Coeur Files Technical Report for Kensington Mine

Similar documents
Coeur Reports Year-End 2016 Mineral Reserves and Resources

Coeur Announces Initial Reserve Estimate and Reserve-Based Mine Plan for Silvertip Mine

Coeur Reports Year-End 2014 Mineral Reserves and Resources

Coeur Reports Year-End 2015 Mineral Reserves and Resources

Coeur Reports Year-End 2018 Mineral Reserves and Resources

Coeur Reports Third Quarter 2018 Production and Sales Results

Coeur Reports 39% Increase in Wharf s Gold Reserves. Adds Three Years of Expected Mine Life

Coeur Provides Updated Palmarejo Mine Plan

Coeur Reports 89% Increase in Silver Reserves and 76% Increase in Gold Reserves at Palmarejo Post-Paramount Acquisition

NEWS RELEASE. Coeur Reports Second Quarter 2014 Results

Coeur Reports Third Quarter 2017 Results

Coeur Reports Second Quarter 2018 Results

Coeur Reports Third Quarter 2018 Results. Reaffirms Full-Year Companywide Production and Cost Guidance

J.P. Morgan High Yield and Leveraged Finance Conference

Coeur to Acquire the High-Grade Silvertip Mine in British Columbia

Coeur to Acquire Wharf Gold Mine from Goldcorp. January 13, 2015

Stock Symbol: AEM (NYSE and TSX) For further information: Investor Relations (416)

Deutsche Bank Leveraged Finance Conference

Morgan Stanley Leveraged Finance Conference

Allied Nevada Announces Improved Mine Plan and Economics for Hycroft Mill Expansion With 77% IRR and $2.7 Billion NPV

RNC MINERALS. Q Results Conference Call TSX:RNX. August 15, 2018

NEWS RELEASE GREAT PANTHER SILVER REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR THE CORICANCHA MINE

HBM. Creating Sustainable Value through High Quality Long Life Deposits

RNC MINERALS Results Conference Call TSX:RNX. April 3, 2018

Alio Gold Reports Second Quarter 2018 Results

NEWS RELEASE GREAT PANTHER SILVER REPORTS FOURTH QUARTER AND ANNUAL 2018 PRODUCTION RESULTS AND PROVIDES CORPORATE UPDATE

Silver and Gold (and Base Metals Too!)

Trevali Reports 2017 Annual Financial Results

Pretivm Reports Third Quarter 2018 Results

SECOND QUARTER 2018 RESULTS. August 10, 2018

Trevali reports Q financial results

Second Quarter 2013 Earnings Conference Call

Third Quarter 2014 Earnings Conference Call

Dalradian Resources Reports Positive Preliminary Economic Assessment for the Curraghinalt Gold Project in Northern Ireland

RNC MINERALS. Q Results Conference Call TSX:RNX. November 15, 2017

Detour Gold Reports Fourth Quarter and Full-Year 2014 Results and Year-end 2014 Mineral Reserve and Resource Estimates

BMO CAPITAL MARKETS 27 TH GLOBAL METALS AND MINING CONFERENCE

Turquoise Hill files 2016 Oyu Tolgoi Technical Report

SUITE WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: FAX: November 12, 2009

AGNICO-EAGLE MINES LIMITED. Corporate Update. May 2012

LEAGOLD FILES UPDATED TECHNICAL REPORT FOR LOS FILOS GOLD MINE, INCREASING RESERVES BY 59% TO 2.7 MILLION OUNCES GOLD

SANDSTORM GOLD ACQUIRES 2% NSR ROYALTY ON ENDEAVOUR S HOUNDÉ GOLD MINE FROM ACACIA MINING

CANADA S INTERMEDIATE GOLD PRODUCER

(PEA) for its project in. anticipated. which are. to produce. Highlights. ounces is now. The 3,500 tpd. After-tax NAV. Guatemala this year,

First Quarter 2012 Results

FNV. Forward-Looking Statements

For further information: Investor Relations (416)

2018 SECOND QUARTER RESULTS WEBCAST. July 26, 2018

SILVERCORP REPORTS Q1 RESULTS: NET INCOME UP 73%, CASH FLOWS FROM OPERATIONS UP 52% TO US$20.2 MILLION

CANADA S INTERMEDIATE GOLD PRODUCER

Exploration Projects September 30, 2014

Trevali Reports Record Preliminary Q and 2017 Annual Production, and Provides 2018 Production and Cost Guidance

News Release. B2Gold Corp. Announces Positive Results from the Preliminary Economic Assessment for the Gramalote Project in Colombia

A $100 per ounce decline in the gold price would reduce the reserves by approximately 3.3% or 310,000 ounces.

Detour Gold Reports Third Quarter 2018 Results

Corporate Update. June 2013

January 18, 2016 Capstone Extends Pinto Valley Mine Life to 2039 (all amounts in US dollars)

Q Earnings Review

ELGIN MINING PROVIDES STRONG FOURTH QUARTER CASH COSTS AND POSITIVE 2014 OUTLOOK

CANADA S INTERMEDIATE GOLD PRODUCER

PRESS RELEASE New Gold Reports Consolidated Reserve & Resource Statements

Hudbay Announces Updated Technical Report for Constancia and Provides Annual Reserve and Resource Update

Detour Gold Reports 2017 Fourth Quarter and Year-End Results

Gold Hawk Resources Inc.

INTERIM QUARTERLY HIGHLIGHTS

Q Conference Call August 15, 2012 HBM

ANNUAL GENERAL MEETING APRIL 28, 2017

SCOTIABANK MINING CONFERENCE

SANDSTORM GOLD ROYALTIES RELEASES HOD MADEN PFS AND INCREASES PRODUCTION GUIDANCE

CANADA S INTERMEDIATE GOLD PRODUCER

YEAR END 2015 CONFERENCE CALL

Prophecy Signs Toll Milling LOI to Produce Zinc-Silver and Lead- Silver Concentrates from Pulacayo Project, Bolivia

Great Panther Reports First Quarter 2019 Production Results

Q May 2, 2013 HBM

ROYAL GOLD ANNOUNCES ORE RESERVE STATUS AND CALENDAR YEAR 2004 PRODUCTION ESTIMATES

Trevali Reports Q Financial Results

Capstone Mining 2017 Production Results and 2018 Operating and Capital Guidance

Young-Davidson Achieves Record Underground Productivity of 4,900 tonnes per day in April

New Gold Announces 2017 Financial Results with 11% Increase in Cash Flow Per Share (All dollar figures are in US dollars unless otherwise indicated)

Spanish Mountain Gold Announces Results of New PEA for the First Zone

YEAR END 2016 CONFERENCE CALL. February 24, 2017

Kensington Mine. Juneau, Alaska. June 2014

Detour Gold Updates Life of Mine Plan for Detour Lake

MCEWEN MINING ANNOUNCES UPDATED RESERVE & RESOURCE ESTIMATE AT THE SAN JOSÉ MINE IN ARGENTINA

THACKER PASS LITHIUM DEPOSIT: GEOLOGY AND PROCESSING OF THE LARGEST LI DEPOSIT IN NORTH AMERICA PDAC 2019 TECHNOLOGY METALS TECHNICAL SESSION

OSISKO UPDATES CANADIAN MALARTIC MINE PLAN

Second Quarter 2016 Financial Results

Forward Looking Statement

San Bartolomé Update and Overview

NEWS RELEASE GREAT PANTHER SILVER REPORTS FOURTH QUARTER AND ANNUAL 2017 PRODUCTION RESULTS AND PROVIDES 2018 OUTLOOK

SILVERCORP REPORTS SIGNIFICANT GAIN IN MEASURED AND INDICATED MINERAL RESOURCES AT THE YING SILVER-LEAD-ZINC MINING DISTRICT, HENAN PROVINCE, CHINA

Detour Gold Achieves Production and Cost Guidance for 2017 and Provides 2018 Guidance

MAG Silver Reports Juanicipio Updated PEA Study Prepared by AMC

Allied Nevada Announces Hycroft Mill Expansion Feasibility Results Highlighted by Improved Projected Returns

Saramacca Reserve Declaration

Q Conference Call November 2, 2012 HBM

Hudbay Announces 2016 Production Guidance and Capital and Exploration Expenditure Forecasts

Marlin Gold Closes Acquisition of Commonwealth Silver and Gold and Provides Corporate Update

N E W S R E L E A S E

BC Natural Resources Forum

Transcription:

Coeur Files Technical Report for Kensington Mine Chicago, Illinois April 25, 2018 Coeur Mining, Inc. ( Coeur or the Company ) (NYSE: CDE) today filed a NI 43-101 Technical Report ( technical report ) for its Kensington gold mine in Alaska, which reflects a 25% increase in proven and probable reserves to 620,700 ounces and a 10% increase in average reserve grade to 0.21 ounces per ton ( oz/t ), or 7.2 grams per tonne ( g/t ), compared to year-end 2016 reserves. Contained in this reserve is an initial reserve estimate for the high-grade Jualin deposit of 74,100 contained ounces of gold based on 157,600 tons of ore at an average grade of 0.47 oz/t, or 16.1 g/t. Summary highlights from Kensington s technical report include: A 13% increase in expected average annual payable production to approximately 130,000 ounces of gold from 2019 through 2021 compared to payable production in 2017 17% increase in anticipated life-of-mine head grade of 0.21 oz/t compared to the 2017 average head grade of 0.18 oz/t Anticipated 8% reduction in average costs from $920 in 2017 to $855 per payable ounce Average annual pre-tax cash flows of over $30 million over the three-year period, up from $1.4 million of pre-tax cash flow in 2017 An extension of mine life from 2020 to 2022 based on current reserves Mining rates at the high-grade Jualin deposit expected to ramp up to 100 tons per day in 2019 and average over 180 tons per day in 2020 84% increase in expected life-of-mine pre-tax cash flows to $90 million compared to $49 million in Kensington s 2014 technical report Addition of 713,000 ounces of measured and indicated resources and 305,000 ounces of inferred resources, conveying potential for further mine life extensions The results of Kensington s technical report illustrate the significant impact a relatively small amount of high-grade mill feed can have on this mine s prospects, said Mitchell J. Krebs, Coeur s President and Chief Executive Officer. Once we complete dewatering efforts at Jualin, we plan to ramp up mining rates beginning in the fourth quarter. This initial reserve declaration at Jualin represents an important milestone, and we continue to work towards defining Kensington s greater potential. Our exploration team has identified numerous high-grade, historically-producing veins that are drill-ready, close to existing infrastructure, and we intend to explore their potential to serve as supplemental sources of high-margin production. Like Jualin and Raven, these targets have the potential to drive value at Kensington for many years to come. 1

The Kensington district once hosted several past producing mines and prospects, which are located on the figure below, illustrating a lengthy mineralization corridor. The Company intends to explore these historic vein structures over the next 18 months to determine their potential to provide high-grade mill feed, both supplementing feed from Raven and Jualin as well as succeeding them in the longer-term. Surface mapping and sampling of these historic veins have demonstrated encouraging results. Coeur s exploration team onsite will endeavor to drill test several of these targets for continuity at depth. Kensington: Mine Map with Near-Term Exploration Targets 2

2017 Year-End Proven and Probable Reserves Short tons Gold Grade (oz/t) Contained Gold (oz) PROVEN RESERVES Kensington 1,271,200 0.20 251,800 Raven 13,500 0.23 3,100 Total 1,284,700 0.20 254,900 PROBABLE RESERVES Kensington 1,499,600 0.19 286,700 Raven 19,200 0.26 5,000 Jualin 157,600 0.47 74,100 Total 1,676,300 0.22 365,800 PROVEN AND PROBABLE Total 2,961,000 0.21 620,700 2017 Year-End Measured and Indicated Resources Short tons Gold Grade (oz/t) Contained Gold (oz) MEASURED RESOURCES Kensington 1,480,300 0.25 374,100 Raven 66,000 0.32 20,900 Total 1,546,300 0.26 395,000 INDICATED RESOURCES Kensington 1,146,000 0.25 287,100 Raven 14,700 0.22 3,200 Jualin 36,800 0.74 27,200 Total 1,197,500 0.27 317,600 MEASURED AND INDICATED Total 2,743,800 0.26 712,600 2017 Year-End Inferred Resources Short tons Gold Grade (oz/t) Contained Gold (oz) INFERRED RESOURCES Kensington 1,244,800 0.22 272,400 Raven 134,400 0.20 27,500 Jualin 8,600 0.58 5,000 INFERRED RESOURCES Total 1,387,800 0.22 304,800 Notes to above mineral reserves and resources (effective December 31, 2017): 1. Assumed metal price for estimated Mineral Reserves was $1,250 per ounce of gold. 2. Assumed metal price for estimated Mineral Resources was $1,400 per ounce of gold. 3. Mineral Reserves are estimated using a cut-off grade between 0.036 and 0.146 oz./ton gold depending on deposit. Mineral Resources are estimated using a cut-off grade of 0.129 oz./ton gold. 4. Mineral Resources are in addition to Mineral Reserves and do not have demonstrated economic viability. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be considered for estimation of Mineral Reserves, and there is no certainty that the Inferred Mineral Resources will be realized. 5. Rounding of tons and ounces, as required by reporting guidelines, may result in apparent differences between tons, grade, and contained metal content. 6. For details on the estimation of mineral resources and reserves, including the key assumptions, parameters and methods used to estimate the Mineral Resources and Mineral Reserves, Canadian investors should refer to the NI 43-101 Technical Reports for Kensington on file at www.sedar.com. 3

Comparison of the 2015 and 2018 Technical Reports Life of Mine ( LOM ) Economic Analyses February 2015 Technical Report April 2018 Technical Report Estimated Mine Life 2020 2022 Production Mill throughput tons (000s) 3,403,000 2,960,973 Head grade oz/t Au 0.18 0.21 Contained metal oz Au 627,943 620,707 Overall recovery % 93% 93% Payable metal oz Au 599,689 577,955 REVENUE Gold price $/oz $1,275 $1,250 Gross revenue $M $765 $722 Refining cost $M ($35) ($20) Net revenue $M $730 $702 OPERATING COSTS Mining $M ($290) ($262) Processing $M ($127) ($118) General and administrative $M ($109) ($109) Royalty $M ($6) ($5) Corporate charges $M ($35) $- Total operating cost $M ($566) ($494) Cost per payable gold ounce $/oz $944 $855 CASH FLOW Operating cash flow $M $164 $209 Capital expenditures $M ($103) ($97) Reclamation $M ($11) ($22) Total pre-tax cash flow $M $49 $90 Notes to the above economic analyses: a. April 2018 Technical Report is effective December 31, 2017 and the February 2015 Technical Report is effective December 31, 2014. b. Rounding of tons and ounces, as required by reporting guidelines, may result in apparent differences between tons, grade, and contained metal content. c. For details on the estimation of mineral reserves, mineral resources, and inferred mineral resources, including the key assumptions, parameters and methods used to estimate the Mineral Reserves, Mineral Resources, and Inferred Mineral Resources, Canadian investors should refer to the applicable NI 43-101 Technical Report for Kensington on file at www.sedar.com. 4

About Coeur Coeur Mining, Inc. is a well-diversified, growing precious metals producer with five mines in North America. Coeur produces from its wholly-owned operations: the Palmarejo silver-gold complex in Mexico, the Silvertip silver-zinc-lead mine in British Columbia, the Rochester silver-gold mine in Nevada, the Kensington gold mine in Alaska, and the Wharf gold mine in South Dakota. In addition, the Company has interests in several precious metals exploration projects throughout North America. Cautionary Statements This news release contains forward-looking statements within the meaning of securities legislation in the United States and Canada, including statements regarding the anticipated installation of dewatering pumps at Jualin and production ramp-up, exploration efforts and value creation, as well as anticipated financial and operating results, including production, mining rates, capital expenditures, recoveries, costs, revenues, asset values, margins, cash flows, and mine life. Such forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause Coeur's actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the risk that the expected financial and operating results for Kensington are not achieved on a timely basis or at all, the risks and hazards inherent in the mining business (including risks inherent in developing large-scale mining projects, environmental hazards, industrial accidents, weather or geologically related conditions), changes in the market prices of gold and silver and a sustained lower price environment, the uncertainties inherent in Coeur's production, exploratory and developmental activities, including risks relating to permitting and regulatory delays, ground conditions, grade variability, any future labor disputes or work stoppages, the uncertainties inherent in the estimation of gold and silver reserves, changes that could result from Coeur's future acquisition of new mining properties or businesses, the loss of any third-party smelter to which Coeur markets silver and gold, the effects of environmental and other governmental regulations, the risks inherent in the ownership or operation of or investment in mining properties or businesses in foreign countries, Coeur's ability to raise additional financing necessary to conduct its business, make payments or refinance its debt, as well as other uncertainties and risk factors set out in filings made from time to time with the United States Securities and Exchange Commission, and the Canadian securities regulators, including, without limitation, Coeur's most recent reports on Form 10-K and Form 10-Q. Actual results, developments and timetables could vary significantly from the estimates presented. Readers are cautioned not to put undue reliance on forward-looking statements. Coeur disclaims any intent or obligation to update publicly such forward-looking statements, whether as a result of new information, future events or otherwise. Additionally, Coeur undertakes no obligation to comment on analyses, expectations or statements made by third parties in respect of Coeur, its financial or operating results or its securities. Christopher Pascoe, Coeur's Director, Technical Services and a qualified person under Canadian National Instrument 43 101, reviewed and approved the scientific and technical information concerning Coeur's mineral projects in this news release. Mineral resources are in addition to mineral reserves and do not have demonstrated economic viability. Inferred mineral resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be considered for estimation of mineral reserves, and there is no certainty that the inferred mineral resources will be realized. For a description of the key assumptions, parameters and methods used to estimate mineral reserves and resources, as well as data verification procedures and a general discussion of the extent to which the estimates may be affected by any known environmental, permitting, legal, title, taxation, socio political, marketing or other relevant factors, Canadian investors should refer to the NI 43-101 Technical Report for Kensington filed April 25, 2018 on SEDAR at www.sedar.com. Cautionary Note to U.S. Investors The United States Securities and Exchange Commission permits U.S. mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. We may use certain terms in public disclosures, such as "measured," "indicated," "inferred and resources," that are recognized by Canadian regulations, but that SEC guidelines generally prohibit U.S. registered companies from including in their filings with the SEC. U.S. investors are urged to consider closely the disclosure in our Form 10 K which may be secured from us, or from the SEC's website at http://www.sec.gov. Conversion Table 1 short ton = 0.907185 metric tons 1 troy ounce = 31.10348 grams 5

For Additional Information Coeur Mining, Inc. 104 S. Michigan Avenue, Suite 900 Chicago, Illinois 60603 Attention: Courtney Lynn, Vice President, Investor Relations and Treasurer Phone: (312) 489-5800 www.coeur.com 6