July 9, Advice Letters: 3050-E

Similar documents
SUBJECT: Establishment of Demand Response Load Shift Working Group Memorandum Account in Compliance with Decision

September 22, Advice Letter 3033-E

SUBJECT: Establishment of the Avoided Cost Calculator Memorandum Account in Compliance with Decision

Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770

SUBJECT: Modification of the Distribution Resources Plan Memorandum Account Pursuant to Decision

Advice Letters 3072-E and 3072-E-A

Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770

January 26, Advice Letter 3721-E

March 15, Advice Letter 3543-E

June 11, 2018 Advice Letter 3803-E. SUBJECT: Qualified Nuclear Trust Investment Management Agreement with NISA Investment Advisors, LLC

March 17, 2008 Advice Letter 2211-E

SUBJECT: Establishment of the Distribution Resources Plan Demonstration Balancing Account (DRPDBA) Pursuant to Decision

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION

October 26, 2017 Advice Letter 3665-E

SUBJECT: Establishment of the Aliso Canyon Energy Savings Assistance Program Memorandum Account in Response to the Aliso Canyon Emergency

SUBJECT: SCEs Request for Cancellation of Plug Load and Appliances (PLA) Subprogram - Appliance Recycling Program (ARP)

SUBJECT: Request for an Amendment to SCE's Bundled Procurement Plan Appendix D.

April 29, Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, CA Dear Ms. Megan Scott-Kakures,

Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770

SUBJECT: Establishment of the Transportation Electrification Portfolio Balancing Account Pursuant to D

January 31, 2006 ADVICE 1960-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

February 26, 2018 Advice Letter 3926-G/5214-E

November 14, 2005 ADVICE 1929-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION

May 25, Revisions to Southern California Edison s Critical Peak Pricing Programs for Large Customers with Demands Above 200 kw

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION

Akbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770

Russell G. Worden Director, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, CA 91770

SUBJECT: Deviation to SCE's Added Facilities Agreement - Applicant Financed (Form ) for Fort Irwin

Feburary 28, 2006 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

Enclosed are copies of the following revised tariff sheets for the utility s files:

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION

January 29, 2018 Advice Letter 5133-G

request for approval of Telecommunication leases between SCEC and MCImetro access transmission services LLC pursuant to GO 173 Accepted

Southern California Edison IEC (Corp ID 6096) Status of Advice Letter 128 As of January 21, Disposition: Effective Date: Accepted

April 3, Megan Scott-Kakures Vice President, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, CA 91770

January 22, Establishment of Smart Energy Program and Modification of Summer Discount Plan in Compliance with Decision

April 4, 2014 Advice Letter 4616-G

June 10, 2005 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

September 5, 2006 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

November 16, Advice Letter 5178-A

April 3, Advice 4085-G/5517-E (Pacific Gas and Electric Company ID U 39 M) Public Utilities Commission of the State of California

July 17, 2013 Advice Letter 4504

SUBJECT: System-wide Curtailment Effective February 20, 2018 through March 6, 2018.

Subject: Core Pricing Flexibility and Noncore Competitive Load Growth Opportunities Programs

January 12, 2017 Advice Letter 5070

February 19, Revisions to SCE s 2008 Santa Catalina Island Water Revenue Requirement

September 22, Establishment of Southern California Edison Company s Credit/Debit Card Bill Payment Option

September 16, 2015 Advice Letter 4845

March 13, Advice Letter 218-G/3730-E

August 15, 2017 Advice Letter 5167-G

July 1, 2015 Advice Letter: 4814-G. Advice Letter 4814-G is effective as of June 29, 2015 with corresponding Tariffs effective as of July 1, 2015.

New Mexico Public Regulation Commission P. O. Box Paseo de Peralta Santa Fe, New Mexico 87504

December 11, 2006 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

June 5, Advice No (U 904 G) Public Utilities Commission of the State of California. Subject: Schedule No. G-CPS May 2018 Cash-Out Rates

December 5, Advice No (U 904 G) Public Utilities Commission of the State of California

November 14, 2014 Advice Letters: 4582-G 4582-G-A. SUBJECT: Establishment of Rule No. 43, OBR Tariff in Compliance with D.

August 11, Supplemental Filing to Advice 3088-E, Establishment of the Mobilehome Park Conversion Program in Compliance with Decision

HOLY CROSS ENERGY November 3, 2015 GENERATOR INTERCONNECT POLICY

New York State Public Service Commission

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems

May 30, Advice Letter 3444-E

December 14, 2016 Advice Letter 5053

October 30, Advice 2839-E-A (Pacific Gas and Electric Company U 39 E) Public Utilities Commission of the State of California

December 14, Modifications to Regulatory Mechanisms Established in Accordance with Decision and Decision

November 20, Advice Letter: 3014-E

June 30, 2015 ADVICE 3241-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

July 7, 2015 Advice Letters: 4668-G & 4718-G. SUBJECT: Request for Approval of Interruptible Transportation Capacity Contracts with Affiliates

December 23, 1998 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation

March 7, 2018 Advice Letter 5234-G. SUBJECT: Modification of the New Environmental Regulation Balancing Account (NERBA).

April 8, 2005 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION. Revision to the Energy Resource Recovery Account

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation

March 1, 2013 Advice Letter 2841-E

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Rule 22 Sheet 1 DIRECT ACCESS

SUBJECT: PG&E, SCE, and SDG&E's Proposed Modifications to Rule 24 and Related Documents

ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex

Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial

August 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation

August 25, Advice Letter 4677-E

October 5, 2017 Advice Letter 3488-E

January 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

February 25, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the LGIA.

October 24, 2000 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

February 1, 2018 Advice Letter 5233-G. SUBJECT: Revision of Gas Preliminary Statements to Implement New Accounting Guidance Principles

May 15, 2013 ADVICE 88-W (U 338-W) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

December 11, 2003 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

September 13, Advice Letter 3452-E

May 17, 2002 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

January 31, 2003 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

Advice Letters 2311-E and 2311-E-A

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

SUBJECT: Adjustment of Existing Income Limitations for CARE and FERA, and Modification of Applicable Forms

Transcription:

STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 July 9, 2014 Advice Letters: 3050-E Megan Scott-Kakures Vice President, Regulatory Operations Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, California 91770 SUBJECT: Revisions to SCE s Rule 21 Tariff and Associated Forms Dear Ms. Scott-Kakures: Advice Letter 3050-E is effective as of July 9, 2014. Sincerely, Edward Randolph, Director Energy Division

Megan Scott-Kakures Vice President, Regulatory Operations June 9, 2014 ADVICE 3050-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revisions to SCE s Rule 21 Tariff and Associated Forms In compliance with Decision (D)14-04-003 (Decision) Decision Adopting Revisions to Electric Tariff Rule 21 to Include a Distribution Group Study Process and Additional Tariff Forms, Southern California Edison Company (SCE) hereby submits for filing the following changes to its tariffs. The revised tariff sheets and filed forms are listed on Attachment A and are attached hereto. PURPOSE Pursuant to D.14-04-003, SCE requests approval of its revised Rule 21 tariff, revised Generating Facility Interconnection Application (Form 14-732) and Rule 21 Exporting Generating Facility Interconnection Request (Form 14-918) and the establishment of three new forms Rule 21 Generator Interconnection Agreement for Exporting Generating Facilities Interconnecting Under the Independent Study, Distribution Group Study, or Transmission Cluster Study Process (Form 14-925); Rule 21 Detailed Study Agreement (Form 14-926); and Pre-Application Report Request (Form 14-922). In addition, SCE is including the transition plan for transitioning interconnection requests submitted prior to the effective date of the revised Rule 21 tariff. BACKGROUND Rule 21 describes the interconnection requirements and cost allocation for generating facilities to be connected to the utilities distribution and transmission systems over which the California Public Utilities Commission (Commission or CPUC) has jurisdiction. In Rulemaking (R.)11-09-011, the Commission sought to review Rule 21 to ensure that the interconnection process was timely, non-discriminatory, cost-effective, and transparent. Under the existing terms of Rule 21, many projects seeking interconnection to the distribution system must be studied serially, in a first-come, P.O. Box 800 8631 Rush Street Rosemead, California 91770 (626) 302-6855 Fax (626) 302-4829

ADVICE 3050-E (U 338-E) - 2 - June 9, 2014 first-served process. This process is referred to as the Independent Study Process (ISP). In D.14-04-003, the Commission concluded that the ISP can be time consuming and that the costs are not distributed among electrically interdependent applicants. The Distribution Group Study Process (DGSP), as adopted in D.14-04-003, provides a more equitable, efficient, and timely approach to the current options for interconnection under Rule 21. This new process will, among other things, promote timeliness, the nondiscriminatory processing of interconnection applications, improve cost-effectiveness, and increase transparency. As a result, the interconnection process for distributed generation will better accommodate increases in applications for interconnection by small distributed generation under California s Renewables Portfolio Standard Program. PROPOSED TARIFF CHANGES Pursuant to D.14-04-003, SCE submits for Commission approval: (1) revised Electric Tariff Rule 21, (2) revised Generating Facility Interconnection Application (Form 14-732), (3) revised Rule 21 Exporting Generating Facility Interconnection Request (Form 14-918), (4) Rule 21 Generator Interconnection Agreement for Exporting Generating Facilities Interconnecting Under the Independent Study, Distribution Group Study, or Transmission Cluster Study Process (Form 14-925), (5) Rule 21 Detailed Study Agreement (Form 14-926), 1 and (6) Pre-Application Report Request (Form 14-922). I. Revisions to Rule 21 SCE has modified Rule 21 consistent with D.14-04-003 Ordering Paragraph 1 and Conclusion of Law 11. Ordering Paragraph 1 directs SCE to file a revised Rule 21 that is substantially similar to the terms and conditions set forth in Pacific Gas and Electric Company s (PG&E) and San Diego Gas & Electric Company s (SDG&E) February 19, 2013 draft tariff proposal (as revised by their March 22, 2014 comments). SCE has complied with this instruction. Subparts 1.a through 1.g of this Ordering Paragraph direct SCE to make additional modifications. Conclusion of Law 11 states that [a]dditional changes to promote the general accessibility of Rule 21 are encouraged and may be included in this same advice letter filing. SCE has made modifications consistent with the Commission s direction, and these modifications are described below. 1 Please note that the Rule 21 ISP Study Agreement Form identified in Ordering Paragraph 5 of D.14-04-003 has been renamed as the Detailed Study Agreement Form to reflect its applicability for both the ISP and the DGSP.

ADVICE 3050-E (U 338-E) - 3 - June 9, 2014 a. Ordering Paragraph 1.a Ordering Paragraph 1.a directs SCE to ensure that the proposed revisions to Rule 21 are substantially similar in substance and format to PG&E s and SDG&E s February 19, 2013 draft tariff proposal. SCE has complied with this instruction, and all proposed modifications to Rule 21 are substantially similar in substance and format. b. Ordering Paragraph 1.b Ordering Paragraph 1.b directs SCE to incorporate a DGSP into Rule 21 that include[s] two fixed-date windows each calendar year for receipt of requests for the group study process, and these open window dates shall be published at least 60 days in advance in a prominent location on their websites. SCE has modified the tariff in Section E.2.c to include the two fixed date open window each calendar year for receipt of requests for the DGSP. The first window will open on March 1 and close on March 31. The second window will open on September 1 and close on September 30. Pursuant to Section E.2.c, SCE will publish these open window dates at least 60 days in advance in a prominent location on its website. c. Ordering Paragraph 1.c Ordering Paragraph 1.c directs SCE to revise its Rule 21 to identify the events that may trigger extensions to the Distribution Group Study Process timeline and include (1) the events resulting in extensions, (2) the expected length of the extensions, and (3) the method to be relied upon to notify group study applicants of timeline extensions. SCE has modified Rule 21 in Section F.3.c.xvi to identify the events that may trigger extensions to the timeline, the expected length of the extensions and the method upon which to notify group study applicants of timeline extensions d. Ordering Paragraph 1.d Ordering Paragraph 1.d directs SCE to revise its Rule 21 to confirm that Phase 1 and Phase 2 study reports will include the type of costs triggered by applicants within a group study and whether these identified costs are shared costs to be allocated on a per kva basis or based on specific contribution. SCE has modified Section E.4.e to confirm that the DGSP Phase I and Phase II study reports will indicate how cost allocation is determined. e. Ordering Paragraph 1.e Ordering Paragraph 1.e directs SCE to revise its Rule 21 to incorporate: (1) a timeline identifying the amount of any required deposit and at what point in the process deposits are forfeited if an applicant drops out of the group, (2) a 60-day re-study timeline in the event a re-study is required after an applicant drops out of the group, and (3) that forfeited funds return to the group to cover future expenses in the event an applicant drops out of the group and any funds remaining at the conclusion of the group study

ADVICE 3050-E (U 338-E) - 4 - June 9, 2014 process being allocated to individual applicants in the group on a per kva basis. SCE has modified Rule 21 as follows: The timeline for Detailed Study deposits as well as the required deposit amounts are identified in Sections E.2.c., E.3.a., F.3.c.viii and Table E-1 under Section E.2.c. Section E.3.a.ii(3) outlines the point in the process that Detailed Study deposits become non-refundable and forfeited if an Applicant withdraws. Section F.3.c.xv outlines the 60-day re-study timeline in the event a re-study is required after an applicant drops out of the group. Section E.3.a.iii.(2) outlines how forfeited funds return to the group to cover future expenses in the event an applicant drops out of the group and how any funds remaining at the conclusion of the group study process will be allocated to individual applicants in the group on a per kva basis. f. Ordering Paragraph 1.f Ordering Paragraph 1.f directs SCE to revise Rule 21 to incorporate minor changes into Rule 21 as follows: (1) cross references to indicate the location and name of all the appropriate forms, (2) more specific identification of behind the meter components on their interconnection application forms, and (3) a modification to the pre-application report request or supplemental review process, which may include an associated cost, to provide applicants with the option of requesting the utility to determine whether the proposed interconnection requires a Direct Transfer Trip. SCE has added Appendix A to Rule 21 that identifies the name and form number of all Commission-approved forms that are relevant to the Rule 21 interconnection process and provides a cross reference for where such forms can be located. SCE has modified Generating Facility Interconnection Application (Form 14-732) and Rule 21 Exporting Generating Facility Interconnection Request (Form 14-918) to address more specific identification of behind the meter components. Attached as Appendix D is a redline of Form 14-732, and attached as Appendix E is a redline of Form 14-918. These redlines reflect changes made pursuant to Ordering Paragraph 1.f. SCE has modified Section F.2.b.ii, which revises the Supplemental Review to provide applicants with the option of requesting the utility to determine whether the proposed interconnection requires a Direct Transfer Trip. 2 2 This proposed tariff language was developed during the California Energy Commission s Synchronous Generator Working Group.

ADVICE 3050-E (U 338-E) - 5 - June 9, 2014 g. Ordering Paragraph 1.g Ordering Paragraph 1.g directs SCE to develop a transition plan, if warranted, for moving pending applications into the DGSP to the extent they are eligible for the DGSP. Attached as Appendix F is SCE s proposed transition plan. 3 h. Conclusion of Law 11 Conclusion of Law 11 of D.14-04-003 states: Minor changes to Rule 21 will improve its accessibility and should be included in the Tier 2 Advice Letter filing required by today s decision. Additional changes to promote the general accessibility of Rule 21 are encouraged and may be included in this same advice letter filing. SCE, in coordination with PG&E and SDG&E, has proposed modifications to multiple sections of Rule 21 to improve accessibility and promote clarity. Such modifications are substantially similar to modifications proposed by PG&E and SDG&E. These proposed modifications are summarized in the attached Appendix A. II. Revisions to Forms Ordering Paragraph 5 instructed SCE to submit the following forms adopted by D.14-04-003: (1) Electric Tariff Rule 21 (Rule 21) Generator Interconnection Agreement for Exporting Generation Facilities Interconnecting Under the Transmission Cluster Study or Independent Study Process (Rule 21 Cluster/ISP GIA); (2) Rule 21 Independent Study Process Study Agreement (Rule 21 ISP Study Agreement); and (3) Rule 21 Pre-Application Report Request. In addition, Ordering Paragraph 5 instructed SCE to revise its forms, as needed, to conform to the revisions to Rule 21 adopted by D.14-04-003 regarding the DGSP. SCE has revised the Rule 21 Cluster/ISP GIA to incorporate Interconnection Requests that were studied under the DGSP. SCE has also modified Section 18.3.4 to reduce the minimum combined single limit per occurrence for Excess Public Liability Insurance (from $20,000,000 to $1,000,000 per MW) to conform this minimum with the minimum requirement identified in SCE s Wholesale Distribution Access Tariff (WDAT) GIAs. SCE made this change to promote consistency and synergy with its WDAT. Such revisions are substantially similar in format and substance to the analogous agreements proposed by PG&E and SDG&E. SCE has renamed this document the Rule 21 Generator Interconnection Agreement for Exporting Generating Facilities Interconnecting Under the Independent Study, Distribution Group Study, or Transmission Cluster Study Process. Attached as Appendix B is a redline that reflects 3 SCE notes that, as of June 9, 2014, there are no pending applications in its current Rule 21 interconnection process that are eligible for such a transition.

ADVICE 3050-E (U 338-E) - 6 - June 9, 2014 all modifications that were made compared to the Rule 21 Cluster/ISP GIA that was approved by D.14-04-003. SCE has revised Rule 21 ISP Study Agreement to incorporate the DGSP. Such revisions and modifications are substantially similar in format and substance to the analogous agreements proposed by PG&E and SDG&E. SCE has renamed this document the Rule 21 Detailed Study Agreement (Form 14-926). Attached as Appendix C is a redline that reflects all modifications that were made compared to the Rule 21 ISP Study Agreement that was approved by D.14-04-003. In addition, as noted above in Section I.f, SCE has revised its Rule 21 Generating Facility Interconnection Application (Form 14-732) and its Rule 21 Exporting Generating Facility Interconnection Request (Form 14-918) to meet the requirements of Ordering Paragraph 1.f.(2) to provide more specific identification of behind the meter components on its interconnection application form. Attached as Appendix D is a redline of Form 14-732, and attached as Appendix E is a redline of Form 14-918. These redlines reflect changes made pursuant to Ordering Paragraph 1.f. No cost information is required for this advice filing. This advice filing will not increase any rate or charge, cause the withdrawal of service, or conflict with any other schedule or rule. TIER DESIGNATION Pursuant to Ordering Paragraphs 1 and 5 of D.14-04-003, this advice letter is submitted with a Tier 2 designation. EFFECTIVE DATE This advice filing will become effective on July 9, 2014, the 30 th calendar day after the date filed. NOTICE Anyone wishing to protest this advice filing may do so by letter via U.S. Mail, facsimile, or electronically, any of which must be received no later than 20 days after the date of this advice filing. Protests should be mailed to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, California 94102 E-mail: EDTariffUnit@cpuc.ca.gov Copies should also be mailed to the attention of the Director, Energy Division, Room 4004 (same address above).

ADVICE 3050-E (U 338-E) - 7 - June 9, 2014 In addition, protests and all other correspondence regarding this advice letter should also be sent by letter and transmitted via facsimile or electronically to the attention of: Megan Scott-Kakures Vice President, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, California 91770 Facsimile: (626) 302-4829 E-mail: AdviceTariffManager@sce.com Leslie E. Starck Senior Vice President, Regulatory Policy & Affairs c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2030 San Francisco, California 94102 Facsimile: (415) 929-5544 E-mail: Karyn.Gansecki@sce.com There are no restrictions on who may file a protest, but the protest shall set forth specifically the grounds upon which it is based and shall be submitted expeditiously. In accordance with Section 4 of General Order (GO) 96-B, SCE is serving copies of this advice filing to the interested parties shown on the attached GO 96-B and R.11-09-011 service lists. Address change requests to the GO 96-B service list should be directed by electronic mail to AdviceTariffManager@sce.com or at (626) 302-2930. For changes to all other service lists, please contact the Commission s Process Office at (415) 703-2021 or by electronic mail at Process_Office@cpuc.ca.gov. Further, in accordance with Public Utilities Code Section 491, notice to the public is hereby given by filing and keeping the advice filing at SCE s corporate headquarters. To view other SCE advice letters filed with the Commission, log on to SCE s web site at https://www.sce.com/wps/portal/home/regulatory/advice-letters. For questions, please contact Ingrid Vigh at (626) 302-7383 or by electronic mail at Ingrid.Vigh@sce.com. Southern California Edison Company MSK:iv:sq Enclosures /s/ MEGAN SCOTT-KAKURES Megan Scott-Kakures

CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/cpuc Utility No.: Southern California Edison Company (U 338-E) Utility type: Contact Person: Darrah Morgan ELC GAS Phone #: (626) 302-2086 PLC HEAT WATER E-mail: Darrah.Morgan@sce.com E-mail Disposition Notice to: AdviceTariffManager@sce.com EXPLANATION OF UTILITY TYPE ELC = Electric GAS = Gas PLC = Pipeline HEAT = Heat WATER = Water (Date Filed/ Received Stamp by CPUC) Advice Letter (AL) #: 3050-E Tier Designation: 2 Subject of AL: Revisions to SCE s Rule 21 Tariff and Associated Forms Keywords (choose from CPUC listing): Compliance, Forms, Rules, Agreements AL filing type: Monthly Quarterly Annual One-Time Other If AL filed in compliance with a Commission order, indicate relevant Decision/Resolution #: D.14-04-003 Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: Summarize differences between the AL and the prior withdrawn or rejected AL: Confidential treatment requested? Yes No If yes, specification of confidential information: Confidential information will be made available to appropriate parties who execute a nondisclosure agreement. Name and contact information to request nondisclosure agreement/access to confidential information: Resolution Required? Yes No Requested effective date: 7/9/14 No. of tariff sheets: -169- Estimated system annual revenue effect: (%): Estimated system average rate effect (%): When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting). Tariff schedules affected: Service affected and changes proposed 1 : Rule 21; Forms 14-732, 14-918, 14-922, 14-925, and 14-926; and Table of Contents Pending advice letters that revise the same tariff sheets: 2952-E 1 Discuss in AL if more space is needed.

Protests and all other correspondence regarding this AL are due no later than 20 days after the date of this filing, unless otherwise authorized by the Commission, and shall be sent to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, California 94102 E-mail: EDTariffUnit@cpuc.ca.gov Megan Scott-Kakures Vice President, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, California 91770 Facsimile: (626) 302-4829 E-mail: AdviceTariffManager@sce.com Leslie E. Starck Senior Vice President, Regulatory Policy & Affairs c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2030 San Francisco, California 94102 Facsimile: (415) 929-5544 E-mail: Karyn.Gansecki@sce.com

PROCEDURES FOR TRANSITIONING INTERCONNECTION REQUESTS SUBMITTED PRIOR TO THE EFFECTIVE DATE OF THE REVISED RULE 21 TARIFF I. Objective a. The objective of this transition plan is to set forth procedures for the transition of existing Rule 21 Interconnection Requests that may be eligible for the Distribution Group Study Process to the Revised Rule 21 1 II. III. Definitions a. Capitalized terms shall have the meaning set forth in the Revised Rule 21 Transition of Interconnection Requests of Existing Rule 21 Applicants a. General: i. The tariff sections referred to here are for convenience and do not imply that other applicable provisions of the Revised Rule 21 do not apply. ii. Section references refer to the Revised Rule 21 unless otherwise noted. b. Applicants that have a queue date on or before the Effective Date of the Revised Rule 21, and pass Screen Q but fail Screen R, shall be processed as follows: i. If Applicant elected to proceed directly to the Transmission Cluster Study Process and withdrew from Rule 21 on or before the Effective Date of the Revised Rule 21, Applicant shall continue to be processed pursuant to Section F.3.d (Transmission Cluster Study Process). ii. If Applicant elected to proceed under the Independent Study Process and executed an Independent Study Process Study Agreement on or before the Effective Date of the Revised Rule 21, Applicant shall continue to be processed pursuant to Section F.3.b (Independent Study Process). iii. All other Applicants shall be processed pursuant to Section F.3.c (Distribution Group Study Process). c. Notification: i. Within 10 Business Days of the Effective Date of the Revised Rule 21, SCE shall provide written notice to all Applicants subject to Section III.b.iii of this transition plan: (1) providing the Applicant a copy of this transition plan; (2) confirming the Applicant s applicable Detailed Study Interconnection Review Process; and (3) citing the Rule 21 Detailed Study Interconnection Review Process provisions now applicable to the Applicant. 2 1 Revised Rule 21 refers to the version of Rule 21 submitted via Advice Letter on June 9, 2014 pursuant to Decision 14-04-003. 2 As of June 9, 2014, SCE has no Interconnection Requests that would be subject to this transition plan.

Public Utilities Commission 3050-E Attachment A Cal. P.U.C. Sheet No. Title of Sheet Cancelling Cal. P.U.C. Sheet No. Revised 54718-E Rule 21 Original 50572-E Revised 54719-E Rule 21 Original 50573-E* Revised 54720-E Rule 21 Original 50574-E Revised 54721-E Rule 21 Original 50575-E Revised 54722-E Rule 21 Original 50576-E Revised 54723-E Rule 21 Original 50577-E Revised 54724-E Rule 21 Original 50578-E Revised 54725-E Rule 21 Original 50579-E Revised 54726-E Rule 21 Original 50580-E* Revised 54727-E Rule 21 Original 50581-E Revised 54728-E Rule 21 Original 50582-E Revised 54729-E Rule 21 Original 50583-E* Revised 54730-E Rule 21 Original 50584-E Revised 54731-E Rule 21 Original 50584-E Original 50585-E Revised 54732-E Rule 21 Original 50586-E Revised 54733-E Rule 21 Original 50587-E Revised 54734-E Rule 21 Original 50588-E Revised 54735-E Rule 21 Original 50589-E Revised 54736-E Rule 21 Original 50590-E Revised 54737-E Rule 21 Original 50591-E Revised 54738-E Rule 21 Original 50592-E Revised 54739-E Rule 21 Original 50593-E Revised 54740-E Rule 21 Original 50594-E Revised 54741-E Rule 21 Original 50595-E Revised 54742-E Rule 21 Original 50596-E Revised 54743-E Rule 21 Original 50597-E Revised 54744-E Rule 21 Original 50598-E Revised 54745-E Rule 21 Original 50599-E Revised 54746-E Rule 21 Original 50600-E Revised 54747-E Rule 21 Original 50601-E Revised 54748-E Rule 21 Original 50602-E Revised 54749-E Rule 21 Original 50603-E* Revised 54750-E Rule 21 Original 50604-E Revised 54751-E Rule 21 Original 50605-E Revised 54752-E Rule 21 Original 50606-E* Revised 54753-E Rule 21 Original 50607-E Revised 54754-E Rule 21 Original 50608-E Revised 54755-E Rule 21 Original 50609-E Revised 54756-E Rule 21 Original 50610-E Revised 54757-E Rule 21 Original 50611-E Original 54758-E Rule 21 Revised 54759-E Rule 21 Original 50612-E* Revised 54760-E Rule 21 Original 50613-E* Original 54761-E Rule 21 Original 50613-E* Revised 54762-E Rule 21 Original 50614-E* Revised 54763-E Rule 21 Original 50615-E Revised 54764-E Rule 21 Original 50616-E Revised 54765-E Rule 21 Original 50617-E Revised 54766-E Rule 21 Original 50618-E* Revised 54767-E Rule 21 Original 50619-E Revised 54768-E Rule 21 Original 50620-E Revised 54769-E Rule 21 Original 50621-E Revised 54770-E Rule 21 Original 50622-E 1

Public Utilities Commission 3050-E Attachment A Cal. P.U.C. Sheet No. Title of Sheet Cancelling Cal. P.U.C. Sheet No. Revised 54771-E Rule 21 Original 50623-E Original 54772-E Rule 21 Original 54773-E Rule 21 Original 50623-E Revised 54774-E Rule 21 Original 50624-E* Revised 54775-E Rule 21 Original 50625-E Revised 54776-E Rule 21 Original 50626-E Revised 54777-E Rule 21 Original 50627-E Revised 54778-E Rule 21 Original 50628-E Original 50629-E* Revised 54779-E Rule 21 Original 50630-E* Revised 54780-E Rule 21 Original 50631-E Revised 54781-E Rule 21 Original 50632-E Revised 54782-E Rule 21 Original 50633-E Revised 54783-E Rule 21 Original 50634-E Revised 54784-E Rule 21 Original 50635-E Revised 54785-E Rule 21 Original 50636-E Original 54786-E Rule 21 Original 50630-E* Revised 54787-E Rule 21 Original 50630-E* Original 54788-E Rule 21 Original 50630-E* Original 50631-E Revised 54789-E Rule 21 Original 50631-E Original 54790-E Rule 21 Revised 54791-E Rule 21 Original 50632-E Revised 54792-E Rule 21 Original 50633-E Revised 54793-E Rule 21 Original 50634-E Original 54794-E Rule 21 Original 54795-E Rule 21 Original 54796-E Rule 21 Revised 54797-E Rule 21 Original 50629-E* Original 54798-E Rule 21 Original 50636-E Revised 54799-E Rule 21 Original 50637-E Revised 54800-E Rule 21 Original 50638-E* Revised 54801-E Rule 21 Original 50639-E Revised 54802-E Rule 21 Original 50640-E Revised 54803-E Rule 21 Original 50641-E Revised 54804-E Rule 21 Original 50642-E Revised 54805-E Rule 21 Original 50643-E Revised 54806-E Rule 21 Original 50644-E* Revised 54807-E Rule 21 Original 50645-E* Revised 54808-E Rule 21 Original 50646-E Revised 54809-E Rule 21 Original 50647-E* Original 54810-E Rule 21 Original 54811-E Rule 21 Original 50647-E* Revised 54812-E Rule 21 Original 50648-E Revised 54813-E Rule 21 Original 50649-E Revised 54814-E Rule 21 Original 50650-E Revised 54815-E Rule 21 Original 50651-E* Revised 54816-E Rule 21 Original 50652-E* Revised 54817-E Rule 21 Original 50653-E* Revised 54818-E Rule 21 Original 50654-E* Revised 54819-E Rule 21 Original 50655-E* Revised 54820-E Rule 21 Original 50656-E* Revised 54821-E Rule 21 Original 50657-E Revised 54822-E Rule 21 Original 50658-E 2

Public Utilities Commission 3050-E Attachment A Cal. P.U.C. Sheet No. Title of Sheet Cancelling Cal. P.U.C. Sheet No. Revised 54823-E Rule 21 Original 50659-E Revised 54824-E Rule 21 Original 50660-E* Revised 54825-E Rule 21 Original 50661-E* Revised 54826-E Rule 21 Original 50662-E* Revised 54827-E Rule 21 Original 50663-E* Revised 54828-E Rule 21 Original 50664-E Revised 54829-E Rule 21 Original 50665-E* Revised 54830-E Rule 21 Original 50666-E* Revised 54831-E Rule 21 Original 50667-E Revised 54832-E Rule 21 Original 50668-E Original 54833-E Rule 21 Original 50668-E Revised 54834-E Rule 21 Original 50669-E Revised 54835-E Rule 21 Original 50670-E Revised 54836-E Rule 21 Original 50671-E Revised 54837-E Rule 21 Original 50672-E Revised 54838-E Rule 21 Original 50673-E Revised 54839-E Rule 21 Original 50674-E Revised 54840-E Rule 21 Original 50675-E Revised 54841-E Rule 21 Original 50676-E Revised 54842-E Rule 21 Original 50677-E Revised 54843-E Rule 21 Original 50678-E Revised 54844-E Rule 21 Original 50679-E Revised 54845-E Rule 21 Original 50680-E Revised 54846-E Rule 21 Original 50681-E Revised 54847-E Rule 21 Original 50682-E Revised 54848-E Rule 21 Original 50683-E Revised 54849-E Rule 21 Original 50684-E Revised 54850-E Rule 21 Original 50685-E Revised 54851-E Rule 21 Original 50686-E Revised 54852-E Rule 21 Original 50687-E Revised 54853-E Rule 21 Original 50688-E Revised 54854-E Rule 21 Original 50689-E Revised 54855-E Rule 21 Original 50690-E Revised 54856-E Rule 21 Original 50691-E Revised 54857-E Rule 21 Original 50692-E Revised 54858-E Rule 21 Original 50693-E Revised 54859-E Rule 21 Original 50694-E Revised 54860-E Rule 21 Original 50695-E Revised 54861-E Rule 21 Original 50696-E Revised 54862-E Rule 21 Original 50697-E Revised 54863-E Rule 21 Original 50698-E Revised 54864-E Rule 21 Original 50699-E Revised 54865-E Rule 21 Original 50700-E Revised 54866-E Rule 21 Original 50701-E Revised 54867-E Rule 21 Original 50702-E Revised 54868-E Rule 21 Original 50703-E Original 50704-E, 50705-E Revised 54869-E Rule 21 Original 50706-E Revised 54870-E Rule 21 Original 50707-E Revised 54871-E Rule 21 Original 50708-E Revised 54872-E Rule 21 Original 50709-E Revised 54873-E Rule 21 Original 50710-E Revised 54874-E Rule 21 Original 50711-E Revised 54875-E Rule 21 Original 50712-E 3

Public Utilities Commission 3050-E Attachment A Cal. P.U.C. Sheet No. Title of Sheet Cancelling Cal. P.U.C. Sheet No. Original 54876-E Rule 21 Original 54877-E Rule 21 50712-E Revised 54878-E Form 14-732 Revised 53273-E Revised 54879-E Form 14-918 Original 50727-E* Original 54880-E Form 14-922 Original 54881-E Form 14-925 Original 54882-E Form 14-926 Revised 54883-E Table of Contents Revised 54705-E Revised 54884-E Table of Contents Revised 54314-E Revised 54885-E Table of Contents Revised 53922-E Revised 54886-E Table of Contents Revised 52752-E 4

Southern California Edison Revised Cal. PUC Sheet No. 54718-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50572-E Rule 21 Sheet 1 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS Sheet No. B. Applicability...9 1. Applicability...9 2. Definitions...9 3. Applicable Codes and Standards...10 C. Definitions...10 D. General, Rules, Rights and Obligations...24 1. Authorization Required to Operate...24 2. Separate Agreements Required for Other Services...24 3. Services Under This Tariff Limited to Interconnection...24 4. Compliance with Laws, Rules, and Tariffs...24 5. Design Reviews and Inspections...25 6. Right to Access...25 7. Confidentiality...25 a. Scope...25 b. Limitations on Scope...26 c. Disclosure to Commission, FERC or their respective Staff...27 d. Required Disclosure...27 8. Prudent Operation and Maintenance Required...28 9. Curtailment and Disconnection...28 10. Local Furnishing Bonds...28 11. Coordination with Affected Systems...29 12. Transferability of Interconnection Request...29 13. Special Provisions Applicable to Net Energy Metered Applicants...30 (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 1H13 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54719-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50573-E* Rule 21 Sheet 2 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS D. General, Rules, Rights and Obligations 14. Compliance with Established Timelines...31 15. Modification of Timelines...31 E. Interconnection Request Submission Process...32 1. Optional Pre-Applicant Report...32 2. Interconnection Request Process...34 a. Applicant Initiates Contact with Distribution Provider...34 b. Applicant Selects a Study Process...34 c. Applicant Completes an Interconnection Request...36 d. Site Exclusivity...38 3. Interconnection Request Fee and Study Deposit...38 a. Detailed Study Deposit...38 4. Interconnection Cost Responsibility...42 a. Costs of Interconnection and Parallel Operation...42 b. Methodology and Timing of Cost Identification...42 c. Timing of Cost Identification...43 d. Producer Costs During Parallel Operation...43 e. Cost Allocation...44 f. Summary Tables...45 5. Interconnection Request Validation and Assignment of Queue Position...46 a. Acknowledgement of Interconnection Request...46 b. Deficiencies in Interconnection Request...46 c. Assignment of Queue Position...47 d. Publication of the Interconnection Queue...48 (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 2H13 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54720-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50574-E Rule 21 Sheet 3 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS F. Review Process For Interconnection Requests...49 1. Overview of the Interconnection Review Process...49 a. Valid Interconnection Request...49 b. Fast Track Review...49 c. Detailed Studies...50 d. Compliance with Timelines...51 2. Fast Track Interconnection Review Process...52 a. Initial Review...52 b. Optional Initial Review Results Meeting...53 c. Supplemental Review...54 d. Optional Supplemental Review Results Meeting...57 e. Execution of the Generator Interconnection Agreement...58 3. Detailed Study Interconnection Review Process...60 a. Detailed Study Track Selection Process...60 b. Independent Study Process...62 c. Distribution Group Study Process...69 d. Transmission Cluster Study Process...80 e. Generator Interconnection Agreement for Detailed Studies...81 f. Engineering & Procurement (E&P) Agreement...83 4. Interconnection Financial Security...84 a. Types of Interconnection Financial Security...84 b. Initial Posting of Interconnection Financial Security...85 c. Second Posting of Interconnection Financial Security...86 d. Third Posting of Interconnection Financial Security...87 e. General Effect of Withdrawal of Interconnection Request or Termination of the Generator Interconnection Agreement on Interconnection Financial Security...88 f. General Effect of Withdrawal of Interconnection Request or Termination of the Generator Interconnection Agreement on Interconnection Financial Security for Interconnection Requests Studied Under the Distribution Group Study Process...93 (N) (N) (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 3H16 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54721-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50575-E Rule 21 Sheet 4 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS F. Review Process For Interconnection Requests 5. Commissioning Testing and Parallel Operation...94 a. Commissioning Testing...94 b. Parallel Operation or Momentary Parallel Operation...95 6. Withdrawal...95 G. Engineering Review Details...96 1. Initial Review Screens...98 a. Screen A: Is the PCC on a Networked Secondary System?...98 b. Screen B: Is Certified Equipment used?...99 c. Screen C: Is the Starting Voltage Drop within acceptable limits?...99 d. Screen D: Is the transformer or secondary conductor rating exceeded?... 100 e. Screen E: Does the Single-Phase Generator cause unacceptable imbalance?... 101 f. Screen F: Is the Short Circuit Current Contribution Ratio within acceptable limits?... 101 g. Screen G: Is the Short Circuit Interrupting Capability Exceeded?... 102 h. Screen H: Is the line configuration compatible with the Interconnection type?... 103 i. Screen I: Will power be exported across the PCC?... 104 j. Screen J: Is the Gross Rating of the Generating Facility 11 kva or less?... 105 k. Screen K: Is the Generating Facility a Net Energy Metering (NEM) Generating Facility with nameplate capacity less than or equal to 500kW?... 106 l. Screen L: Transmission Dependency and Transmission Dynamic/Stability Test... 106 m. Screen M: Is the aggregate Generating Facility capacity on the Line Section less than 15% of Line Section peak load for all line sections bounded by automatic sectionalizing devices?... 107 (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 4H17 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54722-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50576-E Rule 21 Sheet 5 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS G. Engineering Review Details 2. Supplemental Review Screens... 107 a. Screen N: Penetration Test... 108 b. Screen O: Power Quality and Voltage Tests... 109 c. Screen P: Safety and Reliability Tests... 110 3. Detailed Study Screens... 111 a. Screen Q: Is the Interconnection Request electrically Independent of the Transmission System?... 111 b. Screen R: Is the Interconnection Request independent of other earlier-queued and yet to be studied interconnection requests interconnecting to the Distribution System?... 113 c. Independent Study Process and Distribution Group Study Process Interconnection Studies... 114 H. Generating Facility Design and Operating Requirements... 117 1. General Interconnection and Protective Function Requirements... 117 a. Protective Functions Required... 117 b. Momentary Paralleling Generating Facilities... 118 c. Suitable Equipment Required... 119 d. Visible Disconnect Required... 119 e. Drawings Required... 120 f. Generating Facility Conditions Not Identified... 121 2. Prevention of Interference... 121 a. Voltage Regulation... 121 b. Voltage Trip Setting... 121 c. Paralleling... 124 d. Flicker... 124 e. Integration with Distribution Provider s Distribution System Grounding... 124 (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 5H16 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54723-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50577-E Rule 21 Sheet 6 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS H. Generating Facility Design and Operating Requirements f. Frequency... 125 g. Harmonics... 126 h. Direct Current Injection... 127 i. Power Factor... 127 3. Technology Specific Requirements... 127 a. Technology Specific Requirements... 127 b. Induction Generators... 128 c. Inverters... 128 4. Supplemental Generating Facility Requirements... 128 a. Fault Detection... 128 b. Transfer Trip... 129 c. Reclose Blocking... 129 I. Third-Party Installations, Reservation of Unused Facilities, and Refund of Salvage Value... 129 1. Interconnection Facilities and Distribution Upgrades... 129 2. Third-Party Installations... 130 3. Reservation of Unused Facilities... 130 4. Refund of Salvage Value... 130 J. Metering, Monitoring and Telemetering... 131 1. General Requirements... 131 2. Metering by Non-Distribution Provider Parties... 131 3. Net Generation Output Metering... 131 4. Point of Common Coupling (PCC) Metering... 133 5. Telemetering... 133 6. Location... 133 7. Costs of Metering... 134 8. Multiple Tariff Metering... 134 (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 6H17 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54724-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50578-E Rule 21 Sheet 7 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS K. Dispute Resolution Process... 134 1. Scope... 134 2. Procedures... 135 3. Performance During Dispute... 136 L. Certification and Testing Criteria... 136 1. Introduction... 136 2. Certified and Non-Certified Interconnection Equipment... 137 a. Certified Equipment... 137 b. Non-Certified Equipment... 139 3. Type Testing... 139 a. Type Tests and Criteria for Interconnection Equipment Certification... 139 b. Anti-Islanding Test... 141 c. Non-Export Test... 141 d. In-rush Current Test... 142 e. Surge Withstand Capability Test... 142 f. Synchronization Test... 143 g. Paralleling Device Withstand Test... 144 4. Production Testing... 144 5. Commissioning Testing... 144 a. Commissioning Testing... 144 b. Review, Study, and Additional Commissioning Test Verification Costs... 145 c. Other Checks and Tests... 146 d. Certified Equipment... 146 e. Non-Certified Equipment... 147 f. Verification of Settings... 147 g. Trip Tests... 147 h. In-service Tests... 148 (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 7H15 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54725-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50579-E Rule 21 Sheet 8 GENERATING FACILITY INTERCONNECTIONS A. TABLE OF CONTENTS L. Certification and Testing Criteria 6. Periodic Testing... 148 7. Type Testing Procedures Not Defined in Other Standards... 148 a. Non-Exporting Test Procedures... 149 b. In-rush Current Test Procedures... 156 M. Inadvertent Export... 157 Appendix A... 159 (N) (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 8H17 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54726-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50580-E* Rule 21 Sheet 9 GENERATING FACILITY INTERCONNECTIONS B. APPLICABILITY 1. Applicability This Rule describes the Interconnection, operating and Metering requirements for those Generating Facilities to be connected to Distribution Provider s Distribution System and Transmission System over which the California Public Utilities Commission (Commission) has jurisdiction. All Generating Facilities seeking Interconnection with Distribution Provider s Transmission System shall apply to the California Independent System Operator (CAISO) for Interconnection and be subject to CAISO Tariff except for 1) Net Energy Metering Generating Facilities and 2) Generating Facilities that do not export to the grid or sell any exports sent to the grid (Non-Export Generating Facilities). NEM Generating Facilities and Non-Export Generating Facilities subject to Commission jurisdiction shall interconnect under this Rule regardless of whether they interconnect to Distribution Provider s Distribution or Transmission System. Subject to the requirements of this Rule, Distribution Provider will allow the Interconnection of Generating Facilities with its Distribution or Transmission System. Generating Facility interconnections to Distribution Provider s Distribution System that are subject to Federal Energy Regulatory Commission (FERC) jurisdiction shall apply under Distribution Provider s WDAT whether they interconnect to Distribution Provider s Distribution or Transmission System. 2. Definitions Capitalized terms used in this Rule, and not defined in Distribution Provider s other tariffs shall have the meaning ascribed to such terms in Section C of this Rule. The definitions set forth in Section C of this Rule shall only apply to this Rule, the Interconnection Request, study agreements and Generator Interconnection Agreements, and may not apply to Distribution Provider s other tariffs. (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 9C13 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54727-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50581-E Rule 21 Sheet 10 GENERATING FACILITY INTERCONNECTIONS B. APPLICABILITY 3. Applicable Codes and Standards This Rule has been harmonized with the requirements of American National Standards Institute/Institute of Electrical and Electronic Engineers (ANSI/IEEE) 1547-2003 Standards for Interconnecting Distributed Resources with Electric Power Systems. In some sections, IEEE 1547 language has been adopted directly, in others, IEEE 1547 requirements were interpreted and this Rule s language was changed to maintain the spirit of both documents. The language from IEEE 1547 that has been adopted directly (as opposed to paraphrased language or previous language that was determined to be consistent with IEEE 1547) is followed by a citation that lists the Clause from which the language derived. For example, IEEE 1547-4.1.1 is a reference to Clause 4.1.1. In the event of any conflict between this Rule, any of the standards listed herein, or any other applicable standards or codes, the requirements of this Rule shall take precedence. C. DEFINITIONS The definitions in this Section C are applicable only to this Rule, the Interconnection Request, Study Agreements and Generator Interconnection Agreements. Added Facilities: As Defined in Distribution Provider s Rule 2. Affected System: An electric system other than Distribution Provider's Distribution or Transmission System that may be affected by the proposed Interconnection. Affected System Operator: The entity that operates an Affected System. Affiliate: With respect to a corporation, partnership or other entity, each such other corporation, partnership or other entity that directly or indirectly, through one or more intermediaries, controls, is controlled by, or is under common control with, such corporation, partnership or other entity. Allocated Capacity: Existing aggregate generation capacity in megawatts (MW) interconnected to a substation/area bus, bank or circuit (i.e., amount of generation online). Anti-Islanding: A control scheme installed as part of the Generating or Interconnection Facility that senses and prevents the formation of an Unintended Island. (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 10H13 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54728-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50582-E Rule 21 Sheet 11 GENERATING FACILITY INTERCONNECTIONS C. DEFINITIONS Applicant: The entity submitting an Interconnection Request pursuant to this Rule. Application: See Interconnection Request. Available Capacity: Total Capacity less the sum of Allocated Capacity and Queued Capacity. Base Case: Data including, but not limited to, base power flow, short circuit and dynamic/stability data bases, underlying load, generation, and transmission facility assumptions, contingency lists, including relevant special protection systems, and transmission diagrams used to perform the Interconnection Studies. The Base Case may include Critical Energy Infrastructure Information (as that term is defined by FERC). The Base Case shall include (a) transmission facilities as approved by Distribution Provider or CAISO, as applicable, (b) planned Distribution Upgrades that may have an impact on the Interconnection Request, (c) Distribution Upgrades and Network Upgrades associated with generating facilities in (iv) below, and (d) generating facilities that (i) are directly interconnected to the Distribution System or CAISO Controlled Grid; (ii) are interconnected to Affected Systems and may have an impact on the Interconnection Request; (iii) have a pending request to interconnect to the Distribution System or an Affected System; or (iv) are not interconnected to the Distribution System or CAISO Controlled Grid, but are subject to a fully executed Generator Interconnection Agreement (or its equivalent predecessor agreement) or for which an unexecuted Generator Interconnection Agreement (or its equivalent predecessor agreement) has been requested to be filed with FERC. Business Day: Monday through Friday, excluding Federal and State Holidays. CAISO Controlled Grid: The system of transmission lines and associated facilities that have been placed under the CAISO s Operational Control. CAISO Tariff: The California Independent System Operator FERC Electric Tariff. Calendar Day: Any day including Saturday, Sunday or a Federal and State Holiday. Certification Test: A test pursuant to this Rule that verifies conformance of certain equipment with Commission-approved performance standards in order to be classified as Certified Equipment. Certification Tests are performed by Nationally Recognized Test Laboratories (NRTLs). (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 11H14 Resolution

Southern California Edison Revised Cal. PUC Sheet No. 54729-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 50583-E* Rule 21 Sheet 12 GENERATING FACILITY INTERCONNECTIONS C. DEFINITIONS Certification; Certified; Certificate: The documented results of a successful Certification Testing. Certified Equipment: Equipment that has passed all required Certification Tests. Commercial Operation: The status of a Generating Facility that has commenced generating electricity, excluding electricity generated during the period which Producer is engaged in onsite test operations and commissioning of the Generating Facility prior to Commercial Operation. Commercial Operation Date: The date on which a Generator at a Generating Facility commences Commercial Operation as agreed to by the Parties. Commission: The Public Utilities Commission of the State of California. Commissioning Test: A test performed during the commissioning of all or part of a Generating Facility to achieve one or more of the following: Verify specific aspects of its performance; Calibrate its instrumentation; Establish instrument or Protective Function set-points. Confidential Information: See Section D.7. Conservation Voltage Regulation (CVR): The CVR program that the Commission directed Distribution Provider to implement as applicable to the operation and design of distribution circuits and related service voltages. Construction Activities: Actions by Distribution Provider that result in irrevocable financial commitments for the purchase of major electrical equipment or land for Distribution Provider s Interconnection Facilities, Distribution Upgrades, or Network Upgrades assigned to the Interconnection Customer that occur after receipt of all appropriate governmental approvals needed for Distribution Provider s Interconnection Facilities, Distribution Upgrades, or Network Upgrades. (To be inserted by utility) Issued by (To be inserted by Cal. PUC) Advice 3050-E Megan Scott-Kakures Date Filed Jun 9, 2014 Decision 14-04-003 Vice President Effective Jul 9, 2014 12H12 Resolution