RISK M A N A G E M E N T P L A N

Similar documents
CRISC. Isaca CRISC Certified in Risk and Information Systems Control Version: 1.0

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version:

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

Project Risk Management

Risk Management FUN! Humor Me

Actualtests.PRINCE2Foundation.120questions

Prince2 Foundation.exam.160q

Certified in Risk and Information Systems Control

Managing Project Risk DHY

PRINCE2-PRINCE2-Foundation.150q

Project Management. Joycelyn M. Ray HCC Insurance Holdings SCCE- Chicago 9/08

Braindumps.PRINCE2-Foundation.150.QA

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

POWER OF CHOICE IMPLEMENTATION PROGRAM INDUSTRY PLAN RISK & ISSUE MANAGEMENT

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales

2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial.

Plan Advice Manager Dashboard

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Effective Risk Management, Measurement, Monitoring & Control

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

PRINCE2 Sample Papers

Review Criteria. Robotics Program. Reviewer SCORE SUMMARY. Extent of Need 25 Goals Objectives and Milestones

Fundamentals of Project Risk Management

Procedure for Address Business Risk and Opportunities

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework

Introduction to the Fund-Mapping Tool

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Kidsafe NSW Risk Management Plan. August 2014

Risk Management Made Easy. I. S. Parente 1

Risk Assessment Mitigation Phase Risk Mitigation Plan Lessons Learned (RAMP B) November 30, 2016

How to Avoid the Common Problems When Using Risk Management

Risk Management Plan Project Name: Version 1.0 Date: dd/mm/yyyy

Best Practices in Project Risk Management. Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc.

Risk Management Made Easy 1, 2

GOV : Enterprise Risk Management Policy

NERC 2013 Business Plan and Budget Overview. May 3, 2012

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

Classify each risk as a Threat or Opportunity. Most risks will be classified as Threats.

Proposed Criteria for Determining Scope of Section 215 Activities Request for Comments on Revised Draft

Project Risk Management

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

Project Closure TODAY S LESSON

Risk Management Guideline July, 2017

12 GeV CEBAF Upgrade. Risk Management Plan

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Project Management for Graduate Students. The Office Move Case Study. January 2018

Best Practices in ENTERPRISE RISK MANAGEMENT. [ Managing Risks Holistically ]

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty?

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management

Project Theft Management,

Q1 The committee set attainable initiatives.

FUNDING REQUEST APPLICATION FORM

Information Technology Project Management, Sixth Edition

Office of Audit and Evaluation. Audit of Major Capital Project Management

Version 2.0- Project. Q: What is the current status of your project? A: Completed

An Introductory Presentation for ECU Staff

Mn/DOT Scoping Process Narrative

RISK MANAGEMENT PROFESSIONAL. 1 Powered by POeT Solvers Limited

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

ISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management

PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR

RISK MANAGEMENT MADE EASY. Susan Parente Project Management Symposium.

Procedures for Management of Risk

Running Head: RISK MANAGEMENT PLAN 1

THE METHODOLOGY OF PROJECT MANAGEMENT OF SOFTWARE DEVELOPMENT AT THE NATIONAL BANK OF SERBIA

PRINCE2 Sample Papers

Prioritization Matrix

Indicate whether the statement is true or false.

Introduction to Risk for Project Controls

PMI - Dallas Chapter. Sample Questions. March 22, 2002

RISK MANAGEMENT STANDARDS FOR P5M

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management

Risk Management Guidelines

Academic Affairs Department of Environmental Science and Management Online Minor in Sustainability

Risk Video #1. Video 1 Recap

Risk Assessment of the Niagara Tunnel Project

M_o_R (2011) Foundation EN exam prep questions

FUNDING REQUEST APPLICATION FORM

EAN.UCC Project Management Framework Handbook. Issue Version 3.0

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996

What is Risk Management? Phil Barnes Assistant Director Office of Policy Analysis, Research, & Innovation (PARI)

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

National IT Project Management Methodology. IT Project Steering Committee Support Guide

Real-World Project Management. Chapter 15

Version: th November 2010 RISK MANAGEMENT POLICY

Procedure for Developing and Reviewing University College of Osteopathy Policies / Procedures / Regulations

APPENDIX A: 2018 Revisions Log

[Project Title] Project Scope Statement

CAPTIVE BEST PRACTICE GUIDELINES

COMPLIANCE PROJECT PLAN. (a.k.a. Project Charter)

ก ก Tools and Techniques for Enterprise Risk Management (ERM)

ENTERPRISE RISK MANAGEMENT (ERM) GOVERNANCE POLICY PEDERNALES ELECTRIC COOPERATIVE, INC.

COPYRIGHTED MATERIAL. Index

Senior Director, Fire Life Safety & Risk Management

SOLICITATION/ADVERTISEMENT

TONGA NATIONAL QUALIFICATIONS AND ACCREDITATION BOARD

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE TOR - CONSULTANCY IC/2012/026. Date: 16 April 2012

Transcription:

CONTENTS LEARNING OUTCOMES... 2 INTRODUCTION... 3 RISK DEFINITION OVERVIEW... 3 RISK MANAGEMENT ROLES AND RESPONSIBILITIES... 3 RISK MANAGEMENT APPROACH... 4 RISK IDENTIFICATION... 4 RISK QUALIFICATION AND IDENTIFICATION... 4 RISK MITIGATION AND AVOIDANCE... 5 RISK MONITORING... 6 RISK REGISTER... 6

LEARNING OUTCOMES Training Opportunities Overview of project risk management Overview of roles and responsibilities Overview of DSA project risk assessment and identification Definition of mitigating, avoidance, and monitoring Discussion on how identified risks are qualified and monitored Overview of where and when risks are recorded throughout the project life cycles Knowledge Goals and Takeaways Understand project risk in a variety of project samples Comprehend who is involved in identifying and managing risk Know the difference between qualification, mitigation, and avoidance Know where risks are recorded and stored Page 2

INTRODUCTION The purpose of the Risk Management Plan is to establish the risk management framework for projects undertaken by the Department of Information Technology in the Division of Student Affairs (DSA IT). This document defines the procedures involved in identifying risks and the strategies to mitigate or avoid those risks. The tracking documents & templates used to manage finances on projects are provided by the DSA IT PMO. RISK DEFINITION OVERVIEW The DSA Project Management Office (DSA IT PMO) has established predefined risk level definitions for overall risk scores based on the Initial Risk and Complexity Assessment: Low Risk Project: Risk Score = 100 to 150 Medium Risk Project: Risk Score = 151 to 199 High Risk Project: Risk Score = 200 + Projects with a medium or high risk score are subject to project reclassification (activity, small large). The following project elements are managed on a continual basis in order to ensure proper iterative risk reporting. Project Schedule Project Cost Estimate Team/Resource Allocation RISK MANAGEMENT ROLES AND RESPONSIBILITIES The Project Manager is responsible for coordinating, managing, recording, and reporting risk assessment activities on the project. The project team, key stakeholders, Page 3

and project sponsor participate in risk assessment activities throughout the duration of the project. The project manager is responsible for distributing current risk information as defined in the Communications Management Plan. RISK MANAGEMENT APPROACH The Project Manager uses two tools to record project risks. 1. Initial Risk and Complexity Assessment (Stored in PowerSteering) 2. Project Risk Register (Stored in PowerSteering) Throughout the project life cycle all project managers and project teams for DSA IT use a process by which the project team identifies, scores, and ranks various risks. Risks are recorded and ranked in the Project Risk Register for both small and large projects. The most likely and highest impact risks are added to the project schedule to ensure that the assigned risk owners take the necessary steps to implement mitigation response at the appropriate time during the schedule. Risk owners will provide status updates on their assigned risks during project team meetings. Upon completion of the project, during the closing process, the project manager analyzes each risk as well as the risk management process. Based on this analysis, the project manager identifies any improvements that can be made to the risk management process for future projects. These improvements are captured as part of the project Lessons Learned document. RISK IDENTIFICATION Methods used for identifying risks are: 1. Review of historical information from similar projects 2. Dedicating time in project meetings to assess and identify risks. RISK QUALIFICATION AND IDENTIFICATION Page 4

Once risks are identified the probability and impact of each one is determined in order to allow the project manager to prioritize risk avoidance and mitigation strategies. Risks are listed and prioritized in the Project Risk Register. RISK MITIGATION AND AVOIDANCE Once risks have been qualified, the team determines how to address those risks which have the greatest potential, probability, and impact on the project. In addition to defining the severity, a risk strategy is determined for both preventative and corrective actions for each risk. This strategy includes reviewing the severity of the risk impact, the cost-effectiveness of possible actions or contingency plans, the project timeline, and the practicality of the potential response. Response strategies for risks that have a negative impact on the project include: Accepting the risk, with no investment of effort or cost. Transferring the risk to or sharing the risk with a third party who is better able to handle the risk. Avoiding the risk by funding or staffing efforts to reduce the probability the risk will become a threat to project success. Establishing contingency plans for significant risks that cannot be mitigated or otherwise resolved. These plans are executed only under certain predefined conditions and may require additional work that must be budgeted and planned. Not all project risks are negative. Response strategies for risks that have a positive impact on the project include: Exploiting the risk to make sure the condition or event that is favorable to the project happens. Sharing the risk with a third party. Enhancing the risk to increase the probability of occurrence and/or positive impact. Accepting the risk by doing nothing. Page 5

Establishing contingency plans to be executed under certain predefined conditions. All risk response strategies are included in the risk register. The project team is responsible for assigning one or more options to the risk. (Avoid, transfer, mitigate, and/or accept for negative risks; exploit, share, enhance, or accept for positive risks.) RISK MONITORING Risks on all projects are actively monitored. Highest ranking risks are added to project status reports and assigned risk owner. Triggers and aggravating conditions are documented in the Risk Register. RISK REGISTER Every small and large project must maintain a Risk Register in order to track risks and associated mitigation strategies. The Risk Register for DSA IT project is a log of all identified risks, their probability and impact to the project, the category they belong to, mitigation strategy, and when the risk will occur. The project Risk Register is a required project document. The Project Risk Register for all projects is located in the Risk module within PowerSteering. Page 6