RISK MANAGEMENT FOR INFRASTRUCTURE PROJECTS & TERMSHEET DEVELOPMENT

Similar documents
IPP s Project Risk Classification

Overview of the framework

Overview of the framework

Project Finance An Overview

Model Concession Agreement for Highways: An Overview

Public Private Partnerships (PPPs) Projects

Overview of the framework

June 2, 2017 I Ratings

INDEPENDENT POWER PRODUCERS

Nigeria Infrastructure Building Conference 2014

Overview of the framework

PPP PUBLIC PRIVATE PARTNERSHIP

PPP Finance and Legal Issues. Edward Farquharson 25 July 2006

O F F I C I A L S P O N S O R

RETENTION TRUST FUND. you are deemed to have read, understood, and accepted these Terms and Conditions and you are bound by them;

Due Diligence checklist for [insert project name]

Investing in Renewable Assets in Emerging Markets

Life-Cycle Project Delivery

STANDARD TRADING CONDITIONS

TxDOT SH 288 TOLL LANES PROJECT IN HARRIS COUNTY TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET

EMP Commercial Terms and Conditions AS AT DECEMBER 2015 ENERGY DONE BRIGHT

ISSUED: AUGUST 31, 2015 EFFECTIVE: SEPTEMBER 1, 2015 I. APPLICATION OF TARIFF

Construction and Infrastructure Contracts. 30 th August 2015, NJA, Bhopal. Sujit Ghosh Partner & National Head, Advaita Legal, New Delhi

Application in LIBERIA ROAD ASSET MANAGEMENT PROJECT

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA. NOTIFICATION Shimla, the 22 nd November, 2018

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

State Policy on Chhattisgarh Special Economic Zone. Government of Chhattisgarh. Department of Commerce and Industries

General Terms and Conditions of Sale of DSM Resins (Far East) Co., Ltd.

(c) Section 3.07 is deleted and the following is substituted therefor:

SH 183 MANAGED LANES PROJECT TOLL CONCESSION PUBLIC-PRIVATE PARTNERSHIP AGREEMENT TERM SHEET

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

Corporate Finance. Rating Approach to Project Finance. Project Finance Criteria Report. Analysts

SUPPLY CONDITIONS FOR DISTRICT COOLING SERVICE

Solar Energy Projects: Structuring EPC Agreements

Basics of PPA Negotiations. Eng. David M. Mwangi, Individual Energy Consultant Nairobi, Kenya

1. Risk of regularizing illegal connections

Construction Risk in P3 Projects. Timothy J. Murphy Partner McMillan LLP

Preamble : Policy Frame Work :

Need for Commercial Financing of Infrastructure

WHAT IS PROJECT FINANCE? BANKING HANDY GUIDE

USAID-Funded Nepal Hydropower Development Project (NHDP)

COMPETITIVE BIDDING FRAMEWORK IN INDIA MOHAN MENON

Nigeria Power Series - Part 2: Unlocking Financing for Developing Independent Power Projects in Nigeria

Raising Equity for large biomass to power projects

Public Private Partnerships

AIRPORT BOTS/ CONCESSIONS CHECKLIST OF LEGAL AND REGULATORY ISSUES

AGENDA ITEM #9 SUMMARY

EPC CONTRACTS FOR WIND ENERGY PROJECTS - SOUTH AFRICAN RE IPP PROGRAMME - LESSONS LEARNED FROM PHASES 1 AND 2 (OCTOBER 2012)

PPP Arrangement in WtE Plants

1. INTERPRETATION 1.1 In this agreement unless the context shall otherwise require: (a) "We/Us/Our" is defined as Dawson Family Enterprises Pty Ltd

General Terms and Conditions of Sale

Mr Kevin DIXON Managing Director Asia Pacific Mott MacDonald

BOILERS DIRECT (YORKSHIRE) LTD TERMS AND CONDITIONS

Self Invested. SIPP Terms & Conditions. ivcm.com

SOCIEDAD CONCESIONARIA AUTOVÍA A-4 MADRID, S.A.

MBF1223 Financial Management Prepared by Dr Khairul Anuar

DNE PLUMBING & HEATING TERMS AND CONDITIONS

Standard Terms & Conditions of Sale

ANDRA JEWELS LIMITED TERMS & CONDITIONS OF SUPPLY

Attachment 13 Compensation Following Termination

Seminar on Port Reform. World Bank CONCESSION DESIGN PORT TERMINAL. Aqaba Development Corporation Hashemite Kingdom of Jordan

TERMS AND CONDITIONS OF SALE

SCHEDULE 9 COMPENSATION ON TERMINATION TABLE OF CONTENTS 1. TERMINATION FOR AUTHORITY EVENT OF DEFAULT OR AT AUTHORITY S OPTION...

International Advanced Certificate in Purchasing and Supply PREPARING AND MANAGING CONTRACTS. A8/May11 LEVEL 4 MARKING SCHEME. May 2011.

Financing your wind farm: An overview of the technical due diligence process. Ari Liddell Engineering Team Manager Wind Prospect

STANDARD TERMS AND CONDITIONS FOR THE SALE OF GOODS ALL MARKETS EXCEPT OIL AND GAS

Residential mortgages JANUARY Mortgage conditions. First edition

General Purchase Order Terms and Conditions (Pro-buyer)

GARDEN DESIGNER / LANDSCAPER TERMS AND CONDITIONS BUSINESS CLIENTS

KISS COMPANIES: TERMS AND CONDITIONS OF SUPPLY. NOTE: Your attention is particularly drawn to the contents of clause 13.

LOAN AGREEMENT (Ordinary Operations) (North-South Road Corridor Investment Program Project 2) between REPUBLIC OF ARMENIA. and ASIAN DEVELOPMENT BANK

Conditions of Sale Scania Australia Pty Ltd General Terms (ACN Scania ) 1. General Customer Goods Manufacturer Purchase Price

ADDITIONAL POLICY CONDITIONS AND PROPERTY COVERAGE TERMS

dentons.com Project Risks Identifying and allocating risks in international energy and infrastructure projects

VKP WAREHOUSING (PTY) LTD

THE NATIONAL TREASURY. Republic of South Africa

San Diego County Water Authority Special Board of Directors Meeting September 20, 2012

Conditions of Contract for PLANT and Design-Build

I-635 LBJ EAST PROJECT DESIGN-BUILD CONTRACT TERM SHEET

Top Ten Tips for Negotiating an LTSA

FEDERAL RESOURCES SUPPLY COMPANY GENERAL TERMS AND CONDITIONS FOR THE PROVISION OF SERVICES

TERMS & CONDITIONS CONTRACTOR SERVICES

WHITBY HYDRO CONNECTION AGREEMENT FOR A GENERATOR WITH MOMENTARY CLOSED TRANSITION OPERATION

BOOKING CONDITIONS. Please read these booking conditions carefully. They form an important part of your contract. 1. Introduction

Creative Financing & Funding for WTE Projects

CREDIT ACCOUNT APPLICATION FORM

APPENDIX D Glossary of Words & Terms

Terms and Conditions of Sale

ABA Film Services Ltd. Terms and Conditions of Hire

APPENDIX 3 FAYAIR (STANSTED) LIMITED STANDARD TERMS OF BUSINESS. Aircraft means any aircraft in respect of which the Customer has requested Services;

PENTAXIA LIMITED TERMS AND CONDITIONS OF BUSINESS. 1.1 Definitions. In these Conditions, the following definitions apply:

NORTHERN INDIANA PUBLIC SERVICE COMPANY Second Revised Sheet No RATE 324 RATE FOR GAS SERVICE COMPRESSED NATURAL GAS SERVICE

MANAGEMENT AGREEMENT

UNITED STATES AND CANADA TERMS AND CONDITIONS OF SALE NOVEMBER 2006

Contract means the contract for the purchase and/or sale and/or hire of the Goods and/or the supply of Services.

F. No. 1(1)PF- II/2011 Government of India Department of Expenditure (Plan Finance-II Division) OFFICE MEMORANDUM

SAMPLE CONTRACT BETWEEN THE BOARD OF COMMISSIONERS OF THE PORT OF NEW ORLEANS AND CONTRACTOR NAME FOR SERVICES

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

SUMMARY OF ENGINEERING SERVICES MASTER SERVICES AGREEMENT

Power Purchase Agreement (PPA) Guidelines. Zambia Lusaka August 7 to

Transcription:

RISK MANAGEMENT FOR INFRASTRUCTURE PROJECTS & TERMSHEET DEVELOPMENT 1

CORE RISKS REGULATORY FRAMEWORK DEMAND PRICING OF SERVICES REVENUE 2

Regulatory Framework Risk Commercial operations will be feasible only if regulations permit Construction and ownership of facilities Imposition and revision of price for services provided Retention and appropriation of profits by PSP Creation of charge on Project Assets/Facility and receivables Mitigation It is necessary to : Conduct legal due diligence to identify regulatory deficiencies Obtain state commitment to necessary change of law and make government liable for risks change of change in law. 3

Risk Demand Demand estimates may not be there in a green field project (NGHC Project in Ranchi, Jharkhand) or be unrealistic as usually they are derived from macro economic and demographic projections. The establishment of a competing facilities can affect demand adversely. Mitigation Provide for extension of Concession Period in case Project IRR is not achieved/ state support to tariff as sub-debt.. Provision not to establish a competing Facility but restriction should be reasonable- for specified period or in specified area. Upfront offtake commitment from consumers - take or pay contract. 4

Risks Risk lies in : Pricing of Services Losing consumers/ collective resistance- historically infrastructure has been a free or under priced pubic good Securing regulatory approval. Mitigation Make consumers aware of price of existing or competing facilities or services, savings available by use of facility Price discrimination-higher prices for commercial or industrial users, lower prices for weaker sections/frequent users Willingness to pay surveys to be carried out to establish price elasticity 5

Risk Revenue Support Risk of inadequate return is high, demand is uncertain, PSP may not free to determine prices on commercial basis or be required to provide free or cheaper services to target groups. Mitigation Government has to under write a minimum rate of return, through the following Fiscal incentives waivers of stamp duties and registration charges, tax exemptions etc, Compensation to PSP in cash or by extension of Concession Period if PSP is required to provide free good/service In Road Projectscompensation in case of addition to exempted category. Revenue Shortfall Support by way of loan from Government to meet debt service and O&M Expenses. Non competing facilities restricted or regulated. Development Rights 6

CONSTRUCTION RISKS DESIGN CONSENTS CONSTRUCTION COST CONSTRUCTION TIME DEFECTS IN CONSTRUCTION 7

Design Risk The Project Design is usually prepared by private sector participant with approval by the Government or Independent Engineer. Mitigation This risk is allocated to Concessionaire with a pass through to the EPC Contractor. No liability on Government for review or failure to review by Government or Independent Engineer.. 8

Consents Approvals needed from Competent Authorities (Central, State or local bodies). Some affected areas are : Environmental Clearances, particularly for forests, coastal zones etc. Land Development Statutory Approvals of Master Plans etc. Regulation by PSP- Traffic on the Project Road Various Construction and O&M activities Acquiring land, shifting of utilities or removal of encroachments Rehabilitation of PAPs The allocation of this risk between PSP and State should be clearly defined. State typically agrees for best effort assistance but should be made responsible for providing clearances within its control and power and provide facilitation of others 9

Mitigation Consents (contd ) A general principle for effective allocation would be to : Allocate responsibility for clearances/consents on technical, commercial and financial issues to PSP. There may be a pass through to the EPC Contractor. Allocate responsibility for land acquisition, shifting utilities, removing encroachments, rehabilitation, environment to the State entity. Risks of delays in obtaining approval and implication of that on cost needs to be assessed. In Punjab, GOP has agreed to pay for damages in case of delays in providing unencumbered possession of site with caps and for removal of utilities by the PSP. 10

Construction Cost Preferably a single EPC Contractor to avoid interface risks Use of lumpsum turnkey contracting basis to obtain fixity of cost Clearing state circumstances under which the Concessionaire may claim additional remuneration, which should be : i e- Change of Scope Inflation risk etc. should be factored in the lump sum price contingent funding provision should be made Relief should be given for cost overruns due to default or delay of public partner or non-insurable Force Majeure Events this could be in cash or extension of Concession Period. 11

Construction Time Is time the essence of the contract? Monitor time more closely for the essential public components and leave it to PSP for commercial components in which profit sense will motivate PSP Pre qualification and bid evaluation process (technical capacity, financial strength and track record) to establish the PSP s ability for implementation of Project, including timely completion Implementation Schedule should be clearly delineated with milestones for sub-activities. Time extension on payment of liquidated damage for delay. After which State entitled to terminate. Periodic reporting and inspection by Monitoring Agency Commercial incentive for early completion COD achieved earlier and therefore longer Operations Period. 12

Defects in Construction Clearly stated Specifications and Standards to determine performance Testing requirements to be detailed Defects Liability Period LDs for failure to meet performance parameters Performance Security and/or retention of payments Insurances 13

OPERATION & MAINTENANCE RISKS PERFORMANCE COST SECURITY OF FACILITIES 14

Operational Performance Periodic Reporting and Monitoring of performance. Performance Standards should be outlined clearly. Liability on PSP to remove, repair, replace the defects or defaults. Performance Security LDs for failure to meet performance parameters Circumstances in which performance standards may be relaxed may be outlined i.e..lane closure for repairs or under government orders. Insurances 15

Cost of O&M The Operator will be bound to contracted fixed cost and will carry risk of variation, subject to suitable index linkage to compensate for inflation. indexation basis must be aligned to factors affecting cost of operations Operator may be given incentives for performance in form of revenue share in which case the Operator may be willing to absorb the cost risk GENERALLY the construction and O&M risks are allocated to the PSP unless the same are due to the public partner. It is desirable to make the contractor and operator a stakeholder in the Project SPV. 16

FINANCIAL RISKS LIQUIDITY INTEREST RATE EXCHANGE RATE DEBT SERVICE RISK 17

Liquidity Risk Achievement of Financial Close prior to construction commencement. (Wet and Dry Financial Closure). Agreement to be bankable- step in rights, substitute entity, creation of securities in favour of lenders, cross default provision, escrowing of receivable. Matching of payment obligations with draw down from lenders and investors Contingent financing commitments from sponsors/promoters to cover overrun obligations. Billing and collection to be benchmarked and monitored (redressal of complaints, fast track resolution of billing disputes, rebates for down payment or to early birds, loyalty bonus, security deposit from consumers etc.) 18

Interest Rate & Foreign Exchange Risk Where the Concession is structured on a fixed rate of return on total cost of project, the project borrowings must be contracted on corresponding fixed rate basis. Interest rate swaps should be considered to hedge any floating rate exposure. a judicial mix of fixed rate and floating rate instruments may be used. Project could be subject to exchange rate risk on account of foreign currency denominated payment obligations to Contractor or Operator or debt servicing of foreign currency borrowings Where project revenue accrues entirely in local currency, exchange risk should be eliminated through swaps and forward cover 19

Debt Servicing A debt service reserve to be maintained to ensure debt servicing Access to standby line of credit. 20

INSURANCE 21

Insurance : Project Construction Use of insurance must be maximised in infrastructure projects in view of a limited recourse format As best practice, insurance for project construction must be taken jointly covering Concessionaire, contractors and operators Construction/Erection all risks including Design risk cover Escalation Defect liability period Delay in Start Up : Debt service and other fixed costs Third Party Liability The contractor must be bound to take adequate cover for : Construction plant and equipment Workmen s compensation 22

Insurance : Project Operation Insurance cover, post commencement of operations : Fire Machinery Breakdown Cash in safe and in transit Business Interruption Third Party Liability Mandatory public liability insurance, wherever applicable Operator must take insurance for : Workmen s compensation Employee fidelity 23

ENVIRONMENTAL AND SOCIAL RISKS ENVIRONMENTAL RISKS SOCIAL RISKS 24

Environmental Risks Legislation relating to environment protection has been enacted by the Central as well as State Governments The law specifies Impact assessment requirements for proposed projects Review and clearance process and authority Change of law during project construction or operation could increase project cost or prevent operation of facilities altogether Specialised consultants must be used to carry out the EIA and develop the EMP An implementation monitoring framework must be established as part of EMP 25

Management of Environmental Risks Support commitment of the government sponsor to facilitate the process of obtaining requisite clearances and exemptions Change of regulations having a material adverse effect to be treated as a force majeure risk to be underwritten by the government partner The risk of additional costs necessitated by change in regulation may require tariff revision by pass through. 26

Social Risks Social risks arise out of : Displacement of persons from project sites Loss or impairment of livelihood Loss of access rights etc. 27

Framework for Managing Social Risks Land and right of way acquisition and rehabilitation of displaced persons must be the obligation of the state sponsor Effective monitoring of implementation plan for rehabilitating PAPs must be established. Local Law provisions to be explored- Maharashtra Projects involving large scale displacement populations may not be amenable to commercialisation. 28

FORCE MAJEURE & TERMINATION FORCE MAJEURE POLITICAL NON POLITICAL TERMINATION 29

Political Force majeure Force Majeure Nationalisation; Political Agitations; Riots; Change in Law; Court Order; Acts of State Authorities Non Political Force Majeure Earthquake, Cyclone, Floods; Fire, Explosion; Epidemic; War; Labour Disputes Mitigation This risk is mitigated through insurance and back stop by government 30

Termination Government Event of Default Material Breach of Obligations Change in Law Defective Title, Ownership & Possession of Project Site Delay or Omissions Concessionaire Event of Default Material Breach of Obligations Omissions, Delay Liquidation, Winding-up, Re-organisation Abandonment of Project Force Majeure 31

Termination Mitigation Defaulting party liable for termination payments to the extent the same are not covered by insurance. The Government invariable bears the political and sovereign risks; non-insurable political force majeure risks. Government required to back stop lenders. 32

INDEPENDENT REVIEW 33

Independent Review Institutional framework for independent review Nomination of eminent persons to the SPV Board Empowered committee of experts Independent Engineer and Independent Auditor Internal Auditor for the SPV 34

Principles of Risk Allocation It is economically efficient to allocate risks to the party in the best position to manage and control them or insure them Risk allocation should be to achieve Pareto Optimality. Commercial risks should be allocated to the private sector and political risks to the state sector Ensure a stake for each party in fixing uncontrollable risks : so that all parties work together to manage the risk. Notwithstanding risk management, we still have to live with a 9/11, Tsunami or New Orleans. This is why in the case of compensation for factors, profit, being a reward for risk taking, is the highest. 35