NEW PARKLAND HOSPITAL HALF TIME VISITING THE PROJECT TEAM S LOCKER ROOM H A N K A D A M S, A I A, A C H A, E D A C V I C E P R E S I D E N T / D I R E C T O R H E A L T H C A R E, H D R D E S I G N M A N A G E R F O R H D R + C O R G A N J V
T H R E E Y E A R S A G O
» THE FIELD» DEFINING THE PLAYS» LOCKER ROOM AT HALF TIME» REVIEWING TAPE PRESENTATION AGENDA
THE FIELD
EVERYTHING IS BIGGER IN TEXAS
» New Parkland Hospital 64 Acre Campus 17 Stories = 300 Feet High Patient Tower Length = 600 Feet Total Area Campus = 2.7M Square Feet Cost = $1.271B» Cowboys Stadium 73 Acre Site 292 Feet High Stadium Length = 900 Feet Total Area = 3M Square Feet Cost = $1.3B
T H E T E A M
N O V E M B E R 4, 2 0 0 8 By an overwhelming majority, the citizens of Dallas County voted for the construction of a new Parkland Hospital 82%
T H E G A M E I S F O U R Q U A R T E R S 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Original Parkland Master Plan Programming Bond Approval (November 4, 2008) A/E Selection Process Design & Construction Team Awarded (March 2009) Master Plan Schematic Design Design Development Construction Documents Construction Transition / Occupancy
KICK OFF
» October 28, 2010 GROUNDBREAKING
ED WISH Acute Care Tower WISH Clinic Med/Surg Clinic DART Parking Garage MASTER PLAN CONCEPT
Acute Tower Trauma Tower WISH Tower WISH clinic/ Administration Parking Patient/Visitor MASTER PLAN CONCEPT SITE AERIAL
PUT THE PARK BACK IN PARKLAND FROM ITS ORIGIN AS WOODED PARK LAND
DEFINING THE PLAYS
THE COLLABORATIVE TEAM
T H E T E A M : C O L L A B O R AT I V E P R O J E C T D E L I V E R Y Team Members» Big Room» Meeting Space» IT Infrastructure» Interior Mock-Up Spaces» Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
Team Members Big Room Meeting Space IT Infrastructure Interior Mock-Up Spaces Exterior Mock-Ups
T H E P L AY B O O K :» Decision Making Strategy Visioning Decision Making Structure Clinical Liaison Role
T H E P L AY B O O K :» Decision Making Strategy Visioning Decision Making Structure Clinical Liaison Role
T H E P L AY B O O K :» Decision Making Strategy Visioning Decision Making Structure Clinical Liaison Role
A S S E S S I N G F I E L D C O N D I T I O N S : P L A N N I N G F O R C O N S T R U C T I O N Opportunities Risks Enablers Enablers
A S S E S S I N G F I E L D C O N D I T I O N S : P L A N N I N G F O R C O N S T R U C T I O N» Pre-Fab PT Wall Lean and Technology
O P P O R T U N I T Y: P R E FA B R I C AT I O N» 750 bathroom pods» Three miles of overhead mechanical/electrical racks» 850 headwalls Prefabrication enhanced the project schedule, maximized the quality of the finished product and enhanced safety by allowing several trades to work at waist-toshoulder height instead of using ladders in a congested construction zone.
Prefabrication enhanced the project schedule, maximized the quality of the finished product and enhanced safety by allowing several trades to work at waist-toshoulder height instead of using ladders in a congested construction zone. O P P O R T U N I T Y: P R E FA B R I C AT I O N» 750 bathroom pods» Three miles of overhead mechanical/electrical racks» 850 headwalls
Prefabrication enhanced the project schedule, maximized the quality of the finished product and enhanced safety by allowing several trades to work at waist-toshoulder height instead of using ladders in a congested construction zone. O P P O R T U N I T Y: P R E FA B R I C AT I O N» 750 bathroom pods» Three miles of overhead mechanical/electrical racks» 850 headwalls
Prefabrication enhanced the project schedule, maximized the quality of the finished product and enhanced safety by allowing several trades to work at waist-toshoulder height instead of using ladders in a congested construction zone. O P P O R T U N I T Y: P R E FA B R I C AT I O N» 750 bathroom pods» Three miles of overhead mechanical/electrical racks» 850 headwalls
D I A G R A M M I N G P L AY S : B I M / C O N S T R U C T I O N M O D E L Practice makes perfect
RISK: POST-TENSION WALL
RISK: Post-Tension Wall
RISK: Post-Tension Wall
E N A B L E R S : L E A N A N D T E C H N O L O G Y
LOCKER ROOM AT HALF TIME
YOUR HALF TIME SHOW
REVIEWING THE TAPES: PREPARING FOR THE SECOND HALF
T O U C H D O W N!» On-stage/off-stage incorporated» Integrated Design» Sustainability tracking LEED Silver, New Construction» On schedule» On budget
F L A G O N T H E P L AY» Stoppage of Co-Location too Soon» Pre-fabrication efforts could have been more robust» Changes in regulatory requirements» Parkland leadership changes» Volume changes outpacing expectations
T I M E O U T» Create a Strong Vision» Co-Locate and Collaborate» Design for the Future» Mock Ups as Design Tools» Plan Early for Occupancy
NEW PARKLAND HOSPITAL HALF TIME VISITING THE PROJECT TEAM S LOCKER ROOM H A N K A D A M S, A I A, A C H A, E D A C V I C E P R E S I D E N T / D I R E C T O R H E A L T H C A R E, H D R D E S I G N M A N A G E R F O R H D R + C O R G A N J V