INFRASTRUCTURE DIALOGUE ELECTRICITY DISTRIBUTION INDUSTRY INFRASTRUCTURE PERSPECTIVE

Similar documents
Dr Willem J. De Beer, Chief Operations Officer, EDI Holdings (Pty) Ltd, South Africa 23November 2010

POST-CABINET MEDIA BRIEFING

Public Hearing Presenter: D Matsheketsheke Designation: CFO (act) Date: 9 June 2011

Portfolio Committee on Energy

Terms of Reference Development of the City of Tshwane Sustainability Financing Mechanism Strategy

Compliance Monitor Register of Projects

Eskom Presentation Standing Committee on Appropriations

ESKOM s applications for MYPD4 and MYPD3 RCA 2017/18

EDI RESTRUCTURING AMEU 59th CONVENTION POLOKWANE SOUTH AFRICA 28 SEPTEMBER 2005

GUIDE TO THE URBAN DEVELOPMENT ZONE TAX INCENTIVE

EDI HOLDINGS ANNUAL REPORT (2009/10)

DESIGN OF ESKOM DISTRIBUTION SERVICE INCENTIVE SCHEME FOR MYPD2 (2010/ /13) (IDMS no: 47217v1)

Latest Developments on REDs. Presentation to Middle Management

PROVISION OF BULK MUNICIPAL INFRASTRUCTURE BY DEVELOPERS A MODEL THAT WORKS

LABOUR MARKET PROVINCIAL 51.6 % 48.4 % Unemployed Discouraged work-seekers % 71.8 % QUARTERLY DATA SERIES

LABOUR MARKET PROVINCIAL 54.3 % 45.7 % Unemployed Discouraged work-seekers % 71.4 % QUARTERLY DATA SERIES

(011) (fax) Department:

The South African Grid Code. Transmission Tariff Code. Version 9.0

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA

MUNICIPAL KEY HIGHLIGHTS DATA ANALYSIS

Buffalo City Metropolitan Municipality Presentation to the Select Committee on Finance

URBAN RENEWAL TAX INCENTIVE

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA

Electricity blackouts in South Africa: proximate and ultimate causes & recommendations for the future

SWARTLAND MUNICIPALITY

Submission to SALGA and National Treasury

PROGRESS WITH THE NATIONAL INFRASTRUCTURE MAINTENANCE STRATEGY

Cover slide (same as IR cover)

MUNENE RISK SERVICES. Company

A Checklist on the Fitness for Municipal Pooled Financing

Group Interim results for the six months ended 30 September Cover slide (same as IR cover)

Considerations in City Economic Development Strategy

Municipal Infrastructure Grant Baseline Study

Investor Open Day. Wednesday, 9 th April 2014

Residential Property Indices. Date Published: August 2016

Regional and Local Governments (RLGs) Moody s Approach

Urban Settlements Development Grant

A Municipal Entity of the Nelson Mandela Bay Municipality ADJUSTMENTS BUDGET REPORT

Performance of Municipalities in 2015

ESKOM S FINANCIAL CRISES AND CONTINUING TARIFF INCREASES

Brochure on Eskom s Policy for granting the benefit of diversity. July 2013

HOSPITALITY SECTOR MINIMUM WAGES AS FROM 1 JULY 2017 TABLE 1:

Residential Property Indices. Date Published: August 2018

ESKOM One Year Application 2018/19

ABSA Bank and JSE Showcase. 11 April 2013

Residential Property Indices. Date Published: September 2018

Why the Regional Electricity Distributors (REDs) concept is bad for Cape Town

Income Tax Guide to the Urban Development Zone (UDZ) Allowance

As presented at the Institute of Municipal Engineering of South Africa (IMESA) conference 2013

Residential Property Indices. Date Published: July 2018

Residential Property Indices. Date Published: October 2018

Cover slide (same as IR cover)

Eskom 2018/19 Revenue Application

Residential Property Indices. Date Published: 30 June 2014

Investor Presentation. Cover slide (same as IR cover)

CLIMATE FINANCE OPPORTUNITIES FOR ENHANCED LOCAL ACTION

Creating value in Private Equity

Information Disclosure by Aurora Energy Ltd for the year ended 31 March 2008

MYPD 3 (Year 2013/14) Regulatory Clearing Account Submission to NERSA

CITIZENS GUIDE TO THE STATE OF CITY FINANCES 2015

Information Disclosure prepared according to subpart 3 of Part 4A of the Commerce Act 1986

CAMDEBOO MUNICIPALITY

MYPD 3 (Year 2014/15) Regulatory Clearing Account Submission to NERSA

The political-economy of power sector reform in South Africa. Prof Anton Eberhard

Is the South African Government s Growth Target of 6% by 2014 in Jeopardy?

SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017

Eskom RCA: Revenue Application NERSA Public Hearing. City Power Presentation Frank Hinda 11 May 2018

Evaluating the performance of Development Charges in financing municipal infrastructure investment. Discussion Paper. Second Draft 23 March 2009

Inaugural Gauteng Infrastructure Investment Conference

Residential Property Indices. Date Published: February 2018

Tariff Review Application 2017/18. Submitted to LEWA Board of Directors. Corporate Planning 1/3/17 Lesotho Electricity Company

YPD 3: Regulatory Clearing Account Submission to NERSA

Electricity theft and non-payment: Impact and action plan. by Chris Yelland CEng Managing editor EE Publishers

University of Pretoria Department of Economics Working Paper Series

Taking accountability to improve audit outcomes

AMEU Convention Tuesday 28 SEPTEMBER 2010 Stellenbosch

PRESENTATION TO NERSA BY Mr WH BOSHOFF

ESKOM S DEMAND EXEMPTION POLICY. This document may be updated from time to time, please refer to for the latest version.

Corporate profile. Strong foundations Positive momentum. years being listed as Dexus

Presentation of the TCTA Strategy for 2012 to 2013

ESKOM RCA Applications 2015/ / /18

CONSTRUCTION MONITOR Transformation Q4 2014

LINKING POPULATION DYNAMICS TO MUNICIPAL REVENUE ALLOCATION IN SOUTH AFRICAN CITIES

ESKOM S CONNECTION CHARGES METHODOLOGY

MFMA. Audit outcomes of municipalities

cidb development through partnership August 2008 Update on the National Infrastructure Maintenance Strategy (NIMS)

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED MYT Petition, True-up Petition Formats - Transmission

Millions of Euros. The GROSS OPERATING PROFIT (EBITDA) for 2000 totals Ptas. 41,545 million, which is 5.7% higher than in the prior year.

SUBMISSION DOCUMENT EXECUTIVE SUMMARY

Accelerated and Shared Growth Initiative South Africa

Optimising Revenue with Data Insights 1

ANNEXURE 1. Consultation Paper

Eskom group annual results for the year ended 31 March 2018

MYPD3 Application January 2013

FY2017/18, Year 5 of MYPD 3 Period

National Treasury. Modelling the infrastructure investment needs in South African metros: 2016 to FINAL version

Information Disclosure

2014 Appropriation Bill

Quarterly Labour Force Survey

Annual Salaries Report

Transcription:

INFRASTRUCTURE DIALOGUE ELECTRICITY DISTRIBUTION INDUSTRY INFRASTRUCTURE PERSPECTIVE PRESENTED BY DR WILLIE DE BEER 12 MAY 2011

Presentation Context Electricity Distribution Industry (EDI) Introduction Assessment of Asset Condition & Performance Investment Requirement Conclusion Recommendations/Discussion Considerations

ELECTRICITY DISTRIBUTION INDUSTRY INTRODUCTION

Electricity Supply Chain POWER STATIONS GENERATION Transmission Lines TRANSMISSION SUBSTATION ELECTRICITY DISTRIBUTION INDUSTRY (EDI) Reticulation Lines TRANSMISSION (765/400/275 kv) DISTRIBUTION (132/88/66/44/33 kv) Distribution Lines SERVICE CONNECTION Reticulation LV Lines 380/220V Reticulation HV Lines 22 and 11kV DISTRIBUTION SUBSTATION

EDI Profile Revenue : R40 bn Customers : ~9.2 m Staff : ~31 000 Replacement Asset Value (2008) : ~R260 bn Energy Purchases (ESI 2008) : ~224 TWh Distribution Lines : >400 000 km Distribution Cables : >217 000 km Transformers : ~ 366 584 2008 Figures

Electricity Distribution Industry Introduction The electricity distribution industry (EDI) plays a significant role in the economic growth and development of any country; The EDI is an asset centric business; For sustainability, the EDI is directly dependant on the infrastructure performance, the ability to serve the customers effectively and to collect the revenue associated with the products and services delivered.

ASSESSMENT OF ASSET CONDITION & PERFORMANCE

EDI Asset & Performance Assessment Various summits and reports were produced: 2003 Maintenance Summit; 2004 & 2008 Follow up Maintenance Summit; 2006 NERSA Audit Reports (11 Electricity Distributors); 2008 UBS Investment Research Report 2008 EDI Holdings: Approach to Distribution Asset Management (ADAM) Report; 2006 to 2010 EDI Holdings Ringfencing Reports (56 Electricity Distributors); 2010 Eskom Identified 1000 constraint feeders. NOTE: Latest NERSA electricity distributor audit results not released

Some Key EDI Insights ( 1) The EDI is currently generating revenue however the business model is not sustainable; In general the current practices in the EDI do not guarantee business sustainability and economic growth; The Electricity Distribution Industry (EDI) in South Africa is currently experiencing significant challenges as a result of amongst others; Under investment in asset maintenance Lack of refurbishment investment Under performing industry Shortage of skills To effectively manage the future maintenance and refurbishment requirement, an estimated additional R2.5bn per annum will be required (2008); The maintenance, refurbishment & strengthening backlog is estimated at R27.4bn (2008); While there are pockets of good performance; to avoid a collapse of the EDI it is essential for an urgent structured intervention;

Some Key EDI Insights ( 2) The pockets of good performance are decreasing; The increased operation of under maintained plant is a recipe for disaster; Maintenance plans and implementation thereof is not evident in most municipalities electricity departments; Maintenance investment is not consistent or in line with NERSA recommendations; Capital investment plans are not clearly defined on a consistent basis; Average capital investment is < 5% of actual revenue from electricity in a large percentage of municipalities; In terms of electricity, municipalities achieved approximately 47% of their total electricity budgeted capital investment; Demand growth exceeds the loading capacity of the networks which will amongst others pose a significant risk to the effective introduction of Energy Efficiency Strategies; Recruitment, training and retention of skills are significant EDI sustainability risks.

Manage Availability of Supply (Sample of Distributors) Municipality # 3 # 5 # 11 # 14 # 19 No. of Outages (Monthly) 0 (Planned) 20 (Unplanned) 20 (Planned) 30 (Unplanned) 6 (Planned) 6 (Unplanned) 8 (Planned) 150 (Unplanned) 1 (Planned) 3 (Unplanned) Average Downtime per Outage 3 hrs to 1 week Planned < 8 hours Unplanned < 1 hour 6 48 hours Not available ½ hour # 21 2 1 Hour # 22 Not available Not available # 23 Source: EDI Holdings Ringfencing Insights 1 (Planned) 2 (Unplanned) 2-3 Hours Key Points From research conducted, unplanned outages mainly occur due to assets not being well maintained and lack of capacity to perform preventative maintenance; A policy of reactive maintenance is adopted in many cases (rather then preventative maintenance) as planned maintenance does not exist in most municipalities; Skills shortage and key resource vacancies is a key driver of outages; Maintenance plans do not exist in over 50% of the municipalities researched; Data available challenges; Limited system driven management information available. Slide 11

Debtors Days and Bad Debt Challenges D eb to rs Days 160 140 120 100 80 60 40 20 - Cape Town George Ekurhulen i NMBM M Buffalo City City Power Tlokwe ethekwini Msunduzi Tshwan e Wt.Average 07/08 08/09 Debtors Days - significant variation between the various municipal distributors. Notable increase for one specific munic of 27 days (07/08) to 142 days (08/09) - could be the result of a decision not to prosecute customers in arrears. Average Debtor Days: 74 Days Bad Debt / Debt Written O ff (R m illion) 300 250 200 150 100 50 - -50-100 Cape Town George Ekurhuleni NMBM M Buffalo City City Power Tlokwe ethekwini Msunduzi Tshwane Wt. Average 07/08 08/09 Bad Debt - significant increase in bad debt (for municipal distributors that disclosed relevant information). The weighted average bad debt increased by 74% from R61m (07/08) to R107m (08/09). Total bad debt has risen 93% from R311m (07/08) to R600m (08/09). Source: EDI Holdings 2010 Survey

Technical & Non Technical Losses Management ENTITY TECHNICAL (R bn) NON TECHNICAL (R bn) TOTAL (R bn) Eskom Dx 1.444 2.404 3.848 Municipalities 0.856 4.082 4.938 TOTAL 2.3 6.486 8.786 Source: EDI Holdings

Summary of Key Challenges Management and Leadership; Effective management of revenue cycle; Reduce technical and non technical losses; R27,4 billion (2008) Maintenance, Refurbishment and Strengthening backlog; R2,5 billion backlog growth per annum; 35% average vacancy rate; Skills recruitment, retention and development.

INVESTMENT REQUIREMENT (ADAM as Reference)

Approach to Distribution Asset Management (ADAM) ADAM focus on a holistic approach to distribution asset management; maintenance, refurbishment and strengthening requirements, to ensure network reliability, a sustainable industry and an ability to support the required economic growth from an electricity distribution capacity perspective; ADAM is a holistic Asset Management initiative, centrally driven and locally executed, which will follow a parallel phased approach, governed by strict programme and project management practices; ADAM s immediate priority will be the NERSA audited entities and short term projects indentified; ADAM will address the existing skills shortage through: Complementing existing resources in the industry with external expertise; Identifying skilled resources that left the industry, and enticing them back; Focusing on sustainable skills transfer and capacity building during execution; Run in parallel to the normal daily operations of the utilities. Source: EDI Holdings ADAM Report

Investment Requirement per Region Total Backlog Maintenance Refurbishment Short term Strengthening Total R 27,369,146,995 R 2,736,914,699 R 8,210,744,098 R 16,421,488,197 Note: The Local Government Budget and Expenditure review 2003/04 to 2009/10 by National Treasury reveals that the capital expenditure on electricity as a percentage of total capital expenditure is decreasing in real terms by R400m per annum and that the available, capital budget would not be sufficient to cater for growth and the identified backlog.

National Picture: EDI Infrastructure Investment Backlog by RED region Entity Total Backlog Maintenance Refurbishment Short term Strengthening RED ONE (City of Cape Town) RED TWO (Ekurhuleni) RED THREE (Nelson Mandela Bay) RED FOUR (City of Johannesburg) RED FIVE (ethekwini) RED SIX (Tshwane) R 3,851,578,245 R 385,157,825 R 1,155,473,474 R 2,310,946,947 R 5,132,373,764 R 513,237,376 R 1,539,712,129 R 3,079,424,259 R 2,186,296,025 R 218,629,602 R 655,888,807 R 1,311,777,615 R 6,413,148,398 R 641,314,840 R 1,923,944,519 R 3,847,889,039 R 4,158,350,649 R 415,835,065 R 1,247,505,195 R 2,495,010,389 R 5,627,399,914 R 562,739,991 R 1,688,219,974 R 3,376,439,948 TOTAL R 27,369,146,995 R 2,736,914,699 R 8,210,744,098 R 16,421,488,197

Indicative Current Investment per Financial Year Entity Name TOTAL Current Municipal Allocation Current Allocation Towards Routine Maintenance Current Allocation Towards Backlog Backlog Requirement Shortfall per Financial Year Rustenburg R 54,000,000 R 43,200,000 R 10 800 000 R 69,375,000 R 58,575,000 Polokwane R 120,000,000 R 96,000,000 R 24 000 000 R 129,079,000 R 105,079,000 Ekurhuleni R 370,000,000 R 296,000,000 R 74 000 000 R 542,096,000 R 468,096,000 Emfuleni R 47,000,000 R 37,600,000 R 9 400 000 R 219,147,000 R 209,747,000 Nelson Mandela Bay R 43,000,000 R 34,400,000 R 8 600 000 R 244,292,000 R 235,692,000 Umsunduzi R 63,500,000 R 50,800,000 R 12 700 000 R 210,079,000 R 197,379,000 Mbombela R 27,200,000 R 21,760,000 R 5 440 000 R 102,196,000 R 96,756,000 ethekwini R 735,000,000 R 620,000,000 R 115,000,000 R 173,000,000 R 58,000,000 Mangaung R 174,000,000 R 167,724,000 R 6,276,000 R 113,867,000 R 107,591,000 City of Jo burg R 1,305,000,000 R 1,237,500,000 R 67,500,000 R 390,355,000 R 322,855,000 City of Tshwane R 640,000,000 R 544,000,000 R 96,000,000 R 199,815,000 R 103,815,000 City of Cape Town R 711,000,000 R 606,000,000 R 105,000,000 R 184,860,000 R 79,860,000 2008 Data

Conclusion 1 The infrastructure challenges in the electricity distribution industry are real; The backlog figure is not static and the longer it takes to address it the bigger the backlog will become and equally the need for funding and competent resources to address the backlog will increase; The EDI asset turnaround programme must be rolled out to stabilise the EDI, but the biggest challenges remain the funding and skills recruitment; While a 5 year execution period is ideal, given the current capital programmes and skills shortage in the industry, this would not be achievable, hence a 10 year plan is proposed; The successful execution of an asset turnaround programme will call for dedicated resources and very tight programme management;

Conclusion 2 The EDI asset turnaround programme presents a significant skills transfer and job creation opportunity and therefore it is important to establish the necessary mechanism, inclusive of trainers, to ensure effective skills transfer during the EDI asset turnaround programme roll-out; The EDI asset turnaround programme is also a unique national opportunity for a focused long term technical skills development programme across the full engineering spectrum i.e. construction staff, artisans, technicians, technologists, certificated engineers, engineers and training institutions; The EDI asset turnaround programme will fail in its overall objective if it had to recruit resources currently deployed in the industry, to execute the projects associated with the EDI asset turnaround programme programme; It is essential that the appropriate resource allocation and infrastructure required to execute this programme be agreed to upfront and be allocated before the EDI asset turnaround programme is rolled out.

Recommendations/Discussion Considerations Implement ADAM as a centrally driven holistic (10 year project with a 20 year funding plan) National Priority to deal with the infrastructure maintenance, refurbishment and strengthening backlog; Investigated ADAM funding options and make funding available through a central mechanism; Leverage, harness and utilise the skills, expertise and experience gathered during the EDI restructuring process as well as the stakeholder relations and structures developed to resolve the EDI challenges and improve service delivery, especially amongst municipalities; Introduce, through NERSA and National Treasury, tighter regulation and compliance of the electricity distribution entities, inclusive of investment in assets and skills development; Enforce ringfencing of the electricity businesses and accountability through NERSA, CoGTA and the National Treasury. Note: ADAM Report was presented to ASGISA, IDTT on Energy, CoGTA Tech MINMEC, NERSA and various industry stakeholders

THANK YOU