QUALITY CONTROL Prepared: D. Vree Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

Similar documents
Q&A OVERVIEW. Topic Question Answer Date Z (K-I).pdf. 18 enter/access the 66kV SWG, one accompaniment from TenneT is

Offshore grid NL. Hollandse Kust (noord) & Hollandse Kust (west Alpha) General project introduction. 10 september 2018

Offshore grid development

CONNECTION OF OFFSHORE WIND ONSHORE -- Some Food for Thought to Aid the Discussion at the Post-Conference Workshop

Offshore Grid Development in Germany

Information Session. HKZ offshore grid. Rob van der Hage. September

COMPARISION OF OFFSHORE REQUIREMENTS

Dutch offshore wind energy developments:

Independent Review of Aurora Network summary of findings. Michael Van Doornik, Manager Advisory (VIC) 31 October 2018


OFFSHORE WIND REFERENCES

Stage 01: Workgroup Report

P294 Addition of Offshore Transmission System and OTSUA to the definition of the Total System

Questions and Answers

Insuring Offshore Wind Farms. Fraser McLachlan

Unofficial Comment Form Emergency Operations EOP-004-4

Connection and Use of System Charge Methodology Statement ("Condition 25 Statement")

Submitted by Western Power

Expenditure Forecast Methodology

Risk & Contract Management

Questions and Answers

Project Assessment Conclusions Report

Offshore electricity transmission: a new model for delivering infrastructure

Questions and Answers The Ministerial Order for permitting offshore wind energy Hollandse Kust (zuid) Wind Farm Sites I and II

The development of offshore wind - The case of Denmark

Offshore Wind and Development Opportunities in the South West Robert Thornhill Offshore Development Site Manager

T-D Interconnections: Best Value Planning White Paper January 2016

Mobilising institutional investment in offshore wind

Nelson Electricity Ltd Asset Management Plan Update

Questions and Answers

Offshore Wind Cost Reduction Recent and future trends in the UK and Europe

Questions and Answers The Ministerial Order for permitting offshore wind energy Hollandse Kust (zuid) Wind Farm Sites I and II

CMP242 Charging arrangements for interlinked offshore transmission solutions connecting to a single onshore substation

Wellington Electricity CPP assessment of 2010/21 capex

Ireland s. Offshore Wind Resource. An Export Opportunity. Presentation to IWEA Conference Brian Britton Secretary NOW Ireland 22 nd March 2012

Life cycle planning & optimisation making use of a calculation and simulation model

Offshore Legal Framework

APPLICATION PROVISIONS

Impact of Wind Energy Support Schemes on the Development of an Offshore Grid in the North Sea

Cost Estimation for Regional Transmission Overlay Study (RTOS)

Investing in Belgian offshore wind: a comprehensive overview of associated risks. Offshore wind risk analysis provided for Zeewind 1 fund June 2014

Jemena Electricity Networks (Vic) Ltd

Stormy Weathers in the European Wind Power sector how to keep the pace?

Explanatory notes to one-page performance summary of electricity distributors

REISSUED JUNE 1, 1988

Wairakei Ring Investment Proposal. Project Reference: CTNI_TRAN-DEV-01. Attachment A GIT Results

5th Annual Renwable Energy Finance in Practice 21 October Support Tendering - François van Leeuw CEO of Parkwind

UK s Offshore Transmission Regime:

Regional Network Tariffs applicable commenting

ESKOM S CONNECTION CHARGES METHODOLOGY

MainPower New Zealand Limited. Asset Management Plan

Information Document FAC-008-AB-3 Facility Ratings ID # RS

First Offshore Windfarm Project in India (FOWPI) with EU-backing

AGREEMENT FOR CONNECTION TO EASTERN POWER NETWORKS PLC S DISTRIBUTION SYSTEM

Standard Development Timeline

Offshore transmission investments How to regulate these investments? Who should act?

A Scottish Hydro Electric Transmission plc project co-funded by the European Union under the European Energy Programme for Recovery (EEPR)

The Breakdown and Mitigation of Technical Losses on Distribution Power Systems

Unlocking grid flexibility:

AGCS: YOUR PARTNER IN A CHANGING ENERGY LANDSCAPE

SP Transmission successfully fast-tracked

Loss Mitigation in Developing Offshore Wind Farms. For: AOEC 2017, Bali - by Matthew Yau

MEMBER STATE COOPERATION ON RENEWABLE ENERGY. Member State meeting 5 November 2014, Brussels Case study: Offshore wind in the North Sea

Paul Doherty Managing Director, Gavin & Doherty Geosolutions. Investing in Offshore Renewables Can We Capitalise on the Big Opportunity?

Feed-in tariff determination Best practice and cross-country coordination

TRANSGRID PRICING METHODOLOGY 2015/ /18. Contents

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER

DS3 System Services Protocol Regulated Arrangements

Offshore Code of Practice (OCoP)

OPERATIONAL INVESTMENTS

No. 19. Offshore Wind Energy in Europe Fresh Wind for Insurers, Too? A Berkshire Hathaway Company. Topics No. 19

UK Power Networks. Overall Cost Benefit Analysis

Legal developments in offshore wind energy in the Netherlands; part 5

Interconnection and Protection Engineering Breaking News: Policy Update

Network Loss Factor Methodology

SP Energy Networks Business Plan

CA-NLH-59 Depreciation Methodology and Asset Service Lives Page 1 of 3

TNUoS Tariffs in 10 minutes March 2018

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems

The South African Grid Code. Transmission Tariff Code. Version 9.0

Western Power Distribution (East Midlands) plc Registered in England and Wales No

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Generating Unit Operating Requirements

Information Disclosure

Power Transmission - Transform to Win

Transpower Individual Price-Quality Path Determination 2015

83C Questions and Answers

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014

Gunnar Groebler Head of Business Area Wind. Vattenfall Capital Markets Day, Solna, 19 September 2016

PROVISION OF BULK MUNICIPAL INFRASTRUCTURE BY DEVELOPERS A MODEL THAT WORKS

ASSET RISK MANAGEMENT Asset Health Framework

Bonneville Power Administration

Questions and answers

EXCLUSIVE TALKS FOR THE. ACQUISITION OF QUADRAN 21 June 2017

Welcome. Stephanie McGregor Director, Offshore Transmission

UK Onshore Wind. Investment Fundamentals

Support regimes for offshore wind in Europe Florian Bauernfeind

Wind Mills of the Mind Delivering large scale offshore wind. Andy Kinsella CEO, Offshore September 3rd, 2012, Ballina

TRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017


SIMULTANEOUS TRIP OF SOUTH EAST No.1 AND No kv SVCs ON 31 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES

Transcription:

POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.6 Protection Filename ONL 15-080-T6_Protection_PP_v1 Version 1 - release for Expert Meeting of 15-16.04.2015 Pages 9 QUALITY CONTROL Prepared: D. Vree 29.03.2015 Reviewed: M. Müller 31.03.2015 Approved: F. Wester 02.04.2015 Release Public Table of Contents 1. BACKGROUND MATERIAL... 2 2. SCOPE AND CONSIDERATIONS... 2 General... 2 Technical... 3 Implementation... 5 Option 1: PPM owned protection system... 5 Option 2: TenneT owned protection system... 6 Cost, uncertainties and risk... 6 Affected topics... 6 3. POSITION TENNET... 7 4. IMPACT ON COST... 7 5. TOPIC CONSULTATION... 9

PAGE 2 of 9 1. Background material Background material used: N.A. 2. Scope and considerations The figure below shows a schematic cross-section of the connection of an offshore wind farm to the onshore electricity grid. Wind turbines are connected through medium voltage inter-array cables (in orange) to an offshore substation, from which electricity is transported to shore. TenneT will be responsible for the offshore grid, from the onshore substation up to and including, the offshore substation. TenneT intends to standardise the offshore substations for all five wind areas to be realised in the coming years in line with the Energy Agreement. Schematic of the offshore electrical grid. Source: TenneT General The Energy Agreement requires a 40% cost reduction for offshore wind to be realised over the period 2014-2024. Realisation of this cost reduction is expected to require a combination of measures 1, including - but not limited to standardisation of the offshore electrical infrastructure and larger capacity wind turbines within larger wind farms. TenneT contributes to this overall cost reduction target, through a strategic long term vision on the development of the offshore grid. Cost reduction is realised by standardisation of all 5 offshore platforms to be realised for the development of 3450 MW offshore wind, by serving concentrated large wind areas with a single platform and use of technology that is ready for future large capacity wind turbines. 1 http://tki-windopzee.nl/files/2015-01/20141124_tki_roadmap.2015-2020_ezu_f%20(1).pdf

PAGE 3 of 9 Technical The protection requirements and typical characteristics of onshore customers of TenneT, and a common protection scheme of a 350 MW offshore wind farm, are analysed as input for the string protection requirements. Also, implications of the new European network code RfG are taken into account. Finally, the protection requirements for PPM strings are introduced which are based on this analysis. Onshore TenneT protection requirements Protection requirements of the TenneT high voltage grid are defined in [PVE 02 000] 2. The following requirements are applicable to the protection of the outgoing 3 feeder of the TenneT switchgear for customers (grid connection voltage is 110kV or higher): Protection system will be specified, installed and maintained by customer; Additionally TenneT provides an impedance protection. In addition to the above requirements, generators connected to the high voltage grid (greater than or equal to 110kV) shall have fault ride through capabilities as depicted by a red line in figure 2 below which is defined by the system code (article 2.1.16). U [p.u.] Fault-ride-through 1,05 1,00 0,95 0,90 0,85 0,80 0,75 0,70 0,65 0,60 0,55 0,50 0,45 0,40 0,35 0,30 0,25 0,20 0,15 0,10 0,05 0,00-0,50-0,25 0,00 0,25 0,50 0,75 1,00 1,25 1,50 1,75 2,00 2,25 2,50 2,75 3,00 3,25 3,50 t [s] Systeemcode 2.1.16 RfG Figure 2. Fault ride through requirements for generators as defined by the system code (red line) and for shore PPMs as defined by the RfG4. 2 PVE 02 000 Secundair Standaard Programma van Eisen, Oktober 2014, Versie 2); 3 In this paper the term outgoing feeder refers to a feeder which is connected to one of the offshore PPM strings and incoming feeder to a feeder which is connected to one of the offshore platform step-up transformers. 4 The black line is based, on the implementation of TenneT of the draft RfG on the offshore CP.

PAGE 4 of 9 Requirements from the new RfG network code The PPM s connected to the TenneT offshore platform will be subjected to the applicable requirements set out in the RfG, which applies to, but is not limited to, the following subjects (overall list: not all mentioned topics are applicable to this paper): Fault-ride-through capability Electrical protection schemes and settings Priority ranking (not covered in this paper) Information exchange (not covered in this paper) The requirements with respect to the fault-ride-through capabilities are presented by the black line in Figure 2 above. Important to note here is that the RfG implementation is addressed to in a separate process. Electrical faults within the PPM should be cleared as fast as possible, but the RfG explicitly states that the protection scheme and settings for these faults shall be designed not to jeopardize fault-ride-through performance during electrical faults in the network especially with regards to under voltage protection. Typical offshore wind farm string protection scheme The following aspects are applicable to typical protection systems of offshore wind farms currently under construction or in operation: The protection system is designed to protect a long cable string with wind turbines feeding into this string through ring main units. The protection is based on a single relay with a maximum current / time protection (I> and I o > with definite time setting). Time setting is typically in the range of 0.2-0.4 s. The system is earthed through an earthing transformer connected to the MV bus-bar. Back-up protection is the maximum current / time protection in either the incoming feeder of the (single) MV bus-bar (I>) or the feeder of the earthing transformer (I o >), with current and time settings coordinated with the outgoing feeder protection relays. Additional protection by an under voltage relay with a measurement on the bus-bar is applied in the case the protection relay of the earthing transformer has been tripped and an earth fault (single phase to ground) occurs. Time setting for this protection is well above the fault ride through requirements (order of magnitude: a few seconds). The protection in the string is the protection relay in the outgoing feeder of the ring main unit inside the WTG, protecting the WTG transformer. On the low voltage side(s) of the WTG transformer a circuit breaker is used for protection of the WTG power electronics and WTG alternator. Short circuit contribution of a single WTG is limited by power electronics (full scale direct drive converter). With DFIG type WTG s, a higher short circuit contribution has to be taken into account, but fault current contribution will still be significantly lower than the fault current from the 220 kv side.

PAGE 5 of 9 Implementation The following general guidelines will be applicable to the protection system of the offshore PPM strings on a TenneT offshore platform: Voltage level of the strings at CP will be either 33 kv or 66 kv 5. Fault ride through capability for any fault in the grid (on 33/66kV switchgear, in other strings and in the step-up transformer and upstream grid) shall be according to curve as presented in Figure 2 (black line). Fault clearance time for any fault within the string shall be as low as reasonably possible but shall be maximum 0.25 s, to assure that other strings (and individual WTGs) will not trip due to operation below the fault ride through curve (as two PPM's will be connected to one offshore platform). The 33/66kV system will be impedance earthed through an earthing transformer. Protection system shall be aligned with this earthing method by providing earth fault current protection (I o>). Back-up protection systems of the string in upstream circuit breakers will be in a) the incoming feeder of the 33/66 kv switchgear (type to be defined) and b) the feeder of the earthing transformer (I o>) of the 33/66 kv switchgear. TenneT considered two options for the protection of offshore PPM strings connected to a TenneT offshore platform: Option 1: PPM owned protection system Option 2: TenneT owned protection system Option 1: PPM owned protection system In this scenario, the PPM is responsible for the protection of its strings and will design, install, operate and maintain the protection system on the offshore platform. TenneT will make the necessary space and other provisions (amount of available CT/VT, power supply, SCADA connection etc.) available on the offshore platform. This option will have an impact on the design and construction phase of the offshore platform. As each PPM will be actively involved with design of the protection system and installation of this system onto the offshore platform. It is expected that this will have no negative influence on the planning. This option will require access of the PPM to the offshore platform during construction and for planned as well as unplanned maintenance of the protection system. Specific details on access to the offshore platform will be covered in a separate position paper. The protection system shall be aligned with and approved by TenneT with regards to compliance to the RfG and coordination with upstream protection. 5 TenneT s position on voltage level is addressed in position paper ONL 15-058 T.1 Voltage level.

PAGE 6 of 9 Option 2: TenneT owned protection system In the second scenario considered, TenneT is responsible for the protection of the offshore PPM strings and will design, install, operate and maintain the protection system. This (standard) protection system will be based on a primary protection by two protection relays in the outgoing feeder bays which each have either a different measuring principle or a different manufacturer (refer to option 1, second requirement). The protection system and its settings will be aligned with the PPM. With this option, next to the primary equipment, the secondary equipment of TenneT will protect the offshore PPM strings which can have legal consequences. The system operator and PPMs should make arrangements and agreements on these consequences. Those will be addressed to in the 'Customer Connection Agreements'. Cost, uncertainties and risk TenneT identified the following expected impacts on cost and other affected topics, as well as uncertainties and risks as given in the Table 1 below, based on the information provided above. Impact on affected topics Option 1 (PPM owned) Option 2 (TenneT owned) Technical impact Each PPM will make its own design. One protection philosophy for all platforms. Impact on design and construction phase. Each PPM will need to contribute during the offshore platform design and construction phases. Limited contribution of PPM during design phase only (alignment of protection settings). Legal framework According to existing onshore practice. Consequences to be Consequences to be covered in ATO. covered in ATO. Access to platform by PPM Required during construction and for planned and unplanned maintenance. Not required. Cost implications CAPEX Comparable for both options as typical solutions are identical. Cost implications OPEX As each PPM needs to organise its own maintenance program, OPEX for option 1 are expected marginally higher than for option 2. Table 1 - Overview of impact on affected topics for option 1 and 2 Affected topics The choice of protection affects (or can be affected by) a number of subjects that will be discussed in later expert meetings, such as: ATO / REA, access to platform, and operation of bays.

PAGE 7 of 9 3. Position TenneT On the assumption that the additional legal consequences will be acceptable for both TenneT and PPMs, the above considerations lead TenneT to the following position: TenneT is inclined towards standardising the protection of the offshore PPM inter-array cable strings to the TenneT offshore transformer platform by implementing a standard protection system, owned, operated and maintained by TenneT for all five platforms to be realised by TenneT up to 2023. 4. Impact on cost In the table below a summary is presented of the impact - both quantitatively on cost and qualitatively of standardising the protection of the offshore PPM inter-array cable strings.

POSITION PAPER Cost impact: high level breakdown Quantitative LCoE Impact Uncertainty Comment Substation: Connection CAPEX 0.0% Medium Switchgear cost considered comparable for both PPM and TenneT owned option as typical solutions are identical (1). Substation: Connection OPEX 0.0% Each PPM needs to organise its own maintenance program, the additional cost for the OPEX for the PPM owned option are marginally Medium higher than for the TenneT owned option (1)(2). Society Borssele Alpha LCoE impact 0.0% Medium Summation of the LCoE impact from separate items above. Impact future years 0.0% Medium Impact is not expected to change for future years. References: TenneT internal (1), Ecofys internal (2) 6 6 Green represents a (insignificant) decrease in LCoE going from option 1 (PPM owned) to option 2 (TenneT owned).

POSITION PAPER 5. Topic consultation The expert meeting of 15-16.04.2015 gives TenneT the opportunity to get feedback from developers on their position regarding protection. The main goal of this meeting will be to assess whether TenneT s views as documented within this position paper, and background data above, are shared by the industry.