9/9/2015 PLANNED PRODUCTION AT TULU KAPI EXPANDED BY 33% FE InvestEgate PLANNED PRODUCTION AT TULU KAPI EXPANDED BY 33% RNS Number : 2038Y 07 September 2015 7 September 2015 ("KEFI" or the "Company") PLANNED ANNUAL GOLD PRODUCTION AT TULU KAPI EXPANDED BY 33% REVISED PRODUCTION TARGET OF 100,000 OZ PER ANNUM POST-TAX NPV INCREASED BY CIRCA 18% WINNING BIDDER EMERGES FROM TENDER FOR MINING CONTRACT KEFI Minerals (AIM: KEFI), the gold exploration and development company with projects in the Kingdom of Saudi Arabia and the Federal Democratic Republic of Ethiopia, is pleased to report an increase in planned production at Tulu Kapi to an average of c. 100,000 oz per annum over a 10-year period, compared with the previous estimate of an average of c. 75,000 oz per annum over a 13-year period, and that a winning bidder has emerged from the tender for the mining contract. Expansion in planned production The expansion in anticipated production is a result of a planned increase, based on the Company's ongoing discussions with potential project contractors, in process plant capacity from 1.2Mtpa to 1.5Mtpa. Based on the bids received from construction contractors, this expanded plant capacity does not increase the assumed level of funding required to develop Tulu Kapi. The construction contractors short-listed from the eleven candidates have now been invited to submit fixed price bids for the larger plant. This c. 33% increase in planned average annual gold production has no effect on the open-pit mine plan as set out in the recently-released 2015 Definitive Feasibility Study ("2015 DFS") as the 2015 DFS envisaged processing stockpiles over the final three years of 13 years of gold production. However, KEFI expects it to reduce All-in Sustaining Costs from c. US$779/oz (estimated in the 2015 DFS) to c. US$760/oz. The planned process plant expansion increases Tulu Kapi's after-tax Net Present Value http://www.investegate.co.uk/articleprint.aspx?id=201509070700252038y 1/4
9/9/2015 PLANNED PRODUCTION AT TULU KAPI EXPANDED BY 33% FE InvestEgate at the start of construction from US$125 million to US$147 million (approximately 92 million), based on unleveraged cash flows, a gold price of US$1,250/oz and an after-tax discount rate of 8%. At the current spot price of US$1,122/oz, Net Present Value is US$90 million (approximately 56 million) on the same basis. Selection of mining contractor A winning bidder has emerged from the five short-listed candidates who were asked to bid on a 6-year mine operation contract. The five candidates had previously been reduced from ten candidates, all of whom are international leaders and experienced in Africa. The tender's result has also re-affirmed the assumptions underlying the cash flow estimates for the period of the planned banking arrangements covering two years of construction plus six years of operation. The winning bidder and the nearest under bidders have been invited to bid for an expanded scope of work to include the pre-mining site earthworks and the full 10 years of mining the open pit. This is expected to further improve the mining cost per tonne. The Company will then formalise an appointment. Harry Anagnostaras-Adams, Executive Chairman, said: "We are pleased to report an increase in Tulu Kapi's planned gold production and, in particular, that it is likely to have a favourable impact on the All-in Sustaining Costs and cash flow, thereby further improving the economics of the project. "The emergence of the least-cost mining contractor, who will now need to bid for an expanded scope of work, also represents an important step towards reaching the development stage. We look forward to being able to report further improvements in project economics once the final bids have been received." ENQUIRIES Harry Anagnostaras-Adams (Executive Chairman) +357 9945 7843 SP Angel Corporate Finance LLP (Nominated Adviser) Ewan Leggat, Katy Birkin +44 203 470 0470 Brandon Hill Capital Ltd (Joint Broker) Oliver Stansfield, Alex Walker, Jonathan Evans +44 207 936 5200 Beaufort Securities Ltd (Joint Broker) Elliot Hance +44 207 382 8300 Luther Pendragon Ltd (Financial PR) Harry Chathli, Claire Norbury, Oliver Hibberd +44 207 618 9100 Further information can be viewed on KEFI's website at www.kefi-minerals.com NOTES TO EDITOR http://www.investegate.co.uk/articleprint.aspx?id=201509070700252038y 2/4
9/9/2015 PLANNED PRODUCTION AT TULU KAPI EXPANDED BY 33% FE InvestEgate KEFI is the operator of two advanced gold development projects within the highly prospective Arabian-Nubian Shield, with an attributable 1.93Moz (100% of Tulu Kapi's 1.72Moz and 40% of Jibal Qutman's 0.73Moz) gold Mineral Resources (JORC 2012) plus significant resource growth potential. KEFI targets that production at these projects generate cash flows for further exploration and expansion as warranted, recoupment of development costs and, when appropriate, dividends to shareholders. Expected milestones for the remainder of 2015 at Tulu Kapi include: Formalisation of project contracting, senior secured financing and equity funding Full development funding and commencement of construction In addition, during 2015 KEFI anticipates submitting a Mining Licence Application for Jibal Qutman in Saudi Arabia through its joint venture company, Gold & Minerals Ltd ("G&M"). KEFI Minerals in Ethiopia The Tulu Kapi gold project in Western Ethiopia is being rapidly progressed towards development following the Mining Licence being granted in April 2015 and subsequent completion of KEFI's Definitive Feasibility Study. The Company is now refining contractual terms for project construction and operation. Latest estimates for annual gold production are c. 100,000 oz pa for a 10-year period and for All-in Sustaining Costs (including operating, sustaining capital and closure) are c. US$760/oz (excluding initial investment). Tulu Kapi's Ore Reserve estimate totals 15.4Mt at 2.12g/t gold, containing 1.05 million ounces. KEFI Minerals in the Kingdom of Saudi Arabia In 2009, KEFI formed G&M in Saudi Arabia with local Saudi partner Abdul Rahman Saad Al-Rashid & Sons Company Limited ("ARTAR"), to explore for gold and associated metals in the Arabian-Nubian Shield. KEFI has a 40% interest in G&M and is the operating partner. To date, G&M has conducted preliminary regional reconnaissance and has had five exploration licences ("ELs") granted, including Jibal Qutman and the recently-granted Hawiah EL that contains over 6km strike length of outcropping gossans developed on altered and mineralised rocks with all the hallmarks of a copper-gold-zinc VHMS deposit. At Jibal Qutman, G&M's flagship project, Mineral Resources are estimated to total 28.4Mt at 0.80g/t gold for 733,045 contained ounces. The shallow oxide portion of this resource is being evaluated as a low capital expenditure heap-leach mine development. ARTAR, on behalf of G&M, holds 24 EL applications that cover an area of approximately 1,484km 2. ELs are renewable for up to three years and bestow the exclusive right to explore and to obtain a 30-year exploitation (mining) lease within the area. The Kingdom of Saudi Arabia has instituted policies to encourage minerals exploration and development and KEFI Minerals supports this priority by serving as the technical partner within G&M. ARTAR also serves this government policy as the major partner in G&M, which is one of the early movers in the modern resurgence of the Kingdom's minerals sector. http://www.investegate.co.uk/articleprint.aspx?id=201509070700252038y 3/4
9/9/2015 PLANNED PRODUCTION AT TULU KAPI EXPANDED BY 33% FE InvestEgate END This information is provided by RNS The company news service from the London Stock Exchange MSCLLFIAAVIRIIE http://www.investegate.co.uk/articleprint.aspx?id=201509070700252038y 4/4
9/9/2015 UPDATE ON TULU KAPI GOLD PROJECT FINANCING FE InvestEgate UPDATE ON TULU KAPI GOLD PROJECT FINANCING RNS Number : 4619Y 09 September 2015 9 September 2015 ("KEFI" or the "Company") UPDATE ON TULU KAPI GOLD PROJECT FINANCING PEAK FUNDING REQUIREMENT REDUCED APPROVED FUNDING PLAN FOR EQUITY CAPITAL FOR DEVELOPMENT TO BE RAISED AT PROJECT LEVEL KEFI Minerals (AIM: KEFI), the gold exploration and development company with projects in the Kingdom of Saudi Arabia and the Federal Democratic Republic of Ethiopia, is pleased to report that the Board of KEFI has approved the development funding plan for Tulu Kapi Gold Project, which includes equity capital for development to be raised at project level, rather than at the London-listed PLC level, to minimise value dilution for Company shareholders. In addition the approved plan has reduced the estimated peak funding requirement. KEFI's discussions with the shortlisted construction contractors, including further opportunities for value-engineering, has yielded potential reductions in the peak funding requirement from the US$130 million estimated in the 2015 Definitive Feasibility Study ("2015 DFS") to US$120 million as had previously been foreshadowed. This is despite the planned gold production being increased to an average of c. 100,000 oz per annum, as announced on 7 September 2015. Debt-style funding facilities may be up to US$100 million via a senior secured syndicate arrangement. A portion of these facilities is likely to have a tenor greater than the eight years proposed by conventional project finance banks, which is considered prudent due to volatility in markets generally. Planned contractor and financier commitment levels have been incorporated into estimated project cash flows. The remaining equity investment to develop Tulu Kapi is estimated to be c. US$20 million (in addition to the equity of US$65 million http://www.investegate.co.uk/articleprint.aspx?id=201509090700094619y 1/5
9/9/2015 UPDATE ON TULU KAPI GOLD PROJECT FINANCING FE InvestEgate invested in the past). KEFI plans to source this capital as minority equity investment in the project subsidiary, to be priced at a valuation based on Tulu Kapi's Net Present Value, which is c. US$90 million at current gold prices. The Company is in advanced discussions with several interested parties, including the Government of Ethiopia. Formalisation of this funding plan, which requires multi-party agreement of detailed documentation with the mine contractor, construction contractor, financiers and the Government of Ethiopia, is scheduled for Q4 2015. KEFI and the Government have already formalised many of the principal terms within the detailed Mining Agreement executed in April 2015, which reflected the key outcomes of the preliminary negotiations to that point with contractors and financiers. Harry Anagnostaras-Adams, Executive Chairman of KEFI, commented: "KEFI has, in the two years since acquiring Tulu Kapi, overhauled all project development plans and permitted the development of Tulu Kapi. Significantly, project development funding has been more than halved to US$120 million. KEFI is continuing to move forward according to the plan as agreed with the Government of Ethiopia and as laid out in the past to our shareholders. We look forward to updating shareholders upon the finalisation of funding and the commencement of construction by year end." ENQUIRIES Harry Anagnostaras-Adams (Executive Chairman) +357 99457843 SP Angel Corporate Finance LLP (Nominated Adviser) Ewan Leggat, Katy Birkin +44 203 470 0470 Brandon Hill Capital Ltd (Joint Broker) Oliver Stansfield, Alex Walker, Jonathan Evans +44 207 936 5200 Beaufort Securities Ltd (Joint Broker) Elliot Hance +44 207 382 8300 Luther Pendragon Ltd (Financial PR) Harry Chathli, Claire Norbury, Oliver Hibberd +44 207 618 9100 Further information can be viewed on KEFI's website at www.kefi-minerals.com BACKGROUND Capital Expenditure Extensive drilling and evaluation work has been undertaken on Tulu Kapi with approximately US$65 million having been invested to date, mostly by a previous owner of the asset. This work culminated in the recently-released 2015 DFS. The full 2015 DFS is available at: http://www.kefi-minerals.com/files/files/2015_tk_dfs_complete_final_web.pdf. http://www.investegate.co.uk/articleprint.aspx?id=201509090700094619y 2/5
9/9/2015 UPDATE ON TULU KAPI GOLD PROJECT FINANCING FE InvestEgate The capital expenditure required to develop Tulu Kapi, based on an owner mining approach, is estimated to total US$176 million. However, KEFI plans to take a contract mining approach, which reduced the estimated capital expenditure to US$141 million as noted in the 2015 DFS. Taking into account timing of payments and the initial six months of operating cash flow, the peak funding requirement was estimated to be US$130 million. Peak Funding Requirement The discussions with the construction contractors, along with some concurrent valueengineering, has yielded the following potential reductions in the peak funding requirement estimated in the 2015 DFS: Peak funding requirement for a 1.2Mtpa processing plant Less: savings identified during the bidding process Peak funding requirement for a 1.5Mtpa processing plant US$ million (approximate) 130 Per 2015 DFS, assuming contract mining 10 Net savings after capital required to expand processing plant 120 Being refined with contractors The combined effect of these items is that KEFI has reduced the estimated peak capital requirement to c. US$120 million. Debt-Style Funding KEFI is considering two alternatives for debt-style funding: commercial bank debt or a mixture of commercial bank debt and a development bank or gold streaming facility The term for a conventional commercial project finance loan would be up to eight years, including two years for construction and commissioning. The term would be longer for that portion arranged as a development bank loan or a gold-stream facility. A "gold-stream facility" would allocate to the lender a percentage of gold production at a fixed gold price in exchange for an advance payment to fund construction. Minority Equity Investment in the Project Subsidiary The project subsidiary is wholly-owned by and the Government of Ethiopia is entitled to a 5% free carry. Several parties are considering an equity investment of US$20-25 million in the project subsidiary. NOTES TO EDITOR KEFI is the operator of two advanced gold development projects within the highly prospective Arabian-Nubian Shield, with an attributable 1.93Moz (100% of Tulu Kapi's 1.72Moz and 40% of Jibal Qutman's 0.73Moz) gold Mineral Resources (JORC 2012) plus significant resource growth potential. KEFI targets that production at these projects generate cash flows for further exploration and expansion as warranted, recoupment of development costs and, when appropriate, dividends to shareholders. http://www.investegate.co.uk/articleprint.aspx?id=201509090700094619y 3/5
9/9/2015 UPDATE ON TULU KAPI GOLD PROJECT FINANCING FE InvestEgate Expected milestones for the remainder of 2015 at Tulu Kapi include: Formalisation of project contracting, senior secured financing and equity funding Full development funding and commencement of construction In addition, during 2015 KEFI anticipates that through its joint venture company in Saudi Arabia, Gold & Minerals Ltd ("G&M"), it will commence drilling at new licence Hawiah and assemble a Mining Licence Application for its discovery at Jibal Qutman in Saudi Arabia KEFI Minerals in Ethiopia The Tulu Kapi gold project in Western Ethiopia is being rapidly progressed towards development with the Mining Licence being granted in April 2015. KEFI's Definitive Feasibility Study was then completed and the Company is now refining contractual terms for project construction and operation. Latest estimates for annual gold production are c. 100,000 oz pa for a 10-year period and for All-in Sustaining Costs (including operating, sustaining capital and closure) are c. US$760/oz (excluding initial investment). Tulu Kapi's Ore Reserve estimate totals 15.4Mt at 2.12g/t gold, containing 1.05 million ounces. KEFI Minerals in the Kingdom of Saudi Arabia In 2009, KEFI formed G&M in Saudi Arabia with local Saudi partner Abdul Rahman Saad Al-Rashid & Sons Company Limited ("ARTAR"), to explore for gold and associated metals in the Arabian-Nubian Shield. KEFI has a 40% interest in G&M and is the operating partner. To date, G&M has conducted preliminary regional reconnaissance and has had five exploration licences ("ELs") granted, including Jibal Qutman and the recently granted Hawiah EL that contains over 6km strike length of outcropping gossans developed on altered and mineralised rocks with all the hallmarks of a copper-gold-zinc VHMS deposit. At Jibal Qutman, G&M's flagship project, Mineral Resources are estimated to total 28.4Mt at 0.80g/t gold for 733,045 contained ounces. The shallow oxide portion of this resource is being evaluated as a low capital expenditure heap-leach mine development. ARTAR, on behalf of G&M, holds 24 EL applications that cover an area of approximately 1,484km 2. ELs are renewable for up to three years and bestow the exclusive right to explore and to obtain a 30-year exploitation (mining) lease within the area. The Kingdom of Saudi Arabia has instituted policies to encourage minerals exploration and development and KEFI Minerals supports this priority by serving as the technical partner within G&M. ARTAR also serves this government policy as the major partner in G&M, which is one of the early movers in the modern resurgence of the Kingdom's minerals sector. http://www.investegate.co.uk/articleprint.aspx?id=201509090700094619y 4/5
9/9/2015 UPDATE ON TULU KAPI GOLD PROJECT FINANCING FE InvestEgate This information is provided by RNS The company news service from the London Stock Exchange END MSCEAKNPELESEFF http://www.investegate.co.uk/articleprint.aspx?id=201509090700094619y 5/5