Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Similar documents
Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses

Making sense of Schedule Risk Analysis

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM

Schedule Risk Analysis Simplified 1

Project Risk Management

AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E.

PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS. Mairav Mintz, PE, CCM Sagar Khadka, DRMP, FAACE

MINI GUIDE. Project risk analysis and management

Fundamentals of Project Risk Management

Chapter-8 Risk Management

Spheria Australian Smaller Companies Fund

Project Risk Analysis. Neil Dunkerley 17 th May 2012

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Quantitative Risk Analysis with Microsoft Project

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

A Study on Risk Analysis in Construction Project

What are the Essential Features of a Good Economic Scenario Generator? AFIR Munich September 11, 2009

Security Analysis: Performance

Firm Frequency Response Market Information for Apr-16

Financial & Business Highlights For the Year Ended June 30, 2017

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods

Operating Reserves Educational Session Part B

Project Assessment Exercise

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

Order Making Fiscal Year 2018 Annual Adjustments to Transaction Fee Rates

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

The Not-So-Geeky World of Statistics

Understanding the Principles of Investment Planning Stochastic Modelling/Tactical & Strategic Asset Allocation

for 9 Sep 15 SoCal ICEAA Workshop

Looking at a Variety of Municipal Valuation Metrics

Balance-of-Period TCC Auction

Managing Project Risk DHY

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Earned Schedule Analysis

Factor Leave Accruals. Accruing Vacation and Sick Leave

Risk Video #1. Video 1 Recap

CONSTRUCTION CLAIMS MANAGEMENT & EOT DELAYS ANALYSIS. Presented by : Hany Ismail, MSc, PMP

Grant Park Multi Alternative Strategies Fund. Why Invest? Profile Since Inception. Consider your alternatives. Invest smarter.

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY

Uncertainty in Economic Analysis

OTHER DEPOSITS FINANCIAL INSTITUTIONS DEPOSIT BARKAT SAVING ACCOUNT

The Swan Defined Risk Strategy - A Full Market Solution

Executive Summary. July 17, 2015

Economics 883: The Basic Diffusive Model, Jumps, Variance Measures. George Tauchen. Economics 883FS Spring 2015

Beginning Date: January 2016 End Date: June Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Using projections to manage your programs

The Case for Schedule Risk Analysis

Beginning Date: January 2016 End Date: September Managers in Zephyr: Benchmark: Morningstar Short-Term Bond

FOR RELEASE: MONDAY, MARCH 21 AT 4 PM

Manager Comparison Report June 28, Report Created on: July 25, 2013

Risk vs. Uncertainty: What s the difference?

Integrating Contract Risk with Schedule and Cost Estimates

CS/Tremont Hedge Fund Index Performance Review

Risk Assessment of the Niagara Tunnel Project

After complete studying this chapter, You should be able to

Review of Membership Developments

The First Steps in Implementing a Simplified Earned Value Management System

Voya Indexed Universal Life-Protector

PROJECT MANAGEMENT: PERT AMAT 167

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

Risk Management for Pork Producers: Futures Buy and Sell Signals

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

// Measuring Risk Exposure through Risk Range Certainty (RRC) Overcoming the Shortcomings of Schedule Confidence Levels

A Note on the Steepening Curve and Mortgage Durations

Pandemics, Catastrophic Trends and Capital Issues

SmallBizU WORKSHEET 1: REQUIRED START-UP FUNDS. Online elearning Classroom. Item Required Amount ($) Fixed Assets. 1 -Buildings $ 2 -Land $

Risk Management: World s Shortest Tutorial

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

Risk Assessment and Management for Large Infrastructure Projects. Outline

Project Theft Management,

Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc.

Principal Component Analysis of the Volatility Smiles and Skews. Motivation

Isle Of Wight half year business confidence report

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Re-engineering Project Budgeting and Management of Risk

DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK?

Exam 1 Problem Solving Questions Review

Risk Management for Cattle Feedlots: Futures Buy and Sell Signals

White Paper. Risk Assessment

Earned Value Management An Overview March 2014

Discussion of Discounting in Oil and Gas Property Appraisal

Risk Management for Cattle Feedlots: Futures Buy and Sell Signals

THURGOOD MARSHALL MIDDLE SCHOOL LYNN, MA

Hypothetical Illustration

California Department of Transportation(Caltrans)

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

Ho Ho Quantitative Portfolio Manager, CalPERS

Algo Trading System RTM

Energy Yield Reconciliation in Monthly O&M Reports

Business & Financial Services December 2017

Information Technology Project Management, Sixth Edition

Transcription:

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates, LLC 2013 Hulett & Associates, LLC 1

Risk Drivers Method Agenda Risk Register identifies high-priority risks Explain Risk Factors approach Risks have probability, impact Risks are assigned to activities Compute Monte Carlo simulation results Estimate sensitivity and net effect of key risks Apply Risk Factors to simple space vehicle development schedule as an example Collecting risk data for the model How results are used to manage project risk 2013 Hulett & Associates, LLC 2

Limitations with the Traditional 3-point Estimate of Activity Duration Typical schedule risk analysis starts with the activity that is impacted by risks Estimates the 3-point estimate for optimistic, most likely and pessimistic duration Creates a probability distribution for activity duration Performs Monte Carlo simulation Which risks cause the most overall schedule risk? These questions are typically answered by: Sensitivity to activity durations Criticality of activity durations 2013 Hulett & Associates, LLC 3

Some Problems with Traditional Approach Can tell which activities are crucial, but not directly which risks are driving Makes poor use of the Risk Register that is usually available Cannot decompose the overall schedule risk into its components BY RISK Ability to assign the risk to its specific risk drivers helps with communication of risk causes and risk mitigation 2013 Hulett & Associates, LLC 4

We Propose a Different Approach: Start with the Risks Themselves Drive the schedule risk by the risks already analyzed in the Risk Register For each risk, specify: Probability it will occur Impact on time if it does Activities it will affect Starting with the risks themselves gives us benefits Links qualitative analysis to the quantitative analysis Estimates the impact of specific risks for prioritized mitigation purposes Correlations between activities happen automatically never have to guess at these coefficients again, never get impossible matrices 2013 Hulett & Associates, LLC 5

Simple Example of Risk Register Risks Use the Risk Factors feature in Pertmaster 8 Collect probability and impact data on risks Load the risks Assign risks to schedule activities 2013 Hulett & Associates, LLC 6

Risk Factors Mechanics (1) The risk factor is assigned to one or several activities, affecting their durations by a multiplicative factor E.g., the factor may be.90 for optimistic, 1.0 for most likely and 1.25 for pessimistic These factors multiply the schedule durations of the activities to which they are assigned Risks can be assigned to one or more activities Activity durations can be influenced by one or more risks 2013 Hulett & Associates, LLC 7

Risk Factors Mechanics (2) Risk Factors are assigned a probability of occurring on any iteration. When the risk occurs, the factor used is chosen at random from the 3-point estimate and operates on all activities to which it is assigned When not occurring on an iteration the risk factor takes the value 1.0, a neutral value When an activity is influenced by more than one risk, their factors are multiplied together, if they happen, on any iteration 2013 Hulett & Associates, LLC 8

Risk Factor Probability is 100%, Factor can be + or - Entire Plan : Duration 100% 115 Here the Ranges are based on deviations + and from the Plan. Probability is 100% Hits 400 350 300 250 200 150 95% 111 90% 109 85% 108 80% 106 75% 105 70% 104 65% 104 60% 103 55% 102 50% 101 45% 101 40% 100 35% 99 30% 99 Cumulative Frequency For the examples we use an activity with 100 days in the schedule 100 25% 98 20% 97 15% 96 50 10% 95 5% 94 0 0% 90 90 95 100 105 110 115 Distribution (start of interval) 2013 Hulett & Associates, LLC 9

Risk Factor Prob. = 100%, Factor is all Overrun 350 Entire Plan : Duration 100% 130 95% 125 90% 122 Here the Plan is the Optimistic Value. Probability is 100% Hits 300 250 200 150 85% 121 80% 119 75% 118 70% 117 65% 116 60% 115 55% 114 50% 113 45% 112 40% 111 Cumulative Frequency 35% 110 100 30% 109 25% 109 20% 108 50 15% 107 10% 105 5% 104 0 100 105 110 115 120 125 130 0% 100 Distribution (start of interval) 2013 Hulett & Associates, LLC 10

Assigning a Probability Less than 100% The essence of a risk is its uncertainty in two dimensions: Uncertainty of its occurrence, specified by a probability Uncertainty of its impact, specified by a range of durations If the risk may or may not occur, we specify the probability that it will occur The risk occurs and affects the activities it is assigned to on X% of the iterations, chosen at random, the multiplicative factor used is chosen at random from the range of data input by the user On (1 X)% of the iterations, Factor takes 1.0 value 2013 Hulett & Associates, LLC 11

Assigning a Probability Less than 100% Spike contains 40% of the probability Hits 2000 1800 1600 1400 1200 1000 800 Entire Plan : Duration 100% 130 95% 123 90% 120 85% 118 80% 116 75% 114 70% 113 65% 111 60% 110 55% 109 50% 107 45% 106 40% 103 35% 100 Cumulative Frequency Hits 3500 3000 2500 2000 1500 Entire Plan : Duration 100% 114 95% 107 90% 104 85% 101 80% 100 75% 100 70% 100 65% 100 60% 100 55% 100 50% 100 45% 100 40% 100 35% 100 Cum ulative Frequency Spike contains 70% of the probability 600 30% 100 30% 100 25% 100 1000 25% 100 400 20% 100 20% 100 200 15% 100 10% 100 500 15% 100 10% 99 5% 100 5% 97 0 0% 100 0 0% 90 100 105 110 115 120 125 130 90 95 100 105 110 115 Distribution (start of interval) Distribution (start of interval) 2013 Hulett & Associates, LLC 12

Assigning More than One Risk to an Activity If more than one risk is acting on an activity, the resulting ranges are the multiplication of the percentages This is reality an activity is often affected by multiple risks Two cases are shown next: When both risks are 100% likely to occur When both risks are < 100% likely to occur In each case, the computer simulation creates the uncertainty range on an activity s duration it is not estimated 2013 Hulett & Associates, LLC 13

Parallel and Series Risks Additive used with Risk Register Risk 1 20 days 20 days for risk recovery Risk 2 12 days If these two risks are parallel, they can be recovered simultaneously Risk 1 20 days Risk 2 12 days If these two risks are series, they can not be recovered simultaneously so the duration is longer 32 days for risk recovery 2013 Hulett & Associates, LLC 14

Parallel and Series Risks Multiplicative Used with Risk Drivers (RiskFactors) Risk 1 1.2 factor Risk 2 1.05 factor Use 1.2 Factor, the largest factor only If these two risks are parallel, they can be recovered simultaneously Risk 1 1.2 factor Risk 2 1.05 factor If these two risks are series, they can not be recovered simultaneously Use (1.2 x 1.05 = 1.26) Factor, multiply the two 2013 Hulett & Associates, LLC 15

Two Risks affect One Activity using Factors that Occur 100% - placed in Series 260 240 220 Entire Plan : Duration 100% 146 95% 131 90% 127 85% 124 80% 123 Risks in series, P80 is 123 days Hits 200 180 160 140 120 100 75% 121 70% 119 65% 118 60% 117 55% 116 50% 115 45% 114 40% 112 35% 111 Cumulative Frequency 80 30% 110 60 25% 109 20% 108 40 15% 106 20 10% 104 5% 102 0 100 110 120 130 140 Distribution (start of interval) 2013 Hulett & Associates, LLC 16 0% 92

Two Risks affect One Activity using Factors that Occur 100% - in Parallel Entire Plan : Duration 100% 130 95% 125 350 90% 122 85% 121 300 80% 119 75% 118 70% 117 250 65% 116 Risks in parallel, P80 is 119 days Hits 200 150 60% 115 55% 114 50% 113 45% 112 40% 111 35% 111 30% 110 Cumulative Frequency 100 25% 109 20% 108 50 15% 107 10% 106 5% 105 0 100 105 110 115 120 125 130 Distribution (start of interval) 0% 100 2013 Hulett & Associates, LLC 17

Two Risks with Less than 100% Probability Affecting one Activity Risks in Series The spike at 100 days represents (1) the likelihood that neither risk occurs [60% x 50% = 30%] and (2) the chance that 100 days is picked when one or both occur. Hits 1800 1600 1400 1200 1000 800 600 400 200 Entire Plan : Duration 100% 144 95% 123 90% 119 85% 116 80% 114 75% 112 70% 110 65% 108 60% 107 55% 105 50% 103 45% 101 40% 100 35% 100 30% 100 25% 100 20% 100 15% 100 10% 99 5% 96 Cumulative Frequency 0 0% 90 90 100 110 120 130 140 Distribution (start of interval) 2013 Hulett & Associates, LLC 18

Two Risks with Less than 100% Probability Affecting one Activity Risks in Parallel With one risk s having a minimum range of 100%, it cannot be less than 100 days Hits 2200 2000 1800 1600 1400 1200 1000 Entire Plan : Duration 100% 130 95% 122 90% 118 85% 115 80% 113 75% 111 70% 110 65% 109 60% 107 55% 105 50% 103 45% 101 40% 100 Cumulative Frequency 800 35% 100 30% 100 600 25% 100 20% 100 400 15% 100 200 10% 100 5% 100 0 100 105 110 115 120 125 130 Distribution (start of interval) 0% 100 2013 Hulett & Associates, LLC 19

Risk Factors Model How Correlation Occurs Coefficients are Calculated (1) Risk Probability =.5, Range.95, 1.05, 1.15 Activity 1 Activity 2 Correlation = 100% 2013 Hulett & Associates, LLC 20

Scatter showing 100% Correlation 2013 Hulett & Associates, LLC 21

Risk Factors Model How Correlation Occurs Coefficients are Calculated (2) Risk Probability =.25, Range.8,.95, 1.05 Risk Probability =.5, Range.95, 1.05, 1.15 Risk Probability =.45, Range 1.0, 1.10, 1.20 Activity 1 Activity 2 Correlation = 37% Correlation is modeled as it is caused in the project Correlation coefficients are generated, not guessed 2013 Hulett & Associates, LLC 22

Scatter showing 37% Correlation 2013 Hulett & Associates, LLC 23

Sensitivity to the Risk Factors Risk 1 is more important since it affects both Activity A and Activity B 2013 Hulett & Associates, LLC 24

http://www.gao.gov/products/gao-12-120g 2013 Hulett & Associates, LLC 25

Schedule Check Report in Pertmaster (C) 2013 2010-2013 Hulett & Hulett Associates, & LLC 26 26 Associates LLC

Using Acumen FUSE for Best Practices (C) 2013 2010-2013 Hulett & Hulett Associates, & LLC 27 27 Associates LLC

Simple 2-Stage 2 Space Vehicle Schedule Software used: Pertmaster v. 8.7 2013 Hulett & Associates, LLC 28

Two Types of Risk Inherent variability including duration estimating error uncertainty Probability = 100% Used Quick Risk of -5% and +10%, could be reference ranges for different types of activities Could use reference ranges that would differ by type of activity Discrete risks derived from Risk Register Probability < 100% Summarized from detailed Risk Register These have a probability of occurring and an impact on specific activities if they do Parallel to their Risk Register information 2013 Hulett & Associates, LLC 29

Standard 3-point 3 Range Representing Inherent Variability and Duration Estimating Error Inherent variability and estimating error: Optimistic - 5% Pessimistic +10% 2013 Hulett & Associates, LLC 30

Results with Inherent Variability and Duration Estimating Error Only Spacecraft for PMChallenge 2009 Entire Plan : Finish Date 100% 30 Oct 20 400 95% 27 Aug 20 90% 14 Aug 20 350 300 85% 06 Aug 20 80% 30 Jul 20 75% 24 Jul 20 70% 20 Jul 20 Deterministic: 13 APR 2020 is 1% Hits 250 200 150 100 65% 15 Jul 20 60% 10 Jul 20 55% 06 Jul 20 50% 01 Jul 20 45% 26 Jun 20 40% 22 Jun 20 35% 17 Jun 20 30% 11 Jun 20 25% 08 Jun 20 20% 01 Jun 20 15% 25 May 20 Cumulative Frequency P-80 is 30 JUL 20, about 3.5 months later than planned Spread from P-5 to P-95 is 5 MAY 20 to 27 AUG 20 for 3.7 months 50 10% 15 May 20 5% 05 May 20 0 15 Mar 20 04 May 20 23 Jun 20 12 Aug 20 01 Oct 20 Distribution (start of interval) 0% 11 Mar 20 2013 Hulett & Associates, LLC 31

Risk Analysis on Space Vehicle Project Risk Factors are from Risk Register Risk Min Most Likely Max Likelihood Requirements have not been decided 95% 105% 120% 70% Several alternative designs considered 95% 100% 115% 60% New designs not yet proven 90% 103% 112% 40% Fabrication requires new materials 95% 105% 115% 50% Lost know how since last full spacecraft 100% 100% 105% 30% Funding from Congress is problematic 90% 105% 115% 70% Schedule for testing is aggressive 100% 120% 130% 100% Seven risk factors have been identified and quantified. Each Risk has probability assigned Five have optimistic ranges possible, two are pure threats 2013 Hulett & Associates, LLC 32

Risks Assigned to Activities (1) Risk Requirements Definition FS Preliminary Design FS Final Design FS Fabrication Test FS Engine Requirements Not Complete X Alternative Designs Possible X Designs Not Proven X New Materials in Fabrication X Lost Know-How X Funding Problematic X X X X Testing Schedule Aggressive X 2013 Hulett & Associates, LLC 33 33

Risks Assigned to Activities (2) Risk US Preliminary Design US Final Design US Fabrication US Test Integration Integration Testing Requirements Not Complete Alternative Designs Possible X Designs Not Proven X New Materials in Fabrication X Lost Know-How X X Funding Problematic X X X X X X Testing Schedule Aggressive X X 2013 Hulett & Associates, LLC 34 34

Results Adding Risk Factors to the Background Risk Spacecraft for PMChallenge 2009 Entire Plan : Finish Date 100% 08 Mar 22 95% 06 Aug 21 Baseline 13 APR 20 is only 3% likely 550 500 450 90% 16 Jun 21 85% 10 May 21 80% 07 Apr 21 75% 03 Mar 21 80 th percentile is 7 APR 21, 11.8 months later Spread P-5 to P-95 is 13May20 to 6 Aug 21, for ~ 15 months Hits 400 350 300 250 200 150 70% 05 Feb 21 65% 13 Jan 21 60% 22 Dec 20 55% 03 Dec 20 50% 16 Nov 20 45% 29 Oct 20 40% 13 Oct 20 35% 28 Sep 20 30% 11 Sep 20 25% 31 Aug 20 Cumulative Frequency 20% 14 Aug 20 100 15% 28 Jul 20 50 10% 30 Jun 20 5% 13 May 20 0 25 Jan 20 12 Aug 20 28 Feb 21 16 Sep 21 Distribution (start of interval) 0% 12 Nov 19 2013 Hulett & Associates, LLC 35

Activity Tornado Chart from All-In Simulation Spacecraft for PMChallenge 2009 Duration Sensitivity: Entire Plan - All tasks 00025 - US Fabrication 00011 - FS Fabrication 00028 - Integration 00023 - US Final Design 00009 - FS Final Design 00021 - US Preliminary Design 00007 - FS Preliminary Design 70% 70% 81% 81% 79% 76% 75% Risky Activities: Fabrication, Integration, Final Design, Preliminary Design, Testing All are correlated with the finish date > 60% These are activities / paths, NOT RISKS 00029 - Integration Testing 63% 00026 - US Test 61% 00012 - Test FS Engine 61% 2013 Hulett & Associates, LLC 36

Risk Factor Tornado from All-In Simulation Risk Factors Driving Project Schedule 6 - Funding from Congress is problematic 4 - Fabricaton requires new materials 3 - New designs not yet proven Correlation 7 - Schedule for testing is aggressive 2 - Several alternative designs considered 5 - Lost know-how since last full spacecraft 1 - Requirements have not been decided The main RISK, however, is funding from Congress, which affected all activities in this model. This is the main risk to mitigate, if possible 8 - Cost Risk is based on immature data 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 Correlation 2013 Hulett & Associates, LLC 37

Contribution of Each Risk to the Contingency (1) Explain the Contingency to the P-80 P-80 Date Take Risks Out: All Risks In 7-Apr-21 Days Saved % of Contingency Specific Risks Taken Out in Order Funding 23-Nov-20 135 38% Testing Schedule 5-Oct-20 49 14% New Materials 3-Sep-20 32 9% Alternative Design 21-Aug-20 13 4% Requirements 14-Aug-20 7 2% New Design 6-Aug-20 8 2% Lost Know How 31-Jul-20 6 2% Uncertainty Natural Variation & Estimating Error 13-Apr-20 109 30% Total Contingency 359 100% 2013 Hulett & Associates, LLC 38

Contribution of Each Risk to the Contingency (2) 100% 90% Variation:108 Variation:6 Variation:8 Variation:7 Variation:13 Variation:32 Variation:49 Variation:134 80% Graphic of the effect of taking the risks out in order of priority at the P-80 70% 60% 50% 40% C um ulative Probability 30% Variation:50 Variation:3 Variation:4 Variation:5 Variation:3 Variation:11 Variation:45 Variation:1 20% 10% 19 20 Jan 20 10 Mar 20 29 Apr 20 18 Jun 20 07 Aug 20 26 Sep 20 15 Nov 20 04 Jan 21 23 Feb 21 14 Apr 21 03 Jun 21 23 Jul 21 11 Sep 21 31 Oct 21 20 Dec 21 08 Feb 22 0% 2013 Hulett & Associates, LLC 39

Mitigating the Most Important Risk Effect of Partially Mitigating the Risk with the Highest Priority Min Most Likely Max Likelihood P 80 Date Funding from Congress is problematic 90% 105% 115% 70% 7 Apr 21 Mitigation: Mount an "educational campaign" to convince Congress of the scientific and Congressional district employment benefits to funding this project. Impact on the parameters 90% 105% 115% 30% 5 Jan 21 Mitigating the risk is estimated to reduce the probability from 70% to 30% but, if the risk happens, the impact range remains the same. This saves 92 calendar days at the P-80 target level of confidence 2013 Hulett & Associates, LLC 40

Summary (1) The focus is on the risks, not their impact Risks explain the need for a contingency Management appreciates this focus on risks Risk interviews are conducted at 5,000 foot level, where people typically think of risk Interviews go faster, stick to the substance 2013 Hulett & Associates, LLC 41

Summary (2) Use Risk Register for quantitative analysis Specific risks can be quantified and assigned to schedule activities Quantification is probability and impact A risk can affect several activities An activity can be affected by several risks Risk Factors can be combined with other more traditional approaches such as 3-point estimates for inherent variability risk, estimating error or for probabilistic branching 2013 Hulett & Associates, LLC 42