FULL RESERVE STUDY. Home Owners Association for Seale Subdivision Unit-1, Inc. San Antonio, Texas November 17, 2017

Similar documents
FULL RESERVE STUDY Stillwood Cluster Lot Owners' Association, Inc. Stow, Ohio August 15, 2017

Revised FULL RESERVE STUDY. Falcon Ridge at Highland Creek Homeowners Association, Inc.

FULL RESERVE STUDY Ameri-Cana Resorts Co-op, Inc. Rockledge, Florida April 13, 2017

FULL RESERVE STUDY The Towns at Lakeside Association, Inc. North Port, Florida March 2, 2018

FULL RESERVE STUDY. Belair at Carolina Lakes Homeowners Association, Inc. Fort Mill, South Carolina October 21, 2014

FULL RESERVE STUDY Woodridge Park Homeowners' Association, Ltd. Orchard Park, New York November 10, 2017

THE VINEYARDS AT DUBLIN GREENE OWNERS ASSOCIATION

REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION. N & H Enterprises MILLER ~ DODSON ASSOCIATES. Community Management by:

Update With Site Visit

REPLACEMENT RESERVE REPORT FY 2011 VILLAGE GREEN HOA. Ravenel Associates, Inc. Community Management by: Chad Hammond, Property Manager

NEWTON PARISH REPLACEMENT RESERVE REPORT 2008 REPLACEMENT RESERVE REPORT FY CAS, Inc MILLER ~ DODSON ASSOCIATES. Community Management by:

F U L L R E S E RV E S T U DY R E P O RT

CAPITAL RESERVE STUDY. Meadow Wood Commons. City, State

VILLAGE AT LAKE CHELAN

Reserve Study Project No Prepared for Nelson Farm Homeowner Association 1771 Norwood Lane Fort Collins, Colorado

WHAT IS A RESERVE STUDY AND WHY ARE THEY IMPORTANT?

REPLACEMENT RESERVE REPORT FY 2015 WOODBRIDGE CONDOMINIUM CHESAPEAKE BAY MANAGEMENT. Community Management by: Ms. Kimberly Marston

Reserve Analysis Report

TIMBERLAKE COMMUNITY ASSOCIATION

REPLACEMENT RESERVE REPORT FY 2016

Reserve Analysis Report

DRAFT CAPITAL RESERVE STUDY. The Piano Works Condominium Association. Deep River, Connecticut FOR THE. Project Number:

CAPITAL RESERVE STUDY


Reserve Analysis Report

The Ranches HOA. Level II Reserve Study. Report Period 1/01/08 12/31/08

21289 E. Lords Way Queen Creek, AZ Tel: (480) Fax: (888) October 27, Sample Association

RESERVE STUDY SPECIALISTS

GLOBAL Solution Partners, LLC - Toll free phone and fax: (844)

NEW ALBANY COUNTRY CLUB MASTER ASSOCIATION, INC NEW ALBANY, OHIO

Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION CROZET, VA. Prepared by:

Central Pointe HOA. Level I Reserve Study. Report Period 1/01/08 12/31/08

2015 Reserve Study Report LOCATED AT: FOR: AS OF: BY:

FULL RESERVE STUDY FUNDING ANALYSIS PLAN Level I

FLINT HILL MANOR FLINT HILL MANOR. Replacement Reserve Study. Oakton, Virginia. Property Management: Flint Hill Manor Townhouse Association

Fieldstone RESERVE STUDY UPDATE. John D. Beatty & Company OWNERS ASSOCIATION. for. Date Prepared: 12/4/2018 for fiscal year 2019.

Cottonwoods at Vine. Reserve Study. October 2012

OCEAN NEIGHBORS HOMEOWNERS ASSOCIATION REPLACEMENT RESERVE REPORT FY 2017 POSTON & COMPANY. Community Management by: Melissa Blocker, Property Manager

PROFESSIONAL RESERVE STUDY

Full Reserve Study For Glenmoor Homeowners Association Conway, South Carolina

2014 Reserve Study. The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee Report No: 2921 Version 2

2013 Reserve Study. Sea Havens Homeowners Association, Inc Florida Shores Boulevard Daytona Beach Shores, Florida Report No: 2713 Version 2

Level 3 Reserve Study without a Site a Site Visit Visit

REPLACEMENT RESERVE REPORT FY 2016

Arizona Nevada Texas Utah New Mexico

SMA RESERVES. Miramar Plaza Homeowners' Association. Reserve Study For Fiscal Year: 10/01/2014 through 09/30/2015

2019 Reserve Study. Pebble Shores Condominium Association, Inc. Pebble Shores Drive Naples, FL A Service of:

Commercial Assessments

Bridgewood Manor HOA

REPLACEMENT RESERVE REPORT FY 2019 SANCTUARY AT FALSE CAPE. Prepared for: Ms. Rebecca Beamon

SCT RESERVE CONSULTANTS, INC. P.O. BOX TEMECULA, CA

Reserve Analysis Report

Shadow Ridge. Level 2 Reserve Study. Report Period 01/01/ /31/2015. Date of Property Inspection 8/21/2014

SOMERSET CREEK STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT. With funding recommendations for the 2019 fiscal year

- RS. D e sig n atio n

THE SUMMIT AT AUTUMN HILLS CAMAS, WA 98607

FIR RIDGE II CONDOMINIUM

LEVEL 3 RESERVE STUDY UPDATE For ORCHARD GREENS HOMEOWNERS ASSOCIATION, INC.

N SITE RESERVE STUDY Presented by:

Clearbrook HOA. Level 1 Reserve Study. Report Period 1/1/ /31/2010. Client Reference Number /23/2010 Prepared By

Reserve Analysis Report

Parkwood HOA. Level 1 Reserve Study. Report Period 1/1/ /31/2012. Date of Property Inspection. Report prepared on Saturday, August 11, 2012

RESERVE STUDY UPDATE SUMMARY

REPLACEMENT RESERVE REPORT FY 2017 CAMDEN TOWNES ROCKTOWN REALTY. Community Management by: Bernard Hamann

HUDSON PARK ESTATES HOMEOWNERS ASSOCIATION HUDSON, OHIO

Brookwood Homeowners Association, Inc.

Calusa Point Association, Inc. Miami, Florida File #

Urban Heights Condominium

RESERVESTUDYUPDATE. The Villas at Blackberry Run Dallas, GA. Prepared for:

The Ford Plantation - POA Revised August 17, THE FORD10 EXECUTIVE SUMMARY

Sun Peak Master Association

REPLACEMENT RESERVE REPORT FY 2018 SANCTUARY AT FALSE CAPE. Prepared for: Ms. Rebecca Beamon

CAPITAL RESERVE STUDY

REPLACEMENT RESERVE STUDY 2006

RESERVE STUDY LEVEL II UPDATE WITH VISUAL SITE INSPECTION

Sample Community Association

CONTENTS 1.0 INTRODUCTION... 1

Reserve Study. Willow Lake Homeowner's Association, Inc.

RESERVE STUDY ANNUAL REPORT

.USI.COMMERCIAL. (888) Funding Reserve Analysis. for. The Retreat at Gleannloch Farms Homeowners Association Spring, TX

VÜxx~Ëá Xwzx tà fàéçç cé Çà géãç{éåxá

PROFESSIONAL RESERVE STUDY

Reserve Analysis Report

Reserve Fund Study My Condominium Plan

MILL CREEK CONDOMINIUMS RESERVE STUDY

RESERVE STUDY LEVEL II UPDATE WITH VISUAL SITE INSPECTION

PROFESSIONAL RESERVE STUDY

WYLIE, TX. Date of Investigation: February 6, 2018 Investigator: Phillip Nieman, P.E. Reviewed By: David H. Dotson, P.E., R.S.

Full Reserve Study. The Ridge at Rock Creek Marysville, WA 11/13/2012

RESERVE STUDY LEVEL II UPDATE WITH VISUAL SITE INSPECTION. Prepared for:

GLOBAL Solution Partners, LLC - Toll free phone and fax: (844)

PROFESSIONAL RESERVE STUDY

Estates at River Ranch HOA

Reserve Study Transmittal Letter

Country Club Townhomes

Courts of Country Lakes Condominium Association, Inc.

CAPITAL RESERVE STUDY. Ellicott Meadows Condominium Association I. Ellicott City, Maryland

Regarding: Level I Capital Replacement Reserve Study. We are pleased to submit this Level I Reserve Study for Summit Park Condominiums.

DUNN LORING VILLAGE SEQUOIA MANAGEMENT COMPANY. Craig Courtney Property Manager. Vienna, Virginia. Property Management: Consultant:

R E S E R V E S T U D Y

Transcription:

FULL RESERVE STUDY Home Owners Association for Seale Subdivision Unit-1, Inc. San Antonio, Texas November 17, 2017 This Report contains intellectual property developed by Reserve Advisors, Inc. and cannot be reproduced or distributed to those who conduct reserve studies without their written consent. Reserve Advisors, Inc. 2018

Reserve Advisors, Inc. 735 N. Water Street, Suite 175 Milwaukee, WI 53202 Home Owners Association for Seale Subdivision Unit-1, Inc. San Antonio, Texas Dear Board of Directors of Home Owners Association for Seale Subdivision Unit-1, Inc.: At the direction of the Board that recognizes the need for proper reserve planning, we have conducted a Full Reserve Study of Home Owners Association for Seale Subdivision Unit-1, Inc. in San Antonio, Texas and submit our findings in this report. The effective date of this study is the date of our visual, noninvasive inspection, November 17, 2017. This Full Reserve Study exceeds the Association of Professional Reserve Analysts (APRA) standards fulfilling the requirements of a Level I Full Reserve Study. An ongoing review by the Board and an Update of this Reserve Study are necessary to ensure an equitable funding plan since a Reserve Study is a snapshot in time. We recommend the Board budget for an Update to this Reserve Study in two years. We look forward to continuing to help Home Owners Association for Seale Subdivision Unit- 1, Inc. plan for a successful future. As part of our long-term thinking and everyday commitment to our clients, we are available to answer any questions you may have regarding this study. Respectfully submitted on January 9, 2018 by Reserve Advisors, Inc. Visual Inspection and Report by: Victor Vogt Review by: Alan M. Ebert, PRA 1, RS 2, Director of Quality Assurance 1 PRA (Professional Reserve Analyst) is the professional designation of the Association of Professional Reserve Analysts. Learn more about APRA at http://www.apra-usa.com. 2 RS (Reserve Specialist) is the reserve provider professional designation of the Community Associations Institute (CAI) representing America's more than 300,000 condominium, cooperative and homeowners associations.

Table of Contents 1. RESERVE STUDY EXECUTIVE SUMMARY... 1.1 2. RESERVE STUDY REPORT... 2.1 3. RESERVE EXPENDITURES and FUNDING PLAN... 3.1 4. RESERVE COMPONENT DETAIL... 4.1 Property Site Elements... 4.1 Asphalt Pavement, Repaving... 4.1 Concrete Sidewalks... 4.2 Fences, Wood... 4.3 Irrigation System... 4.4 Light Poles and Fixtures... 4.5 Perimeter Walls, Panelized Concrete... 4.6 Playground Equipment... 4.7 Shade Structure... 4.8 Signage, Entry Monuments... 4.8 Site Furniture... 4.10 Pool Elements... 4.10 Concrete Deck... 4.10 Fence, Steel... 4.11 Furniture... 4.12 Mechanical Equipment... 4.13 Pergola, Wood... 4.14 Pool Finish, Plaster... 4.15 Roof, Asphalt Shingles... 4.16 Rest Room... 4.17 Shade Structures... 4.18 Water Features... 4.18 Reserve Study Update... 4.19 5. METHODOLOGY... 5.1 6. CREDENTIALS... 6.1 7. DEFINITIONS... 7.1 8. PROFESSIONAL SERVICE CONDITIONS... 8.1

1. RESERVE STUDY EXECUTIVE SUMMARY Client: Home Owners Association for Seale Subdivision Unit-1, Inc. (Laurel Mountain) Location: San Antonio, Texas Reference: 171919 Property Basics: Home Owners Association for Seale Subdivision Unit-1, Inc. is a planned unit development which is responsible for the common elements shared by 1,365 single family homes. The community began construction in 2004 and construction is ongoing with an expected completion date in 2019. Reserve Components Identified: 23 Reserve Components. Inspection Date: November 17, 2017. Funding Goal: The Funding Goal of this Reserve Study is to maintain reserves above an adequate, not excessive threshold during one or more years of significant expenditures. Our recommended Funding Plan recognizes this threshold funding year in 2045 due to replacement of the panelized concrete perimeter walls. Cash Flow Method: We use the Cash Flow Method to compute the Reserve Funding Plan. This method offsets future variable Reserve Expenditures with existing and future stable levels of reserve funding. Our application of this method also considers: Current and future local costs of replacement 1.2% annual rate of return on invested reserves 1.7% future Inflation Rate for estimating Future Replacement Costs Sources for Local Costs of Replacement: Our proprietary database, historical costs and published sources, i.e., R.S. Means, Incorporated. Cash Status of Reserve Fund: $170,493 as of December 31, 2017 2018 budgeted Reserve Contributions of $73,000 Project Prioritization: We recommend the Association prioritize the following projects in the next five years based on the conditions identified: Replace the plaster finish at the pool Recommended Reserve Funding: We recommend the following in order to achieve a stable and equitable Funding Plan: Reduced reserve budget of $33,500 in 2019 Inflationary increases through 2047, the limit of this study's Cash Flow Analysis 2019 Reserve Contribution of $33,500 is equivalent to an average annual contribution of $24.54 per homeowner. Page 1.1 - Executive Summary

Laurel Mountain Recommended Reserve Funding Table and Graph Reserve Contributions ($) Reserve Balances ($) Year Reserve Contributions ($) Reserve Balances ($) Year Reserve Contributions ($) Reserve Balances ($) Year 2018 73,000 245,977 2028 39,000 397,873 2038 46,200 497,766 2019 33,500 282,630 2029 39,700 420,788 2039 47,000 514,288 2020 34,100 259,317 2030 40,400 376,230 2040 47,800 312,887 2021 34,700 278,396 2031 41,100 422,091 2041 48,600 296,634 2022 35,300 286,341 2032 41,800 277,172 2042 49,400 291,257 2023 35,900 314,650 2033 42,500 301,436 2043 50,200 331,531 2024 36,500 355,145 2034 43,200 348,512 2044 51,100 341,502 2025 37,100 358,669 2035 43,900 362,925 2045 52,000 169,373 2026 37,700 400,899 2036 44,600 395,519 2046 52,900 224,623 2027 38,300 381,310 2037 45,400 445,938 2047 53,800 163,006 600 500 400 300 200 100 0-100 -200-300 Recommended Reserve Contributions Reserve Expenditures Year-End Reserve Balances Years Page 1.2 - Executive Summary

2. RESERVE STUDY REPORT At the direction of the Board that recognizes the need for proper reserve planning, we have conducted a Full Reserve Study of Home Owners Association for Seale Subdivision Unit-1, Inc. San Antonio, Texas and submit our findings in this report. The effective date of this study is the date of our visual, noninvasive inspection, November 17, 2017. We present our findings and recommendations in the following report sections and spreadsheets: Identification of Property - Segregates all property into several areas of responsibility for repair or replacement Reserve Expenditures - Identifies reserve components and related quantities, useful lives, remaining useful lives and future reserve expenditures during the next 30 years Reserve Funding Plan - Presents the recommended Reserve Contributions and year-end Reserve Balances for the next 30 years Reserve Component Detail - Describes the reserve components, includes photographic documentation of the condition of various property elements, describes our recommendations for repairs or replacement, and includes detailed solutions and procedures for replacements for the benefit of current and future board members Methodology - Lists the national standards, methods and procedures used to develop the Reserve Study Definitions - Contains definitions of terms used in the Reserve Study, consistent with national standards Professional Service Conditions - Describes Assumptions and Professional Service Conditions Credentials and Resources Page 2.1 - Report

IDENTIFICATION OF PROPERTY Our investigation includes Reserve Components or property elements as set forth in your Declaration. The Expenditure tables in Section 3 list the elements contained in this study. Our analysis begins by segregating the property elements into several areas of responsibility for repair and replacement. Our process of identification helps assure that future boards and the management team understand whether reserves, the operating budget or Homeowners fund certain replacements and assists in preparation of the annual budget. We derive these segregated classes of property from our review of the information provided by the Association and through conversations with Management and the Board. These classes of property include: Reserve Components Long-Lived Property Elements Operating Budget Funded Repairs and Replacements Property Maintained by Homeowners Property Maintained by Others We advise the Board conduct an annual review of these classes of property to confirm its policy concerning the manner of funding, i.e., from reserves or the operating budget. The Reserve Study identifies Reserve Components as set forth in your Declaration or which were identified as part of your request for proposed services. Reserve Components are defined by CAI as property elements with: Page 2.2 - Report

Laurel Mountain responsibility Limited useful life expectancies Predictable remaining useful life expectancies Replacement cost above a minimum threshold Long-Lived Property Elements may not have predictable Remaining Useful Lives or their replacement may occur beyond the 30-year scope of the study. The operating budget should fund infrequent repairs. Funding untimely or unexpected replacements from reserves will necessitate increases to Reserve Contributions. Periodic updates of this Reserve Study will help determine the merits of adjusting the Reserve Funding Plan. We identify the following Long-Lived Property Elements as excluded from reserve funding at this time. Electrical Systems, Common Foundations, Pool House Pipes, Interior Building, Water and Waste, Pool House Pipes, Subsurface Utilities Structural Frames, Pool House The operating budget provides money for the repair and replacement of certain Reserve Components. The Association may develop independent criteria for use of operating and reserve funds. For purposes of calculating appropriate Reserve Contributions, we identify the following list of Operating Budget Funded Repairs and Replacements: General Maintenance to the Common Elements Expenditures less than $4,000 (These relatively minor expenditures have a limited effect on the recommended Reserve Contributions.) Asphalt Pavement, Crack Repair, Patch and Seal Coat Applications Concrete Culverts, Minor Repairs Fence, Steel, Paint Finishes Fences, Wood, Interim Repairs Irrigation System, Controllers Irrigation System, Minor Repairs and Replacements Landscape Paint Finishes, Touch Up Pool House, Exterior, Repairs and Paint Finishes Pool House, Interior, Repairs and Paint Finishes Pool House, Light Fixtures, Replacement Signage, Entry Monuments, Interim Paint Finishes Other Repairs normally funded through the Operating Budget Certain items have been designated as the responsibility of the homeowners to repair or replace at their cost. Property Maintained by Homeowners, including items billed back to Homeowners, relates to unit: Home and Lots Page 2.3 - Report

Fences at Lot Lines Certain items have been designated as the responsibility of others to repair or replace. Property Maintained by Others relates to: Asphalt Pavement Street Systems (City of San Antonio) Mailbox Stations (United States Postal Service) Page 2.4 - Report

3. RESERVE EXPENDITURES and FUNDING PLAN The tables following this introduction present: Reserve Expenditures Line item numbers Total quantities Quantities replaced per phase (in a single year) Reserve component inventory Estimated first year of event (i.e., replacement, application, etc.) Life analysis showing useful life remaining useful life Unit cost of replacement 2017 local cost of replacement Total future costs of replacement anticipated during the next 30 years Schedule of estimated future costs for each reserve component including inflation Reserve Funding Plan Reserves at the beginning of each year Total recommended reserve contributions Estimated interest earned from invested reserves Anticipated expenditures by year Anticipated reserves at year end Predicted reserves based on current funding level Financial statements prepared by your association, by you or others might rely in part on information contained in this section. For your convenience, we have provided an electronic data file containing the tables of Reserve Expenditures and Reserve Funding Plan. Page 3.1 - Reserve Expenditures and Funding Plan

Reserve Advisors, Inc. Years 2017 to 2032 RESERVE EXPENDITURES Explanatory Notes: Home Owners Association for Seale 1) 1.7% is the estimated future Inflation Rate for estimating Future Replacement Costs. Subdivision Unit-1, Inc. 2) FY2017 is Fiscal Year beginning January 1, 2017 and ending December 31, 2017. San Antonio, Texas Estimated Life Analysis, Costs, $ Line Total Per Phase 1st Year of Years Unit Per Phase Total 30-Year Total RUL = 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Item Quantity Quantity Units Reserve Component Inventory Event Useful Remaining (2017) (2017) (2017) (Inflated) FY2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 ---------------------------- ------------- ------------------- ------------------------------------------------------------------------------------------ --------------- ----------- ---------------- ------------------- ---------------------------------------- -------------------- ---------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- Property Site Elements 4.040 700 700 Square Yards Asphalt Pavement, Mill and Overlay 2027 15 to 20 10 15.50 10,850 10,850 12,842 12,842 4.045 700 700 Square Yards Asphalt Pavement, Total Replacement 2047 15 to 20 30 27.00 18,900 18,900 31,339 4.140 7,500 565 Square Feet Concrete Sidewalks, Partial 2030 to 65 13 to 30+ 8.50 4,803 63,750 27,260 5,979 4.285 3,620 3,620 Linear Feet Fences, Wood 2032 15 to 20 15 25.00 90,500 90,500 116,537 116,537 4.420 73,910 24,637 Square Feet Irrigation System, Phased 2044 to 40 27 to 30+ 1.00 24,637 73,910 38,837 4.560 9 9 Each Light Poles and Fixtures (Includes Light Poles and Fixtures at Pool) 2032 to 25 15 2,000.00 18,000 18,000 23,179 23,179 4.640 2,280 1,140 Linear Feet Perimeter Walls, Panelized Concrete, Phased 2040 30 to 40 23 to 28 100.00 114,000 228,000 350,755 4.660 1 1 Allowance Playground Equipment 2027 15 to 20 10 42,000.00 42,000 42,000 119,355 49,712 4.670 1,120 1,120 Square Feet Shade Structure, Fabric Replacement 2025 6 to 8 8 8.00 8,960 8,960 21,988 10,254 4.671 1,120 1,120 Square Feet Shade Structure, Total Replacement 2041 20 to 25 24 25.00 28,000 28,000 41,962 4.800 1 1 Allowance Signage, Entry Monuments, Renovation 2025 15 to 20 8 15,300.00 15,300 15,300 42,038 17,509 4.820 16 16 Each Site Furniture 2036 15 to 25 19 500.00 8,000 8,000 11,020 Pool Elements 6.200 7,060 7,060 Square Feet Concrete Deck, Inspections, Partial Replacements and Repairs 2022 8 to 12 5 4.00 28,240 28,240 110,130 30,723 36,365 6.400 420 420 Linear Feet Fence, Steel 2039 to 35 22 60.00 25,200 25,200 36,514 6.500 2 1 Allowance Furniture, Phased 2023 to 12 6 to 12 10,100.00 10,100 20,200 69,102 11,175 12,364 6.600 2 1 Allowance Mechanical Equipment, Phased 2021 to 15 4 to 11 10,000.00 10,000 20,000 51,521 10,698 12,037 6.750 1 1 Allowance Pergola, Wood 2032 to 25 15 11,500.00 11,500 11,500 14,809 14,809 6.800 5,110 5,110 Square Feet Pool Finish, Plaster 2020 8 to 12 3 10.50 53,655 53,655 202,305 56,438 66,801 6.850 22 22 Squares Pool House, Roof, Asphalt Shingles 2025 15 to 20 8 400.00 8,800 8,800 23,710 10,070 6.860 2 2 Each Pool House, Rest Rooms, Fixtures 2030 to 25 13 6,800.00 13,600 13,600 16,932 16,932 6.870 500 500 Square Feet Shade Structures, Fabric Replacement 2020 6 to 8 3 8.00 4,000 4,000 16,023 4,207 6.871 500 500 Square Feet Shade Structures, Total Replacement 2028 20 to 25 11 25.00 12,500 12,500 15,047 15,047 6.950 2 1 Each Water Features, Phased 2021 to 12 4 to 12 7,600.00 7,600 15,200 50,961 8,130 9,304 ------------------------------------------------------------------------------------------ ---------------------------- ---------------- ------------------- ---------------------------------------- -------------------- ---------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- Anticipated Expenditures, By Year $1,444,166 0 0 0 60,645 18,828 30,723 11,175 0 37,833 0 62,554 27,084 21,668 89,712 0 190,890 Printed on 1/9/2018 Expenditures - Section 3-1 of 2

Reserve Advisors, Inc. RESERVE EXPENDITURES Years 2033 to 2047 Home Owners Association for Seale Subdivision Unit-1, Inc. San Antonio, Texas Estimated Life Analysis, Costs, $ Line Total Per Phase 1st Year of Years Unit Per Phase Total 30-Year Total 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Item Quantity Quantity Units Reserve Component Inventory Event Useful Remaining (2017) (2017) (2017) (Inflated) 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 ---------------------------- ------------- ------------------- ------------------------------------------------------------------------------------------ --------------- ----------- ---------------- ------------------- ---------------------------------------- -------------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- Property Site Elements 4.040 700 700 Square Yards Asphalt Pavement, Mill and Overlay 2027 15 to 20 10 15.50 10,850 10,850 12,842 4.045 700 700 Square Yards Asphalt Pavement, Total Replacement 2047 15 to 20 30 27.00 18,900 18,900 31,339 31,339 4.140 7,500 565 Square Feet Concrete Sidewalks, Partial 2030 to 65 13 to 30+ 8.50 4,803 63,750 27,260 6,505 7,077 7,699 4.285 3,620 3,620 Linear Feet Fences, Wood 2032 15 to 20 15 25.00 90,500 90,500 116,537 4.420 73,910 24,637 Square Feet Irrigation System, Phased 2044 to 40 27 to 30+ 1.00 24,637 73,910 38,837 38,837 4.560 9 9 Each Light Poles and Fixtures (Includes Light Poles and Fixtures at Pool) 2032 to 25 15 2,000.00 18,000 18,000 23,179 4.640 2,280 1,140 Linear Feet Perimeter Walls, Panelized Concrete, Phased 2040 30 to 40 23 to 28 100.00 114,000 228,000 350,755 167,991 182,764 4.660 1 1 Allowance Playground Equipment 2027 15 to 20 10 42,000.00 42,000 42,000 119,355 69,643 4.670 1,120 1,120 Square Feet Shade Structure, Fabric Replacement 2025 6 to 8 8 8.00 8,960 8,960 21,988 11,734 4.671 1,120 1,120 Square Feet Shade Structure, Total Replacement 2041 20 to 25 24 25.00 28,000 28,000 41,962 41,962 4.800 1 1 Allowance Signage, Entry Monuments, Renovation 2025 15 to 20 8 15,300.00 15,300 15,300 42,038 24,529 4.820 16 16 Each Site Furniture 2036 15 to 25 19 500.00 8,000 8,000 11,020 11,020 Pool Elements 6.200 7,060 7,060 Square Feet Concrete Deck, Inspections, Partial Replacements and Repairs 2022 8 to 12 5 4.00 28,240 28,240 110,130 43,042 6.400 420 420 Linear Feet Fence, Steel 2039 to 35 22 60.00 25,200 25,200 36,514 6.500 2 1 Allowance Furniture, Phased 2023 to 12 6 to 12 10,100.00 10,100 20,200 69,102 6.600 2 1 Allowance Mechanical Equipment, Phased 2021 to 15 4 to 11 10,000.00 10,000 20,000 51,521 36,514 13,680 15,136 16,747 13,545 15,241 6.750 1 1 Allowance Pergola, Wood 2032 to 25 15 11,500.00 11,500 11,500 14,809 6.800 5,110 5,110 Square Feet Pool Finish, Plaster 2020 8 to 12 3 10.50 53,655 53,655 202,305 79,066 6.850 22 22 Squares Pool House, Roof, Asphalt Shingles 2025 15 to 20 8 400.00 8,800 8,800 23,710 13,640 6.860 2 2 Each Pool House, Rest Rooms, Fixtures 2030 to 25 13 6,800.00 13,600 13,600 16,932 6.870 500 500 Square Feet Shade Structures, Fabric Replacement 2020 6 to 8 3 8.00 4,000 4,000 16,023 5,510 6,306 6.871 500 500 Square Feet Shade Structures, Total Replacement 2028 20 to 25 11 25.00 12,500 12,500 15,047 6.950 2 1 Each Water Features, Phased 2021 to 12 4 to 12 7,600.00 7,600 15,200 50,961 9,953 11,390 12,184 ------------------------------------------------------------------------------------------ ---------------------------- ---------------- ------------------- ---------------------------------------- -------------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- ------------- Anticipated Expenditures, By Year $1,444,166 21,687 0 33,730 16,530 0 0 36,514 254,134 68,488 58,283 13,640 45,143 227,176 0 117,729 Printed on 1/9/2018 Expenditures - Section 3-2 of 2

Reserve Advisors, Inc. Page 1 of 1 RESERVE FUNDING PLAN CASH FLOW ANALYSIS Home Owners Association for Seale Subdivision Unit-1, Inc. Individual Reserve Budgets & Cash Flows for the Next 30 Years San Antonio, Texas FY2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 Reserves at Beginning of Year (Note 1) N/A 170,493 245,977 282,630 259,317 278,396 286,341 314,650 355,145 358,669 400,899 381,310 397,873 420,788 376,230 422,091 Total Recommended Reserve Contributions (Note 2) N/A 73,000 33,500 34,100 34,700 35,300 35,900 36,500 37,100 37,700 38,300 39,000 39,700 40,400 41,100 41,800 Plus Estimated Interest Earned, During Year (Note 3) N/A 2,484 3,153 3,232 3,207 3,368 3,584 3,995 4,257 4,530 4,665 4,647 4,883 4,754 4,761 4,171 Less Anticipated Expenditures, By Year N/A 0 0 (60,645) (18,828) (30,723) (11,175) 0 (37,833) 0 (62,554) (27,084) (21,668) (89,712) 0 (190,890) ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- Anticipated Reserves at Year End $170,493 $245,977 $282,630 $259,317 $278,396 $286,341 $314,650 $355,145 $358,669 $400,899 $381,310 $397,873 $420,788 $376,230 $422,091 $277,172 (continued) Individual Reserve Budgets & Cash Flows for the Next 30 Years, Continued 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 Reserves at Beginning of Year 277,172 301,436 348,512 362,925 395,519 445,938 497,766 514,288 312,887 296,634 291,257 331,531 341,502 169,373 224,623 Total Recommended Reserve Contributions 42,500 43,200 43,900 44,600 45,400 46,200 47,000 47,800 48,600 49,400 50,200 51,100 52,000 52,900 53,800 Plus Estimated Interest Earned, During Year 3,451 3,876 4,243 4,524 5,019 5,628 6,036 4,933 3,635 3,506 3,714 4,014 3,047 2,350 2,312 Less Anticipated Expenditures, By Year (21,687) 0 (33,730) (16,530) 0 0 (36,514) (254,134) (68,488) (58,283) (13,640) (45,143) (227,176) 0 (117,729) ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- Anticipated Reserves at Year End $301,436 $348,512 $362,925 $395,519 $445,938 $497,766 $514,288 $312,887 $296,634 $291,257 $331,531 $341,502 $169,373 $224,623 $163,006 (NOTE 5) (NOTE 4) Explanatory Notes: 1) Year 2017 starting reserves are projected by Management and the Board as of December 31, 2017; FY2017 starts January 1, 2017 and ends December 31, 2017. 2) Reserve Contributions for 2017 are budgeted; 2018 is budgeted; 2019 is the first year of recommended contributions. 3) 1.2% is the estimated annual rate of return on invested reserves; 2017 is a partial year of interest earned. 4) Accumulated year 2047 ending reserves consider the age, size, overall condition and complexity of the property. 5) Threshold Funding Year (reserve balance at critical point). Printed on 1/9/2018 Funding Plan - Section 3

4. RESERVE COMPONENT DETAIL The Reserve Component Detail of this Full Reserve Study includes Enhanced Solutions and Procedures for select significant components. This section describes the Reserve Components, documents specific problems and condition assessments, and may include detailed solutions and procedures for necessary capital repairs and replacements for the benefit of current and future board members. We advise the Board use this information to help define the scope and procedures for repair or replacement when soliciting bids or proposals from contractors. However, the Report in whole or part is not and should not be used as a design specification or design engineering service. Asphalt Pavement, Repaving Line Items: 4.040 and 4.045 Property Site Elements Quantity: Approximately 700 square yards of pavement at the pool History: Original to construction in 2007 Condition: Good overall with isolated cracks evident Asphalt pavement parking area Isolated cracks Useful Life: 15- to 20-years Component Detail Notes: The initial installation of asphalt uses at least two lifts, or two separate applications of asphalt, over the base course. The first lift is the binder course. The second lift is the wearing course. The wearing course comprises a finer aggregate for a smoother more watertight finish. The following diagram depicts these components: Page 4.1 - Reserve Component Detail

The manner of repaving is either a mill and overlay or total replacement. A mill and overlay is a method of repaving where cracked, worn and failed pavement is mechanically removed or milled until sound pavement is found. A new layer of asphalt is overlaid atop the remaining base course of pavement. Total replacement includes the removal of all existing asphalt down to the base course of aggregate and native soil followed by the application of two or more new lifts of asphalt. We recommend mill and overlayment on asphalt pavement that exhibits normal deterioration and wear. We recommend total replacement of asphalt pavement that exhibits severe deterioration, inadequate drainage, pavement that has been overlaid multiple times in the past or where the configuration makes overlayment not possible. Based on the apparent visual condition and configuration of the asphalt pavement, we recommend the mill and overlay method for initial repaving followed by the total replacement method for subsequent repaving at Laurel Mountain. Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Our cost for milling and overlayment includes area patching of up to ten percent (10%). We also include replacement of up to ten percent (10%) of the concrete curbs and gutters at the parking area. Concrete Sidewalks Line Item: 4.140 Quantity: Approximately 7,500 square feet of concrete sidewalks near the pool and at the rear of the houses at the north side of the west portion of the community. Page 4.2 - Reserve Component Detail

Condition: Good overall with erosion evident along the length of the sidewalk at the north side of the west portion of the community. This is likely due to its location in a drainage area. Concrete sidewalk at the north side of the west portion of the community Erosion along the length of the sidewalk due to its location in a drainage area Useful Life: Up to 65 years although interim deterioration of areas is common Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. We estimate that up to 2,260 square feet of concrete sidewalks, or thirty percent (30.1%) of the total, will require replacement during the next 30 years. We assume the developer will remediate erosion at the sidewalk in the drainage area prior to turnover to the Association. Fences, Wood Line Item: 4.285 Quantity: Approximately 3,620 linear feet along Emory Peak History: Original to construction in 2012 through 2015 Condition: Good overall condition with leaning sections and previous repairs evident Page 4.3 - Reserve Component Detail

Wood fence along Emory Peak Leaning section of fence Leaning section of fence Previous repair and wood deterioration Useful Life: 15- to 20-years Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. The Association should anticipate periodic partial replacements due to the non-uniform nature of wood deterioration. Along with these partial replacements, the Association should apply periodic paint applications as needed and fund these activities through the operating budget. Irrigation System Line Item: 4.420 Quantity: Approximately 73,910 square feet at the common areas and entry monuments Page 4.4 - Reserve Component Detail

History: Original to construction Condition: Good overall and Management and the Board does not report any deficiencies Useful Life: Up to 40 years Component Detail Notes: components: Irrigation systems typically include the following Electronic controls (timer) Impact rotors Network of supply pipes Pop-up heads Valves Laurel Mountain should anticipate interim and partial replacements of the system network supply pipes and other components as normal maintenance to maximize the useful life of the irrigation system. The Association should fund these ongoing seasonal repairs through the operating budget. Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Light Poles and Fixtures Line Item: 4.560 Quantity: Nine each History: Original to construction in 2007 Condition: Good overall Page 4.5 - Reserve Component Detail

Typical light pole and fixture Useful Life: Up to 25 years Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Perimeter Walls, Panelized Concrete Line Item: 4.640 Quantity: Approximately 2,280 linear feet along Emory Peak History: Original to construction in 2007 Condition: Good with areas of no visible deterioration Panelized concrete wall along Emory Peak Isolated cracks Page 4.6 - Reserve Component Detail

Isolated deterioration Useful Life: 30- to 40-years Priority/Criticality: Not recommended to defer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. We recommend the Association fund repairs through the operating budget. Playground Equipment Line Item: 4.660 History: Original to construction in 2007 Condition: Good overall Useful Life: 15- to 20-years Playset Page 4.7 - Reserve Component Detail

Component Detail Notes: Safety is the major purpose for maintaining playground equipment. We recommend an annual inspection of the playground equipment to identify and repair as normal maintenance loose connections and fasteners or damaged elements. We suggest the Association learn more about the specific requirements of playground equipment at PlaygroundSafety.org. We recommend the use of a specialist for the design or replacement of the playground equipment environment. Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. We include an allowance in the unit cost for replacement of the safety surface. Shade Structure Line Items: 4.670 and 4.671 Quantity: Approximately 1,120 square feet at the playground History: Installed within the last year Condition: The fabric and structure are in good condition overall Shade structure over the playset Useful Life: The fabric has a useful life of six- to eight-years. The structure has a useful life of 20- to 25-years. Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Signage, Entry Monuments Page 4.8 - Reserve Component Detail

Line Item: 4.800 History: Original to construction Condition: Good overall Entry monument at Emory Peak Entry monument near the recreation center Useful Life: 15- to 20-years Entry monument at Dodge City Trail Component Detail Notes: Community signage contributes to the overall aesthetic appearance of the property to owners and potential buyers. Renovation or replacement of community signs is often predicated upon the desire to "update" the perceived identity of the community rather than for utilitarian concerns. Therefore, the specific times for replacement or renovation are discretionary. The signage includes the following elements: Light fixtures Stucco Masonry, stone Page 4.9 - Reserve Component Detail

Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Our cost for renovation includes repointing and repairs to the masonry, paint finishes and repairs to the stucco and replacement of the remaining components listed above. Site Furniture Line Item: 4.810 History: Mostly at an age of one year Condition: Good overall Bench near the playground Table and grill Useful Life: 15- to 25-years Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Pool Elements Concrete Deck Line Item: 6.200 Quantity: 7,060 square feet History: Original to construction in 2007 Page 4.10 - Reserve Component Detail

Condition: Good condition Concrete deck at the pool Concrete deck in good condition Useful Life: The useful life of a concrete pool deck is up to 60 years or more with timely repairs. We recommend the Association conduct inspections, partial replacements and repairs to the deck every 8- to 12-years. Component Detail Notes: We recommend the Association budget for the following: Selective cut out and replacements of up to ten percent (10%) of concrete Crack repairs as needed Mortar joint repairs Caulk replacement Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Fence, Steel Line Items: 6.400 Quantity: Approximately 420 linear feet History: Original to construction in 2007 Condition: Good overall Page 4.11 - Reserve Component Detail

Steel fence with masonry columns at the pool Steel fence in good condition Useful Life: Up to 35 years Component Detail Notes: Steel components at grade and key structural connections are especially prone to failure if not thoroughly maintained. Secure and rust free fasteners and connections will prevent premature deterioration. Preparation of the steel before application of the paint finish is critical to maximize the useful life of the finish. Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. We recommend the Association apply paint finishes to the steel fence with funds from the operating budget. Furniture Line Item: 6.500 History: Varied ages Condition: Good overall Page 4.12 - Reserve Component Detail

Pool Furniture Useful Life: Up to 12 years Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. We recommend interim re-strapping, refinishing, cushion replacements, reupholstering and other repairs to the furniture as normal maintenance to maximize its useful life. Mechanical Equipment Line Item: 6.600 Quantity: Automatic chlorinator Controls Filters Interconnected pipe, fittings and valves Pumps Electrical panel History: Varied ages Condition: Reported satisfactory Page 4.13 - Reserve Component Detail

Mechanical equipment Mechanical equipment Useful Life: Up to 15 years Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Failure of the pool mechanical equipment as a single event is unlikely. We consider interim replacement of motors and minor repairs as normal maintenance. Pergola, Wood Line Item: 6.750 History: Original to construction in 2007 Condition: Good overall Useful Life: Up to 25 Wood pergola Page 4.14 - Reserve Component Detail

Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. The Association should anticipate periodic partial replacements due to the non-uniform nature of wood deterioration. Along with these partial replacements, the Association should apply periodic paint applications as needed and fund these activities through the operating budget. Pool Finish, Plaster Line Item: 6.800 Quantity: 5,110 square feet based on the horizontal surface area History: Likely original to construction in 2007 Condition: Good overall with isolated cracks at the zero depth entry at the wading section Pool plaster at the main section Pool plaster at the wading section Page 4.15 - Reserve Component Detail

Pool plaster at the zero depth entry with isolated cracks Pool plaster at the steps Useful Life: 8- to 12-years Component Detail Notes: Removal and replacement provides the opportunity to inspect the pool structure and to allow for partial repairs of the underlying concrete surfaces as needed. To maintain the integrity of the pool structure, we recommend the Association budget for the following Removal and replacement of the finish Partial replacements of the scuppers and coping as needed Replacement of tiles as needed Replacement of joint sealants as needed Concrete structure repairs as needed Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Roof, Asphalt Shingles Line Item: 6.850 Quantity: Approximately 22 squares 1 History: Original to construction in 2007 Condition: Good overall. Management does not inform us of a history of leaks. 1 We quantify the roof area in squares where one square is equal to 100 square feet of surface area. Page 4.16 - Reserve Component Detail

Asphalt shingle roof Useful Life: 15- to 20-years Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Rest Room Line Item: 6.860 Quantity: Two common restrooms at the pool house History: Components are original to construction in 2007 Condition: Good overall Restroom stalls Sinks and mirrors Page 4.17 - Reserve Component Detail

Useful Life: Up to 25 years Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Shade Structures Line Items: 6.870 and 6.871 Quantity: Approximately 500 square feet History: Original to construction in 2007 Condition: The fabric and structure are in good condition overall Shade structure at the pool Fabric at the shade structure in good condition Useful Life: The fabric has a useful life of six- to eight-years. The structure has a useful life of 20- to 25-years. Priority/Criticality: Defer only upon opinion of independent professional or engineer Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Water Features Line Item: 6.950 History: The yellow aqua dome is original to construction in 2007. The green aqua dome was installed within the last year. Conditions: Good overall Page 4.18 - Reserve Component Detail

Water features Useful Life: Up to 15 years Priority/Criticality: Per Board discretion Expenditure Detail Notes: Expenditure timing and costs are depicted in the Reserve Expenditures table in Section 3. Reserve Study Update An ongoing review by the Board and an Update of this Reserve Study are necessary to ensure an equitable funding plan since a Reserve Study is a snapshot in time. Many variables change after the study is conducted that may result in significant overfunding or underfunding the reserve account. Variables that may affect the Reserve Funding Plan include, but are not limited to: Deferred or accelerated capital projects based on Board discretion Changes in the interest rates on reserve investments Changes in the local construction inflation rate Additions and deletions to the Reserve Component Inventory The presence or absence of maintenance programs Unusually mild or extreme weather conditions Technological advancements Periodic updates incorporate these variable changes since the last Reserve Study or Update. We recommend the Board budget for an Update to this Reserve Study in two years. Budgeting for an Update demonstrates the Board's objective to continue fulfilling its fiduciary responsibility to maintain the commonly owned property and to fund reserves appropriately. Page 4.19 - Reserve Component Detail

5. METHODOLOGY Reserves for replacement are the amounts of money required for future expenditures to repair or replace Reserve Components that wear out before the entire facility or project wears out. Reserving funds for future repair or replacement of the Reserve Components is also one of the most reliable ways of protecting the value of the property s infrastructure and marketability. Laurel Mountain can fund capital repairs and replacements in any combination of the following: 1. Increases in the operating budget during years when the shortages occur 2. Loans using borrowed capital for major replacement projects 3. Level monthly reserve assessments annually adjusted upward for inflation to increase reserves to fund the expected major future expenditures 4. Special assessments We do not advocate special assessments or loans unless near term circumstances dictate otherwise. Although loans provide a gradual method of funding a replacement, the costs are higher than if the Association were to accumulate reserves ahead of the actual replacement. Interest earnings on reserves also accumulate in this process of saving or reserving for future replacements, thereby defraying the amount of gradual reserve collections. We advocate the third method of Level Monthly Reserve Assessments with relatively minor annual adjustments. The method ensures that Homeowners pay their "fair share" of the weathering and aging of the commonly owned property each year. Level reserve assessments preserve the property and enhance the resale value of the homes. This Reserve Study is in compliance with and exceeds the National standards 1 set forth by the Community Associations Institute (CAI) and the Association of Professional Reserve Analysts (APRA) fulfilling the requirements of a Full Reserve Study. These standards require a Reserve Component to have a predictable remaining Useful Life. Estimating Remaining Useful Lives and Reserve Expenditures beyond 30 years is often indeterminate. Long-Lived Property Elements are necessarily excluded from this analysis. We considered the following factors in our analysis: The Cash Flow Method to compute, project and illustrate the 30-year Reserve Funding Plan Local 2 costs of material, equipment and labor Current and future costs of replacement for the Reserve Components Costs of demolition as part of the cost of replacement Local economic conditions and a historical perspective to arrive at our estimate of long term future inflation for construction costs in San Antonio, Texas at an annual inflation rate. Isolated or regional markets of greater 1 Identified in the APRA Standards - Terms and Definitions and the CAI "Terms and Definitions". 2 See Credentials for addition information on our use of published sources of cost data. Page 5.1 - Methodology

construction (development) activity may experience slightly greater rates of inflation for both construction materials and labor. The past and current maintenance practices of Laurel Mountain and their effects on remaining useful lives Financial information provided by the Association pertaining to the cash status of the reserve fund and budgeted reserve contribution The anticipated effects of appreciation of the reserves over time in accord with a return or yield on investment of your cash equivalent assets. (We did not consider the costs, if any, of Federal and State Taxes on income derived from interest and/or dividend income). The Funding Plan excludes necessary operating budget expenditures. It is our understanding that future operating budgets will provide for the ongoing normal maintenance of Reserve Components. Updates to this Reserve Study will continue to monitor historical facts and trends concerning the external market conditions. Page 5.2 - Methodology

6. CREDENTIALS HISTORY AND DEPTH OF SERVICE Founded in 1991, Reserve Advisors, Inc. is the leading provider of reserve studies, insurance appraisals, developer turnover transition studies, expert witness services, and other engineering consulting services. Clients include community associations, resort properties, hotels, clubs, non-profit organizations, apartment building owners, religious and educational institutions, and office/commercial building owners in 48 states, Canada and throughout the world. The architectural engineering consulting firm was formed to take a leadership role in helping fiduciaries, boards, and property managers manage their property like a business with a long range master plan known as a Reserve Study. Reserve Advisors employs the largest staff of Reserve Specialists with bachelor s degrees in engineering dedicated to Reserve Study services. Our principals are founders of Community Associations Institute's (CAI) Reserve Committee that developed national standards for reserve study providers. One of our principals is a Past President of the Association of Professional Reserve Analysts (APRA). Our vast experience with a variety of building types and ages, on-site examination and historical analyses are keys to determining accurate remaining useful life estimates of building components. No Conflict of Interest - As consulting specialists, our independent opinion eliminates any real or perceived conflict of interest because we do not conduct or manage capital projects. TOTAL STAFF INVOLVEMENT Several staff members participate in each assignment. The responsible advisor involves the staff through a Team Review, exclusive to Reserve Advisors, and by utilizing the experience of other staff members, each of whom has served hundreds of clients. We conduct Team Reviews, an internal quality assurance review of each assignment, including: the inspection; building component costing; lifing; and technical report phases of the assignment. Due to our extensive experience with building components, we do not have a need to utilize subcontractors. OUR GOAL To help our clients fulfill their fiduciary responsibilities to maintain property in good condition. VAST EXPERIENCE WITH A VARIETY OF BUILDINGS Reserve Advisors has conducted reserve studies for a multitude of different communities and building types. We've analyzed thousands of buildings, from as small as a 3,500-square foot day care center to the 2,600,000-square foot 98-story Trump International Hotel and Tower in Chicago. We also routinely inspect buildings with various types of mechanical systems such as simple electric heat, to complex systems with air handlers, chillers, boilers, elevators, and life safety and security systems. We're familiar with all types of building exteriors as well. Our well versed staff regularly identifies optimal repair and replacement solutions for such building exterior surfaces such as adobe, brick, stone, concrete, stucco, EIFS, wood products, stained glass and aluminum siding, and window wall systems. OLD TO NEW Reserve Advisors experience includes ornate and vintage buildings as well as modern structures. Our specialists are no strangers to older buildings. We're accustomed to addressing the unique challenges posed by buildings that date to the 1800's. We recognize and consider the methods of construction employed into our analysis. We recommend appropriate replacement programs that apply cost effective technologies while maintaining a building's character and appeal. Page 6.1 - Credentials

QUALIFICATIONS THEODORE J. SALGADO Principal Owner CURRENT CLIENT SERVICES Theodore J. Salgado is a co-founder of Reserve Advisors, Inc., which is dedicated to serving community associations, city and country clubs, religious organizations, educational facilities, and public and private entities throughout the United States. He is responsible for the production, management, review, and quality assurance of all reserve studies, property inspection services and consulting services for a nationwide portfolio of more than 6,000 clients. Under his direction, the firm conducts reserve study services for community associations, apartment complexes, churches, hotels, resorts, office towers and vintage architecturally ornate buildings. PRIOR RELEVANT EXPERIENCE Before founding Reserve Advisors, Inc. with John P. Poehlmann in 1991, Mr. Salgado, a professional engineer registered in the State of Wisconsin, served clients for over 15 years through American Appraisal Associates, the world's largest full service valuation firm. Mr. Salgado conducted facilities analyses of hospitals, steel mills and various other large manufacturing and petrochemical facilities and casinos. He has served clients throughout the United States and in foreign countries, and frequently acted as project manager on complex valuation, and federal and state tax planning assignments. His valuation studies led to negotiated settlements on property tax disputes between municipalities and property owners. Mr. Salgado has authored articles on the topic of reserve studies and facilities maintenance. He also co-authored Reserves, an educational videotape produced by Reserve Advisors on the subject of Reserve Studies and maintaining appropriate reserves. Mr. Salgado has also written in-house computer applications manuals and taught techniques relating to valuation studies. EXPERT WITNESS Mr. Salgado has testified successfully before the Butler County Board of Tax Revisions in Ohio. His depositions in pretrial discovery proceedings relating to reserve studies of Crestview Estates Condominium Association in Wauconda, Illinois, Rivers Point Row Property Owners Association, Inc. in Charleston, South Carolina and the North Shore Club Associations in South Bend, Indiana have successfully assisted the parties in arriving at out of court settlements. EDUCATION - Milwaukee School of Engineering - B.S. Architectural Engineering PROFESSIONAL AFFILIATIONS/DESIGNATIONS American Association of Cost Engineers - Past President, Wisconsin Section Association of Construction Inspectors - Certified Construction Inspector Association of Professional Reserve Analysts - Past President & Professional Reserve Analyst (PRA) Community Associations Institute - Member and Volunteer Leader of multiple chapters Concordia Seminary, St. Louis - Member, National Steering Committee Milwaukee School of Engineering - Member, Corporation Board Professional Engineer, Wisconsin (1982) and North Carolina (2014) Ted continually maintains his professional skills through American Society of Civil Engineers, ASHRAE, Association of Construction Inspectors, and continuing education to maintain his professional engineer licenses. Page 6.2 - Credentials