Ontario s Renewable Energy Standard Offer Program - LDC Information Package

Size: px
Start display at page:

Download "Ontario s Renewable Energy Standard Offer Program - LDC Information Package"

Transcription

1 Ontario s Renewable Energy Standard Offer Program - LDC Information Package Prepared with input and assistance of members of the OPA s Electricity Distributors Working Group Last updated April 03,

2 Disclaimer This information package is intended only as a starting point to identify metering, connection and settlement issues pertaining to t Renewable Energy Standard Offer Program (RESOP) facilities. It provides high level outlines and simplifications of issues, processes and regulatory requirements. This package was prepared based upon information current at the time of preparation and no representation or warranty is provided, nor shall any be implied that such information continues to be accurate or current. Though prepared for an LDC audience, some content may be of interest to project proponents; however, interested proponents must m discuss their plans with their Local Distribution Company (LDC), whose specific requirements and procedures may differ from the general information provided in this package. If there is any conflict between this information package and either the RESOP Rules or the RESOP Contract, the latter will prevail. Similarly, if there is any conflict between this information package and such applicable rules and regulations regarding connection of o electricity generation facilities to a distribution system in Ontario, the latter shall take precedence. 2

3 Acknowledgements The Renewable Energy Standard Offer Program (RESOP) policy was developed over a 2 year period, with program specifics developed in 2006 over several months The OPA chose solutions with the input of stakeholders, via several specific working groups, and other consultation processes The LDC RESOP Information Package is based both on the initial pre-launch work of the Electricity Distributors Working Group, and on subsequent post-launch input by select LDCs and the OEB The Electricity Distributors Working Group (ED WG) had members from Hydro One, the IESO, various LDC volunteer representatives on behalf of the Electricity Distributors Association, the Ontario Ministry of Energy, and the OEB The OPA would like to acknowledge the on-going efforts and input of various LDCs who continued to consult with the OPA and OEB after the launch of the RESOP, with particular thanks to: Graham Henderson, Hydro One Distribution; Gerry Hilhorst, Waterloo North Hydro; Stephen Sottile, KEDL; and Darius Vaiciunas, Collus Hydro The OPA has developed this LDC Information Package for general overview and information exchange. It is an in-progress, living document and so written feedback and suggestions are welcome 3

4 Table of Contents Ontario Renewable Energy Policy and Market Context (slides 5-9) 5 Background and Select RESOP Features (slides 10-23) OEB Code Changes past and future (slides 24-28) 28) Note: OEB is lead agency on issues relating to Select Metering, Settlement and Payment Issues (slides 29-46) Main Meter Configuration Options (slides 47-63) For more Information (slides 64-65) 65) 4

5 Ontario Renewable Energy Policy and Market Context Source: OPA s IPSP Scope and Overview, June 29,

6 Ontario Renewable Energy Policy and Market Context (cont d) Source: OPA s IPSP Scope and Overview, June 29,

7 Ontario Renewable Energy Policy and Market Context (cont d) Procurement Targets Resource Type Near-Term Potential (MW) Committed Near-Term (MW) (%) Un-Committed Near-Term (MW) (%) Conservation and Demand Management 2, % 2, % Renewable Energy Hydroelectric % % Wind 2, % 1,505 61% Biomass % % Subtotal 3,490 1,003 29% 2,487 71% Nuclear 2,020 1,500 74% % Natural Gas 5,520 3,265 59% 2,255 41% Cogeneration/CHP 1, % % IGCC Promising Technologies Solar % Micro CHP/Fuel Cells % Generation Storage 7

8 Ontario Renewable Energy Policy and Market Context (cont d) - Opportunities in a Growing Market Global Annual Investment in Renewable Energy Renewable Global Status Report

9 Ontario Renewable Energy Policy and Market Context (cont d) Drivers: Why Renewable Energy? Climate Change reducing GHG emissions Reduced environmental impacts (cleaner air, water, soil) = less impact on human health and on ecosystems Diversified fuel supply = domestic energy security Electricity rate stability: fixed prices mitigate against future market price increases due to reliance on fossil fuels Distributed generation can promote transmission and distribution system reliability Locating generation close to load can reduce transmission line losses and so reduce need for, or delay, costly Tx and/or Dx infrastructure improvements New project investment = local economic development, diversified tax base & high-skill job creation Positive investment climate can incent new domestic manufacturing plants, reducing costs for future projects 9

10 Background and Select RESOP Features Program History Need to reduce barriers to small renewable generators Government accepts joint OPA/OEB recommendations in March 2006 and directs implementation The OPA role: Eligibility Criteria Pricing Methodology Contact Terms and Conditions The OEB role: Ensuring non-discriminatory access to the electricity system Required changes to Codes and connection requirements 10

11 Background and Select RESOP Features Guiding Principles Keep it simple Remove barriers to smaller renewable developers Balance new renewable generation contribution and value to ratepayers 11

12 Background and Select RESOP Features Who Will Be Eligible for the Program? Fuel/Technology Types Renewable energy projects : wind, thermal electric solar, photovoltaic (PV), renewable biomass, bio-gas, bio-fuel, landfill gas, or waterpower. Capacity Requirements - Installed generating capacity of no more than 10,000 kw. Projects that began commercial operation after November 7, See RESOP Rules for full details 12

13 Background and Select RESOP Features Transmission Issues for Some Applicants Transmission System Constraints account count for capacity limits on getting generation into the grid (similar approach as taken by Ministry of Energy in RES II RFP) - Some transmission areas and zones will experience such Contract issuance restrictions - Some exemptions to these restrictions (see Rules) OPA will ensure that up-to to-date information is available for generators and distributors; see Transmission Constraints on RESOP microsite: Orange Zone map: functional map shows the high- voltage transformer stations in Transmission System which cannot accept new power from LDC feeders - Gx may ask LDCs if their feeder connects to a HV transformer station in Orange Zone 13

14 Background and Select RESOP Features Transmission Issues (Cont d) 14

15 Transmission Issues (Cont d) - Some Tx Dynamic Flow Constraints Within the Bruce Zone Portion of RESOP Orange Zone 15

16 Background and Select RESOP Features Application Eligibility Requirements Contract awarded after the following conditions met by applicant: Completed and current Connection Impact Assessment (<6 mo.) for approx. size of Project, no larger than 10 MW Gross Nameplate Capacity CIA not required by OPA if an In- Service Project or if 10 kw or under Environmental Assessment underway (if applicable) Demonstrated Site Access Authorize OPA access to Gx meter data Other electronic application deliverables 16

17 Background and Select RESOP Features Generator Opportunity: Secure Contract RESOP Contract Term Up to 20 years = securing financing Third Anniversary Requirements Projects must achieve Commercial Operation within 3 years of Contract Waterpower facilities: projects must obtain location approval/ priority permit within 3 years 17

18 Background and Select RESOP Features Opportunities: Program Flexibility Project can be completed in two or more phases All phases of a Project must be in-service within three years (waterpower exceptions) Separate applications required for longer phase-in periods (waterpower exceptions) Incremental Projects are eligible: Total nameplate capacity of initial facility plus RESOP project plus must not exceed 10,000 kw Only the percentage capacity increase is eligible for RESOP payment 18

19 Background and Select RESOP Features Some Generator Issues, Steps and Responsibilities Generators responsible for project development and costs, including successful completion of RESOP Application - Gx determines resource assessment, payback period and feasibility studies ex. RETScreen ( Must contact Local Distribution Company re: CIA if new project, and resolve all metering and connection issues Must obtain municipal approvals for zoning and permits Must obtain relevant approvals from pertinent ministries Environment (screening and approvals) Natural Resources (waterpower) If successfully meet Third Anniversary Requirements, then RESOP Contract Payment provides financing with 20 year term with guaranteed price 19

20 Background and Select RESOP Features Contract Payments under the Program Until April 30/07, all except for Solar $0.11 / kwh On-Peak performance $ / kwh (Gx must apply for incentive) Note that On-Peak Hours RESOP definition differs from RPP definition Escalation for Inflation 20% of Base Rate indexed at CPI Escalation on May 1 st annually Payments for Solar PV $0.42 / kwh, regardless of date $0.42 / kwh is fixed over time; PV not eligible for inflation increases or peak performance under current Program Rules Generator receives RESOP payment from LDC as per DSC and typical utility practice (for example, see slide #45) Nominally, payment is made up of 2 components LDC pays HOEP OPA pays (contract price HOEP) via the LDC through the IESO Pricing Reviews Pricing will be reviewed for future applicants for contracts only y (not retroactive to holders of executed contracts) 20

21 Background and Select RESOP Features Some Connection and Metering Requirements Generator must connect within an eligible distribution system as defined by RESOP Rules Metering under the control of the LDC, and as per OEB s Distribution System Code Hourly data required (by RESOP Rules) for all Gx larger than 10 kw No hourly data required for micro-scale generation (10kW and under), unless micro-gx locating behind load customer meter Gx has sole responsibility for coordinating metering configuration and metering requirements with their LDC RESOP Contract Facility meters must be under the control of the applicable LDC Generator pays for connection and metering 21

22 Background and Select RESOP Features Some Connection and Metering Requirements (Cont d) In terms of metering and settlement of micro-generators of 10 kw and under, Sections 6.1 and 6.3 of the Renewable Energy Standard Offer Program Program Rules Version 2.0 (November 22, 2006) provide some guidance (note, these sections are not limited to micro-gx). Section 6.1 states (in part) that:. Subject to Section 6.3 hereof, Contract Facilities that are less than or equal to 10 kw in Gross Nameplate Capacity will not require meters that provide hourly data until such time as the relevant LDC serving the Contract Facility requires the use of metering that provides hourly data. Section 6.3 states: Where the Contract Facility is connected directly to a Load Customer as permitted in Section 6.2, both the Contract Facility s meter and the Load Customer s meter must provide hourly data, including Contract Facilities of 10 kw or less. 22

23 Background and Select RESOP Features Eligible Distribution System In Which RESOP Gx Can Locate Eligible distribution system eligibility factors: - Generator must connect to an eligible distribution system via a single connection at a voltage of 50 kilovolts (kv) or less - Eligible distribution systems are those that are both: - OEB-licensed and - connected to the IESO-Controlled Grid Note: an embedded LDC may be an eligible Dx system if its host LDC is connected to the IESO-Controlled Grid RESOP contracts are not available in Remote Communities or Cornwall Electric distribution service area LDCs which are exempt Section 26(1) of the Electricity Act which governs the provision of non-discriminatory access would not be required to connect RESOP generators 23

24 OEB Code Changes DSC Amendments in support of RESOP Note: OEB is lead agency on these issues Metering to be as appropriate for RESOP settlement Standardized connection agreement for small and mid-sized generation facilities Distributors to provide contact and technical information to prospective generators 24

25 OEB Code Changes DSC Amendments (cont d) Note: OEB is lead agency on these issues First-come come-first-served served queuing for available Dx capacity Queue position assigned at CIA Position may be held for 12 months Material change in the project will trigger need for a second CIA and reassignment of queue position Does not apply to micro-embedded generation or load displacement only generation DSC Amendment includes a dispute resolution process (binding arbitration) 25

26 OEB Code Changes (Cont d) RSC Amendments Note: OEB is lead agency on these issues Obliges electricity distributors to settle contracts between generators and OPA in accordance with the pricing provisions of the contract Electricity distributors will recover the Market Price Variance associated with these payments through the use of existing IESO settlement processes 26

27 OEB Code Changes Next Steps Note: OEB is lead agency on these issues The OEB Compliance Office intends to issue clarifications on the following issues: A Compliance Bulletin to give clarity in terms of metering which is appropriate for settlement for these two main RESOP Gx connection types, and their variants: Directly connected (i.e. in parallel) Indirectly connected Generators (i.e. in series or behind the load customer s s meter ) 27

28 OEB Code Changes Next Steps (Cont d) Note: OEB is lead agency on these issues Generators to choose Connection Location based on information from LDC LDCs will have discretion in terms of whether RESOP Generators can be treated as new accounts (criteria tba by OEB) LDCs to assign RESOP Gx to existing rate class according to load characteristics and other relevant factors (factors tba by OEB) 28

29 Select Metering, Settlement and Payment Issues - Contract Payment and GST treatment by LDCs A generator with a RESOP Contract may be required to register, collect and remit GST applicable to Contract Payments It is the sole responsibility of the RESOP Generator to determine their GST status and to complete any relevant submissions - If the Excise Tax Act applies to the Generator, it must provide the OPA with written notice of its GST registration number, and the OPA will inform the LDC. The CRA may require it to register with the CRA - If the Excise Tax Act does not apply to the Generator, it must inform the OPA of its GST status before it declares Commercial Operation, and the OPA will inform the LDC It is recommended that all RESOP Generators obtain independent GST, tax and legal advice pertaining to the RESOP Contract 29

30 Select Metering, Settlement and Payment Issues - Contract Payment and GST treatment by LDCs (Cont d) As per Section 5.1(c) of the RESOP Contract, the OPA has no obligation to make any Contract Payments if the generator does not first (1) provide notice in writing to the OPA of its GST status,and (2) if a registrant, provide its GST registration number to the OPA The LDC s s regulatory obligation is settle with the generator in accordance with the RESOP Contract In order to receive RESOP Contract Payments from the LDC, the Generator must first properly declare Commercial Operation with the OPA Then the OPA must provide the LDC with the Generator s s self-declared GST status (and if applicable, its GST registration number) so that the LDC can properly issue Contract Payment (and if applicable, remit GST) 30

31 Select Metering, Settlement and Payment Issues LDC Settlement Systems Setting up the LDC Billing System to Invoice, Track, and Record settlements for the RESOP will involve some planning to manage 20 year contracts. An LDC may choose to use combinations of Rate Codes, Customer Classifications or Customer Categories to track RESOP Settlements The next set of slides provides an overview of scenarios related to RESOP Billing and Tracking to provide insight to an LDC when designing their systems for RESOP Settlements 31

32 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements The RESOP Requires the LDC to pay the Generator for the energy delivered to the Distribution System at the OPA Contract Price (CP). Given that the contracts will have different start times and the OPA will be reviewing Contract Pricing on a regular basis, the CP tracking in a Settlements System will need to be specific to groups of Generation Facilities. For Example: In Year 1 (up to April 30, 2007): Generator 1 will have the fixed price of 11 cents per kwh for all output. Generator 2 will have the fixed price of 42 cents per kwh for all output. Generator 3 will have the Performance Incentive and thereby is paid 11 cents for all output during off peak times, and cents during peak times. 32

33 Select Metering, Settlement and Payment Issues Discussion of RESOP Settlements (Cont d) The Base Rate of cents per kwh is escalated at 20% of the annual CPI. Now the pricing for RESOP Generators would be as follows: In Year 2 (from May 01, 2007 to April 30, 2008): Generator 1 receives the fixed price of cents per kwh for all output. Generator 2 receives the fixed price of 42 cents per kwh for all output. Generator 3 receives the Performance Incentive and thereby is paid cents for all output during off peak times, and cents during On-Peak Hours (as defined under RESOP). 33

34 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements (Cont d) From a Billing and Payment Perspective, it is likely for a single non-pv generator to have a different rate each year of the 20 year contract due to the CPI increase calculations. Given that an LDC must be able to track payments and credits on an ongoing basis, one option for keeping track of the various payments would be to establish a new rate tied to a rate change for each new contract rate. Using the examples outlined, the LDC could set up 4 rates for year 1 (ending April 30/07): Rate A1 = (11 Cents for all output) Rate B1 = (42 Cents for all output) Rate C1 = (11 Cents for Off-Peak Output) Rate D1 = (14.52 Cents for On-Peak Output) OR the LDC can set up 3 rates for year 1: Rate A1 = (11 Cents for all output) Rate B1 = (42 Cents for all output) Rate C1 = (3.52 Cent Rider for On-Peak Output tied to Rate A) 34

35 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements (Cont d) Assuming the 4 Rate Option, the LDC would set up additional rates for year 2 (beginning May 1/07 ending April 30/08): Rate A2 = (11.04 Cents for all output) Rate C2 = (11.04 Cents for Off-Peak Output) Rate D2 = (14.56 Cents for On-Peak Output) In this way - a Generator's Payments could be re-calculated by tying a specific rate to delivered output at any given time in a calendar year. This would provide an easy method of re-calculating costs during audit processes etc. Since the RESOP rules state that the Solar PV rate will not be indexed, there would likely be no need to establish a rate B2. 35

36 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements (Cont d) Under the basic concepts of settlements, the LDC settles with all Generators at the HOEP, and collects from all Consumers at HOEP. This practice keeps the LDC indifferent to the supply and sale of electricity. At the most basic of concepts, an LDC would purchase all power from the IESO at HOEP and sell all the power to the Consumers at HOEP. 36

37 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements (Cont d) Embedded Generators: When some of the power is purchased from the IESO and some from an Embedded Generator, the balance remains intact if all Consumers pay at HOEP and all Generators are paid at HOEP. The change here would simply be where the HOEP dollars flow to, some to the IESO, and some to the Embedded Generator. Assuming that all power is sold to consumers at HOEP, this means that there are adjustments performed to settlements when other parties or rates are involved. For example... 37

38 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements (Cont d) Retailer Contracts: An LDC collects from the Customer the Retailer Rate for energy consumed, and settles with the Retailer for the difference between HOEP and the Retailer Rate for that same unit of energy. (Retailer Settlements) This leaves the LDC with the HOEP equivalent value for every kwh sold. RPP Split Rate: An LDC collects from the Customer the RPP Split Rate for Energy Consumed, and settles with the IESO for the difference between the HOEP and the RPP Split Rate for that same unit of energy (using Form 1598). This leaves the LDC with the HOEP equivalent value for every kwh sold. 38

39 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements (Cont d) Generators Receiving Rates other than the HOEP: Under the RESOP, Generators will be receiving contract rates which differ from the HOEP. Since the settlements processes noted above are in place to ensure the LDC always receives HOEP for energy sold to consumers, a similar process needs to be in place to ensure the LDC can pay the Generators the difference between HOEP and the Contract Rate. The IESO settlements system (through Form 1598) will be used to manage the difference between HOEP and the RESOP Rate that the LDC must pay the Generator. 39

40 Select Metering, Settlement and Payment Issues - Discussion of RESOP Settlements (Cont d) In an effort to centralize the reporting and tracking of the RESOP program, the IESO (as a tracking condition requested by the OPA) requires a variety of information, in addition to the variance between HOEP and RESOP dollars reported on the Form Dollar Variance (Positive or Negative) between HOEP and RESOP energy Purchased from Generators. Total kwh's related to the Dollars Further to the basic requirements, the Dollars and kwh's need to be split out to On- Peak and Off-Peak periods in order to allow the OPA to track the costs and benefits related to the On-Peak Performance Incentive Payment. This information is required to be further split out based on the four main renewable energy categories under the RESOP: Wind; Biomass; Small Hydro; Solar Photovoltaic 40

41 Select Metering, Settlement and Payment Issues Discussion of RESOP Settlements (Cont d) Draft Form 1598 (current form at 41

42 Select Metering, Settlement and Payment Issues Discussion of RESOP Settlements (Cont d) Given the additional tracking required, an LDC will need to identify the various forms of Generators in their CIS either as part of their Customer Category, or through the use of additional Rate Codes. Setting up different categories of Generators would enable an LDC to attach the different rate codes to each Generator as required. Using the examples described in the General Notes, one could envision the following... Wind Generator = Rate A1 Biomass = Rate A1 Biomass = Rate C1 & D1 Small Hydro = Rate A1 Small Hydro = Rate C1 & D1 Year 1 (if they qualify for On-Peak Incentive) (if they qualify for On-Peak Incentive) Solar Photovoltaic = Rate B1 42

43 Select Metering, Settlement and Payment Issues Discussion of RESOP Settlements (Cont d) On-Peak vs Off-Peak - (Form 1598 Reporting) When calculating Off-Peak dollars and kwh's - include the base rate dollar variance for Off-Peak kwh's only. - for a generator receiving the fixed rate without the On-Peak Performance Incentive, all their kwh s would be treated as Off-Peak When calculating On-Peak dollars and kwh's - include On-Peak kwh's and total Dollars ( X kwh's) - for a Generator receiving the On-Peak Performance Incentive, the full cost of the On-Peak kwh s should be reported separate from Off-Peak Note: The On-Peak Periods are defined in the RESOP as Business Days from 11:00 am to 7:00 pm, and Business Days have their own definition. The Off-Peak Periods are defined as All Other Hours 43

44 Select Metering, Settlement and Payment Issues Discussion of RESOP Settlements (Cont d) A generator is essentially a manufacturer whose product is electricity. At times when the generators' production facility is not on-line, the facility requires energy to support what are referred to as Parasitic or House Loads or Station Service. This energy is purchased from other generators, and must be paid for. Therefore a generator can be both a consumer and a supplier at any given time. As a result, it is necessary (in most cases) to measure the energy flow through the meter in both directions. The settlement statement sent to the Generator would include both a charge for the energy purchased from other generators (when total Station Service is not self-supplied), and a payment for energy generated when they are on-line and producing electricity. 44

45 Select Metering, Settlement and Payment Issues Discussion of RESOP Settlements (Cont d) Metering and Settlements of generation facilities will vary depending on the location and type of facility involved. The simplest form of generation customer is a stand-alone generation facility. A stand-alone generation facility may be primary metered or secondary metered (metered on the High Side, or Low Side of the Dx Transformer) For Settlements, a Consumer is considered to have received power at the low side of the transformer, and a Generator is considered to have delivered power to the grid at the high side of the transformer. Since a generator can be both a supplier and consumer of electricity at different times, and since it is most cost efficient to install only one meter, this means that the consumed value or the delivered value is adjusted accordingly, depending on which side of the transformer the meter is located. 45

46 Select Metering, Settlement and Payment Issues Discussion of RESOP Settlements (Cont d) Electricity Sales to a Consumer are measured by the meter and adjusted by the OEB approved Loss Factor and (if required) will receive the Primary Metering Discount of 1%. Electricity Purchases from a Generator that is Primary Metered will not require adjustments. Electricity Purchases from a Generator that is Secondary Metered would be subject to the 1% Primary Metering Discount (or Site Specific Loss Factor) as a default. RSC Section 3.2 A distributor shall calculate its weighted average supply facility loss factor by summing energy delivered at each of the supply facility points plus associated supply facility losses, including all supplies from the transmission system, supplies from all embedded generators and supplies from host distributors which sum shall be divided by the total energy delivered at all of the supply facility delivery points. Each of these supplies shall be adjusted for the appropriate loss factor representing the energy losses between the meter point and the defined point of sale. 46

47 Arrows denote Measurement Direction Deemed point of sale for RESOP Transformer Location Main Meter Configuration Options & Settlement No Existing Load Customer Stand-alone Generator Customer Secondary Metered: ~ m1 Distribution System Settlements: Energy delivered reduced by Site Specific Losses. RESOP Rate (kwh / (1+SSL)) x RESOP Rate Energy consumed increased by LDC approved loss factor. Billed at HOEP. (kwh x (1+LDCL)) x HOEP Primary Metered: ~ m1 Distribution System Settlements: Energy delivered- No adjustment required. RESOP Rate. kwh x RESOP Rate Energy consumed increased by LDC approved loss factor less 1% for primary metering discount. HOEP. (kwh x (1+LDCL)) x.99 x HOEP Note: Load Customer (Station Service) is also required to pay for additional energy related charges: WMSC, DRC, Network Service, Line & Transformation, and Distribution Variable Charges. 47

48 Meter Configuration Options & Settlement - Direct Connect Generator Sharing a Secondary Transformer with a Separate Load In some cases, a generator may choose to establish themselves on the site of an existing customer, and share a transformer. This may significantly reduce the costs of this type of connection (though other connection types may be more economic). Secondary Metered: ~ m1 Settlements - Generator: Energy delivered reduced by Site Specific Losses (kwh / (1+SSL)) x RESOP Rate Energy consumed increased by LDC approved loss factor (kwh x (1+LDCL)) x HOEP Secondary Metered: LOAD m2 Distribution System Settlements - Load: Energy consumed increased by LDC approved loss factor. (kwh x (1+LDCL)) x HOEP or (kwh x (1+LDCL)) x RPP In this example, the consumer and the generator are sharing a transformer. They are connected in parallel on the secondary side of the transformer. The LDC may choose to treat them as fully separated accounts. The Load Customer s metered value is calculated as a normal consumer with LDC approved losses applied to the metered consumption. The Generator s metered values are also adjusted: - Consumed Energy is adjusted using the LDC approved Total Loss Factor - Delivered Energy is adjusted to account for the Transformer Losses and SSL if necessary 48

49 Meter Configuration Options & Settlement Direct Connect Generator and Load Customer Each have a Separate Transformer These two examples depict how either Primary Metering or Secondary Metering configurations can account for a generator who locates on a load customer s premises, where the generator connects to the grid in Parallel to the existing load customer without sharing the load customer s transformer (i.e. the generator has a separate transformer) Primary Metered: ~ m1 Secondary Metered: LOAD Primary Metered: m2 ~ m1 Primary Metered: LOAD m2 Distribution System Distribution System Settlements - Generator: Energy delivered no adjustment required kwh x RESOP Rate Energy consumed increased by LDC approved loss factor less 1% Primary Metering discount. (kwh x (1+LDCL)) x.99 x HOEP Settlements - Load: Energy consumed increased by LDC approved loss factor. (kwh x (1+LDCL)) x HOEP or Settlements - Generator: Settlements - Load: (kwh x (1+LDCL)) x RPP Energy delivered no adjustment required kwh x RESOP Rate Energy consumed increased by LDC approved loss factor less 1% Primary Metering discount. (kwh x (1+LDCL)) x.99 x HOEP Energy consumed increased by LDC approved loss factor less 1% Primary Metering Discount. (kwh x (1+LDCL)) x.99 x HOEP or RPP (kwh x (1+LDCL)) x.99 x 49

50 Meter Configuration Options & Settlement Generator Located Behind an Existing Load Customer (aka the Load Displacement Option ) In some cases, a generator may establish themselves on the site of an existing customer, and wish to provide power directly to the customer, with only the excess generation reaching the grid. This is generally referred to as a Load Displacement Generator. For proper RESOP settlements, the Generator s meter must be downstream of the customer s meter in order to ensure the generator receives appropriate RESOP payment on their full output (not just the excess reaching the grid). Additionally, to properly calculate the RESOP payment, both the customer and generator meter may need to be able to measure energy flow in both directions. Secondary Metered: ~ m1 m2 LOAD Distribution System 50

51 Renewable Energy Standard Offer Program Settlements Avoiding Any Double-counting of the Power Output Section 5.6 of the Renewable Energy Standard Offer Program - Program Rules, Version 2.0 (November 22, 2006) states: In accordance with the provisions of Section 6.4, where a Contract Facility is connected directly to a Load Customer and has its meter configured in a manner which reduces the amount payable by the Load Customer to the LDC for its metered consumption of Electricity because part or all of the Load Customer s Electricity consumed is supplied from the Contract Facility, Contract Payments will be reduced by an amount equal to the Hourly Ontario Energy Price in respect of the Hourly Delivered Electricity consumed by the Load Customer. In the event that such reduction results in a negative Contract Payment, a corresponding amount shall be paid by the Generator to the OPA (underlined emphasis added). Secondary Metered: ~ m1 m2 LOAD Distribution System 51

52 Renewable Energy Standard Offer Program Settlements Use of two Bi-Directional Meters May Be An Appropriate Option Why Might an LDC Insist on Two Bi-Directional Meters? Using the diagram below, output of the Generation Facility is fully measured by the meter M1; however, the meter M2 only captures the amount of energy supplied from the grid when the Generator is producing less than the Load is consuming. Depending on the amount of energy consumed and the amount of energy generated at any given time, all four metered values may be required to establish proper settlement calculations. Secondary Metered: ~ m1 m2 LOAD Distribution System 52

53 Arrows denote Measurement Direction Deemed point of sale for RESOP Transformer Location Main Meter Configuration Options and Settlement - Load Displacement Option Secondary Metered: ~ m1 m2 Load Displacement Generator and Load Customer Settlements - Generator: Energy delivered reduced by Site Specific Losses and contract payment reduced by HOEP LOAD Distribution System [(m1 Delivered x Site Specific Losses) x (Standard Offer Price)] minus [(m1 Delivered - M2 Delivered ) x HOEP] Energy consumed increased by LDC approved loss factor m1 consumed (kwh x (1+LDCL)) x HOEP Note: Load Customer is also required to pay for additional energy related charges: WMSC, DRC, Network Service, Line & Transformation, and Distribution Variable Charges. Settlements Load: Energy consumed increased by LDC approved loss factor (m2 consumed kwh - m1 consumed kwh) x (1+LDCL))] x (HOEP) 53

54 Main Meter Configuration Options and Settlement - Load Displacement Option (cont d) Example 1: Generator Output of 1,500 kwh s Load Consumption of 1,000 kwh s M1 Output = 1500 M1 Input = 0 M2 Output = 500 M2 Input = 0 Load Consumption = = 1000 Generator RESOP Settlement : (1500 X RESOP Rate) (1000 X HOEP) For simplicity loss calculations have been omitted Customer Charge : M2 Input = 0 Secondary Metered: ~ m1 m2 LOAD Distribution System 54

55 Main Meter Configuration Options and Settlement - Load Displacement Option (cont d) Example 2: Generator Output of 1,000 kwh s Load Consumption of 1,000 kwh s M1 Output = 1000 M1 Input = 0 M2 Output = 0 M2 Input = 0 Load Consumption = = 1000 Generator RESOP Settlement : (1000 X RESOP Rate) (1000 X HOEP) For simplicity loss calculations have been omitted Customer Charge : M2 Input = 0 Secondary Metered: ~ m1 LOAD m Distribution System 55

56 Main Meter Configuration Options and Settlement Load Displacement Option (cont d) Example 3: Generator Output of 500 kwh s Load Consumption of 1,000 kwh s M1 Output = 500 M1 Input = 0 M2 Output = 0 M2 Input = 500 Generator SOP Settlement : (500 X RESOP Rate) (500 X HOEP) Customer Charge : M2 Input = 500 Load Consumption = = 1000 Secondary Metered: ~ m1 m2 LOAD Distribution System 56

57 Main Meter Configuration Options and Settlement - Load Displacement Option (cont d) Example 4: Generator RESOP Settlement: Generator Output of 0 kwh s Generator Consumption of 100 kwh s Load Consumption of 1,000 kwh s M1 Output = 0 M1 Input = 100 M2 Output = 0 M2 Input = 1100 Load Consumption = = 1000 (0 x RESOP Rate) - (0 x HOEP) Generator Charge : M1 Input = 100 Customer Charge : M2 Input M1 Input = 1000 Secondary Metered: 0 0 ~ m1 m2 LOAD Distribution System 57

58 Example 5: Main Meter Configuration Options and Settlement - Load Displacement Option (cont d) Generator RESOP Settlement : Generator Output of 1,000 kwh s Generator Consumption of 100 kwh s Load Consumption of 1,400 kwh s M1 Output = 1000 M1 Input = 100 M2 Output = 0 M2 Input = 500 Load Consumption = ( ) + ( ) = 1100 (1000 x RESOP Rate) (700 x HOEP) Generator Charge: M1 Input = 100 Customer Charge : M2 Input M1 Input = 400 Secondary Metered: ~ m1 LOAD 700 m Distribution System 58

59 Arrows denote Measurement Direction Deemed point of sale for RESOP Transformer Location Secondary Metered: Main Meter Configuration Options and Settlement Net Metering Is Not an Option for RESOP Generator and Load Customer Sharing One Meter (Simple Net Metering, not RESOP) ~ LOAD Primary Metered: ~ LOAD m1 m1 Distribution System Distribution System Note: Net Metering Regulations also require calculating credit to customer on Additional Charges: WMSC, DRC, Network Service, Line & Transformation, and Distribution Variable Charges. Settlements: Energy delivered with no adjustment for Losses. (O. Reg. 541/05, s. 8 (2) ) kwh x (RPP or HOEP) Rate Energy consumed increased by LDC approved loss factor. (kwh x (1+LDCL)) x (RPP or HOEP) Rate Settlements: Energy delivered with no adjustment for losses. (O. Reg. 541/05, s. 8 (2) ) kwh x (RPP or HOEP) Rate Energy consumed increased by LDC approved loss factor less 1% for primary metering discount. HOEP. (kwh x (1+LDCL)) x.99 x (RPP or HOEP) Rate 59

60 RESOP Settlement Examples of Physical Metering In this Diagram the green arrows depict the normal flow of electricity from the service entrance through the meter and into the load panel Service Entrance To House Panel 60

61 RESOP Settlement Examples of Physical Metering (Cont d) In this Diagram we have added a second meter configured to measure the energy output of a micro-generator of 10 kw or under To House Panel From Generator Service Entrance Tracing the red arrows one can see that the generator s output is delivered (in parallel) to either the grid or to the consumer. This is not Load Displacement since all the energy consumed is separately metered and as such according to the rules of the RESOP, would not be required to be an hourly meter. 61

62 RESOP Settlement Examples of Physical Metering (Cont d) Settlements would be based on the Fixed RESOP Price multiplied by the total energy registered through the generator meter. To House Panel From Generator Service Entrance If the micro-scale generator does not provide hourly data, it will not be possible to calculate the HOEP for the variance amount to be claimed through the IESO Form 1598 LDC to use Second Tier of RPP for Variance Calculation. (RESOP Rate X Kwh) * Minus * (Tier2 X Kwh) 62

63 RESOP Settlement Examples of Physical Metering (Cont d) In a parallel metering configuration, it could be possible for a customer to purposely or inadvertently connect a load to the generator side of the second meter. If a load connects on the secondary side of a generator with a unidirectional meter, this would in essence provide free power from the LDC to the new load. Similarly, if a unidirectional meter was To House Panel To Second Load Service Entrance installed to measure the output of a parallel connection generator, then at times of low or no generation, it may be that station service would then be supplied by the LDC (i.e. a solar PV system at night). Again, the customer would in essence be able to get free power from the LDC. Thus, LDC s may insist on a bi-directional meter to monitor the Generation. 63

64 For Further Information OPA Renewable Energy Standard Offer Program Website: OEB Renewable Energy Standard Offer Program Websites: /ongoingprojects_standardofferprogram.htm and entre/fsheets-elec/fs_sop_questionstoask.htm elec/fs_sop_questionstoask.htm and entre/fsheets-elec/fs_sop_gettingconnected.htm elec/fs_sop_gettingconnected.htm IESO Form 1598 (note the SOP tab): _FORM_1598.xls 64

65 For Further Information (cont d) Generation Connection ; ; Hydro One: s/generation_connections/ and Connecting New Generation to Hydro One s s Electricity System ; ; Hydro One: s/generation_connections/distribution/default.asp [Note: the 2 nd link provides sample CIA forms of potential interest to LDCs] Guidelines for Applicants Connecting Distributed Generation ; ; Cornerstone Hydro Electric Concepts (CHEC Group): eneration_guide_aug10_2006.pdf Guide for Distributed Generators ; ; Kingston Electricity Distribution Ltd. (KEDL): ml 65

microfit RULES Version 1.6 December 8, 2010

microfit RULES Version 1.6 December 8, 2010 microfit RULES Version 1.6 December 8, 2010 Ontario Power Authority, 2010 RULE CHANGE (May 19, 2010) IN-SERIES METERING IS NO LONGER PERMITTED UNDER THE microfit RULES. In-series metering is no longer

More information

microfit RULES Version 4.1 January 1, 2017

microfit RULES Version 4.1 January 1, 2017 microfit RULES Version 4.1 January 1, 2017 Independent Electricity System Operator, 2017 Table of Contents Section 1 Introduction...1 1.1 Background to the microfit Program... 1 1.2 Important Information

More information

MicroFIT: An Introduction

MicroFIT: An Introduction MicroFIT: An Introduction By Thomas Brett, Partner Introduction On September 24 th, in conjunction with the FIT Program, the Ontario Government announced the MicroFIT Program ("MicroFIT"), a streamlined,

More information

FEED-IN TARIFF MICROFIT CONTRACT Version 3.3 Part 1 Contract Details

FEED-IN TARIFF MICROFIT CONTRACT Version 3.3 Part 1 Contract Details FEED-IN TARIFF MICROFIT CONTRACT Version 3.3 Part 1 Contract Details The Independent Electricity System Operator ( IESO ) is offering the microfit Program pursuant to Ministerial Direction issued pursuant

More information

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

FEED-IN TARIFF CONTRACT (FIT CONTRACT) FEED-IN TARIFF CONTRACT (FIT CONTRACT) Version 1.5.1 (July 15, 2011) CONTRACT IDENTIFICATION # FIT REFERENCE # FIT- FIT- CONTRACT DATE SUPPLIER SUPPLIER S ADDRESS SUPPLIER INFORMATION GROSS NAMEPLATE CAPACITY

More information

Independent Electricity System Operator Licence EI

Independent Electricity System Operator Licence EI Licence Valid Until September 25, 2033 Original signed by Peter Fraser Vice President, Industry Operations & Performance Ontario Energy Board Date of Issuance: September 26, 2013 Date of Amendment: July

More information

2019 PRICE CAP INCENTIVE REGULATION ELECTRICITY DISTRIBUTION RATE APPLICATION

2019 PRICE CAP INCENTIVE REGULATION ELECTRICITY DISTRIBUTION RATE APPLICATION 2019 PRICE CAP INCENTIVE REGULATION ELECTRICITY DISTRIBUTION RATE APPLICATION November 2, 2018 SIOUX LOOKOUT HYDRO INCORPORATED 25 FIFTH AVENUE, P.O. BOX 908 SIOUX LOOKOUT, ON P8T 1B3 Contents MANAGER

More information

REGULATORY ACCOUNTS. The purpose of this Exhibit is to provide a description of Hydro One Distribution s regulatory accounts.

REGULATORY ACCOUNTS. The purpose of this Exhibit is to provide a description of Hydro One Distribution s regulatory accounts. Updated: 000 Tab Page of REGULATORY ACCOUNTS. INTRODUCTION The purpose of this Exhibit is to provide a description of Hydro One Distribution s regulatory accounts. 0 All of the regulatory accounts reported

More information

TNUoS Tariffs in 10 minutes March 2018

TNUoS Tariffs in 10 minutes March 2018 TNUoS s in 10 minutes March 2018 An overview of TNUoS tariffs This information paper provides an overview of National Grid s Transmission Network Use of System (TNUoS) tariffs, applicable to transmission

More information

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

FEED-IN TARIFF CONTRACT (FIT CONTRACT) FEED-IN TARIFF CONTRACT (FIT CONTRACT) Version 2.1.1 March 22, 2013 SUPPLIER INFORMATION & ADDRESS 1. 2. SUPPLIER S ADDRESS COMPANY REPRESENTATIVE Fax: Phone: E-mail: 3. SUPPLIER INFORMATION Not a Non-Resident

More information

Canadian Manufacturers & Exporters (CME) INTERROGATORY #1 List 1

Canadian Manufacturers & Exporters (CME) INTERROGATORY #1 List 1 Filed: December, 00 Schedule Page of 0 0 0 0 Canadian Manufacturers & Exporters (CME) INTERROGATORY # List General Issues. Ref: Exhibit A, Tab, Schedule, paragraph Exhibit A, Tab, Schedule, page Exhibit

More information

Electricity Power System Planning

Electricity Power System Planning Chapter 3 Section 3.02 Ministry of Energy Electricity Power System Planning Standing Committee on Public Accounts Follow-Up on Section 3.05, 2015 Annual Report The Committee held a public hearing in November

More information

Transmission Connection Procedures EB

Transmission Connection Procedures EB Transmission Connection Procedures Transmission Connection Procedures Table of Contents 1.0 INTRODUCTION...1 2.0 HYDRO ONE CONNECTION PROCEDURES...4 2.1 TOTAL NORMAL SUPPLY CAPACITY PROCEDURE...5 2.2 AVAILABLE

More information

RATE DESIGN. The proposed distribution rates for each rate class over the Custom COS period are summarized in Table 1.

RATE DESIGN. The proposed distribution rates for each rate class over the Custom COS period are summarized in Table 1. Updated: 0-0-0 EB-0-0 Exhibit G Schedule Page of RATE DESIGN.0 INTRODUCTION The purpose of this evidence is to present the proposed rates designed to collect the revenue requirement as determined by the

More information

TRANSMISSION LOAD CONNECTIONS

TRANSMISSION LOAD CONNECTIONS TRANSMISSION LOAD CONNECTIONS HYDRO ONE NETWORKS INC. SEPTEMBER 2014 BACKGROUND Important Information for Transmission Load Customers This package was published for s Tx Load Customers as a supplement

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER TILLSONBURG HYDRO INC. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information

Achievable Potential Study FAQs for LDCs

Achievable Potential Study FAQs for LDCs Achievable Potential Study FAQs for LDCs November 25, 2016 1. What is the Achievable Potential Study? The IESO is required, through direction from the Minister of Energy, to conduct an Achievable Potential

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB KENORA HYDRO ELECTRIC CORPORATION LTD.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB KENORA HYDRO ELECTRIC CORPORATION LTD. Commission de l énergie de l Ontario DECISION AND RATE ORDER KENORA HYDRO ELECTRIC CORPORATION LTD. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information

Ontario Energy Board Commission de l énergie de l Ontario

Ontario Energy Board Commission de l énergie de l Ontario Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER HYDRO ONE NETWORKS INC. Application for electricity distribution rates and other charges beginning January 1, 2017 BEFORE:

More information

Regional Planning and Cost Allocation Review EB Working Group meeting #1 - Webinar

Regional Planning and Cost Allocation Review EB Working Group meeting #1 - Webinar Regional Planning and Cost Allocation Review EB-2016-0003 Working Group meeting #1 - Webinar Tuesday July 12, 2016 1 Agenda 1) Introduction OEB 2) Presentation IESO 3) Presentation Hydro One 4) Discussion

More information

POWER TO CONNECT A ROADMAP TO A BRIGHTER ONTARIO

POWER TO CONNECT A ROADMAP TO A BRIGHTER ONTARIO POWER TO CONNECT A ROADMAP TO A BRIGHTER ONTARIO FEBRUARY 2018 TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 1 2. INTRODUCTION AND BACKGROUND 6 2.1 Background on the EDA s Vision Paper: The Power to Connect 6

More information

FEED-IN TARIFF MICROFIT CONTRACT Version 2.0 Part 1 Contract Details

FEED-IN TARIFF MICROFIT CONTRACT Version 2.0 Part 1 Contract Details FEED-IN TARIFF MICROFIT CONTRACT Version 2.0 Part 1 Contract Details The Ontario Power Authority ( OPA ) is offering the microfit Program pursuant to Ministerial Direction issued pursuant to Section 25.35

More information

Balsam Lake Coalition Interrogatory # 8

Balsam Lake Coalition Interrogatory # 8 Tab Schedule BLC- Page of 0 0 0 Balsam Lake Coalition Interrogatory # Issue : Are the proposed amounts, disposition and continuance of Hydro One s existing deferral and variance accounts appropriate? Ontario

More information

No An act relating to the Vermont energy act of (S.214) It is hereby enacted by the General Assembly of the State of Vermont:

No An act relating to the Vermont energy act of (S.214) It is hereby enacted by the General Assembly of the State of Vermont: No. 170. An act relating to the Vermont energy act of 2012. (S.214) It is hereby enacted by the General Assembly of the State of Vermont: * * * Renewable Energy Goals, Definitions * * * Sec. 1. 30 V.S.A.

More information

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Advisory Service for Energy and Climate Change John Lambert Senior Business Development Manager Direct Energy

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB COLLUS POWERSTREAM CORP.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB COLLUS POWERSTREAM CORP. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER COLLUS POWERSTREAM CORP. Application for an order approving just and reasonable rates and other charges for electricity

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ORANGEVILLE HYDRO LIMITED

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ORANGEVILLE HYDRO LIMITED Commission de l énergie de l Ontario DECISION AND RATE ORDER ORANGEVILLE HYDRO LIMITED Application for an order approving just and reasonable rates and other charges for electricity distribution to be

More information

DECISION AND ORDER ON PHASE 1

DECISION AND ORDER ON PHASE 1 Commission de l énergie de l Ontario DECISION AND ORDER ON PHASE 1 HYDRO ONE NETWORKS INC. Leave to construct a new transmission line and facilities in the Windsor-Essex Region, Ontario. Before: Ken Quesnelle

More information

STANDING COMMITTEE ON PUBLIC ACCOUNTS

STANDING COMMITTEE ON PUBLIC ACCOUNTS STANDING COMMITTEE ON PUBLIC ACCOUNTS ELECTRICITY POWER SYSTEM PLANNING (Section 3.05, 2015 Annual Report of the Office of the Auditor General of Ontario) 2 nd Session, 41 st Parliament 66 Elizabeth II

More information

PARTIAL DECISION AND RATE ORDER

PARTIAL DECISION AND RATE ORDER Ontario Energy Board Commission de l énergie de l Ontario PARTIAL DECISION AND RATE ORDER KITCHENER-WILMOT HYDRO INC. Application for rates and other charges to be effective January 1, 2018 BEFORE: Lynne

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB VERIDIAN CONNECTIONS INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB VERIDIAN CONNECTIONS INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER VERIDIAN CONNECTIONS INC. Application for rates and other charges to be effective May 1, 2018 By Delegation, Before: Jane

More information

CHAPLEAU PUBLIC UTILITIES CORPORATION ED IRM APPLICATION EB

CHAPLEAU PUBLIC UTILITIES CORPORATION ED IRM APPLICATION EB CHAPLEAU PUBLIC UTILITIES CORPORATION ED-2002-0528 2018 IRM APPLICATION EB-2017-0337 Rates Effective: May 1, 2018 Submitted on: February 9, 2018 Chapleau Public Utilities Corporation 110 Lorne St. S Chapleau,

More information

GUELPH HYDRO ELECTRIC SYSTEMS INC.

GUELPH HYDRO ELECTRIC SYSTEMS INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER GUELPH HYDRO ELECTRIC SYSTEMS INC. Application for an order approving just and reasonable rates and other charges for electricity

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, (Schedule B); EB20170266 IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, (Schedule B); AND IN THE MATTER OF an application by Peterborough Distribution Inc. for an order approving just and reasonable

More information

EXECUTIVE SUMMARY OF APPLICATION

EXECUTIVE SUMMARY OF APPLICATION Updated: 0-0-0 EB-0-00 Page of EXECUTIVE SUMMARY OF APPLICATION. SCOPE OF APPLICATION Hydro One Networks Inc. ( Hydro One ) is applying for an Order approving the revenue requirement, cost allocation and

More information

Global Adjustment. Overview. Christine Woon, P. Eng. Key Account Specialist Customer Care

Global Adjustment. Overview. Christine Woon, P. Eng. Key Account Specialist Customer Care Global Adjustment Overview Christine Woon, P. Eng. Key Account Specialist Customer Care Understanding Global Adjustment (GA) The GA was established by the Provincial Government in 2005 to cover the cost

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB HYDRO ONE NETWORKS INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB HYDRO ONE NETWORKS INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB-2017-0050 HYDRO ONE NETWORKS INC. Application for rates and other charges to be effective May 1, 2018 for the former

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB WEST COAST HURON ENERGY INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB WEST COAST HURON ENERGY INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER WEST COAST HURON ENERGY INC. Application for an order approving just and reasonable rates and other charges for electricity

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Essex Powerlines Corporation

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB GUELPH HYDRO ELECTRIC SYSTEMS INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB GUELPH HYDRO ELECTRIC SYSTEMS INC. Commission de l énergie de l Ontario DECISION AND RATE ORDER GUELPH HYDRO ELECTRIC SYSTEMS INC. Application for rates and other charges to be effective January 1, 2018 By Delegation, Before: Theodore Antonopoulos

More information

ENERGY PARTNERSHIPS PROGRAM APPENDIX 1 DEFINITIONS

ENERGY PARTNERSHIPS PROGRAM APPENDIX 1 DEFINITIONS ENERGY PARTNERSHIPS PROGRAM APPENDIX 1 DEFINITIONS Version 1.0 (June 13, 2016) IESO, 2016 APPENDIX 1 DEFINITIONS Term or Acronym Acceptance Period Access Rights ACEP Activities Affiliate Applicant Applicant

More information

How Ontario is Putting Conservation First

How Ontario is Putting Conservation First How Ontario is Putting Conservation First Nik Schruder Conservation & Corporate Relations, IESO September 2015 Presented at the 2015 ACEEE National Conference on Energy Efficiency as a Resource Overview

More information

microfit LDC CONNECTION REQUEST CHECKLIST

microfit LDC CONNECTION REQUEST CHECKLIST microfit LDC CONNECTION REQUEST CHECKLIST Waterloo ON, N2J 4G8 Waterloo North Hydro Inc. ( WNH ) will make all reasonable efforts to promptly connect a microembedded generation facility ( Project ) to

More information

Orangeville Hydro Limited 2019 IRM APPLICATION EB Submitted on: September 24, 2018

Orangeville Hydro Limited 2019 IRM APPLICATION EB Submitted on: September 24, 2018 0 IRM APPLICATION Submitted on: September, 0 Orangeville Hydro Limited 00 Line C Orangeville, ON LW Z Page of 0 TABLE OF CONTENTS Table of Contents... Introduction... Distributor s Profile... Publication

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB NIAGARA PENINSULA ENERGY INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB NIAGARA PENINSULA ENERGY INC. Commission de l énergie de l Ontario DECISION AND RATE ORDER NIAGARA PENINSULA ENERGY INC. Application for an order approving just and reasonable rates and other charges for electricity distribution to

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ALGOMA POWER INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ALGOMA POWER INC. Commission de l énergie de l Ontario DECISION AND RATE ORDER ALGOMA POWER INC. Application for rates and other charges to be effective January 1, 2019 By Delegation, Before: Jane Scott 1 INTRODUCTION AND

More information

Ontario Energy Board Commission de l énergie de l Ontario RATE ORDER EB HYDRO ONE NETWORKS INC.

Ontario Energy Board Commission de l énergie de l Ontario RATE ORDER EB HYDRO ONE NETWORKS INC. Ontario Energy Board Commission de l énergie de l Ontario RATE ORDER HYDRO ONE NETWORKS INC. Application for electricity distribution rates and other charges beginning January 1, 2016 BEFORE: Allison Duff

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC

More information

NEW HAMPSHIRE CODE OF ADMINISTRATIVE RULES NET METERING FOR CUSTOMER-OWNED RENEWABLE ENERGY GENERATION RESOURCES OF 1,000 KILOWATTS OR LESS

NEW HAMPSHIRE CODE OF ADMINISTRATIVE RULES NET METERING FOR CUSTOMER-OWNED RENEWABLE ENERGY GENERATION RESOURCES OF 1,000 KILOWATTS OR LESS CHAPTER Puc 900 NET METERING FOR CUSTOMER-OWNED RENEWABLE ENERGY GENERATION RESOURCES OF 1,000 KILOWATTS OR LESS PART Puc 901 PURPOSE Puc 901.01 Purpose. The purpose of Puc 900, pursuant to the mandate

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER TILLSONBURG HYDRO INC. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information

PowerStream Inc. (Licence Name PowerStream Inc. ED ) 2010 Electricity Distribution Rate Adjustment Application EB

PowerStream Inc. (Licence Name PowerStream Inc. ED ) 2010 Electricity Distribution Rate Adjustment Application EB Ms. Kirsten Walli Board Secretary Ontario Energy Board 2300 Yonge Street 26th Floor, Box 2319 Toronto, ON M4P 1E4 October 21, 2009 Dear Ms. Walli Re:. (Licence Name. ED20040420) 2010 Electricity Distribution

More information

Enersource Hydro Mississauga Inc. Application for Distribution Rates Effective January 1, 2017 Board File No.: EB

Enersource Hydro Mississauga Inc. Application for Distribution Rates Effective January 1, 2017 Board File No.: EB August 15, 2016 BY RESS & OVERNIGHT COURIER Ms. Kirsten Walli Board Secretary Ontario Energy Board P.O. Box 2319 2300 Yonge Street, Suite 2700 Toronto, Ontario M4P 1E4 Dear Ms. Walli: Re: Enersource Hydro

More information

DECISION AND RATE ORDER

DECISION AND RATE ORDER DECISION AND RATE ORDER WELLINGTON NORTH POWER INC. Application for rates and other charges to be effective May 1, 2019 By Delegation, Before: Pascale Duguay March 28, 2019 Ontario Energy Board 1 INTRODUCTION

More information

2.11 EXHIBIT 8: RATE DESIGN... 2 Overview... 2

2.11 EXHIBIT 8: RATE DESIGN... 2 Overview... 2 Waterloo North Hydro Inc. Exhibit 8 Page 1 of 19 Filed: May 1, 2015 TABLE OF CONTENTS 2.11 EXHIBIT 8: RATE DESIGN... 2 Overview... 2 2.11.1 Fixed/Variable Proportion... 3 Current Fixed / Variable Proportion...

More information

04/16/2014- AMENDED AND REPORTED OUT TO THE FLOOR 04/04/14-AMENDED AND REPORTED OUT TO THE COMMITTEE ON RULES AND JUDICIARY 09/13/13-NO ACTION TAKEN

04/16/2014- AMENDED AND REPORTED OUT TO THE FLOOR 04/04/14-AMENDED AND REPORTED OUT TO THE COMMITTEE ON RULES AND JUDICIARY 09/13/13-NO ACTION TAKEN COMMITTEE ON ENERGY AND ENVIRONMENTAL PROTECTION 0//0- AMENDED AND REPORTED OUT TO THE FLOOR 0/0/-AMENDED AND REPORTED OUT TO THE COMMITTEE ON RULES AND JUDICIARY 0//-NO ACTION TAKEN BILL NO. 0-000 Thirtieth

More information

THE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM FOR NON-RESIDENTIAL CUSTOMERS

THE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM FOR NON-RESIDENTIAL CUSTOMERS Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to

More information

Oakville Hydro Electricity Distribution Inc Distribution Rate Adjustment Application (EB ) Effective January 1, 2018

Oakville Hydro Electricity Distribution Inc Distribution Rate Adjustment Application (EB ) Effective January 1, 2018 Oakville Hydro Electricity Distribution Inc. 2018 Distribution Rate Adjustment Application (EB-2017-0067) Effective January 1, 2018 IN THE MATTER OF the Ontario Energy Board Act, 1998, being Schedule B

More information

The Filing includes the Application; the Manager s Summary; and live versions of the following models:

The Filing includes the Application; the Manager s Summary; and live versions of the following models: August th, 206 Via RESS and Courier Ms. Kirsten Walli, Board Secretary Ontario Energy Board 2300 Yonge Street, 27th Floor Toronto, Ontario M4P E4 Dear Ms. Walli, Re: Electricity Distribution Licence ED-2006-003

More information

An Application. Canadian Niagara Power Inc. To Adjust. Electricity Distribution Rates. Effective January 1, 2019 EB

An Application. Canadian Niagara Power Inc. To Adjust. Electricity Distribution Rates. Effective January 1, 2019 EB An Application By To Adjust Electricity Distribution Rates Effective January 1, 2019 Submitted: August 13, 2018 Page 2 of 18 Index Application 3 Manager s Summary 6 Preamble 6 Elements of the Application

More information

ATTACHMENT 8 SUMMARY OF FIXED/VARIABLE SPLITS HORIZON UTILITIES RZ

ATTACHMENT 8 SUMMARY OF FIXED/VARIABLE SPLITS HORIZON UTILITIES RZ EB-2017-0024 Alectra Utilities Corporation 2018 EDR Application Exhibit 3 Tab 1 Schedule 1 Filed: July 7, 2017 ATTACHMENT 8 SUMMARY OF FIXED/VARIABLE SPLITS HORIZON UTILITIES RZ Summary of Fixed Variable

More information

HYDRO ONE INC. ANNUAL CONSOLIDATED FINANCIAL STATEMENTS

HYDRO ONE INC. ANNUAL CONSOLIDATED FINANCIAL STATEMENTS ANNUAL CONSOLIDATED FINANCIAL STATEMENTS Management s Discussion and Analysis 2 Management s Report 41 Independent Auditors Report 42 Consolidated Statements of Operations and Comprehensive Income, Retained

More information

The following words and terms shall have the following meanings when used in this Tariff:

The following words and terms shall have the following meanings when used in this Tariff: Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to

More information

WHITBY HYDRO ELECTRIC CORPORATION

WHITBY HYDRO ELECTRIC CORPORATION Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER WHITBY HYDRO ELECTRIC CORPORATION Applications for an order approving just and reasonable rates and other charges for electricity

More information

Oakville Hydro Electricity Distribution Inc Distribution Rate Adjustment Application (EB ) Effective January 1, 2017

Oakville Hydro Electricity Distribution Inc Distribution Rate Adjustment Application (EB ) Effective January 1, 2017 Oakville Hydro Electricity Distribution Inc. 2017 Distribution Rate Adjustment Application (EB20160097) Effective January 1, 2017 IN THE MATTER OF the Ontario Energy Board Act, 1998, being Schedule B to

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontari o Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro One Remote Communities

More information

Distributed Generation Connection Standard ST B Planning Engineer. Network Planning Manager. General Manager Network

Distributed Generation Connection Standard ST B Planning Engineer. Network Planning Manager. General Manager Network Effective Date 1 May 2018 Issue Number 1.1 Page Number Page 1 of 26 Document Title Distributed Generation Connection Standard Document Number ST B1.1-001 Document Author Planning Engineer Document Reviewer

More information

NEWMARKET - TAY POWER DISTRIBUTION LTD.

NEWMARKET - TAY POWER DISTRIBUTION LTD. Commission de l énergie de l Ontario DECISION AND RATE ORDER NEWMARKET - TAY POWER DISTRIBUTION LTD. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information

Collus PowerStream Corp. ED Incentive Regulation Mechanism Electricity Distribution Rate Application

Collus PowerStream Corp. ED Incentive Regulation Mechanism Electricity Distribution Rate Application Collus PowerStream Corp. ED20020518 2018 Incentive Regulation Mechanism Electricity Distribution Rate Application Board File Number EB20170034 For Rates Effective May 1, 2018 Collus PowerStream 43 Stewart

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB GUELPH HYDRO ELECTRIC SYSTEMS INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB GUELPH HYDRO ELECTRIC SYSTEMS INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER GUELPH HYDRO ELECTRIC SYSTEMS INC. Application for electricity distribution rates and other charges beginning January 1,

More information

Additional Agenda. City of Mississauga. General Committee. Date June 27, 2018 Time 9:00 A.M. Location Council Chamber 2 nd Floor 300 City Centre Drive

Additional Agenda. City of Mississauga. General Committee. Date June 27, 2018 Time 9:00 A.M. Location Council Chamber 2 nd Floor 300 City Centre Drive City of Mississauga Additional Agenda General Committee Date June 27, 2018 Time 9:00 A.M. Location Council Chamber 2 nd Floor 300 City Centre Drive REMOVAL OF DEPUTATION 5.5 Kevin Sherwin, Chair of the

More information

RESIDENTIAL SERVICE CLASSIFICATION

RESIDENTIAL SERVICE CLASSIFICATION Niagara-on-the-Lake Hydro Inc. Page 1 of 10 RESIDENTIAL SERVICE CLASSIFICATION This classification applies to an account taking electricity at 750 volts or less where the electricity is used exclusively

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro Ottawa Limited

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro One Inc. for

More information

Renewable Energy Guidance

Renewable Energy Guidance NewClimate Institute, Verra Renewable Energy Guidance Guidance for assessing the greenhouse gas impacts of renewable energy policies May 2018 How to describe the policy or action being assessed 5. DESCRIBING

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop an Electricity Integrated Resource Planning Framework and to Coordinate and Refine Long-Term Procurement

More information

HOLY CROSS ENERGY November 3, 2015 GENERATOR INTERCONNECT POLICY

HOLY CROSS ENERGY November 3, 2015 GENERATOR INTERCONNECT POLICY GENERATOR INTERCONNECT POLICY GENERATOR INTERCONNECT (PROCEDURE) GENERATOR INTERCONNECT (GUIDELINES) Page 1 of 50 TABLE OF CONTENTS GENERATOR INTERCONNECT (PROCEDURE)... 4 I. GENERAL OVERVIEW... 5 A. Applicability...

More information

AIRD BERLIS. October 16, 2017 VIA COURIER, AND RESS

AIRD BERLIS. October 16, 2017 VIA COURIER,  AND RESS AIRD BERLIS Scott Stoll Direct: 416.865.4703 E-mail:sstoll@airdberlis.com VIA COURIER, EMAIL AND RESS Ms. Kirsten Walli Board Secretary Ontario Energy Board P.O. Box 2319, 27th Floor 2300 Yonge Street

More information

MicroFIT-Generation Connection Application For Connection of Micro-Generation Facilities of 10 kw

MicroFIT-Generation Connection Application For Connection of Micro-Generation Facilities of 10 kw This application is applicable to individual or multiple generating units at the Applicant s facility with total nameplate rating of 10 kw or less. The applicant s generation facility must generate electricity

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Hydro One Inc. for

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Erie Thames Powerlines

More information

Long Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES

Long Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES Long Island Power Authority Fifth Revised Leaf No. 280 PSEG LONG ISLAND LONG ISLAND CHOICE PROGRAM TARIFF LEAVES Long Island Power Authority Fifth Revised Leaf No. 280 IX. LONG ISLAND CHOICE PROGRAM TABLE

More information

OREGON STANDARD AVOIDED COST RATES AVOIDED COST PURCHASES FROM ELIGIBLE QUALIFYING FACILITIES Page 1

OREGON STANDARD AVOIDED COST RATES AVOIDED COST PURCHASES FROM ELIGIBLE QUALIFYING FACILITIES Page 1 S ELIGIBLE QUALIFYING FACILITIES Page 1 Available To owners of Qualifying Facilities making sales of electricity to the Company in the State of Oregon. Applicable For power purchased from Base Load and

More information

SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED

SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED Attachment E to Notice of Revised Proposed Amendments to the System Code and the Distribution System Code August 23, 2018 EB-2016-0003 SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED Below is a high level

More information

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA The

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B); AND IN THE MATTER OF an application by Wellington North Power

More information

ONTARIO POWER GENERATION REPORTS 2013 FINANCIAL RESULTS

ONTARIO POWER GENERATION REPORTS 2013 FINANCIAL RESULTS ONTARIO POWER GENERATION REPORTS 2013 FINANCIAL RESULTS Mar. 6, 2014 [Toronto]: Ontario Power Generation Inc. (OPG or Company) today reported its financial and operating results for year ended Dec. 31,

More information

REFURBISHMENT AND NEW GENERATION NUCLEAR

REFURBISHMENT AND NEW GENERATION NUCLEAR Filed: 00--0 EB-00-00 Exhibit D Tab Page of 0 0 0 REFURBISHMENT AND NEW GENERATION NUCLEAR.0 PURPOSE The purpose of this evidence is to present an overview description of the nuclear plant refurbishment

More information

ONTARIO POWER GENERATION REPORTS 2013 FIRST QUARTER FINANCIAL RESULTS

ONTARIO POWER GENERATION REPORTS 2013 FIRST QUARTER FINANCIAL RESULTS May 16, 2013 ONTARIO POWER GENERATION REPORTS 2013 FIRST QUARTER FINANCIAL RESULTS [Toronto]: Ontario Power Generation Inc. (OPG or Company) today reported its financial and operating results for the three

More information

TERMS AND CONDITIONS OF ELECTRICITY AND NATURAL GAS FOR A BUSINESS

TERMS AND CONDITIONS OF ELECTRICITY AND NATURAL GAS FOR A BUSINESS TERMS AND CONDITIONS OF ELECTRICITY AND NATURAL GAS FOR A BUSINESS 2 What words mean in this Contract We, us and our refer to Planet Energy. You and your refers to the Business whose name is set out beside

More information

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46)) GOVERNMENT NOTICE NO. 77 published on 02/03/2018 THE ELECTRICITY ACT (CAP.131) RULES (Made under sections 18(5), 45 and 46)) THE ELECTRICITY (DEVELOPMENT OF SMALL POWER PROJECTS) RULES, 2018 1. Citation

More information

SUMMARY OF APPLICATION

SUMMARY OF APPLICATION Page of 0 0 SUMMARY OF APPLICATION OVERVIEW AND CONTEXT This is an application for an order or orders of the Ontario Energy Board ( OEB ) approving payment amounts for OPG s prescribed hydroelectric and

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION, ITS COMPLIANCE AND IMPLEMENTATION OF RENEWABLE ENERGY CERTIFICATE FRAMEWORK)

More information

PROJECT COSTS, ECONOMICS, AND OTHER PUBLIC INTEREST CONSIDERATIONS

PROJECT COSTS, ECONOMICS, AND OTHER PUBLIC INTEREST CONSIDERATIONS Filed: September, 00 EB-00-0 Schedule Page of PROJECT COSTS, ECONOMICS, AND OTHER PUBLIC INTEREST CONSIDERATIONS This set of exhibits describes the costs of the proposed facilities and the economics of

More information

TORONTO HYDRO CORPORATION MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS FOR THE YEAR ENDED DECEMBER 31, 2005

TORONTO HYDRO CORPORATION MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS FOR THE YEAR ENDED DECEMBER 31, 2005 TORONTO HYDRO CORPORATION MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS FOR THE YEAR ENDED DECEMBER 31, 2005 The following discussion and analysis should be read

More information

EXHIBIT 9 DEFERRAL AND VARIANCE ACCOUNTS

EXHIBIT 9 DEFERRAL AND VARIANCE ACCOUNTS acr EXHIBIT DEFERRAL AND VARIANCE ACCOUNTS 0 Cost of Service Chapleau Public Utilities Corporation Page of 0 0. TABLE OF CONTENTS.. TABLE OF CONTENTS. Table of Contents..... Table of Contents..... List

More information

Advancing Customer-Driven Solutions for Ontario

Advancing Customer-Driven Solutions for Ontario The Power to Connect Advancing Customer-Driven Solutions for Ontario IESO STAKEHOLDER SUMMIT PRESENTATION June 12, 2017 The Vision This is about preparing Ontario s electricity industry today for tomorrow

More information

No. 47. An act relating to the Vermont Energy Act of (H.56) It is hereby enacted by the General Assembly of the State of Vermont:

No. 47. An act relating to the Vermont Energy Act of (H.56) It is hereby enacted by the General Assembly of the State of Vermont: No. 47. An act relating to the Vermont Energy Act of 2011. (H.56) It is hereby enacted by the General Assembly of the State of Vermont: * * * Net Metering * * * Sec. 1. 30 V.S.A. 219a is amended to read:

More information

Achievable Potential Study - LDC Working Group Meeting #1 #7

Achievable Potential Study - LDC Working Group Meeting #1 #7 Achievable Potential Study - LDC Working Group Meeting #1 #7 Minutes of Meeting Date held: June 23 rd, 2015 Time held: 1:00pm 4:00pm Location held: IESO Office Invited/Attended Company Name Attendance

More information

SUMMARY OF APPLICATION

SUMMARY OF APPLICATION Filed: September, 00 EB-00-00 Schedule Page of SUMMARY OF APPLICATION Hydro One Networks ( Hydro One or Hydro One Transmission ) is applying for an Order approving the revenue requirement, cost allocation

More information

Welcome. Welcome to the VDER Phase I Solar Installer Roundtable Info Session April 26, 2017

Welcome. Welcome to the VDER Phase I Solar Installer Roundtable Info Session April 26, 2017 Welcome Welcome to the VDER Phase I Solar Installer Roundtable Info Session April 26, 2017 1 Installed Capacity, MW Installed Capacity, MW State of the Market 150 100 50 0 NYC Installed Capacity by Borough

More information