NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

Similar documents
THE PMP EXAM PREP COURSE

Earned Value Management - EVM

PMP Exam Prep Coaching Program

PROJECT MANAGEMENT BODY OF KNOWLEDGE

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

Cumulative trends Problems and issues since last report

INSE 6230 Total Quality Project Management

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

Professional Development Seminar Series

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PROJECT COST MANAGEMENT

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

Self-Assessment Questions for Module 07 Project Cost Management

Project Management -- Monitoring the progress

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

next level PMP Exam Preparation Formula Guide for the PMP Exam

Carlos Consulting Group

Lesson 7 The Project Budget

Formulas to Know for EXAM

Thomas Carlos Consulting. Simple Earned Value Management

Earned Value Management Guide

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

Earned Value Management

MMZG 523 PROJECT MANAGEMENT

CPM (College of Performance Management) Meetings have focused on this topic in the last year

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

Introduction to Project Management. Modeling after NYS ITS

Department of Industrial Engineering

Earned Value Formulae

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

Project Management Certification. Multiple Choice Questions

Project Performance Evaluation By Earned Value Method

PMP Exam Preparation Workshop Chapter 7 Project Cost Management

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

CAPM Exam Prep.

A Practical Way To Learn About EVM. ***The Deck Project***

Application of Earned Value Management (EVM) for Effective Project Control

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

A Layman s Guide to Earned Value

Earned Value Management An Overview March 2014

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

The Four Pillars of project management

Application of Earned Value Analysis in Analysing Project Performance

IP-CIS : CIS Project Management

Project Controls Expo 16 th Nov 2016

Predicting Project Completion Date Using Earned Value Management

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

PROJECT BY PROJECT MANAGEMENT T OOLS

Performance measurement

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Monitoring System For Project Cost Control In Construction Industry

Achieve PMP Exam Success Five-Day Course Syllabus

Presenting Earned Value

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

GPE engineering project management. Project Management in an Engineering Context

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

Presenting Earned Value

Project Performance Status Report

A Case for Project Revenue Management. Peter Varani PMP

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Braindumps.PMI-SP.323 questions

IRNOP 2017 Fuzzy Earned Value Management model for uncertain and complex projects. Leila M. Naeni Amir Salehipour

Five-Day Schedule and Course Content

Roberta Tomasini Defense Acquisition University DSN

Gate Value Method Overview document

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

PMP Notes. Project time management

Earned Schedule schedule performance

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP

Earned Value Management Handbook. arne. alu

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

SAMPLE. AACE International Recommended Practice No. 80R-13

Earned Value Management. Danielle Kellogg. Hodges University

Administration. Course Aim. Introductions

Earned Value Management (EVM) and the Acquisition Program

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

THE VALUE OF EARNED VALUE MANAGEMENT

Measuring Time An earned value simulation study

PMI - Dallas Chapter. Sample Questions. March 22, 2002

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Earning Value From Risk

The Value of EVM. Earned Value Management

Project Management Webinar

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA

GEOTHERMAL PROJECT MANAGEMENT

ENGINEERING MANAGEMENT (GE

EARNED VALUE MANAGEMENT. Is it worth the effort?

Long Description. Figure 15-1: Contract Status. Page 1 of 7

Detailed Project Scheduling and Cost Management

Earned Schedule Analysis

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

Homework 6 Questions and Answers

Humphreys &Associates, Inc.

Transcription:

NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

2

3

4

5

6

Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process group): -25% to +75% Definitive (also called Control, often done late in the planning process group): -5% to +10%

8

9

10

11

Budget components 12

13

14

15

Earned Value Key Measures Planned Value (PV): the monetary (e.g. dollar) value of the work that should have been accomplished as of the status date Earned Value (EV): the monetary value of the work that was accomplished as of the status date Actual Cost (AC): the amount of money actually spent to accomplish the work as of the status date

Earned Value Key Measures Planned Value (PV): the monetary (e.g. dollar) value of the work that should have been accomplished as of the status date BAC

Earned Value Key Measures Actual Cost (AC): the amount of money actually spent to accomplish the work as of the status date BAC

Earned Value Key Measures Earned Value (EV): the monetary value of the work that was accomplished as of the status date BAC

Earned Value Key Measures Earned Value (EV): the monetary value of the work that was accomplished as of the status date % complete x PV

Schedule Formulas Schedule Variance (SV): EV-PV Greater than zero indicates ahead of schedule Less than zero indicates behind schedule SV = -

Cost Formulas Cost Variance (CV): EV-AC Greater than zero indicates under budget Less than zero indicates over budget CV = -

Schedule Formulas Schedule Performance Index (SPI): EV/PV Greater than 1 indicates ahead of schedule Less than 1 indicates behind schedule SPI = /

Cost Formulas Cost Performance Index (CPI): EV/AC Greater than 1 indicates under budget Less than 1 indicates over budget CPI = /

25 CAPS

Lab Exercise - EVM A project manager performs Earned Value Analysis and finds the following results: AC: 220,000, PV: 250,000, EV: 220,000. A. CV = 0 B. CV = 30,000 C. CV = -30,000 CV = 1 26

Lab Exercise - EVM A project manager performs Earned Value Analysis and finds the following results: AC: 220,000, PV: 250,000, EV: 220,000. A. CV = 0 B. CV = 30,000 C. CV = -30,00 D. CV = 1 27

28 Lab Exercise - EVM

Lab Exercise - EVM EV = AC CV EV = 4M 500K 29 EV = 3.5 M

Earned Value Forecast Measures and Formulas Estimate To Completion (ETC) The amount of money expected to be spent to complete the remaining work Management ETC: a new, detailed, bottom-up estimate for the remaining work (most accurate) Calculated/Statistical ETC: uses efficiencies to date: (BAC-EV)/CPI (or EAC-AC) Note: calculated ETC should be used to validate, but not replace, more detailed and accurate bottom up methods.

Estimate At Completion (EAC) Estimate At Completion (EAC) The forecasted amount of money estimated to be spent on the entire project Equals BAC before the work begins, but changes as actual spending varies from planned Several different calculations based on the assumptions of the project management team 1. EAC = AC + ETC Most common and accurate. Add the costs to date (AC) plus new bottom-up estimates for remaining work (ETC). Useful when the initial plan is no longer valid: when ETC is expected to be noticeably higher or lower than originally planned

Estimate At Completion (EAC) Formulas 2. EAC = BAC/CPI When past and current cost performance (good or bad) is expected to continue for the rest of the work; a linear relationship between past and future is expected 3. EAC = AC + (BAC-EV) When past and current cost performance (good or bad) differed from planned, but future cost performance is expected to align with planned 4. EAC = AC + [(BAC-EV) / (CPI X SPI)] When the schedule is a factor impacting ETC: (BAC-EV) / (CPI X SPI) CPI and SPI can be assigned different weights such as 50/50, 20/80, etc.

Variance at Completion VAC = BAC EAC The expected difference in money between what the project was originally expected to spend and what the project is currently expected to spend Greater than 0 indicates the project is expected to spend (or if completed, did spend) less money than originally anticipated Less than 0 indicates the project is expected to spend (or if completed, did spend) more money than originally anticipated

To-Complete Performance Index (TCPI) A ratio showing how cost efficient the project needs to be to complete the remaining work with the funds originally established for the project (BAC) TCPI = Remaining Work/Remaining Money. Thus: TCPI = (BAC-EV)/(BAC-AC) Greater than 1 indicates the project is currently overbudget. Less than 1 indicates the project is currently underbudget E.g. A TCPI of 2.0 means the project team needs to get $2 of value for every $1 of money left. For some projects, this would be unachievable, prompting a significant change request to address this shortcoming.

To-Complete Performance Index (TCPI) Alternatively, TCPI can use a revised estimate at completion (EAC) instead of the original BAC. Indicates the necessary efficiency to complete the current EAC TCPI = (BAC-EV)/(EAC-AC) Note: BAC-EV in this formula calculates the remaining work, whereas EAC-AC reflects the remaining money based on an updated cost estimate to complete (EAC)

36 EVM Formulas

37 EVM Formulas

38

Question One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI B. Multiply by SPI C. Multiply by CPI D. Divide by CPI 39

Answer One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI B. Multiply by SPI C. Multiply by CPI D. Divide by CPI 40

Question Estimate at completion (EAC) is a periodic evaluation of: A. The cost of work completed B. The value of work performed C. The anticipated total cost at project completion D. What it will cost to finish the job 41

Answer Estimate at completion (EAC) is a periodic evaluation of: A. The cost of work completed B. The value of work performed C. The anticipated total cost at project completion D. What it will cost to finish the job 42

Question A particular project in the domain of civil construction requires that every on-site worker be insured. Which of the following inputs best conveys this requirement to the Estimate Cost process so that the insurance cost is estimated and subsequently budgeted? 43 A. Enterprise Environmental Factor B. Organizational Process Assets C. Scope Baseline D. Project Management Plan

Answer A particular project in the domain of civil construction requires that every on-site worker be insured. Which of the following inputs BEST conveys this requirement to the Cost Estimation process so that the insurance cost is estimated and subsequently budgeted? A. Enterprise Environmental Factor B. Organizational Process Assets C. Scope Baseline D. Project Management Plan 44

45

46

Quality

48

49

50 Precision

Precision 1/16 51

52 Precision vs. Accuracy

Example Size to be produced: 2 + or -.004 53

Example Size to be produced: 2 + or -.004 54

55 Size to be produced: 2 + or -.004

Example Size to be produced: 2 + or -.004 Results of first process run 40% above range, 20% within range 40% below range 56

57 Plan Quality Management

61

62

63

Fishbone (Ishikawa) diagram

65 Flowcharts

66 Histogram

67

68 Scatter diagrams

69 The 6-Sigma Limit

The 3-Sigma Rule The 3-sigma rule, an empirical rule, states that for normal distribution, almost all values lie within 3 standard deviations of the mean. The values in the normal distribution will exhibit deviation as follows: 70 About 68.27% of the values lie within 1 standard deviation of the mean. About 95.45% of the values lie within 2 standard deviations of the mean. About 99.73% of the values lie within 3 standard deviations of the mean. About 99.98% of the values lie within 6 standard deviations of the mean.

71

72

73

74

75 Project Resource Management

76

77

Org Chart Project Sponsor Project Expeditor Project Manager Project Coordinator Project Team Project Team Project Team 78

79

Organizational Theory McGregor s Theory X and Theory Y Ouchi s Theory, Theory Z Herzburg s Motivation-Hygiene Theory Maslow s Hierarchy of Needs ERG Theory McClelland s Theory of Needs Vroom s Expectancy Theory 80

81

82

84

85 Acquire Project Team

86

87

88