RESOLUTION NO. R Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming

Similar documents
Cancelled. Final Action

MOTION NO. M Tacoma Link Expansion CMC Phase 1 Preconstruction Services PROPOSED ACTION

MOTION NO. M Tacoma Link Extension CMC Phase 2 Construction Management Services

RESOLUTION NO. R Baseline Budget and Schedule, and Approve Gates 5 and 6 for the East Link Extension

Recommend to Board. Final Action

Recommendation to the Board Final Action

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT:

MOTION NO. M Funding and Cooperative Agreement with the City of Shoreline related to the Lynnwood Link Extension

MOTION NO. M Agreement with the City of Seattle and King County Metro for Downtown Seattle Transit Tunnel Mitigation

SOUND TRANSIT STAFF REPORT MOTION NO. M D Street-to-M Street Track & Signal Project Preferred Alternative

MOTION NO. M Contract Amendment for Final Design Services for Tacoma Trestle Track & Signal Project

RESOLUTION NO. R Federal Way Link Extension Project Scope Expansion and Budget Amendment

SOUND TRANSIT RESOLUTION NO. R99-14

SOUND TRANSIT STAFF REPORT MOTION NO. M Contract Amendment for Construction Management Services

Proposed Transit Improvement Plan

MOTION NO. M Sole-Source Contract Amendment for Operational Reporting Technology Tools

MOTION NO. M Contract Amendment for Technology Software, Hardware and Related Maintenance Services

University Link LRT Extension

Adopted Transit Improvement Plan

MOTION NO. M Contract Amendment for Sounder Equipment Technical Services PROPOSED ACTION

SOUND TRANSIT STAFF REPORT RESOLUTION NO. R Sammamish Park-and-Ride Project Property Acquisition

MOTION NO. M Contract Amendment for Agency Budgeting System PROPOSED ACTION

CHAPTER 9 FINANCIAL CONSIDERATIONS

Transit Improvement Plan

CENTRAL PUGET SOUND REGIONAL TRANSIT AUTHORITY. Schedule of Sources and Uses of Funds by Subarea. Years Ending December 31, 2010 and 2009

Central Puget Sound Regional Transit Authority

SOUND TRANSIT STAFF REPORT MOTION NO. M Select a draft Sounder fare structure change and fare increase for public review and comment

MOTION NO. M Agreement with the City of Bothell for Partnering on the SR 522 BRT and I-405 BRT Projects

CENTRAL CITY LINE PROJECT UPDATE AND SMALL STARTS EVALUATION & RATINGS APPLICATION UPDATED & REVISED 4/20/17

Chairman Smedberg and the VRE Operations Board

Final Interim Policy Guidance Federal Transit Administration Capital Investment Grant Program

Adopted Budget. December Capitol Hill Station and UW Station. Canyon Park Freeway Station. Sounder s 15th Anniversary

May 1, Dear Board of Directors:

Columbia River Crossing Project Vancouver, Washington Engineering (Rating Assigned November 2012)

NE 130th Street Infill Station Contract Amendment for Preliminary Engineering Services. Meeting: Date: Type of action: Staff contact:

SOUND TRANSIT RESOLUTION NO. R

Legislation Passed August 11, 2015

Adopted Budget. December 2014

CENTRAL PUGET SOUND REGIONAL TRANSIT AUTHORITY. Summary of Sources and Uses of Funds by Subarea

2018 Budget Proposed October 2017

Central Puget Sound Regional Transit Authority

SOUND TRANSIT STAFF REPORT RESOLUTION NO. R Contract for Start-up Tasks and Interim Funding for Rainier Valley Community Development Fund

Executive Change Control Board. January 15, 2016

Financial Plan & Proposed Budget

READINESS REVIEW ENTRY INTO PROJECT DEVELOPMENT. Columbia Pike Streetcar Arlington County, Virginia FTA Region 3

SB 83 Additional Vehicle Registration Fee Expenditure Plan (July 15, 2010)

2018 Adopted Budget December 2017

Central Puget Sound Regional Transit Authority

INTERGOVERNMENTAL AGREEMENT BETWEEN METRO AND WASHINGTON COUNTY FOR THE SOUTHWEST CORRIDOR PLAN

Updated Planning Commission Work Program ( )

4 Cost Estimation Assumptions

Chapter 9 Financial Considerations. 9.1 Introduction

Corridor Management Committee. May 6, 2015

B. Resolution P Administration and Projects Committee STAFF REPORT October 1, 2015 Page 2 of 2 Changes from Committee Background MTC committed a

CHAPTER 9 FINANCIAL CONSIDERATIONS

THIS PRINT COVERS CALENDAR ITEM NO. : 16 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY. DIVISION: Finance and Information Technology

Proposed Planning Commission Work Program ( )

CHAPTER 6: COST ESTIMATES

Sound Transit Report of Telephone Survey Results

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

MOTION NO. M Contract for Risk Management Information Systems Software and Related Services

Central Puget Sound Regional Transit Authority

2008 Citizens Guide to Sound Transit, Phase 2

AGENDA. City of Tacoma Planning Commission

2016 Adopted Budget December 2015

APPENDIX B TECHNICAL MEMORANDUM #2 TRANSPORTATION FUNDING

SOUTHWEST LIGHT RAIL TRANSIT PROJECT (METRO GREEN LINE EXTENSION) Section 106 Memorandum of Agreement

SOUND TRANSIT STAFF REPORT MOTION NO. M Contract Amendment for Passenger Information Management System

SOUTHWEST LIGHT RAIL TRANSIT PROJECT (METRO GREEN LINE EXTENSION) Section 106 Memorandum of Agreement. Quarterly Report No. 4 (March 1 May 31, 2017)

SOUND TRANSIT STAFF REPORT MOTION NO. M Agreement with the City of Newcastle for the Newcastle Transit Center Project

MOTION NO. M Contract for Fall Restraint Enhancement and Repair Services PROPOSED ACTION

Central Puget Sound Regional Transit Authority

Capital. Finance. Repor. $34.3 Million Bond Issue for Police Facilities Goes to Tacoma Voters February 5. Background

Capital Cost Estimation Methodology

Additional support documents to the resolution:

SUBJECT: Burloak Drive grade separation and Drury Lane pedestrian bridge update

Region of Waterloo Transportation and Environmental Services Rapid Transit Corporate Services Financial Services and Development Financing

Proposed Budget. September Capitol Hill Station and UW Station. Canyon Park Freeway Station. Sounder s 15th Anniversary

Wednesday, January 31, 2018, (February Meeting) 10:00 a.m. Spokane Transit Southside Conference Room AGENDA

Quarterly Financial Performance Report Q1 2017

Seattle Economics Council February 1, 2017

Adopted. Budget. Dec. 2011

BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM. Dulles Corridor Metrorail Phase 2 Update

MOTION NO. M Contract Amendment for Risk Management Information System PROPOSED ACTION

Funding Application. Project Information. Contact Information. Project Description. 1 of 11. April 30th, :36 PM

MOTION NO. M Amend Four Agreements with BNSF Railway Company to Adjust Insurance Provisions

The DRAFT Bus and Rail Investment Plan in Orange County

Memorandum. Date: RE: Plans and Programs Committee

SOUND TRANSIT STAFF REPORT MOTION NO. M

Central Puget Sound Regional Transit Authority

Environmental Analysis, Chapter 4 Consequences, and Mitigation

DULLES CORRIDOR COMMITTEE

Executive Change Control Board. March 30, 2016

RESOLUTION NO. R Reauthorizing the Investment of Public Funds in the Local Government Investment Pool

PUBLIC WORKS DIRECTOR

Title VI Service Equity Analysis

Available Fund Balance $ 5,268,755 $ 4,551,743 $ 5,442,764 $ 5,442,764 $ 3,411,136

TEX Rail Fort Worth, Texas Project Development (Rating Assigned November 2012)

SOUTHWEST LIGHT RAIL TRANSIT PROJECT (METRO GREEN LINE EXTENSION) Section 106 Memorandum of Agreement

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008

Transcription:

RESOLUTION NO. R2017-31 Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 09/14/2017 09/28/2017 Recommend to Board Final Action Ahmad Fazel, DECM Executive Director Madeleine Greathouse, Project Director (1) Adopts the Tacoma Link Expansion baseline schedule and budget by increasing the authorized project allocation from $34,622,000 to $217,346,000 and establishing a project revenue service date of May 2022; (2) approves passage through Gate 5 within Sound Transit s Phase Gate process; and (3) approves Tacoma Link Extension as the project name. KEY FEATURES SUMMARY This action adopts the baseline schedule and budget to extend the current Tacoma Link light rail system, which constitutes Board approval to pass through Gate 5 Establish Baseline within Sound Transit s Phase Gate process. The baseline budget of $217,346,000 will provide agency administration, design, acquisition of right-of-way, construction, construction services, light rail vehicle (LRV) procurement, testing and startup, MOU requirements, and third-party activities. This action establishes the project revenue service date as May 2022. Based on other recent national project experience, the Federal Transit Administration (FTA) has recommended that the Tacoma Link project completion milestone stated in the Single Year Grant Application (SYGA) be changed to September 2022 in accordance with FTA schedule contingency guidelines. Sound Transit s internal target date of May 2022 for start of revenue service, however, remains unchanged and includes eight months of project float. This action approves Tacoma Link Extension as the project name. BACKGROUND The Tacoma Link Expansion is a 2.4-mile extension of light rail from the Theater District in downtown to the Hilltop neighborhood in Tacoma. The extension will travel at-grade, in-street with traffic along Stadium Way, North 1st Street, Division Avenue, and Martin Luther King Jr. Way. The project includes six new stations, relocates the Theater District Station, expands the existing Tacoma Operations and Maintenance Facility (OMF), and provides for additional light rail vehicles. The Tacoma Link Expansion completed environmental review in compliance with both NEPA and SEPA with approval of a NEPA Documented Categorical Exclusion (DCE) on June 25, 2015, by the Federal Transit Administration and a SEPA Determination of Nonsignificance (DNS), issued by Sound Transit on July 13, 2015. The Sound Transit Board selected the project to be built on November 19, 2015. The Tacoma Link Expansion will be delivered as a single design-bid-build contract package. Design and construction includes: 2.4 miles of double-track embedded rail from the Theater District to the terminus at South 19th Street and Martin Luther King Jr. Way. Seven station platforms located in the street median. Water, power, sanitary and storm utility relocations along the alignment.

Pedestrian safety enhancements with ADA curbs and curb bulbs. Four new traction power substations (TPSS) to power the overhead contact system (OCS) along the alignment and one additional TPSS at the expanded OMF yard. Expansion of the existing OMF to accommodate additional administrative and operations and maintenance functions for the expanded LRV fleet and system. Final design is approximately 60 percent and is anticipated for completion in first quarter 2018. Sound Transit performed a quantitative risk assessment at the 60 percent design milestone completion. The risk assessment confirmed Sound Transit s baseline cost estimate was sufficient. However, the FTA independent risk assessment concluded additional contingencies were required due to concerns regarding market conditions and recommended adding these contingencies to the baseline cost estimate. This recommendation was accepted by Sound Transit and these contingencies were added to the baseline cost estimate. PROJECT STATUS Project Identification Alternatives Identification Conceptual Engineering Preliminary Engineering Final Design Construction Projected Completion Date: May 2022 Project scope, schedule and budget summary located on page 69 of the June 2017 Agency Progress Report. FISCAL INFORMATION This action approves passage through Phase Gate 5 and establishes a baseline budget and schedule for the Tacoma Link Expansion project. The authorized project allocation to date is increased by $182,724,000 to $217,346,000 for the project. This baseline budget will fund the project through to revenue service by increasing the authorized project allocation to date in the following phases; agency administration, third-party agreements, right-of-way, construction, construction services, vehicles and contingency. Tacoma Link Expansion (in thousands) Project Phase Adopted 2017 Annual Project Budget Annual Project Budget Budget Revision Revised 2017 Annual Project Budget Authorized Project Allocation to Date (Current) Allocation Change Authorized Project Allocation to Date (New) Agency Administration $1,606 $1,606 $10,600 $6,348 $16,948 Preliminary Engineering 5,872 (313) 5,559 Final Design 5,775 5,775 10,830 10,830 Third Party Agreements 750 750 1,310 156 1,466 Right of Way 2,565 2,565 3,200 355 3,555 Construction 127,155 127,155 Construction Services 600 600 810 9,081 9,891 Vehicles 800 800 2,000 33,377 35,377 Contingency 6,565 6,565 Total $12,096 $12,096 $34,622 $182,724 $217,346 Notes: Amounts are expressed in Year of Expenditure. For detailed project information, see page 19 or 147 in the Adopted 2017 Transit Improvement Plan. Authorized Project Allocation to Date Resolution No. R2017-31 Page 2 of 4 Staff Report

Funding Draft Funding Agreement with the City of Tacoma Proposed Baseline $ 217,346,000 Funding Small Starts Grant (Assumed) 74,999,999 City of Tacoma Commitment 47,744,444 Sound Transit Commitment 94,601,557 Affordability The City of Tacoma contributes financially to this project. The table above provides a breakdown of the City s participation and other funding that contributes to the project. The result is a Sound Transit commitment of $94.6M. The project is affordable within the Agency Finance Plan and Pierce subarea under the current funding plan presented above. This assumes the draft amendment to the Funding Agreement with the City of Tacoma has no significant changes and that the Small Starts grant is executed by the FTA in November of this year. The draft amendment with the city will be brought to the Board for review in October or November 2017. The draft amendment outlines that increases to the project above $185 million will be borne by Sound Transit and is reflected in the baseline budget amount. If the grant does not materialize, then for the project to proceed it would require a larger financial commitment from Sound Transit. SMALL BUSINESS PARTICIPATION Not applicable for this action. PUBLIC INVOLVEMENT Over the past several years, Sound Transit conducted extensive public outreach to inform preliminary engineering and final design decisions on the project alignment, station locations, Operations and Maintenance Facility expansion, and station naming. Public involvement included email notifications, open houses, online surveys, stakeholder roundtables, and community and Tacoma City Council briefings. Sound Transit will continue to conduct public outreach through completion of the design phase and during construction and pre-revenue service. TIME CONSTRAINTS A one-month delay will not impact the overall project schedule. PRIOR BOARD/COMMITTEE ACTIONS Motion No. M2017-33: Authorized the chief executive officer to execute a Funding Agreement with the City of Tacoma for the Tacoma Link Expansion Project. Motion No. M2017-32: Authorized the chief executive officer to execute an amendment to the Tacoma Link Right of Use Agreement with the City of Tacoma for the Tacoma Link Expansion. Resolution No. R2017-31 Page 3 of 4 Staff Report

Motion No. M2017-08: Authorized the chief executive officer to execute a City Services Agreement with the City of Tacoma for expedited design, design review, permitting, and construction services for the Tacoma Link Expansion in the amount of $1,116,100, with a 4% contingency of $40,000, for a total authorized agreement amount not to exceed $1,156,100. Motion No. M2016-105: Ratified a Sub-recipient Funding Agreement with the City of Tacoma for a Federal Transit Administration grant for the Enhancements to Tacoma Link Expansion project in the amount of $2,500,000, which includes $500,000 in City of Tacoma local match contribution. Resolution No. R2015-22: Selected the route, stations, and operations and maintenance facility expansion site for the Tacoma Link Expansion. Motion No. M2014-11: Identified the Tacoma Link Expansion light rail alignment(s) to advance into environmental review. Motion No. M2013-31: (1) Selected E1 North Downtown Central as the corridor and light rail as the mode for detailed study in the Tacoma Link light rail expansion environmental review, and (2) approved Gate 2 within Sound Transit s Phase Gate process. ENVIRONMENTAL REVIEW KH 6/28/17 LEGAL REVIEW JW 9/11/17 Resolution No. R2017-31 Page 4 of 4 Staff Report

RESOLUTION NO. R2017-31 A RESOLUTION of the Board of the Central Puget Sound Regional Transit Authority (1) adopting the Tacoma Link Expansion baseline schedule and budget by increasing the authorized project allocation to date from $34,622,000 to $217,346,000 and establishing a project revenue service date of May 2022; (2) approving Gate 5 within Sound Transit s Phase Gate process; and (3) approving Tacoma Link Extension as the project name. WHEREAS, the Central Puget Sound Regional Transit Authority, commonly known as Sound Transit, was formed under RCW Chapters 81.104 and 81.112 for the Pierce, King, and Snohomish Counties region by action of their respective county councils pursuant to RCW 81.112.030; and WHEREAS, Sound Transit is authorized to plan, construct, and permanently operate a high-capacity system of transportation infrastructure and services to meet regional public transportation needs in the Central Puget Sound region; and WHEREAS, in general elections held within the Central Puget Sound Regional Transit Authority district on November 5, 1996, November 4, 2008, and November 8, 2016, voters approved local funding to implement a regional high-capacity transportation system for the Central Puget Sound region; and WHEREAS, the Tacoma Link Expansion project was included in the voter approved Sound Transit 2 plan; and WHEREAS, on February 27, 2014 the Sound Transit Board identified the alignment for environmental review; and WHEREAS, the FTA approved a NEPA Documented Categorical Exclusion on June 25, 2015, and Sound Transit issued a SEPA Determination of Nonsignificance on July 13, 2015; and WHEREAS, the Sound Transit Board selected the project route, profile, and stations on November 19, 2015; and WHEREAS, the Tacoma Link Expansion will extend the Tacoma Link system from the Theater District Station in Tacoma to the Hilltop neighborhood to provide transit access between and within high-growth population areas and employment centers; and WHEREAS, the project includes a 2.4-mile extension running in-street; six new stations and relocates the existing Theater District Station; traction power substations; expansion of the existing Tacoma Link Operations and Maintenance Facility; and allows for the acquisition of additional Link vehicles; and WHEREAS, Sound Transit conducted extensive public outreach for the Tacoma Link Expansion from alignment selection through preliminary engineering and final design which included email notifications, open houses, online surveys, stakeholder roundtables, and community and Tacoma City Council briefings; and WHEREAS, on March 23, 2017, the Sound Transit Board approved a Funding Agreement with the City of Tacoma which identified an estimated contribution of $43.3 million toward the

project and documents the Federal Transit Administration and Washington State Department of Transportation grants available to the project in the amount of $33 million; and WHEREAS, the project to be built shall be known as the Tacoma Link Extension which is consistent for extensions of existing Link projects. NOW, THEREFORE, BE IT RESOLVED by the Board of the Central Puget Sound Regional Transit Authority that the Tacoma Link Expansion baseline schedule and budget is adopted by: Section 1. Increasing the authorized project allocation from $34,622,000 to $217,346,000; Section 2. Establishing a project revenue service date of May 2022; Section 3. Approving Gate 5 within Sound Transit s Phase Gate process; and Section 4. Approving Tacoma Link Extension as the project name. ADOPTED by the Board of the Central Puget Sound Regional Transit Authority at a regular meeting thereof held on September 28, 2017. ATTEST: Dave Somers Board Chair Fathryn Fl res Board Administrator Resolution No. R201 7-31 Page 2 of 2

Board 09/28/2017 ACTION Tacoma Link Expansion SOUNDTRANSIT [MEETING IDATE TSTAFF CONTACT Löpitai Committee 9/14/2017 jahmad Fazel, DECM Executive Director Madeleine Greathouse, Project Director _J GATE I GATE 2 GATE 3 GATE 4 GATE 5 GATE 6 GATE 7 GATE $ Enter Project Identify ID Preferred Enter Final Establish Proceed to Transition to Close Out Development Alternatives Alternative Design Baseline Construction Operations Project ACTION REQUESTED Resolution No. R201 7-31 authorizes the Tacoma Link Expansion to advance through Gate 5 to adopt the baseline budget and schedule. PROJECT BUDGET PROJECT SCHEDULE Adopted Project Budget: $34,622,000 YOE$ Schedule to complete Final Design:Q1 2018 Estimated Final Project Cost: $21 7,346 (YOE$) Estimated Project Completion: May 2022 PROJECT DESCRIPTION The Tacoma Link Expansion project is a 2.4-mile extension of the existing Tacoma Link light rail from the Theater District in downtown Tacoma to the Hilltop neighborhood in the City of Tacoma. The extension will travel primarily in-street along Stadium Way, North 1st Street, Division Avenue, and Martin Luther King Jr. Way. The project includes six new stations and relocates the Theater District Station. It also includes an expansion of the existing Tacoma Link Operations and Maintenance Facility and additional Tacoma Link vehicles. Environmental review for the project in compliance with NEPA (National Environmental Policy Act) and SEPA (State Environmental Policy Act) has been completed. The Federal Transit Administration approved a NEPA Documented Categorical Exclusion (DCE) on June 25, 2015. Sound Transit issued a SEPA Determination of Nonsignificance (DNS) on July 13, 2015. The Sound Transit Board selected the project to be built on November 19, 2015. Preliminary engineering was completed on the project. The final design phase is progressing from the 60% toward 90% with the 100% design milestone scheduled for completion in December 2017. The Tacoma Link Expansion will be delivered as a design-bid-build project in a single construction contract package. This Phase Gate action will allow the project to baseline the project budget and schedule. Future Board actions and authorization to enter construction (Phase Gate 6) will be brought to the board at a later date. ACTION APPROVED September28, 2017 1 Date Dave Somers Board Chair