Key Performance Indicators for the Provision of Medium Construction Related Works and Building Refurbishment for the University of Worcester

Similar documents
SUSTAINABILITY ACTION PLAN

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010

DIRECTORATE OF ESTATES AND FACILITIES

CONSULTANT EVALUATION SYSTEM GENERAL CRITERIA

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

Purchase Card Program Cardholder Manual

To ensure telephone enquiries are handled at first point of contact, minimising abandoned calls

HUB PROGRAMME DELIVERY OFFICE GUIDANCE NOTE. Revisions to Payment Provisions for Consultants

Section 7. General Conditions of Contract for the Procurement of Works

Conditions of Contract for PLANT and Design-Build

Whereas the Contractor has entered into an agreement (the "Prime Contract") dated the, 20 with:

CODE OF PRACTICE FOR SUBCONTRACTORS

Capital Project Approval Request

DRAFT FORM OF CONTRACT

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement

Consultancy Services Contract

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION

Part 2 Employer s preliminary notice of Fair Payment requirements 3. Part 4 Suggested modifications to SBCC Main Contracts 5

Inform Practice Note #19

Payment Act Comparison NJ/DE/PA/MD/NY

M 3. Planned and cyclical maintenance policy. August 2013 August If you require this policy in a different format please ask a member of staff

Current as of 1 May

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies

Contract HSE Management/Part I

SAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS

HUME Community Housing Association Company Ltd.

Project Alliance Agreement (PAA) Between

CCWater Records Management Schedule - electronic and paper records. Version Description Date Author 1.0 Version 1 17/05/2018 Colin Lench

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Evaluating tenders offers

Report of Head of Estates Management. Status Public (with separate exempt report) Summary

Yellow cells denote information required to be entered. Grey cells denote no information should be entered.

Module 23 Revenue TEST YOUR KNOWLEDGE. Question 1. Question 2

PROCUREMENT POLICY AND PROCEDURES 1. PURPOSE

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

ARTICLE 8 - OWNER S RESPONSIBILITIES

REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS

The Community Housing Group & all subsidiaries. Executive Business Manager (Repairs & Voids)

Repair Authority - Terms of Authority

Session 3 by Zoltán Záhonyi, FIDIC AIT,

Contractor Code of Conduct

ATTACHMENT A - STATEMENT OF WORK INVITATION TO BID FOR FIRE SPRINKLER SYSTEM INSPECTIONS ITB NO.: DMS-14/15-004

Preparing Interim Payment Valuations for Construction Works - Worked Examples and Solutions

The New NZS 3910:2013

SCHEME ADMINISTRATOR:

Occupational Safety & Health Policy & Guidelines for Contractors

Terms & Conditions. Rev A - Feb 2017

SENIOR EXECUTIVE ARCHITECT

External Consultants & General Contractors Contracts

CS ENERGY LIMITED SERVICE CONDITIONS

SAMPLE COPY ONLY NOT FOR USE. Client / Architect Agreement (Short Form 2011 Edition) Client Details. Contact Name:

UNCONTROLLED WHEN PRINTED

Sub Contract Agreement

General Conditions of Purchase of BASF Holdings South Africa (Pty) Ltd and its Affiliated Companies Located in South Africa

University of Maine System Supplementary Requirements to AIA Document B Standard Form of Agreement Between Owner and Architect

Work Method and OH&S Statement

Appendix K Model Letters for Use by the Engineer

NEC4 Engineering and Construction Contract review of changes from NEC3

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

Environmental. The Director of Estates and ICT. Estates and ICT Directorate 25/04/12 PIN039. See Section 5 28/04/ /04/2015

PREQUALIFICATION QUESTIONNAIRE

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

Request for Quotations. For. Operations and Supervision of Parkland County Rural Transfer Stations (Keephills, Tomahawk and Moon Lake)

SUB CONTRACTOR INDUCTION PACK

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

MEMORANDUM. May 13, 2016

Gulfport, Mississippi May 21, 2007

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent

A Simple Guide to applying the Security of Payments Act 2009 (Vic)

Request for Proposals COMPOSTING TECHNICAL ASSISTANCE

SUMMARY OF MECHANICS LIEN LAW FOR NEW HAMPSHIRE. Section Contents Pre-lien Notice(s)

THE CORPORATION OF THE DISTRICT OF SAANICH

to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the

NCF 7 Project Implementation Manual

MDB Harmonised Particular Conditions

The Nuclear Decommissioning Authority s Magnox contract

Project Sponsor Group Handbook

Cleaning Services Contract

POUDRE SCHOOL DISTRICT R-1 PURCHASING MANUAL Number: 1.0 Effective Date: 7/1/07 TABLE OF CONTENTS

CONTRACTOR S RESPONSIBILITY FOR PROJECT SAFETY [Major Construction Category]

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

ALBERTA STANDARD GUIDE FOR TAKE-OVER PROCEDURES

Tender Terms and Conditions: 1. This invitation of bid is open to contractors, Class-Small registered with the Construction Development Board.

Supplier Manual Version February 2016

Standard Form Project Agreement (hub DBFM Projects)

Risk Management Policy

HALIFAX REGIONAL WATER COMMISSION PROCUREMENT POLICY. Edited May 22, 2012

Chatham County Request for Proposals Biannual Customer Service Survey

JCT 2016 Edition of Contracts

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

Alabama State Port Authority

Smart Metering Infrastructure Program

SUMMARY OF MECHANICS LIEN LAW FOR TEXAS. With Changes for 2012

Asbestos Management Policy

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints

Preliminary Information on the Vermont E-Waste Collection and Recycling Program Request for Proposal (RFP)

Western Water Development Consultant Accreditation Deed

Transcription:

for the Provision of Medium Construction Related Works and Building Refurbishment for the University of Worcester 15/01/2016 1:13 Page 1 of 15

for the Contract Scored s The Contractor must achieve the minimum acceptable weighted score for all measures in the scoring table. Failure to achieve this suspends the Contractor from the subsequent Framework tender opportunity for this period. Ref Weighting Minimum acceptable performance Weighted score Maximum available % score (A) (B) (C) (A/5) x (B) (E) = (B) 1.01 TIME Taken for construction against 5 10% 10.00% 10.00% contract practical completion date 1.02 TIME To rectify defects 3 10% 2.00% 6.00% 2.01 COST No. of inflated claims for variations 5 5% 2.00% 5.00% 2.02 COST Cost savings and value improvements against contract sum 3 5% 0.00% 3.00% 3.01 QUALITY No. of defects/snags at contract completion 3.02 QUALITY Acting in a spirit of mutual trust and cooperation with Employer 5 10% 0.00% 10.00% 3 5% 1.00% 3.00% 3.03 QUALITY With product from Client 2 5% 2.00% 2.00%.01 BUSINESS PERFORMANCE Time taken to settle final accounts.02 BUSINESS PERFORMANCE Time taken to pay subcontractors 1 5% 1.00% 1.00% 3 10%.00% 6.00% 5.01 HEALTH AND SAFETY Yellow, Red, Black 3 10% 2.00% 6.00% card system 6.01 SUSTAINABILITY Reduced waste to 2 10% 2.00%.00% landfill 7.01 SOCIAL VALUE Positive Local Impact 3 5% 0.00% 3.00% 8.01 ENVIRONMENT Considerate Contractor 3 10% 2.00% 6.00% 100% 65.00% for each is measured (A) above. Each performance indicator has its own weighting (B). The maximum available percentage score (E) is capped at the value shown. Overall the Contractor must pass the Gateway s, meet the minimum acceptable weighted score for every scored indicator and achieve a total score of 65 to be eligible for the subsequent Framework tender opportunity. Draft KPI definitions are in the following pages. These will be finalised with the successful tenderers. 15/01/2016 1:13 Page 2 of 15

1.01 TIME TIME Taken for construction against Practical Completion date TBC Minimise disruption to Employer and Users. Measure the ability of the Contractor to complete the works by the Practical Completion date. Practical Completion is achieved when all the necessary construction work is completed, operation and maintenance manuals are available and corrected any items which would prevent the employer from using the works. Employer inspects all parts of works and agrees to take possession of the works. This date is recorded against the specified completion date. Practical completion date missed 0 1 2 3 Practical completion date 5 achieved Date achieved = pass Information Source Employer Inspection Records 15/01/2016 1:13 Page 3 of 15

1.02 TIME TIME To rectify defects within rectification period Service Manager The Contractors time taken to rectify all defects. The Contractors time taken to rectify all defects in the rectification period after Practical Completion. Rectification periods as detailed in the Preliminaries. Employer records time taken to rectify defects once they have been notified to the contractor. Actual time taken to rectify all defects 0% 0 1% - 79% 1 2 80% - 99% 3 100% 5 Information Source Project Manager's Report 15/01/2016 1:13 Page of 15

2.01 COST COST No. of inflated claims for variations Reduce the number of inflated claims submitted by the contractor. Order Changes which apply to alterations to the employer s requirements or contractors proposals. The submitted cost of change should not be artificially inflated above the actual cost of construction. An inflated price shall be defined as one which includes items that are non-existent, exaggerated, or unrelated. 2+ inflated claims 0 1 inflated claim 1 2 3 Nil 5 Cost of order change is verified by Employer or his nominated representative as inflated. Information Source Service Manager's Reports 15/01/2016 1:13 Page 5 of 15

2.02 Cost COST Cost savings and value improvements against contract sum To manage efficiency and deliver value for money Proposals can be capital or revenue savings; be specific and relevant to the project; and must retain compliance with the Client Brief. Annual % cost reduction achieved through continuous improvement and innovation in each project. Nil contribution 0 1 2 Contribution up to +5% 3 Contribution +5 to +15% Contribution >15% 5 Value engineering proposals to be submitted by contractor. Information Source TBC 15/01/2016 1:13 Page 6 of 15

3.01 QUALITY QUALITY No. of defects/snags at contract completion Quality outputs and outcomes (right first time) Monitor quality of works as evaluated at Practical Completion. An employer s pre-completion list of outstanding work, which is shared with the contractor to clarify what work remains outstanding before Practical Completion. "snagging" is used to describe unsatisfactory work or small items of work still to be completed which are discussed/discovered during final site inspections. Up to 30+ defects/snags only 0 Up to 20 defects/snags only 1 Up to 10 defects/snags only 2 Site inspections may be limited to a random sample or representative area of the project works. 3 No defects at all 5 Number of defects/snags evident during inspection. Information Source Employer s pre-completion list of outstanding work 15/01/2016 1:13 Page 7 of 15

3.02 QUALITY QUALITY Acting in a spirit of mutual trust and cooperation with Employer Effective delivery, strategic alignment of partners and win/win relationship. To measure the Contactor's delivery of Thirteenth Recital and Schedule 5 SUPPLEMENTAL PROVISIONS Collaborative working: Paragraph 1 Timely, sincere, impartial and open communication and relationship management. Approach to problem solving, adhering to requirements, conflict resolution and flexibility 0% - 25% 0 26% - 50% 1 51% - 75% 2 76% - 99% 3 100% 5 Data from representative anonymous random survey to Employer's staff issued using a grading system representing their actual experiences. Information Source Survey of Employers' staff 15/01/2016 1:13 Page 8 of 15

3.03 QUALITY QUALITY with product from Client Use surveys to assess whether project meet clients expectations and whether they are satisfied with the results. How satisfied the Client (Project Manager or Contract Administrator) was with the finished product using the score against the 1 to 10 scale set out criteria below. Survey to Client with a grading system representing their actual experiences. 10 = Totally satisfied 5/6 = Neither satisfied nor dissatisfied 1 = Totally dissatisfied Totally dissatisfied 0 1 2 Neither satisfied nor 3 dissatisfied Totally satisfied 5 Information Source Data from survey to Client. 15/01/2016 1:13 Page 9 of 15

.01 BUSINESS PERFORMANCE BUSINESS PERFORMANCE To settle final accounts Ensure agreement of the final accounts by planned date. Time taken to reach final account from Practical Completion expressed in weeks. Settled within 3 months of Practical Completion date Over 3 months 0 Within 3 months 1 Within 2 months 3 Within 1 month 5 Information Source Project Manager s Report 15/01/2016 1:13 Page 10 of 15

.02 BUSINESS PERFORMANCE BUSINESS PERFORMANCE time taken to pay subcontractors Contractor should pay undisputed invoices of small suppliers not more than 5 calendar days from the end of the calendar month, in accordance with the UK Prompt Payment Code. Payment by the Contractor (Tier 1) is received by their subcontractors (Tier 2) within 5 days of the due date for payment. 0% 0 0% - 50% 1 51% - 75% 2 Days are calendar days excluding bank holidays 5 days 76% - 99% 3 100% 5 Information Source Sub-contractor reports Sub-contractor reports to Employers 15/01/2016 1:13 Page 11 of 15

5.01 HEALTH AND SAFETY HEALTH AND SAFETY Amber, Red card system Ensure site health and safety Notices and warnings received under the University of Worcester H&S card system. No more than Yellow Cards 10 Red Cards 1 10+ Yellow or 1 Red 0 8+ Yellow 1 + Yellow 2 Up to 3 Yellow only 3 Up to 2 Yellow only Zero cards issued 5 Site inspection carried out by Employer Information Source Health Safety and Environment Inspection Report 15/01/2016 1:13 Page 12 of 15

6.01 SUSTAINABILITY SUSTAINABILITY Waste reduced to landfill Encourage sustainability and reduce waste to landfill. Exemptions include asbestos and other deleterious materials. Amount of waste recycled, divided by the amount of waste produced. 0% 0 1% - 25% 1 26% - 50% 2 51% - 75% 3 76% - 99% 100% 5 Information Source Contractors waste tickets 15/01/2016 1:13 Page 13 of 15

7.01 SOCIAL VALUE (Discretionary) SOCIAL VALUE Positive Local Impact Ensuring delivery of commitments made at tender stage. Positive Local Impact - achievement of plans identified in Tender submission and agreed with the Client. Compare actual achievement to proposals for percentage complete result. Information Source Tender document and Contractor's Plan. 0% 0 1% - 25% 1 26% - 50% 2 51% - 75% 3 76% - 99% 100% 5 15/01/2016 1:13 Page 1 of 15

8.01 ENVIRONMENT (Discretionary) ENVIRONMENT Considerate Constructor Scheme CCS Site Report Encourage the construction of new and refurbished buildings in a manner that will promote sustainability, conserve and enhance natural resources and prevent environmental pollution. As required by the Considerate Constructor Scheme CCS Scheme Assessment Average score of 33 Less than 30 0 30 32.5 1 2 CCS Assessment Score Criteria CCS score 36 or over Score Excellent; 33 to 35.5 Score Acceptable (see note below) 30-32.5 Score Poor; less than 30 Score Unacceptable 33 35.5 3 36 or over 5 (if a project specific requirement has been made in excess of 33 eg for BREEAM- then this target must be achieved for 3 to be scored) Information Source CCS Site Report 15/01/2016 1:13 Page 15 of 15