Going Green What Every College or University President Needs to Know about Renewable Energy Renewable Energy on Campus

Similar documents
Solar: Wind: Total: (AC Nameplate Rating) x (720 hrs/mo) x (0.15 = solar/ 0.10 = wind) Date(s) of Parallel Operation Rebate Expiration

STANDARD INTERCONNECTION AGREEMENT FOR TIER 1 RENEWABLE GENERATOR SYSTEMS

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR ELECTRIC GENERATING FACILITES Customer Owned Generation-Distribution Rate (Schedule G-1)

UNIQUE ATTRIBUTES OF RENEWABLE POWER PURCHASE AGREEMENTS

Create and integrate

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Corporate Renewable Energy Procurement

SOLAR POWER PURCHASE AGREEMENT

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

NET ENERGY METERING AND INTERCONNECTION AGREEMENT

Renewable Generation (Category 1-20 kw and less):

Renewable Generation (Category 1 20 kw and less):

Direct Purchasing and PPAs 101

NHEC s 2016 Residential Solar Photovoltaic Incentive Program

UPMIFA Guide for Florida Not-For-Profit Corporations August 31, 2011

Saving Money On Electricity Bills With Solar

NHEC s 2014 Residential Solar Photovoltaic Incentive Program

DISTRIBUTED GENERATION REBATE APPLICATION FORM

STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM

Illinois Shines PV System Power Purchase Agreement Disclosure Form

Project Finance An Overview

Illinois Adjustable Block Program PV System Purchase Disclosure Form

Superseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 RULE NO. 18. Net Energy Metering

IN THE MATTER OF THE BOARD S INVESTIGATION OF CAPACITY PROCUREMENT AND TRANSMISSION PLANNING BPU - Docket No. EO

Standard Interconnection Agreement for Customer-Owned Renewable Generation System

WHAT S SO SPECIAL? Mastering Special. Purpose Entities

2. IDENTITY AND LOCATION OF GC

MODEL RFI Introduction

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:

To P3 or Not to P3 By JohN Gross

Holden Municipal Light Department Interconnection Agreement for Net Metering Service

OVERTON POWER DISTRICT No North Moapa Valley Boulevard P O Box 395 Overton, Nevada

Tier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System

Feed-in Terms. (Victoria) VIC Version v1 01/13

STANDARD INTERCONNECTION AGREEMENT FOR TIER 2 RENEWABLE GENERATOR SYSTEMS

POWER PURCHASE and INTERCONNECTION AGREEMENT FOR SNAP GENERATION

PROJECT FINANCING RENEWABLE ENERGY PROJECTS

MicroFIT: An Introduction

Prototype Wind PPA Term Sheet

Standard Interconnection Agreement for Customer-Owned Renewable Generation System kw

D Los Angeles ""VV Department of

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:

Solar Services Agreement

An Assessment of Incentives for Solar Power in Washington State. Prepared by: Center for Economic and Business Research Western Washington University

Azure Power Announces Results for Fiscal Fourth Quarter 2018

South Carolina Electric & Gas Company ("SCE&G" or the "Company") hereby

Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating)

Solar Power Purchase Agreement

LEVEL 1: STANDARD APPLICATION FORM AND INTERCONNECTION AGREEMENT

CITY OF UKIAH PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR NET ENERGY METERING FROM SOLAR ELECTRIC GENERATING FACILITIES OF 1 KW (KILOWATT) TO 100 KW

How Do We Pay For It? Special Financing Mechanisms for Energy Management Projects

Re: ForeFront Power Comments on Illinois Adjustable Block Program PV System Power Purchase Agreement Disclosure Form

M&A INDEMNIFICATION SURVEY 2017 SURVEY OF KEY M&A INDEMNIFICATION DEAL TERMS

Town of Highlands Board Approved as of May 17, 2012

This Agreement will start on a meter-read date set by your EDC ( Start Date ). See Paragraph 4 for details. Section 7 for details.

PUBLIC SERVICE COMPANY OF NEW MEXICO AGREEMENT NO.

Community-Solar Utility Programs

Owner Occupied Power Purchase Agreement

Please Refer to Attached Sample Form

RENEWABLE ENERGY SOLUTIONS

INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

Making green, greener

Azure Power Announces Results for Fiscal First Quarter 2018

Electric Supply Enrollment Form

Revenue for power and utilities companies

Using Partnership Flips to Finance Renewable Energy Projects: Evaluating Tax Risks, Navigating IRS Safe Harbors

PROPERTY MANAGEMENT AGREEMENT

Sarah Riley Saving or Investing. April 17, 2017 Page 1 of 11, see disclaimer on final page

May 2003 (reprint June 2005) EVCA Governing Principles

Reading Essentials and Study Guide

Methodology for Rating Parents, Subsidiaries, and Issues

Heating Repair Program. Terms and Conditions Please read this Program carefully

Please Refer to Attached Sample Form

Steps to Success. Energy Efficiency Loans in Wales Applicant Supporting Information. Updated May 2018

Azure Power Announces Results for Fiscal Third Quarter 2017

Using Partnership Flips to Finance Renewable Energy Projects: Evaluating Tax Risks, Navigating IRS Safe Harbors

SolarCurrents Program Agreement

INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS

1. FORWARD A. Tax Equity Due Diligence Summary FINANCING STRUCTURES OVERVIEW... 6

Dear Oklahoma Electric Cooperative member:

Managing Risk in PPP Projects through Legal Documentation

Public Utility District No. 1 Of Jefferson County

Please Refer to Attached Sample Form

How Do We Pay For It? Special Financing Mechanisms for Energy Management Projects

STANDARD INTERCONNECTION AGREEMENT FOR INTERCONNECTED CUSTOMER-OWNED BATTERY SUBSYSTEMS 1 KW OR MORE

STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission

University of Missouri Retirement Plan Report from UM Retirement Plan Advisory Committee March Background

ENTERGY MISSISSIPPI, INC. STANDARD INTERCONNECTION APPLICATION AND AGREEMENT FOR NON-RESIDENTIAL NET METERING FACILITIES (for kw systems)

Six Things Every Purchaser of US Commercial Accounts Receivable Should Know

UK Solar Investment. 8% return per annum. Defined exit strategy at the end of year 3 with option to extend. Pension Compatible.

INTERCONNECTION & NET ENERGY METERING AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC GENERATING FACILITIES

MBF1223 Financial Management Prepared by Dr Khairul Anuar

Raising Equity for large biomass to power projects

MOSAIC SOLAR GREEN USE OF PROCEEDS SECURITIZED BOND

REVISED REQUEST FOR PROPOSALS SOLAR POWER PURCHASE

A. CUSTOMER INFORMATION Customer. B. PROJECT INFORMATION Project. C. CONTRACTOR INFORMATION Contractor D. INCENTIVE PAYMENT RELEASE

Transcription:

Going Green What Every College or University President Needs to Know about Renewable Energy By Lee Goodwin, Richard Cogen, and Michael Cooney Cambridge, Palo Alto, the Research Triangle... academic institutions are often defined by their geography and world-class facilities. They are also defined by their dedication to new ways of thinking. Institutional constituencies demand the highest levels of attention to environmental concerns on those campuses and facilities, and many college and university presidents have made pledges to that effect. Yet the greening of America s campuses is highly variable, with some institutions far out-stripping others in their level of innovation and commitment. While limitations on technology and financing may impede university green development, so does the lack of familiarity with available alternatives. This paper is intended for college and university presidents and their advisors as an introduction to the opportunities and challenges surrounding sustainability, and in particular the promise of renewable energy. We hope this introduction provides a context for examining various alternatives, so that institutional performance can better meet public expectations. Renewable Energy on Campus One of the most visible ways for an institution to improve its carbon footprint is through renewable energy. Some are building their own renewable energy facilities, from rooftop solar panels to biomass electric and steam generating plants. However, others seem to be reluctant to pursue these types of projects on their own, either because of capital constraints or a lack of expertise to build or maintain such a facility. Fortunately, there are other options available to institutions that want to host renewable energy projects. Increased interest in the renewable sector has spurred the growth of a variety of private companies whose business is developing renewable energy projects and selling that energy to institutional customers. Private developers have already installed rooftop and free-standing solar systems at dozens of colleges, universities, hospitals, and other institutions across the country.

Unfortunately, institutions of higher education are often at a strategic disadvantage, since private sector providers have much more experience with these types of transactions than their institutional customers, and a much better understanding of the risks involved. Once an institutional customer understands what drives the private sector, and what commercial risks they can and cannot accept, it will be in a better position to achieve its ultimate objectives. Understanding The Private Energy Services Sector In order to negotiate the best terms for implementing a renewable energy project, prospective hosts need to understand the profile, and the needs, of the private sector companies that are active in this area. These companies come in all shapes and sizes, including: Multinational equipment manufacturers and vendors. Well-capitalized renewable energy project developers with national portfolios totaling hundreds or thousands of megawatts, including utility scale power projects, as well as smaller commercial scale projects. Smaller regional project developers whose focus is on smaller commercial and even residential developments. All of these developers have one objective in common: to make each project stand on its own in terms of revenue, expense, and risk. For many developers without deep pockets of their own, this is critical so that the project can be financed on a stand-alone, project finance basis with debt and equity provided by third parties. However, even for those companies with the resources to finance a project on their own, these concepts are important since they also have to justify the investment to their investors. Project financing is actually a relatively simple concept. It requires that a project provide an income stream that will both cover its capital costs and provide the developer a return on its investment. That requires that expenses be managed and risks be allocated to others to the extent appropriate. These three needs have a direct impact on the host institution: Income Stream: Project owners are primarily concerned with a dependable income stream sufficient to cover debt service or equity returns. Most would rather be paid a fixed price per kilowatt hour (kwh) rather than a variable price that is indexed to a benchmark (such as the price of competing retail rates from the local utility), even if that means giving up some of the upside potential if the benchmark rate goes up more than expected. This can be a benefit for the purchaser too, since it means that it will have predictable long-term energy costs. Expenses: Project owners also try to minimize significant variations in expenses. For green projects with a truly renewable source, such as solar and wind, expenses are not difficult to control. However, for projects that are dependent on a fuel source, such as waste-to-energy or biomass projects, expenses may be more of an issue, particularly if the fuel source is not controlled by one of the parties or cannot be locked up in a longterm supply contract with a dependable supplier. Risk Allocation: Project owners will also try to minimize economic risks by allocating risks to third parties more capable of managing them. For example, operational risks can be managed by entering into a long-term operation and maintenance agreement, or by securing long-term equipment warranties. Many other risks can be covered by insurance. To the project owner, protecting the income stream and allocating the costs and risks of a renewable energy project to the appropriate party are critical to making the project viable.

The Power Purchase Agreement The allocation of benefits and risks from a renewable energy project is at the heart of the commercial relationship between the college, university, or other institution (the host) and the company developing the project (the developer). This relationship is embodied in the power purchase agreement (PPA) or other energy service agreement between the host and the developer. PPAs can be complex documents, but hosts should not let this complexity put them off. Most developers would be perfectly happy to sign a one-page contract that simply says that if the project produces energy, the host will buy it. Most of the complexity that has been introduced into PPAs is due to the host protections built into these documents. Some of the key points of contention in recent PPA negotiation include: Design Approval and Construction Supervision: Developers are by nature wary of granting rights to a host to second-guess design and other business decisions made in the development and operation of a project. However, colleges and universities are not like other purchasers, and they have legitimate reasons to make the development of the project an interactive process to ensure that safety, aesthetic, and other relevant considerations are taken into account during the development process. The choice of developer should be dependent, in part, on its openness to, and facility with, such a process. Once the site for a project has been selected, the host should have the right to review and approve detailed designs for the project. This is particularly important if the project will be roof-mounted, since many roofs with otherwise favorable insolation characteristics may not be structurally capable of supporting the project. One recent study in Southern California suggested that as many as 80% of the commercial rooftops studied would not be strong enough to support a solar installation. However, the PPA should also make it clear that the developer is the one responsible for the design of the project, and that the host s review does not mean that it is assuming any liability or other responsibility regarding the adequacy of the design. As part of the review process, the developer should be required to obtain warranties sufficient to guarantee that the project will operate as expected over as much of the contract life as possible. Manufacturers of solar components typically will provide warranties of up to 20 years on solar panels, and up to 10 years on other components such as inverters and racking systems. Since the developer itself may be a thinly capitalized entity, the host has an interest in the scope of these warranties, since it may have to rely on them someday in the event that the developer fails to perform. The host should also have the right to inspect the project during construction and after completion to ensure that the project has been properly installed and has not damaged the structure on which it was mounted. It may also want the right to access the system for educational purposes. Milestones and Deadlines: A PPA should include firm deadlines for commencing and completing construction of the project. It is common for developers to ask for extensions for delay in achieving a particular deadline due to force majeure delay by a third party (such as the local utility or a governmental permitting authority), or delay by the host itself. But even excused delays should have an outside deadline after which the host can terminate the PPA. Many PPAs include intermediate milestones that the developer must also meet, such as closing financing, ordering equipment, and issuing a notice to proceed to the construction contractor. Developers resist intermediate milestones because they want to preserve the opportunity to make up time later in the development process to compensate for delays in the early stages. As host, the university will find that milestones serve as a good early warning of problems down the road, and give it an opportunity to terminate a faltering relationship and move on to a more promising alternative. They are an essential element to a PPA in the university context.

Most PPAs include some sort of liquidated damages for failure to meet major milestones. Liquidated damages serve two purposes. First, they compensate the host for any economic loss that it might suffer due to the delay. This is particularly appropriate where the output of the project is being purchased at a discount. Second, they serve as an added incentive to keep the developer focused on the project. Some PPAs only impose damages if the PPA is terminated, but others include lower levels of damages that are payable even if the delay is not so long as to justify terminating the PPA altogether. Commercial Operation and Acceptance: Commercial operation should be more than just a notice that the project is ready for operation. There should be some confirmation that the project that was installed is the same as what the host contracted for. Performance testing is not always conducted on solar systems, but the developer should at least be able to produce an independent engineer s certificate that the project satisfies the PPA s requirements in terms of output capability, expected useful life, and so on. Often the same engineer who provides this certificate to the project s lenders can provide this certificate to the host as well. Output Guarantees: Most PPAs include some form of performance guarantee to assure the host that the project will actually produce what it is expected to produce. Output guarantees take two forms: performance guarantees and availability guarantees. The difference is that the performance guarantee promises that the project will produce a specified minimum amount of output during the year, whereas an availability guarantee merely guarantees that the project will be capable of operating for a minimum amount of time during the year. The main difference between the two forms of guarantee is that in giving a performance guarantee the developer takes the resource risk (i.e., for a solar project, the risk that there will be sufficient sunlight to produce a minimum amount of power), whereas the host takes that risk in the case of an availability guarantee. Assuming that the equipment has been purchased from a reputable manufacturer, and carries a longterm warranty on the equipment s output, it may be reasonable for the host to take the resource risk, particularly if that gets it a lower price under the PPA. Default and Termination: A PPA can run as long as 20 or 25 years, so it is important that the host be in a position to terminate the PPA if the developer is no longer performing satisfactorily. Triggers for default can include poor output performance or excessive maintenance outages over an extended period of time, failure to maintain licenses and permits, financial problems or bankruptcy, or actual negligence or willful misconduct on the part of the developer. In the event that the PPA is terminated following a developer default, the developer should pay damages sufficient to cover any of the host s costs or losses caused by the default, and to make the host whole for its expected savings over the life of the PPA. These can either be liquidated (i.e., a specified level of damages) or actual (the difference between the PPA price and the expected cost of replacement renewable energy as of the date of the default). If the PPA is terminated due to a developer default, the developer should also be obligated to remove the project, or pay a third party to remove it, and to restore the project site to a reasonable condition. This is particularly important if the project is roofmounted. Any removal should be closely monitored to ensure that the structural integrity of the roof is protected.

Performance Security: For financing and other reasons, developers usually place individual projects in separate special purpose companies (usually limited partnerships or limited liability companies). This is not optimal from the host s perspective, but it may be difficult for the developer to finance its project without such segregation. However, this does expose the host to risks that it might not otherwise face with respect to the project because it limits the host s options in the event of a developer default. If the special purpose company is thinly capitalized, the host may have no option but to go after the developer s assets to collect damages and removal costs. However, following a default, those assets may not have much, if any, value. Accordingly, most hosts ask the developer to post security to cover potential liquidated damages, default damages, and removal and restoration costs. Performance security can take a variety of forms. If the developer is owned by a creditworthy entity, a parental guarantee may be sufficient. However, in most cases, developers prefer to post a letter of credit from a bank or another third party as performance security. The amount of security posted varies, and can be as high as a year s projected payments under the PPA. Some PPAs also provide that the level of security will be reduced after the project has achieved commercial operation, and has demonstrated the ability to operate as expected. Termination for Convenience and System Relocation: Many hosts would like the right to terminate a PPA even in the absence of a default. Reasons for such termination may include a desire to modify or abandon the building that the project is located on, or a change in energy prices that makes the PPA uneconomical. However, because the project s equipment is not likely to have much value once it is removed from the original site, the price for terminating the PPA for convenience once the project has been completed may have to be fairly high in order for the developer to secure financing. However, termination during the development phase is a different matter. The host should have the right to terminate the PPA during development even in the absence of a default by reimbursing the developer for its actual costs, and possibly paying a breakup fee as well. This does not mean that the host cannot preserve some flexibility to respond to changed circumstances over the life of what could be a relatively long contract. Most PPAs allow the host the flexibility to require the developer to relocate the project to a comparable location in the event that its current location is no longer viable. This is particularly important if the project will be roof-mounted, since the use of buildings can change over time, and it is not at all uncommon for a campus to add improvements to a building, or to tear the building down and replace it with an improved structure. If the PPA grants the host the right to have the project relocated, the host should expect to compensate the developer for the cost of the relocation, and for any revenue lost during the relocation. If the substitute site does not have comparable sunlight (i.e., if there is overshadowing of the site for a portion of the day), the host should expect to compensate the developer for that as well. Purchase Options: Many hosts enter into PPA discussions with the objective of ultimately owning the project. For this reason, many PPAs include a purchase option that allows the host to purchase the project at some point during the life of the PPA. However, hosts should be aware that the developer s ability to offer a purchase option is often constrained by tax and financing considerations.

One of the most compelling considerations for the developer is avoiding recapture of investment credits and depreciation deductions, which are vital to the initial financing of the project. The investment credit for solar equipment is 30% of the cost of the equipment, and is one of the principal reasons why solar investments are able to compete with other, less capital intensive alternatives. However, the taxpayer who claims the credit must repay some or all of the credit if the property is disposed of during the first five years after it achieves commercial operation. For this reason, most developers will be reluctant to offer a purchase option until after the first five years of the project s operation. Since colleges and universities are almost always tax exempt, other tax considerations may also come into play. Tax incentives for what the Internal Revenue Code defines as tax-exempt use property are severely restricted. One of the ways that equipment used to provide services to a tax-exempt entity can be considered to be tax-exempt use property is if a tax-exempt entity has an option to purchase the property at a fixed price, other than fair market value. For this reason, the developer may be unable to grant the host a purchase option at anything other than fair market value, as determined at the time that the option is exercised. Regulatory Considerations: Electricity is a heavily regulated commodity, and the local utility regulations should be consulted before PPA negotiations even start. Federal law exempts sales from small and medium size renewable energy projects from federal and state rate regulation if the sale is to a utility for resale. However, federal law does not apply to retail sales (i.e., direct sales from a developer to the host or another end-user). If state law does not provide an exemption, it may not be feasible for the developer to enter into a PPA, and the host would have to purchase the project outright, or lease it from the developer. However, as indicated above, the tax incentives that help make renewable energy projects economical are significantly reduced when the project is owned by or leased to a tax-exempt entity. This has stifled a number of potential projects in states such as North Carolina that do not permit direct retail sales. For those states in which retail sales are allowed (and for others, where the host owns the project), net metering can provide a significant benefit to the host. Under net metering, the energy from the project will offset the host s retail purchases from its local utility, and when the project is producing more power than the host needs, the utility meter runs backwards, reducing the net amount of the host s electric purchases (hence, net metering ). Most states (43 at last count) have some sort of net metering program. However, there are often size, technology, and other restrictions that limit eligibility for the program, so as with retail sales in general, the host should check the local rules before starting to discuss a PPA. Renewable Energy Credits: The Renewable Energy Credit, or REC, is the attribute of renewable energy that makes it green. RECs are sometimes called by different names, such as green tags or environmental credits, but they are all essentially the same thing. Generally, one REC is the renewable attribute associated with one kilowatt-hour of renewable energy. In many markets, RECs can be separated from the power that they are associated with, and if there is a liquid market for RECs the developer may want to keep the REC and sell it. Customers for RECs include utilities that need RECs to meet statemandated renewable portfolio standards, and companies that want to be able to claim that their activities are carbon neutral. Some state net metering laws even require that the customer taking advantage of net metering turn over to the utility any RECs associated with net metered energy.

However, without the REC attached, even the most renewable energy is no different from a legal perspective from brown power produced by a coal or other fossil power plant. If the host wants to be able to use the output of a renewable energy project to support its own claim that its operations are carbon neutral, it should purchase both the power and the REC, and the PPA should be very clear that it, rather than the developer, has the right to publicly claim credit for RECs associated with the power it is purchasing. Impact on Other Agreements: Before embarking on a renewable energy project, a college or university should carefully consider how the project might impact other agreements that it may have entered into before. For example, allowing a private business to lease space on the roof of a building built with tax exempt bonds could create problems for the underlying bond financing. Similarly, any mortgages or other financing instruments that the college or university may have entered into could include covenants that either prevent long-term leases of space to a private entity, or that at least require consent before any such lease is entered into.

About Nixon Peabody At Nixon Peabody, we see 21st century law as a tool to help shape our clients futures. We are constantly thinking about what is important to our clients now and next so we can foresee obstacles and opportunities in their space and smooth the way. We work together to handle complex challenges in litigation, real estate, corporate law, intellectual property and finance anywhere in the world. For more information, please CONTACT: Lee M. Goodwin, Partner 202-585-8299 lgoodwin@nixonpeabody.com Richard M. Cogen, Partner 212-493-6639 rcogen@nixonpeabody.com Michael J. Cooney, Partner 202-585-8188 mcooney@nixonpeabody.com www.nixonpeabody.com This material may be considered advertising under certain rules of professional conduct. The content should not be construed as legal advice, and readers should not act upon information in this publication without professional counsel. Copyright 2014 Nixon Peabody LLP. All rights reserved.