PILGANGOORA UPDATE: EXCELLENT PROGRESS WITH STAGE 1 CONSTRUCTION AND DEVELOPMENT AND DSO OPERATION

Similar documents
PILBARA MINERALS FINALISES AGREEMENT WITH MINERAL RESOURCES

PILBARA MAINTAINS GROWTH MOMENTUM WITH STRONG CUSTOMER SUPPORT TO UNDERPIN FUNDING PACKAGE FOR STAGE 2 PILGANGOORA EXPANSION

For personal use only

SEPTEMBER 2016 QUARTERLY ACTIVITIES REPORT

For personal use only

For personal use only

The following is an Inside Briefing interview with Pilbara Minerals CEO, Mr Neil Biddle

Strong progress on construction and supply contracts puts Battery Minerals on track for commissioning in November

QUARTERLY ACTIVITIES REPORT September 2017

WODGINA ORE RESERVE COMMENTARY

Strategic Entry into the Lithium Market

For personal use only

Pilgangoora: a world class lithium and tantalum project

For personal use only

Pilgangoora: discovery to product shipment in under four years

For personal use only

For personal use only

LARGE STRIKE LENGTH SPODUMENE PEGMATITE DISCOVERED AT MALLINA

For personal use only

14 March ASX Announcements Platform Bridge Street Sydney NSW 2000

Advancing a Portfolio of Lithium Projects

For personal use only. ASX Code: GMM

For personal use only

Charging forward with Lithium. Investor Update. August Pilgangoora Lithium: World Class Near Term Production Project

For personal use only

For personal use only

Developing NT s First Lithium Resource

Sourcing the raw materials of the future

For personal use only

For personal use only

NEWS RELEASE. Equinox Gold Commences Stockpiling of Ore at Aurizona Gold Mine

For personal use only

For personal use only

For personal use only

Strong progress on construction at Montepuez

QUARTERLY ACTIVITIES REPORT PERIOD ENDING 30 SEPTEMBER 2015

Mining Projects to acquire the Pilbara Lithium-Gold Project in WA

AMG Lithium & Tantalum

INVESTOR PRESENTATION

Sourcing the raw materials of the future

O 5. LPS (p) (0.50) (0.036)

March 2018 Quarterly Report 17 April Summary

For personal use only

For personal use only

PHILIP PASCALL CHAIRMAN & CEO ANNUAL GENERAL MEETING

ASX ANNOUNCEMENT. 22 February 2019

BMO 2018 Global Metals and Mining Conference

For personal use only

Kidman signs lithium processing MOU as part of strategy to accelerate Mt Holland project in WA

Developing First Lithium Resource in NT

For personal use only

For personal use only

Pathway to Production

QUARTERLY ACTIVITIES REPORT PERIOD ENDING 30 JUNE 2016

LITHIUM PROJECT TRANSACTION AND $3.6M CAPITAL RAISING

For personal use only

Half Year Financial Results to 31 December 2017

Positive Definitive Feasibility Study for Authier Lithium Project shows potential for a profitable and sustainable new lithium mine

Pilgangoora the world s leading lithium development project. Corporate Presentation 15 May 2017

For personal use only

BALAMA PROJECT UPDATE

For personal use only

Outlook for Australian cathode production

Li 3. Rio Tinto Serbia Highlights Innovating to Develop New Resources. Lithium. From the General Manager

For personal use only

SEPTEMBER 2018 QUARTERLY REPORT

Kennedy Ventures plc Interim Results and First Consignment Leaves Mine

For personal use only

GAINING MOMENTUM: DRILLING TWO HIGH POTENTIAL AUSTRALIAN LITHIUM PROJECTS MARCH 2018 ASX : LTR

Key Highlights. Significant Events Post Quarter End. Outlook

FRONTIER LITHIUM INC. ANNOUNCES POSITIVE PRELIMINARY FEASIBILITY STUDY FOR THE PAK LITHIUM PROJECT, NORTHWESTERN ONTARIO

For personal use only

PJSC Polyus. Financial Results for 1H 2017

For personal use only

For personal use only

For personal use only

JAMBREIRO IRON ORE PROJECT SET TO DELIVER STRONG CASH FLOWS AND RETURNS: PRE-FEASIBILITY STUDY

Authier Lithium Project Advances to the Definitive Feasibility Stage

AMG Advanced Metallurgical Group N.V. January 2018 Investor Update

For personal use only

For personal use only

FINNISS LITHIUM. PROJECT Sydney Resources Round-Up Conference May ASX code: CXO

ANNUAL GENERAL PRESENTATION

ASX ANNOUNCEMENT DEFINITIVE FEASIBILITY STUDY DELIVERS EXCELLENT RESULTS AT PILGANGOORA LITHIUM PROJECT

PROSPECT ANNOUNCES SIGNIFICANT VALUE UPGRADE OF ARCADIA LITHIUM PROJECT FOLLOWING UPDATED PRE-FEASIBILITY STUDY

Cobre Montana NL POWERING A CLEAN ENERGY FUTURE. For personal use only L I T H I U M 1. Presentation to the Annual General Meeting 24 November, 2014

Visible Lithium Mineralisation extended to depth by Diamond Drilling

For personal use only

DEVELOPMENT UPDATE - ATO

China Gold International Annual General Meeting 2013 Financial Growth, Expansion Progress, M&A

Disclaimer. Forward Looking Statements

SAYONA MINING LIMITED AND CONTROLLED ENTITIES

Cobre Montana NL (ASX:CXB)

The Company also announced that executive director Mr Charles Whitfield retired from the Board effective as of 19 August 2016

REPLACEMENT INVESTOR PRESENTATION

For personal use only

FY2017 RESULTS INFORMATION PACK

For personal use only

US$335,000, % Senior Secured Notes Due 2018 (Issued February 2011) Nomura Fixed Income Corporate Day 15 November 2012

Power Metals to Commence Maiden Resource Estimate and Provides Summary of 2018 Exploration Activities at Case Lake

Transcription:

ASX/Media Announcement 27 February 2018 PILGANGOORA UPDATE: EXCELLENT PROGRESS WITH STAGE 1 CONSTRUCTION AND DEVELOPMENT AND DSO OPERATION First spodumene concentrate on track for late Q2 with Stage 1 plant construction and mine development advancing rapidly; establishment of DSO operation underway with first sales expected early Q2 Highlights Plant construction progressing rapidly on multiple fronts. Civil works well advanced with over 3,800m 3 of concrete poured. Structural steel erection commenced in January with over 1,100 tonnes of plant steel (~60% of the total) now landed on site. Mill shell, trunnions, bearings and drive components installed into position. Wet plant commissioning on schedule to start in early Q2. Activities for operational readiness progressing in earnest, including employment of key plant operations staff and ordering of key plant consumables. Mining well underway for both Stage 1 and the DSO operations. Australian lithium developer Pilbara Minerals Limited (ASX: PLS) ( Pilbara or the Company ) is pleased to advise that construction and development of its flagship 100%-owned Pilgangoora Lithium-Tantalum Project ( Pilgangoora Project or Project ) is progressing well and remains on schedule to commence plant commissioning in Q2 2018 and deliver its first spodumene concentrate by late Q2 2018. Civil works are well established with over 3,800m 3 of concrete poured to date. The concrete foundations are now largely complete for priority mechanical areas. Completed areas include: high-pressure grinding rolls (HPGR) vault, wet screen area, heavy media separation (HMS) building, gravity grinding, and concentrate storage infrastructure areas. The crusher pad was recently completed with crusher construction underway, and construction of the tailings storage facility is also progressing well. Construction of the power plant is rapidly taking shape and forecast to be delivered on-schedule by mid-march. First structural steel was erected in late January, with the plant structure now rapidly taking shape. The mill structure is 50% complete with shell, trunnions, bearings and drive components recently installed. To date, over 1,100 tonnes of structural steel have been delivered to site, with over 350,000 site man-hours completed and over 450 people currently on site. Works are continuing on night-shift for certain subsets of the plant construction. Manning will peak over the coming 6 to 8 weeks at over 600 people, in support of the accelerated development schedule negotiated with RCR in the latter part of 2017. In addition to Stage 1 construction efforts, MACA Mining Ltd has mobilised the mining fleet for Direct Shipping Ore (DSO) operations, with the first blast undertaken in late January and mining activities currently progressing to achieve first sales early Q2. Activities for operational readiness are also progressing including ordering of key plant consumables, employment of plant operations staff and maintenance planning. Pilbara Minerals Limited Level 2, 88 Colin Street, P: +61 8 6266 6266 Web: www.pilbaraminerals.com.au ASX Code: PLS West Perth, Western Australia, 6005 F: +61 8 6266 6288 ACN 112 425 788

The commissioning plans are being further refined with the intention of prioritising the fines flotation circuit over the coarse circuit. It is expected that this will assist in speeding up the ramp-up of the processing plant and provide higher early production volumes. Pilbara Minerals Managing Director and CEO, Ken Brinsden, said: It s fantastic to see the Stage 1 development and DSO operation coming to life so quickly. The Pilbara Minerals team has been working closely with our contracting partners to ensure that we achieve our aggressive development targets while continuing to maintain a safe site at all times. I am excited to see the changes as the project rapidly transforms and we march towards first concentrate production late next quarter. PROGRESS PHOTOS Figure 1 Pilgangoora process plant construction 2

Figure 2 Power station generator installation Figure 3 Ball mill construction 3

Figure 4 Tails thickener installation Figure 5 Spodumene concentrate shed under construction 4

Figure 6 Direct Shipping Ore operation mining establishment works 5

Figure 7 First blast of central pit on 30 November 2017 Figure 8 Central pit mining pre-strip (foreground) and Pilgangoora plant site (background). Photo taken 20 February 2018. 6

Additional Information: ABOUT PILBARA MINERALS LIMITED Pilbara Minerals Limited ( Pilbara ASX: PLS) is a mining and exploration company listed on the ASX, specialising in the exploration and development of the specialty metals lithium and tantalum. Pilbara owns 100% of the world class Pilgangoora Lithium-Tantalum Project which is among the largest Spodumene (Lithium Aluminium Silicate) projects in the world. Pilgangoora is also one of the largest pegmatite hosted tantalite resources in the world and Pilbara proposes to produce tantalite as a by-product of its spodumene production. ABOUT LITHIUM Lithium is a soft silvery white metal which is highly reactive and does not occur in nature in its elemental form. It has the highest electrochemical potential of all metals, a key property in its role in Lithium-ion batteries. In nature, it occurs as compounds within hard rock deposits and salt brines. Lithium and its chemical compounds have a wide range of industrial applications resulting in numerous chemical and technical uses. A key growth area is its use in lithium batteries as a power source for a wide range of applications including consumer electronics, power station-domestic-industrial storage, electric vehicles, power tools and almost every application where electricity is currently supplied by fossil fuels. ABOUT TANTALUM The tantalum market is boutique in size with around 1,300 tonnes required each year. Its primary use is in capacitors for consumer electronics, super alloys as in aircraft engines, flat panel displays, surgical instruments and particularly where high melting point, strength, ductility and anti-corrosive performance is required. Contacts: Investors / Shareholders Ken Brinsden Managing Director and CEO Ph. +61 (0)8 6266 6266 Media Nicholas Read Read Corporate Ph. +61 (0)8 9388 1474 FORWARD LOOKING STATEMENTS AND IMPORTANT NOTICE This announcement may contain some references to forecasts, estimates, assumptions and other forward-looking statements. Although the Company believes that its expectations, estimates and forecast outcomes are based on reasonable assumptions, it can give no assurance that they will be achieved. They are indicative and may be affected by a variety of variables and changes in underlying assumptions that are subject to risk factors associated with the nature of the business, which could cause actual results to differ materially from those expressed herein. All references to dollars ($) and cents in this announcement are to Australian currency, unless otherwise stated. Investors should make and rely upon their own enquiries before deciding to acquire or deal in the Company's securities. 7