Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Similar documents
Standard forms of partnering contracts The ultimate contractual commitment? Part 4

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

Retention Payments in the Construction Industry: A Response from Build UK and CECA

ENGINEERING AND CONSTRUCTION CONTRACT

A Users Guide to the recast Late Payment Directive

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

JCT 2016 Edition of Contracts

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry

TERMS OF BUSINESS 1. INTRODUCTION AND DEFINITIONS

CONSTRUCTION PLANT-HIRE ASSOCIATION STANDARD TERMS AND CONDITIONS FOR A CONTRACT FOR THE LIFTING AND MOVEMENT OF GOODS INVOLVING CRANE OPERATION

Homeowner Contract (with Consultant) 2013 Edition for use in Scotland. This publication contains:

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

The New NZS 3910:2013

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

JCT/CIMAR 2016 Construction Industry Model Arbitration Rules 2016

See article 36A4 of The Financial Services and Markets Act 2000 (Regulated Activities) Order 2001, S.I. 2001/544. 2

CS ENERGY LIMITED SERVICE CONDITIONS

Conditions for the Carriage of Goods by Road

Somewhere in Time - Securing and Protecting your Contractual Rights

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Principles & guidance

Official. NHS standard sub-contract for the provision of clinical services 2017/18 and 2018/19 (full length and shorterform.

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

Code for Underwriting Agents: UK Personal Lines Claims & Complaints Handling Update (July 2018)

Response to Ofcom s consultation on price rises in fixed term contracts

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

BUILDING INFORMATION MODELLING (BIM) PROTOCOL SECOND EDITION. Standard Protocol for use in projects using Building Information Models

DOUKPSC04 Rev Feb 2013

Scottish Conditions of Appointment of an Architect SCA/2014 (Apr 2015)

Kingdom of the Netherlands

Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996

Pepper Money Terms of Business for Intermediaries

2 The Contractor s main responsibilities

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

CHAPTER 14 SPECIALIST COMPANIES

Thank you for the opportunity to provide feedback on this important piece of legislation.

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:-

Sub-consultant 2010 (2012 revision)

Code of conduct & complaints procedures

NEC4 Engineering and Construction Contract review of changes from NEC3

Miller Insurance Services (Singapore) Pte Ltd. Terms of Business Agreement ( TOBA )

Conditions of Appointment for an Architect for a Domestic Project 2010 (2012 revision) Incorporating Amendment 1, September 2011

Code for Underwriting Agents: UK Personal Lines Claims & Complaints Handling

Submission to the Consultation on the Rules and Procedures of the Tax Appeals Commission

City Policy & Procedure

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

Section 7. General Conditions of Contract for the Procurement of Works

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

Terms of Business. Our Service Having assessed your needs we will provide you with information or make a recommendation on the basis of either:-

TRUSTED TRADER. Trusted Trader terms and conditions. Contents.

Construction traps and solutions for development projects

BEGINNERS GUIDE TO YOUR GUIDE TO CREDIT INSURANCE

Claims & Compensation Policy

Contractor and subcontractor insolvency January 2010

AIRPORT AUTHORITY HONG KONG

Quality Leisure Management Ltd Terms and Conditions of Business

Authorised Officer is any officer permitted by an Appropriate Officer to authorise orders and contracts as per clause 2.5.

GLOBAL ANTI-CORRUPTION POLICY

Challenger Guaranteed Income Fund (For IDPS investors)

Ombudsman s Determination

Appendix 1. Regulatory Impact Statement Retentions in construction contracts. Agency Disclosure Statement

General Sales and Delivery Terms Version: February I. Scope, exclusion of purchase terms

Inform Practice Note #19

Approved Dispute Resolution Schemes: Minimum Compensation Cap for Insurance Disputes Discussion Document March 2015

CONDITIONS OF CONTRACT. The Builder must execute and complete the Works in a workmanlike manner and ensure the Works are adequately supervised.

Privacy Policy. Pursuant to U.S. State & Federal Laws the following is a statement of your legal rights.

PLEASE READ THESE TERMS AND CONDITIONS OF USE CAREFULLY BEFORE USING. Welcome to our website. If you continue to browse and use this website you are

INSURANCE IN SUPERANNUATION VOLUNTARY CODE OF PRACTICE

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

Client Agreement & Terms and Conditions for Business

CONSTRUCTION CLAIMS DISCLOSURE (NRS )

Conditions of Contract for PLANT and Design-Build

Example letter of engagement for audit assignment for an incorporated company Period of engagement Scope of services to be provided

NPO General Terms and Conditions for Service Contracts 2014

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

Professional Indemnity Initiative

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

LICENCE AGREEMENT. For a Holiday Home at. Old Park Wood

RULES OF THE RECKITT BENCKISER GROUP 2015 LONG TERM INCENTIVE PLAN

Employer s agent services

MODERN WORKING PRACTICES: EMPLOYMENT STATUS RULES FOR EMPLOYMENT RIGHTS AND TAX/NIC

National SMSF Conference 2013

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

We have seen and generally support the comments made by Law Society of England and Wales in its response (the Law Society Response).

CONDITIONS OF CONTRACT FOR QUOTATION

Code of Practice for Non-domestic Third Party Intermediaries and Energy Brokers. Energy Managers Association Code of Practice

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

GUIDANCE FOR PROFESSIONAL CONSULTANTS

REGULATORY Code of practice

ARM HOLDINGS PLC RULES ARM HOLDINGS PLC EMPLOYEE STOCK PURCHASE PLAN

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking

Landbay Investor Terms & Conditions

Webinar: Making the Right Choices in Government Contracting Part 3

Contract Certainty Principles and Guidance Notes

Terms of Business. For Intermediaries Trading Legg Mason Funds. Via Platforms

Standard Terms of Business

Financial Services Authority FINAL NOTICE. Mr Richard Anthony Holmes. 14 Falmouth Avenue Highams Park London E4 9QR. Individual. Dated: 1 July 2009

Transcription:

Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note

Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and when due for all work properly carried out, or products supplied, in accordance with the contract. We will ensure any withholding of payment due to defects or non-delivery is proportionate, and clearly, specifically and demonstrably justified in line with the arrangements set out in the contract. 3 2. We will not deliberately delay or unreasonably withhold payment. 4 3. For all new construction contracts we will ensure that payments are made to our supply chain not more than 45 calendar days from the end of the calendar month in which the work is carried out or products are supplied. From January 2018 that will decrease to not more than 30 days. 4. Public authorities are already required to pay within 30 calendar days. On central Government contracts, payment will be made to Tier 1 within 14 days, to Tier 2 within 19 days and to Tier 3 within 23 days of the due date, which will be 7 days after the common assessment or valuation date established by the client in the Tier 1 contract. 5. We will either not withhold cash retention or ensure that any arrangements for retention with our supply chain are no more onerous than those implemented by the client in the Tier 1 contract. Our ambition is to move to zero retentions by 2025. 6. We will issue pay less notices at the earliest opportunity and no later than 7 days prior to the final date for payment. 7. We will have processes in place to enable the effects of contract variations to be agreed promptly and fairly and payments for such variations to be included in the payment immediately following the completion of the varied works. 4 5 5 6 6 8. We will make payments electronically unless agreed otherwise. 7 9. We will use Project Bank Accounts on central Government contracts where specified by the client. 10. Where Supply Chain Finance schemes allowing members of the supply chain to secure earlier payment are offered, we will not impose fees or costs for receiving payment within the terms set out in the contract. 11. We will adopt a transparent, honest, and collaborative approach when resolving differences and disputes. 8 8 8 Signatories 9 2

Introduction Fair payment is essential for a successful construction industry with a strong and sustainable supply chain capable of meeting its clients needs and delivering the necessary infrastructure and built environment across the UK. The Construction Supply Chain Payment Charter contains 11 commitments, which Build UK members have agreed set out what best payment practice in construction looks like, including 30-day payment terms by 2018 and no retentions by 2025. Signatories to the Payment Charter are free to interpret how the 11 commitments are given effect in contractual provisions and this Build UK Guidance Note sets out how to meet the intent, as well as the letter, of the 11 commitments and what should and should not be included within a contract that truly complies with the Payment Charter. For the purposes of this Guidance Note, the term Client means the employing/paying party under the contract regardless of tier and the term Contractor means the party providing the goods and/or services and to whom payment will be made. Implementing the Payment Charter The Payment Charter applies to construction contracts as defined by the Construction Act 1, which is set out in the introduction to the 11 commitments, meaning that supply contracts are outside of the scope of the Payment Charter. However, signatories are encouraged to implement the spirit of the Payment Charter, particularly in relation to payment terms, for supply contracts as well as construction contracts. The Payment Charter has set payment terms of 45 days (reducing to 30 days from January 2018) and signatories will be expected to pay 95% of their undisputed invoices within this timeframe or show that nonpayment was due to exceptional circumstances. Standard forms of contract such as JCT and NEC generally satisfy the commitments within the Payment Charter and both produce suites of contracts for use from Tier 1 to at least Tier 3. By far the simplest way to meet most of the commitments is to use standard forms of contract throughout the supply chain with only such amendments as necessary to ensure compliance. Commitments 1. We will make correct full payment as and when due for all work properly carried out, or products supplied, in accordance with the contract. We will ensure any withholding of payment due to defects or non-delivery is proportionate, and clearly, specifically and demonstrably justified in line with the arrangements set out in the contract. This commitment is divided into two parts, both of which should be sufficiently widely worded to enable you to comply. Correct full payment as and when due for all work properly carried out seems very straightforward but is intended to prevent practices such as: Linking payment to long and/or high value milestones; or Making payment conditional on specific KPIs having been satisfied. 1 The Housing Grants Construction and Regeneration Act 1996 as amended by the Local Democracy Economic Development and Construction Act 2009. 3

You should always ensure that the payment terms in your contract are clear, fair and result in regular payments being made for the correct value of the work. In order to be confident that any withholding of payment is "proportionate, and clearly, specifically and demonstrably justified", you should look to provide the same level of justification as you would if making a claim for extra payment. This should include proving both the cause and effect to the reasonable satisfaction of the other party, including substantiating the loss. Ensure you use clear language to set out the procedure for withholding, which should include, as a minimum: The reason(s) for the withholding, including reference to the specific contract requirement(s) that have not been met, The nature of the loss or additional cost that the Client has suffered as a result, and A detailed build up to the amount deducted including substantiation. You should not include provisions that permit: Deduction of costs that have not yet been incurred, including bona fide estimates of likely future costs, Deduction of costs from monies due under other contracts between the Client and Contractor, or Withholding of payment for work on suspicion that it might be defective. 2. We will not deliberately delay or unreasonably withhold payment. It is rare for even bespoke contract provisions to expressly allow a Client to deliberately delay or unreasonably withhold payment so this commitment is more about behaviour in practice. Best practice suggests you should not include the following in your contract: Clauses to the effect that the Contractor recognises that from time to time payments may be made late and has allowed for this in his pricing Payment schedules that omit payments in certain months, typically at year end and half year end reporting dates Very low rates of interest, which could suggest an expectation of late payment and a desire to mitigate its consequences. 3. For all new construction contracts we will ensure that payments are made to our supply chain not more than 45 calendar days from the end of the calendar month in which the work is carried out or products are supplied. From January 2018 that will decrease to not more than 30 days. Bespoke contracts often include payment provisions whereby payments become Due within what appears to be a reasonable period, say 30 days, but the Final Date for Payment is then a further period of time after that, often another 30 days or more. Alternatively they provide that a payment becomes Due at the end of the month following the month in which work is carried out and the Final Date for Payment is a further period after that. Such provisions give the impression of 30-day payment but in reality it is much longer. This commitment removes any confusion by defining the longest period between performance and receipt of cash as 45 days (reducing to 30 days from January 2018) from the end of the month in which performance takes place. By way of example, for any work performed in April, payment must be received by the middle of June and, from January 2018, by the end of May. To comply with this commitment in the fairest way to all parties, valuation dates should be the last calendar day of each month. However, in practice, they are often the second or last Friday or a fixed date in each month. Whilst there is no reason why mid-month valuations cannot continue to be used, the Client will be required to pay for a portion of the work in less than 45 days in order to comply with this commitment. 4

To avoid unnecessarily elongating the timetable for payment: Do not impose unnecessary, awkward or vague requirements on the Contractor's payment applications and do not challenge their validity on technical and/or tenuous grounds The information required for a payment application to be considered should be no more than the requirement under the Construction Act, namely to state the amount the Contractor considers to be due and the basis on which it is calculated Any requirements for supporting documentation should be no more than are reasonably neccessary to allow assessment of the value of work performed and they should be built into the timetable. Is it a Construction Contract? Contracts for the supply of goods or for time-related labour or professional services are not subject to the Construction Act and are therefore out of scope of the Payment Charter. Contractors are free to invoice for their services at any time after they have provided them and it is customary for Clients to pay for such goods or services within 30/45 days of the end of the month in which the invoice is received which would be compliant with this commitment. However, if the contract imposes a minimum period after supply or an earliest date before which invoices may not be issued, it is unlikely to be compliant. 4. Public authorities are already required to pay within 30 calendar days. On central Government contracts, payment will be made to Tier 1 within 14 days, to Tier 2 within 19 days and to Tier 3 within 23 days of the due date, which will be 7 days after the common assessment or valuation date established by the client in the Tier 1 contract. This commitment applies to all parties on central Government contracts, whether they are signatories to the Payment Charter or not, as a result of The Public Contracts Regulations 2015. Over 400 central government departments and agencies have a commitment to pay at least 80% of undisputed invoices within 5 days, with the remainder paid within 30 days, and details of their performance is published every three months. The most important point about this commitment is that all the payment periods for the various Tiers are calculated from the same dates. Tier 1 contracts should include a schedule of Assessment or Valuation Dates and contracts at Tiers 2 and 3 should include the same schedule, together with a mechanism for calculating further dates if required. The NEC or JCT standard forms provide the necessary contractual tools to meet this commitment. NEC publishes Additional Public Sector Z Clauses for inclusion in central Government contracts. These clauses create a contractual obligation on the parties at all Tiers to ensure that the central Government payment timescales are passed on through the entire supply chain. JCT has introduced the concept of a common valuation date in its 2016 forms, including the Standard Building and Design and Build Contracts, which meets this commitment. 5. We will either not withhold cash retention or ensure that any arrangements for retention with our supply chain are no more onerous than those implemented by the client in the Tier 1 contract. Our ambition is to move to zero retentions by 2025. The easiest way to demonstrate compliance with this commitment between now and 2025 is for the Client to reproduce the retention arrangements from the Tier 1 contract in the contract that they enter into with their lower Tier Contractor. The Contractor can then verify at a glance that the amount of retention (if any) being held by his Client is no more than that being held at Tier 1. 5

Both JCT and NEC forms for Tier 2 contracts include requirements to reproduce particulars from the Tier 1 contract, including retention arrangements. If the standard forms are not suitable for a particular project, you could demonstrate compliance by including a simple statement to the effect that the retention percentage under this contract is less than or equal to the retention percentage being held under the contract between the Client and the Main Contractor for this Project. Obviously parties at any Tier are free to agree zero retention whether retention is being withheld from them or not. Every instance of retention removal or reduction will be a step closer to achieving the ambition of zero retentions by 2025. 6. We will issue pay less notices at the earliest opportunity and no later than 7 days prior to the final date for payment. This commitment is very simple to comply with. The Construction Act requires that all construction contracts include a prescribed period prior to the Final Date for Payment for the issue of any Pay Less Notices so the Client simply needs to state that this period will not be less than 7 days in any contracts with his Contractors. The NEC standard forms require Pay Less Notices to be issued not less than 7 days before the Final Date for Payment, so using and complying with these forms without amendment will automatically satisfy the commitment. The JCT standard forms require five days but can easily be amended to read seven days instead of five. 7. We will have processes in place to enable the effects of contract variations to be agreed promptly and fairly and payments for such variations to be included in the payment immediately following the completion of the varied works. Meeting this commitment requires cooperation and effort from both Client and Contractor. A Client cannot reasonably be expected to agree the cost and time effects of a variation until they have been explained and supported with reasonable detail but, once such information has been submitted, a Contractor should not have to wait indefinitely for it to be reviewed and agreed. Whilst what amounts to prompt and fair agreement of variations is invariably subjective, you should ideally have processes in place to cover three basic scenarios: Planned or proposed variations from the Client Reactive variations directed by the Client Variations notified by the Contractor. Planned or proposed variations from the Client will generally require a negotiation over the amount of any adjustments to cost and/or time. Where possible, agree the effects of such variations before the work is carried out so that payment can flow as the additional or varied work is performed. Both JCT and NEC provide detailed mechanisms for this process, which include the level of detail required to support the Contractor s quotation and the timescales for the Client to respond. Reactive variations directed by the Client often mean there is insufficient time to allow a full quotation, review and negotiation process to take place before the additional or varied work is begun. To help overcome this, ensure your process: Expressly permits assessment of variations on a fair and reasonable basis within the valuation period in which additional or varied work was performed Sets out an appropriate level of detail required from the Contractor to allow a reasonable, provisional assessment to be made 6

Allows for payment of at least the cost incurred by the Contractor to be made, pending agreement of the final adjustments to the contract. JCT forms require variations to be valued by the Client where prior agreement has not been achieved and these valuations are required to be included in each payment. The level of detail as to how the valuation should be done varies from one form to another but in all cases there is a requirement for it to be fair and reasonable. NEC forms do not expressly permit any payment to be made for variations (compensation events) until the variation is implemented, which is after agreement. The standard NEC process for notification and agreement of compensation events takes a minimum of five weeks and this can be as long as 10 weeks if resubmission of quotations is required. These periods are longer for lower Tier contracts. Whilst unamended NEC provisions would comply with the commitment for a fair process for agreement, it may not be considered prompt and they would not strictly meet the commitment to payment immediately following completion. Clients should improve compliance by shortening the standard periods for submitting and replying to quotations. They could also include express terms to the effect that work carried out on compensation events that have not been implemented can be included in payment assessments pending final determination. Variations notified by the Contractor require processes to determine whether or not there is agreement in principle to an entitlement to adjustments to the contract, before moving onto the issue of quantifying the effects. It is important that the issue of entitlement in principle is determined quickly to allow the process of valuation and assessment to take place within a timescale that is consistent with this commitment. This can be achieved by ensuring your processes: Require the Contractor to notify his opinion that a variation has occurred, to provide reasonable details of the factual and contractual basis for this opinion, and to provide an indication of the likely effects Expressly require the Client to notify in turn whether or not he agrees in principle that an entitlement exists. If he does, the process simply moves onto the evaluation stage, as outlined above; if he does not, the Contractor may decide whether or not to pursue the matter as a dispute (see commitment 11). You should be careful not to impose unreasonable time limits or other unnecessary, awkward or vague requirements for the provision of notices and supporting information for variations. In particular, do not deny the Contractor the right to seek redress if such deadlines are not met. Both JCT and NEC have processes that meet the necessary requirements. The NEC process requires the Client to notify his decision within one week of receipt of the notification from the Contractor, allowing the valuation stage to be dealt with in a short timescale that is consistent with this commitment. NEC also includes a further provision in relation to both agreement in principle to and evaluation of compensation events. In both cases, a failure to respond, after a further notice, results in deemed acceptance by the Client. The 2016 edition of the JCT contracts include timescales for response but at Tier 2 level this is 42 days which does not strictly comply with the requirement for payment to be included in the payment immediately following the completion of the varied works. 8. We will make payments electronically unless agreed otherwise. Most businesses are now capable of making and receiving payments electronically so this commitment should be very simple to comply with. 7

9. We will use Project Bank Accounts on central Government contracts where specified by the client. Central Government departments are required to adopt Project Bank Accounts (PBAs) unless there are compelling reasons not to do so 2, in order to provide security and certainty of payment to the supply chain. Whilst not specified within the commitment, if a Contractor is unaware of or unfamiliar with PBAs, it should be made clear where they are to be used and support should be provided to establish the facilities and help the Contractor to understand and comply with the processes. Similarly, for contracts below the Tier 1 contract, provision should be made for payments due to lower Tier contractors that are not payable by the project client. For example, a lower Tier contractor may have an agreed price for an item of work, which is higher than the price agreed between the higher Tier parties. As payment of the full amount due will never be made into the PBA, arrangements for payment of the difference need to be included. 10. Where Supply Chain Finance schemes allowing members of the supply chain to secure earlier payment are offered, we will not impose fees or costs for receiving payment within the terms set out in the contract. In practice, this commitment means that receipt of payment within the periods set out in commitment 3 (or any shorter periods agreed in a particular contract) would never result in a charge to the Contractor. If a Client has standard payment terms in excess of the periods set out in commitment 3, no charge should be made for reducing those standard terms to Payment Charter signatories under a Supply Chain Finance scheme. To ensure compliance with this commitment, expressly state in any Supply Chain Finance Scheme that charges of any kind are prohibited, except where payments are made earlier than the timescales agreed in the construction contract. Supply Chain Finance Schemes often exist alongside construction contracts and their terms (which sometimes set Final Dates for Payment at 120 days or more), not those in the construction contract, govern the definition of the period of early payment for which fees are charged. 11. We will adopt a transparent, honest, and collaborative approach when resolving differences and disputes. A common way of giving practical effect to this commitment is to include a dispute ladder in the contract, which sets out procedures and timescales for raising disputes at various levels within the organisations of the parties to the contract. This is followed by less adversarial third party solutions such as mediation with arbitration and/or litigation as solutions of last resort. This approach does not prevent or delay a party from referring a dispute to Adjudication at any time, provided the dispute has crystallised, as this is a statutory right. However, a clear process for dispute resolution by negotiation, within reasonable defined timescales, is often sufficient to avoid such escalation. Ensure dispute ladders are effective by providing for the following: The decision making to be elevated away from individuals directly involved in the disputed issues A simple procedure for dealing with the dispute, such as a written statement from each side of a reasonable but limited length Strict, short timescales, ideally aiming for a resolution within four weeks of a notification. 2 Policy Procurement Note 2/2010 8

Signatories A current list of organisations signed up to the Construction Supply Chain Payment Charter who have agreed to meet the commitments within the Payment Charter can be found on the Construction Supply Chain Payment Charter website. To apply to become a signatory to the Payment Charter, an organisation must first sign up to the Prompt Payment Code (PPC). Signatories to the PPC that operate in the construction sector will then be listed in a drop down menu on the Construction Supply Chain Payment Charter website and they will be validated before being sent a link to the online application form for the Payment Charter. To sign up to the Payment Charter, organisations will need to provide information on their standard payment terms, retentions and any Supply Chain Finance scheme they operate. To challenge the status of a signatory to the Payment Charter, organisations should complete the form on the Construction Supply Chain Payment Charter website. January 2017 9

Implementing the Construction Supply Chain Payment Charter This publication is issued by Build UK Group Limited ('Build UK') in order to give general guidance only on what it considers to be best practice; if you require guidance on a specific issue, you should seek your own independent professional advice. It is issued on the basis that, to the extent permitted by applicable law: (i) (ii) neither Build UK nor any author of any content in the publication is responsible for the results of any action taken on the basis of information in it, or for any error in or omission from it; and Build UK and the respective authors of the contents of the publication expressly disclaim all and any liability and responsibility to any person, whether a subscriber or reader of it or not, in respect of anything, and of the consequences of anything, done or omitted to be done by any such person in reliance, whether wholly or partially, upon the whole or any part of the said contents. Copyright All rights reserved. No part of this publication may be reduced in any material form (including photocopying or storing it in any medium by electronic means, and whether or not transiently or incidentally to some other use of this publication) without the written permission of the copyright owner except in accordance with the provisions of the Copyright, Designs and Patents Act 1988. Application for such permission should be addressed in writing to: Build UK Group Limited 6-8 Bonhill Street London EC2A 4BX United Kingdom Warning: The doing of an unauthorised act in relation to a copyright work may result in both a civil claim for damages and criminal prosecution. Build UK Group Limited 2017. 10