Budget York Region Rapid Transit Corporation

Similar documents
York Region Rapid Transit Corporation Board of Directors. YRRTC 2018 Multi-Year Capital and Operating Expenditures Budget, Regional Capital Program

York Region Rapid Transit Corporation Board of Directors. YRRTC 2016 Metrolinx Multi-Year Capital Expenditures Budget

Public Transit Infrastructure Fund (PTIF) Phase I Progress Update and Next Steps

Budget York Telecom Network

Proposed Regional Budget

Investing in our Region Investing in our Future

Toronto Transit Commission

Financial Statements and Auditor's Report

Toronto Transit Projects April 25, Jack Collins Vice President, Rapid Transit Implementation

January Ontario Financing Authority

Tax Supported Preliminary Operating Budget. Book 1. Budget Summary Report FCS17001

10 Property Tax Treatment for Regional Transit Facilities

5 Draft 2017 Development Charge Background Study and Proposed Bylaw

Financial Statements and Auditor s Report

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JUNE 19, 2018

TRANSPORT ACTION ONTARIO

% Spent (Capital Budget)

BACKGROUNDER TO REPORT ARE WE THERE YET? The state of transit investment in the Greater Toronto & Hamilton Area

Development Charge Bylaw Directions

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 5, 2011

2018 TTC AND WHEEL-TRANS OPERATING BUDGETS

Frequently Asked Questions

JUNE 2015 STRATEGIC PLAN

Office of the Mayor BUDGET NOTES. What We Do. Why We Do It. Our Successes. Priority Actions

2017 to 2018 Regional Budget

Report Card May 2015 T H I S P L A N I S A V A I L A B L E I N A L T E R N A T E F O R M A T B Y R E Q U E S T

Report to: General Committee Report Date: March 10 th, 2015

This report has been prepared in conjunction with the CEO of the TTC.

Recommended Capital Budget and Plan, and Proposed Capital Forecast

2009 ANNUAL REPORT. Toronto Transit Commission. Vice-Chair Joe Mihevc. Chair Adam Giambrone. Commissioners. As at December 31, 2009.

Appendix A Debt Strategy

BUDGET 2014 Building Modern Infrastructure

Intergovernmental Funding in the Recommended Capital Budget and Plan

Financial Update for the Period Ended June 2, 2018

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 19, 2016

STAFF REPORT INFORMATION ONLY

Report to: Development Services Committee Date: June 26, 2017

3. Household Size and Family Status

Public Transit Services Summary of Submitted 2015 Budget From Rates

PRELIMINARY BUDGET OVERVIEW

Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects

EX31.2al REPORT FOR ACTION

Capital Funding Program Notes ATTACHMENT B. 1. Ontario Bus Replacement Program (OBRP)

Move Ontario Trust Financial Statements For the year ended December 31, 2016

Move Ontario Trust Financial Statements For the period ended September 30, 2017

RANSIT INFRASTRUCTURE NEEDS

FY19 Budget Development -Process -Outreach -Assumptions

Financial Update for the Period Ended April 7, 2018

SHIFT RAPID TRANSIT MASTER PLAN AND BUSINESS CASE RECOMMENDATION

Utility Relocation Innovations vivanext Bus Rapid Transit Projects

Office of the Mayor Budget Summary OPERATING PROGRAM SUMMARY CONTENTS Service Performance N/A

1 LONG TERM FINANCING OF TOM TAYLOR PLACE

City Planning CONTENTS Year Preliminary Capital. 2. Issues for Discussion Performance Preliminary Capital

Infrastructure: The City of Toronto Gap

Report of the Expert Advisory Panel Regarding Transit on Sheppard Avenue East. March 15, 2012

7 Meeting Growth Plan Infrastructure Demands and Financial Sustainability: 2018 Update

1. Introduction Companies

6 Draft 2018 Development Charge Background Study and Proposed Draft Bylaw Amendment

Stage 2 Light Rail Transit Project and Procurement Update. Transportation Services Department

Town of Aurora General Committee Report

For Action. TTC 15-Year Capital Investment Plan & Capital Budget & Plan. Summary

Parks & Urban Forestry Multi-Year Budget

SUBJECT: Capital Program and 10-Year Capital Forecast

3.09. Metrolinx Regional Transportation Planning. Chapter 3 Section. Background

2017 Annual Report Toronto Transit Commission

Implementation of the SmartTrack Stations Program and the Metrolinx Regional Express Rail Program

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 26, 2017

FROM VISION TO RESULTS

Proposed 2014 Budget and Plan

Growth Plan for Greater Golden Horseshoe 2006 Office Consolidation January 2012 Including Amendment 1 to the Growth Plan for the Simcoe Sub-area

Operating Budget Stability Q1 FY17 Financial Update

2014 BUDGET EXECUTIVE SUMMARY 2014 BUDGET

Executive Summary Operating Budget and Forecast

Operating Variance Report for the Year Ended December 31, Deputy City Manager & Chief Financial Officer

3 YORK REGION 2031 POPULATION AND EMPLOYMENT FORECASTS

FORWARD-LOOKING INFORMATION

Capital Budget and Ten Year Capital Plan (Including Capital Amendments)

to 2023 Strategic Plan Development

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 20, 2015

Toronto and Region Conservation Authority - Additional Information for the Long Term Accommodation Project

Budget York Regional Police

Parks & Urban Forestry Multi-Year Budget

Toronto Transit Commission

THE CITY OF VAUGHAN BY-LAW BY-LAW NUMBER

Transportation Services

THE CITY OF VAUGHAN BY-LAW BY-LAW NUMBER

FY2018 Third Quarter Financial Update

2019 Draft Capital Budget and Forecast

Toronto Transit Commission

MEMORANDUM OF AGREEMENT

2019 Business Plan & Budget Vision

Report to: General Committee Date Report Authored: June 1, 2016

Policy for the Deferral of Payment of Development Charges & Planning Application Fees within the Urban Centres

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MARCH 19, SOLID WASTE MANAGEMENT OPERATIONAL REVIEW STATUS UPDATE

Operating Amendments

2 YORK REGION TRANSIT 2008 FARE RATE CHANGE

Solid Waste Management Services

The 2017 Audit Work Plan provides City Council with an overview of how the resources allocated to the Auditor General s Office will be used in 2017.

Executive Summary Operating Budget and Forecast

Toronto Transit Commission

Transcription:

Clause 5 in Report No. 18 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on December 15, 2016. 5 2017-2018 Budget York Region Rapid Transit Corporation 1. Receipt of the presentation by Mary-Frances Turner, President, York Region Rapid Transit Corporation. 2. Adoption of the following recommendations contained in the report dated November 16, 2016 from the Commissioner of Finance recommending that: 1. The Committee of the Whole recommends the budget as submitted for York Region Rapid Transit Corporation as follows: a) The 2017 operating budget and the outlook for 2018, as summarized in Attachment 1 b) The 2017 capital expenditures and the 2017 Capital Spending Authority, as summarized in Attachment 2. 2. The recommended budget be consolidated by the Treasurer for consideration by Council on December 15, 2016. Report dated November 16, 2016 from the Commissioner of Finance now follows: Committee of the Whole 1 York Region Rapid Transit Corporation December 1, 2016

2017-2018 Budget York Region Rapid Transit Corporation 1. Recommendations It is recommended that: 1. The Committee of the Whole recommends the budget as submitted for York Region Rapid Transit Corporation as follows: a) The 2017 operating budget and the outlook for 2018, as summarized in Attachment 1 b) The 2017 capital expenditures and the 2017 Capital Spending Authority, as summarized in Attachment 2. 2. The recommended budget be consolidated by the Treasurer for consideration by Council on December 15, 2016. 2. Purpose This report provides a summary of the 2017-2018 Operating and Capital Budget for York Region Rapid Transit Corporation for consideration by Committee. 3. Background and Previous Council Direction On December 17, 2015 Council approved an operating outlook for 2017 and 2018 As part of the 2016-2018 Budget, Council approved an outlook for the operating budget for 2017 and 2018. This approved outlook formed the starting point for this year s budget. Evolving circumstances and emerging pressures are a natural part of a multi-year budget process. Absent of extraordinary pressures, departments and agencies were expected to stay within their outlook. The 2017-2018 operating budget reflects any revisions that have been made to the previously approved outlook. The 2017 Budget was tabled on November 17, 2016 The consolidated 2017-2018 Operating and Capital Budget was tabled with Council on November 17, 2016. It was received and referred to the December meetings of Committee of the Whole for consideration and recommendation. The 2017 Budget Direction report, approved by Council on May 19, 2016, outlined in the proposed timelines and indicated that the 2017-2018 budget Committee of the Whole 2 York Region Rapid Transit Corporation December 1, 2016

2017-2018 Budget York Region Rapid Transit Corporation would be approved in December 2016, as long as Council is satisfied with it through the review process. A two-year operating budget was tabled for Council s consideration The operating budget presented is a two-year budget that spans the remaining years of Council s term. Council is asked to approve the budget for 2017 and the outlook for 2018. The approved outlook will then form the basis for the budget process next year. Council has the authority to change the budget each year in response to changing circumstances and new information. Multi-year commitments for capital projects are proposed as part of the budget process Many complex capital projects span several years of planning, design and construction, requiring multi-year spending authority. Capital Spending Authority is requested for projects with contractual and other clear or certain multi-year commitments. As in previous years, Council is asked to approve multi-year Capital Spending Authority for capital projects. 4. Analysis and Implications Operating Budget (page 90) Tax levy funds 19% of York Region Rapid Transit total spending The budget shows both the gross operating expenditures (total budget) and the net tax levy (the portion of the budget paid for by the tax levy). York Region Rapid Transit total gross budget for 2017 is $24.9 million. As shown in Graph 1 below, the tax levy pays for 19% of the services provided by the agency. The rest of the funding largely comes from draws from the development charge reserve, which are used to repay debt. Committee of the Whole 3 York Region Rapid Transit Corporation December 1, 2016

2017-2018 Budget York Region Rapid Transit Corporation Graph 1 Gross expenditures of $24.9 million are primarily funded from development charge reserve draws The proposed budget for York Region Rapid Transit Corporation reflects net operating expenditures of $4.7 million in 2017 The 2017-2018 Operating Budget includes the cost of providing: Base services Legislated and contractual requirements Fiscal strategy requirements Impact of capital Growth Service enhancements. The proposed net budget for York Region Rapid Transit Corporation is $4.7 million, or 0.5% of the total 2017 proposed Regional net operating budget as shown in Graph 2 below. Committee of the Whole 4 York Region Rapid Transit Corporation December 1, 2016

2017-2018 Budget York Region Rapid Transit Corporation Graph 2 York Region Rapid Transit accounts for 0.5% of the tax dollar The proposed budget also includes an outlook for 2018. Table 1 in Attachment 1 summarizes the proposed gross and net operating budgets for 2017 and the outlook for 2018. York Region Rapid Transit is within the approved outlook for all years York Region Rapid Transit proposed 2017 budget and outlook for 2018 is within the outlook approved as part of the 2016 to 2018 Budget. Capital Budget (page 92) Approval of the 2017 capital expenditures of $310.4 million and Capital Spending Authority of $442.4 million is requested for York Region Rapid Transit Corporation The capital budget includes new infrastructure projects in support of growth, rehabilitation and replacement of existing infrastructure and service enhancement. The proposed Capital Spending Authority for York Region Rapid Transit Corporation is $442.4 million, or 17% of the total 2017 Capital Spending Authority, as shown below in Graph 3. Committee of the Whole 5 York Region Rapid Transit Corporation December 1, 2016

2017-2018 Budget York Region Rapid Transit Corporation Graph 3 York Region Rapid Transit accounts for 17% of 2017 Capital Spending Authority Attachment 2 summarizes the 2017 Capital Spending Authority by program and shows the associated financing sources for York Region Rapid Transit Corporation. Major initiatives include Facilities & Terminals in support of the Viva bus rapid transit system, the completion of the Spadina Subway, and the planning and design of the Yonge Subway. Details on the individual projects included in the program groups are available in the 2017-2018 Budget book. The budget is informed by Council-approved strategies and plans The 2017-2018 budget for York Region Rapid Transit Corporation reflects the directions and strategies set out in Vision 2051, the York Region Official Plan and the Transportation Master Plan. The budget is also supportive of the objectives outlined in the 2015 to 2019 Strategic Plan. 5. Financial Considerations The net operating budget for York Region Rapid Transit Corporation totals $4.7 million in 2017 and includes an outlook for 2018, as summarized in Attachment 1. Council will have an opportunity to make adjustments to the outlook next year if required. The proposed 2017 Capital Spending Authority reflects a multi-year commitment of $442.4 million, as summarized in Attachment 2. Expenditures not identified as part of Capital Spending Authority, but contained within the Ten-Year Capital Committee of the Whole 6 York Region Rapid Transit Corporation December 1, 2016

2017-2018 Budget York Region Rapid Transit Corporation Plan, are provided for planning purposes and will be brought forward for formal approval in subsequent budget years. 6. Local Municipal Impact The Region provides essential services to the residents and businesses in York Region. The challenge of meeting growing demands for service and improving service delivery is addressed through the Region s business planning process. The Region s investments support local municipalities. 7. Conclusion This report sets out the proposed 2017-2018 budget for York Region Rapid Transit Corporation. To facilitate the completion of the budget process, it is recommended that the Committee s recommendations be forwarded to Council for consideration on December 15, 2016. For more information on this report, please contact Kelly Strueby, Director, Office of the Budget, at ext. 71611. The Senior Management Group has reviewed this report. November 16, 2016 Attachments (2) 7148672 Accessible formats or communication supports are available upon request. Committee of the Whole 7 York Region Rapid Transit Corporation December 1, 2016

2017 to 2018 Budget Summary for York Region Rapid Transit Corporation Proposed Operating Budget Expenditures (in $000s) 2017 Outlook 2018 Outlook Department Page No. Gross Net Gross Net York Region Rapid Transit Corporation 91 24,884 4,667 31,535 4,441 Total 24,884 4,667 31,535 4,441 Note: Net operating expenditures = tax levy Attachment 1 edocs # 7032682

Attachment 2 2017 Capital Expenditures and Capital Spending Authority (CSA) York Region Rapid Transit Corporation York Region Rapid Transit Corporation Page No. 2017 $000s 2017 CSA $000s Project Expenditures: York Region Rapid Transit Corporation 92 310,413 442,420 Total Financing Sources: Debt Reduction Reserve 92 3,438 3,438 Reserves 92 45,807 79,919 Debenture Proceeds 92 117,209 117,209 Development Charge Reserve Draws 92 58,464 91,602 Grants and Subsidies 92 85,485 138,242 Other Recoveries 92 10 12,010 Total Financing Sources 310,413 442,420 edocs #7032640 Page 1 of 1

2017 Multi-Year Capital & Operating Budget Presentation to Committee of the Whole Mary-Frances Turner, President, York Region Rapid Transit Corp. December 1, 2016 1

Overview of Presentation Part 1: Overview of York Region Rapid Transit Corporation and Rapid Transit Achievements Part 2: 2017 Multi-Year Capital and Operating Budget Part 3: Budget Recommendations 2

Part 1: Overview of York Region Rapid Transit Corporation and Rapid Transit Achievements 3

Overview of York Region Rapid Transit Corp. YRRTC a wholly-owned subsidiary of York Region. The Board of Directors comprises of: Executive Management Team 4

Highway 7 East Rapidway Warranty work completed October 2016 5

Geographic Extent Davis Drive Rapidway of the Plans Construction completed November 2016 6 6

Geographic Extent Highway 7 West Rapidway of the Plans Rapidway east of Jane Street complete December 2016 7

Highway 7 West Rapidway - Vaughan Metropolitan Centre vivastation Construction on the VMC Spadina Subway vivastation started in August 2016 and will open in early 2018 8

Yonge Street Rapidway Utility work is ongoing gas main work completed in Newmarket, Telecommunications & hydro work continues along Yonge Street 9 9

Hwy. 7, Bathurst and Centre Street Rapidway Bathurst Street water main replacement work is complete Centre Street water main replacement and gas main 10 installation under way

Operations, Maintenance and Storage Facility LEED Silver certification received September 2016 11 11

Cornell Station Design and engineering underway, and the Construction Contract will be procured in early 2017 12

SmartREIT Terminal VMC Station Construction Contract awarded October 2016 13 13

Toronto-York Spadina Subway Extension Station work at Pioneer Village, 407, and the Vaughan Toronto Transit Commission 2016 Metropolitan Centre Stations are approximately 90% complete 14

Yonge Subway Extension > The Yonge North Subway Extension project is moving forward with preliminary engineering 15

Rapid Transit Funded Program, $3.6B 16

Rapid Transit Funded Program, $3.6B TYSSE Project in the Region $1.3B BRT Rapidways, Facilities and Terminals $2.3B 17

10-Year Capital Program, $6.1B 18

Part 2: 2017 Multi-Year Capital and Operating Budget 19

Proposed Regional Budget at a Glance Approved in 2016 (for 2017) Proposed in 2017 (for 2017) Operating Budget $4.9M $4.7M Pages 85, 90 Ten-Year Capital Plan $146.4M $442.4M 2017 Capital Spending Authority $135.9M $442.4M Pages 85, 92 2017 Capital $93.4M $310.4M 20

Operating Budget Summary 2016 Approved 2017 Proposed 2018 Outlook Operating Expenditures ($M) 35.3 39.0 45.6 Allocations and Recoveries ($M) (11.1) (14.1) (14.1) Gross Expenditures ($M) 24.2 24.9 31.5 Non-Tax Revenues ($M) (16.3) (20.2) (27.1) Net Expenditures / Tax Levy ($M) 7.9 4.7 4.4 Increase/(Decrease) (Year-over-Year) 2016 Approved Outlook Total FTEs * New FTEs * - 48.0 - (40.8%) (40.8%) 48.0 - (4.8%) (4.8%) 48.0 - Top two charts on Page 90 Middle graph on Page 85 2016 Approved Outlook New FTEs * - - - * FTEs = Regular Full-Time Staff at YRRTC; Temporary Full-Time Staff not included 52 21

Operating Budget Summary 4-year Operating Budget Spending Middle graph on 22 Page 85

2017 Gross Operating Budget YRRTC Gross Operating Budget $24.9M YRRTC Funding Sources $24.9M YRRTC Staff & Admin. => $2.5M Net Financing costs => $2.2M Top graphs on 23 Page 85

2017 Net Operating Budget YRRTC Net Operating Budget $4.7M Other Regional Services 99.5% 24 Page 42

Proposed Capital Budget Capital Plan & Budget ($ Millions) Regional Appendix section Total Regional Funded Program $1,694.6 Ten-Year Capital Plan $442.4 Page 261 Top chart 2017 Capital Spending Authority $442.4 Page 92 2017 Capital $310.4 25

2017 CSA and Funding Sources, $442.4M YRRTC 10-Year Capital Plan & CSA $442.4 Million YRRTC Funding Sources $442.4 Million Bottom charts on 26 Page 92

2017 CSA, $442.4M Appendix section on Appendix section on Page 261 Page 263 Total Capital Programs $1.695 billion Total York Region Funded $764.8M Capital Spending Authority $442.4M York Region Funded $292.2M 27

2017 CSA: Facilities & Terminals, $63.2M OMSF $0.3M Cornell Terminal $21.2M SmartREIT Terminal VMC $32.9M Park n Ride Facilities $8.9M Park n Ride Facility at Warden Ave. & Enterprise Dr. Other Facilities along Highway 7 West and Yonge St. under review 28

2017 CSA: TYSSE, $287.1M Total TYSSE $3.184 Billion TYSSE $1.275 Billion 29

2017 CSA: Yonge Subway Extension, $91.3M Key Objectives to Move Yonge Subway Extension Forward Establish interim governance and project management structure Execute memorandum of agreement Build project team organization Finalize work program Issue preliminary engineering study request for proposal [RFP] Establish communications & community relations plan Procure advisory services Secure PTIF funding Develop activity stream work plans Establish formal governance and project management structure 30

Ten-Year Capital Plan and Capital Spending Authority 2016 Capital Expenditures * $1,252.2M * 2017 Capital Spending Authority * $442.4M * Bottom graph on 31 Page 85

Part 3: Budget Recommendations 32

Budget Recommendations 1. The Committee of the Whole recommends the budget as submitted for YRRTC as follows: a) The 2017 operating budget and the outlook for 2018, as summarized in Attachment 1 a) The 2017 Capital Expenditures and Capital Spending Authority, as summarized in Attachment 2 2. That the recommended budget be consolidated by the Treasurer for consideration by Council on December 15, 2016 33

Thank you 34