Case Study: Key Performance Indicators implementation in gas transmission pipeline. María José Gutiérrez Argentina

Similar documents
Paper Number:

PIPELINE INVESTIGATION REPORT P07H0014 CRUDE OIL PIPELINE RUPTURE

RAILROAD COMMISSION OF TEXAS

ENBRIDGE PIPELINES (VIRDEN) INC. Proposed NGL Injection Station and Connecting Pipeline W1M to W1M Near Cromer, Manitoba

PIPELINE INVESTIGATION REPORT P01H0004 CRUDE OIL PIPELINE RUPTURE

The Bison Pipeline Project. Public Disclosure Document

CERTIFICATE OC-063. IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

PIPELINE RISK ASSESSMENT

Hydraulic Series Coupon Holders

SIL and Functional Safety some lessons we still have to learn.

Pipeline Application

SENATE, No STATE OF NEW JERSEY. 217th LEGISLATURE INTRODUCED JUNE 6, 2016

Guide for the Extension of Boiler Internal Inspections

Developments Towards a Unified Pipeline Risk Assessment Approach Essential Elements

Presentation to National Academy of Sciences

DEPARTMENT OF ENVIRONMENTAL CONSERVATION

Pipeline Regulatory Issues

Notes on Enbridge and Line 9 and Its Impact on the Haldimand Tract

PIPELINE INVESTIGATION REPORT P09H0084 CRUDE OIL PIPELINE LEAK

Message to Shareholders 2. Management s Discussion and Analysis 4. Consolidated Financial Statements and Notes 27. Corporate Information 58

PACP Based Asset Management

ATCO Gas and Pipelines Ltd. (South)

ASSEMBLY, No STATE OF NEW JERSEY. 211th LEGISLATURE INTRODUCED JUNE 14, 2004

Message to Shareholders

National Energy Board Suite 210, 517 Tenth Avenue SW Calgary, Alberta T2R 0A8. Attention: Ms. Sheri Young, Secretary of the Board. Dear Ms.

1301: (a) The same purpose for which it was used originally;

2. Address: (Number) (Street) (City) (Prov) (Postal Code) 3. Is Applicant an Individual Partnership Corporation Other (give details)

ASPECTS REGARDING THE QUALITATIVE ANALYSIS OF RISKS DUE TO THE OCCURRENCE OF LOW PROBABILITY AND VERY HIGH IMPACT EVENTS

Carbon Dioxide Transport Infrastructure for the UK. UKOPA Dent Assessment Algorithms: A Strategy for Prioritising Pipeline Dents

IMPORTANT PIPELINE SAFETY INFORMATION

Why a Near-Miss is Never a Leading Indicator. or why we need to think in system outcomes. Ian Travers, Principal Consultant, Process Safety

As presented at the Institute of Municipal Engineering of South Africa (IMESA) conference 2013

Header Tile ATTACHMENT 2. City of Saskatoon

Guide for Completing Form AB-83

Pre-Earthquake, Emergency and Contingency Planning August 2015

Vintage Pre-Aged Faceted Metallic Substrate Limited Warranty

Requirements for Mapping Levees Complying with Section of the NFIP Regulations

Overview of the Northern Gateway Pipelines Project March 2013

Project Selection Risk

Hazard Mitigation Planning

ASSET INTEGRITY INTELLIGENCE. ADVANCEMENTS IN CUI DETECTION AND OVERVIEW OF MsS GUIDED WAVE. ADAM GARDNER, NDE Specialist at PinnacleART

Message to Shareholders-Q3 2016

Annual Report.

Notification of Fire Breaks, Leaks, or Blow-Outs, and 3.71, relating to Pipeline Tariffs. The

Second Quarter.

LETTER DECISION. File OF-Fac-OtherComm-H October 2016

Valley Creek Trunk Sewer (VCTS) Evaluation Status. Tredyffrin Township Board of Supervisors Meeting

6 th Floor G. Mennen Williams Building Environmental Quality 525 W. Ottawa Street Constitution Hall

Investigation Summary Report : Pengrowth Energy Corporation

To: All Oil and Gas Pipeline Companies under the National Energy Board (Board) All Interested Parties.

LCC Methodology. Håkan Sundquist Structural Design and Bridges KTH. ETSI Methodology 1

FINAL REPORT R-ENB Review and Assessment of Technical Evaluation for Enbridge Line 9B Reversal

OIL INDIA LIMITED (A GOVT. OF INDIA ENTERPRISE) CONTRACTS DEPARTMENT, DULIAJAN DISTRICT: DIBRUGARH (ASSAM), PIN TEL: (91) , FAX:

Advances in Layer of Protection Analysis. Wayne Chastain, P.E. Eastman Chemical Company

Use of QRM to Quantify Particulate Contamination Risks

TransCanada s Risk Management System for Pipeline Integrity Management

New-Generation, Life-Cycle Asset Management Tools

Pipeline Safety Seminar Distribution Pipe Segment Risk Assessment and Replacement Panel Discussion

Procedures for Management of Risk

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

4101: Existing boilers and pressure vessels.

Appendix C Council Resource Consents and CLCLR Information

(2) BOARD means the Colorado Water and Wastewater Facility Operators Certification Board or its designee.

ENBRIDGE ENERGY LIMITED PARTNERSHIP SPECIAL USE PERMIT

Investor Day Natural Gas & Pipeline Duke Austin President

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

1) SUBJECT OF THE STANDARD WARRANTY

CEPA S200 The Risk-based Approach

2664 RIVA ROAD, P.O. BOX 6675

6.0 MONITORING AND CONTINGENCY PLANS

Addendum to Enbridge s 2013 Corporate Social Responsibility Report (with a focus on 2013 data)

Texas Department of Transportation. DESIGN-BUILD SPECIFICATIONS Items Attachment 14-1 Utility Adjustment Forms

DATA GAPS AND NON-CONFORMITIES

HCG PURCHASING CO-OP INVITATION TO BID

ANSI API RP-754 Quarterly Webinar

Guidance for Analysis Required by COMAR Hazardous Material Security

Warranty Information (1) LIMITED LIFETIME STRUCTURAL WARRANTY

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND ORDER EB UNION GAS LIMITED

Expenditure Forecast Methodology

IMPORTANT PIPELINE SAFETY INFORMATION

City of Centerville BMP Pages Table of Contents. Minimum Control Measure 1. Public Education and Outreach

CERTIFICATE OC-56. IN THE MATTER OF the National Energy Board Act (NEB Act) and the regulations made thereunder; and

PAGE 1 OF 7 HEALTH, SAFETY & ENVIROMENTAL MANUAL PROCEDURE: S220 Hazard Communication Program REV /13/2012

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection&Control. Transmission & Distribution

Directlink Joint Venture. Transmission Network Service Provider Annual Performance Report

Risk-based Techniques for LV/MV Cable Prioritization and Aging Management

QUANTIFIED EMISSION LIMITATION AND REDUCTION OBJECTIVES (QELROs)

Draft Pipeline Financial Requirements Guidelines FOR DISCUSSION PURPOSES ONLY

Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop -

CFRP Repair of Pipelines The Current State of the Art

BETWEEN: CANADIAN NATIONAL RAILWAY COMPANY, a corporation having its head office at 935 de la Gauchetière Street West, Montreal, Quebec H3B 2M9

MVMCC CAPITAL IMPROVEMENT PROGRAM (CIP) UPDATE AND ADOPTING A RESOLUTION APPROVING A MVMCC CAPITAL BUDGET ALLOCATION AMENDMENT

Regulation DD-12.0: Risk Assessment Study

SCHEDULE B. TABLE OF CONDITIONS FOR A SECTION 10(1)(B) EXEMPTION ORDER Progress Energy Lily Dam

Keystone XL oil pipeline: What you need to know about the dispute - LA...

Development and Implementation of a High Energy Piping Program. Prepared by: Matthew C. Dowling

CHAPTER 2 REQUIREMENTS FOR STATEWIDE ONE-CALL NOTIFICATION CENTER

A. These rules and regulations are promulgated pursuant to the authority conferred by R.I. Gen. Laws

Validating Process Safety Assumptions using Operations Data Taylor W. Schuler & Jim Garrison aesolutions

Transcription:

Paper Number: 2015-07 Case Study: Key Performance Indicators implementation in gas transmission pipeline María José Gutiérrez Argentina Abstract Corrosion is a major threat that affects many assets of the oil and gas industry. Therefore, it is important to develop and implement good corrosion control strategies. The key performance indicators (KPIs) provide operators an effective tool to track implementation and success of the corrosion control strategies. Fifty (50) KPIs have been previously identified to track implementation of corrosion control strategies. This paper evaluates the applicability of these 50 KPIs for tracking the implementation of corrosion control strategies in a gas transmission pipeline. 1. Introduction The gas transmission pipeline used in this case study receives dry natural gas from another transmission line and transports it to several factories and distribution centers all along its path. The pipeline networks includes measurement, odorization and pressure regulation stations to control fluid parameters, to enable detection of gas leakage, and to regulate operating pressure respectively. This 30-year old pipeline is of 6 inch in diameter, of 80 km in length and has a nominal wall thickness of 5.56 millimeters. It operates at 60 bars of pressure and at 25 C of temperature. Over the years, the regulations in Argentina have become stringent and, about five years ago, the regulations required that pipeline integrity management system (PIMS) was developed and implemented. To meet this regulation, a qualitative risk assessment was undertaken following ASME B 31.8S 1 and methodology developed by Mulhlbauer 2. The assessment established third party damages and design (fabrication and construction) as main risks, and internal and external corrosion as secondary risks. Third party damage was considered as a main risk because the pipe traverses through populated regions and no records were available to indicate the third parties were educated of the existence of pipeline. Further the pipeline traversed through soil that was prone to soil erosion. Therefore risk due to natural events existed. S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 1 9

Design (fabrication and construction) related activities were considered as higher risk because no records on hydrostatic test results and on specified minimum yield strength (SMYS) levels were available. Further, the operating pressure of the pipeline was close to maximum allowable operating pressure (MAOP). Internal corrosion was not considered as the main risk because the pipeline transported dry natural gas that is free of contaminants. The pipeline, however, was non-piggable. Therefore internal corrosion risk existed. External surface of the pipeline was coated and further backed up by cathodic protection. Therefore, external corrosion risk was considered as minimum. In this paper, the applicability of 50 KPIs 3-4 to implement corrosion control strategies in this gas transmission pipeline is evaluated. 2. Context of Corrosion Control Corrosion control strategy adopted by the pipeline operator was based on a detailed analysis of the conditions the pipeline is exposed to both internally and externally. For assessing the risk from corrosion, the operator had sub-divided the pipeline into segments as described in NACE ICDA and ECDA methodologies 5-7. Analysis revealed that the risk from internal and external corrosion was relatively low. But consequence of a failure was high because sections of pipeline traversed through highly populated areas. KPIs relevant to the context of corrosion control are: 1, 2, 3, 4, and 5. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipelines analyzed in this paper. 3. Internal corrosion Model Model helps to establish probability of internal corrosion and, possibly, to determine internal corrosion rate. KPIs 6, 7, 9, 10, 11, 12, 14, 39, and 40 are used to track application of internal corrosion models. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: The commodity being transported by the pipeline was dry natural gas with no liquid water and with no or minimum amounts of corrosive gases (carbon dioxide and hydrogen sulphide), solids, condensates and other contaminants. The water content and impurities content were below the level allowed by the regulation. Under these conditions, the probability of internal corrosion was very low. The pipeline was constructed in carbon steel and corrosion allowance was established based on similar systems. But no record of the anticipated corrosion rate of the pipeline was available. Corrosion professionals were not involved during the construction of the pipeline. No accessories for mitigation or monitoring internal corrosion were installed. Locations where internal corrosion could occur were recently determined using methods prescribed in NACE DG-ICDA document 5. Impact of upset conditions in the sector on the downstream sectors and upset conditions of upstream sectors on this sector were understood and communication plans were established to provide information to appropriate persons should upset conditions occur. 4. Internal corrosion Mitigation Mitigation strategies are required if the internal corrosion rates are higher. KPIs 16, 17, 18, and 19 are used to track application of mitigation strategies. Tables 1 and 2 present details of the KPIs and the S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 2 9

rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: No internal corrosion mitigation strategy was developed because the probability of internal corrosion to occur was low. Operating conditions and fluid composition were routinely monitored as several locations in the pipelines to ensure that they did not change. The gas composition was strictly controlled by the upstream operator to meet the regulatory requirements. 5. Internal corrosion Monitoring Monitoring techniques are used to determine corrosion rate under the current operating conditions. KPIs 24, 25, 26, 27, 32, and 33 are used to track utilization of monitoring techniques. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: No internal corrosion monitoring plan was developed No equipment installed No activities to monitor internal corrosion were carried out. Direct inspection performed as per ICDA requirement did not reveal any internal corrosion occurrence. 6. External corrosion Model Model helps to establish probability of internal corrosion and, possibly, to determine external corrosion rate. KPIs 6, 7, 9, 10, 11, 13, 14, 41, and 42 are used to track application of external corrosion models. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The entire pipeline was buried below-ground. The soil surrounding the external surface was not analyzed in detail in the design stages of the pipeline Based on the type of soil, humidity, ph and bacteria content, the soil was considered as moderately corrosive. Based on available data upset condition in the segment would not affect downstream segments and upset conditions in the upstream would not affect external corrosion of this segment. 7. External corrosion Mitigation Mitigation strategies are required if external corrosion rates are higher. KPIs 20, 21, 22, and 23 are used to track application of mitigation strategies. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: The externally surface of carbon steel pipeline is protected by 2-layer coating and cathodic protection (CP). The coating and CP designs were established in the design stage and installed during construction. 8. External corrosion Monitoring Monitoring techniques are used to determine corrosion rate under the current operating conditions. KPIs 28, 29, 30, 31, 32, and 34 are used to track utilization of techniques for monitoring external corrosion. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 3 9

categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: On and off potential were measured at fixed locations every three months. Available readings indicated that the CP system was working properly. Cathodic protection rectifiers were checked and adjusted every 6 months. Close interval survey (CIS) and direct current voltage drop (DCVG) inspections were carried out frequently and the results indicated that the external surface of the pipeline was in good condition. Every time the pipe was excavated, coating condition, soil around the pipe and the pipe surface are examined. No significant corrosion was found in any of the under-ground measurements. In conjunction with the ICDA, an external corrosion direct assessment (ECDA) 7 was carried out. Test stations were properly installed during construction every one kilometer and at cased crossings. No pig launcher and receiver to carry out in-line-inspection were installed. 9. Measurement During operations several other parameters are measured; some of them are related to corrosion. KPIs 35 and 36 are used to track utilization of data from measured properties. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: The pipeline operator developed standards and practices to collect many parameters based on industry best practices. But no proper database to integrate the data was established. The data could only be manually analyzed. For this reason, many important information were missing or could not be used due to errors in matching different data. 10. Maintenance During operations the pipelines may be serviced and maintained. KPIs 8, 15, 37, 38, 43, 44, 45 and 46 are used to track maintenance activities. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: Maintenance activities were conducted according to a preventive maintenance plan A schedule was also available to carry out maintenance activities based on inspection or monitoring data. The maintenance was generally carried as per the schedule, with some minor exceptions. The number of workers involved in corrosion control of the pipeline were enough, but none of them had corrosion education or training Field inspection or maintenance activities were mostly carried out by third parties. 11. Management Establishing appropriate management system is essential for coordination of many corrosion control activities. KPIs 47, 48, 49, and 50 are used to track management activities. Tables 1 and 2 present details of the KPIs and the rationale for ranking KPIs in various categories with respect to the gas transmission pipeline analyzed in this paper. The following aspects were considered in ranking KPIs: The pipeline operator has developed a good plan for communications with regulator public, and landowners and among various groups within the company. However documented evidence that the all communication plan were executed was not available. The corrosion control related data were not reviewed periodically, except for the cathodic protection results. S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 4 9

KPIs Status Good Poor No failures have occurred due to corrosion for the entire 20 years of operating the pipeline. 12. Status of KPIs and Status of infrastructure Figure 1 presents the status of the KPIs implementation in the pipeline of interest. The green color bar indicates successful implementation of the strategy, yellow color bar indicates inadequate implementation of the strategy, and red color bar indicates poor or non- implementation of the strategy. 13. Recommendations It is obvious from Figure 1 that implementation of most KPIs are good and that opportunities to improve their corrosion control strategies exist. Some are discussed in the following paragraphs: Develop a corrosion management plan (KPI 49): Periodically review data from corrosion control strategies. Install monitoring devices (KPIs 24, 25, 26, 27, 39, 40, 41, and 42): Implementation of monitoring devices and monitoring corrosion rates will increase the confidence that the pipeline is continued to be safe. Develop a corrosion database (KPIs 45 and 46): Establishment of user-friendly database will facilitate easier and fast access of data and enable quick decision making. 14. Conclusions This paper has analyzed implementation of KPIs to control corrosion in a gas transmission pipeline. The risk from corrosion in this gas transmission pipeline is low. Many KPIs have been implemented but opportunities exist to implement other KPIs. Implementation of additional KPIs will further decrease the risk from corrosion. Additional KPIs that would further decrease corrosion risk to the gas transmission pipeline has been recommended. 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041424344454647484950 KPI indicator Figure 1: Key Performance Indicators evaluation results S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 5 9

KPI No. KPI description Table 1: KPI description and ranking Ranking Remarks Segmentation of the 1 infrastructure 2 Corrosion risks Good Low corrosion risk Segmentation was done according to NACE ECDA and DG-ICDA. Segments are of different in size and are of several km in length The pipeline was in high consequence area and transports highly flammable product 3 Location of the infrastructure Poor Overall corrosion risk (Risk times 4 consequence) Overall risk of corrosion is medium 5 Life of the infrastructure Poor Operated beyond its designed life. 6 Materials of construction Carbon steel is appropriate for this service Corrosion allowance (wall The corrosion allowance was established in the 7 thickness) design base on similar operations. Operating conditions were maintained within the 8 Main operating conditions Good range established during design 9 10 Potential upset conditions in the upstream sector affecting this sector Potential upset conditions in this sector affecting downstream sector 11 Mechanisms of corrosion Good Maximum corrosion rate 12 (Internal) Poor Not established. Maximum corrosion rate 13 (External) Poor Not established. 14 Installation of proper accessories during construction Poor 15 Commissioning 16 Mitigation to control internal corrosion is it necessary? Good Mitigation strategies to control 17 internal corrosion Good Not needed 18 Mitigated internal corrosion rate, Poor Not established. Upset conditions would influence in internal corrosion, but not external corrosion. Communication plan has been established to provide information in case of an upset. Upset conditions would influence in internal corrosion, but not external corrosion. Communication plan has been established to provide information in case of an upset. All corrosion mechanisms where evaluated and the most probable once identified. The pipeline had no pig launcher and receiver facilities, no inhibitor injection points, no sample collecting points, and no coupons/probes insertion points. But CP application facilities and CP test points were installed during construction. No documented report on hydrostatic test and cleaning procedure. But baseline corrosion conditions qualitatively and mitigation strategies defined. No, because the pipe transports dry natural gas containing low amounts of corrosive gases and water (below levels required by regulations. S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 6 9

19 20 21 22 23 24 25 26 27 28 29 target Percentage time efficiency of internal corrosion mitigation strategy Good Not relevant. Mitigation to control external corrosion is it necessary? Yes. Mitigation strategies to control Coatings applied and CP installed during external corrosion Good construction. Mitigated external corrosion rate, target Poor Not established. Percentage time efficiency of external corrosion mitigation CP worked properly for the entire duration of strategy Good operation of the pipeline. Internal corrosion monitoring techniques Poor None. Number of probes per square area to monitor internal corrosion Poor None. Internal corrosion rate, from monitoring technique Poor None. targeted mitigated internal corrosion rate and corrosion rate from monitoring technique Poor Not applicable. CP potential on test points, close-interval service External corrosion monitoring (CIS) and direct current voltage gradient techniques (DCVG). No coupons or probes installed. Number of probes per square area to monitor external corrosion Enough to cover most critical areas. No corrosion rate monitoring techniques used. CIS data revealed the potential was more negative than -850 mv off vs copper-copper External corrosion rate, from sulphate (CCS) reference electrode over 99% of 30 monitoring technique Poor the pipeline. targeted mitigated external corrosion rate and corrosion rate 31 from monitoring technique Poor Not established. 32 Frequency of inspection Good Established based on risk analysis and regulation targeted mitigated internal corrosion rate or corrosion rate from monitoring techniques and corrosion rate from inspection 33 technique Poor No internal corrosion monitoring performed. targeted mitigated external corrosion rate or corrosion rate from monitoring techniques and corrosion rate from inspection 34 technique Poor No internal corrosion monitoring performed. S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 7 9

35 Measurement data availability Good 36 Validity and utilization of measured data All data collected was available in a readily usable format, but not all data required was collected. Data were validated using standard or recommended practices, but no process was established to integrate and determine corrosion rate. Further, no database was available to integrate data. Preventive maintenance to keep the risk below as low as reasonably possible (ALARP) level was established based on results from inspection and monitoring. 37 Procedures for establishing the maintenance schedule 38 Maintenance activities Generally carried out on time Internal corrosion rate, after 39 maintenance activities Poor Not established. targeted mitigated internal corrosion rate or corrosion rate from monitoring or inspection technique (whichever is decided in activity 27) and corrosion rate 40 before maintenance activities. Poor No internal corrosion monitoring performed. 41 42 43 External corrosion rate, after maintenance activities Poor Not established. targeted mitigated external corrosion rate or corrosion rate from monitoring or inspection technique and corrosion rate before maintenance activities. Poor No external corrosion monitoring performed. Workforce - Capacity, education, and training Number of people just enough. Many activities were carried out by third party company personnel. Workforce - Experience, Personnel has extensive experience knowledge on pipeline integrity but not enough on corrosion 44 knowledge, and quality control. 45 Data management - Data to database Data were collected and stored properly. 46 Data management - Data from database Information was available in the database but they were not property integrated. A communication strategy was established but 47 Internal communication strategy were not practiced appropriately. A communication strategy was established but 48 External communication strategy were not practiced appropriately. 49 Corrosion management review Poor 50 Failure frequency Good CP information was reviewed and improved once a year. There was no scheduled review on other corrosion control strategies No failure due to corrosion over the past 20 years of operation. S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 8 9

Category Context of Corrosion Control Model (Internal Mitigation (Internal Monitoring (Internal Model Mitigation Monitoring (External (External Stage implementation Conceptual Table 2: KPIs results by category of Design / Commissioning / Design / Commissioning / KPI identification* Numbers (Percentage) Good Poor 1, 2, 3, 4, 5 1 (20) 2 (40) 2 (40) 6, 7, 9, 10, 11, 12, 14, 39, 40 1 (11) 4 (44.5) 4 (44.5) 16, 17, 18, 19 3 (75) - 1 (25) 24, 25, 26, 27, 32, 33 1 (17) - 5 (83) 6, 7, 9, 10, 11, 13, 14, 41, 42 1 (11) 4 (44) 4 (44) 20, 21, 22, 23 2 (50) 1 (25) 1 (25) (External 28, 29, 30, 31, 32, 34 2 (33) 1 (17) 3 (50) 35, 36 1 (50) 1 (50) - 8, 15, 37, 38, 43, 44, 45, 1 1 Maintenance 46 (12.5) 6 (75) (12.5) Management 47, 48, 49, 50 1 (25) 2 (50) 1 (25) *Some KPIs are included in more than one category. The most conservative result was considered in Table 1. 15. References 1. ASME B31.8S, Managing System Integrity of Gas Pipelines 2. W.K. Muhlbauer, Pipeline Risk Management Manual, (2004), Elsevier, ISBN: 978-0-7506-7579-6 3. S. Papavinasam, Corrosion Control in the Oil and Gas Industry, (October 2013), Gulf Professional Publication (Imprint of Elsevier), ISBN: 978-0-1239-7022-0. 4. S. Papavinasam, AIM Corrosion Management: Perfect Key Performance Indicators, NACE Northern Area Western Conference, Calgary, Alberta, Canada, Feb. 24-25, 2015. 5. NACE SP 0206, Internal Corrosion Direct Assessment (Dry Gas) (DG- ICDA), NACE International, Houston, TX. 6. NACE SP0110, Wet Gas Internal Corrosion Direct Assessment, NACE International, Houston, TX. 7. NACE SP0502, Pipeline External Corrosion Direct Assessment, NACE International, Houston, TX. S T E M - C o r r o s i o n, P a p e r # : 2 0 1 5-07, D e c e m b e r 2 0 1 5 P a g e 9 9