Monitoring and Controlling RCC Work in Delayed Construction Projects

Similar documents
PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Lesson 7 The Project Budget

A Study on Risk Analysis in Construction Project

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

Detailed Project Scheduling and Cost Management

PROJECT COST MANAGEMENT

PMP Exam Prep Coaching Program

Earned Value Management Guide

PROJECT MANAGEMENT BODY OF KNOWLEDGE

Application of Earned Value Management (EVM) for Effective Project Control

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

Application of Earned Value Analysis in Analysing Project Performance

EVM WITHOUT QUALITY IS UNSUITABLE FOR SOFTWARE PROJECT & PROGRAM MANAGEMENT

INSE 6230 Total Quality Project Management

Unit 5 Slide Lectures of 04/05/06 April 2017

The Cost Monitoring of Construction Projects Through Earned Value Analysis

The Four Pillars of project management

Earned Value Management. Danielle Kellogg. Hodges University

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Professional Development Seminar Series

Risk Analysis and Strategic Evaluation of Procurement Process in Construction

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE

Project Performance Evaluation By Earned Value Method

Department of Industrial Engineering

The Value of EVM. Earned Value Management

Chapter 9: Reducing Project Duration 4KF3

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

Measuring Time An earned value simulation study

PROJECT BY PROJECT MANAGEMENT T OOLS

Earned Value Management - EVM

PMI - Dallas Chapter. Sample Questions. March 22, 2002

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

Administration. Course Aim. Introductions

Connecting Earned Value to the Schedule

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Time and Cost Optimization Techniques in Construction Project Management

CPM (College of Performance Management) Meetings have focused on this topic in the last year

Reducing Project Duration

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

Monitoring System For Project Cost Control In Construction Industry

Project health monitoring by Earned Value Analysis

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Carlos Consulting Group

Optimization on Earned Value Method Combined with Critical Path

A Layman s Guide to Earned Value

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule schedule performance

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management -- Monitoring the progress

ievm (INTEGRATED EARNED VALUE MANAGEMENT) AN APPROACH FOR INTEGRATING QUALITY WITH TRADITIONAL EVM FOR EFFECTIVE PROGRAM AND PROJECT MANAGEMENT

Cumulative trends Problems and issues since last report

Earned Value Management An Overview March 2014

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

Base Line Fixing and Earned Value Analysis in Construction Industry using Primavera

Three Numbers to Measure Project Performance

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

CHAPTER 6 PROJECT CASH FLOW

MTP_Intermediate_Syl2016_June2018_Set 2 Paper 8- Cost Accounting

Presenting Earned Value

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

5-D Integrated Earned Value Analysis

A Case for Project Revenue Management. Peter Varani PMP

Project planning and creating a WBS

Factors Affecting Cost and Inflation of a Project

FRx FORECASTER FRx SOFTWARE CORPORATION

Project Assessment Exercise

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

Predicting Project Completion Date Using Earned Value Management

+44 (0) The first annual earned value conference for continental Europe

Quick Reference Card PPM Pro Project Data Field Dictionary

Software Process and Management

DISCLAIMER. The Institute of Chartered Accountants of India

Project Risk and CPI Why Should CPI = 1?

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Gate Value Method Overview document

Running head: VALUE ANALYSIS REPORTING 1

Homework 6 Questions and Answers

Self-Assessment Questions for Module 07 Project Cost Management

Project Time-Cost Trade-Off

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

Developing a Project Execution Plan on the guidelines of Pmbok for a Real Estate Project

PMP Exam Preparation Workshop Chapter 7 Project Cost Management

Indirect cost associated with project increases linearly with project duration. A typical line for indirect cost is shown in figure above.

Cost Slope Analysis 1

CHAPTER 7 PROJECT CONTROL

Critical Path and Earned Value Management

COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING

VALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke

Project Management Certification. Multiple Choice Questions

Realization on Construction management of residential apartments

MTP_Intermediate_Syl2016_June2017_Set 1 Paper 8- Cost Accounting

ECONOMICS. Time Allowed: 3 hours Maximum Marks: 100

Transcription:

Monitoring and Controlling RCC Work in Delayed Construction s Nimesh Gujarati, Dr. B S Balapgol Post Graduate Student (Construction and Management), DYPCOE, Akurdi, Pune-44, Maharashtra, India Principal, DYPCOE, Akurdi, Pune-44, Maharashtra, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - In construction sector, cost overruns and schedule delays are two most important problems which happen due to absence of well-established effective cost monitoring and controlling systems in projects. Effective monitoring and controlling systems enables project manager to monitor the actual project performance. EVM (Earn Value Management) is one of the reliable and well proved monitoring and controlling system which helps the client, project Managers and contractor to predict or Forecast the project performance. This study helps to forecast the project at periodic intervals and thereby finding the alternative solutions by applying controlling techniques to reduce the variances in the project. and - are schedule compression techniques which are used to reduce the delay of project. Key Words: Slope,,, Scheduling, Rework, Crash.. INTRODUCTION The entire life cycle of a construction project comprises of initiating phase, planning phase, execution phase, and closing phase. management means applying knowledge, skills, tools and techniques to project in order to meet owner or stakeholder s needs and expectations. management involves project managers to understand the scope of project and enables him to answer question like What will be at completion time and cost of project? Risk curve shows that, risk involved in project is higher in the early stages and it gradually decreases towards the end. performance forecast is very important for project managers to find out variances in the project.. Earned Value Management The traditional method of Monitoring differs from Earn value Management. In traditional method emphasis is given on comparison between planned and actual spending. While Earn Value Management focuses on three elements namely budgeted value of work scheduled (PV), budgeted value of work done (EV) and actual value of work done (AC). Earn Value Management proves to be one of the most important and efficient monitoring and controlling system which helps in providing accurate project forecasts. It acts as decision making tool and provides an early warning to the managers about the problems and helps in taking corrective actions. Various Earned Value Indices are used to find out project performances like (CPI), performance (SPI), Earn Value, Value,, Variance, and Variance, BAC(Budget at Completion) etc.[][]. Variance (CV): It is the difference between Earned value (EV) and the of Work Performed (AC). A positive value of Variance indicates that money spent is less than planned budget and vice-versa. CV = EV - AC () (CPI): It is the ratio of Earned Value (EV) and to the of Work Performed (AC). If ratio is greater than, project is under budget and vice-versa. CPI = EV AC () (SPI): It is the ratio of Earned Value (EV) and to the Value (PV). If the ratio is greater than, project is going ahead of schedule and viceversa. SPI = EV PV (). one of the Compression Technique that is used by many industries especially construction industries to accelerate the project progress. If the project is lagging behind the schedule, the respective delay in the project can be minimized by fast tracking the remaining project. In fast tracking we start the second of two sequential activities when first activity is approx. % complete i.e. by performing tasks in parallel. tracking is applied by rescheduling various activities within the project to be worked on simultaneously instead of waiting for each piece to be completed separately. But the fast tracking is done keeping in mind the risk associated with that activities being fast tracked. Because if the project is fast tracked without proper planning, it can cause the disruption of construction processes. In fast tracking, only normal duration of the project is reduced without changes made in number of resources needed for the particular activities. - always involves high risk that could lead to increased cost and rework at later stage. The relation between fast tracking 0, IRJET ISO 00:00 Certified Journal Page

and project predictability revealed that fast tracking has impact on project predictability in terms of unexpected outcomes which can be avoided by unrealistic goals, aggressive overlapping []. Poor handling of material can cause the loss of profit in construction firm. There is need for developing new approaches to material management in fast track construction to improve efficiency of production [4].. is also one of the important Compression Technique in which the scheduled duration is shortened for the least incremental cost by adding resources. When the crashing approach is used, any additional costs associated with rushing the project are reviewed against the possible benefits of completing the project on a faster timeline. Additional items to consider when using the crashing approach includes adding more resources for the project, allowing additional overtime, paying extra to receive delivery of critical components more quickly etc. involves activities whose cost slope value is less to shorten the project duration. Where, U i = Slope of the Activity C c = Crash of the Activity C n = Normal of the Activity T n = Normal Duration T c = Crashed Duration U i = (4) There are two type of cost involved in the project which are project direct cost and project indirect cost. direct cost includes labour cost, material cost, equipment cost and subcontractor cost. In short it is a cost that is required for a specific activity. overhead costs are called as indirect cost. It is distinguished into two, project overhead and general overhead. overhead includes cost of site utilities, supervisors, and accommodation of project staff, parking facilities, office, workshops and stores. General overheads include cost of the head office expenses, managers, directors, design engineers etc. Generally, overall indirect cost ranges between %-5% of the contract direct cost. can be applied to the critical activities only and crashing of non-critical activities will not cause any reduction in project completion time [5]. A simulation based methodology was adopted in which crashing is done in two phases: phase I involved crashing before start of project and phase II included dynamic crashing which is applied throughout the project life []. Linear programming technique was used for crashing of project by researcher [].. OBJECTIVE The primary objective of this study is to find out project performance periodically using EVM as performance measurement tool and also aims at suggesting various alternative solutions by controlling techniques to bring back the delayed project back on scheduled time.. METHODOLOGY a) First of all, each and every major activity involved in the RCC work is being listed down. b) Quantities of activities are calculated by referring drawings of the case studies. c) All the resources are noted down along with their company s rates/unit after consulting with site supervisor. d) By using standard labour output and resource constant, number of resources is being calculated for each and every quantity. e) All the above data (i.e. - quantities, resources, standard durations etc.) is fed in Primavera software and activities are linked as per their relationships with each other. f) After giving start date and after feeding all data in primavera baseline of the project is set. g) Now the actual duration or actual progress of the work is noted down by consulting with site supervisor and following their DPR (Daily Progress Report). h) is tracked for one month as per the actual progress of the work. i) After finding out the status of project at the end of month, monitoring and controlling processes are adopted to the project for the remaining part of project. j) tracking and are adopted as schedule compression techniques to bring back the project on the scheduled time. k) Depending on the risk associated with the two alternative solutions produced by and, best one is selected keeping in mind scheduled time as a constraint. l) Now the selected solution is applied to the project and again tracked for the next month and same procedure is followed as described above. 4. CASE STUDY The case study is a commercial plus residential project in Nasik city. RCC cost covers the larger portion of any project cost. Monitoring and Controlling of only RCC work is taken into consideration while carrying out this study. The project is tracked for monthly basis and solutions are proposed to minimize the delays. This study takes into considerations constraint of completing the project on scheduled time. Indirect cost is assumed to be.5% of project cost. PRIMAVERA is used for tracking the actual progress of work 0, IRJET ISO 00:00 Certified Journal Page 000

against the baseline scheduled work. - and are schedule compression techniques used to fulfill the objective of this study. Table -: Progress after uary Duration 5 04 Indirect (Rs.0/day) 5 4 Total cost 4 54 A50, A0 A40, A500 A4, A0 A50, A00 A, A0 5 0 5 55 55 54 5 400+ Rs.400 400+ Rs.000 400+ Rs.00 00+ (x0)= Rs.500 500+ (x0)= Rs.400 5 4 55 4 5 Duration 0 - Variance 0 (400) Variance 0 (04) 0 0. 0 0. Table -: - after uary Duration 5 5 04 Indirect (Rs.0/day) 5 4 Total cost 4 54 40 5 Duration 0-0 Variance 0 (400) (400) Variance 0 (04) (04) 0 0. 0. 0 0. 0. Table -4: Crashed after uary Duration Indirect (Rs.0/day) 5 5 5 04 5 4 Crash - - - 400 5 Total cost 4 54 40 4 Duration Variance Variance 0-0 0 0 (400) (400) (400) 0 (04) (04) (04) 0 0. 0. 0. 0 0. 0. 0. Table -: calculation for crashing after uary Activity Crashed till st JAN A540, A50 A0, A0 A0, A of Days Crashed Duration Normal Indirect = Duration X Rs.0 Crash Total = (N.C+ I.C + C.C) - 5 0 54 0 50 5 5 4 Rs.00 00+ Rs.00 00+ Rs.400 4 440 40 Chart -: Duration Summary after uary 0, IRJET ISO 00:00 Certified Journal Page 00

Table -5: Summary of after February No Duration Indirect (Rs.0/day) Proposed Solution after th Feb after th Feb 5 5 5 5 5 5 5 4 4 4 Crash - - - 000 5 Total cost 5 4 Duration Variance - -5 0 0 (50) (50) (50) (50) Variance (454) (45) (45) (45) Chart -: Duration Summary after March 0. 0. 0. 0. 0. 0. 0. 0. 5. RESULTS By tracking project for the month of uary, it is seen that project is days delayed. compression techniques - and are used to find out alternatives to bring back project back on scheduled time. There is restriction of completing the project on scheduled time. So keeping this in mind and increase in cost, best option is selected as a proposed solution. Similarly for the month of February and March the delay comes out to be 5 and days respectively. is again proposed solution for the month of February also. But in the month of March the delay of days has been fully minimized by crashing and it is seen that it can t be fully minimized by. So comes out to be the proposed solution after March. Chart -: Duration Summary after February Table -: Summary of after March Duration Indirect (Rs.0/day) Proposed Solution March March 5 4 5 5 0 0 0 0 545 40 4 4 Crash - - - 500 5 Total cost 45 45 00 55 Duration Variance Variance - - -5 0 (500) (500) (500) (500) (40) (0) (0) (0) 0. 0. 0. 0. 0. 0. 0. 0.. CONCLUSION By using schedule compression techniques like - and, the delayed projects can be brought back on scheduled time. While applying schedule compression techniques, - should be applied first because the increase in project cost is minimum as compared to. After that should be applied till there is no room for in the project. These solutions will act decision making tool for the higher authority or top management. Earned Value Management is one of most efficient project performance measurement tool. REFERENCES [] Management Institute (PMI), A Guide to the Management Body of Knowledge, rd ed., 004. [] Muhammad Waris. (0, November). The Monitoring of Construction through Earned 0, IRJET ISO 00:00 Certified Journal Page 00

Value Analysis. KICEM Journal of Construction Engineering and Management. [online]. pp.4-45 Available:http://dx.doi.org/./JCEPM.0..4.0 [] A. A. Alhomadi. (0). The Predictability of -Track s. Presented at The Twelfth East Asia-Pacific Conference on Structural Engineering and Construction. [online]. Available: www.elsevier.com [4] Kasim. (005, September). Improving material pratices on fasttrack construction projects. Presented at st Annual ARCOM Conference. [online]. Vol., pp. -0. Available: http://www.researchgate.net [5] Komesh Sahu. (04). & Time and also Minimum Duration Using Alternative Method. Presented at International Review of Applied Engineering Research. Vol. 5, Number 5. pp. 40-4. [online]. Available: http://www.ripublication.com/iraer.htm [] Michael E. Kuhl. (00). A Dynamic Method For Management Using Simulation-Based Optimization, Presented at Proceedings of the 00 Winter Simulation Conference. [online]. Available: http://www.ieee.com [] Omar M. Elmabrouk. (0, July). Scheduling Time using Linear Programming Technique. Presented at Proceedings of the 0 International Conference on Industrial Engineering and Operations Management. 0, IRJET ISO 00:00 Certified Journal Page 00