COSTING AND PROJECT EVALUATION USING NODOC

Similar documents
CHEMICAL ENGINEERING DESIGN & SAFETY

Chemical Process Design / Diseño de Procesos Químicos

SAMPLE. AACE International Recommended Practice No. 16R-90

CAS 13 COST ACCOUNTING STANDARD ON COST OF SERVICE COST CENTRE

Spring Manufacturing Company Sales Budget 2007

SALT Whitepapers. Industrial Processor

COMPOSED AND SOLVED BY (SADIA ALI) MBA

79. PROFILE ON PRODUCTION OF DEXTRIN

322 Roll No : 1 : Time allowed : 3 hours Maximum marks : 100

Analysing cost and revenues

CS Executive Programme Module - I December Paper - 2 : Cost and Management Accounting

ADDENDUM #1 RFQ M1201M. 06/07/13 Please replace Chiller Maintenance Specifications with the attached Chiller Maintenance Specifications.

CHAPTER 9 CAPITAL COST ESTIMATES & FINANCIAL ANALYSIS

195. PROFILE ON THE PRODUCTION OF WATER HEATER

177. PROFILE ON THE PRODUCTION OF METALLIC CONTAINERS

Construction E & O Application

Estimate Considerations. Estimate Considerations

Investment Analysis and Project Assessment

الجامعة التكنولوجية قسم الهندسة الكيمياوية ادارة صناعية

105. PROFILE ON THE PRODUCTION OF INDUSTRIAL FILLERS

Earnings Conference Call. First Quarter 2017 May 3, 2017

Due to the numerous sections and comprehensiveness of this PP/OP, the following index is provided for quick reference and clarity:

70. PROFILE ON THE PRODUCTION OF SODIUM SULPHATE

78. PROFILE ON THE PRODUCTION OF FIBERGLASS REINFORCED PLASTICS

156. PROFILE ON THE PRODUCTION OF BOILER

66. PROFILE ON THE PRODUCTION OF RED OXIDE PAINT

SUNPOWER GROUP LTD. Corporate Presentation August 2016

Fill-in-the-Blank Equations. Exercises

12A Manufacturing. (1)(a) Any person who manufactures, produces, compounds, processes, or fabricates in any manner an article of tangible

Further details of the Proposed Acquisition are set out in the ensuing sections. The Power Plant shall consist of the following key components:

COST ACCOUNTING STANDARD ON MATERIAL COST

Chemical Process Design

Nordic Delivers Record Net Profit for FY2016 of S$ 12.7 million, Up 21%

104. PROFILE ON THE PRODUCTION OF GYPSUM BOARD

FEASIBILITY STUDIES AN INTRODUCTION

Manufacturing Accounts

PAPER 19: COST AND MANAGEMENT AUDIT

Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE

Learning Legacy Document

KPMG Major Projects Advisory Project Leadership Series: Budgeting, Estimating, and Contingency Management for Construction Projects

GENERAL CONTRACTORS GENERAL LIABILITY SUPPLEMENTAL

Summary of 2 nd Edition Changes

Let s trace the budgets through for a company called the Hayes Company. Sales Budget The first budget prepared, comes from the Sales Forecast

Please complete the whole form to the best of your ability, clarifying any areas where necessary and continuing on a separate sheet if required.

TABLE OF CONTENTS. (i) Page

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:

No. 10 Caribbean Community (CARICOM) Dominican Republic Free Trade

Attached please find the cost estimates as requested. Let us know if you have any questions whatsoever.

Paper 8- Cost Accounting

111. PROFILE ON THE PRODUCTION OF AGGREGATES

Construction of the Leased Premises

BPC6C Cost and Management Accounting. Unit : I to V

157. PROFILE ON THE PRODUCTION OF BOLTS AND NUTS

Questionnaire and Proposal for Erection All Risks Insurance

COST MANAGEMENT. discretionary costs, relevant and nonrelevant

Byte Paradigm General Conditions ( Design version)

51. PROFILE ON THE PRODUCTION OF GLYCERIN

Issued by the Association FME-CWM, P.O. Box 190, 2700 AD ZOETERMEER

Procurement Contracting Strategies. Nicola Dimitri IMPPM Rome March-April 2014

186. PROFILE ON THE PRODUCTION OF SHOCK ABSORBER (HYDRAULIC)

[To be published in the Gazette of India, Extraordinary, Part II, Section 3, Subsection GOVERNMENT OF INDIA MINISTRY OF CORPORATE AFFAIRS NOTIFICATION

PROFESSIONAL PROGRAMME EXAMINATION (NEW SYLLABUS) ELECTIVE PAPER BANKING LAW AND PRACTICE MODEL TEST PAPER. Time allowed: 3 hours Max Marks: 100

A&E. Application Form INSURANCE FOR ARCHITECTS & ENGINEERS

BOILER LAW Health and Safety Code, Chapter 755 Administered by the Texas Department of Licensing and Regulation (Effective September 1, 2009)

PTP_Intermediate_Syllabus 2012_Jun2014_Set 1

A&E. Inter-Pacific Insurance Brokers, Inc. APPLICATION FORM INSURANCE FOR ARCHITECTS & ENGINEERS

Contract Pricing Reference Guides Volume 3 Chapter 9 Analysis of Indirect Costs

The amendments to this rule are created pursuant to , and (1)(a) of the Colorado Revised Statutes (CRS).

187. PROFILE ON THE PRODUCTION OF SHOCK ABSORBER (SPRING)

Haldor Topsøe A/S. Annual Report 2011 RESEARCH TECHNOLOGY CATALYSTS. Haldor Topsøe A/S - Nymøllevej Kgs. Lyngby - Denmark CVR No.

2018 Results Conference Call. March 27, 2019

سند پیش ارزیابی 2 ) E4 پروژه طرح جامع برق )پروژه

Decision on the Maximum Reserve Capacity Price proposed by the Independent Market Operator for the 2015/16 Capacity Year

CENVAT Credit Rules, 2004

Item. Metro Contingency and Risk Management

108. PROFILE ON THE PRODUCTION OF ROOF TILES AND BRICKS

Haldor Topsøe A/S. Annual Report 2009 RESEARCH TECHNOLOGY CATALYSTS. Haldor Topsøe A/S - Nymøllevej Kgs. Lyngby - Denmark CVR No.

CH2404 Process Economics Unit V Economic Balance. Dr. M. Subramanian

LIMITED LIFETIME TRANSFERABLE WARRANTY

NODIA AND COMPANY. GATE SOLVED PAPER Chemical Engineering Plant Design and Economics. Copyright By NODIA & COMPANY

Cost Analysis for Pollution Prevention

Limited Revision of CASs

AOA LEAD Conference: 2019 Exhibitor Registration

Overview & Development

INTRODUCTION TO RISK MANAGEMENT FOR CONSTRUCTION PROJECTS. Prof. Reda Abdulaal Vice Presidency for Projects

Rule No. 16 Service Connections, Meters, and Customer s Facilities


Province of British Columbia. BC-23 APPLICATION FOR GAS COST ALLOWANCE For Reporting Production Periods Prior to October 2018 LAND COSTS INCURRED $

BURSA MALAYSIA SECURITIES BERHAD

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

BUSINESS INCOME (AND EXTRA EXPENSE) COVERAGE FORM

183. PROFILE ON ASSEMBLY OF REFRIGERATOR

MTP_Intermediate_Syllabus 2008_Jun2015_Set 2

BUSINESS INCOME (AND EXTRA EXPENSE) COVERAGE FORM

AIG Global Property Construction Risk Engineering

CONTRACTING OPERATIONS INFORMATION

University of Maine System Supplementary Requirements to AIA Document B Standard Form of Agreement Between Owner and Architect

Educational & Performing Arts Center: Downriver Campus

2. Address: (Number) (Street) (City) (Prov) (Postal Code) 3. Is Applicant an Individual Partnership Corporation Other (give details)

Economic and Technical Evaluations for Engineering and Maintenance Projects. Germany, Munich, relexa hotel München.

Transcription:

COSTING AND PROJECT EVALUATION USING NODOC

Three types of Capital cost estimates 1- Preliminary (approximate) estimates 2- Authorization (Budgeting) estimates 3- Detailed (Quotation) estimates

1- Preliminary (approximate) estimates Accuracy typically ± 30 per cent Used in initial feasibility studies and to make coarse choices between design alternatives.

2- Authorization (Budgeting) estimates accuracy typically ± 10-15 per cent used for the authorization of funds

3- Detailed (Quotation) estimates accuracy ± 5-10 per cent used for project cost control and estimates for fixed price contracts These are based on the completed (or near complete) process design, firm quotations for equipment, and a detailed breakdown and estimation of the construction cost.

Fixed capital The total cost of the plant ready for start-up. It is the cost paid to the contractors. It includes the cost of: 1. Design, and other engineering and construction supervision. 2. All items of equipment and their installation. 3. All piping, instrumentation and control systems. 4. Buildings and structures. 5. Auxiliary facilities, such as utilities, land and civil engineering work.

Working capital the additional investment needed, over and above the fixed capital, to start the plant up and operate it to the point when income is earned. It includes the cost of: 1. Start-up. 2. Initial catalyst charges. 3. Raw materials and intermediates in the process. 4. Finished product inventories. 5. Funds to cover outstanding accounts from customers.

Working capital can vary from as low as 5 per cent of the fixed capital for a simple, single-product, process, with little or no finished product storage; to as high as 30 per cent for a process producing a diverse range of product grades for a sophisticated market. A typical figure for petrochemical plants is 15 per cent of the fixed capital.

Fixed capital is a once-only cost that is not recovered at the end of the project life, other than the scrap value. Most of the working capital is recovered at the end of the project. The total investment needed for a project is the sum of the fixed and working capital.

COST ESCALATION (INFLATION) used to update historical cost data makes use of published cost indices. Cost in year A = Cost in year B (Cost index in year A / Cost index in year B)

To get the best estimate, each job should be broken down into its components and separate indices used for labor and materials.

Example: C = 0.45Eq + 0.1Ci + 0.19Cn + 0.26Di where C = the composite index Ci = civil engineering index Cn = site engineering index Di = design index

Caution All cost indices do not necessarily relate the true make-up of costs for any particular piece of equipment or plant; nor the effect of supply and demand on prices

RAPID CAPITAL COST ESTIMATING METHODS 1-Historical costs 2-Step counting methods

1- Historical costs An approximate estimate of the capital cost of a project can be obtained from a knowledge of the cost of earlier projects using the same manufacturing process.

C2 = capital cost of the project with capacity S2, C1 = capital cost of the project with capacity S1. The value of the index n is traditionally taken as 0.6; the well-known six-tenths rule.

Caution Where UK, or other local, indexes and historical exchange rates are available, it is probably better to convert costs to the local currency using the rate of exchange ruling at the date of the costs and update using the local index:

2- Step counting methods Step counting estimating methods provide a way of making a quick, order of magnitude, estimate of the capital cost of a proposed project. The technique is based on the premise that the capital cost is determined by a number of significant processing steps in the overall process. Factors are usually included to allow for the capacity, and complexity of the process: material of construction, yield, operating pressure and temperature.

THE FACTORIAL METHOD OF COST ESTIMATION 1- Lang factors 2- Detailed factorial estimates

Capital cost estimates for chemical process plants are often based on an estimate of the purchase cost of the major equipment items required for the process The other costs being estimated as factors of the equipment cost.

1- Lang factors The fixed capital cost of the project is given as a function of the total purchase equipment cost by the equation = fixed capital cost = the total delivered cost of all the major equipment items: storage tanks, reaction vessels, columns, heat exchangers, etc., = 3.1 for predominantly solids processing plant = 4.7 for predominantly fluids processing plant = 3.6 for a mixed fluids-solids processing plant

2- Detailed factorial estimates To make a more accurate estimate, the cost factors that are compounded into the Lang factor are considered individually

Direct-cost items 1. Equipment erection, including foundations and minor structural work. 2. Piping, including insulation and painting. 3. Electrical, power and lighting. 4. Instruments, local and control room. 5. Process buildings and structures. 6. Ancillary buildings, offices, laboratory buildings, workshops. 7. Storages, raw materials and finished product. 8. Utilities (Services), provision of plant for steam, water, air, firefighting services (if not costed separately). 9. Site, and site preparation.

The contribution of each of these items to the total capital cost is calculated by multiplying the total purchased equipment by an appropriate factor.

Note The accuracy and reliability of an estimate can be improved by dividing the process into sub-units and using factors that depend on the function of the subunits

Indirect costs 1. Design and engineering costs, which cover the cost of design and the cost of engineering the plant: purchasing, procurement and construction supervision. Typically 20 per cent to 30 per cent of the direct capital costs. 2. Contractor s fees, if a contractor is employed his fees (profit) would be added to the total capital cost and would range from 5 per cent to 10 per cent of the direct costs. 3. Contingency allowance, this is an allowance built into the capital cost estimate to cover for unforeseen circumstances (labor disputes, design errors, adverse weather). Typically 5 per cent to 10 per cent of the direct costs.

The capital cost required for the provision of utilities and other plant services will depend on whether a new (green field) site is being developed, or if the plant is to be built on an existing site and will make use of some of the existing facilities.