Average Project 8
9 COST OVERRUN OVER THE YEARS Average CO = 37% Post 2010 average CO growth rate is showing signs of slowing down after reaching above 40%. 9
10 COST OVERRUN & PROJECT SIZE Average CO = 37% 10
11 COST OVERRUN & COMMODITY TYPE 11
12 BROWNFIELD vs. GREENFIELD PROJECTS 12
13 DEBT VS. EQUITY FUNDING 120% 45% 100% 42% 40% 35% 80% 60% 49% 62% 27% 30% 25% 20% 40% 15% 20% 0% 51% 38% Debt < 50% (22) Debt > 50% (40) Average Equity Average Debt Average CO 10% 5% 0% 13
14 COST OVERRUNS AROUND THE WORLD 14
15 DISTRIBUTION OF PROJECT COST BY REGION Africa 9% Asia 3% South America 47% Australia 25% Europe 1% North America 15% 15
16 TAKE AWAYS 2015 STUDY Average cost overrun 37% Significant increases in cost overruns are recent trend Variables with significant impact: Project Size Project Location Project Sponsor Headquarters Type of commodity Leverage (Debt to Equity Structure) Variables with negligible impact Sponsor Size (Major, Mid Size, Junior) Product Type (Concentrate, Cathode, Doré) Mining Method (Open Pit, Underground) 16
17 CONCLUSION ADOPTED APPROACH 1. Verify that capex estimates are carried out to AACE Class 3 or better. 2. Confirm whether budgeted contingencies are commensurate with level of engineering completed. 3. Undertake comprehensive review of estimates by independent engineer. 4. Recognize that capex estimates are carried out to feasibility level (AACE Class 3), but stated accuracy levels are higher than AACE s expected accuracy of -20% to +40%. 5. Consider factors from 2015 study. 6. Assess points 1 to 5 to gauge potential cost overrun risk in a specific project. 7. Deploy structural features to address potential cost overrun risk - completion guarantee, committed cost overrun funding, conditions to funding, cost-tocomplete test. 17
18 OPERATIONAL PERFORMANCE 18
19 BACKGROUND Projected production and opex performance is a key due diligence area. Earlier study on the subject showed that companies forecasts generally tend to over-estimate production and under-estimate operating costs. Since the dataset was small, expanded the study. Consider whether findings from the expanded study could/should be applied in due diligence. 19
20 DATASET 36 TSX listed gold and copper producers Junior, intermediate and senior producers Production and operating cost figures 6 year period ( ) 338 data points Data source: company s press releases and annual reports 20
21 PRODUCTION PERFORMANCE Production Performance = Actual Production / Company Production Guidance 110% 105% 104% 101% 100% 99% 97% 97% 95% 90% 89% 85% 80%
22 PRODUCTION PERFORMANCE SCATTER PLOT 250% 200% Mean 99% Min 40% Max 211% Std dev 20% 150% 100% 50% 0%
23 PRODUCTION PERFORMANCE BY PRODUCER TYPE 23
24 OPERATING COST PERFORMANCE Opex Performance = Actual Opex / Company Opex Guidance 24
25 OPERATING COST SCATTER PLOT 25
26 KEY SITE OPEX DRIVERS Labour Cost per employee - relatively stable Workforce count potential fluctuation Power Onsite generation potential fluctuation Long term Power Purchase Agreements relatively stable Consumables Potential fluctuation 26
27 IS AVERAGE OPEX PERFORMANCE GETTING BETTER? R 2 (coefficient of determination) between average Opex Performance and WTI:
28 PERFORMANCE INDEX COMBINING PRODUCTION & OPEX PERFORMANCE Performance Index = Production Performance / Opex Performance Criteria <= 0.95 Underachiever Satisfactory >1.0 Overachiever Average 0.99 Min 0.69 Max 1.36 Std dev
29 Questions and Comments? Tin Lwin Managing Principal Technical Advisory Services Jose Lazo Senior Technical Advisor Technical Advisory Services Export Development Canada 150 Slater Street Ottawa, ON Canada K1A 1K3 29
International Gold & Silver Symposium Lima Peru Perspectives on Gold Mining
International Gold & Silver Symposium Lima Peru Perspectives on Gold Mining NICK HOLLAND CEO: GOLD FIELDS 29 May 218 Forward looking statement Certain statements in this document constitute forward looking
More informationAldridge Announces Results for Yenipazar Optimization Study
ALDRIDGE MINERALS INC. 10 King Street East, Suite 300 Toronto, Ontario Canada M5C 1C3 www.aldridgeminerals.ca Aldridge Announces Results for Yenipazar Optimization Study - Pre- Production Capital Costs
More informationInvestor Briefing RIGHT S O L U T I O N S RIGHT PARTNER. Singapore & United Kingdom April Greg Kilmister - CEO
Investor Briefing Singapore & United Kingdom April 2013 Greg Kilmister - CEO RIGHT S O L U T I O N S RIGHT PARTNER IMPORTANT NOTICE AND DISCLAIMER This presentation has been prepared by ALS Limited, (ALS
More informationMining Projects from Discovery to Financing
Mining Projects from Discovery to Financing December 11, 2013 Workshop Financing Mining Projects Embassy of Canada to Germany, Berlin Dirk Sindermann, Vice President Metals & Mining Bank aus Verantwortung
More informationWhy Mines Fail. Presented by: Richard J. Lambert, MBA, P.E., P.Eng. Seeking Better Mining Outcomes in the Next Cycle.
Why Mines Fail Seeking Better Mining Outcomes in the Next Cycle Presented by: Richard J. Lambert, MBA, P.E., P.Eng. March 6, 2017 About RPA Advice to the mining industry for 30 years The specialty firm
More informationFinancing conditions for bankable projects
Financing conditions for bankable projects Within a project finance framework, debt and equity providers will have a number of requirements to make a project bankable. Equity investors will choose how
More information2013 Senior Management Compensation Survey
2013 Senior Management Compensation Survey Attached are the results of the 2013 River Cities Capital Funds Senior Management Compensation Survey. Twenty-four private-growth companies from the IT and healthcare
More informationAfrica Projects February 2016
Africa Projects Cautionary statement Cautionary statement regarding forward looking statements: This presentation contains forward-looking statements within the meaning of Section 27A of the Securities
More informationMajor Drilling Announces Annual and Fourth Quarter Results
NEWS RELEASE Major Drilling Announces Annual and Fourth Quarter Results MONCTON, New Brunswick (June 7, 2018) Major Drilling Group International Inc. (TSX: MDI) today reported results for the year and
More informationMASON GRAPHITE PRESENTS ITS UPDATED FEASIBILITY STUDY ECONOMIC RESULTS FOR THE LAC GUÉRET GRAPHITE PROJECT
MASON GRAPHITE PRESENTS ITS UPDATED FEASIBILITY STUDY ECONOMIC RESULTS FOR THE LAC GUÉRET GRAPHITE PROJECT December 5 th, 2018 Montreal, Quebec, Canada Mason Graphite Inc. ( Mason Graphite or the Company
More informationFor personal use only
20 June 2017 SIANA GOLD PROJECT AND COMPANY UPDATE Key Points Siana Gold Project, Philippines Key milestones achieved with underground development prior to suspension of underground activities: o Combined
More informationStock Symbol: AEM (NYSE and TSX) For further information: Investor Relations (416)
Stock Symbol: AEM (NYSE and TSX) For further information: Investor Relations (416) 947-1212 (All amounts expressed in U.S. dollars unless otherwise noted) AGNICO-EAGLE FILES NEW TECHNICAL REPORT ON GOLDEX
More informationATLANTIC ANNOUNCES STRATEGIC INVESTMENT IN VELOCITY MINERALS LTD.
ATLANTIC ANNOUNCES STRATEGIC INVESTMENT IN VELOCITY MINERALS LTD. January 17, 2019 Canadian dollars unless otherwise noted Vancouver, British Columbia Atlantic Gold Corporation (TSX-V: AGB) ("Atlantic"
More informationInvestor Update July 27, 2004
July 27, 2004 FORWARD LOOKING STATEMENT Certain statements included herein, including those regarding production, costs, development schedules and other statements that express management s expectations
More informationVelocity Hole RDD-009 Intersects New Zone at Rozino Gold Project, Southeast Bulgaria
NR-17-11 October 19, 2017 Velocity Hole RDD-009 Intersects New Zone at Rozino Gold Project, Southeast Bulgaria Highlights include 27.0 metres @ 2.64 g/t gold Vancouver, British Columbia Velocity Minerals
More informationSpanish Mountain Gold Announces Results of New PEA for the First Zone
1120-1095 West Pender Street Vancouver, British Columbia, V6E 2M6 Tel: 604.601.3651 April 10, 2017 Spanish Mountain Gold Announces Results of New PEA for the First Zone VANCOUVER, B.C. Spanish Mountain
More informationFORACO INTERNATIONAL REPORTS Q Increased revenue by 37% and EBITDA by 88% YoY
NEWS RELEASE FORACO INTERNATIONAL REPORTS Q3 Increased revenue by 37% and EBITDA by 88% YoY Toronto, Ontario/Marseille, France November 2,. Foraco International SA (TSX: FAR) (the Company or Foraco ),
More informationOverview & Strategy. Don Lindsay President & CEO
Overview & Strategy Don Lindsay President & CEO Forward Looking Information Both these slides and the accompanying oral presentation contain certain forward-looking statements within the meaning of the
More informationCAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION
International Mine Production LBMA/LPPM Precious Metals Conference 01 Hong Kong November 01 1 CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION Certain information contained or incorporated by reference
More informationPRUDENTAND DISCIPLINED
TSX: YRI NYSE: AUY PRUDENTAND DISCIPLINED TD Securities 2014 Mining Conference January 2014 2 Cautionary Note Regarding Forward-looking Statements CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS:
More informationCOPPER SHINES BRIGHTLY FOR MCEWEN MINING - ENHANCED ECONOMICS OF LOS AZULES
COPPER SHINES BRIGHTLY FOR MCEWEN MINING - ENHANCED ECONOMICS OF LOS AZULES $2.2 Billion After-Tax NPV@8 and IRR of 20. 3.6 Year Payback at $3.00/lb. Copper and 36 Year Mine Life 45 Million lbs. Average
More informationOracle Mining signs indicative term sheet for US$6.5 million secured convertible loan and up to CAD$20 million future project financing
NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES OF AMERICA Oracle Mining Corp. Oracle Mining signs indicative term sheet for US$6.5 million secured convertible
More informationSkouries Update March 2018
Skouries Update March 2018 Cautionary Note About Forward Looking Statements and Information Certain of the statements made and information provided in this presentation are forward-looking statements or
More informationOutlook for Mining Projects
Outlook for Mining Projects John R. Craynon, PhD, PE Senior Mining Engineer VMA Market Outlook Workshop August 3-4, 2017 Disclaimer This presentation, particularly the comments about the domestic mining
More informationFinancial Review of TransCanada and Proposal
Financial Review of TransCanada and Proposal June 10, 2008 1 Discussion Topics Key Findings Financial Strength of TransCanada Financing Review of Proposal 2 Summary of Findings Is the Proposal Base Case
More informationOutlook for Mining Projects
Outlook for Mining Projects John R. Craynon, PhD, PE Senior Mining Engineer VMA Market Outlook Workshop August 3-4, 2017 Disclaimer This presentation, particularly the comments about the domestic mining
More informationFiresteel Resources Inc. and Nordic Mines sign JV agreement for Laiva Mine in Finland
Vancouver, BC, September 11 th, 2017 Trading Symbol: TSX-V: FTR NEWS RELEASE Firesteel Resources Inc. and Nordic Mines sign JV agreement for Laiva Mine in Finland FIRESTEEL RESOURCES INC. (TSX-V: FTR)
More informationMine Latin America November 15, 2013
Mine Latin America November 15, About EDC s export credit agency Develop and expand s international trade Financing and insurance solutions for Canadian exporters and investors Partnership preferred philosophy
More informationFY16 Financial Results Investor Presentation. August 2016
FY16 Financial Results Investor Presentation August 2016 FY16 Results Summary Improvement on FY15 across all key earnings metrics EPS growth and improved shareholder returns Revenue EBITDA PBT EPS Dividend
More informationFirst Quantum (TSE: FM)
Company report First Quantum (TSE: FM) Rating: SELL (PT: CAD 12.38, 30.6% downside) FM is a small player with cost of production right at the industry average Speculative credit rating, high debt balance
More informationTSX: LUN OMX: LUMI Bank of America Merrill Lynch Canada Mining Conference September 2015
TSX: LUN OMX: LUMI Bank of America Merrill Lynch Canada Mining Conference September 2015 Cautionary Statements Caution Regarding Forward-Looking Information This presentation contains forward-looking information,
More informationdiversify our services within the drilling field; be the best in class in safety and human resources; and
2015 ANNUAL REPORT CORPORATE PROFILE Major Drilling Group International Inc., ( the Company ) is one of the world s largest drilling services companies primarily serving the mining industry. To support
More informationHY18 RESULTS PRESENTATION FEBRUARY 2018
PACIFIC ENERGY LIMITED ASX : PEA HY18 RESULTS PRESENTATION FEBRUARY 2018 Important Notice and Disclaimer This presentation has been prepared by (PEA) for information purposes only. This presentation is
More information2017 ETP Fall Forum New York City November 28, 2017 Panel: The Need to Differentiate Among Smart Beta Strategies
2017 ETP Fall Forum New York City November 28, 2017 Panel: The Need to Differentiate Among Smart Beta Strategies Ed Coyne, EVP, National Sales, Sprott Asset Management USA, Inc. (646) 599-0859 / mailto:ecoyne@sprottusa.com
More informationBARRICK GOLD CORPORATION Merrill Lynch Conference Toronto September 16, 2004
FORWARD LOOKING STATEMENT Certain statements included herein, including those regarding production, costs, development schedules and other statements that express management s expectations or estimates
More informationQ4 and Year End 2012 Conference Call. ArgonautGold.com
Q4 and Year End 2012 Conference Call Forward Looking Statement FORWARD LOOKING INFORMATION ALL MONETARY AMOUNTS IN U.S. DOLLARS UNLESS OTHERWISE STATED This document contains certain forward-looking statements
More informationWorkshop on PPP in Roads and Highways
Workshop on PPP in Roads and Highways Vickram Cuttaree, PPP-Coordinator, Europe & Central Asia Member of the Global Expert Team on PPP June 7, 2011 Agenda Rationale for PPP and International Experience
More informationEldorado Gold Reports Results of Technical Studies
NEWS RELEASE TSX: ELD NYSE: EGO March 21, 2018 Eldorado Gold Reports Results of Technical Studies VANCOUVER, BC Eldorado Gold Corporation, ( Eldorado or the Company ) today announces the release of three
More informationGlobal Nature of the Mining Industry and the Role of International Reporting Standards
Global Nature of the Mining Industry and the Role of International Reporting Standards Harry Parker, Chairperson CRIRSCO Astana Mining and Metallurgy Congress Astana, Kazakhstan 15 June 2016 Abstract The
More informationTHE MINERAL EXPLORATION INDUSTRY An Introduction
THE MINERAL EXPLORATION INDUSTRY An Introduction April 24, 2017 Kuujjuaq Workshop Kuujjuaq Workshop, April 2016 Forward-Looking Information Disclaimers and Cautionary Statements: The information contained
More informationThe Relative Strength of Industries and Countries in Emerging Markets
Global Market Report The Relative Strength of Industries and Countries in Emerging Markets A Case Study Using the Barra Emerging Markets Equity Model (EMM1) Jose Menchero and Zoltán Nagy jose.menchero@
More informationCapstone Mining 2017 Production Results and 2018 Operating and Capital Guidance
Suite 2100 510 West Georgia Street Vancouver, BC, V6B 0M3, Canada Tel: 604-684-8894 Fax: 604-688-2180 www.capstonemining.com January 10, 2018 Capstone Mining 2017 Production Results and 2018 Operating
More informationFORACO INTERNATIONAL REPORTS Q Revenue still low but increased tendering activity
NEWS RELEASE FORACO INTERNATIONAL REPORTS Q2 2016 Revenue still low but increased tendering activity Toronto, Ontario / Marseille, France Tuesday, August 2, 2016. Foraco International SA (TSX:FAR) (the
More informationFor personal use only
INDEPENDENCE GROUP NL PETER BRADFORD, MANAGING DIRECTOR AND CEO Australian Nickel Conference 20 October 2016 Cautionary statements & disclaimer This presentation has been prepared by Independence Group
More informationThe New Leader in Global Copper. June, 2013
The New Leader in Global Copper June, 2013 Cautionary Note Regarding Forward-Looking Statement Certain statements and information contained in this presentation, including all statements that are not historical
More informationPresident s Report to Shareholders Second Quarter 2018
President s Report to Shareholders Second Quarter 2018 During the quarter, the Company generated revenue of $88.0 million, up 10.1% from $79.9 million recorded in the same quarter last year. Net loss was
More informationStrategies for Evolving Market Conditions Mines and Money Conference & Exhibition March 2013, Hong Kong
Strategies for Evolving Market Conditions Mines and Money Conference & Exhibition 20-22 March 2013, Hong Kong Greg Robinson Managing Director and Chief Executive Officer Disclaimer Forward Looking Statements
More informationCompany Announcements Office. PNG Chamber of Mines and Petroleum Mining Seminar Wafi-Golpu Joint Venture
LEVEL 9 600 ST KILDA ROAD MELBOURNE VICTORIA 3004 AUSTRALIA To: Company Announcements Office From: Peter Larsen Date: 6 December 2013 PO BOX 6213 ST KILDA ROAD CENTRAL MELBOURNE 8008 Subject: PNG Chamber
More informationTrade Finance Fixed Income Strategy
Trade Finance Fixed Income Strategy Highlights Attractive, floating rate returns Diversifies portfolios to reduce reliance on traditional performance drivers Potential for higher absolute returns versus
More information29, 2018 ( ) (TSX, NYSE
PRESS RELEASE ASANKO GOLD TO RECEIVE US$185 MILLION FROM GOLD FIELDS FOR 50% JOINT VENTURE INTEREST AND US$17.6 MILLION FOR 9.9% PRIVATE PLACEMENT IN ASANKO GOLD Vancouver, British Columbia, March 29,
More informationNEWS RELEASE. Resources at Galat Sufar South ( GSS ), in-pit and outside current design, continue to increase
Orca Gold Inc. 2000-885 West Georgia St. Vancouver, B.C., V6C 3E8, Canada Tel: +1 604 689 7842 Fax: +1 604 689 4250 NEWS RELEASE Orca Gold Drills 123 m at 1.96 g/t Au and 12.0 m at 8.36 g/t Au and Proves
More informationFundamentals of Capital Cost Estimating A TCM approach. Lou Vidotto Managing Director of Vidotto Group
Fundamentals of Capital Cost Estimating A TCM approach Lou Vidotto Managing Director of Vidotto Group Contents 1. Background; 2. Introduction; 3. Total Cost management; 4. Types of Estimates; 5. WBS and
More informationFORACO INTERNATIONAL REPORTS Q2 2017
NEWS RELEASE FORACO INTERNATIONAL REPORTS Q2 2017 Toronto, Ontario / Marseille, France Tuesday, August 1, 2017. Foraco International SA (TSX:FAR) (the Company or Foraco ), a leading global provider of
More informationVelocity Announces C$9M Strategic Investment by Atlantic Gold
NR-19-02 January 17, 2019 Velocity Announces C$9M Strategic Investment by Atlantic Gold NOT FOR DISTRIBUTION TO UNITED STATES NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES Vancouver, B.C
More informationMcEWEN MINING REPORTS 2015 FIRST QUARTER OPERATING & FINANCIAL RESULTS
McEWEN MINING REPORTS 2015 FIRST QUARTER OPERATING & FINANCIAL RESULTS TORONTO, ONTARIO - (May 11, 2015) - McEwen Mining Inc. (NYSE: MUX) (TSX: MUX) is pleased to report our financial results for the three
More informationCenturion Asset Management Income, Stability & Growth
Centurion Asset Management Income, Stability & Growth Who We Are Based in Toronto, Centurion Asset Management Inc. is a Canadian company that owns and manages approximately $1B in total assets. Multi-Residential
More informationVelocity Extends East Zone Discovery at Rozino Gold Project, Southeast Bulgaria
NR 18 02 February 5, 2018 Velocity Extends East Zone Discovery at Rozino Gold Project, Southeast Bulgaria Mineralization Remains Open for Further Expansion Vancouver, British Columbia Velocity Minerals
More informationDeveloping a Diversified Minerals Portfolio Investor Presentation August 2017
1 Developing a Diversified Minerals Portfolio Investor Presentation August 2017 2 Important Notices This presentation has been prepared by BC Iron Limited ABN 21 120 646 924 ( BCI ). This document contains
More informationConstruction and Mining Technique
Construction and Mining Technique Atlas Copco Capital Markets Day, December 2, 2008 Björn Rosengren, Business Area President Atlas Copco Capital Markets Day, December 2, 2008 Construction and Mining Technique
More informationPresident s Report to Shareholders First Quarter 2019
President s Report to Shareholders First Quarter 2019 During the quarter, the Company generated revenue of $98.5 million, up 17% from the $84.0 million recorded for the same quarter last year. Net loss
More informationFortuna reports consolidated financial results for full year 2018 (All amounts expressed in US dollars, unless otherwise stated)
Fortuna reports consolidated financial results for full year 2018 (All amounts expressed in US dollars, unless otherwise stated) Vancouver, March 13, 2019: Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI)
More informationThe Case for a Greenfields Renaissance
The Case for a Greenfields Renaissance J.M.A. Hronsky, B. J. Suchomel, and J.F. Welborn The collapse in commodity prices in the latter half of 2008, triggered by the Global Financial Crisis, heralded a
More informationDetour Gold Achieves Production and Cost Guidance for 2017 and Provides 2018 Guidance
January 16, 2018 NEWS RELEASE Detour Gold Achieves Production and Cost Guidance for 2017 and Provides 2018 Guidance Detour Gold Corporation (TSX: DGC) ( Detour Gold or the Company ) today announces fourth
More informationBank of America Merrill Lynch 2014 Global Metals, Mining & Steel Conference
Bank of America Merrill Lynch 2014 Global Metals, Mining & Steel Conference TSX: YRI NYSE: AUY Cautionary Note Regarding Forwardlooking Statements CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS:
More informationArgonaut Gold Announces Updates on the Magino and San Agustin Projects. Magino Metallurgical Column Test Work Shows Results of up to 70% Recovery
Argonaut Gold Announces Updates on the Magino and San Agustin Projects Magino Metallurgical Column Test Work Shows Results of up to 70% Recovery The San Agustin Preliminary Economic Assessment Results
More informationArgonaut Gold Announces Q2 Production of 29,237 Gold Equivalent Ounces. Cash Balance Increases to $54.1 Million. 2 nd Quarter.
Argonaut Gold Announces Q2 Production of 29,237 Gold Equivalent Ounces Cash Balance Increases to $54.1 Million Toronto, Ontario (July 14, 2016) Argonaut Gold Inc. (TSX: AR) ( Argonaut, Argonaut Gold or
More informationABACUS MINING & EXPLORATION CORPORATION (An exploration stage company) Management s discussion & analysis. For the period ended March 31, 2012
ABACUS MINING & EXPLORATION CORPORATION (An exploration stage company) Management s discussion & analysis For the period ended March 31, 2012 May 29, 2012 The following management s discussion and analysis
More informationCORPORATE PRESENTATION Lima, August 2015 Q & A
CORPORATE PRESENTATION Lima, August 2015 Q & A Disclaimer The information contained in this presentation concerning projections may be deemed to include statements which constitute forward-looking statements
More informationHudbay Announces 2016 Production Guidance and Capital and Exploration Expenditure Forecasts
Hudbay Announces 206 Production Guidance and Capital and Exploration Expenditure Forecasts Summary (all amounts are in US dollars, unless otherwise noted) 205 production of all key metals was within guidance
More information2018 FIRST QUARTER RESULTS. May 3, 2018
2018 FIRST QUARTER RESULTS May 3, 2018 CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS 2 CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS: This presentation contains or incorporates by reference
More informationCRR IV - Article 194 CRR IV Principles governing the eligibility of credit risk mitigation techniques legal opinion
CRR IV - Article 194 https://www.eba.europa.eu/regulation-and-policy/single-rulebook/interactive-single-rulebook/- /interactive-single-rulebook/article-id/1616 Must lending institutions always obtain a
More information2017 AGM PRESENTATION NOVEMBER 2017
PACIFIC ENERGY LIMITED ASX : PEA 2017 AGM PRESENTATION NOVEMBER 2017 Important Notice and Disclaimer This presentation has been prepared by (PEA) for information purposes only. This presentation is not
More informationPresident s Report to Shareholders Second Quarter 2019
During the quarter, demand for our services continued to grow in all of our regions. Despite the recent drop in commodity prices, most senior mining companies are continuing with their original plans as
More informationCONDOR GOLD. Mines and Money Conference. 1 st to 3 rd December 2015 CONDOR GOLD PLC
CONDOR GOLD Mines and Money Conference 1 st to 3 rd December 2015 DISCLAIMER This written presentation (the "Slides") has been prepared by Condor Gold plc (the "Company"). The Slides are the sole responsibility
More informationBuilding value for shareholders
Annual Meeting of Shareholders MAY 3, 2016 Building value for shareholders Strong production, financial strength, underground preparation Forward-looking statements This presentation includes certain forward-looking
More informationPRIMERO ANNOUNCES $75 MILLION TERM LOAN REFINANCING AND ORGANIZATIONAL REVIEW
PRIMERO ANNOUNCES $75 MILLION TERM LOAN REFINANCING AND ORGANIZATIONAL REVIEW (Please note that all dollar amounts in this news release are expressed in U.S. dollars unless otherwise indicated.) Toronto,
More informationEBRD Mining Investments Invest Mongolia London, June Eric Rasmussen Director Natural Resources
EBRD Mining Investments Invest Mongolia London, June 2018 Eric Rasmussen Director Natural Resources Mining sector importance for the economies of EBRD Countries of Operations (COOs) Countries with high
More informationPrice discovery in battery raw materials A news-based perspective
Price discovery in battery raw materials A news-based perspective Barbara O Donovan, Industrial Minerals Advanced Automotive Battery Conference Mainz 2017 Agenda 1.Industrial Minerals: Price discovery
More informationImportant Information
Important Information The information contained in this presentation is intended solely for your personal reference and may not be reproduced, redistributed or passed on, directly or indirectly, to any
More informationFORACO INTERNATIONAL S.A. MANAGEMENT S DISCUSSION & ANALYSIS
FORACO INTERNATIONAL S.A. MANAGEMENT S DISCUSSION & ANALYSIS Three-month and nine-month periods ended September 30, 2018 FORACO INTERNATIONAL S.A. MANAGEMENT S DISCUSSION AND ANALYSIS The following Management
More informationCONSOLIDATED EARNINGS RELEASE
COMPAÑIA MINERA MILPO CONSOLIDATED EARNINGS RELEASE THIRD QUARTER 2017 1 This report analyzes the most important operating and financial results related to the development of Compañía Minera Milpo SAA
More informationA LEADING DIVERSIFIED MID-TIER MINER
A LEADING DIVERSIFIED MID-TIER MINER SECOND QUARTER 2018 RESULTS WEBCAST JULY 27, 2018 TSX & NYSE NSU FORWARD LOOKING STATEMENT This Presentation contains forward-looking statements or forward-looking
More information2017 INVESTOR PRESENTATION SEPTEMBER 2017
PACIFIC ENERGY LIMITED ASX : PEA 2017 INVESTOR PRESENTATION SEPTEMBER 2017 Important Notice and Disclaimer This presentation has been prepared by (PEA) for information purposes only. This presentation
More informationAcacia Mining plc (formerly African Barrick Gold plc) LSE: ACA. ( Acacia or the Company ) Approval of Gokona Underground project at North Mara
27 November 2014 Acacia Mining plc (formerly African Barrick Gold plc) LSE:ACA ( Acacia or the Company ) Approval of Gokona Underground project at North Mara Total production of 450,000 ounces over a 5
More informationIluka Resources Limited
Iluka Resources Limited Iluka Getting Set In The Cycle TZMI Congress 2016 Matt Blackwell - Head of Marketing Hong Kong, 8 November 2016 Disclaimers Forward Looking Statements Slide 24 Important Notice
More informationAlbourne Update Real Assets SDCERA Board of Retirement. February 20 th 2014
Albourne Update Real Assets SDCERA Board of Retirement February 20 th 2014 Agenda 1) Program History 2) Current allocation vs. targets 3) Portfolio composition 4) Performance 5) Future Pacing 6) Market
More informationBank of America-Merrill Lynch 18th Annual Canada Mining Conference
Bank of America-Merrill Lynch 18th Annual Canada Mining Conference September 6, 2012 CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION Certain information contained or incorporated by reference in this
More informationHIGHLIGHTS DETAILS. Commenting on the new discovery, Hugh Stuart, President and Director of Orca Gold, said Our aim in Côte 1 O r c a G o l d I n c.
Orca Gold Inc. 2000-885 West Georgia St. Vancouver, B.C., V6C 3E8, Canada Tel: +1 604 689 7842 Fax: +1 604 689 4250 NEWS RELEASE Orca Gold Discovers Significant 8km x 1km Soil Anomaly on its 100%-owned
More informationMajor Drilling Reports First Quarter Results for Fiscal 2019
NEWS RELEASE Major Drilling Reports First Quarter Results for Fiscal 2019 MONCTON, New Brunswick (September 4, 2018) Major Drilling Group International Inc. (TSX: MDI) today reported results for its first
More information15, 2007 YAMANA GOLD INC. MERIDIAN GOLD INC.
NEWS RELEASE YAMANA GOLD S TENDER OFFER FOR MERIDIAN GOLD SUCCESSFULLY ACCEPTED BY SHAREHOLDERS; YAMANA AND MERIDIAN PROVIDE COMBINED THIRD QUARTER OPERATIONAL HIGHLIGHTS Toronto, Ontario, October 15,
More informationTRI-RIVER VENTURES INC. Management s Discussion and Analysis Period Ended March 31, 2015
TRI-RIVER VENTURES INC. Management s Discussion and Analysis Period Ended March 31, 2015 MANAGEMENT S DISCUSSION AND ANALYSIS The following Management Discussion and Analysis ( MD&A ) of ( Tri-River or
More informationCorporate Presentation Winter 2017 TSX-V: RRI OTC: RVSDF Frankfurt: R99
Corporate Presentation Winter 2017 TSX-V: RRI OTC: RVSDF Frankfurt: R99 DISCLAIMER Forward-Looking Statements This document contains forward-looking statements and factual information that are current
More informationHedging Sales Revenue by Commodity Production
Hedging Sales Revenue by Commodity Production By: Andrew Volz, Solutions Consultant, Reval April 8, 2010 CONTENT Executive Summary Introduction Life Cycle of the Producer Evaluate the Ability to Hedge
More informationQ Conference Call August 15, 2012 HBM
Creating sustainable value through high quality, long-life deposits Q2 2012 Conference Call August 15, 2012 HBM Forward Looking Information This presentation contains forward-looking statements and forward-looking
More informationIPD PAN EUROPEAN QUARTERLY TRANSACTION LINKED INDICATORS
IPD TRANSACTION LINKED INDICATORS IPD PAN EUROPEAN QUARTERLY TRANSACTION LINKED INDICATORS April 2015 APRIL 2015 CONTENTS IPD Pan European Quarterly Transaction Linked Indicators... 3 IPD Transaction Linked
More informationRoyal Gold Announces Acquisition of High-Quality Silver Stream on Khoemacau Copper Project
Royal Gold Announces Acquisition of High-Quality Silver Stream on Khoemacau Copper Project DENVER, COLORADO. FEBRUARY 25, 2019: ROYAL GOLD, INC. (NASDAQ: RGLD) (together with its subsidiaries, Royal Gold
More informationVOLUNTARY GUIDELINES FOR FUND MANAGERS REGARDING FUND VOLATILITY RISK CLASSIFICATION
VOLUNTARY GUIDELINES FOR FUND MANAGERS REGARDING FUND VOLATILITY RISK CLASSIFICATION June 2016 Data Updated to December 31, 2015 IMPORTANT NOTICE TO FUND MANAGERS AND DEALERS: The following voluntary guidelines
More informationMEDIA RELEASE OCEANAGOLD TO ACQUIRE ROMARCO CREATING THE LOWEST COST GOLD PRODUCER GLOBALLY
MEDIA RELEASE 30 July 2015 OCEANAGOLD TO ACQUIRE ROMARCO CREATING THE LOWEST COST GOLD PRODUCER GLOBALLY (MELBOURNE) and (TORONTO) OceanaGold Corporation (TSX/ASX/NZX: OGC) ( OceanaGold ) and Romarco Minerals
More information2011 Senior Management Compensation Survey
2011 Senior Management Compensation Survey www.rccf.com 221 East 4 th Street, Suite 2400, Cincinnati, Ohio 45202 (513) 621-9700 Attached are the results of the 2011 River Cities Capital Funds Senior Management
More informationBRINGING TOGETHER CHINESE AND INTERNATIONAL MINING EXPERTISE
1208:HK MINES & MONEY BEIJING, JUNE 2012 BRINGING TOGETHER CHINESE AND INTERNATIONAL MINING EXPERTISE DAVID LAMONT, CHIEF FINANCIAL OFFICER Disclaimer The information contained in this presentation is
More information