ESTABLISHING THE EFFICACY OF THE JBCC CONSTRUCTION AND PAYMENT GUARANTEES

Similar documents
LIEN RIGHTS IN SOUTH AFRICA. Authors: Sean Vianello and Gaye le Roux

PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS PRACTITIONER, AND ARCHITECTURAL SERVICE TO THE CLIENT

Inform Practice Note #19

Inform Practice Note #16

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

MDB Harmonised Particular Conditions

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of

Standard Terms & Conditions of Trade

The 2014 JBCC suite of documents: a legal contract, risk and administration tool

CHAPTER 1 25 INTRODUCTION

GCC: The GCC 2015 (3 rd Edition) Welcomed with Open Arms

Conditions of Contract for PLANT and Design-Build

RESULTS OF THE 2010 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MAY Prepared by: Dr HJ Marx

The Extent of Enforcement of The Penalty Clause on Public Sector Construction Contracts in South Africa

STANDARD PROFESSIONAL SERVICES CONTRACT. July, 2009: Edition 3 of CIDB document 1015

Danida Business Finance. Rules for Procurement

Sedna Standard Terms and Conditions

Trade Credit Insurance Policy Wording Page 1

April 2018 NATIONAL WESTMINSTER BANK PLC AS CASH MANAGER ULSTER BANK IRELAND DAC AS SELLER AND SERVICER

RESULTS OF THE 2011 SURVEY OF THE. cidb CONSTRUCTION INDUSTRY INDICATORS MARCH Prepared by: Prof. HJ Marx

AGREEMENT: ACCEPTANCE OF QUOTATION TERMS AND CONDITIONS

JSE LIMITED PROPOSED INCENTIVE SCHEME FOR THE RETENTION OF BLACK SHAREHOLDERS

DOUKPSC04 Rev Feb 2013

CESSION OF BOOK DEBTS

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT

INSTITUTIONAL CONTRACT (CONTRACT AMOUNT LESS THAN $30,000) Contract No.:

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND


STANDARD TERMS AND CONDITIONS

AGREEMENT SALE OF SHARES

2. TIME OF PERFORMANCE

Standard Terms & Conditions for Purchase Order

ANNEX III INDIVIDUAL CONSULTANT GENERAL TERMS AND CONDITIONS

Application for CREDIT FACILITIES & SURETYSHIP

Form of Agreement Between the Client And the Quantity Surveyor

VIRGIN ISLANDS MUTUAL FUNDS (RESTRICTED PUBLIC FUND) REGULATIONS, 2005 ARRANGEMENT OF REGULATIONS

REPUBLIC OF SOUTH AFRICA SOUTH GAUTENG HIGH COURT JOHANNESBURG

REPUBLIC OF SOUTH AFRICA IN THE HIGH COURT OF SOUTH AFRICA GAUTENG LOCAL DIVISION JOHANNESBURG ARGENT INDUSTRIAL INVESTMENT (PTY) LTD

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

The JCT Contract In a Cold Climate

ANNEXURE "A" CONDITIONS OF CARRIAGE OF GOODS BY ROAD

TAX RISK INSURANCE CLASSIC POLICY WORDING

CLAUSE AND EFFECT BASIC CONTRACT LAW PRINCIPLES AND KILLER CONTRACT CLAUSES

STONE INTERIORS Terms of Trade. 1 Definitions. 2 Estimate Validity and Existence of Contract. 3 Cancellations

DEPARTMENT OF PUBLIC WORKS

RULES OF THE PHANTOM SHARE PLAN

1. PURPOSE OF THESE TERMS AND CONDITIONS 2. DEFINITIONS AND INTERPRETATION

Sub Contract Agreement

China s Market Economy Status: the Commission proposal to change the anti-dumping methodology for Non-Market Economy countries. AEGIS EUROPE position

ANNEX A Standard Special Conditions For The Salvation Army

MTN ZAKHELE BEE CONTRACT FOR USE BY PERSONS IN RESPECT OF THE MTN ZAKHELE INDEPENDENT TRADING PROCESS. entered into between:

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

Terms & Conditions of Sale

ICT SERVICES AGREEMENT SCHEDULES SCHEDULE 9.1 STAFF TRANSFER

Agreement for Supply of Goods and Services - Standard Terms & Conditions

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES

GENERAL TERMS AND CONDITIONS FOR THE SUPPLY OF GRAPHIC PRODUCTS 2010 (ALG 10)

General Conditions of Sale Online of B2B LEARNING SPRL (Belgium January 2018)

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS

Schedule 10. Part 2 from Subcontractors to Beneficiaries DATED [ ] [NAME OF BENEFICIARY] and [NAME OF SUBCONTRACTOR] DEED OF WARRANTY

ACA UNIFORM TERMS AND CONDITIONS

APPLICATION FOR CREDIT

GUARANTEE DEED {PERSONAL GUARANTEE}

INTERNAL REGULATIONS PREAMBLE

SECURITISED DERIVATIVES LISTING RULES INSTRUMENT 2002

OVERALL AGREEMENT General terms (664-14)

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

W-9 PROCUREMENT OF VERY SMALL WORKS UNDER NATIONAL COMPETITIVE BIDDING PROCEDURES

HKIS QSD PQSL Series Payment Valuation and Post-Contract Cost Monitoring

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE

Please complete the form in full as all the information requested is critical to processing your application promptly.

Article 1. Definitions Article 2 Applicability Article 3 Offers Article 4 Prices

LCM CREDIT RISK (PTY) LTD (REGISTRATION NO: 2003/028768/07) (hereinafter referred to as CREDITRISK ) STANDARD TERMS AND CONDITIONS

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

MT WELD MINING PTY LTD ACN Purchase Order Terms and Conditions for the Supply Of Goods and/or Services

SPECIAL CONDITIONS OF CONTRACT

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

AN ISO 9001 & ISO COMPANY TENDER DOCUMENT. NIT No.: NRO/CON/738/667 date : FOR

General Conditions of Purchase of BASF Holdings South Africa (Pty) Ltd and its Affiliated Companies Located in South Africa

Section Payment Conditions

(1986 to 1994) ( 1 ), in particular under Article 3(1)(a) and paragraph (j) of Annex I thereto;

NAB EQUITY LENDING. Facility Terms

General Conditions of Sale

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT

IOP(SA) PLUMBING WORKS AGREEMENT

INVITATION TO TENDER TENDER FORM

TREATT PLC. Deed of Trust and Rules. of the TREATT plc Share Incentive Plan

Westpac NZD Subordinated Notes Master Deed Poll

Stifel, Nicolaus & Company, Incorporated

Amendments to Core Clauses

Inform Practice Note #17

PROGRAMME MEMORANDUM SUPERDRIVE INVESTMENTS (PROPRIETARY) LIMITED (RF)

Standard Purchase Terms & Conditions for The Supply and Delivery of Goods

Standard Form Project Agreement (hub DBFM Projects)

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE

Revenue 920,306 1,937,672 Dividend income 875,665 1,918,035 Interest income 44,641 19,451 Scrip lending income - 186

GENERAL: WITNESSETH: That the said Contractor and the said District, for consideration hereinafter named agree as follows: DESCRIPTION OF WORK:

Conditions for the Carriage of Goods by Road

INTERIOR ARCHITECTURE & DESIGN TERMS & CONDITIONS DESIGN SERVICES ZUNICA P/L LEVEL 1, 216 CHAPEL STREET PRAHRAN VICTORIA 3181

Data#3 Limited Long Term Incentive Plan

Transcription:

ESTABLISHING THE EFFICACY OF THE JBCC CONSTRUCTION AND PAYMENT GUARANTEES Prof. Marthinus J Maritz tinus.maritz@up.ac.za Head of Department, Department of Construction Economics, Faculty of Engineering, Built Environment and Information Technology, University of Pretoria, Pretoria, 0002, RSA ABSTRACT The Joint Building Contracts Committee (JBCC) 1991 suite of contracts was the first in South Africa to introduce the concept of construction and payment guarantees that provided the requisite cover available on call from approved financial institutions. In the process the construction guarantee replaced the performance guarantee (surety) that prevailed in addition to the retention fund in construction contracts. Standard forms, which embodied the terms and conditions of the guarantees, were prepared for this purpose by the JBCC. These terms and conditions had been negotiated by the JBCC with the legal/technical committees of the banking and insurance institutions and were fully approved by them (Finsen, 2005: 100). However, for some time now concerns have been raised regarding the difficulties experienced in getting all banks and/or their property finance divisions to comply with the JBCC guarantees. Because the construction and payment guarantees are so closely linked to the terms of the principal and nominated/selected subcontract JBCC agreements, changes made to the pro forma guarantees or agreements which disturb the risk of the guarantor, could very well render the guarantee null and void. For this reason the banking and insurance institutions, who often wish to customise the wording of standard forms for their specific requirements, should be made aware of the fact that such modifications could lead to the guarantees being ineffective when required and that this practice could increase the risk of the parties concerned. The practice of altering standard documents is unavoidable, but cognisance should be taken of the inherent danger of such modifications. Suites of documents are interrelated and alterations made in any one document could lead to inconsistencies elsewhere in the documentation. Experience has shown that changes drafted by others, including members of the building professions, are often prejudicial to one of the parties or to both parties (JBCC PBA, 2007). This paper will report the findings of research conducted on perceived problems experienced by the construction industry with regard to construction and payment guarantees, and present what is considered to be best practice to ensuring that these guarantees are used effectively. INTRODUCTION Uncertainty about future events creates the risk of losses occurring. The aim of risk management is to reduce such risks, while the effective level of control that a party exercises over risk largely impacts on the profitability of the business venture. Losses because available security often does not completely liquidate the exposure are inevitable, and are accepted as part of the business of property finance. Efforts to reduce the severity and variability of such losses are an ongoing management function requiring the constant monitoring, developing and refining of policies, procedures, skills and knowledge (Wight & Ghyoot, 2008). 1

Many activities are performed during the execution of building contracts. As such an efficient construction process is invaluable. Moreover, due to the inherent divergence of interests, conflict among the contracting parties appears inevitable. Construction conflicts include, but are not limited to, the following main types: general breach of contract; failure to perform; delays; payment disputes; workmanship standards; labour disputes; and termination (including repudiation). Often, the unfortunate outcome of such conflicts is loss of productivity, delays and increase in construction costs. In an effort to reduce risks and to protect the interests of the contracting parties, various types of securities have over the years been introduced into standard building agreements. As the contents of agreements gradually became more sophisticated and included new provisions, inventive ways had to be developed to protect the risks and interests of the parties with greater certainty. Therefore, when the new parcel of contract documents prepared by the JBCC was introduced to the South African building industry in 1991, Brink & Botha (1991: 2) stated that the aims, inter alia, were to: review the areas of uncertainty that exist in the documents then in use; re-examine the distribution of risks; find a way of improving cash flow to the contractor and his subcontractors; provide better and more cost effective security to the employer; and encourage better and greater discipline in the industry. It is essential that the project team establishes and understands the client requirements as accurately and as quickly as is appropriate and possible, and these requirements must reflect the needs and objectives of the clients. The oft cited Latham Report (1994) suggested that a client s project needs are: obtaining value for money; ensuring the project is delivered on time; having satisfactory durability; incurring durable running costs; being fit for its purpose; being free from defects on completion; having an aesthetically pleasing appearance; and being supported by meaningful guarantees. There are a number of standard contracts that are currently being used in South Africa. The South African Construction Industry Status Report (2004: 50) prepared by the Construction Industry Development Board (CIDB) stated that the following forms of contract were considered to be meeting the principles of modern contracting if utilised unaltered: Federation Internationale Des Ingenieurs-Conseils (FIDIC French acronym for International Federation of Consulting Engineers); 2

General Conditions of Contract for Construction Works (GCC 2004); New Engineering Contract (NEC now referred to as the Engineering and Construction Contract, ECC); and The Joint Building Contracts Committee (JBCC Series 2000). These modern forms of contracts are supposed to appropriately allocate risks, responsibilities and obligations and contain administrative procedures that enable proactive management of the delivery process. As part of their supplementary documents these contracts offer pro forma deed of surityship and guarantee forms. Informal observation that will be evaluated in this paper has indicated that these forms are regularly changed leading to poor interpretation and increased risk to the contracting parties. This paper focuses primarily on the JBCC Series 2000 suite and more specifically on its variable construction guarantee, which must be provided by the contractor/subcontractor, and its payment guarantee, which must be provided by the employer/contractor, and reference will only be made to the other JBCC guarantees (fixed construction guarantees and advance payment guarantees), where they are of consequence. This will be done merely for the sake of convenience as matters affecting the variable/fixed construction guarantees and payment guarantees are very similar. In the absence of a specific agreement, the contractor is not obliged to provide any form of security for the due fulfilment of his obligations. Loots (1995: 647) states, however, that it is customary to require the contractor to furnish such a guarantee. The security may either be in the form of a suretyship or a performance (or demand ) guarantee or indemnity. Forsyth and Pretorius (1992: 26) define a suretyship as: an accessory contract by which a person (the surety) undertakes to the creditor of another (the principal debtor), primarily that the principal debtor, who remains bound, will perform his obligation to the creditor, and secondarily, that if and so far as the principal debtor fails to do so, the surety will perform it or, failing that, indemnify the creditor. The performance (or demand ) guarantee, on the other hand, is usually an undertaking whereby the guarantor unconditionally and irrevocably undertakes to pay certain amounts (as may be specified in the agreement) on demand and without proof of any breach of contract. The 1991 edition of the JBCC suite of contracts was the first in South Africa to introduce the concept of a construction guarantee aimed at replacing the retention fund. In the process the construction guarantee also replaced the performance guarantee that, at that time, prevailed in addition to the retention guarantee in construction contracts. Both performance guarantees and retention guarantees were mainly drafted in the form of a suretyship, which after the guarantor had been made a coprincipal debtor and had denounced his benefits of excussion and division still had the defence in law of challenging the right of the employer to call up the guarantee and to challenge the quantum of the guarantee before paying over the money. In short, a suretyship is not tangible money. It has to be earned, often by taking recourse to the courts. In the case of the JBCC construction guarantees, which were introduced with the aim of making the requisite cover available on call or on demand, the guarantor undertakes to pay the employer the certified amount upon receipt of the following documents, which will serve as conclusive proof that the employer is entitled to call up the guarantee: 3

1. A copy of a first written demand issued by the employer to the contractor stating that payment of an amount certified by the principal agent in an interim or final payment certificate has not been made in terms of the agreement and failing such payment within seven (7) calendar days, the employer intends to call upon the guarantor to make payment. 2. A first written demand issued by the employer to the guarantor at the guarantor s physical address with a copy to the contractor stating that the period of seven (7) calendar days has elapsed since the first written demand, and that the amount certified has still not been paid, therefore the employer calls up the construction guarantee and demands payment from the guarantor. 3. A copy of the said payment certificate which entitles the employer to receive payment in terms of the agreement. Understandably employers prefer to receive on demand guarantees because these guarantees can be called up without having to first prove the contractor s default in arbitration or litigation, which can be time consuming. Guarantors likewise prefer on demand guarantees because in this instance they do not need to read the building agreement, investigate the contractor s alleged default and assess the employer s entitlement to compensation (Uff, 2005: 330). Standard forms, which embodied the terms and conditions of the respective guarantees, were prepared for this purpose by the JBCC. According to McDonald (2002) problems initially existed in the wording thereof and in the matter of Basil Read (Pty) Ltd v Beta Hotels (Pty) Ltd and Others 2001, Judge Van Reenen stripped the JBCC 1991 construction guarantee of all its guarantee status and dignity, thus exposing it for what it really was, namely a simple suretyship. The current JBCC Series 2000 guarantees have rid themselves of the words in respect of expense and loss, and the destroyer of all guarantees, by virtue of non-performance, in an effort to provide the market with a true blue guarantee, without the cumbersome obligations of a suretyship. Because the construction guarantee replaced both the retention fund and performance guarantee, the JBCC decided that the guarantee should broaden its application base to also include expense or loss suffered by the employer due to reasons other than through non-performance of the contractor. The broader base of security offered by the guarantee indemnified the employer against expenses or loss in circumstances where: The employer effects the insurances on behalf of the contractor; The contractor refuses to carry out contract instructions and where another contractor is called upon to do so; The nominated subcontract is terminated due to default by the contractor; The contract is terminated due to default by the contractor and another contractor is employed to complete the works; The selected subcontract is terminated on other grounds than due to the employer defaulting; The recoupment of advance payments; The recovery statement reflects an overpayment to the contractor; The contractor does not pay the nominated/selected subcontractor and the employer elects to pay the subcontractor directly; and The contractor is liable for penalties due to late or non-completion of the work. In deciding the quantum of the construction guarantee the JBCC compared the level of security that existed with the 10% performance guarantee, adding the 5% (maximum) retention fund and the delay in receipt of payment by the contractor from the date of valuation on site, with the level of security related to the exposure of the employer. During this exercise it was established that the existing 4

security level increased from 10 percent at the beginning to approximately 22% at the certificate of practical completion stage (Diagram 1). It is generally recognised that the exposure of the employer to expense or loss due to the default of the contractor is greatest at the beginning of the contract and reduces towards the end. The JBCC therefore concluded that the existing system was not cost effective because it underprotected the employer at the beginning and overprotected him at the end (Diagram 2). 20% 15% 10% 5% NSC PERFORMANCE GUARANTEES DELAY IN PAYMENTS 5% MAX RETENTION 10% PERFORMANCE GUARANTEE 0% 2.5% RETENTION 0% 25% 50% 75% PC FCC FPC Diagram 1: Levels of security for the employer prior to introduction of the JBCC 1991 suite of contracts (Brink & Botha, 1991: 36) 20% 15% 10% 5% UNDER PROVISION OVER PROVISION 0% 0% 25% 50% 75% PC FCC FPC Diagram 2: Exposure of the employer to expense or loss resulting from default by the contractor prior to introduction of the JBCC 1991 suite of contracts (Brink & Botha, 1991: 38) In order to make the construction guarantee more cost effective and available to everyone in the building industry, while at the same time avoiding placing the smaller contractors at a disadvantage, the JBCC decided to initially fix the variable construction guarantee at 12,5% of the contract amount. This ratio is reduced to 7,5% of the contract amount when 50% of the value of work satisfactorily executed has been certified for payment; whereafter it is reduced to 4% at the issue of the certificate of practical completion; and reduced to 2% at the issue of the certificate of final completion; and then expires on final settlement between the contracting parties. The initial percentage of 12,5% has subsequently been reduced to 10%, while the 7,5% was reduced to 6% in the latest edition of the JBCC Series 2000 documents (fifth edition, 2007) to bring about parity between private and state usage of the guarantee (Diagram 3). 5

16% 12% 8% 10.0% 6.0% 4% 4.0% 2.0% 0% 0% 50% of Contract Sum Practical Completion Final Completion Final Payment Certificate Diagram 3: Current (maximum) levels of security for the employer should the contractor select the variable construction guarantee (adapted from the JBCC Guide to Valuation, Certification & Payment, 2007: 4) The JBCC construction guarantee is deemed to be more cost effective in its application than the previous forms of security it replaced, and its application base has been broadened in favour of the employer. Contractors and subcontractors are likewise prepared to offer this improved facility to the employer in exchange for the enhanced cash flow occasioned by the replacement of the retention fund with the guarantee. In terms of its conditions, the JBCC construction guarantee expires in one of five ways. These are when: 1. The final amount owing to the contractor in the recovery statement is paid in full. 2. The final amount owing to the employer in the recovery statement is paid in full. 3. The contract is terminated on the default of the employer. 4. Payment in full of the guarantee sum is made. 5. The expiry date of the guarantee occurs. It should be appreciated that the guarantees are stand alone documents where the conditions are set by the bank or issuing institution, and that these conditions are not effected by a change in the wording of the agreement which is to be signed. RESEARCH METHODOLOGY The primary objective of the research was to establish whether the application of on demand guarantees which were introduced in 1991, has met with the aims set by the JBCC (supra), and to gather accurate and useful information on perceptions and the application of construction guarantees in the South African construction industry. It was evident that the research had to be conducted methodically and systematically in order to obtain the data which was required to support the conclusions. Thus the research methodology embraced both quantitative and qualitative methods of data gathering in order to generate relevant information from the target population. 6

To establish the quantitative criteria whereby the effectiveness of the guarantees could be evaluated, a questionnaire was circulated via email to a target population of randomly selected contractors and employers in the Gauteng region. The target population is divided into two categories: 1. Contractors A selection of main contractors in the building industry that are registered with the Construction Industry Development Board (CIDB) with a Grading Designation of at least 7. 2. Employers A selection of clients or developers undertaking and being responsible for the funding of larger building projects (the party engaging in contract with the contractor). Respondents were requested to respond to statements related to the application of the JBCC construction and payment guarantees in projects where the following was applicable: Instances where recognised bank or insurance companies underwrite the guarantees; Instances where the JBCC construction and payment guarantees are applied; Instances in which contracts are based on the JBCC terms and conditions; Instances where the work to be completed is building related; and Instances where a main contractor, professional team and employer are involved. Considering that there could be a wide range of expected or possible responses, questions that were open-ended were avoided. Respondents were, however, invited to provide relevant comments at the end of the questionnaire if they wished to clarify their responses. For most of the questions a 5-point Likert scale ranging from strongly agree to strongly disagree was deemed appropriate and scaled responses were developed. The questionnaire was accompanied by a covering letter which explained the reasons for and background to the research, and the email message informed the addressees that the questionnaire was designed to be completed by the senior legal advisor/s of the company. A qualitative research approach that utilised personal interviews was adopted to obtain the requisite data from the banking sector which underwrite construction and payment guarantees for the South African building industry. The target population was made up of individuals from the banks legal departments who were deemed to be knowledgeable on the application of the JBCC guarantees. The content and purpose of the research were first explained to these individuals, whereafter structured interviews were conducted in order to ascertain perceptions and viewpoints on the importance, application and effectiveness of the JBCC guarantees. Due to the small size of the target population this survey did not require sampling. Every effort to eliminate the likelihood of biased data was made, but should such data be identified, it is acknowledged. Buys (cited in Buys & Tonono, 2007) defines bias as any influence, condition, or set of conditions that may singly or together distort the data from what may have been obtained under the conditions of pure chance. 7

TRENDS INDICATED BY THE DATA COLLECTED Statement SA A N D SD Mean The introduction of construction guarantees provided by financial institutions in place of the retention fund and performance surety has been well accepted by all stakeholders in the building industry The obligation on the parties to furnish construction and payment guarantees is so fundamental that failure to do so by the start of the construction period is sufficient grounds for cancellation of the agreement The reduced cover in the 5th edition of the JBCC for the variable (12,5% 10%) and fixed (7,5% 5% plus 5% reduced payment) construction guarantees (to bring about parity between private and state usage) remains adequate to protect the interests of the employer Lack of uniformity in the wording of construction and payment guarantees often results in inadequate or defective protection The construction and payment guarantees are truly guarantees at call and the guarantor will make payment forthwith on receipt of written demand No 5 10 3 0 0 % 28% 56% 17% 0 0 No 7 5 1 3 2 39% 28% 6% 17% 11% No 5 9 4 0 0 % 28% 50% 22% 0 0 No 4 10 3 1 0 % 22% 56% 17% 6% 0 No 0 5 11 1 1 % 0 28% 61% 6% 6% 4.11 3.67 4.06 3.94 3.11 Construction guarantees provided by a financial institution No 2 9 2 4 1 curtail the liquidity of established contractors % 11% 50% 11% 22% 6% 3.39 The lapsing of the construction guarantee after its expiry date leaves the employer with little recourse against the contractor for rectification of latent defects and the guarantee should therefore be extended to the end of the latent defects liability period Employers are often caught unawares in that the construction guarantee lapses because the expiry date on the guarantee is generally set too early No 5 2 2 6 3 % 28% 11% 11% 33% 17% No 3 4 6 3 2 % 17% 22% 33% 17% 11% 3.00 3.17 Table 1: Application of the JBCC construction and payment guarantees as viewed by contractors and developers The results in Table 1 indicate that the introduction of on-demand guarantees has been well accepted by the industry and that it is a definite obligation on the parties to furnish such guarantees at the commencement of the project. The reduced cover currently available to employers should the contactor default, is regarded as adequate by the majority of the respondents. The respondents are, however, concerned that amendments to the pro forma wording of the guarantees may result in inadequate protection when needed. The relatively low mean rating of 3.11 is an indication that respondents are not entirely convinced that banks will make payment forthwith when called upon. The lapsing of the construction guarantee leaving the employer with little recourse against the contractor for rectification of latent defects and the expiry date on payment guarantees that is set too early are 8

further problem areas for employers and contractors respectively as indicated by almost half of the respondents. Statement SA A N D SD Mean Underwriting JBCC guarantees is an important No 5 0 0 0 0 commercial business for banks in South Africa % 100% 0 0 0 0 5.00 JBCC guarantees are regarded as true blue guarantees on call, i.e. the bank will pay out without asking questions No 5 0 0 0 0 % 100% 0 0 0 0 5.00 The bank does not get involved in any way in the No 5 0 0 0 0 dispute between contracting parties % 100% 0 0 0 0 5.00 The bank is kept informed on the latest revisions of the guarantee forms as and when published by the JBCC The standard JBCC guarantee forms are available on the bank s electronic server system and the wording is never tampered with Except for what is referred to in the guarantee form the bank does not require any additional documentation to be submitted when a guarantee is called up Data on turnover and number of guarantees called up are annually collected and made available by the bank No 0 1 0 4 0 % 0 20% 0 80% 0 No 1 3 0 1 0 % 20% 60% 0 20% 0 No 0 4 1 0 0 % 0 80% 20% 0 0 No 0 0 0 5 0 % 0 0 0 100% 0 2.40 3.80 3.80 2.00 Table 2: Application of the JBCC construction and payment guarantees as viewed by the banking sector The findings in Table 2 indicate that all the main stream banks in South Africa (ABSA, FirstRand, Nedbank, RMBH and Stanbank) regard the underwriting of JBCC guarantees as an important part of the bank s day-to-day business. There was consensus among the interviewees regarding the undertaking by the banks to pay out the amount available on call or demand without getting involved in the dispute. In most instances the wording of the guarantees is not amended by the banks, but the interviewees acknowledged that they are not always informed about the revised wording of new editions as and when issued by the JBCC. No statistics on the application of the guarantees are kept by the banks although all interviewees agreed that such information will have significant value. The findings in Table 2 are based on the responses provided by representatives of the abovementioned banks, but the research ascertained that the responses would have been significantly different if based on the policies adopted by their corporate property finance divisions, such as Nedbank Corporate Property Finance. When a payment guarantee forms part of the development loan finance structure between the property finance institution and the client or borrower, the wording of the guarantee the bank would give to the contractor (normally in exchange for a waiver of the builder s lien from the contractor) must incorporate the following aspects (D Arcy-Donnelly, 2007): 9

The JBCC payment guarantee is for a fixed amount and usually equivalent to three months projected payments at any one time. Usually a property development loan is approved on the basis of a defined expenditure amount. In the event of valid variations issued in terms of the JBCC contract between the employer and the contractor, the bank s guaranteed amount would in terms of the wording of the guarantee inherently guarantee these additional amounts occasioned by the variation order, notwithstanding that the bank has not agreed to the variations (there is no mechanism for this). The net effect by the end of the project is that the bank s total loan exposure would be higher than the total amount approved. Property finance institutions generally have a standard requirement that the work, while signed off by the relevant professional, must be vetted by the bank s agent before payment is made. It is not always possible for the bank to rely solely on the professional s sign off, as they do not owe the bank a duty of care, nor does the bank obtain cession of their professional indemnity cover, nor can the bank always ensure that the cover is up to date and valid. The fact that the bank utilises its agent to verify the works is not uncommon and, in fact, prudent. The JBCC payment guarantee does not provide for this. Banks issue a guarantee which indicates the full facility available to the contractor. This amount does not always constitute the full contract amount and the employer may be required to initially pay a portion from his/her own resources. The JBCC does not provide a mechanism where banks do not guarantee the full contract amount. The guarantees by property finance institutions provide for payments to be made on a balance to complete. In other words, upon payment of a draw, the bank must have a sufficient facility to fund the completion of the work. Inherent in this is the fact that banks do not automatically assume full liability for all and any overruns. In the event that a "buffer" facility is required by the contractor over and above the agreed contingency amount provided, this would need to be a defined amount and the borrower/employer would need to furnish the bank with appropriate security for this additional facility. This is an additional credit risk which banks do not automatically assume as is envisaged by the JBCC payment guarantee, but if banks were required to assume it, it would need to be quantified and secured. The expiry date in the JBCC payment guarantee does not necessarily coincide with the bank s facility. If a loan is settled from the proceeds of the units as they are transferred, the contingent liability that remains in terms of the guarantee would necessitate banks holding back the proceeds from the transfers pending finalisation of the accounts which may take some time. This would clearly not be acceptable to the employer/borrower. As the JBCC payment guarantee is normally a standard annexure to the JBCC contract, it is usually the employers who find themselves in a difficult position. This is due to the fact that they are legally required to procure the financial guarantee in accordance with the annexure, which they may be unable to do under certain the circumstances. CONCLUSION The research has identified that the JBCC guarantees have largely met the aims set by the JBCC (supra), but that the following problem areas exist which may have an influence on the effectiveness of the guarantees: The insistence by banks (more specifically property finance institutions) to amend the pro forma JBCC guarantees. A typical example of such an amendment is the insertion of the following sub-clause in the payment guarantee: 10

1.3 The Guaranteed Amount shall be reduced by any amounts paid directly to the Contractor in terms of the Agreement It is generally accepted that contractors are more exposed to risk of payment default towards the end of the contract, and acceptance of subclause 1.3 above would dilute the contractors protection, as the employer s guarantee may then be exhausted. Therefore a fixed guaranteed amount, as provided for by the JBCC, must remain in place. Contractors require the payment guarantee to expire only on payment of the final payment certificate, but banks insist on an expiry date that is certain most often the contract s practical completion date which, more often than not, is delayed beyond such date. This means that it may be several months (or even years) before final payment will be made. The principal agent s certification is final and constitutes a liquid document, but often payment guarantees are subject to the bank s own quantity surveyor or valuer s approval, which is not acceptable to contractors as such a provision could be abused by the issuing financial institution. Confusion exists in the industry as to whether the JBCC guarantees are amortising. Finsen (2005: 106) states that the JBCC payment guarantee is an undertaking by the guarantor to pay on call the certified amount in terms of a payment certificate where the employer has failed to do so within seven calendar days of the date of issue of the certificate. It is unclear whether the contractor may call up the entire amount of the guarantee, or the outstanding balance of the guarantee. Banks are uncomfortable with their position where the employer and contractor have agreed to numerous variation orders, resulting in a substantial increase in the original contract amount, without notifying the bank and allowing the bank to participate in the discussions in order to protect its own interest. It appears that the bank may be at risk where no certificate is issued in circumstances where substantial variations to the original contract were agreed to. It should be noted that the aforementioned problem areas apply mostly to payment guarantees which are to be provided by the employer in terms of the JBCC principal building agreement. Most of the abovementioned aspects do not apply in respect of payment guarantees which are to be provided by the contractor to subcontractors in terms of the JBCC nominated/selected subcontract agreement nor to construction guarantees which are to be provided by the contractor to the employer in terms of the JBCC principal building agreement. The risks carried by subcontractors are generally less than those carried by the contractor because of their additional rights in the event of payment defaults. The payment guarantee provided by the contractor also remains fixed to the end of the subcontract. Likewise, in the case of the construction guarantee provided by the contractor, the employer s security is not influenced by any loan agreements etcetera between the financier and developer, and the security will in almost all instances remain as structured in the guarantee until the end of the contract. RECOMMENDATION It is recommended that the JBCC and the legal commission of the Banking Council should engage more regularly to discuss and find solutions for the problems that have been identified in this study as well as address other concerns that may be voiced from time to time. The CEO of JBCC confirmed to the author that regular meetings were held soon after the introduction in 1991 of the JBCC suite of contracts, but that it has for some time now been neglected, mainly because of the poor attendance by delegates from the Banking Council. 11

REFERENCES Brink WAC & Botha PC. (1991) Know the JBCC Agreements: Comparison with Existing Documents. Braamfontein, RSA. Buys NS & Tonono E. (2007) Reasons for the transformation of facilities management in the public sector. Acta Structilia, Vol. 14 No. 2 of 2007. Bloemfontein, RSA. Construction Industry Development Board (CIDB). (2004) South African Construction Industry Status Report. Pretoria, RSA. D Arcy-Donnelly R. (2007) Personal communication. 19 May. Nedbank Corporate Property Finance Legal. Johannesburg, RSA. Finsen E. (2005) The Building Contract: A commentary on the JBCC Agreements. 2 nd ed. Juta & Co Ltd: Capetown, RSA. Joint Building Contracts Committee Inc. (JBCC). (2007) Principal Building Agreement (PBA). 5 th ed. Code 2101. Johannesburg, RSA. Joint Building Contracts Committee Inc. (JBCC). (2007) Construction guarantee for use with the JBCC Principal Building Agreement. Code 2122. Johannesburg, RSA. Joint Building Contracts Committee Inc. (JBCC). (2007) Payment guarantee for use with the JBCC Principal Building Agreement. Code 2124. Johannesburg, RSA. Joint Building Contracts Committee Inc. (JBCC). (2007) Guide to Valuation, Certification & Payment. Code 2201. Johannesburg, RSA. Loots PC. (1995) Construction law and related issues. Juta & Co Ltd: Kenwyn, RSA McDonald T. (2002) Quest: Science for South Africa. Vol. 3 of April 2002. Academy of Science of South Africa (ASSAf). RSA. Forsyth CF & Pretorius JT. (1992) The law of suretyship in South Africa, 4 th ed. Juta & Co Ltd.: Kenwyn, RSA. Uff J. (2005) Construction Law. 9 th ed. Sweet & Maxwell: London, UK. Wight A & Ghyoot V. (2008) The property finance business. 2nd ed. Unisa Press: Pretoria, RSA. 12