ALBERTA STANDARD GUIDE FOR TAKE-OVER PROCEDURES

Similar documents
AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER. Pre-Construction and Construction Phase Services

Section Payment Conditions

Construction of the Leased Premises

RENOVATION CONTRACT. Borrower Name(s): Phone #: Phone #:

Standard Form of Agreement Between Owner and Architect without a Predefined

THIS CONSTRUCTION CONTRACT ( Contract ) dated as of ( Owner ) and ( Contractor ) having a principal place of business at.

4. The Division shall receive tenders at a location specified by the Secretary-Treasurer up to the time and date specified on the tender documents.

Educational Use Only S A M P L E S A M P L E

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project

CONSTRUCTION CONTRACT RIDER

CONSTRUCTION MANAGEMENT-AT-RISK AGREEMENT

203(K) STANDARD OWNER/CONTRACTOR AGREEMENT

EXHIBIT E SUBCONTRACT TERMS ARTICLE I THE CONTRACT DOCUMENTS

Educational Use Only S A M P L E S A M P L E

{Company.Name} {ToContact.DisplayAddress} {Projects.Name}

AIA Document A101 TM 2007

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

STANDARD FORM OF AGREEMENT BETWEEN DESIGN CONSULTANT AND DESIGN SUB-CONSULTANT

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

Document B101 TM. Standard Form of Agreement Between Owner and Architect

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION

OWNER/PROFESSIONAL SERVICES CONSULTANT AGREEMENT PROJECT TITLE UNIVERSITY OF ILLINOIS

External Consultants & General Contractors Contracts

GENERAL CONDITIONS UNIT PRICE CONTRACT

CITY OF GLENDALE. Project: Project No.:

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

WASHTENAW COMMUNITY COLLEGE CONSTRUCTION CONTRACT - GC

AIA Document B141 TM 1997 Part

AIA Document A101 TM 1997

SC BUILDERS, Inc. SAMPLE MASTER SUBCONTRACT AGREEMENT TABLE OF CONTENTS

Standard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price

AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER

Construction Management-at-Risk Agreement

MANITOBA HOUSING SUPPLEMENTAL CONDITIONS CONTRACT #: XXXX GENERAL

INSTITUTIONAL CONTRACT (CONTRACT AMOUNT LESS THAN $30,000) Contract No.:

1.1 The Canadian standard Construction Document CCDC 2, 2008 for Stipulated Price Contract, English version hereby forms the basis of this Contract.

Engineering, Procurement and Construction Contract

GENERAL TERMS AND CONDITIONS OF SALES

Agreement. Preconstruction Services

Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM

SECTION 8 - MEASUREMENT AND PAYMENT TABLE OF CONTENTS

Conditions of Contract for PLANT and Design-Build

SECTION SUPPLEMENTARY CONDITIONS

2. Attachments a) Design Drawings Drawing(s) Revision Revision Date Specifications (T1.1-T2.8) N/A N/A A /06/17 A1.1 N/A N/A A2.

CITY UNIVERSITY CONSTRUCTION FUND GUIDELINES FOR PROCUREMENT CONTRACTS (as amended through June 23, 2016)

THE CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA, INC. CMAA Document CMAR-1 (2004 Edition)

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between

PART INSTRUCTIONS TO BIDDERS

SCHEME ADMINISTRATOR:

TRADE CONTRACTOR MASTER AGREEMENT

SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS

THE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL

SPECIAL CONDITIONS OF CONTRACT

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS

EXHIBIT M PUBLIC FUNDS AMOUNT PAYMENT TERMS

WATER QUALITY MAINTENANCE-SPARKS MARINA CANAL CITY OF SPARKS, NEVADA

Northern Town of La Ronge Box Hildebrand Drive La Ronge, Saskatchewan S0J 1L0 TENDER TOWN OF LA RONGE

Form of Agreement Between the Client And the Quantity Surveyor

Document C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser

STATE OF VERMONT STANDARD FORM. GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017)

AIA Document A101 TM 2007

HUNTER WATER CORPORATION AND. [INSERT Developer: NAME OF DEVELOPER(S)] DEVELOPER WORKS DEED ROUTINE MAJOR WORKS [INSERT LOCATION] Development Site:

REQUEST FOR QUALIFICATIONS (RFQ) FOR DSA INSPECTOR OF RECORD (IOR) SERVICES

STIPULATED PRICE CONTRACT. (the "Owner") and. (the "Contractor") COVERING. (Work Description)

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition)

STANDARD FORM AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER FOR PROFESSIONAL SERVICES. THIS AGREEMENT is made this day of, 20,

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent

[CONTRACT NAME] CCDC 2 (2008) -SUPPLEMENTARY CONDITIONS

Document A Exhibit A

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope

Tri-Cities Academic Building Washington State University Richland, WA Project Manual

Standard Subcontract

SAMPLE SPECIFICATION SECTION SALES AND USE TAX SAVINGS

Canadian Standard Form of Contract for Architectural Services

Works Appointment: We, on behalf of the Employer, would like to inform you that your quotation, Reference Number

SCHEDULE 8 PAYMENTS TABLE OF CONTENTS 1. CALCULATION OF SERVICE PAYMENTS... 1

PROFESSIONAL SERVICES AGREEMENT. For On-Call Services WITNESSETH:

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-BS-EQC as follows:

PERMIT TO ENTER YOU ARE REQUIRED TO COMPLY WITH THE ENDORSEMENTS AND DETAILS SHOWN ON THIS PERMIT

AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER

Educational Use Only S A M P L E S A M P L E

Santa Ana Unified School District

HALIFAX REGIONAL MUNICIPALITY SECTION GENERAL CONDITIONS PAGE 1 OF THE CIVIL WORKS CONTRACT JANUARY 2018

City means the municipal corporation, generally known as the City of Richmond.

CONSULTATION AND DESIGN AGREEMENT Between ROMAN FOUNTAINS, a New Mexico Corporation and

REQUEST FOR QUALIFICATIONS (RFQ) FOR DSA INSPECTOR OF RECORD (IOR) SERVICES. April 18, 2006

Sample Payment Terms. A variety of sample payment language from different contracts. Form Copyright LegalDocs Online, Inc. All Rights Reserved.

Attachment I GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

Standard Form of Agreement between Owner and Construction Manager

FHA Renovation Loan Program, or 203K

General Terms and Conditions Logistik Zentrum Allgäu GmbH & Co. KG Area of Operations Sorting Services (VDL)

Contractor shall provide new thermal fused plastic laminate doors for each interior opening as scheduled. All openings are to receive new hardware.

stipulated price contract

REQUEST FOR QUOTATIONS

DEMARIA SUBCONTRACTOR TERMS AND CONDITIONS. Table of Contents

CONSTRUCTION AGREEMENT (Stipulated Sum) BY AND BETWEEN. NEW YORK UNIVERSITY SCHOOL OF MEDICINE, an administrative unit of NEW YORK UNIVERSITY

Knox County Government and Strategic Equipment and Supply

Transcription:

ACA DOCUMENT C 2004 ALBERTA STANDARD GUIDE FOR TAKE-OVER PROCEDURES For use in conjunction with the CONDITIONS OF CONSTRUCTION CONTRACTS COPYRIGHT 2004 ALBERTA CONSTRUCTION ASSOCIATION Prepared by Standard Practices Committee Alberta Construction Association In consultation with and endorsed by: CONSULTING ENGINEERS OF ALBERTA THE ALBERTA ASSOCIATION OF ARCHITECTS

RECOMMENDED PROCEDURES CONCERNING FINAL COMPLETION AND TAKE-OVER OF CONSTRUCTION PROJECTS INTRODUCTION The purpose of this document is to provide recommended standard procedures to facilitate the closing phases of a construction contract and the orderly take-over of the construction project by the owner from the contractor. The Standard Practices Committee of the Alberta Construction Association has developed this document in the hope that it will be accepted by the industry and become a part of the general conditions of construction contracts. N.B. Words in this document importing the masculine gender include the feminine gender. INDEX Documentation Procedures Definition of Substantial Performance Stage 1 Contractor s Inspection for Substantial Performance Stage 2 - Contractor s Application for Certificate of Substantial Performance Stage 3 Following Substantial Performance Stage 4 Application for Final Payment Stage 5 Guarantee Period (s) App. A Sample Certificate of Substantial Performance DOCUMENTATION PROCEDURES A. The contractor, in consultation with the owner/architect/engineer and as soon as possible after the award of the contract, shall initiate preparation of two lists as follows (except when specified otherwise in the contract documents): 1. Items required for operation of occupied premises: This first list shall itemize all data, operating instructions, maintenance manuals, record drawings, spare parts, materials and other items, as required by the contract documents. 2. Items required to complete the contract: the second list shall show all documentation which will later be required to be submitted and approved by the owner/architect/engineer before he will issue his certificate for payment covering the release of final payment and of the lien holdbacks (statutory declarations, Workers Compensation Board letter of good standing, guarantees and other items as required by the contract documents as applicable to the project). B. The contractor shall transmit copies of the above-mentioned two lists to the owner/architect/engineer for review and approval. 2

C. Within 14 calendar days of receipt of said lists, the owner/architect/engineer shall review said lists and notify the contractor of his approval of same, with or without changes; assembly by the contractor of the items on said lists shall then commence. DEFINITION OF SUBSTANTIAL PERFORMANCE For the purposes of this document and the Alberta Builder s Lien Act, a contract is substantially performed: a. when the work or a substantial part thereof is ready for use or is being used for the purpose intended, and when the work to be done under the contract is capable of completion or correction at a cost nor more than: 1. 3 per cent of the first $500,000 of the contract price. 2. 2 per cent of the next $500,000 of the contract price, and 3. 1 per cent of the balance of the contract price, or b. when the work or a substantial part thereof is ready for use or is being used for the purpose intended and where the work cannot be completed expeditiously for reasons beyond the control of a contractor, the value of the work to be completed shall be deducted from the contract price in determining substantial performance. STAGE 1 CONTRACTOR S INSPECTION FOR SUBSTANTIAL PERFORMANCE 1.1 When in the contractor s opinion the project meets the requirements of substantial performance, he shall make a preliminary inspection giving written notice of this to the owner/architect/engineer for information only. 1.2 The inspection team shall consist of: a. the contractor or his representative(s) b. such subcontractors or their representatives as may be required by the contractor. 1.3 Upon completion of this inspection a list of all incomplete and deficient work shall be prepared by the contractor and issued to those concerned including the owner/architect/engineer. 1.4 Any sub-contractor may request substantial performance for his sub-contract. The contractor shall then initiate inspection as outlined in Stage 1. 1.5 The contractor is cautioned that the work should be ready prior to calling for inspection. Any visits to inspect work not ready may cause the owner to incur additional costs for unnecessary visits by his consultants, and may cause the consultants to be inconvenienced and incur additional costs as well. Premature inspections may result in disputes over payment for additional costs incurred by the owner and its consultants. 3

STAGE 2 CONTRACTOR S APPLICATION FOR CERTIFICATE OF SUBSTANTIAL PERFORMANCE 2.1 When the contractor considers that the work is substantially performed he shall submit a comprehensive list of items to be completed or corrected and a Certificate of Substantial Performance for review by the owner/architect/engineer to establish a date for Substantial Performance. 2.2 This application shall include: a. A statement to the owner (through the architect/engineer where applicable) to the effect that: 1. the work has been executed in accordance with the plans and specifications, and 2. the contract is substantially completed, and 3. the performance of the balance of the contract is in process and total completion is scheduled for the day of.., 20.. b. A statement of completion with the cost values of: 1. work to be completed; 2. work which cannot be performed for reasons beyond the control of the contractor. c. The submission of all data, operating instructions, evidence of all tests, maintenance manuals, record drawings, spare parts and materials, etcetera, to enable the owner to use the constructed works. 2.3 Concurrent with submission of the Certificate of Substantial Performance, the contractor shall complete the preparation and assembly of all items covered by the second list as approved by the owner or his representative under Documentation Procedures A.2. 2.4 a. Not later than 10 days after receipt of the contractor s application, the owner/architect/engineer shall make an inspection of the work covered by the application and such other work, if any, which the owner/architect/engineer may deem necessary. b. Not later than 7 days after his inspection the owner/architect/engineer shall notify the contractor in writing of his agreement or disagreement with the contractor s assessment of the work. c. Where there is disagreement the contractor shall make the necessary corrections and reapply. d. Where there is agreement the owner/architect/engineer shall issue a Certificate of Substantial Performance and assign an appropriate date. STAGE 3 FOLLOWING SUBSTANTIAL PERFORMANCE 3.1 In accordance with the Alberta Builder s Lien Act, holdback monies are payable on the 46 th day following the issuance of a Certificate of Substantial Performance, provided that no builder s liens have been filed in the intervening period. 3.2 Upon receipt of verification of acceptance of the Certificate of Substantial Performance as set forth in Stage 2, the contractor should invoice the owner for release of the appropriate holdback monies. 4

FOR EDUCATIONAL PURPOSES ONLY 3.3 The holdback to be released following Substantial Performance of the Work is 10% of the value of the work performed to that time and in Alberta is referred to as the major lien fund. The owner is not entitled to withhold any portion of the lien fund to meet the cost values set out in 2.2 (b) above. Instead, such cost values should be taken into account in determining the value of the work upon which to base the lien fund calculation. STAGE 4 APPLICATION FOR FINAL PAYMENT 4.1 When the contractor is satisfied that the entire work is completed, and after making his own inspection, he shall make a written request for a final inspection by the owner/architect/engineer. This inspection shall be carried out and completed not later than 10 days of the request, and shall constitute the inspection prior to the issuance of the final certificate for payment. 4.2 If there are any deficiencies determined by this inspection, they shall be listed by the owner/architect/engineer and provided to the contractor. This list shall be recognized as the deficiency list for purposes of completion of the work under the contract. 4.3 Such deficiencies shall be corrected by a date mutually agreed upon between the contractor and the owner/architect/engineer, unless a specific date is required by the contract, and a re-inspection by the owner/architect/engineer shall be called for by the contractor, following his own inspection, to take place not later than 7 days from the date of the request. 4.4 Upon request, the owner shall make monthly progress payments on completed deficiencies. 4.5 When all work has been completed and all deficiencies have been rectified, excepting incomplete work or deficiencies not rectified due to reasons beyond the control of the contractor or a sub-contractor, then all amounts due under the contract shall become payable, and a final certificate for payment shall be issued. Any remaining holdback monies are payable on the 46 th day following the date of total completion of the Work, provided that no builder s liens have been filed in the intervening period. STAGE 5 GUARANTEE PERIOD(S) 5.1 The guarantee period(s) for the project shall commence at the date of substantial performance of the work, as noted on the Certificate of Substantial Performance. 5.2 No later than 30 days before the expiry of the guarantee period(s), the contractor shall arrange with the owner for an inspection of the project to be carried out by the contractor with the owner/architect/engineer. This inspection shall be carried out and completed not later than 10 days before the expiry of the guarantee period(s). 5.3 If there are any defects determined by this inspection, they shall be listed by the owner/architect/engineer and provided to the contractor. This list shall be recognized as the final deficiency list for purposes of completing the contractor s guarantee obligations under the contract. 5

SAMPLE CERTIFICATE OF SUBSTANTIAL PERFORMANCE To Owner And To Contractor Date of Inspection.. Project Address In accordance with the contract dated. between the contractor and the owner, hereby certifies that, WITH THE EXCEPTION OF THE ITEMS LISTED ON THE ATTACHED PAGE, 1. (a) the work or a substantial part thereof is ready for use, or (b) the work is being used for the purposes intended; and 2. The work to be done under the contract is capable of completion or correction at a cost of not more than $... The contractor and his sub-contractors shall continue to work towards total completion. Provided no liens are registered, holdback monies withheld under the contract are due and payable 46 days after the date of this Certificate. Architect/Engineer. Signed by Distribution:.. Date. Owner Contractor (This is a sample only of the Certificate of Substantial Performance, referred to as Appendix A in the index) 6