Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7

Similar documents
Haeryip Sihombing 1. Risk. Risk Management

Risk Video #1. Video 1 Recap

Project Management. Estimating Project Times and Costs. Clifford F. Gray Eric W. Larson Third Edition. Chapter 5

Project Risk Management

Project planning and creating a WBS

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Cost Slope Analysis 1

Chapter-8 Risk Management

Reducing Project Duration

Appendix A Decision Support Analysis

Fundamentals of Project Risk Management

Scheduling Resources and Costs

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

PROJECT MANAGEMENT: PERT AMAT 167

Poor Man s Approach to Monte Carlo

Managing Project Risk DHY

Estimating Project Times and Costs

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

COPYRIGHTED MATERIAL. Index

MS Project 2007 Page 1 of 18

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

WHY ARE PROJECTS ALWAYS LATE?

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty?

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

INTRODUCTION PROJECT MANAGEMENT

Cumulative trends Problems and issues since last report

Project Management Chapter 13

Real Options and Risk Analysis in Capital Budgeting

Running Head: RISK MANAGEMENT PLAN 1

CHAPTER 5 STOCHASTIC SCHEDULING

Project Management. Session 5 Budgets and Estimation Andre Samuel

u w 1.5 < 0 These two results imply that the utility function is concave.

Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001

Formulas to Know for EXAM

Achieve PMP Exam Success Five-Day Course Syllabus

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

Five-Day Schedule and Course Content

Contingency Reserve and Uncertainty

RISK MANAGEMENT PROFESSIONAL. 1 Powered by POeT Solvers Limited

UNIT-II Project Organization and Scheduling Project Element

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

PROJECT COST MANAGEMENT

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

CISC 322 Software Architecture

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Information Technology Project Management, Sixth Edition

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

Textbook: pp Chapter 11: Project Management

1 A Brief History of. Chapter. Risk and Return. Dollar Returns. PercentReturn. Learning Objectives. A Brief History of Risk and Return

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

PERMUTATION AND COMBINATIONS APPROACH TO PROGRAM EVALUATION AND REVIEW TECHNIQUE

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

1 of 14 4/27/2009 7:45 AM

PROJECT SCENARIOS, BUDGETING & CONTINGENCY PLANNING

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1

The Not-So-Geeky World of Statistics

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

M_o_R (2011) Foundation EN exam prep questions

PROJECT COST MANAGEMENT

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

Download slides on SEO Südwest

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

L U N D S U N I V E R S I T E T. Projektledning och Projektmetodik

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION

Appendices to NCHRP Research Report 903: Geotechnical Asset Management for Transportation Agencies, Volume 2: Implementation Manual

Project Risk Management

COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING

Project Theft Management,

How to Avoid the Common Problems When Using Risk Management

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Principles of Corporate Finance

Project Management Techniques (PMT)

CHAPTER 5. Introduction to Risk, Return, and the Historical Record INVESTMENTS BODIE, KANE, MARCUS. McGraw-Hill/Irwin

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Unit 5 Slide Lectures of 04/05/06 April 2017

*Efficient markets assumed

RISKS. Diane Van Hoy and Jacob Kloos

SAMPLE. Answer all 60 multiple choice questions sample paper contains 30 questions only Use the proforma answer sheet provided.

Exam Questions PMI-SP

CHAPTER 9: PROJECT MANAGEMENT

Chapter 11. Portfolios. Copyright 2010 by The McGraw-Hill Companies, Inc. All rights reserved.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

Quantitative Risk Analysis with Microsoft Project

Making sense of Schedule Risk Analysis

A Comparative Assessment of the PERT vs Monte Carlo simulation for. Schedule Risk Assessment

Programmatic Risk Management in Space Projects

Real-World Project Management. Chapter 15

Project Management. A Practitioner s Guide. Steven M. Bragg

Transcription:

Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Managing Risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by Charlie Cook

Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 2

Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a project s success. What can go wrong (risk event). How to minimize the risk event s impact (consequences). What can be done before an event occurs (anticipation). What to do when an event occurs (contingency plans). Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 3

The Risk Event Graph FIGURE 7.1 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 4

Risk Management s Benefits A proactive rather than reactive approach. Reduces surprises and negative consequences. Prepares the project manager to take advantage of appropriate risks. Provides better control over the future. Improves chances of reaching project performance objectives within budget and on time. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 5

The Risk Management Process FIGURE 7.2 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 6

Managing Risk Step 1: Risk Identification Generate a list of possible risks through brainstorming, problem identification and risk profiling. Macro risks first, then specific events Step 2: Risk assessment Scenario analysis Risk assessment matrix Failure Mode and Effects Analysis (FMEA) Probability analysis Decision trees, NPV, and PERT Semiquantitative scenario analysis Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 7

Partial Risk Profile for Product Development Project FIGURE 7.3 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 8

Risk Assessment Form FIGURE 7.4 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 9

Risk Severity Matrix FIGURE 7.5 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 10

Risk Schedules FIGURE 7.6 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 11

Managing Risk (cont d) Step 3: Risk Response Development Mitigating Risk Reducing the likelihood an adverse event will occur. Reducing impact of adverse event. Transferring Risk Paying a premium to pass the risk to another party. Avoiding Risk Changing the project plan to eliminate the risk or condition. Sharing Risk Allocating risk to different parties Retaining Risk Making a conscious decision to accept the risk. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 12

Contingency Plan Contingency Planning An alternative plan that will be used if a possible foreseen risk event actually occurs. A plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event. Risks of Not Having a Contingency Plan Having no plan may slow managerial response. Decisions made under pressure can be potentially dangerous and costly. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 13

Risk Response Matrix FIGURE 7.7 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 14

Risk and Contingency Planning Technical Risks Backup strategies if chosen technology fails. Assessing whether technical uncertainties can be resolved. Schedule Risks Use of slack increases the risk of a late project finish. Imposed duration dates (absolute project finish date) Compression of project schedules due to a shortened project duration date. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 15

Risk and Contingency Planning (cont d) Costs Risks Time/cost dependency links: costs increase when problems take longer to solve than expected. Deciding to use the schedule to solve cash flow problems should be avoided. Price protection risks (a rise in input costs) increase if the duration of a project is increased. Funding Risks Changes in the supply of funds for the project can dramatically affect the likelihood of implementation or successful completion of a project. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 16

Contingency Funding and Time Buffers Contingency Funds Funds to cover project risks identified and unknown. Size of funds reflects overall risk of a project Budget reserves Are linked to the identified risks of specific work packages. Management reserves Are large funds to be used to cover major unforeseen risks (e.g., change in project scope) of the total project. Time Buffers Amounts of time used to compensate for unplanned delays in the project schedule. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 17

Contingency Fund Estimate (000s) TABLE 7.1 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 18

Managing Risk (cont d) Step 4: Risk Response Control Risk control Execution of the risk response strategy Monitoring of triggering events Initiating contingency plans Watching for new risks Establishing a Change Management System Monitoring, tracking, and reporting risk Fostering an open organization environment Repeating risk identification/assessment exercises Assigning and documenting responsibility for managing risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 19

Change Management Control Sources of Change Project scope changes Implementation of contingency plans Improvement changes Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 20

Change Management Control The Change Control Process Identify proposed changes. List expected effects of proposed changes on schedule and budget. Review, evaluate, and approve or disapprove of changes formally. Negotiate and resolve conflicts of change, condition, and cost. Communicate changes to parties affected. Assign responsibility for implementing change. Adjust master schedule and budget. Track all changes that are to be implemented Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 21

The Change Control Process FIGURE 7.8 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 22

Benefits of a Change Control System 1. Inconsequential changes are discouraged by the formal process. 2. Costs of changes are maintained in a log. 3. Integrity of the WBS and performance measures is maintained. 4. Allocation and use of budget and management reserve funds are tracked. 5. Responsibility for implementation is clarified. 6. Effect of changes is visible to all parties involved. 7. Implementation of change is monitored. 8. Scope changes will be quickly reflected in baseline and performance measures. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 23

Change Request Form FIGURE 7.9 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 24

Change Request Log FIGURE 7.10 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 25

Key Terms Avoiding risk Budget reserve Change management system Contingency plan Management reserve Mitigating risk Risk Risk profile Risk severity matrix Scenario analysis Sharing risk Time Buffer Transferring risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 26

Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Appendix PERT and PERT Simulation Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by Charlie Cook

PERT PROGRAM EVALUATION REVIEW TECHNIQUE Assumes each activity duration has a range that statistically follows a beta distribution. PERT uses three time estimates for each activity: optimistic, pessimistic, and a weighted average to represent activity durations. Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations. Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 28

Activity and Project Frequency Distributions FIGURE A7.1 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 29

Activity Time Calculations The weighted average activity time is computed by the following formula: (7.1) Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 30

Activity Time Calculations (cont d) The variability in the activity time estimates is approximated by the following equations: The standard deviation for the activity: (7.2) The standard deviation for the project: Note the standard deviation of the activity is squared in this equation; this is also called variance. This sum includes only activities on the critical path(s) or path being reviewed. (7.3) Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 31

Activity Times and Variances TABLE A7.1 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 32

Probability of Completing the Project The equation below is used to compute the Z value found in statistical tables (Z = number of standard deviations from the mean), which, in turn, tells the probability of completing the project in the time specified. (7.4) Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 33

Hypothetical Network FIGURE A7.2 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 34

Hypothetical Network (cont d) FIGURE A7.2 (cont d) Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 35

Possible Project Duration FIGURE A7.3 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 36

Z Values TABLE A7.3 Copyright 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 7 37