Dulles Corridor Metrorail Project

Similar documents
DULLES CORRIDOR METRORAIL PROJECT MONTHLY COST SUMMARY AS OF FEBRUARY 28, 2013 APRIL 2013

Dulles Corridor Metrorail Project

DULLES CORRIDOR METRORAIL PROJECT MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF MAY 31, 2014 JULY 2014

Dulles Corridor Metrorail Project

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting

DULLES CORRIDOR COMMITTEE

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA).

Dulles Corridor Enterprise May 2012 Financial Report

METROPOLITAN WASHINGTON AIRPORTS AUTHORITY

BOARD OF SUPERVISORS TRANSPORTATION/LAND USE COMMITTEE INFORMATION ITEM. Dulles Corridor Metrorail Phase 2 Update

METRO. Fiscal Year 2015 Monthly Board Report. February 2015

Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun

Dulles Corridor Enterprise June 2014 Financial Report

METROPOLITAN WASHINGTON AIRPORTS AUTHORITY DULLES TOLL ROAD REVENUE BONDS ANNUAL REPORT

FY2014 Capital and Operating Budget Discussion

Key IRS Interest Rates After PPA

SOUND TRANSIT STAFF REPORT MOTION NO. M D Street-to-M Street Track & Signal Project Preferred Alternative

Dulles Corridor Enterprise January 2017 Financial Report UNAUDITED COPY

Dulles Corridor Enterprise Financial Report for the Year Ended December 31, 2016 (Preliminary Unaudited) UNAUDITED COPY

METRO. Fiscal Year 2012 Monthly Board Report. September 2012 (Fourth Quarter Fiscal Year-to-Date)

METRO. Fiscal Year 2014 Monthly Board Report. May 2014

Operating Budget. Third Quarter Financial Report (July 2005 March 2006)

M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y. Dulles Corridor Enterprise September 2015 Financial Report

Historical Pricing PJM COMED, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22

METROPOLITAN WASHINGTON AIRPORTS AUTHORITY

Getting Metro Back on Track

METRO. Fiscal Year 2013 Monthly Board Report. December 2012 (First Quarter Fiscal Year-to-Date)

METRO. Fiscal Year 2013 Monthly Board Report. January 2013

Amend FY07 System Access Program for Artwork

Quarterly Capital Progress Update

Historical Pricing PJM PSEG, Around the Clock. Cal '15 Cal '16 Cal '17 Cal '18 Cal '19 Cal '20 Cal '21 Cal '22

Performance Management Accountability Meeting Data as of October, 2012

FY2018 Third Quarter Financial Update

Executive Change Control Board. January 15, 2016

FY2017 Third Quarter Financial Update and CIP Amendment

METRO. Fiscal Year 2013 Monthly Board Report. November 2012

Fiscal Year 2010 Columbia Generating Station Annual Operating Budget

SUBJECT: APPROVAL OF FISCAL CAPITAL IMPROVEMENT PROGRAM

Fiscal Year 2013 Columbia Generating Station Annual Operating Budget

CHAPTER 6: COST ESTIMATES

FY2014 Operating Budget Performance Report

METRO. Fiscal Year 2017 Monthly Performance Report. Revenue Expense Ridership Performance. October 2016

Capital Budget Summary Capital Funding Summary

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017.

Fiscal Year 2018 Project 1 Annual Budget

Project Connect. August 10, 2011

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016.

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. November 2018 (Third Quarter Fiscal Year-to Date)

METRO. Fiscal Year 2015 Monthly Board Report. September 2015 (Fourth Quarter Fiscal Year-to-Date)

Budget Discussion. July 2009 Citizens Advisory Committee

The year to date is less than budget and prior year by 15.4 million and 11.6 million, respectively.

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. February 2018 (First Quarter Fiscal Year-to Date)

December 10, Butler School District 53 1

RECOMMENDATION PAPER FOR THE DULLES CORRDOR COMMITTEE

CHAPTER 7: Financial Plan

Ohlone Community College District

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

Getting Metro Back on Track

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY TRANSPORTATION IMPROVEMENT PROGRAM CAPITAL COSTS (in $1,000)

Capital & Strategic Planning Committee. Item III - A. January 25, FY2019 Capital Budget Work Session

MIAMI INTERMODAL CENTER

Financial Report Fiscal Year 2018

METRO. Fiscal Year Monthly Performance Report. Revenue Expense Ridership Performance. May 2018 (Second Quarter Fiscal Year-to Date)

Keeping Metro Safe, Reliable and Affordable

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

FY2013 Preliminary Operating Budget

Project NEON Interim Finance Committee Rudy Malfabon Director

Financial Report - FY 2017 Year to Date May 31, 2017

Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016

Amend FY 2006 Infrastructure Renewal Program

Cash & Liquidity The chart below highlights CTA s cash position at February 2017 compared to February 2016.

Operating Budget Report

Key IRS Interest Rates After PPA

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Capital Cost Estimation Methodology

Operating Budget Stability

BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE INFORMATION ITEM

REPORT TO THE CITY COUNCIL rd Avenue NE, Woodinville, WA

Project Connect Connect January 11, 2012

City of Baker City Financial Report for the General Fund Report for the Month Ending September 30, % of Year Elapsed

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Fiscal Year 2016 Columbia Generating Station Annual Operating Budget

Planned Procurement Opportunities Report. August 2015

Planned Procurement Opportunities Report. August 2015

Capital Metropolitan Transportation Authority Monthly Financial Report For Period Ending November 30, 2013

FEBRUARY 2015 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS

TR-1: Standard form for notification of major holdings

($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M) ($M)

Business & Financial Services December 2017

MIAMI INTERMODAL CENTER

Operating Budget. Second Quarter Financial Report

AMENDED AND RESTATED DESIGN-BUILD CONTRACT. Dulles Corridor Metrorail Project. Dated as of July 25, by and between

Operating Budget Report

METRO. Fiscal Year 2012 Monthly Board Report. December 2011 (First Quarter Fiscal Year-to-Date)

SCHEDULE and 2019 Budget Assumptions

February 2016 Financial Report

DETROIT LAKES CITY COUNCIL SPECIAL MEETING AGENDA TUESDAY, June 19, 2018

TR-1: Standard form for notification of major holdings

Metropolitan Transportation Authority: East Side Access Cost Overruns

Transcription:

Dulles Corridor Metrorail Project QUARTERLY COST AND SCHEDULE UPDATE PHASE 1 AS OF APRIL 30, 2016 JUNE 2016

Phase 1 Cost Summary Quarter Expenditures (Feb, Mar, Apr) Total Expenditures (Thru April 30, 2016) $ 25.5 Million $ 2.846 Billion Forecast at Completion $ 2.982 Billion

Phase 1 Quarterly Update Dulles Transit Partners (DTP) Closeout Status: Estimated completion date for DTP performed punch list work: June 30, 2016. Credit negotiations are underway with DTP for punch list work that will be assigned to the Task Order Closeout Contract (most notably VDOT items). Warranty claims processing and remedial work by DTP will continue; most significant item is storm sewer and roadway underdrain repair. WMATA Facilities Major Activities through 2016 Art-in-Transit was completed in April. Automatic Train Control (ATC) Remote Terminal Units were completed in March. Estimated completion date for Traction Power Remote Terminal Unit Upgrade: June. This work is being performed by WMATA. Estimated completion date for ATC Training Equipment: August. Estimated completion date for Third Rail Heater Controllers: December.

Phase 1 Quarterly Update Closeout of VDOT Comprehensive Agreement VDOT has proposed an all-inclusive cost for performance of disputed punch list items and DTP warranty work in the amount of $ 37m. Warranty work must remain the responsibility of DTP. The remaining cost and scope of the punch list items will be negotiated with VDOT on an individual basis. Task Order Contract Status Task Orders with Notice To Proceed: 24 issued; 12 complete. The largest outstanding task orders will be for: Heat Tape Upgrades (Negotiations nearing completion). Old Meadow Road Conceptual Study (Contractor Proposal Evaluation) in progress. Concrete pavement repairs (related to disputed VDOT punchlist) in preparation.

Old Meadow Road Schedule In April 2016, Verizon provided evidence of Prior Rights which meant the Project is responsible for the fiber optic communication ductbank relocation costs. Project is pursuing an alternate design concept to avoid the cost and time of the ductbank relocation. Evaluate Alternate Design Concept: Late August 2016. Develop Property Acquisition/Permit Drawings: October 2016. Property Acquisition Process: October 2016 October 2017. Complete Final Design: March 2017. Award Construction Contract: September 2017. Construction: September 2017 to April 2018. If the alternate concept is not feasible, ductbank relocation may add up to a year to the schedule.

DULLESMETRO.COM

Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 1 MONTHLY COST SUMMARY As of April 30, 2016 Description Budget Budget Total Budget Variances Expenditures to Date Contract Contract DULLES CORRIDOR METRORAIL PROJECT - PHASE 1 Authorization 1,6 Amount 2 Forecast 3 Amount Percent Amount Total NTP Substantial Over / (Under) Percent a b b-a b-a/a c c/b Note 5 DESIGN-BUILD 2,051,345,982 1,712,504,539 2,048,638,486 (2,707,496) -0.1% 2,048,425,236 100% 2-Mar-09 9-Sep-13 UTILITY RELOCATION 178,607,183 129,016,151 178,802,182 194,999 0.1% 176,142,038 99% 1-Aug-07 30-Sep-10 ROW 71,709,235 87,215,795 70,806,290 (902,945) -1.3% 69,403,850 98% 1-Aug-07 28-Feb-10 WMATA 293,901,156 271,635,628 293,901,156 0 0.0% 195,916,178 67% 28-Jul-07 8-Dec-13 PRELIMINARY ENGINEERING 4 100,730,999 100,968,646 100,730,999 0 0.0% 100,730,999 100% 28-Jun-04 30-Jun-08 PROJECT MANAGEMENT 285,418,775 142,109,519 288,834,217 3,415,442 1.2% 255,615,858 88% n/a n/a TOTAL FOR DCMP 2,981,713,330 2,443,450,278 2,981,713,330 0 0.0% 2,846,234,159 95% Notes: 1 Budget Authorization based on FFGA project budget with estimated contingency spread among line items; includes interrelated highway improvements; does not include financing costs. 2 Budget Amount is based on FFGA project budget but does not include finance costs and contingency distribution. 3 Total Forecast includes approved change orders, estimates at completion and the estimated cost of future contingency utilization. It does not include finance costs. 4 Preliminary Engineering expenditures have been agreed to be $100,731,000. This is $237,646 under the original budget of $100,968,646. The under run is transferred to unallocated contingency. 5 Design-Build Contract Substantial Completion Date was revised from the original date of 7/31/2013 to 9/9/2013. 6 Additional Budget Authorization of $150 million was approved by the Airports Authority's Board on June 22, 2012; Another additional Budget Authorization of $76 million was approved by the Airports Authority's Board on May 20, 2015. Legend: Black - Forecast within Authorization Green - Forecast less than 3% over Authorization Red - Forecast greater than 3% over Authorization

DULLES CORRIDOR METRORAIL PROJECT - PHASE 1 CONTINGENCY UTILIZATION As of April 30, 2016 Dulles Rail ATTACHMENT 2 Description DULLES CORRIDOR METRORAIL PROJECT - PHASE 1 Amount in million ($) Total Contingency (including additional funding) $ 538.3 Total Contingency Utilized through April 2016 $ 538.3 Remaining Contingency $ -

ATTACHMENT 1 Dulles Rail Airport Project No Description DULLES CORRIDOR METRORAIL PROJECT - PHASE 1 Original Budget Amount Budget Authorization DESIGN-BUILD DCMP 5101/5103 DTP - FFP 1,185,980,111 1,322,086,717 DCMP 5101/5103 Trackwork Allowance 75,378,042 88,408,431 DCMP 5101/5103 Station Finishes & MEP Allowance 81,953,493 96,120,562 DCMP 5101/5103 WFCY Sound and Box Platforms Allowance 6,686,211 7,842,037 DCMP 5101/5103 Pedestrain Bridges Allowance 12,239,488 14,355,294 DCMP 5101/5103 Site Development Allowance 61,718,153 70,200,426 DCMP 5101/5103 Installation of Public Art Allowance 633,862 743,436 DCMP 5101/5103 Communications and Securtiy Allowance 24,300,826 28,501,641 DCMP 5101/5103 Fire Suppression Allowance 2,667,214 3,128,288 DCMP 5101/5103 Elevators and Escalators Allowance 38,732,282 45,427,822 DCMP 5101/5103 Spare Parts Allowance 5,515,011 6,468,375 DCMP 5101/5103 WFCY S&I Building Allowance 27,613,591 32,387,074 DCMP 5101/5103 Traction Power Supply Allowance 45,594,511 53,393,254 DCMP 5101/5103 ATC Supply Allowance 26,918,598 31,571,940 DCMP 5101/5103 Corrosion & Stray Currents Allowance 1,579,685 1,852,761 DCMP 5101/5103 Contact Rail Allowance 8,431,848 9,889,438 DCMP 5101/5103 Wiehle Parking Garage Allowance (By others) 29,091,684 34,120,681 DCMP 5101/5103 Commodity Index Payments 77,469,926 86,241,691 DCMP 5101/5103 Contingency 220,235,332 Adjustment due to Additional Funding 2012 95,036,208 Adjustment due to Additional Funding 2015 23,569,907 SUBTOTAL - DESIGN-BUILD 1,932,739,867 2,051,345,982 UTILITY RELOCATION DCMP 5101/5103 DTP (Lane) 83,310,836 98,449,857 DCMP 5101/5103 Design 2,394,135 2,775,026 DCMP 5101/5103 PM/CM 8,347,544 9,498,307 DCMP 5101/5103 Legal Permit Fee 834,796 923,095 DCMP 5101/5103 TERF 6,502,667 7,137,990 DCMP 5101/5103 Washington Gas Light - Force Account 4,231,456 4,644,877 DCMP 5101/5103 Dominion Power - Force Account 7,410,599 8,134,628 DCMP 5101/5103 Verizon - Force Account 3,418,254 3,752,224 DCMP 5101/5103 ATT Local - Force Account 1,935,438 2,124,534 DCMP 5101/5103 ATTLD - Force Account 216,276 237,407 DCMP 5101/5103 Verizon Business (MCI) - Force Account 1,761,409 1,933,502 DCMP 5101/5103 FiberLight - Force Account 75,234 82,585 DCMP 5101/5103 Qwest Government - Force Account 1,708,886 1,875,847 DCMP 5101/5103 Qwest Comercial - Force Account 993,153 1,090,186 DCMP 5101/5103 Above Net - Force Account 1,467,478 1,610,853 DCMP 5101/5103 Level 3 Com - Force Account 995,253 1,092,491 DCMP 5101/5103 XO Communication - Force Account 250,922 275,438 DCMP 5101/5103 Cox - Force Account 752,115 825,598 DCMP 5101/5103 Comcast - Force Account 178,697 196,156 DCMP 5101/5103 Fibergate - Force Account 31,512 34,591 DCMP 5101/5103 Time-Warner - Force Account 199,576 219,075 DCMP 5101/5103 FastToll (Qwest Business) - Force Account 220,584 242,135 DCMP 5101/5103 VDOT - Force Account 178,568 196,014

ATTACHMENT 1 Dulles Rail Airport Project No Description Original Budget Budget Amount Authorization DCMP 5101/5103 ITS Fiber - Force Account 26,260 28,826 DCMP 5101/5103 UTILITY COMPANIES DESIGN 1,574,500 1,728,332 DCMP 5101/5103 Contingency 20,093,426 Adjustment due to Additional Funding 2012 39,130,452 Adjustment due to Additional Funding 2015 (9,632,843) SUBTOTAL - UTILITY RELOCATION 149,109,574 178,607,183 ROW DCMP 5101/5103 Support Services 8,171,000 8,625,590 DCMP 5101/5103 Land & Relocation 79,044,794 87,639,548 DCMP 5101/5103 Contingency 9,049,345 Adjustment due to Additional Funding 2012 (9,496,008) Adjustment due to Additional Funding 2015 (15,059,895) SUBTOTAL - ROW 96,265,139 71,709,235 WMATA DCMP 5101 Vehicles 195,138,328 222,863,121 DCMP 5101 Construction and Procurement 31,484,799 35,958,085 DCMP 5101 WMATA Force Account Startup 13,777,100 15,734,518 DCMP 5101 Project Management and Final Design 31,235,400 35,673,251 DCMP 5101/5103 Contingency 38,593,348 Adjustment due to Additional Funding 2012 (31,743,347) Adjustment due to Additional Funding 2015 15,415,528 SUBTOTAL - WMATA 310,228,975 293,901,156 PRELIMINARY ENGINEERING DCMP PRELIMINARY ENGINEERING 100,968,646 100,968,646 Adjustment due to Additional Funding 2012 (237,647) Adjustment due to Additional Funding 2015 - SUBTOTAL - PRELIMINARY ENGINEERING 100,968,646 100,730,999 PROJECT MANAGEMENT DCMP 5101/5103 MWAA 23,225,715 27,133,777 DCMP 5101/5103 PMSS 88,565,041 103,771,334 DCMP 5101/5103 VDOT 1,439,608 1,686,783 DCMP 5101/5103 OTHERS 28,879,153 33,791,186 DCMP 5101/5103 Contingency 24,273,563 Adjustment due to Additional Funding 2012 57,310,061 Adjustment due to Additional Funding 2015 61,725,634 SUBTOTAL - PROJECT MANAGEMENT 166,383,080 285,418,775 TOTAL FOR DCMP 2,755,695,281 2,981,713,330