CAPSTONE PROJECT. DEBM Planning Capacity for Prishtina s Current and New Government Buildings

Similar documents
Thesis/Dissertation Collections

The 2017 budget and the European Commission recommendations

United States Federal Government Workforce: Planning in an Era of Change. December 9, 2010

Executive Summary. Kosovo held on 17th November 2015, Source:

Audit based on the agreement for the project financed from funds allocated by the World Bank

REPUBLIC OF KOSOVA NATIONAL AUDIT OFFICE

Audit based on the agreement for the project financed from funds allocated by the World Bank

IMPLEMENTATION OF THE STRATEGY ON MODERNISATION OF PUBLIC ADMINISTRATION MONITORING PERIOD: OCTOBER 2015 OCTOBER 2016

Iceland s means to restrict compensation

Implementation of the Kosovo Government Capital Investment Projects

THE COUNCIL OF MINISTERS DECREED:

EEA Financial Mechanism Memorandum of Understanding Hungary MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM.

Existing Score. Proposed Score

THE NEW KOSOVO GOVERNMENT 2002 BUDGET

DECREE No 104 OF 17 MAY 2008 ON ORGANIZATION AND COORDINATION OF MANAGEMENT OF RESOURCES FROM THE FUNDS OF THE EUROPEAN UNION

AUDIT REPORT ON THE ANNUAL FINANCIAL STATEMENTS OF THE CIVIL AVIATION AUTHORITY FOR THE YEAR ENDED 31 DECEMBER 2017

PROGRESS REPORT. Preparatory Assistance National Programme for Improving Living Conditions of the Poor in Lebanon (Leb/98/004)

Business Enabling Environment Program (BEEP) Program Overview May 2011

ATTACHED TECHNICAL ASSISTANCE

Projekti Mbështetje Teknike për MASHT (FBSA) Kosovë. Technical Assistance to MEST (ESPF) Kosovo Project

ON STRATEGIC INVESTMENTS IN THE REPUBLIC OF KOSOVO. Based on Article 65 (1) of the Constitution of the Republic of Kosovo,

ASIAN DEVELOPMENT BANK

Budget Document Number /12 Output Based Budget Document

Annex 2 Template for MoU EEA Financial Mechanism

REPUBLIC OF KOSOVA OFFICE OF THE AUDITOR GENERAL

Terms of Reference for Senior Non-Key Short-Term Expert: e- Commerce Regulatory Issues

Terms of Reference for Junior Non-Key Expert on e-invoicing, e-ordering and the respective framework

IMPROVING LOCAL FINANCING SYSTEMS

Communication agenda of SECO mechanism

THE PRIME MINISTER THE SOCIALIST REPUBLIC OF VIETNAM Independence Freedom Happiness. No. 504/QD-TTg Hanoi, 21 April 2010

NAIROBI CITY COUNTY GAZETTE SUPPLEMENT

Open Call for Consulting Services Consultant for Mapping of funding opportunities for Roma integration measures, policies and programs

PUBLIC-PRIVATE PARTNERSHIP DEVELOPMENT STRATEGY FOR

CONTRACT NOTICE SERVICES Accelerated time According to Article 40 of Law No. 04/L-042 on Public Procurement in Kosovo

Western Balkans and Europe 2020 Supporting Convergence and Growth

SUMMARY OF SERVICES BY STRATEGIC PRIORITY

Development Account Project on Strengthening Capacity for Post 2015 Monitoring Third Workshop ADDIS ABABA, ETHOPIA, 14 th 18 th May, 2018

Annual Revenues from Kosovo s Value Added Tax

STRATEGIC PLANNING AT CANTONAL LEVEL STEP CLOSER TO EU: CANTON SARAJEVO EXAMPLE

Challenges Of The Indirect Management Of Eu Funds In Albania

JORDAN. Terms of Reference

Central Training TRIALOG Annual Exchange Meeting SERBIA Marija Dimitrijevic Miskovic Civic Initiatives Prague April 24-25, 2012

Administrator s Weekly Report

Roma Responsive Budgeting in Albania & Kosovo Reflections

THE REPUBLIC OF KENYA CONSOLIDATED FINANCIAL STATEMENTS MINISTRIES, DEPARTMENTS AND AGENCIES FOR THE FINANCIAL YEAR ENDED 30 TH JUNE 2016

Head 23: Ministry of Attorney

IMPORTANCE OF TAX REVENUE CONCERNING BUDGETS OF LOCAL AND REGIONAL SELF- GOVERNMENT UNITS

THEMATIC COMPILATION OF RELEVANT INFORMATION SUBMITTED BY RWANDA ARTICLE 9, PARAGRAPHS 2 AND 3 UNCAC MANAGEMENT OF PUBLIC FINANCES

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN,

2. Companies applying for Fiscal Incentives are required to complete in full:

Date of Issue: January 27, 2017 Closing Date & Time: 4:00 PM, March 3, 2017

H.B. 12, 2018.] Appropriation (2019)

Annex 2 Template for MoU Norwegian Financial Mechanism

Legal and Institutional Frameworks Supporting Accountability in Budgeting and Service Delivery Performance. Veronika Meszarits, Mostar, 4-6 Dec 2007

Fiscal transfer between different levels of governments in Vietnam

Session C Ownership and Alignment. Gender responsive Budgets in Morocco: illustration of the Paris Declaration Alignment and Ownership principles

Ontario Pension Board

Anti-Poverty in China: Minimum Livelihood Guarantee Scheme

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN,

At the latest by 31 December At the latest by 31 December 2016

Background and Introduction

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE NORWEGIAN FINANCIAL MECHANISM between THE KINGDOM OF NORWAY,

Comunity Development Fund

Technical Assistance Report

REPUBLIC OF KENYA COUNTY GOVERNMENT OF BUSIA DEPARTMENT OF FINANCE AND ECONOMIC PLANNING

FINAL REPORT EXECUTIVE SUMMARY

AUDIT REPORT ON THE ANNUAL FINANCIAL STATEMENTS OF THE MINISTRY OF AGRICULTURE, FORESTRY AND RURAL DEVELOPMENT FOR THE YEAR ENDED 31 DECEMBER 2017

International Monetary Fund Washington, D.C.

PUBLIC PROCUREMENT LEGISLATION IN KOSOVO

MEMORANDUM OF UNDERSTANDING ON THE IMPLEMENTATION OF THE EEA FINANCIAL MECHANISM between ICELAND, THE PRINCIPALITY OF LIECHTENSTEIN,

Operational Programme Regional Development

Annual Bulletin 2016 on Public Debt

UNICEF Moldova. Terms of Reference

ASIAN DEVELOPMENT BANK

National Plan Commission April 2018 Addis Ababa

APPROVED BUDGET MWANANCHI EDITION

Assignment Name: Workshop on EU Budget Support for civil servants of Macedonia Section 1. Introductory Information

SUMMARY OF SERVICES BY STRATEGIC PRIORITY

Terms of Reference. External monitoring mission for the Project Mid-Term Review

Job Description and Requirements Programme Manager State-building and Governance Job no in the EU Delegation to the Republic of Yemen

TERMS OF REFERENCE FOR INTERNATIONAL CONSULTANT

with the National Rural Support Programme (NRSP) for the Islamic Republic of Pakistan 13 November 2015 NDA Strengthening & Country Programming

Parliament of the Republic of Macedonia. Law on Balanced Regional Development

United States Federal Statistical System: Coordination, Cooperation, and Collaboration

Increasing the efficiency of revenue collection in the budget of the Republic of Kosovo

FRAMEWORK AGREEMENT BETWEEN THE SWISS FEDERAL COUNCIL AND THE GOVERNMENT OF THE CZECH REPUBLIC CONCERNING

Chart 1 Development of real GDP by quarters (year-on-year growth in %)

Reasons and Consequences of Failure to recommendations for Public Institutions by OAG

NATIONAL TEAM FOR THE ACCELERATION OF POVERTY REDUCTION (TNP2K)

JESSICA JOINT EUROPEAN SUPPORT FOR SUSTAINABLE INVESTMENT IN CITY AREAS JESSICA INSTRUMENTS FOR ENERGY EFFICIENCY IN LITHUANIA FINAL REPORT

STANDARD PROJECT FICHE

Law On Foreign Investment Promulgated

REPIM Curriculum Vitae Sharon Hanson-Cooper

INTERNAL AUDIT DIVISION REPORT 2018/014. Audit of quick-impact projects in the African Union-United Nation Hybrid Operation in Darfur

EUROPEAN COMMISSION DIRECTORATE-GENERAL HOME AFFAIRS

Financial Instruments in Energy Efficiency in Lithuania Agnė KAZLAUSKAITĖ, Ministry of Finance Junona BUMELYTĖ, EIB

1. Name of the Project 2. Necessity and Relevance of JBIC s Assistance

Each Programme is managed by EC services or executive agencies in Brussels with dedicated structures normally established at national level.

Table 1 KOSOVO GENERAL BUDGET 2006 (in Euro) Budget 2006 Reg. 2005/55. Revenue Tax Revenue

Maung Maung Win Deputy Minister Ministry of Planning and Finance Myanmar. Tokyo, Japan 6 th June, 2017

Transcription:

CAPSTONE PROJECT DEBM Planning Capacity for Prishtina s Current and New Government Buildings Mimoza KURTESHI e mail: mimoza.kurteshi@ks gov.net 1

Table of current and future of Capital Investment comparing Human Investment on DEBM 40,000,000 35,000,000 30,000,000 25,000,000 20,000,000 15,000,000 10,000,000 5,000,000 0 Past and current amount of capital investment for 2009-2010 Future amount of capital investment for 2011-2015 Total yearly sum for 51 employees Total sum for 25 new additional professionals for 2011-2015 2

Table of current and future investment on DEBM 40,000,000 35,000,000 30,000,000 25,000,000 20,000,000 15,000,000 10,000,000 Table of Capital Investment 1,200,000 1,150,000 1,100,000 1,050,000 1,000,000 950,000 Table of Human Investment 5,000,000 900,000 0 Past and current amount of capital investment for 2009-2010 Future amount of capital investment for 2011-2015 850,000 Total yearly sum for 51 employees Total sum for 25 new additional professionals for 2011-2015 3

The aim of the Capstone Project This capstone project assesses the restructuring of the Department of Engineering and Building Management (DEBM). Serious capacities shortages and delays on implementation of projects in DEBM. The technical issues have been considered with the mission of the DEBM. 4

Background Development of DEBM DEBM were created since 2001 and is one of the oldest department on MPA. DEBM is responsible for performing engineering services and management of buildings for all Kosova s Government buildings and as well for their maintenances, too. The mission of the DEBM is to find and accommodate all government staff on their buildings, creating better working conditions, maintaining building infrastructure and in the same time planning for new project. 5

Current DEBM function DEBM actually is functioning from two divisions: a. Division of Engineering Services b. Division of Building Management 100 80 60 40 20 Engineering Division Mantaining Division Planing 0 2001 2002 2003 2004 2005 2006 2007 2008 2009 Chart it shows development and coordination of engineering divisions though years. 6

Reformation and Organization of MPA In order to achieve its strategic objectives, the Ministry should address current capacity gaps. Reviewing FRIDOM's functioning has identified a number of measures to achieve this. These measures are set during an intense process of consultations within the responsibility of the Ministry and other stakeholders of interest for changes that should be undertaken. *FRIDOM Functional Review and Institutional Design of Ministries is a DFID funded project. 7

Reformation and Organization of MPA Base for Capstone Will be independent agency Department will be transferred on MTI 8

DEBM New Initiatives The new structure of DEBM will be based on necessity of implementing policies and restructuring of management. Proposed new Division 9

Future structure of DEBM The future structure of DEBM will be based on FRIDOM recommendation of implementing policies and restructuring of management. In this context, FRIDOM proposed new structure for better and easy management of state properties through division of planning and real estate. The main tasks relating to the management of this real estate in the coming mid term period include: 10

Future structure of DEBM Centralization of the management of real estate by the establishment of a public fund as a special publicbodyfortheimplementationofexperttasks in this field; Uniform management and disposition of stateowned real estate; Establishment and managing of central records of the real estate owned by the Republic of Kosova; Management of the internal market of state owned real estate. 11

Future structure of DEBM Future organogram of DEBM 12

DEBM Past Projects 2008 2009 MPA/DEBM has developed operational plans and concrete plans of action and long term capital investments in the infrastructure space for permanent residential accommodation for permanent public administration. DEBM projects from 2008 start with two, actually three projects on the center of the city: Ministry of Science and Technology together with Academy of Science Constitutional Court of Kosova. 13

Complex of New Buildings For Academy Of Science And Arts And Ministry of Science And Technology In this complex of 14000m² are accommodated 250 staff members of the Ministry of Technology and Science and 30 staff members of Academy of Science. Completion of project was the end of 2009. 14

Constitutional Court The building was designed and renovated according to the standards for designing and constructing such facilities. Building is provides working and accommodation space for local and supporting staff around 50 officials. 15

Current Projects 2010 present To start the engineering projects is necessary to have a concept and definition for the project. Template design The general engineering template represents the steps and relationships required to scope, evaluate and design millions of capital as project cost. Template organization Conceptual phase Definition phase Design phase 16

Current Projects 2010 present Preparing Project for New Building Of Ministry of Security Forces Modern building will provide working space for 300 officials, local and international staff. Total area of the facility that is needed is about 6000m². 17

Current Projects 2010 present Preparing Project for New Building of Kosovo Agency of Intelligence Modern building will provide working space for 250 officials local and international staff. Total area of the facility that is needed is about 5000m². 18

Current Projects 2010 present Preparing Project for New Protocol Center, Blinaja" Complex Modern buildings will provide working and relaxing space for 200 officials local and international staff. Total area of the facility that is needed is about 5800m². 19

Future Projects 2010 2015 Based on urban strategic plan and needs for permanent accommodation, government has two options to implement the government movements: First option is the New Compound of Government Building is planned on Ajvalia area. Second option is on the Center of the city. 20

General & detail map of Strategic Development Plan for Prishtina City 21

Future Projects 2010 2015 Ajvalia Complex Propose of new governmental complex presents the basic design idea of permanent solution for accommodation of governmental staff of the Republic of Kosovo. The possibility for accommodation is around 3200 employees. New governmental Complex Ajvali 22

Future Projects 2010 2015 Rilindja & EULEX complex The location for the proposal of accommodation on center for movement of government building is the best choice because in itself has its own parameters that can be used especially with residential neighborhoods and it will be met with relevant social infrastructure 23

Future Projects 2010 2015 Rilindja Complex for annex B & C and New annex D 1. Annex A 18.000m² newly refurbished tower 2. Annex B 32,850m² refurbishment of printing house 3. Annex C 4,000 m² refurbishment 4. Annex D 10,000m² new constructed tower. B&D C A 24

Future Projects 2010 2015 "EULEX Complex with Annexes Complex Capacity accommodation for about 620 employees with Head Quarter 3600m² East wing 3800m². Annex build. 720m² Creating the infrastructure backbone Central Government Complex currently is used by EULEX 25

Finance on the Project Governmental capital investment for 2009 2010 Finance Tables of budget allocated for capital budget for governmental ministries 1 M. of Finance and Economy 34,38mil. 2 M. of Public Administration 6,02mil. 3 M. of Agriculture 2,52mil. 4 M. of Trade and Industry 6,27mil. 250,000,000.00 200,000,000.00 150,000,000.00 5 M. Transport &Telecom. 192,25mil. 6 M. of Health 9,18mil. 7 M. of Culture 5,68mil. 8 Ministry of Education 27,50mil. 9 M. of Social Welfare 2,59mil. 10 M. of Planning 10,00mil. 11 M. of Communities 6,84mil. 12 M. of Local Government 7,62mil. 13 M. of Energy and Mining 0.80mil. 14 M. of Internal affairs 16,77mil. 15 M. of Justice 4,19mil. 16 Ministry of Foreign Affairs 2,16mil. 17 M. of Security Force 11,24mil. 100,000,000.00 50,000,000.00 0.00 26 M. of Finance and Economy M. of Public Administration M. of Agriculture M. of Trade and Industry M. Transport &Telecom. M. of Health M. of Culture Ministry of Education M. of Labor and Social M. of Planning &Environment M. of communities and M. of Local Government M. of Energy and Mining M. of Internal affairs M. of Justice Ministry of Foreign Affairs M. of Security Force

Finance on the Project MPA budget Budget that is spend for 2010 for MPA (capital investment) 3,500,000.00 3,000,000.00 2,500,000.00 1 IT Department 722,871.00 2 Engineering Department 3,055,744.00 3 Administration Department 61,590.00 2,000,000.00 1,500,000.00 1,000,000.00 500,000.00 0.00 4 Civil Department 26,600.00 5 Statistical Agency 250,717.00 6 Reform Department 1,440,000.00 27

Finance on the Project Human Investment Program of DEBM Currently DEBM is enrolled by 51 employees who from them are 16 professionals (engineers) and 35 supporting staff. Table that shows monthly payment that is needed for current DEBM staff Nr Name Number of staff Payment / Quantity / Implementation 1 Professional staff 16 13,500.00 2001 2 Supporting staff 35 13,500.00 2001 Total 51 27,000.00 28

Finance on the Project Future Human Investment Program of DEBM Table illustrate amount of budget will be used for 25 additional professional staff in context that this investment necessary and can be more efficient on the implementation of projects. Shows total necessary cost on human and equipment investment for next three years Total for payment/salary 784,800.00 Total for facility 144,000.00 Total for the maintain cars 16,200.00 Total amount for maintaining the building 54,000.00 Total amount for training staff 75,000.00 Total amount for equipment 96,400.00 TOTAL 1,170,400.00 29

Finance on the Project Investment Program of DEBM 18,000,000.00 16,000,000.00 14,000,000.00 12,000,000.00 10,000,000.00 8,000,000.00 6,000,000.00 4,000,000.00 2,000,000.00 0.00 Renovation of annex B & C Building of annex D EULEX -complex MFSK KIA Protocol Center "Blinaja 30

Finance on the Project Options of Investment Program of DEBM Option # 1 Option # 2 40,000,000 12,000,000 35,000,000 30,000,000 10,000,000 25,000,000 8,000,000 20,000,000 6,000,000 15,000,000 10,000,000 4,000,000 5,000,000 2,000,000 0 Future amount of capital investment for 2011-2015 Total sum for 25 new additional professionals for 2011-2015 0 Future amount of capital investment for 2011 2015 Total sum for 25 new additional professionals for 2011 2015 31

Recommendation Better utilization of existing sites of buildings at the center of the city. Use the existing infrastructure in the center of the city Decentralization or gradual trade maintenance Need to restructure and recruit more professional staff for DEBM. Investment on professional staff it will not impact DEBM budget, comparing with total capital investment. Complete and approve strategic document for public policies and real estate. Divisions that will be responsible for state properties and maintenance 32

Recommendation Effectives Implementation on the Law for Investments. DEBM should strengthen its capacities regarding public procurement for important and major investments Specified prioritization procedures in selecting projects. It is recommended to the government and ministries to be more specific on their priorities and requests Prescribe and detail maintenance of projects. DEBM should monitor and maintain project implementation special BMS must be managed by professionals. Developing of training program. To increase a good quality performance of professionalism, development of training programs are necessary. 33

CAPSTONE PROJECT DEBM Planning Capacity for Pristina's Current and New Government Buildings Comment s or questions! 34