HRPP 358. Adapting flood risk management for an uncertain future: Flood management planning on the thames estuary. D. Ramsbottom & T.

Similar documents
HRPP 313. Developing a performance - based management system for flood and coastal defence assets

Climate Change and Flood Risk. Tim Reeder Regional Climate Change Programme Manager

Consider the risks to your own business as well as to your operations

EFRA Select Committee Enquiry on Climate Change Submission from the Association of British Insurers (ABI), October 2004

HRPP 359. Integrated flood risk management progress from the FLOODsite project

Evidence for Environmental Audit Committee Enquiry on Sustainable Housing Submission by Association of British Insurers, May 2004

Lowestoft. Summary 2016 FLOOD RISK MANAGEMENT. Mike Page

Planning and Flood Risk

National Infrastructure Assessment Technical Annex. Technical annex: Flood modelling

Frequently Asked Questions

IRISH FLOOD PREVENTION PROGRAMME Example of integrating climate change adaptation into projects

Lowestoft Flood Risk Management Project

Environment Agency pre-application advice incorporating Local Flood Risk Standing Advice from East Lindsey District Council

Assessing future flood risk across the UK

PRESENTATION BY OPW TO JOINT OIREACHTAS COMMITTEE ON CULTURE, HERITAGE, AND THE GAELTACHT

Severn Estuary Flood Risk Management Strategy. Report on 2013 Consultation

National Assessment of Defence Needs and Costs for flood and coastal erosion management (NADNAC) Summary Report

The London to Fishguard Trunk Road (East of Magor to Castleton) Order 201-

CHAPTER 10 FLOOD RISK

PLANNING FOR SAFE AND SUSTAINABLE COMMUNITIES

Flood and Coastal Risk Management - A Risk Based. David Rooke Head of Flood & Coastal Risk Management 20 March 2009

Flood Risk Management Planning in Scotland: Arrangements for February 2012

Edmund C. Penning-Rowsell, Nick Haigh, Sarah Lavery & Loraine McFadden

The AIR Coastal Flood Model for Great Britain

Kirkwall (Potentially Vulnerable Area 03/05) Local Plan District Local authority Main catchment Orkney Orkney Islands Council Orkney coastal Backgroun

Derry City & Strabane District Council 17th July 2015, 3pm.

Contents Amendment Record

Reservoir safety risk assessment a new guide

Planning for Sustainable Drainage and Permeable Surfaces

Recent developments in loss of life and evacuation modelling for flood event management in the UK

Barry Island and Docks (2)

Engineers Ireland Annual Conference

Future flood risk management in the UK

Development and Flood Risk - the Environment Agency s approach to PPS25. scrutinised before planning decisions are made

Product 4 (Detailed Flood Risk) for Our Ref: OX_0748_01. Mill Lane, Somerford Keynes

Implementation processes for the Flood Risk Management (Scotland) Act 2009

Protocol for the maintenance of flood and coastal risk management assets (England only) Version 4, 27/01/2014 UNCLASSIFIED

FLOODING INFORMATION SHEET YOUR QUESTIONS ANSWERED

Introduction Tool 1: Exploring the Risk Context Tool 2: Developing Adaptation Actions... 8

Decision Support Methods for Climate Change Adaption

Adaptation Practices and Lessons Learned

Broad-Scale Assessment of Urban Flood Risk Mark G. E. Adamson 1

COASTAL GROUPS IN ENGLAND THE ENVIRONMENT AGENCY STRATEGIC OVERVIEW OF SEA FLOODING AND COASTAL EROSION RISK MANAGEMENT MARCH 2008

COASTAL FLOOD RISK THINKING FOR TOMORROW, ACTING TODAY

Strategic flood risk management

Ellon (Potentially Vulnerable Area 06/12) Local Plan District North East Local authority Aberdeenshire Council Main catchment River Ythan, Buchan coas

Flood Risk Management: Modelling blockage and breach scenarios February 2015

Undertaking national flood risk assessment in England, United Kingdom Jonathan Simm

STANDARDS FOR MODELLING OF FLOODING IN OPEN COASTS AND LARGE ESTUARIES

Managing flood risk on the Severn Estuary Gloucestershire. January 2011

River Lugg Internal Drainage Board. Policy Statement on Flood Protection and Water Level Management

Review of preliminary flood risk assessments (Flood Risk Regulations 2009): guidance for lead local flood authorities in England

The AIR Inland Flood Model for Great Britian

Isle of Arran (Potentially Vulnerable Area 12/08) Local Plan District Local authority Main catchment Brodick to Kilmory Ayrshire North Ayrshire Counci

Flood Risk Management in Ireland. The National CFRAM Programme & overview of the Capital Works Programme. Click to add text

Solway Local Plan District 1 Flood risk management in Scotland 1.1 What is a Flood Risk Management Strategy? Flood Risk Management Strategies have bee

INSURANCE AFFORDABILITY A MECHANISM FOR CONSISTENT INDUSTRY & GOVERNMENT COLLABORATION PROPERTY EXPOSURE & RESILIENCE PROGRAM

Economics of Climate Adaptation

Unique ID: (from PFRA database) Location: Nenagh, Co. Tipperary. Stage 1: Desktop Review

Creetown (Potentially Vulnerable Area 14/17) Local Plan District Local authority Main catchment Dumfries and Galloway Solway Moneypool Burn Council Ba

Defra/Environment Agency Flood and Coastal Defence R&D Programme

investing for the future

Fluvial Flood Defence Asset Management Plan. Tuesday 11 January Angus Pettit WDR & RT TAGGART

National Flood Risk Assessment Key facts. Environment Agency 1 NaFRA 2005 Key Facts

Clyde south - Port Glasgow to Inchinnan (Potentially Vulnerable Area 11/09) Local Plan District Clyde and Loch Lomond Local authority Inverclyde Counc

National-scale assessment of current and future flood risk in England and Wales

Fort William (Potentially Vulnerable Area 01/25) Local authority Main catchment The Highland Council Appin coastal Background This Potentially Vulnera

Climate adaptation: Risk, uncertainty and decision-making

Presentation Overview

Submission to the Department of Public Expenditure and Reform on the Review of the Public Capital Programme

Nairn Central (Potentially Vulnerable Area 01/18) Local authority Main catchment The Highland Council Moray coastal Background This Potentially Vulner

THE EFFECTIVENESS OF FLOOD MANAGEMENT

Guildford Borough Level 1 Strategic Flood Risk Assessment Summary Report. January 2016

Adapting to coastal change in England: some practical experiences. Nick Hardiman, Senior Coastal Adviser Environment Agency Paris June 2015

BACKGROUND When looking at hazard and loss data for future climate projections, hardly any solid information is available.

FLOOD SOLUTIONS Residence

Indicators and trends

A Floodsmart Future Strategic Flood Risk Management in Brisbane Authors: Ellen Davidge (Brisbane City Council), Greg Rogencamp (Sinclair Knight Merz)

Modernization, FEMA is Recognizing the connection between damage reduction and

Dornoch (Potentially Vulnerable Area 01/07) Local Plan District Highland and Argyll Local authority The Highland Council Main catchment Dornoch coasta

Adapting to heatwaves and coastal flooding

Unique ID: (from PFRA database) Location: Bridgetown, Co. Clare. Stage 1: Desktop Review

DRAFT Revised Guide to the National CDEM Plan 2015 July 2015

Oban (Potentially Vulnerable Area 01/31) Local authority Main catchment Argyll and Bute Council Knapdale coastal Background This Potentially Vulnerabl

Good Practice Guide. GPG 101 Document Owner: Steve Cook. Page 1 of 7.

To protect their property

Porthcawl to Sker Point (7)

SME Resilience to Extreme Weather Events: Important initiatives for informing policy making in the area

Arbroath (Potentially Vulnerable Area 07/07) Local Plan District Local authority Main catchment Tay Estuary and Montrose Basin Angus Council Brothock

West Wight Coastal Flood and Erosion Risk Management Strategy Appendix D Flood Risk Modelling and Mapping March 2016

The approach to managing natural hazards in this Plan is to: set out a clear regional framework for natural hazard management

RIVER LUGG INTERNAL DRAINAGE BOARD. Statement on Water Level and Flood Risk Management

Strategic Flood Risk Assessment (SFRA)

Glasgow City centre (Potentially Vulnerable Area 11/16) Local Plan District Local authority Main catchment Clyde and Loch Lomond Glasgow City Council

DRAFT STRATEGIC ENVIRONMENTAL ASSESSMENT SCREENING REPORT. Climate Change Sectoral Adaptation Plan for Flood Risk Management ( )

Risk of Flooding from Rivers and Sea

LLDC Flood Risk Review Summary Report. Issue 2 13 January 2017

Resilience to Flooding of Grid and Primary Substations

Vulnerability and Risk Assessment for the PFRA in Ireland

Climate risk management plan. Towards a resilient business

Transcription:

HRPP 358 Adapting flood risk management for an uncertain future: Flood management planning on the thames estuary D. Ramsbottom & T. Reeder Reproduced from a paper presented at: The 43rd Defra Flood and Coastal Management Conference Manchester University, UK 1 to 3 July 2008

ADAPTING FLOOD RISK MANAGEMENT FOR AN UNCERTAIN FUTURE: FLOOD MANAGEMENT PLANNING ON THE THAMES ESTUARY David Ramsbottom 1 & Tim Reeder 2 1 HR Wallingford Ltd 2 Environment Agency Key Words Flood, Planning, Adaptation Abstract A flood risk management plan is being developed for the Thames Estuary, covering the next 100 years. In 2007 flood risk management options (the High Level Options ) were developed for a range of different climate change scenarios. The objective was to provide initial flood risk management options for the estuary, and identify how the uncertainties of future climate change could be managed. Since then the options have been further developed to take into account other drivers including the deterioration of the existing flood risk management assets. Whilst the Plan will lead to preferred options for managing flood risk, it is recognised that the assumptions used to develop these options could change. The paper demonstrates how the options would be adapted to change. Whilst the main options have been developed to manage flood risk for the whole estuary, there are choices to be made at the local or Policy Management Unit (PMU) level. Hence the approach applies to both the estuary-wide and PMU levels. The main steps of the approach to adaptation are as follows: 1. The main drivers of flood risk management have been identified. These include, for example, climate change and socio economic change. 2. For each driver, a number of indicators have been identified which describe the impact of the driver. For example, indicators of climate change include sea level, which is rising, and fluvial flood flows. 3. For each indicator, thresholds have been identified where interventions are needed to maintain the required level of flood risk (for example, in the case of climate change, a particular sea level at Southend or a particular fluvial flow on the Thames). 4. Possible interventions for each threshold have been identified, for example the need to raise some of the defences when a certain water level is reached as the sea level rises. 5. The lead time for implementing each intervention at each threshold has been estimated. This is the time needed to plan and construct the intervention. 6. The rate of change of each indicator will be monitored. This is used to predict future change in the value of the indicator. From the predicted future change, the threshold value when an intervention will be required and the lead time, it is possible to estimate when a decision to implement an intervention must be made. This is referred to as a decision point. The identification of a decision point is illustrated on Figure A.1. 7. Figure A.1 also shows conceptually how to take account of uncertainty in decision making. 2008 1 HRPP 358

8. The decision to implement the intervention is taken at the decision point that takes account of uncertainty. 9. The same process is followed at estuary-wide level for all key indicators. This leads to the development of an option, which consists of a number of interventions throughout the century to respond to the different drivers. Figure A.2 shows an option developed for a small number of drivers, together with the decision points and lead times. 10. The indicators are monitored. If there are significant changes in the indicators compared with the assumptions in the Plan, the Plan must be reviewed. The review may either lead to the conclusion that the option is still satisfactory, although the timing of the interventions may change, or the change in the indicators is such that an alternative option is required. 11. As there is a chance that the Plan could change, responses should be as adaptable as possible to avoid undertaking work that may not be needed in the future. Indicator value (e.g. sea level rise) Threshold value of indicator when intervention is needed Lead time for planning and construction Decision point based on best estimate Decision point taking account of uncertainty Band of uncertainty Predicted values of indicator based on rate of change Recorded values of indicator Date of review Time Figure A.1 Decision making with an uncertain future Main Assumptions Abbreviations: Legend Policy Iteration B (P5 introduced in 2080) d/r Defences downriver of the Thames Barrier Defra climate change u/r Defences upriver of the Thames Barrier Decision point and lead time 70 Barrier closures per year TB Thames Barrier New infrastructure: London Gateway port Option Indicators Epoch 2000 2010 2020 2030 2040 2050 2060 2070 2080 2090 2100 2110 2120 2130 2140 2150 2160 2170 2180 Option 1 Extreme tidal WL Raise d/r defences Improve TB and raise downriver defences Thames flow Raise West London defences including demountables; receptor responses Barrier closures Raise u/r 0.5m Raise u/r 0.5m New barrage New port No navigation constraint downriver of new port Habitat area 1050ha managed realignment (total) Further habitat creation Figure A.2 An option, showing interventions and decision points 2008 2 HRPP 358

Background Following the 1953 floods the Thames Barrier and associated defence improvements were planned and built over a 30 year period to protect London and the Thames Estuary from tidal flooding. Given the challenge of climate change and the long timescales required to plan major improvements to the system, the Environment Agency has set up the Thames Estuary 2100 (TE2100) project. The project will develop a Flood Risk Management Plan for the Thames Estuary for the next 100 years. The project has included managing uncertainty as part of its approach to developing the Plan. This has been based on existing guidance from UKCIP (Willows & Connel 2003) and has been further developed through the ESPACE Project (European Spatial Planning Adapting to Climate Events) to develop and refine transnational methods. As part of the Plan, flood risk management options (the High Level Options ) were developed in 2007 for a range of different climate change scenarios. The objective was to provide initial flood risk management options for the estuary, and identify how they could be adapted if the rate of climate change (particularly sea level rise) changed (Ramsbottom & Lavery 2007). Since then the options have been further developed to take into account other drivers including the deterioration of the existing flood risk management assets. Whilst the Plan will lead to a preferred option for managing flood risk, it is recognised that the assumptions used to develop the options could change. The paper demonstrates how the options would be adapted to change. The flood risk management system Structural elements of the flood risk management system on the Thames Estuary are shown on Figure 1. The system includes the Thames Barrier, over 300km of fixed tidal defences, nine other major barriers and control structures, and numerous smaller structures. Thames Barrier Southend River Lee River Roding Canvey Island Westminster Tilbury Greenwich Teddington Weir River Darent Legend Gravesend River Thames Tidal flood risk area Tidal flood defences Other Barriers Figure 1 The Flood Risk Management System 2008 3 HRPP 358

The options include separate changes to the upriver defences, which are the tidal defences upriver (west) of the Thames Barrier, and the downriver defences, which are the tidal defences downriver (east) of the Thames Barrier. Future change and adaptation The Plan is designed to adapt to future change. Some of the main future changes which are taken into account in the development of the Plan are summarised below. Climate Climate change presents perhaps the greatest challenge in terms of future uncertainty. The impacts include expected rises in Mean Sea Level, peak surge tide level, wave heights and fluvial flows (Church & White 2006). Socio economic The Foresight Flood Risk project (OST 2004) identified the critical uncertainty that socio economic development presents to the future of flood risk. On a national scale it was more influential in changing the scale of future flood damages than the effects of climate change. Asset deterioration The deterioration of existing assets means that much of the existing flood management infrastructure will require replacement over the next 100 years, at a cost of several billion pounds. The rate of deterioration is therefore a vital factor in future planning. The physical environment (including estuary morphology) The estuary has an essentially fairly stable history over the last century or so in terms of its physical development. The outer sandbanks in the estuary protect it from the worst effects of wave attack. However sea level rise could disturb this picture and it will be essential to monitor the state of the estuary into the future. Public behaviour At present the awareness of flooding on the estuary is low, and the present high standard of protection means that there is little need for the public to be aware of the risk. However with an uncertain future, it may be desirable for this situation to change so that the public can be better prepared for the risk of future flooding. The types of adaptation envisaged within the Plan to cope with future change include the following (where an option is defined as a series of interventions to manage flood risk over the next 100 years): Changes to the timing of new interventions The Plan will have a preferred option for managing flood risk throughout the century given the envelope of change that is considered to be most likely based on current information. However the actual rate of change is likely to differ from the rates assumed in the Plan, and this could lead to changes in the timing of interventions. Ability to change between options If the rate of change of a critical factor is predicted or is observed to change significantly above the expected rate of change when the preferred option is selected, it may be necessary to switch to an alternative option that is able to cope with larger changes. Adaptation of engineering responses Engineering responses should be designed so that they can be adapted to changing circumstances, for example by providing foundations for new defences that can take higher future loadings, or designing barriers and other control structures that can be modified in the future. Land use planning that provides flexibility in the selection of options Each flood risk management option will require land for new defences, enlarged defences, new areas of habitat creation, and 2008 4 HRPP 358

in some cases flood storage. It is essential that the planning system is aware of the land required for the preferred option and the alternative options so that the land can be safeguarded. Adaptation to new infrastructure New infrastructure on the Thames Estuary could have a major impact on flood risk management. For example, the proposed new port at Shellhaven will require free access for navigation, which will affect any outer barrier or barrage options. New transport links could provide the opportunity to combine a new crossing of the estuary with a new barrage. The Plan should be flexible enough to accommodate major changes such as these. Procedure for developing the plan A set of options including a preferred option is a key output of the TE2100 Plan. The preferred option is needed to set the direction for flood risk management. The alternative options are needed in case the preferred option is no longer able to manage flood risk because the actual rate of future change is greater than expected. The method for developing the options at estuary-wide level is described in the following steps. 1. The main drivers of flood risk management are identified. 2. For each driver, indicators are identified which describe the impact of the drivers and can be monitored. 3. For each indicator, the thresholds where interventions are needed to maintain the required level of flood risk are identified. For example, in the case of climate change, a particular sea level at Southend or fluvial flow at Teddington. 4. A range of possible interventions for each threshold is identified. 5. The lead time for implementing each intervention is estimated. This is the time needed to plan and construct the intervention, in order to determine when decisions should be taken. 6. Options are developed for the following cases: 7. Best available estimate of future change. 8. Different what if assumptions regarding the rate of change of key indicators. For each option, interventions needed for each threshold are identified. The overall option consists of all the interventions needed to manage all the thresholds. 9. A preferred option is identified for the best estimate of future change available at the time that the options are developed. This is achieved by appraisal of the options developed under 6a above. 10. The options are developed at estuarywide and Policy Management Unit (PMU) level. The process of linking them is as follows: a. Estuary-wide options are developed and a preferred option is selected. b. PMU options are then developed which include the relevant components of the estuary-wide options. c. There may be some feedback from the PMU options into the estuary-wide options which could lead to refinement of the estuary-wide options. This should not affect the overall estuary-wide approach. 11. At this stage there is: a. A preferred option for the best available estimate of future change. b. Alternative options for different assumptions of future change. 2008 5 HRPP 358

This information will be provided by the TE2100 Plan. Drivers and indicators of change Drivers are defined in this context as the factors that create the need for flood risk management and therefore the TE2100 Plan. The main drivers of the TE2100 Plan include the following: The existing (present day) flood risk. Much of the tidal Thames floodplain is protected from flooding by flood defences. As the floodplain is intensely developed, it is essential that the Plan includes management of the existing flood risk. Flood Risk Management Policy. This determines the direction in which flood risk in the floodplains will change (e.g. increase, reduce, stay the same). Climate change. Deterioration of the existing defence system. Probability of failure of the Thames Barrier and other barriers. Socio economic development on the floodplains. New infrastructure that directly affects flood management. Physical change to the estuary. Loss of habitat. Creating a better place. The Environment Agency s Corporate Strategy entitled Creating a Better Place seeks to achieve an improved environment, taking account of a wide range of issues including improving river environments and landscapes, enhancing biodiversity, and working with natural processes. Public behaviour. This includes public awareness of flood risk under conditions of an uncertain future. Measurable indicators for the above drivers include the following: Peak surge tide level Frequency of closure of the Thames Barrier Developed area or asset value of development Intertidal habitat area Condition Grade of the flood defences Extent of erosion/deposition Public awareness of flood risk and how to respond The options are based on assumptions about each of these indicators. For example, Defra guidance on climate change is assumed. Information on such indicators as frequency of closure of the Thames Barrier and area of intertidal habitat has been obtained from studies carried out as part of TE2100. Option development Interventions are developed for each of the key drivers. In some cases there is overlap between the key drivers and the indicators. For example, the amount of habitat loss depends on sea level rise and physical change in the estuary. Figure 2 shows portfolios of responses to manage the rise in peak surge tide level. A single event frequency is used in this illustration. Peak surge tide level is the main driver for the choice of tidal flood risk management interventions downriver of the Thames Barrier. An important threshold is the maximum annual number of Thames Barrier closures before the reliability of the Barrier is compromised. Once the maximum number of closures has been reached, the mitigation intervention is to raise the upriver defences. As the number of closures of the Thames Barrier is primarily driven by an increase in Mean Sea Level, this means that the raising of upriver defences is also driven by increases in Mean Sea Level. This is shown on Figure 3. Mean Sea Level 2008 6 HRPP 358

Time 2100 Threshold 1 Threshold 2 Threshold 3 Maximum sea level Raise defences Receptor Responses Over-rotate Barrier Flood Storage Improve Barrier New Barrier New Open Barrage Tide-excluding Barrage Flood Storage Improve Barrier Receptor Responses & Improve Defences Threshold 1: Limit of present system Threshold 2: Limit of Thames Barrier Threshold 3: Limit of Thames Barrier with over-rotation or flood storage Impact of maximum sea level on downriver defences Figure 2 Responses to manage increases in surge tide peak level Time New barrage or convert Thames Barrier to barrage Raise upriver defences 2100 No. of closures with no interventions Raise upriver defences Threshold 1 (70 closures per year) Threshold 2 Threshold 3 Annual number of closures of the Thames Barrier (depends on Mean Sea Level rise) Note: The portfolios of responses are designed to keep the annual number of closures below 70. Thus the actual number of closures follows the full lines. Impact of Mean Sea Level on upriver defences Figure 3 Responses to limit the increases in Thames Barrier closures 2008 7 HRPP 358

Main Assumptions Abbreviations: Policy Iteration B (P5 introduced in 2080) d/r Defences downriver of the Thames Barrier Defra climate change u/r Defences upriver of the Thames Barrier 70 Barrier closures per year TB Thames Barrier New infrastructure: London Gateway port Option Indicators Epoch 2000 2010 2020 2030 2040 2050 2060 2070 2080 2090 2100 2110 2120 2130 2140 2150 2160 2170 2180 Option 1 Extreme tidal WL Raise d/r defences Improve TB and raise downriver defences Thames flow Raise West London defences including demountables; receptor responses Barrier closures Raise u/r 0.5m Raise u/r 0.5m New barrage New port No navigation constraint downriver of new port Habitat area 1050ha managed realignment (total) Further habitat creation Figure 4 An option developed from several drivers Responses for different drivers can be added together to create a complete option. An example is shown on Figure 4. This shows the main assumptions made, and the portfolios of responses for a range of thresholds arising from different drivers and indicators. The complete option consists of all the responses shown, including raising downriver defences, improving the Thames Barrier, raising upriver defences, improvements in West London, habitat creation, and a future new barrage. Several alternative options have been developed, and selection of the preferred option(s) is carried out by appraisal. The option shown above involves improving the existing flood defence system. Implementation of the plan The Plan is based on assumptions about the way in which future drivers will change. The process of implementation is as follows: 1. The key indicators are monitored. 2. If the actual values of the indicators do not correspond with the assumed values, the preferred option will be affected. This can affect the timing and choice of interventions 3. The timing of a decision to implement an intervention must be made based on: a. The rate of change of the indicator (which is unlikely to be linear). b. The threshold value when an intervention is required. c. An estimate of how the indicator will continue to change, in order to estimate the date when it reaches the threshold value. d. The lead time. This process is illustrated in Figure 5. 4. The choice of intervention will be guided by the options developed in the TE2100 Plan. It is based on the preferred option but may change to an alternative if the rates of change are significantly different from those assumed in the development of the Plan. 5. Thus the timing and possibly the choice of interventions will be guided by the rates of change of the indicators which represent the key drivers of flood risk. 6. The monitoring should be regularly reviewed, and the Plan updated if and when significant deviations occur between actual change and the assumptions made in the Plan. The above procedure is simplified by the fact that the Thames Estuary is a constrained system where most of the floodplain is already developed. Hence the number of choices available is limited. The monitoring results are then used to calculate new decision points using the process shown in Figure 5. 2008 8 HRPP 358

Figure 7 shows an example of the possible impacts of actual future change on the option shown above. In this example the decision points come forward in time as a result of an increase in peak surge tide level and an increase in Mean Sea Level. Other indicators are assumed to be the same as in the Plan. Figure 6 shows the option developed in Figure 4, but with the decision points added. Indicator value (e.g. sea level rise) Threshold value of indicator when intervention is needed New Decision Point Higher rate of change Decision Point in Plan New Decision Point Lower rate of change Lead time for planning and construction Predicted values of indicator based on rate of change (examples of faster and slower rates given) Recorded values of indicator Assumed values of indicator in Plan Date of review Change in date of Decision Point Time Figure 5 Timing of decisions Main Assumptions Abbreviations: Legend Policy Iteration B (P5 introduced in 2080) d/r Defences downriver of the Thames Barrier Defra climate change u/r Defences upriver of the Thames Barrier Decision point and lead time 70 Barrier closures per year TB Thames Barrier New infrastructure: London Gateway port Option Indicators Epoch 2000 2010 2020 2030 2040 2050 2060 2070 2080 2090 2100 2110 2120 2130 2140 2150 2160 2170 2180 Option 1 Extreme tidal WL Raise d/r defences Improve TB and raise downriver defences Thames flow Raise West London defences including demountables; receptor responses Barrier closures Raise u/r 0.5m Raise u/r 0.5m New barrage New port No navigation constraint downriver of new port Habitat area 1050ha managed realignment (total) Further habitat creation Figure 6 Option with decision points 2008 9 HRPP 358

Main Assumptions Abbreviations: Legend Policy Iteration B (P5 introduced in 2080) d/r Defences downriver of the Thames Barrier Defra climate change u/r Defences upriver of the Thames Barrier Decision point and lead time 70 Barrier closures per year TB Thames Barrier New infrastructure: London Gateway port Option Indicators Epoch 2000 2010 2020 2030 2040 2050 2060 2070 2080 2090 2100 2110 2120 2130 2140 2150 2160 2170 2180 Option 1 Extreme tidal WL Raise d/r defences Improve TB and raise downriver defences Thames flow Raise West London defences including demountables; receptor responses Barrier closures Raise u/r 0.5m Raise u/r 0.5m New barrage New port No navigation constraint downriver of new port Habitat area 1050ha managed realignment (total) Further habitat creation Example update of the option Epoch Option Indicator 1 2000 2010 2020 2030 2040 2050 2060 2070 2080 2090 2100 2110 2120 2130 2140 2150 2160 2170 2180 Option 1 Extreme tidal WL Raise d/r Improve TB and raise d/r defences 2 Thames flow Raise West London defences including demountables; receptor responses Barrier closures Raise u/r Raise u/r 0.5m New barrage (or convert Thames Barrier) New port No navigation constraint downriver Habitat area 1050ha MR Further habitat creation 3 Figure 7 Example update of an estuary-wide option The main impacts of changes following the update of the Plan in this example are as follows: The decision to raise downriver defences comes forward from 2030 to 2015 (Arrow 1). The decision to improve the Thames Barrier comes forward from 2070 to 2050, following the raising of downriver defences. The decision to raise upriver defences comes forward from 2070 to 2055 (Arrow 2). The decision to construct a barrage comes forward from 2120 to 2090 (Arrow 3). Decisions regarding managed realignments come forward. The West London interventions have not been changed. The next step is to consider whether the preferred option is still the best. In this illustrative example, an option based on improving the existing defence system is shown. Alternative options investigated in the Plan include: Tidal flood storage. Tidal flood storage plus over-rotate Thames Barrier, and associated defence raising. Convert Thames Barrier to an open barrage (including locks), and associated defence raising. Raise upriver defences as the sea level rises, to avoid increasing the number of Barrier closures. New Barrier and associated defences, with or without the Thames Barrier. New Barrage and associated defences. Greater use of secondary defences (in combination with an estuary-wide defence system). Greater use of resilient development (in combination with an estuary-wide defence system). Greater investment in contingency and emergency planning (in combination with an estuary-wide defence system). Greater emphasis on floodplain management and land use planning to manage flood risk (in combination with an estuary-wide defence system). The preferred option and the alternatives are reviewed and. if necessary, re-appraised, in order to decide whether the existing preferred option is still the best choice, or an alternative should be adopted. 2008 10 HRPP 358

If an alternative is adopted, some of the works in the preferred option will no longer be required. For this reason, any design and construction work should take account of the possibility of future change. Monitoring Monitoring of the indicators is required in order to assist with decision making at estuary-wide and PMU level. The indicators to be monitored include: Mean Sea Level Surge tide peak level (based on updating predictions of extremes) Peak river flood flows (based on updating predictions of extremes) Condition of assets Probability of failure of the Thames Barrier Accuracy of flood forecasting Floodplain development Physical condition of the estuary Intertidal area Public attitudes Some of these indicators are monitored already. In addition, existing close links should be maintained with those responsible for assessing and predicting future change, particularly climate change and socio economic change. This is because changes may not show in monitoring results until it is too late to make an appropriate response. The general approach to adaptation The approach to flood risk management presented in the TE2100 Plan includes a method of developing options together with a regular updating process in which options and decisions are reviewed taking account of changing circumstances. Interventions will be introduced as the need arises, taking account of the lead time needed for planning, design and construction. These include both flood defences and floodplain management. In some cases it may be recommended that pre-design work is commenced early to reduce lead times and the vulnerability of the Plan to rapid change. The flood defences involve engineering construction works to provide continuous flood defence systems for the estuary and tributaries. They require land for the works, including land for future improvement and adaptation. Floodplain management includes non-structural responses and some structural works, such as safe havens. A preferred option will be identified by the appraisal process. This will set the direction for flood risk management on the estuary, but will be reviewed as change occurs. If future changes are within the envelope that can be accommodated by the preferred option, it is likely that the choice of option will be unchanged. There may however be changes in the timings of future interventions, which depend on the rate of change of the drivers of flood risk management. If future changes lie outside the envelope of change that can be accommodated by the preferred option, an alternative option will be selected. This could lead to significant changes in the interventions. The evolutionary approach of responding to change is intended to minimise the risk of implementing responses that become redundant long before they reach the end of their design lives. Adaptability of individual responses As part of the process of adaptation, it is necessary to consider how individual responses can be adapted to future change. Some examples of how responses could adapt to change are as follows: Tidal flood storage that is no longer required because of a new downriver intervention (e.g. a barrage) could be adapted to provide regulated tidal exchange, thus creating intertidal habitats. 2008 11 HRPP 358

A new defence for which the future raising requirement is not known could have foundations designed to permit future raising, or an alternative alignment identified for a future defence. Secondary defence designs should include landscaping so that they are integrated with the environment and do not form barriers between communities. This should also provide the space needed for future adaptation. Barriers should be designed for conversion to a barrage when their limits of operation are reached. Pre-event measures and flood warning should be flexible to allow for future change. This includes updating of information, and briefings to advise partners of change. There is a need to ensure that flood risk management and land use planning are integrated so that changes in land use planning does not conflict with the requirements of flood risk management. This may require a more formal approach to land use planning on the Thames floodplains. Conclusions 1. Long-term planning for future flood risk management should take account of possible future change, including changes in the climate and socio economic conditions. 2. As future change is uncertain, a flexible approach is needed. 3. An approach has been developed for the Thames Estuary TE2100 Plan which involves monitoring of key indicators of change and identifying when key decisions must be made based on the lead times needed to plan and implement interventions. 4. In addition to monitoring, close links should be maintained with those responsible for assessing and predicting future change, particularly climate change and socio economic change. This is because changes may not show in monitoring results until it is too late to make an appropriate response. References OST 2004 Foresight - Future flooding, Scientific summary: Volume II Managing future risks, Office of Science and Technology, April 2004 Ramsbottom & Lavery 2007 The Thames Estuary: The Environment Agency s Flood Management Planning to 2100, Ramsbottom D M, Lavery S, Paper presented at the 42 nd Conference of River and Coastal Engineers, York, 2007 Willows & Connel 2003 Climate adaptation: Risk, uncertainty and decision-making. UKCIP Technical Report. May 2003 Church & White 2006. A 20th Century acceleration in global sea level rise. Church, J. A., & White, N.J., Geophysical Research Letters, 33 L01602, 10.1029/2005GL024826. 2008 12 HRPP 358

Fluid thinking smart solutions g y, pp hydraulics, and in the management of water and the water environment. Created as the Hydraulics Research Station of the UK Government in 1947, the Company became a private entity in 1982, and has since operated as a independent, non profit distributing firm committed to building knowledge and solving problems, expertly and appropriately. Today, HR Wallingford has a 50 year track record of achievement in applied research and consultancy, and a unique mix of know-how, assets and facilities, including state of the art physical modelling laboratories, a full range of computational modelling tools, and above all, expert staff with world-renowned skills and experience. The Company has a pedigree of excellence and a tradition of innovation, which it sustains by re-investing profits from operations into programmes of strategic research and development designed to keep it and its clients and partners at the leading edge. Headquartered in the UK, HR Wallingford reaches clients and partners globally through a network of offices, agents and alliances around the world. HR Wallingford Ltd Howbery Park Wallingford Oxfordshire OX10 8BA UK tel +44 (0)1491 835381 fax +44 (0)1491 832233 email info@hrwallingford.co.uk www.hrwallingford.co.uk