1 EnPe application form Instructions Saving an application form in progress and sharing the form between partners This application form has 15 pages. On each page, there is an option to save what has been entered in the form so far in order to continue later. This means that the form does not need to be completed in one sitting or by one individual, but may be worked on in increments and shared by several partners. The save option is found at the very top of each page. Clicking it will allow you to enter your e- mail address to receive a unique link to the specific form you have been working on. This link may later be opened by yourself or your partner for review or further work. You will need to forward this specific link to your partner in order to allow them to open your common application. Where to find resource documents In this application, reference is made to several EnPe templates, guidelines and background documents. These may be found and downloaded from NTNU's EnPe web pages. Among these are EnPe guidelines Budget document template Implementation plan template Questions or technical issues If you encounter any problems or technical issues filling in the application form, please contact the EnPe secretariat at enpe@adm.ntnu.no for support. 1

2 A. Basic project information Project title and synopsis This descriptions of the project will be used to present the application for the EnPe board, on the web site and in other relevant fora. Max. 100 words. 2

3 B. Project partners 1/4 Partner institution in LMIC Name: Postal address: Institutional responsible: Central coordinating unit: Accreditation: Department: Head of department name: Head of department contact details: Project coordinator name: Project coordinator contact details: Project coordinator e- mail address: CV/resumé - project coordinator LMIC Please select file to upload from your desktop. CV/resumé must not exceed 1 - one - page. File size is limited to 2 MB. 3

4 B. Project partners 2/4 Partner institutions in Norway (UiN) Name: Postal address: Institutional responsible: Central coordinating unit: Accreditation: Department: Head of department name: Head of department contact details: Project coordinator name: Project coordinator contact details: Project coordinator e- mail address: CV/resumé - project coordinator UiN Please select file to upload from your desktop. CV/resumé must not exceed 1 - one - page. File size is limited to 2 MB. 4

5 B. Project partners 3/4 Additional partner (if relevant in the project application) Name: Postal address: Institutional responsible: Central coordinating unit: Accreditation: Department: Head of department name: Head of department contact details: Project coordinator name: Project coordinator contact details: CV/resumé - project coordinator additional partner Please select file to upload from your desktop. CV/resumé must not exceed 1 - one - page. File size is limited to 2 MB. 5

6 B. Project partners 4/4 Which partner institution will be lead partner in the project? ( ) Partner institution in LMIC ( ) Partner institution in Norway Division of responsibility and labour between institutions Please fill in description according to guidelines Cooperation: Existing cooperation between the applying institutions Other relevant international cooperation at the institutions Have the partners previously received support from Norad or EnPe programmes? If yes, please describe. 6

7 Reasons for choice of a Norwegian lead partner (Dependent on answer of first question on page B. 4/4) Reasons for choice of a Norwegian lead partner According to EnPe guidelines, it is strongly recommended to designate the partner institution in the LMIC as lead partner in the project unless there are specific challenges related to this. Please state the reasons for choosing the Norwegian partner institution as lead partner in this project application. What capacity building elements does the project intend to initiate to meet the identified challenges in the LMIC institution(s)? 7

8 C. Project information Project description Relevance of the proposed project Please describe the relevance of the project to the country and its development goals. Maximum 300 words. Synergy with other activities/projects Maximum 100 words. Gender Please describe how the project will approach issues of gender and the goal of gender equality, including the identification of a Gender Focal Point, who must be a member of the project management team. Maximum 100 words. 8

9 D. Results framework Project vision/development impact on society The vision of the project should describe the long term desired impact of the EnPe project, in terms of sustainable economic, social and environmental development in the country. The vision should be formulated as an answer to the following question: What impact will the project have on society in 2050? Project goal/overall purpose of project The project goal should describe the overall purpose of the project. The goal should be set in terms of the effect that the project will have achieved for its target groups and target areas in the year ANALYSIS OF PROJECT OUTCOMES Project outcomes/intended effects of project The outcomes should be a limited set of positive changes that will be stimulated by the implementation of the project. This set of positive changes are the effects that will combine to achieve the project goal (described above). Formulation of outcome Indicator(s) Outcome 1 Outcome 2 Outcome 3 Outcome 4 Outcome 5 Risks and assumptions tied to the project outcomes 9

10 Mitigation of risks tied to the project outcomes Indicators of the outcomes: Baseline and target The indicators of the outcomes of the project (see table above) should be realistic and measurable. The baseline values describes the present situation as a basis for measuring change of the indicators towards their target values. Thereby the progress towards achieving the outcomes of the project will be assessed. Baseline value(s) Means of verification Target(s) in final year Pertains to indicators of outcome 1 (see table above) Pertains to indicators of outcome 2 Pertains to indicators of outcome 3 Pertains to indicators of outcome 4 Pertains to indicators of outcome 5 10

11 ANALYSIS OF PROJECT OUTPUTS Project outputs/expected results, services or products The outputs of the project should describe the concrete results of the activities of the project. The outputs are the single components that contribute towards the outcomes of the project (see above). The outputs should be to some extent measurable results, services or product of the activities. Examples could be tangible deliverables like manuals written or number of students graduated, or less tangible outputs like increase of knowledge or experience. Number of students enrolled and graduated are relevant to enter as outputs here. You will also be requested to provide more details on these aspects further down on this page. Contributes to outcome no. (select 1-5) Formulation of output Indicator Output 1 Output 2 Output 3 Output 4 Output 5 Output 6 Output 7 Output 8 Output 9 Output 10 Risks and assumptions tied to the project outputs* Mitigation of risks tied to the project outputs* 11

12 Indicators of the outputs: Baseline and target The indicators of the outputs of the project (see table above) should be realistic and measurable. The baseline values describes the present situation as a basis for measuring change of the indicators towards their target values. Thereby the progress towards achieving the outputs will be assessed. Baseline value Means of verification Target in final year Pertains to indicators of output 1 (in table above) Pertains to indicators of output 2 Pertains to indicators of output 3 Pertains to indicators of output 4 Pertains to indicators of output 5 Pertains to indicators of output 6 Pertains to indicators of output 7 Pertains to indicators of output 8 Pertains to indicators of output 9 Pertains to indicators of output 10 12

13 PROJECT ACTIVITIES Planned project activities/implementation plan The planned project activities should be the steps that the project will take to produce the planned outputs. This is for instance where the arrangement of a workshop or a course should be listed, while the output of that activity, for instance attainment of necessary competence, should be listed under outputs. Contributes to output no. Main activity Input Responsible partner Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 Activity 6 Activity 7 Activity 8 Activity 9 Activity 10 Activity 11 Activity 12 Activity 13 Activity 14 Activity 15 Activity 16 Activity 17 Activity 18 Activity 19 Activity 20 13

14 Risks and assumptions tied to the project activities Mitigation of risks tied to the project activities Schedule of enrollment and graduation of students and PhD candidates Please provide the planned number of students entered into master programmes, planned number of PhD candidates and planned number of students who will have graduated, year by year. Not applicabl e Number of enrolled master students Number of PhD candidates Number of graduated master students [ ] [ ] [ ] Upload of implementation plan* The implementation plan/implementation schedule will consist of all the project activities, listed in detail, by year, with responsibilities and budgets given. Such an implementation plan should be drawn up in a separate document to be uploaded here. It is recommended to consult the implementation plan template found on the EnPe website. It could be used in itself as a template or as guidance to what kind of content and setup the plan should contain. Size is limited to 2mb. 14

15 E. Assessment of sustainability, cross cutting issues, risk factors and mitigation measures Assessment of how the project relates to the strategic plans and priorities of national and partner institutions (in countries where capacity will be developed) Assessment of institutional capacity of partner institutions, including risk factors Assessment of financial management and corruption (refer to partnership assessment if relevant) Please see the guidelines for more information. Assessment of gender equality in the project implementation and the expected results Please see the guidelines for more information. Assessment of conflict sensitivity For projects to be implemented in countries or areas where there is an ongoing conflict or where such a conflict has recently ended, and in cases where there is a high probability that a violent conflict may break out. Assessment of human rights Assessment of issues concerning human rights and inclusion of marginalized groups that may be of relevance to the project. 15

16 Assessment of environmental and climate sustainability Identification of other risk factors and management of identified risks Plans for students after graduation What plans does the project have to ensure that the students will be able to put their education to optimal use after graduation? 16

17 F. Financing and budget Upload of budget file Please upload the budget file(s) for the project application here. Please consult EnPe budget template for guidelines on required content and preferred setup. Comments to the budget Please refer to the guidelines and make specific comments regarding the following sections in the budget. Education Salaries Scholarships Publication & dissemination Travel expenses Gender mainstreaming Research and PhD Salaries Fellowships Publication & dissemination Research expenses Travel expenses Gender mainstreaming Institutional development Salaries techn. & adm. staff Travel expenses techn. & adm. staff Courses Consultancies ICT Scientific equipment Infrastructure Gender Project management Salary compensation Costs annual meeting Annual external audit Consultancy Comments 17

18 Other collaborative activities Administrative support Additional financing Please fill in description according to guidelines. Own funding Please fill in description according to guidelines. 18

19 G. Date and confirmation I confirm that the information contained in this application is correct to the best of my knowledge. I hereby commit to participate in EnPe evaluations irrespective of whether the application will receive funding or not. Agreement partner Place and date: Name: Title: Online signature with mouse or touchpad Norwegian partner Place and date: Name: Title: Online signature with mouse or touchpad LMIC partner Place and date: Name: Title: Online signature with mouse or touchpad 19

20 H. Assessment of institutional capacity of lead partner in LMIC This assessment shall be performed only if the partner in the LMIC is designated as the lead partner of the project. This assessment shall be performed jointly by future partner institutions during the preparation of an EnPe project. It should provide basic information about the existing institutional capacity of a partner in the LMIC for the purpose of assessing whether this partner will be able to carry the responsibility as contractual partner with Norad and act as the lead partner in the project. Furthermore it will assist in identifying what capacities will need strengthening with regards to financial and administrative management through the EnPe project in order to maximize the outcomes and impact of the project and ensure smooth project management. Please answer the questions and provide further information to explain and comment on the given topics. You are also encouraged to identify areas that are weak and need to be strengthened as part of the implementation plan for the EnPe project. We encourage you also infrom about major uncertainties. Institutional structure and legal framework Description/comments Areas in need of strengthened capacity What is the legal status of the Higher Education Institution (HEI) - official registration/accreditation? Does the partner institution have the authority to enter into legal agreements with other partners? Does the partner institution have the authority to enter into legal agreements with other partners? Project management and reporting capacity Description/comments Areas in need of strengthened 20

21 capacity Does the project partner have sufficient administrative capacity to manage the project, inlcuding reporting capacity (financial and narrative)? Financial management and control Description/ comments Areas in need of strengthened capacity Flow of funds: Can the HEI receive and transfer funds? Does the HEI have the necessary mechanisms to transfer funds to other partners in South and to track the use of funds? What is the annual budget and what are the various financing sources of the HEI? Are there kept separate accounts for each project? Does the HEI receive funding from the government? How are scholarship funds distributed? (Process: announcement, decision making, distribution). What are the eligibility criteria (subjects/genders/social origin)? Financial reporting and monitoring: What is the sequence of financial reporting and who approves this (Board/Council/Chief of Finance or others)? Financial policies and procedures: Are financial policies and procedures in place and do they adhere to/build on national regulations? Control mechanisms: are controls in place concerning the preparation and approval of budget and transactions, ensuring that transactions are independently checked, reviewed and approved by an authorized person? Is there a segregation of duty between the 21

22 accounting and the handling of cash? Procurement and assets: Are there procurement procedures in place and is there adequate segregation of duties? Is there a system of adequate safeguards to protect assets? Are there periodic physical inventories of fixed assets? Information systems: What accounting systems are in place? Are these systems computerized? If not, what system is used? Can the system produce the necessary financial reports? Audit: Is the HEI financial statement audited regularly by an independent auditor or by the State Auditor? Who is the auditor? Is the audit of the HEI conducted according to the International Standards on Auditing? Is a Management Letter issued by the auditor annually? Does the Board/Council respond to it? (If audit is performed by State Auditor, there is no need for a Management Letter) Financial irregularities: What systems and routined are in place to disclose and report on financial irregularities such as conflicts of interest and corruption? Does the HEI have guidelines on how to deal with suspicion of financial irregularities and corruption? Please explain. If your project is considered for funding under EnPe main call, you may be required to make available the following documents (not limited to): 1. Governance structure and procedures 2. Copy of Board's/Council's most recent financial report and minutes of last meeting 3. Financial management regulations including the procurement guidelines and schemes of delegated authority in financial management for the HEI 4. Documentation showing clear division of responsibilites in financial management execution (internal procedures) 5. The accounting regulations for the HEI and documentation of segregation of duty between accounting and handling of cash (internal procedures) 6. Copy of last financial year's audit for the entire HEI 7. Copy of last financial year's Management letter to the HEI, with response from the management of the HEI 22

23 Letter of Commitment and other uploads Upload of Letter of Commitment Please see EnPe web pages for Letter of Commitment template. The Letter should be signed by all parties, scanned and uploaded here. If you do not have a completed Letter of Commitment when filling in this application, please make sure that a fully signed Letter of Commitment is sent to the EnPe secretariat at enpe@adm.ntnu.no within three weeks after the application deadline. Additional uploads Please use this page to upload any additional documents that are of relevance to the application and that you wish to include. Up to 5 files may be included. File size limit per file is 1mb. Review and download Application form completed 23

Oil for Development in South Sudan. Program Document for an Institutional Cooperation between

Oil for Development in South Sudan. Program Document for an Institutional Cooperation between Oil for Development in South Sudan Program Document for an Institutional Cooperation between The Ministry of Petroleum and Mining, Republic of South Sudan and The Ministry of Petroleum and Energy, Norway

More information

WSSCC, Global Sanitation Fund (GSF)

WSSCC, Global Sanitation Fund (GSF) Annex I WSSCC, Global Sanitation Fund (GSF) Terms of Reference Country Programme Monitor (CPM) BURKINA FASO 1 Background The Water Supply and Sanitation Collaborative Council (WSSCC) was established in

More information

UKF Project Monitoring Guidelines Version 4

UKF Project Monitoring Guidelines Version 4 REPUBLIC OF CROATIA MINISTRY OF SCIENCE, EDUCATION AND SPORTS UKF Project Monitoring Guidelines Version 4 UNITY THROUGH KNOWLEDGE FUND office@ukf.hr, www.ukf.hr, +385 1 2352 685 Planinska 1, HR-10000 Zagreb,

More information

PROJECT IMPLEMENTATION DOCUMENT NO.2 REPORTING TEMPLATES & E-TOOL

PROJECT IMPLEMENTATION DOCUMENT NO.2 REPORTING TEMPLATES & E-TOOL Establishing the European Geological Surveys Research Area to deliver a Geological Service for Europe PROJECT IMPLEMENTATION DOCUMENT NO.2 REPORTING TEMPLATES & E-TOOL Joint Call on applied geoscience

More information

Guideline for strengthened bilateral relations. EEA and Norway Grants

Guideline for strengthened bilateral relations. EEA and Norway Grants Guideline for strengthened bilateral relations EEA and Norway Grants 2009 2014 Adopted by the Financial Mechanism Committee 29.03.2012, amended on 28 January 2016 Contents 1 Purpose of the guideline...

More information

Annex 2 Template for MoU Norwegian Financial Mechanism

Annex 2 Template for MoU Norwegian Financial Mechanism Regulation on the implementation of the Norwegian Financial Mechanism 2009-14 Annex 2 Template for MoU Annex 2 Template for MoU Norwegian Financial Mechanism 2009-2014 MEMORANDUM OF UNDERSTANDING ON THE

More information

Building Stronger Universities

Building Stronger Universities Building Stronger Universities Platform for Stability, Democracy & Rights Inception Report TABLE OF CONTENTS Table of Contents... 1 List of Abbreviations... 2 1. Background... 3 2. Recommendations and

More information

Office of the Auditor General of Norway. Handbook for the Office of the Auditor General s Development Cooperation

Office of the Auditor General of Norway. Handbook for the Office of the Auditor General s Development Cooperation Office of the Auditor General of Norway Handbook for the Office of the Auditor General s Development Cooperation i Photo: The Office of the Auditor General of Norway Illustration: Lobo Media AS March 2009

More information

UNDP Initiation Plan to programme the project preparation grant received from the GEF. (otherwise called GEF PPG)

UNDP Initiation Plan to programme the project preparation grant received from the GEF. (otherwise called GEF PPG) UNDP Initiation Plan to programme the project preparation grant received from the GEF (otherwise called GEF PPG) effective for all PIFs approved as of GEF November work programme 2017 A. Background: The

More information

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change Version No 13 of 23 November 2018 Table of contents I. GETTING STARTED: THE INITIATION

More information

NEPAD/Spanish Fund for African Women s empowerment

NEPAD/Spanish Fund for African Women s empowerment NEPAD/Spanish Fund for African Women s empowerment Project Proposal Format Annex 0 1 P age Proposal Format Proposal Cover Page: PROPOSAL TO THE NEPAD- SPANISH FUND FOR AFRICAN WOMEN s EMPOWERMENT Organization

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism the European Economic Area (EEA) Financial Mechanism 2014-2021 Adopted by the EEA Financial Mechanism Committee pursuant to Article 10.5 of Protocol 38c to the EEA Agreement on 8 September 2016 and confirmed

More information

with the Ministry of Finance and Planning for the United Republic of Tanzania 08 November 2015 NDA Strengthening & Country Programming

with the Ministry of Finance and Planning for the United Republic of Tanzania 08 November 2015 NDA Strengthening & Country Programming with the Ministry of Finance and Planning for the United Republic of Tanzania 08 November 2015 NDA Strengthening & Country Programming PAGE 1 OF 8 (Please submit completed form to countries@gcfund.org)

More information

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TABLE OF CONTENTS Introduction... 3 A. Background... 7 B. Project Management... 7 C. Consultations with concerned parties...

More information

with the National Rural Support Programme (NRSP) for the Islamic Republic of Pakistan 13 November 2015 NDA Strengthening & Country Programming

with the National Rural Support Programme (NRSP) for the Islamic Republic of Pakistan 13 November 2015 NDA Strengthening & Country Programming with the National Rural Support Programme (NRSP) for the Islamic Republic of Pakistan 13 November 2015 NDA Strengthening & Country Programming READINESS AND PREPARATORY SUPPORT PROPOSAL PAGE 1 OF 10 Country

More information

Bilateral Guideline. EEA and Norwegian Financial Mechanisms

Bilateral Guideline. EEA and Norwegian Financial Mechanisms Bilateral Guideline EEA and Norwegian Financial Mechanisms 2014 2021 Adopted by the Financial Mechanism Committee on 9 February 2017 09 February 2017 Contents 1 Introduction... 4 1.1 Definition of strengthened

More information

REPORT 2015/009 INTERNAL AUDIT DIVISION. Audit of a donor-funded project implemented by the International Trade Centre in Côte d Ivoire

REPORT 2015/009 INTERNAL AUDIT DIVISION. Audit of a donor-funded project implemented by the International Trade Centre in Côte d Ivoire INTERNAL AUDIT DIVISION REPORT 2015/009 Audit of a donor-funded project implemented by the International Trade Centre in Côte d Ivoire Overall results relating to the effective management of the donor-funded

More information

H2020 proposal preparation RI-Links2UA Horizon 2020 Info Day 8 June, 2018

H2020 proposal preparation RI-Links2UA Horizon 2020 Info Day 8 June, 2018 H2020 proposal preparation RI-Links2UA Horizon 2020 Info Day 8 June, 2018 Acknowledgement Slides, prepared by Gorazd Weiss are used in this presentation Today s topics 1. INTRODUCTION FROM IDEA TO IMPLEMENTATION

More information

with Fundación Avina for Republic of Paraguay 11 October 2017 Strategic Frameworks

with Fundación Avina for Republic of Paraguay 11 October 2017 Strategic Frameworks with Fundación Avina for Republic of Paraguay 11 October 2017 Strategic Frameworks PAGE 1 OF 36 Ver. 15 June 2017 Readiness and Preparatory Support Proposal How to complete this document? - A Readiness

More information

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/053. Audit of the management of the ecosystem sub-programme in the United Nations Environment Programme

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/053. Audit of the management of the ecosystem sub-programme in the United Nations Environment Programme INTERNAL AUDIT DIVISION AUDIT REPORT 2013/053 Audit of the management of the ecosystem sub-programme in the United Nations Environment Programme Overall results relating to effective management of the

More information

Fact Sheet 14 - Partnership Agreement

Fact Sheet 14 - Partnership Agreement - Partnership Agreement Valid from Valid to Main changes Version 2 27.04.15 A previous version was available on the programme website but all projects must use this version. Core message: It is a regulatory

More information

DEPARTMENT OF CANADIAN HERITAGE FINAL REPORT AUDIT OF THE CANADIAN HERITAGE INFORMATION NETWORK (CHIN)

DEPARTMENT OF CANADIAN HERITAGE FINAL REPORT AUDIT OF THE CANADIAN HERITAGE INFORMATION NETWORK (CHIN) DEPARTMENT OF CANADIAN HERITAGE FINAL REPORT AUDIT OF THE CANADIAN HERITAGE INFORMATION NETWORK (CHIN) October 19, 2005 TABLE OF CONTENTS Executive Summary 1.0 Background 2.0 Audit Objectives and Scope

More information

STRATEGY OF PUBLIC INTERNAL FINANCIAL CONTROL DEVELOPMENT IN THE REPUBLIC OF SERBIA FOR THE PERIOD OF

STRATEGY OF PUBLIC INTERNAL FINANCIAL CONTROL DEVELOPMENT IN THE REPUBLIC OF SERBIA FOR THE PERIOD OF Ministry of Finance STRATEGY OF PUBLIC INTERNAL FINANCIAL CONTROL DEVELOPMENT IN THE REPUBLIC OF SERBIA FOR THE PERIOD OF 2017-2020 www.mfin.gov.rs REPUBLIC OF SERBIA MINISTRY OF FINANCE TABLE OF CONTENTS

More information

IPA National Programme 2009 Part II - Bosnia and Herzegovina Fiche 3 Preparation for IPA components III and IV

IPA National Programme 2009 Part II - Bosnia and Herzegovina Fiche 3 Preparation for IPA components III and IV IPA National Programme 2009 Part II - Bosnia and Herzegovina Fiche 3 Preparation for IPA components III and IV 1. Basic information 1.1 CRIS Number: 2009 / 021-650 1.2 Title: Preparation for IPA components

More information

with GIZ for the Republic of Peru 29 January 2018 NDA Strengthening & Country Programming

with GIZ for the Republic of Peru 29 January 2018 NDA Strengthening & Country Programming with GIZ for the Republic of Peru 29 January 2018 NDA Strengthening & Country Programming PAGE 1 OF 19 Ver. 30 November Readiness and Preparatory Support Proposal How to complete this document? - A readiness

More information

with the Food and Agriculture Organization of the United Nations (FAO) for the Former Yugoslav Republic of Macedonia

with the Food and Agriculture Organization of the United Nations (FAO) for the Former Yugoslav Republic of Macedonia with the Food and Agriculture Organization of the United Nations (FAO) for the Former Yugoslav Republic of Macedonia 20 December 2017 NDA Strengthening & Country Programming PAGE 1 OF 30 Ver. 15 June 2017

More information

with GIZ for the Kingdom of Thailand 3 July 2015 NDA Strengthening & Country Programming

with GIZ for the Kingdom of Thailand 3 July 2015 NDA Strengthening & Country Programming with GIZ for the Kingdom of Thailand 3 July 2015 NDA Strengthening & Country Programming PAGE 1 OF 14 ver. 19 August Readiness and Preparatory Support Proposal How to complete this document? - A short

More information

with Caribbean Community Climate Change Centre (5Cs) for Belize 14 December 2016 NDA Strengthening & Country Programming

with Caribbean Community Climate Change Centre (5Cs) for Belize 14 December 2016 NDA Strengthening & Country Programming with Caribbean Community Climate Change Centre (5Cs) for Belize 14 December 2016 NDA Strengthening & Country Programming PAGE 1 OF 16 28 July 2016 Readiness and Preparatory Support Proposal Readiness -

More information

REPORT 2016/012 INTERNAL AUDIT DIVISION

REPORT 2016/012 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2016/012 Audit of the management of the technical cooperation project on Information and Communication Technologies in Africa Phase II in the Economic Commission for Africa

More information

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof, L 244/12 COMMISSION IMPLEMTING REGULATION (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU)

More information

FINANCIAL STANDING ORDERS

FINANCIAL STANDING ORDERS FINANCIAL STANDING ORDERS As adopted at 70 th Board Meeting in Bergen, Norway, 12 th to 14 th of May 2016 Table of Content Section 1: Definitions... 4 1.1. Fiscal year... 4 1.2. Budget... 4 1.3. Financial

More information

GUIDE FOR FILLING IN THE APPLICATION FORM 4TH CALL. Central Baltic Programme Version 4.0 ( )

GUIDE FOR FILLING IN THE APPLICATION FORM 4TH CALL. Central Baltic Programme Version 4.0 ( ) GUIDE FOR FILLING IN THE APPLICATION FORM 4TH CALL Central Baltic Programme 2014-2020 Version 4.0 (4.7.2018) Contents Introduction... 2 Small and regular projects... 2 The emonitoring System... 2 Important

More information

HEI ICI administra ve handbook Project implementa on

HEI ICI administra ve handbook Project implementa on Higher Educa on Ins tu ons Ins tu onal Coopera on Instrument HEI ICI HEI ICI administra ve handbook Project implementa on 2017 2020 Version 1.0 26.6.2017 Table of contents 1. Introduction... 2 2. The HEI

More information

Danida Fellowship Centre February

Danida Fellowship Centre February Danida Fellowship Centre February 2017-1 General Conditions for Grants to Development Research Supported through Denmark s International Development Cooperation Content: Introduction... 4 1. Ethical and

More information

Annex 2 Template for MoU Norwegian Financial Mechanism

Annex 2 Template for MoU Norwegian Financial Mechanism Annex 2 Template for MoU Norwegian Financial Mechanism 2014-2021 MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE NORWEGIAN FINANCIAL MECHANISM 2014-2021 between THE KINGDOM OF NORWAY, hereinafter

More information

Annex 1. Action Fiche for Solomon Islands

Annex 1. Action Fiche for Solomon Islands Annex 1 Action Fiche for Solomon Islands 1. IDENTIFICATION Title/Number FED/2012/023-802 Second Solomon Islands Technical Cooperation Facility (TCF II) Total cost EUR 1,157,000 Aid method / Method of implementation

More information

EUROPEAN COMMISSION DG Employment, Social Affairs and Equal Opportunities VP/2007/010

EUROPEAN COMMISSION DG Employment, Social Affairs and Equal Opportunities VP/2007/010 EUROPEAN COMMISSION DG Employment, Social Affairs and Equal Opportunities Equality between Men and Women, Action against Discrimination, Civil Society Equality between Men and Women Restricted Call for

More information

CONCORD, the European NGO Confederation for Relief and Development, is seeking a:

CONCORD, the European NGO Confederation for Relief and Development, is seeking a: CONCORD, the European NGO Confederation for Relief and Development, is seeking a: CONSULTANT TO PRODUCE A PUBLICATION ON THE ENGAGEMENT OF EU DELEGATIONS WITH CSOs CONCORD is the European Confederation

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6

EXHIBIT A RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6 EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6 3. PLANNING AND ADMINISTRATION A-6 OF THE PROJECT 4. PRECONSTRUCTION PHASE A-7 5. PRE-BIDDING

More information

ASEAN-ROK Cooperation Fund (AKCF) Manual

ASEAN-ROK Cooperation Fund (AKCF) Manual ASEAN-ROK Cooperation Fund (AKCF) Manual Working Draft Prepared by ASEAN-ROK Programme Management Team (AKPMT) 1 P a g e Table of Contents 1. Introduction: How to use this Manual 1.1 Objective 1.2 Target

More information

Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation)

Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation) EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation) p10 addition of 3 bullet points for specific

More information

MONTENEGRO. Support to the Tax Administration INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) Action summary

MONTENEGRO. Support to the Tax Administration INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) Action summary INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) 2014-2020 MONTENEGRO Support to the Tax Administration Action summary This Action aims to support Montenegro in the process of fulfilling the EU preaccession

More information

MONTENEGRO. Enhanced control and management of fisheries INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II)

MONTENEGRO. Enhanced control and management of fisheries INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) INSTRUMENT FOR PRE-ACCESSION ASSISTANCE (IPA II) 2014-2020 MONTENEGRO Enhanced control and management of fisheries Action summary The objective of the Action is to align the electronic data collection

More information

III. modus operandi of Tier 2

III. modus operandi of Tier 2 III. modus operandi of Tier 2 Objective, country and project eligibility 70 Budget and timing 71 Project preparation: formulation of proposals 71 Project appraisal 72 Project approval 73 Agreements and

More information

URBACT II PROGRAMME MANUAL

URBACT II PROGRAMME MANUAL European Regional Development Fund 2007-2013 Objective 3: European Territorial Cooperation URBACT II PROGRAMME MANUAL (Technical Working Document) Approved by the Monitoring Committee on 21/11/2007 Modified

More information

Required Pre-Implementation Review of Research Policies RIA-01 Page 1 of 6

Required Pre-Implementation Review of Research Policies RIA-01 Page 1 of 6 Required Pre-Implementation Review of Research Policies RIA-01 Page 1 of 6 SEATTLE CHILDREN S HOSPITAL RESEARCH INSTITUTE OPERATING POLICIES / PROCEDURES DEPARTMENT: Research Institute Administration POLICY

More information

Annex 1. ISP Guidelines for financial administration Reporting, audit, procurement, revised budget and requests

Annex 1. ISP Guidelines for financial administration Reporting, audit, procurement, revised budget and requests International Science Programme (ISP) Uppsala University Revised Jan 2019 Annex 1. ISP Guidelines for financial administration Reporting, audit, procurement, revised budget and requests Contents Requests

More information

2016/17 Ministry Annual Service Plan Report Guidelines. Crown Agencies Resource Office Ministry of Finance

2016/17 Ministry Annual Service Plan Report Guidelines. Crown Agencies Resource Office Ministry of Finance 2016/17 Ministry Annual Service Plan Report Guidelines Crown Agencies Resource Office Ministry of Finance Table of Contents PART I. INTRODUCTION... 3 1. Purpose of Guidelines... 3 2. Guiding Legislation

More information

Annex 2 Template for MoU EEA Financial Mechanism

Annex 2 Template for MoU EEA Financial Mechanism Annex 2 Template for MoU EEA Financial Mechanism 2014-2021 MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM 2014-2021 between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN,

More information

REPORT ON FACTUAL FINDINGS

REPORT ON FACTUAL FINDINGS Monitoring; Evaluacija; Revizija Finansijskih Izvještaja 71000 Sarajevo, Porodice Ribar 37; tel: ++ 387 33 521 195, ++ 387 61 172 276; fax: 387 33 521 195; e-mail: merfi.d@bih.net.ba; www.merfi.ba INDEPENDENT

More information

Project Document Cap. Bldg.

Project Document Cap. Bldg. Cover Page Year / Country: Project Title: Project No: (to be assigned by CEWARN Addis Ababa) Contents: Part A: Project Description 1. Overview 2. Problem description 3. Objective, results, approach 4.

More information

PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS

PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS Establishing the European Geological Surveys Research Area to deliver a Geological Service for Europe PROJECT IMPLEMENTATION DOCUMENT NO.1 REPORTING PROCEDURES AND MONITORING INDICATORS Joint Call on applied

More information

Initial Structure and Staffing of the Secretariat

Initial Structure and Staffing of the Secretariat Initial Structure and Staffing of the Secretariat GCF/B.05/10 26 September 2013 Meeting of the Board 8-10 October 2013 Paris, France Agenda item 6 Page b Recommended action by the Board It is recommended

More information

Report on the activities of the Independent Integrity Unit

Report on the activities of the Independent Integrity Unit Meeting of the Board 1 4 July 2018 Songdo, Incheon, Republic of Korea Provisional agenda item 23 GCF/B.20/Inf.17 30 June 2018 Report on the activities of the Independent Integrity Unit Summary This report

More information

Modernization of WBC universities through strengthening of structures and services for knowledge transfer, research and innovation

Modernization of WBC universities through strengthening of structures and services for knowledge transfer, research and innovation Internal Monitoring Report Project Acronym: WBCInno strengthening of Project full title: structures and services for knowledge transfer, research and innovation Project No: 530213-TEMPUS-1-2012-1-RS-TEMPUS-JPHES

More information

HEALTH RESEARCH CAPACITY STRENGTHENING INITIATIVE. Program Risk Management Policy. September Imperial : +265 (0)

HEALTH RESEARCH CAPACITY STRENGTHENING INITIATIVE. Program Risk Management Policy. September Imperial : +265 (0) HEALTH RESEARCH CAPACITY STRENGTHENING INITIATIVE Program Risk Management Policy September 2012 Imperial : +265 (0) 111 924 335 Appendix II: Final Rating The rating for the Likelihood shall be multiplied

More information

UN-Habitat Policy For Implementing Partners. UN-Habitat. Policy For. Partners

UN-Habitat Policy For Implementing Partners. UN-Habitat. Policy For. Partners UN-Habitat Policy For Implementing Partners 01 Version Date Author/Reviewer Status V1 06.12.2016 Mohamed Robleh Circulated for SMB comments V2 27.01.2017 Andrew Cox Approved For further information, please

More information

PROGRAMME MANUAL. Guide for applicants and project partners responding to the calls for proposals of the South-East Finland Russia CBC

PROGRAMME MANUAL. Guide for applicants and project partners responding to the calls for proposals of the South-East Finland Russia CBC PROGRAMME MANUAL Guide for applicants and project partners responding to the calls for proposals of the South-East Finland Russia CBC 2014-2020 HOW TO USE THIS MANUAL This Programme Manual is designed

More information

3 rd Call for Project Proposals

3 rd Call for Project Proposals IPA CROSS-BORDER PROGRAMME "GREECE THE FORMER YUGOSLAV REPUBLIC OF MACEDONIA 2007-2013" 3 rd Call for Project Proposals Project Selection Criteria CCI: 2007 CB 16 I PO 009 The following Project Selection

More information

Guidelines for the AF DSP call for proposals

Guidelines for the AF DSP call for proposals Guidelines for the AF DSP call for proposals A stream of cooperation edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2018 Programme co-funded by the European Union Table of content

More information

DG Justice & Consumers. Project Management.General Principles

DG Justice & Consumers. Project Management.General Principles DG Justice & Consumers Project Management.General Principles Project Life-Cycle Start Eligibility Monitoring End Eligibility Closing of Project A M E N D M E N T S Proposal Grant Agreement Progress report

More information

GUIDE FOR PROJECT IMPLEMENTATION

GUIDE FOR PROJECT IMPLEMENTATION GUIDE FOR PROJECT IMPLEMENTATION PRACTICAL GUIDANCE FOR PROJECT PARTNERS Version 5.0 (15.1.2019) Contents 1. Introduction... 3 2. Starting up the project... 4 2.1. Fulfilling conditions... 5 2.2. Hand

More information

Mongolia: Developing an Information System for Development Policy and Planning

Mongolia: Developing an Information System for Development Policy and Planning Technical Assistance Report Project Number: 51136-001 Knowledge and Support Technical Assistance (KSTA) September 2017 Mongolia: Developing an Information System for Development Policy and Planning This

More information

P. O. Box 3243, Addis Ababa, ETHIOPIA Tel.: (251-11) Fax: (251-11)

P. O. Box 3243, Addis Ababa, ETHIOPIA Tel.: (251-11) Fax: (251-11) AFRICAN UNION UNION AFRICAINE UNIÃO AFRICANA P. O. Box 3243, Addis Ababa, ETHIOPIA Tel.: (251-11) 5517700 Fax: (251-11) 5517844 www.au.int VACANCY ANNOUNCEMENT: FINANCE OFFICER TO WORLD BANK FUNDED PROJECTS

More information

BEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS

BEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS REPORT NO. 97-34 BEST FINANCIAL MANAGEMENT PRACTICES SELF-ASSESSMENT INSTRUMENT FOR FLORIDA SCHOOL DISTRICTS January 1998 Florida Legislature Office of Program Policy Analysis and Government Accountability

More information

THE GREEK ANTI-FRAUD STRATEGY FOR STRUCTURAL ACTIONS - ACTION PLAN (update 2017)

THE GREEK ANTI-FRAUD STRATEGY FOR STRUCTURAL ACTIONS - ACTION PLAN (update 2017) THE GREEK ANTI-FRAUD STRATEGY FOR STRUCTURAL - ACTION PLAN (update 2017) COMPETENT AUTHORITY TARGET GROUPS INDICATORS OF SUCCESS (/IN OBJECTIVE 1: Promote and establish an Ethical, Anti-Fraud Culture 1.1

More information

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN,

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN, MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM 2009-2014 between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN, THE KINGDOM OF NORWAY, hereinafter referred to as the Donor

More information

This action is funded by the European Union

This action is funded by the European Union This action is funded by the European Union ANNEX 10 of the Commission implementing Decision on the Annual Action Programme 2015 of the DCI Pan-African Programme Action Document for "Support Measures Annual

More information

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA)

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) 2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) TECHNICAL SPECIFICATIONS 15 July 2016 1 1) Title of the contract The title of the contract is 2nd External

More information

State of New Jersey Department of Education Division of Administration & Finance Office of School Finance

State of New Jersey Department of Education Division of Administration & Finance Office of School Finance 2016-2017 State of New Jersey Department of Education Division of Administration & Finance Office of School Finance Audit Summary Online Technical Manual Table of Contents Purpose.. 3 Submission dates....

More information

Danida Fellowship Centre January 2016

Danida Fellowship Centre January 2016 Danida Fellowship Centre January 2016 General Conditions for Grants to Development Research Supported through Denmark s International Development Cooperation Contents: Introduction... 4 1. Ethical and

More information

Guidelines for the United Nations Trust Fund for Human Security

Guidelines for the United Nations Trust Fund for Human Security Guidelines for the United Nations Trust Fund for Human Security Eighth Revision 1 30 October 2014 1 This sets out the revised Guidelines for the United Nations Trust Fund for Human Security, effective

More information

Project Reporting: GCF Legal Agreements and GCF Monitoring & Evaluation

Project Reporting: GCF Legal Agreements and GCF Monitoring & Evaluation Project Reporting: GCF Legal Agreements and GCF Monitoring & Evaluation ARMENIA De-risking and Scaling-up Investment in Energy Efficient Building Retrofits UNDP-GCF Project INCEPTION WORKSHOP Cynthia Page,

More information

P Periodic project report Please remove this front page when using the template

P Periodic project report Please remove this front page when using the template P Periodic project report Please remove this front page when using the template IMI1 programme Template for periodic project report Recommendations for project coordinators When preparing a periodic report,

More information

HEI ICI HIGHER EDUCATION INSTITUTIONS INSTITUTIONAL COOPERATION INSTRUMENT. Coordinator s meeting / Alva Bruun

HEI ICI HIGHER EDUCATION INSTITUTIONS INSTITUTIONAL COOPERATION INSTRUMENT. Coordinator s meeting / Alva Bruun HEI ICI HIGHER EDUCATION INSTITUTIONS INSTITUTIONAL COOPERATION INSTRUMENT Coordinator s meeting /27.8.2013 Alva Bruun HEI ICI COORDINATOR S MEETING Content of the afternoon: Administrative handbook (draft)

More information

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN,

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN, MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM 2014-2021 between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN, THE KINGDOM OF NORWAY, hereinafter referred to as the Donor

More information

AUDIT OF THE NATIONAL ARCHIVAL DEVELOPMENT PROGRAM

AUDIT OF THE NATIONAL ARCHIVAL DEVELOPMENT PROGRAM AUDIT OF THE NATIONAL ARCHIVAL DEVELOPMENT PROGRAM AUDIT REPORT JUNE 2010 Library and Archives Canada Page 2 TABLE OF CONTENTS EXECUTIVE SUMMARY 4 1.0 PROGRAM DESCRIPTION 6 1.1 BACKGROUND 6 1.2 FINANCIAL

More information

PROJECT MANAGEMENT MANUAL for FOKUS member organizations

PROJECT MANAGEMENT MANUAL for FOKUS member organizations PROJECT MANAGEMENT MANUAL for FOKUS member organizations Contents 1. About the Project Management Manual 2 2. Introduction 3 What is FOKUS 3 FOKUS from project to programme 4 3. Calendar 5 4. Applications/Budget

More information

BIOSURF. (BIOmethane SUstainable and Renewable Fuel) Project Handbook (D1.1) Loriana PAOLUCCI & Stefano PROIETTI (ISIS)

BIOSURF. (BIOmethane SUstainable and Renewable Fuel) Project Handbook (D1.1) Loriana PAOLUCCI & Stefano PROIETTI (ISIS) (BIOmethane SUstainable and Renewable Fuel) Project Handbook (D1.1) Authors: Loriana PAOLUCCI & Stefano PROIETTI (ISIS) Version: Final Quality Review: Stefano PROIETTI Date: 28-02-2015 Grant Agreement

More information

Such Personal Data will be collected, used, disclosed, transferred and/or processed by SIT for the following purposes: -

Such Personal Data will be collected, used, disclosed, transferred and/or processed by SIT for the following purposes: - Personal Data Protection Policy The Singapore Institute of Technology ( SIT ) collects personal data to support its teaching, learning, research, administration, personal development, to process applications

More information

REPORT 2016/030 INTERNAL AUDIT DIVISION. Audit of project management at the United Nations Institute for Training and Research

REPORT 2016/030 INTERNAL AUDIT DIVISION. Audit of project management at the United Nations Institute for Training and Research INTERNAL AUDIT DIVISION REPORT 2016/030 Audit of project management at the United Nations Institute for Training and Research Overall results relating to effective management of projects were initially

More information

ACCREDITATION STANDARDS RELATED TO ANTI- MONEY-LAUNDERING / COUNTERING THE FINANCING OF TERRORISM

ACCREDITATION STANDARDS RELATED TO ANTI- MONEY-LAUNDERING / COUNTERING THE FINANCING OF TERRORISM Adaptation Fund Board Ethics and Finance Committee Twenty-third meeting Bonn, Germany, 9-10 October 2018 9 September 2018 Agenda item 6 ACCREDITATION STANDARDS RELATED TO ANTI- MONEY-LAUNDERING / COUNTERING

More information

2011 SURVEY ON MONITORING THE PARIS DECLARATION

2011 SURVEY ON MONITORING THE PARIS DECLARATION TASK TEAM ON MONITORING THE PARIS DECLARATION 2011 SURVEY ON MONITORING THE PARIS DECLARATION Revised Survey Materials Initial Annotated Draft 3 May 2010 FOR COMMENT This initial text with annotations

More information

REQUIRED DOCUMENT FROM HIRING UNIT

REQUIRED DOCUMENT FROM HIRING UNIT Terms of reference GENERAL INFORMATION Title: Finance Management Technical Assistance Consultant for the Global Fund Principal Recipient Aisyiyah (National Consultant) Project Name: Management and Technical

More information

Standard Operating Procedure (SOP)

Standard Operating Procedure (SOP) SOP number: 34 Standard Operating Procedure (SOP) Version: 1.0 (last update: 19 May 2016) Effective Date: 12 June 2014 Maintained by/author: COB/OES Title: Standard Operating Procedure on Legal Instruments

More information

UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK

UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK 1 TABLE OF CONTENTS FIGURES AND TABLES... 3 1. INTRODUCTION... 4 2. KEY TERMS AND DEFINITIONS... 5 2.1 Risk... 5 2.2 Risk Management... 5 2.3 Risk Management

More information

Duration of Assignment: Apprx. 150 working days from January to September 2015

Duration of Assignment: Apprx. 150 working days from January to September 2015 Terms of reference GENERAL INFORMATION Title: Governance and Institutional Expert _CPEIR Bangka Belitung (Indonesian National) Project Name : Environment Unit/ Sustainable Development Financing (SDF) SIDA

More information

Cross-border Cooperation Action Programme Montenegro - Albania for the years

Cross-border Cooperation Action Programme Montenegro - Albania for the years ANNEX 1 Cross-border Cooperation Action Programme Montenegro - Albania for the years 2015-2017 1 IDENTIFICATION Beneficiaries CRIS/ABAC Commitment references Union Contribution Budget line Montenegro,

More information

CEI Know-how Exchange Programme (KEP) KEP AUSTRIA Call Expression of Interest

CEI Know-how Exchange Programme (KEP) KEP AUSTRIA Call Expression of Interest ANNEX I To be completed by the CEI Executive Secretariat Ref. No.: 1206.XXXA-14 CEI Know-how Exchange Programme (KEP) KEP AUSTRIA Call 2015 Expression of Interest IMPORTANT This Expression of Interest,

More information

PROGRAMME MANUAL. Guide for applicants and project partners responding to the calls for proposals of the South-East Finland Russia CBC

PROGRAMME MANUAL. Guide for applicants and project partners responding to the calls for proposals of the South-East Finland Russia CBC PROGRAMME MANUAL Guide for applicants and project partners responding to the calls for proposals of the South-East Finland Russia CBC 2014-2020 Published by the Managing Authority Publication date 30 January

More information

OPERATIONAL INSTRUCTION REF. OI.IPMG ACCEPTANCE OF ENGAGEMENT AGREEMENTS

OPERATIONAL INSTRUCTION REF. OI.IPMG ACCEPTANCE OF ENGAGEMENT AGREEMENTS Headquarters, Copenhagen 3 April 2018 OPERATIONAL INSTRUCTION REF. OI.IPMG.2018.02 ACCEPTANCE OF ENGAGEMENT AGREEMENTS 1. Authority 1.1. This Operational Instruction (OI) is promulgated by the Director

More information

ASEANSAI KNOWLEDGE SHARING COMMITTEE TERMS OF REFERENCE

ASEANSAI KNOWLEDGE SHARING COMMITTEE TERMS OF REFERENCE ASEANSAI KNOWLEDGE SHARING COMMITTEE TERMS OF REFERENCE 1. Background 1.1 The ASEANSAI was duly formed on November 16, 2011 in Bali, Indonesia as a professional organization which is autonomous, independent

More information

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE NORWEGIAN FINANCIAL MECHANISM between THE KINGDOM OF NORWAY,

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE NORWEGIAN FINANCIAL MECHANISM between THE KINGDOM OF NORWAY, MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE NORWEGIAN FINANCIAL MECHANISM 2014-2021 between THE KINGDOM OF NORWAY, hereinafter referred to as Norway and The Republic of Latvia, hereinafter

More information

Internal, Operational, and Compliance Auditing

Internal, Operational, and Compliance Auditing CHAPTER 21 Internal, Operational, and Compliance Auditing Review Questions 21 1 Internal auditing may be defined as an independent, objective assurance and consulting activity designed to add value and

More information

Regional HFA Monitor Template Regional HFA Monitor Template and Guidance

Regional HFA Monitor Template Regional HFA Monitor Template and Guidance Regional HFA Monitor Template and Guidance Regional HFA monitoring and review in support of regional and national disaster risk reduction 2011-2013 1 Progress monitoring and review through a multi stakeholder

More information

2 SCOPE OF WORK, RESPONSIBILITIES AND DESCRIPTION OF THE PROPOSED ANALYTICAL WORK

2 SCOPE OF WORK, RESPONSIBILITIES AND DESCRIPTION OF THE PROPOSED ANALYTICAL WORK UNITED NATIONS COUNTRY TEAM in TURKEY INDIVIDUAL CONSULTANT PROCUREMENT NOTICE 09.09.2016 Country Description of the Assignment Contracting Office Type of Contract Period of Assignment/Services Turkey

More information

REPUBLIC OF ZAMBIA. Ministry of National Development Planning

REPUBLIC OF ZAMBIA. Ministry of National Development Planning REPUBLIC OF ZAMBIA Ministry of National Development Planning Terms of References For Individual Local Consultant to Develop Guidelines and Procedures for a Comprehensive Framework for Public Investment

More information

Guide for Applicants

Guide for Applicants EUROPEAN COMMISSION EUROSTAT Guide for Applicants Eurostat Grants Version 4.0 11 January 2018 1/55 IMPORTANT NOTICE The Guide for Applicants is a user guide that aims to explain to applicants and beneficiaries

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

Project management guidelines. November 2013

Project management guidelines. November 2013 p r o j e c t m a n a g e m e n t g u i d e l i n e s N O V E M B E R 2 0 1 3 T e l e c o m m u n i c a t i o n D e v e l o p m e n t S e c t o r Project management guidelines November 2013 Please consider