Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Similar documents
GPE engineering project management. Project Management in an Engineering Context

Appendix A Decision Support Analysis

Project Management Techniques (PMT)

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

CHAPTER 9: PROJECT MANAGEMENT

CISC 322 Software Architecture

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

Textbook: pp Chapter 11: Project Management

Research Methods Outline

Real-World Project Management. Chapter 15

UNIT-II Project Organization and Scheduling Project Element

Project Management -- Developing the Project Plan

Project Management Chapter 13

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Teori Pengambilan Keputusan. Week 12 Project Management

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

After complete studying this chapter, You should be able to

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Construction Management

ETSF01: Software Engineering Process Economy and Quality

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

PROJECT MANAGEMENT DIPLOMA COURSE

SCM 301 (Solo) Exam 1 Practice Exam Solutions

SCM 301 (Lutz) Exam 1 Practice Exam Solutions

Handout 4: Deterministic Systems and the Shortest Path Problem

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

IE 102 Spring Project Management

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Project planning and creating a WBS

SWEN 256 Software Process & Project Management

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

Project Management Fundamentals

The Critical Path Method

Project Planning. Planning is an important step in project execution. Planning means:

Lecture 3 Project Scheduling

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Cost Reduction: Planning & Control. Impacting the Bottom Line

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

Chapter16Project Management and. Scheduling Project management

Plan Implementation. Pushpa Lal Shakya

Chapter 11: PERT for Project Planning and Scheduling

1 of 14 4/27/2009 7:45 AM

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

Schedule/Milestones. Figure 14 An example of a schedule

MS Project 2007 Page 1 of 18

MnDOT use of Calendars in Primavera P6

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

Project Time-Cost Trade-Off

Impacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)

u w 1.5 < 0 These two results imply that the utility function is concave.

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Decision Support Tool for Project Time-Cost Trade-off

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

POLYTECHNIC OF NAMIBIA

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

Project orie:nta.teci pla.:n:ni:ng, scheduling a.:nci controlling technique

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

COPYRIGHTED MATERIAL. Index

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

CHAPTER 5 STOCHASTIC SCHEDULING

Project Management with Brief Information regarding CPM and PERT Methods

Project Management and Cost Control

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

06IP/IM74 OPERATIONS RESEARCH

Appendix B: Glossary of Project Management Terms

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

Line Of Balance. Dr. Ahmed Elyamany

Quality Project Management

Management Management

Introduction to Project Management. Modeling after NYS ITS

56:171 Operations Research Midterm Exam Solutions October 22, 1993

Project Controls Expo 16 th Nov 2016

Project Management. A Practitioner s Guide. Steven M. Bragg

PMP032 Project Management Leadership Skills

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Managing Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost

Project Assessment Exercise

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

Project Management. Basic Definitions: Project and Project Plan

Brown hamburger and assemble tacos (including cheese)


Transcription:

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller

PROJECT MANAGEMENT Project Managers can use project management software to keep track of the project in real time, and use it as a tool for planning and a guide in case circumstances change. One method which time has proven to be of invaluable use to project managers is the Critical Path Method (CPM). The CPM identifies the relationships between interrelated project components and shows a clear critical path of activities that must be completed by a certain date (project deadline). This helps to create a timescale for the development of the project, allowing the project manager to plan and allocate resources more efficiently e.g. staff. UNDERSTANDING THE SYMBOLS Node this represents the end of the previous activity and the starting point of those activities to follow. à Arrow this shows the direction of the project, as activities follow on one from another. This arrow can only ever point forward on the diagram, since a project cannot go backwards. Square this will contain a number which will represent the earliest start time of this activity. Triangle this will also contain a number which will represent the latest start time of this activity. CALCULATING EARLIEST START DATE 0 A B C D To calculate, for example, the earliest start time of activity C, it is simply the number of days it takes to complete activity A i.e.. However, to calculate this for the final node (the earliest time the project could be finished), the earliest time the project could be finished would be the cumulative of the longest path in the project i.e. Path : B () + D () = Path : A () + C () =

CALCULATING LATEST START DATE 0 0 A B 3 C D To calculate, for example, the latest start time of activity C, it is simply the earliest start time of the previous activity less the number of days that activity takes to complete i.e. - = 3 The latest start time for the final node will always equal the same as the earliest start time. This remains true for the beginning node. THE FLOAT The float of any activity is the number of days the activity could be delayed by but still finish on time before the following activity. It is calculated using this simple formula: - - duration of activity = float So, the float for activities B and D would be 0 as they are on the critical path, but the float for activities A and C would be and repectively; A 3 0 = C = Answer to worked example below: ACTIVITY A B C D E F G H I FLOAT 0 3 0 0 8 0 THE CRITICAL PATH The critical path is essentially where and are equal to each other. The significance of the critical path is that activities on this path cannot have their durations extended, and must start on time so the project is completed in the minimum time allowed. The critical path in essence shows the shortest duration possible for the project. To mark out the critical path, the arrows for the path are often drawn in a different colour, or given double lines as shown above.

A COMPLEX CPM EXAMPLE GANTT CHARTS & STAFFING PROFILES Gantt charts are used to illustrate a project schedule the start and finish dates of each project element. They also show the dependency relationships between activities and can compare the planned and actual progress of the project. Modern systems have a Today line to show the present progress of the project. The length of each activity is plotted on a graph as follows to show the relationship between each project element. *NOTE: there should be a float of days on activity A

Gantt charts can also be used to plan resources and create other charts such as staffing profiles to allocate staff to projects. The numbers in the boxes in this case are the number of staff required to complete each activity. However, there are sometimes limitations to, for example, the number of staff available at a given time, and thus certain activities may not be able to be completed on time. Staffing profiles can help to overcome this particular limitation by moving project elements within their float to satisfy these conditions. Continued example DAY 3 6 7 8 9 0 3 6 Staff Required 3 9 8 8 8 3 3 3 3 3 3 Staff Required 0 9 8 7 6 3 0 3 6 7 8 9 0 3 6 DAY The staffing profile above shows the number of staff required to work on the project each day (black lines). However, if there was a staff restriction of a maximum of 7 staff available on any one day the Gantt chart shows the float of each activity, and allows us to see how activities can be maneuvered to fit this restriction. In this example, move activity H to start on day (see red in above graphs). DAY 3 6 7 8 9 0 3 6 Staff Required 3 9 8 8 8 3 3 3 3 3 3 Restriction 3 7 7 7 7 7 7