1 CAPITAL PROGRAMME & PROPERTY UPDATE Report of: Executive Director of Planning AGENDA ITEM 4.4 Paper prepared by: Assistant Director of Planning Capital & Estates Executive Summary This report provides an overview of the current status of the UHB s Major and Discretionary Capital Programmes including progress, project issues and financial position. The report includes the current Capital Resource Limit (CRL) as agreed with Welsh Government (WG) together with details of any income generated through the disposal of property. The UHB has a CRL of m for the 2012/13 financial year, comprising of approved funding of m, m of potential funding indentified for projects but yet to receive approval and 6.598m of other potential schemes. Although the 6.598m for other potential schemes remains included on the latest UHB CRL Statement, on going discussions with WG indicate these funds will not be available during The approved funding includes 8.097m Discretionary Capital and m for approved Major Capital projects. It should be noted that WG have reduced the original discretionary capital funding allocation from 8.757m by 0.660m resulting in the revised WG funding allocation of 8.097m. The current discretionary capital funding allocated to deliver the programme is 9.507m. The additional funds relate to sales from land and property, 0.130m from WG for LIMS system and 0.130m funds transferred from Velindre NHS Trust to undertake refurbishment works at Capital Programme and Property Update Page 1 of 10 Strategic Planning and Performance Committee

2 laboratories at UHL. The Committee is requested to: Note: the project status updates Note: adjustments made to the Discretionary Capital Programme during the reporting period The report has financial consequences: Yes / No. The financial implications are generally supported from within the existing capital programme. Where major capital schemes have identified funding issues these are subject to ongoing discussions with the Welsh Government. Board Assurance Framework: The Report provides assurances against Healthcare Standard 12 (Environment). Capital Programme and Property Update Page 2 of 10 Strategic Planning and Performance Committee

3 CAPITAL PROGRAMME & PROPERTY UPDATE 1.0 INTRODUCTION. The purpose of this report is to enable the committee to provide the assurance to the UHB Board that the Capital Programmes are being managed and monitored appropriately and that due consideration is given to any potential Property acquisition or disposals. This report provides the current status of the UHB Capital Programme in respect of progress and financial position. The report highlights any significant project issues that have arisen during the reporting period together with the recommendations or options for consideration to mitigate same. The UHB has a capital funding allocation of m. This can be analysed between: m Strategic Projects with approved funding Discretionary Capital Forecast capital projects without approved funding Potential other schemes TOTAL A copy of the latest UHB CRL (as at 31 August 2012) is provided in Appendix DISCRETIONARY CAPITAL PROGRAMME 2012/13. The initial UHB Discretionary Capital allocation provided by WG was 8.757m. Following an All Wales capital shortfall, WG removed 0.660m from the UHB funding on the basis that, the 0.660m will be the first call on any additional WG funding which may become available later in the financial year. It was previously reported that Velindre NHS Trust have transferred 0.130m to the UHB to undertake work to refurbish laboratory areas at UHL, subsequently, a further 0.140m is being transferred as revenue funds to cover the anticipated outturn cost. Finally WG have transferred 0.130m relating to a new Renal IT system. Capital Programme and Property Update Page 3 of 10 Strategic Planning and Performance Committee

4 Together with property disposals effected in year to date, the net effect of the above adjustments is that the UHB Discretionary capital programme funding has increased to 9.507m. As can be seen from Table 1 below a number of adjustments have been made to some of the schemes within the programme, which have resulted from the receipt of tenders and the firming up of budget costs as the scheme design develops. The current level of over-commitment identified is 1.220m, net of the WG reduction. The committee previously approved the disposal of 3 residential properties and Pen Yr Ynys clinic the proceeds from which should realise circa 0.9m. Following the sale of these properties the balance of the over-commitment would then reduce to a level which can be easily managed through the overall Discretionary Capital Programme. Capital Programme and Property Update Page 4 of 10 Strategic Planning and Performance Committee

5 Table 1 Revised Discretionary Capital Programme Cost Centre Description Orig Adj Latest O'Turn k k k FUNDING: Original Allocation 8,757 8,757 WG Land at Canton Sale Sale of Residential Properties x UHL Labs Sale of Splott Clinic LIMS System DISCRETIONARY CAPITAL ALLOCATION 8, ,507 COMMITMENTS: CED9 Whitchurch Lymphodemia Services CEB1 UHW Laparoscopic Theatre CEB7 UHW Theatre Endoscopy CED2 Barry Hospital Reception CDE2 UHW Dental Rolling Eqt Prog CEB2 UHW Urology Suite 18 Phases 2& CED5 UHW Legionellae Works CEC8 UHW SCT Haematology database CEA4 UHW Bathrooms/Toilets upgrade C5,C6,C CED6 Grangetown HC Works CD86 UHB Electrical Infrastructure Works CEDA UHW Breastcare Services Phase II CEDE UHW Modernisation of Health Records CD09 UHB Misc / Feasibility Fees CD67 UHB Misc Minor Capital Schemes 9 9 CEDK UHW Suite 2 IVF CEDG UHW NICU conversion works CEDJ UHW A3 refurbishment works CD11 UHB Estates Site Upgrade Works * CEDM UHW Labs - newborn blood spotting CDJ7 UHW DDA (Heathfields Entrance Lift) CED4 Rockwood Enabling Works - inc ALAS CDA2 UHB Fire Precautions CD50 UHB Energy Sources CDH9 UHB Accommodation Strategy * CDP7 UHB Statutory Compliance Asbestos/Legionella CEDT Whitchurch west 3 ward upgrade works CEDU Whitchurch Development Triage Assessment ward CEDP UHW Main Theatres upgrade works CEDW UHW Installation Air Conditioning Paediatrics South CEDO UHW Cellular Pathology CEDR Glan Ely Ward Adaptations CEDX UHW Refurb Heathfields Restaurant & entrance 7 7 CEDQ UHB R22 Gas replacement CDZ4 UHL Ward Upgrading CEC9 UHW Theatres Upgrading CEC7 UHW Remodelling Emergency Unit N/A 2 Stanwell Road N/A PSA Building CEDL UHL Labs CEDV LIMS System CD93 UHB Capitalisation of Salaries N/A UHB Strategic capital payback 2,300 2,300 CEDB UHB Director of Planning Staff CDN8 UHB Revenue to Capital DISCRETIONARY CAPITAL COMMITMENTS 9,283 1,444 10,727 Over / Under commitment ,220 Capital Programme and Property Update Page 5 of 10 Strategic Planning and Performance Committee

6 3.0 ALL WALES CAPITAL PROGRAMME 2012/13. UHL Mental Health Unit for Older Persons Formal handover of the building has now taken place with a number of outstanding external elements of work to complete, including: I. The Section 278 works, being the highway alterations on the junction of Penlan Road and the main hospital entrance. These works include the installation of traffic signals and the widening of the entrance to improve visibility. II. The completion of template 1 courtyard III. The removal and reinstatement of the area of the site accommodation The majority of the wards/departments have successfully relocated to the new unit. Early indications from patients, staff and visitors alike are extremely positive. Both the Minister for Finance and the Minister for Health and Social Services visited the unit on Monday 1 st October 2012 and were extremely impressed with the facility and in particular the attention to detail within the development which was only achieved by the involvement of the clinical teams, careers and service users with the technical team from an early stage. UHL Integrated Stroke Unit Ward East 4 has been re-occupied following the completion of the works, with the exception of the solarium. Ward East 6 has now relocated to West 4 to enable the removal of asbestos, attend to statutory works in the area and install roof lights in the cubicles to be progressed. Demolition works in East 5 including the solarium are also continuing. Capital Programme and Property Update Page 6 of 10 Strategic Planning and Performance Committee

7 A partial possession of the Stroke Unit to include East 3 and the Ground floor of the infill blocks will be possible in December This could facilitate the relocation of the patients from West Wing. Discussions are on going with the Directorate to agree a way forward. As previously reported the scheme is projected to be considerably over budget and discussions continue with WG to find a solution to funding the shortfall. UHW Remodelling of the Emergency Unit Detailed design works continue to progress in conjunction with the Directorate team, with the intention to commence the phased programme of works on Monday 3 rd December The phasing programme is subject to confirmation with detailed discussions taking place with the department leads, Welsh Ambulance Trust and the Contractors, in order to minimise as far as practicable the disruption to the service. CRI Conservation works - The extent of the conservation works is now being curtailed whilst the need for additional funding is discussed with WG. Correspondence has been received from the Local Authority Planning Officer expressing concern at the progress being made as it is evident through his regular site visits that activity in this area of the scheme has slowed considerably. The LA has indicated that this scheme remains their most significant restoration project in the city at this present time. CRI Business Justification Cases Work continues in all areas at present however, progress has been affected whilst the investigation into the dry/wet rot continues and the associated remedial works are identified. A detailed report on all technical issues identified including costs and programme effects is being prepared for consideration by the UHB Board. Capital Programme and Property Update Page 7 of 10 Strategic Planning and Performance Committee

8 UHW Children s Hospital for Wales - The construction of the facility is progressing extremely well, with erection of the steel frame having progressed. Currently, the SCP is reporting that they are two weeks ahead of programme. Following approval in principal of the proposal to provide family accommodation in the existing Directorate offices, discussions with the Trust for Sick Children are progressing. It has been confirmed that the Ronald McDonald House Charity does not use the Golden Arches and that the unit is to be named, Ronald McDonald House Ty Croeso, thereby maintaining the original links with the Trust for Sick Children in Wales. UHW Neurosciences The drawings have now been signed off and the detailed design work is progressing so as to allow the scheme to be tendered. It is anticipated that the construction works will commence in the New Year and completed by the end of March UHL Adult Mental Health Unit Development of the FBC is nearing completion and following the market testing exercise undertaken by the SCP a not to exceed cost has been identified. This figure has resulted in the cost plan indicating a project cost of 87,992,080 against an approved OBC allowance of 88,278,893 (a variance of - 286,813). This figure will be used for the financial model to be included in the FBC. The enabling works contract has commenced on site with the temporary entrance and access road being the priority. Works are also progressing to install the hoarding around the site of the proposed multi deck car park. The planning application for the main scheme is yet to be determined. However, it is understood that it is to be considered at Capital Programme and Property Update Page 8 of 10 Strategic Planning and Performance Committee

9 the Vale Local Authority Planning Committee meeting on 22 nd October Making a Difference Rookwood Relocation Approval of the Strategic Outline Case (SOC) has still not been received. With regards to the OBC, the UHB took the decision to progress the scheme without including the possible receipt form the disposal of the existing Rookwood site due to the legal complexities affecting this proposal. A separate paper has been prepared for consideration by the SPPC seeking approval of the OBC. CONCLUSION The UHB continues to progress and manage a large Capital programme in terms of Discretionary and Major capital developments. Emphasis in this report is given to the Progress of the Major Capital schemes whilst there are some interesting minor developments progressing, eg. the refurbishment of Ward A3S South at UHW, amongst others, all of which are providing an improved environment for our patients and staff RECOMMENDATION The Committee is asked to: Note: the project status updates Note: adjustments made to the Discretionary Capital Programme during the reporting period Capital Programme and Property Update Page 9 of 10 Strategic Planning and Performance Committee

10 Appendix 1 Cardiff & Vale 2012/13 - Capital Resource Limit (CRL) - Date Last Updated 31 August ) DISCRETIONARY CAPITAL FUNDING [A] 2012/13 m Capital Resource Limit (CRL) 2) CAPITAL PROJECTS WITH APPROVED FUNDING [B] Llandough EMI Children's Hospital Final Phase Neurosciences Spend to Save Scheme - UHW Remodel Emergency CRI GMS, Integrated Sexual Health and CHAPS Adult Acute Mental Health Unit Adult Acute Mental Health Unit (Enabling Works) Microbiology Labs Renal IT TOTAL CRL [C = A+B] (Approved Funding) ) FORECAST CAPITAL PROJECTS WITHOUT APPROVED FUNDING Adult Acute Mental Health Unit CRI enabling works CRI further works Integrated Stoke Unit Rookwood Specialist Rehab - OBC Fees Discretionary Adjustment ) Sub Total Forecast Capital Projects Without Approved Funding [D] 4)Total Potential CRL if all Funding Approved [E=C+D] Capital Resource Limit 5) Potential other new schemes Potential other schemes funding value ) Sub Total Potential Schemes [F] )Total Potential CRL if all Funding Approved including potential other new schemes [G=E+F] Capital Programme and Property Update Page 10 of 10 Strategic Planning and Performance Committee

DISCRETIONARY CAPITAL ALLOCATION AND EXPENDITURE REPORT. Author: Assistant Director of Planning, Capital Planning & Estate Management

DISCRETIONARY CAPITAL ALLOCATION AND EXPENDITURE REPORT. Author: Assistant Director of Planning, Capital Planning & Estate Management DISCRETIONARY CAPITAL ALLOCATION AND EXPENDITURE REPORT Executive Lead: Director of Planning Author: Assistant Director of Planning, Capital Planning & Estate Management Financial impact Quality, Safety,

More information

REPROVISION OF ROOKWOOD NEURO AND SPINAL REHABILITATION

REPROVISION OF ROOKWOOD NEURO AND SPINAL REHABILITATION AGENDA ITEM 2.2 15 May 2012 REPROVISION OF ROOKWOOD NEURO AND SPINAL REHABILITATION Report of Paper prepared by Director of Finance Director of Finance Executive Summary The update report summarises the

More information

Aneurin Bevan University Health Board. Capital Programme Update

Aneurin Bevan University Health Board. Capital Programme Update Aneurin Bevan University Health Board Capital Programme Update 1 Introduction This paper updates the Board on the Capital Programme for 2014/15 and priorities for future years. The Board is requested to:

More information

Outline Business Case for Prince Charles Hospital Ground and First Floor Refurbishment Scheme 3 Executive Summary

Outline Business Case for Prince Charles Hospital Ground and First Floor Refurbishment Scheme 3 Executive Summary Agenda Item 13 Appendix 1 Outline Business Case for Prince Charles Hospital Ground and First Floor Refurbishment Scheme 3 Executive Summary Cwm Taf Health Board ii Executive summary (ES) Introduction 1.

More information

Agenda Item 2.3a. Laboratory Information Network Cymru (LINC) Programme. Outline Business Case Executive Summary

Agenda Item 2.3a. Laboratory Information Network Cymru (LINC) Programme. Outline Business Case Executive Summary Agenda Item 2.3a Laboratory Information Network Cymru (LINC) Programme Outline Business Case Executive Summary Document Control Document Information: Document Name: Version: 0.3 Issue Date: 13 December

More information

Capital Programme to

Capital Programme to Aneurin Bevan University Health Board Capital Programme 2014-2015 to 2016-2017 1 Introduction This paper updates the Board on the Capital Programme for 2014-2015 and future years. The Board is requested

More information

Five-Year Capital Expenditure Plan Prepared by the Director of Finance & Information

Five-Year Capital Expenditure Plan Prepared by the Director of Finance & Information The Lewisham Healthcare NHS Trust Meeting of the Trust Board 5 th July 2011 Five-Year Capital Expenditure Plan Prepared by the Director of Finance & Information 1. Introduction The Trust Board is required

More information

NHS GRAMPIAN. Asset Management Plan. The Board is asked to consider and approve the Asset Management Plan.

NHS GRAMPIAN. Asset Management Plan. The Board is asked to consider and approve the Asset Management Plan. NHS GRAMPIAN Board Meeting 01.06.17 Open Session Item 10 Asset Management Plan 1. Actions Recommended The Board is asked to consider and approve the Asset Management Plan. 2. Strategic Context The Scottish

More information

APPENDIX 5a Optimism bias calculations

APPENDIX 5a Optimism bias calculations APPENDIX 5a Optimism bias calculations Sustainable Services Programme Final Draft Strategic Outline Case for submission to SaTH Trust Board 22 March 2016 SaTH Sustainable Services Programme: Emergency

More information

NHS PENSION RETIRE AND RETURN OPTION QUESTIONS AND ANSWERS

NHS PENSION RETIRE AND RETURN OPTION QUESTIONS AND ANSWERS NHS PENSION RETIRE AND RETURN OPTION QUESTIONS AND ANSWERS What is the Retire and Return Option? The UHB Retirement Policy includes a number of Flexible Retirement options. One of the options is the Retire

More information

Appendix A HRA REVENUE ACCOUNT

Appendix A HRA REVENUE ACCOUNT Appendix A HRA REVENUE ACCOUNT 1. The HRA annual expenditure budget is 22.389M and income budget is 28.580M, which allows a contribution of 6.191M to reserves to present a net budget of zero. A subjective

More information

APPENDIX 1. Contents Section 1: Summary 1.1 Performance Summary: Performance Indicators KPI s & PSA Targets Page 1

APPENDIX 1. Contents Section 1: Summary 1.1 Performance Summary: Performance Indicators KPI s & PSA Targets Page 1 Quarterly Performance Management Report Select Committee Report Adult & Community Services + Housing Benefits Quarter 3 Report: October - December 2004 Contents Section 1: Summary 1.1 Performance Summary:

More information

2015/16 Financial Position (Month 2) Author: Lorraine Bentley Sponsor: Paul Traynor Date: Trust Board - Thursday 2 nd July 2015

2015/16 Financial Position (Month 2) Author: Lorraine Bentley Sponsor: Paul Traynor Date: Trust Board - Thursday 2 nd July 2015 U N I V E R S I T Y H O S P I T A L S O F L E I C E S T E R N H S T R U S T P A G E 1 O F 2 2015/16 Financial Position (Month 2) Author: Lorraine Bentley Sponsor: Paul Traynor Date: Trust Board - Thursday

More information

BOARD MEETING DATE OF MEETING: 18 JULY Month 3 (June) Financial Performance Update Eifion Williams, Director of Finance

BOARD MEETING DATE OF MEETING: 18 JULY Month 3 (June) Financial Performance Update Eifion Williams, Director of Finance AGENDA ITEM: 3.1 BOARD MEETING DATE OF MEETING: 18 JULY 2018 Subject : Approved and Presented by: Prepared by: Considered by Executive Committee on: Other Committees and meetings considered at: Month 3

More information

Report to the Merton Clinical Commissioning Group Governing Body

Report to the Merton Clinical Commissioning Group Governing Body MCCG Bd 24.01.13 Pt1 :6.1 : Att 03 Merton Clinical Commissioning Group Report to the Merton Clinical Commissioning Group Governing Body Date of Meeting: Thursday 24 th January 2013 Agenda No: 6.1 ATTACHMENT

More information

2015/16 Financial Position to Month 1 - April. Author: [Lorraine Bentley] Sponsor: [Paul Traynor] Date: [Thursday 4 June 2015]

2015/16 Financial Position to Month 1 - April. Author: [Lorraine Bentley] Sponsor: [Paul Traynor] Date: [Thursday 4 June 2015] U N I V E R S I T Y H O S P I T A L S O F L E I C E S T E R N H S T R U S T P A G E 1 O F 2 2015/16 Financial Position to Month 1 - April Author: [Lorraine Bentley] Sponsor: [Paul Traynor] Date: [Thursday

More information

The Royal Wolverhampton NHS Trust

The Royal Wolverhampton NHS Trust The Royal Wolverhampton NHS Trust Trust Board Report Meeting Date: 25 April 2016 Title: Capital Programme 2016/17 and Five Year Capital Programme 2016/17 2020/21 Executive Summary: This report seeks approval

More information

CWM TAF UNIVERSITY HEALTH BOARD MINUTES OF THE MEETING OF THE AUDIT COMMITTEE HELD ON 3 JUNE 2015 AT YNYSMEURIG HOUSE, ABERCYNON

CWM TAF UNIVERSITY HEALTH BOARD MINUTES OF THE MEETING OF THE AUDIT COMMITTEE HELD ON 3 JUNE 2015 AT YNYSMEURIG HOUSE, ABERCYNON CWM TAF UNIVERSITY HEALTH BOARD MINUTES OF THE MEETING OF THE AUDIT COMMITTEE HELD ON 3 JUNE 2015 AT YNYSMEURIG HOUSE, ABERCYNON PRESENT Mr G Bell - Independent Member (Chair) Mr M Forey - Independent

More information

1. The provisional outturn provides for a transfer to reserves of 6.590M.

1. The provisional outturn provides for a transfer to reserves of 6.590M. Appendix A HRA Detailed Commentary 1. The provisional outturn provides for a transfer to reserves of 6.590M. 2. Due to the changes in Right to Buy discounts, the Council achieved a higher level of capital

More information

This report provides headlines of the finance and contracting position for the 12 months ended 31st March 2017.

This report provides headlines of the finance and contracting position for the 12 months ended 31st March 2017. Finance & Contracting Performance Report: Period ended 31 March 2017 Introduction This report provides headlines of the finance and contracting position for the 12 months ended 31st March 2017. 1 Revenue

More information

Public Document Pack

Public Document Pack Public Document Pack Neuadd y Sir / County Hall, Llandrindod, Powys, LD1 5LG Os yn galw gofynnwch am - If calling please ask for Elizabeth Patterson Ffôn / Tel: 01597 826980 elizabeth.patterson@powys.gov.uk

More information

Integrated Performance Report M Executive Summary

Integrated Performance Report M Executive Summary M1 2017-2018 Executive Summary Risk ratings Financial Use of Resources Rating: 17/18 Plan: YTD FY Performance: YTD 2 2 Current 3 Previous Mth Summary Performance: The Trust has recorded a YTD loss of 5.2M,

More information

Annual Report: SAFEGUARDING ADULTS AND CHILDREN

Annual Report: SAFEGUARDING ADULTS AND CHILDREN Annual Report: SAFEGUARDING ADULTS AND CHILDREN Children, young people, vulnerable adults and victims of domestic abuse are considered in all interactions with service users and carers. Safeguarding, protecting

More information

Control of Contractors Policy

Control of Contractors Policy Reference Number: UHB 163 Version Number: 2 Date of Next Review: 19/07/2019 Previous Trust/LHB Reference Number: Control of Contractors Policy Policy Statement To ensure the Health Board delivers its aims,

More information

Month 10 Finance Report

Month 10 Finance Report TAUNTON & SOMERSET NHS FOUNDATION TRUST Month 10 Finance Report Report to: Trust Board on 24 February 2016 Purpose of the Report: The purpose of the report is to update the Board on the Month 10 financial

More information

UNIVERSITY HOSPITAL SOUTHAMPTON NHS FOUNDATION TRUST. Finance Report. Paul Goddard, Assistant Director of Finance

UNIVERSITY HOSPITAL SOUTHAMPTON NHS FOUNDATION TRUST. Finance Report. Paul Goddard, Assistant Director of Finance UNIVERSITY HOSPITAL SOUTHAMPTON NHS FOUNDATION TRUST Finance Report Report to: Trust Board 29 th November 2011 Report from: Sponsoring Executive: Purpose of Report: Review History to Date: Recommendation:

More information

Chief Finance Officer. The CCG reports a surplus of 79k for the year after holding a projected a surplus of 32k for the last three months.

Chief Finance Officer. The CCG reports a surplus of 79k for the year after holding a projected a surplus of 32k for the last three months. Agenda item 8 TITLE PRESENTED BY LEAD MANAGER PURPOSE OF PAPER RECOMMENDATION EQUALITY & DIVERSITY IMPACT FINANCE REPORT Stephen Schofield Chief Finance Officer Stephen Schofield Chief Finance Officer

More information

Report to: Public Trust Board Agenda item: 2.2 Date of Meeting: 12 May 2010

Report to: Public Trust Board Agenda item: 2.2 Date of Meeting: 12 May 2010 Report to: Public Trust Board Agenda item: 2.2 Date of Meeting: 12 May 2010 Title of Report: Status: Board Sponsor: Author: Appendices 1 2 3 4 5 6 7 Finance report Discussion Catherine Phillips, Director

More information

Review of Estates Cardiff and Vale University Health Board

Review of Estates Cardiff and Vale University Health Board Review of Estates Cardiff and Vale University Health Board Date issued: March 2017 Document reference: 674A2016 This document has been prepared as part of work performed in accordance with statutory functions.

More information

Date: December 2016 Author: Lawson Bisset Job Title: Head of Estates, Facilities & Medical Physics Decision / Action required by meeting:

Date: December 2016 Author: Lawson Bisset Job Title: Head of Estates, Facilities & Medical Physics Decision / Action required by meeting: Board Paper 2016/57 Shetland NHS Board Meeting: Shetland NHS Board Paper Title: Capital Programme 2016/17 Date: December 2016 Author: Lawson Bisset Job Title: Head of Estates, Facilities & Medical Physics

More information

Revenue Monitoring 2017/18 - Outturn. Director of Corporate Services - Graham Ebers. Executive Member for Finance - Julian McGhee- Sumner

Revenue Monitoring 2017/18 - Outturn. Director of Corporate Services - Graham Ebers. Executive Member for Finance - Julian McGhee- Sumner Agenda Item 7. TITLE Revenue Monitoring 2017/18 - Outturn FOR CONSIDERATION BY The Executive on 31 May 2018 WARD DIRECTOR LEAD MEMBER None Specific; Director of Corporate Services - Graham Ebers Executive

More information

RELOCATION COSTS AND ASSOCIATED PROVISIONS FOR DOCTORS AND DENTISTS IN THE TRAINING GRADES POLICY. UHB 059 Version No: 1 Previous Trust / LHB Ref No:

RELOCATION COSTS AND ASSOCIATED PROVISIONS FOR DOCTORS AND DENTISTS IN THE TRAINING GRADES POLICY. UHB 059 Version No: 1 Previous Trust / LHB Ref No: RELOCATION COSTS AND ASSOCIATED PROVISIONS FOR DOCTORS AND DENTISTS IN THE TRAINING GRADES POLICY Reference No: UHB 059 Version No: 1 Previous Trust / LHB Ref No: 10 Documents to read alongside this Policy

More information

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES)

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES) Prop Co (NO APPENDICES) 1 CONTENTS 1 Context 4 2 Overview of PropCo 5 2.1 Form of PropCo 5 2.2 Scope of PropCo 5 2.3 Included services 6 2.4 Excluded services 6 2.5 Services to be included subject to confirming

More information

2013/005. Subject: Author: Lead Clinician KCCG): Purpose:

2013/005. Subject: Author: Lead Clinician KCCG): Purpose: 213/5 Subject: Author: Lead Clinician KCCG): Purpose: Date of meeting: Finance, Performance & Quality Simon Bolitho, Deputy Director of Finance Katherine Paddock, Finance and Performance Manager Natalie

More information

Cabinet Decisions. excellent services, valued by customers. Tuesday, 22 August 2017 DATE OF PUBLICATION. Wednesday, 23 August 2017 CALL-IN DEADLINE

Cabinet Decisions. excellent services, valued by customers. Tuesday, 22 August 2017 DATE OF PUBLICATION. Wednesday, 23 August 2017 CALL-IN DEADLINE Decisions Tuesday, 22 August 2017 DATE OF PUBLICATION Wednesday, 23 August 2017 CALL-IN DEADLINE 4.00 p.m. Wednesday, 30 August 2017 excellent services, valued by customers Compiled by the Democratic Services

More information

Welsh Risk Pool Services. Concerns, Claims Management and Learning from Events Assessment. Powys Teaching Health Board Final Report

Welsh Risk Pool Services. Concerns, Claims Management and Learning from Events Assessment. Powys Teaching Health Board Final Report Welsh Risk Pool Services Concerns, Claims Management and Learning from Events Assessment Powys Teaching Health Board Final Report 2015/2016 CONTENTS Contents... 1 Background to the standard and scope of

More information

Policy on Planned Preventative Maintenance

Policy on Planned Preventative Maintenance Policy on Planned Preventative Maintenance PPM Policy SLA & Buildings Maintenance Manager v1 Oct 2016 Page 1 Policy Title: Executive Summary: Planned Preventative Maintenance This policy provides guidance

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy Originator: Executive Management Team Approval Date: Policy and Strategy Policy 18 July 2017 Review date: July 2018 1 Introduction 1.1 1.2 1.3 1.4 The scope of this Policy sets

More information

Are you due to go to hospital? What you need to know before you go.

Are you due to go to hospital? What you need to know before you go. Are you due to go to hospital? What you need to know before you go. The essentials Your hospital stay is covered Do you need inpatient treatment? This brochure explains the factors you should consider

More information

Housing & Neighbourhoods Committee are requested to consider and approve the Council s Housing Adaptations Policy 2018.

Housing & Neighbourhoods Committee are requested to consider and approve the Council s Housing Adaptations Policy 2018. Subject: Community Housing Adaptations Policy 2018 Report to: Management Team 29 th May 2018 Housing & Neighbourhoods Committee 14 th June 2018 Report by: Senior Projects Officer SUBJECT MATTER/RECOMMENDATIONS

More information

Supporting NHS providers: guidance on merger benefits

Supporting NHS providers: guidance on merger benefits www.gov.uk/monitor Supporting NHS providers: guidance on merger benefits About Monitor As the sector regulator for health services in England, our job is to make the health sector work better for patients.

More information

Board Sponsor: Sarah Truelove, Director of Finance and Deputy Chief Executive. Author: Lynne Abbott, Head of Financial Management

Board Sponsor: Sarah Truelove, Director of Finance and Deputy Chief Executive. Author: Lynne Abbott, Head of Financial Management Report To: Public Trust Board Agenda item: 13 Date of Meeting: 23 October 2013 Title of Report: Finance Report Status: Discussion Board Sponsor: Sarah Truelove, Director of Finance and Deputy Chief Executive

More information

Audit of financial statements: issues for the attention of the Audit Committee Cardiff and Vale NHS Trust

Audit of financial statements: issues for the attention of the Audit Committee Cardiff and Vale NHS Trust Audit 2009-10 February 2010 Author: Auditor General for Wales Ref: 182A2010 Audit of financial statements: issues for the attention of the Audit Committee Cardiff and Vale NHS Trust The Auditor General

More information

Internal Audit Incident Management Review

Internal Audit Incident Management Review PHWQSC 22.13.02 Internal Audit Incident Management Review Author: Keith Cox Date: 08/04/2015 Version: 1 Sponsoring Executive Director: Keith Cox Who will present: Keith Cox Date of Committee / Board meeting:

More information

The National Health Service (General Medical Services Premises Costs) (Wales) Directions 2004

The National Health Service (General Medical Services Premises Costs) (Wales) Directions 2004 The National Health Service (General Medical Services Premises Costs) (Wales) Directions 2004 The Premises Directions provide the contractual rules for the funding of primary care premises under the new

More information

Discussion. Information

Discussion. Information Item 10.8 To: From: Trust Board Kevin Turner, Deputy Chief Executive Date: 4 th July 2017 Title: Strategic Risk Management Report Responsible Director: Kevin Turner, Deputy Chief Executive Author: Karen

More information

Royal National Orthopaedic Hospital Trust. Minutes of the Trust Board Meeting. Held on Monday, 20 th December 2010

Royal National Orthopaedic Hospital Trust. Minutes of the Trust Board Meeting. Held on Monday, 20 th December 2010 Royal National Orthopaedic Hospital Trust Minutes of the Trust Board Meeting Held on Monday, 20 th December 2010 Present: Trust Board Members Mr G Billington Mr R Hurd Mr A Koray Mrs L Hill Mrs K Corder

More information

29th September Spencer Prosser, Chief Financial Officer. Bill Stronach, Deputy Chief Financial Officer. Finance Report Month /17

29th September Spencer Prosser, Chief Financial Officer. Bill Stronach, Deputy Chief Financial Officer. Finance Report Month /17 Meeting: Date: Board Sponsor: Paper Author: Subject: Brighton and Sussex University Hospitals NHS Trust Board of Directors 29th September 2016 Spencer Prosser, Chief Financial Officer Bill Stronach, Deputy

More information

HOUSING AND COMMUNITIES (COUNCILLOR LYNDA THORNE) DIRECTOR COMMUNITIES, HOUSING & CUSTOMER SERVICE

HOUSING AND COMMUNITIES (COUNCILLOR LYNDA THORNE) DIRECTOR COMMUNITIES, HOUSING & CUSTOMER SERVICE CARDIFF COUNCIL CYNGOR CAERDYDD CABINET MEETING: 18 JANUARY 2018 SUPPORTING PEOPLE LOCAL DELIVERY PLAN HOUSING AND COMMUNITIES (COUNCILLOR LYNDA THORNE) AGENDA ITEM: 7 DIRECTOR COMMUNITIES, HOUSING & CUSTOMER

More information

The Royal Wolverhampton NHS Trust

The Royal Wolverhampton NHS Trust The Royal Wolverhampton NHS Trust Trust Board Meeting Date: 25 April 2016 Title: Income and Expenditure Plan for 2016/17 Executive Summary: Action Requested: This report details the proposed Income & Expenditure

More information

NHS LANARKSHIRE FINANCE REPORT FOR THE YEAR ENDED 31 MARCH 2006

NHS LANARKSHIRE FINANCE REPORT FOR THE YEAR ENDED 31 MARCH 2006 NHS LANARKSHIRE FINANCE REPORT FOR THE YEAR ENDED 31 MARCH 2006 1. Purpose of Report The purpose of this report is to provide the NHS Board with the summary financial position for the year ended 31 March

More information

PPP IN THE UK HEALTH SECTOR. Section Head, Capital Investment Branch, Department of Health, UK Government. Susan Peak

PPP IN THE UK HEALTH SECTOR. Section Head, Capital Investment Branch, Department of Health, UK Government. Susan Peak PPP IN THE UK HEALTH SECTOR Susan Peak Section Head, Capital Investment Branch, Department of Health, UK Government December 2007 Areas covered in presentation: Context the use of PFI (Private Finance

More information

Scottish Government Draft 2010/11 Budget Proposals. Response to the call for evidence from the Health and Sport Committee

Scottish Government Draft 2010/11 Budget Proposals. Response to the call for evidence from the Health and Sport Committee Scottish Government Draft 2010/11 Budget Proposals Response to the call for evidence from the Health and Sport Committee The UNISON Scotland submission to the Scottish Parliament s Health and Sport Committee

More information

One Public Estate. Craig Egglestone, Local Government Association John Goulston, Croydon Health Services NHS Trust

One Public Estate. Craig Egglestone, Local Government Association John Goulston, Croydon Health Services NHS Trust One Public Estate Craig Egglestone, Local Government Association John Goulston, Croydon Health Services NHS Trust https://www.local.gov.uk/topics/housing-and-planning/one-publicestate/about-one-public-estate

More information

Agenda Item: 4.4 Finance Report

Agenda Item: 4.4 Finance Report Agenda Item: 4.4 Finance Report For the period to 31 January 213 and Forecast Outturn for 212/13 CONTENTS 1. Introduction and Background 2. Performance against statutory duties 3. Available Resources 4.

More information

Patient Fare Reimbursement Procedure

Patient Fare Reimbursement Procedure Patient Fare Reimbursement Procedure Version: 2.3 Bodies consulted: na Approved by: PASC Date Approved: 12.5.16 Lead Manager: General Office Manager Lead Director: Deputy Chief Executive Date issued: May

More information

UNIVERSITY HOSPITAL SOUTHAMPTON NHS FOUNDATION TRUST. Activity Management Monitoring

UNIVERSITY HOSPITAL SOUTHAMPTON NHS FOUNDATION TRUST. Activity Management Monitoring UNIVERSITY HOSPITAL SOUTHAMPTON NHS FOUNDATION TRUST Activity Management Monitoring Report to: Trust Board - 29 th November 2011 Report from: Sponsoring Executive: Aim of Report/ Principle Topic: Review

More information

Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009

Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009 Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009 1 CHAPTER 1 EXECUTIVE SUMMARY 1.1 Introduction 1.1.1 This document sets out the Strategic content and Outline Business Case

More information

Martin Riley, Head of Finance

Martin Riley, Head of Finance Gwasanaethau Cronfa Risg Cymru yn is-adran o fewn Partneriaeth Cydwasanaethau GIG Cymru Welsh Risk Pool Services is a division of the NHS Wales Shared Services Partnership Welsh Risk Pool Committee 4 CIRCULATION

More information

NHSGGC Revenue and Capital Report to 31 August 2018 (Paper 18/54) Board Official

NHSGGC Revenue and Capital Report to 31 August 2018 (Paper 18/54) Board Official NHSGGC Revenue and Capital Report to 31 August 2018 (Paper 18/54) Purpose and Format Purpose and Format of Report The purpose of this report is to provide the Board with an update of the current and projected

More information

CWM TAF HEALTH BOARD. FINANCIAL PLAN 2013/14 to 2015/16 FINAL DRAFT

CWM TAF HEALTH BOARD. FINANCIAL PLAN 2013/14 to 2015/16 FINAL DRAFT CWM TAF HEALTH BOARD FINANCIAL PLAN 2013/14 to 2015/16 FINAL DRAFT 3 APRIL 2013 0 1. INTRODUCTION The context for the Financial Plan is outlined below in terms of : Quality and safety Comparisons within

More information

Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014

Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014 TFA document Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014 Tripartite Formal Agreement between: North Bristol NHS Trust NHS Bristol Department of Health Introduction This

More information

Consider report from Capital Planning Group

Consider report from Capital Planning Group NHS Board Meeting 23 April 2008 Paper 10 NHS BOARD MEETING 23 APRIL 2008 Subject : Capital Programme 2008/09 Purpose : Consider report from Capital Planning Group Recommendation : To approve content of

More information

Town of Gawler Special Council Meeting Agenda 14 February 2017

Town of Gawler Special Council Meeting Agenda 14 February 2017 Town of Gawler Special Council Meeting Agenda 14 February 2017 ATTACHMENTS UNDER SEPARATE COVER Item 4.1 Civic Centre Redevelopment Updated Prudential Report ATTACHMENT 1 Prudential Report by Skilmar Systems

More information

Balanced year end position Remain within overall resources

Balanced year end position Remain within overall resources Appendix A Commercial and Investment Finance and Performance Report November 2018 1. SUMMARY 1.1 Finance Previous Status Red Green Category Income and Expenditure Capital Programme Target Balanced year

More information

Quarter Quarter Quarter Additional information / Action taken Non-Residential services commissioned and provided for

Quarter Quarter Quarter Additional information / Action taken Non-Residential services commissioned and provided for Financial Monitoring 2017/18 General Fund Revenue Material s Appendix 2 Education, Communities and Economy Children s Services Reason for Additional information / Action taken Non-Residential services

More information

Risk Management Policy

Risk Management Policy Risk Management Policy Originator: Barbara Gale Chief Executive Review date: April 2015 Revision date: April 2017 Approved by: Finance & Investment Committee Date of meeting: 22 April 2015 Name of Chair:

More information

2017/18 Financial Plan and Budgets. John Ingham, Chief Finance Officer, NHS Norwich CCG. Discussion and Approval

2017/18 Financial Plan and Budgets. John Ingham, Chief Finance Officer, NHS Norwich CCG. Discussion and Approval Agenda Item: 13 NHS Norwich CCG Governing Body Tuesday 28 th March 2017 Subject: Presented By: 2017/18 Financial Plan and Budgets John Ingham, Chief Finance Officer, NHS Norwich CCG Submitted To: NHS Norwich

More information

BOARD OF DIRECTORS COVER SHEET PART 1. DATE: 30 January Subject: CHARITABLE FUNDS EXPENDITURE OVER 25,000

BOARD OF DIRECTORS COVER SHEET PART 1. DATE: 30 January Subject: CHARITABLE FUNDS EXPENDITURE OVER 25,000 BOARD OF DIRECTORS COVER SHEET PART 1 DATE: 3 January 219 Agenda item: 11 Paper: F Subject: CHARITABLE FUNDS EXPENDITURE OVER 25, Prepared by: Presented by: Purpose of paper Background Key points for Board

More information

Trust Board Meeting: Wednesday 13 November 2013 TB

Trust Board Meeting: Wednesday 13 November 2013 TB Trust Board Meeting: Wednesday 13 November 2013 Title Financial Performance to 30 September 2013 Status History For Information This is a regular report. Board Lead(s) Mr Mark Mansfield, Director of Finance

More information

Capital Funding Meeting on 14 th November 2017 Agenda item 2a Capital Programme Funding Update Ian MacDonald, Head of Capital Finance

Capital Funding Meeting on 14 th November 2017 Agenda item 2a Capital Programme Funding Update Ian MacDonald, Head of Capital Finance Finance & Performance Committee ABM University Health Board Capital Funding Meeting on 14 th November 2017 Agenda item 2a Subject Prepared by Approved by Presented by Capital Programme Funding Update Ian

More information

City of Edinburgh Council

City of Edinburgh Council City of Edinburgh Council 10am, Thursday, 10 March 2016 Funding package proposal for a new Meadowbank Item number Report number Executive Wards All, and particularly Craigentinny/Duddingston Executive

More information

TAMESIDE AND GLOSSOP SINGLE COMMISSIONING BOARD. 11 April 2017

TAMESIDE AND GLOSSOP SINGLE COMMISSIONING BOARD. 11 April 2017 TAMESIDE AND GLOSSOP SINGLE COMMISSIONING BOARD 11 April 2017 Commenced: 3.00 pm Terminated: 4.20 pm PRESENT: IN ATTENDANCE: Alan Dow (Chair) Tameside and Glossop CCG Steven Pleasant Tameside Council Chief

More information

The Board is asked to note progress against the current key challenges in relation to the financial performance:

The Board is asked to note progress against the current key challenges in relation to the financial performance: Agenda item 4.1 2011/67 Board Meeting 31 August 2011 SUBJECT: Financial Performance Report for period to 31 July 2011 1. Purpose of the report The purpose of this report is to advise the Board of the financial

More information

Agenda Item AOB Date: 26 June David Evans, Associate Director of Estates and Facilities

Agenda Item AOB Date: 26 June David Evans, Associate Director of Estates and Facilities Trust Board Agenda Item AOB Date: 26 June 2013 Title of Report Purpose of the report and the key issues for consideration/decision Prepared by: Name & Title Presented by: Action Required (please X) Strategic/Corporate

More information

Construction Insurance

Construction Insurance Construction Insurance Product overview All construction, erection and installation work contain an element of risk, whether created by the nature of the work to be carried out, by the contractual liability

More information

BARNSLEY METROPOLITAN BOROUGH COUNCIL

BARNSLEY METROPOLITAN BOROUGH COUNCIL BARNSLEY METROPOLITAN BOROUGH COUNCIL This matter is a Key Decision within the Council s definition and has been included in the relevant Forward Plan Joint Report of the Executive Director-Core Services

More information

2 December In-Year Financial Position (excludes UHMB tariff modification impact)

2 December In-Year Financial Position (excludes UHMB tariff modification impact) NHS Cumbria CCG Governing Body Agenda Item 2 December 2015 14 Finance Report October Purpose of Report: The purpose of the report is to provide the Governing Body with an update on financial issues facing

More information

Consolidated pathology network Commercial structure and operational guide

Consolidated pathology network Commercial structure and operational guide Consolidated pathology network Commercial structure and operational guide February 2018 We support providers to give patients safe, high quality, compassionate care within local health systems that are

More information

SOMERSET PARTNERSHIP NHS FOUNDATION TRUST FINANCE REPORT. Report to the Trust Board 4 July 2018

SOMERSET PARTNERSHIP NHS FOUNDATION TRUST FINANCE REPORT. Report to the Trust Board 4 July 2018 G SOMERSET PARTNERSHIP NHS FOUNDATION TRUST FINANCE REPORT Report to the Trust Board 4 July 2018 Sponsoring Director: Author: Executive Summary Director of Finance. Director of Finance supported by Deputy

More information

Disabled Adaptations Policy

Disabled Adaptations Policy Disabled Adaptations Policy Contents Page 1 Introduction 2 2 Policy Aims 2 3 Relevant legislation 3 4 Definition 3 5 Adaptation process overview 3 6 Examples of work carried out by East Kent Housing 4

More information

GOVERNING BODY FINANCE REPORT MONTH 9

GOVERNING BODY FINANCE REPORT MONTH 9 LEAD: Neil Ferrelly, Chief Finance Officer REPORT AUTHOR: Jenny Sinnott, Head of Finance GOVERNING BODY ATTACHMENT: AGENDA ITEM: 9 H RECOMMENDATION: The Governing Body is asked to note the points raised

More information

NHS (Wales) Summarised Accounts

NHS (Wales) Summarised Accounts PUBLIC AUDIT (WALES) ACT 2004 GOVERNMENT OF WALES ACT 2006 NATIONAL HEALTH SERVICE (WALES) ACT 2006 Summarised accounts of local health boards and NHS trusts in Wales for the year ended 31 March 2017 Presented

More information

The 2014/15 year to date (YTD) revenue position for GYW CCG is 1,565k surplus which is to plan.

The 2014/15 year to date (YTD) revenue position for GYW CCG is 1,565k surplus which is to plan. Governing Body Meeting 27 November 2014 Agenda Item 17 Title of paper What the Committee is being asked to decide or approve Great Yarmouth & Waveney Clinical Commissioning Group Finance & QIPP Report

More information

Balanced year end position Remain within overall resources

Balanced year end position Remain within overall resources Appendix A Commercial and Investment Finance and Performance Report December 2018 1. SUMMARY 1.1 Finance Previous Status Red Green Category Income and Expenditure Capital Programme Target Balanced year

More information

Barnet Partnership Board

Barnet Partnership Board Barnet Partnership Board One Public Estate One Public Estate (OPE) is a Cabinet Office, Government Property Unit (GPU) and Local Government Association (LGA) initiative, established in 2013. OPE actively

More information

Wales Patient Access Scheme: Process Guidance

Wales Patient Access Scheme: Process Guidance Wales Patient Access Scheme: Process Guidance July 2012 (Updated August 2016) This guidance document has been prepared by the Patient Access Scheme Wales Group, with support from the All Wales Therapeutics

More information

Toronto Paramedic Services

Toronto Paramedic Services CAPITAL PROGRAM SUMMARY Highlights Overview and Recommendations I: 10-Year Capital 5 II: Issues for Discussion 18 Toronto Paramedic Services 2016 2025 CAPITAL BUDGET AND PLAN OVERVIEW Toronto Paramedic

More information

Health Board Revenue Allocations

Health Board Revenue Allocations 2011-12 Health Board Revenue Allocations To: Chief Executives - Health Boards Chief Executives - NHS Trusts Mr Paul Williams OBE OStJ DL Director General, Health & Social Services Chief Executive, NHS

More information

CROYDON HEALTH SERVICES CHARITABLE FUND ANNUAL REPORT 2009/2010

CROYDON HEALTH SERVICES CHARITABLE FUND ANNUAL REPORT 2009/2010 CROYDON HEALTH SERVICES CHARITABLE FUND (formerly Mayday Healthcare Charitable Fund) ANNUAL REPORT 2009/2010 Registered Charity No. 1054824 About the Fund Croydon Health Services Charitable Fund ( the

More information

2017/18 Month 3 Financial. Performance Report

2017/18 Month 3 Financial. Performance Report 2017/18 Month 3 Financial 04a.270717 Performance Report Author: Tamira Rolls, Deputy Director of Finance Date: 12 June 2017 Version: 1 Sponsoring Executive Director: Huw George, Deputy Chief Executive/Executive

More information

THE NORTHERN MEDICAL AID SOCIETY

THE NORTHERN MEDICAL AID SOCIETY THE NORTHERN MEDICAL AID SOCIETY Management Rules and Schedule of Benefits As of 1 st November 2013 NMAS Rules 8/13 Page 1 DIGEST OF RULES This digest of rules only contains a summary of those Rules of

More information

Mergers: Motives, Message Management and Morale

Mergers: Motives, Message Management and Morale Mergers: Motives, Message Management and Morale Richard Thomas, Agency Manager Care & Repair Cardiff / Care & Repair in the Vale Matthew Thomas, Director of Customer and Community Services Cardiff Community

More information

GOVERNING BODY. 2. To ensure the CCG financial position recovers to meet all statutory financial duties. X

GOVERNING BODY. 2. To ensure the CCG financial position recovers to meet all statutory financial duties. X Enclosure: H Agenda item: 10 GOVERNING BODY Title of paper: QIPP Report Date of meeting: 21st September 2016 Presented by: Regina Shakespeare Prepared by: Regina Shakespeare and Nick Varney Title: Turnaround

More information

TRUST BOARD. Minutes of a meeting held at Devon House, Heartlands Hospital. on 24 April 2007

TRUST BOARD. Minutes of a meeting held at Devon House, Heartlands Hospital. on 24 April 2007 TRUST BOARD Minutes of a meeting held at Devon House, Heartlands Hospital on 24 April 2007 PRESENT: IN ATTENDANCE: Mr C Wilkinson (Chairman) Ms M Coalter Mrs A East Mrs B Fenton Mr M Goldman Ms N Hafeez

More information

Shetland NHS Board. Board Paper 2017/03

Shetland NHS Board. Board Paper 2017/03 Board Paper 2017/03 Shetland NHS Board Meeting: Shetland NHS Board Paper Title: Capital Programme 2016/17 and 2017/18 Date: January 2017 Author: Lawson Bisset Job Title: Head of Estates, Facilities & Medical

More information

An approved delegation was in place to enter into a voluntary agreement in accordance with Full Council and Cabinet approval:-

An approved delegation was in place to enter into a voluntary agreement in accordance with Full Council and Cabinet approval:- 8.1 Appendix 1 Housing Revenue Account Subsidy (HRAS) System Exit Background Up to 1 April 2015, eleven Welsh landlord authorities operated within a centralised HRA Subsidy system which was deemed complex,

More information

Cash and Treasury Management Policy and Procedure

Cash and Treasury Management Policy and Procedure Cash and Treasury Management Policy and Procedure Date: December 2014 Release: FINAL Lead Manager: John Leslie, Chief Finance Officer Clinical Leads: Not applicable Revision History Author Version Revision

More information

Section 7 Capital Strategy

Section 7 Capital Strategy Capital Strategy Section 7 Section 7 Capital Strategy Contents 1: Introduction 2: Vision and priorities 3: Operating framework 4: Capital expenditure Appendix 1: Allowable capital expenditure Appendix

More information

Report. Chris Ford Joint Chief Finance Officer

Report. Chris Ford Joint Chief Finance Officer Governing Body Meeting held in public Report Date of Meeting: 8 November 2018 Agenda Item: 15.0 Report Title Finance Report as at 30 th September 2018 (Month 6) Report Author Presented By Responsible Director

More information