Project Development - Rules on eligibility of expenditure

Similar documents
Rules on eligibility of expenditure

First level control report including checklist

Q&A on simplified cost options in programmes. March 2018 Application, control and audit: use of simplified cost options for staff costs

Article 14(1) ESF. Elsa KMIECIK, DG Employment, ESF coordination unit

Interreg Nord

ADRION 2 call for proposals Priority Axis 2 Financial aspects. Tirana, 11 April 2018

South East Europe (SEE) SEE Control Guidelines

TABLE OF CONTENTS PREFACE 0 GENERAL PROVISIONS 1 STAFF COSTS 2 OFFICE AND ADMINISTRATIVE EXPENDITURE 3 TRAVEL AND ACCOMMODATION COSTS

Guidance on Simplified Cost Options (SCOs):

ELIGIBILITY OF EXPENSES: APPLICABLE RULES

Budget & Finances. Interreg Europe Secretariat. 23 March 2016 Lead applicant workshop. Sharing solutions for better regional policies

IPA partners seminar. Eligibility of expenditure and specificities of the public procurement. Dubrovnik, 5 th February 2013

Madrid, 7 November 2013

PROGRAMME RULES ON ELIGIBILITY OF EXPENDITURES

Financial errors in FP7 How to improve the quality of financial statements?

ESF Certifying Authority, Department of Education and Skills Circular 1/2016 (replacing Circular 1/2015)

STAFF. CONSIDERED ELIGIBLE at the EU level (some costs may not be elegible based on programme/national rules)

How to plan your budget and project management?

Financial Control. Thi s p r og r am m e is co- f i nanced by t he E ur op ean R eg i onal D ev el op m ent F und.

Guidance for Member States on Article 42(1)(d) CPR Eligible management costs and fees

ESF Certifying Authority, Department of Education and Skills Circular 1/2015

Annex 3 First level control report including checklist

Simplified Cost Options:

Investing in your future

Coordinators' day on ICT PSP project management Financial Issues, Reporting, payments, cost claims and Certification Modalities

Follow up and reporting procedures. Lead partners seminar 5th targeted call Lydwine Lafontaine

Lump sum under preparatory support and flat rate under running and animation costs (SCOs for LAGs under RDP in Poland)

1st Level Control in the North Sea Region Programme

Preparatory support... 4 Q. In the context of multi-funded CLLD, can preparatory support be funded by one Fund only?. 4

Administrative, Financial and Operational Aspects of Project Management

Eligibility Rules of Expenditures

Mono-Beneficiary Model Grant Agreement

Lead Partner Seminar. JS/MA Riga

Multi-beneficiary Model Grant Agreement

CHECK-LIST FOR CONTROLLERS/AUDITORS

Eligibility principles and sound financial management

Mono-Beneficiary Model Grant Agreement

MTR - Legislative changes affecting the ESI Funds

FIRST LEVEL CONTROL: PRINCIPLES AND PRACTICE

Project Monitoring and Reporting Workshop for Interreg programmes

Programme general rules on eligibility of expenditure Priority Axis 1-6

1 st call for proposals, 2 nd call for proposals, Priority 3 Better network of harbours version

First Level Control and Verifications of ESI Funds

INTERREG III B CADSES. Payment Claim Manual

*This circular was reissued in October 2015 to reflect minor clarifications to Rules 4 and 14.9

8 th Financial Managers Seminar

Welcome and Introduction

Audit certificate template for Horizon2020 projects funded by SERI

European Union Regional Policy Employment, Social Affairs and Inclusion. EU Cohesion Policy Proposals from the European Commission

Official Journal of the European Union

Financial rules and procedures in Interreg Europe - second call projects

Eligibility rules, Financial control, Procurement

Project costs have to be actually incurred due to the project implementation, in order to be considered as eligible costs.

Practicalities in the Financial Management of FP7 projects - An outlook to audits and Horizon 2020 rules

European Metrology Programme for Innovation and Research (EMPIR) Multi-beneficiary Model Grant Agreement. (EMPIR MGA - Multi)

Decommitment methodology and process in

Version 4: 29 th June 2017

Multi-Beneficiary Model Grant Agreement

Fact Sheet 14 - Partnership Agreement

Effective as of 1 January 2007 Promulgated, SG, No 78 of 28 September 2007

EU School Scheme. Points for clarification to assist Member States in implementing the school scheme

Legal and Financial Issues in H2020

Annex VI. Model terms of reference for the Certificate on the Financial Statements

Financial Rules in FP7 Projects

COST ELIGIBILITY CRITERIA AND BUDGET

THE POLAND-RUSSIA CROSS-BORDER COOPERATION PROGRAMME ST CALL FOR PROPOSALS BUDGET

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS

Click to edit Master title style Enabling LEADER through improved. funding mechanisms

FCH 2 JU Grant Agreement.

CENTRAL EUROPE Control and Audit Guidelines TABLE OF CONTENTS

Important Messages - Grants

Knowledge and Innovation Consultants. Financial Management and Reporting Greek Magistral Lesson Izmir, 28/06/2011

Project Implementation. Project Implementation Seminar Monika Balode, Project Coordinator September 2018 Tallinn & Stockholm

Full Application Form

ELIGIBILITY RULES. Rule No 1: Expenditure Actually Paid Out

Financial Webinar. IMI 2 projects :00 CET

FINANCIAL REGULATION

Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation (EC) No 1083/2006

Fact Sheet; Errors, financial corrections, irregularities, recoveries and withdrawals

Financial Guidance. Guidance on how to carry out financial management and reporting under the EEA and Norwegian Financial Mechanisms for

The Marie Curie Actions FP7 Financial Guidelines

ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS

ELIGIBILITY OF EXPENDITURES: FOCUS ON THE ITALIAN BENEFICIARIES

MODEL FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS

Eligibility. Joint Secretariat

IN2IT FINANCIAL WORKSHOP

Eligibility of expenditures in Structural Funds Trainer: Marco Lopriore, EIPA

EN New options for financing rural development projects: Simpler but not focused on results. Special Report

Multi-Beneficiary Model Grant Agreement

Multi-beneficiary Model Grant Agreement for Members

LIFE Grant Agreement Financial Aspects Highlights

PROCUREMENT OF SERVICES OPEN CALL FOR TENDERS (Article 29 decree No of 30/12/2005) FRAMEWORK CONTRACT

COMMISSION DECISION. of

COMMISSION DELEGATED REGULATION (EU)

Administrative and financial aspects: recommendations for the preparation of proposals

Legal and financial issues in Horizon Bonn,

Template for submitting data for the consideration of the Commission (Article 14(1) ESF)

Financial Guidelines for Beneficiaries EDCTP Association October 2016

Guide to Financial Issues relating to ICT PSP Grant Agreements

AUDIT REFERENCE MANUAL FOR THE STRUCTURAL FUNDS

Transcription:

Project Development - Rules on eligibility of expenditure Interreg finance management camp 20 23 March 2018 I Sofia, Bulgaria Iuliia Kauk, Interact Programme Hierarchy of rules Rules on eligibility of expenditure! National rules Programme rules EU rules EU rules Programme rules National rules 2007-2013 2013 2014-2020 2020 Art. 65, CPR and Art. 18, ETC Reg. Hierarchy of rules 1. Common Provisions Regulation (CPR) 1303/2013 2. ERDF Regulation 1301/2013 3. ETC Regulation 1299/2013 4. EC Delegated Regulation 481/2014 EU rules - Established jointly by the Member States in the programme monitoring committee - Apply to the programme as a whole - Cannot contradict EU rules Rules on eligibility of expenditure! Programme rules - Matters not covered by EU rules and programme rules - Cannot abolish or restrict EU rules and programme rules National rules 1

Reimbursement: forms Real costs Simplified cost options Flat rate Standard scale of unit cost Lump sum FUNDING Options applied in 2007-2013 Options in CPR 1303/2013 and ETC Reg. 1299/2013 Ex-ante calculations Novelties in Omnibus Regulation 2014-2020 SCO: Flat rate calculation of costs of a specific budget line(s) calculated by applying a percentage fixed in advance percentage applied to one/several other Example: Staff costs * 0,15 = Office and Administration costs Direct costs othen than the staff costs * 0,20 = Staff costs SCO: Standard scale of unit costs calculation of all or part of costs of a specific budget line calculated by applying a standard unit cost fixed in advance applied to easily identifiable quantities Established based on fair, equitable and verifiable calculation method Example: Cost for advisory service based on historical data Number of days * EUR 350 2

SCO: Lump sum calculation of all or part of costs of the subject to achievement of predefined outputs/activities single payment maximum limit EUR 100.000 of public contribution per *in 2007-2013 or Example: Project preparation costs Costs of predefined activities Small s/ people-to-people s Use simplified cost options as much as possible!!! Commission s position on SCOs Omnibus novelties and extension of SCOs Commission delegated act for any type of SCO Financing based on fulfilment of conditions Mandatory for small ERDF operations < EUR 100 000 of public support No limit for lump sums Increased flexibility for the hourly rate for staff costs 3

Omnibus novelties for the establishment of the SCOs New flat rates: Up to 20% of the direct costs other than staff costs of the operation to calculate the direct staff costs Up to 40% of eligible direct staff costs to calculate all the other costs Ineligible expenditure: non-exhaustive list Art. 69, CPR 1303/2013 Interest on debt Purchase of land not built on and land built on in the amount exceeding 10 % of the total eligible expenditure Recoverable VAT Delegated Regulation 481/2014 Fines, financial penalties, expenditure on legal disputes and litigation Costs of gifts (except gifts not exceeding EUR 50, related to promotion, communication, publicity or information) Costs of fluctuation of foreign exchange currency Budget lines 1. Staff costs 2. Office and administration 3. Travel and accommodation 4. External expertise and services 5. Equipment 6. Infrastructure and works HOW calculated Available on Interact website Matrix of Costs 4

STAFF COSTS BL1 HOW calculated Staff costs Eligible cost Full and part-time work on the Salary payments and other linked costs all costs fixed in employment document/ law salaries related to responsibilities specified in job description Forms of reimbursement Real costs (payslips and proof of payment) Simplified cost options Staff costs Real costs Full-time on the SCs = total gross employment cost No time registration required Part-time on the Fixed % of time per month SCs = fixed % * gross employment cost No time registration required Document setting out the % of time on the Time varies every month SCs = No of hours worked * gross employment cost Time registration of 100% working time Part-time flexible number of hours per month Step 1: Hourly rate 1. Monthly gross employment cost and working time fixed in employment document/ No of working hours per month 2. Latest documented annual gross employment cost/ standard 1720 hours Step 2: Hourly rate * number of hours actually worked on the Time registration of 100% working time Working time does not include holidays, illness 5

Staff costs Part-time Real costs via standard 1720h/year Example: Annual gross employment cost 34.400 EUR Option MONTHLY working hours ANNUAL working hours Hourly rate Hours on the Working time fixed in contract Standard 1720 hours/year 160 140 143,33 1920 1680 1720 34.400/1920 = 17,9 34.400/1680 = 20,5 34.400/1720 = 20 10 hours 10 hours 10 hours STAFF COST 17,9 x 10 = 179 20,5 x 10 = 205 20 x 10 = 200 Working time does not include time reserved to holidays, illness. Time registration system: 100% of the working time. Staff costs Part-time Minimum requirements for time registration Identification: title, organisation name, employee name Signatures: employee, line manager Working time recorded per month Date Project work description No. of hours worked on the Other activities (No. of hours) Total 12.06.2015 Work package 1 5 3 8 13.06.2015 Work package 2 8 0 8 TOTAL 13 3 100% working time Staff costs Flat rate Art. 19, ETC Regulation Staff costs of an operation may be calculated as a flat rate of up to 20 % of the direct costs other than the staff costs of the operation can apply on individual partner level partners do not need to provide audit trail for staff costs (but for direct costs) Each partner can decide on the reimbursement option, unless applicable options are set at programme level. 6

Staff costs Standard scale of unit costs Art. 67, CPR Ex-ante calculation based on a fair, equitable and verifiable calculation method Category Example Annual gross employment cost Hourly rate (annual gross employment cost / 1720h) 1 Below EUR 19.999 11,63 2 EUR 20.000 49.999 20,35 3 EUR 50.000 74.999 36,34 4 EUR 75.000 99.999 50,87 5 Above EUR 100.000 65,41 Data: NWE area, all MS, 5 s from 2007-2013, 18,5 m ERDF, 51 beneficiary organisations, 297 employees EX Exercise Staff costs calculation Your task work in groups Imagine that you are PP2. You need to budget costs for your staff. Part A: calculate staff costs using SCOs (flat rate, SSUC); Part B: calculate staff costs using real costs method; Part C: consider pros and cons of both methods, pick the best scenario for PP2 Exercise Staff costs calculation Simplified cost options Standard scale of unit costs (SSUC) Monthly gross Annual Hourly rate Annual working Annual gross Annual staff employment working according hours on the employment cost cost cost hours to SSUC Staff cost3 years Annika 45,600.00 28.00 640 17,920.00 =3.040* 12 =40*10+120*2 =28* 640 53,760.00 Mikael 3,040.00 36,480.00 18.00 560 10,080.00 30,240.00 =2.500* 12 =40*10+80*2 =18* 560 Jan-Erik 8,448.00 11.00 384 4,224.00 12,672.00 =32* 12* 22 =32*12 =11* 384 Agnes 2,500.00 30,000.00 18.00 1459.2 26,265.60 =2.500* 12 =152*0,8*12 =18*1459,2 78,796.80 Robert 3,000.00 36,000.00 18.00 729.6 13,132.80 =3.000* 12 =152*0,4*12 =18*729,6 39,398.40 TOTAL 71,622.40 214,867.20 Flat rate Direct costs Flat rate Staff costs 57,000.00 20% 11,400.00 = 57,000*0,2 TOTAL 11,400.00 7

Exercise Staff costs calculation Real costs Real costs Monthly Annual gross Annual Annual working gross Annual staff Staff cost3 employment working Hourly rate hours on the employment cost years cost hours cost 3,800.00 45,600.00 1720 26.51 640 16,967.44 Annika =45.600/1720 50,902.33 =40*10+120*2 =26.51*640 Mikael 3,040.00 36,480.00 1824 20.00 560 11,200.00 33,600.00 =3.040* 12 =152*12 36.480/1824 =40*10+80*2 =20* 560 Jan-Erik 22.00 384 8,448.00 25,344.00 =32*12 =22* 384 2,500.00 30,000.00 30,000.00 Agnes 90,000.00 =2.500* 12 3,000.00 36,000.00 14,400.00 Robert 43,200.00 =3.000* 12 =36.000*0.4 TOTAL 81,015.44 243,046.33 HOW calculated OFFICE and ADMINISTRATION BL2 Office and administration Eligible cost Indirect costs - operating and administrative expenses of the partner organisation that support delivery of the Exhaustive list of costs defined in Del. Reg. 481/2014 Forms of reimbursement Real costs Flat rate 8

Office and administration Flat rate Art. 68(1), CPR Indirect costs may be calculated at a flat rate of: Up to 25% of eligible direct costs Fair, equitable and verifiable calculation method Up to 15% of eligible direct staff costs No calculation method is required can apply at individual partner level partners do not need to provide any audit trail HOW calculated TRAVEL and ACCOMMODATION BL3 Travel and accommodation Eligible cost General principles Forms of reimburse ment Travel and accommodation costs of staff of partner organisations that relate to delivery of the Exhaustive list of costs defined in Del. Reg. 481/2014 Travel and accommodation of external experts - under External Expertise and Services, BL4 Daily rates for hotel and subsistence should be respected, in line with national legislation or internal policy of the partner organisation Cost related to travel outside the programme area (Art. 5, Del. Reg. 481/2014) location of the partner Real costs SCO - SSUC 9

Travel and accommodation Standard km rate for travel, Interreg Europe, based on Erasmus + methodology Distance, km Km rate for travel, EUR 10 99.99 20.00 100 499.99 180.00 500 1 999.99 275.00 2 000 2 999.99 360.00 3 000 3 999.99 530.00 4 000 7 999.99 620.00 http://ec.europa.eu/programmes/erasmus-plus/resources/distance-calculator_en HOW calculated EXTERNAL EXPERTISE and SERVICES BL4 External expertise and services Eligible cost External expertise and services provided by a public or private body or a natural person outside the partner organisation Open list of costs defined in Del. Reg. 481/2014 ; other specific expertise and services needed for operations 10

EQUIPMENT BL5 HOW calculated Equipment Eligible cost Equipment purchased, rented or leasedby a partner, necessary to achieve objectives of the May include costs of equipment already in possession by the partner Open list of costs defined in Del. Reg. 481/2014 ; other specific equipment needed for operations General principles Second-hand equipment is eligible (under conditions, Del. Reg. 481/2014), unless decided otherwise by the programme Depreciation is eligible (under conditions, Art. 69 CPR) Equipment pro-rata cost and depreciation Full purchase cost of equipment is eligible, provided: Equipment is used solely for the. The total economic and depreciable life-time falls within the period of support. Otherwise: Pro-rata use Equipment partially used for the (degree of use for the ) Share has to be calculated according to a justified and equitable method. Depreciation Costs related to the period of support for the (period of use) Equipment purchased before the approval and used for the purpose Cost calculated in line with legislation or general accounting principles of the partner organisation. 11

HOW calculated INFRASTRUCTURE and WORKS BL6 Infrastructure and works Rules on eligibility of infrastructure expenditure Covers costs related to investments in infrastructure that do not fall into the scope of other Some general rules defined in CPR 1303/2013; e.g., purchase of land, durability of operations No specific rules defined in the Del. Reg. 481/2014 See the fact sheet on the budget line Infrastructure and works Infrastructure and works Types of activities supported by ERDF Productive investment Fixed investment in equipment Investment in infrastructure Networking, exchanges of experiences Studies, preparatory actions, capacity-building Costs of activities: Budget lines Staff costs Office and administration Travel and accommodation External expertise and services Equipment Infrastructure and works 12

Cooperation works All materials will be available on: www.interact-eu.net 13