Allocate and Level Project Resources
Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time.
Resource Allocation: Defined Resource allocation permits efficient use of physical assets Within a project, or across multiple projects Drives both the identification of resources, and timing of their application There are generally two conditions for allocating resources: Normal Most likely task duration Crashed Expedite an activity, by applying additional resources to with cost considerations Specialized or additional equipment/material Extra labor (e.g., borrowed staff, temps) More hours (e.g., overtime, weekends)
Resource Levelling: Defined Resource leveling is a technique used to examine unbalanced use of resources (usually people or equipment) over time, and for resolving over-allocations or conflicts resulting from scheduling certain tasks simultaneously. Such conflicts are: more resources such as machines or people are needed than are available, or a specific person is needed in both tasks, the tasks will have to be rescheduled concurrently or even sequentially to manage the constraint. It is used to balance the workload of primary resources over the course of the project[s], usually at the expense of one of the traditional triple constraints (time, cost, scope).
Why Resource Allocations and Leveling is important? To complete and finalize project schedule for completion of the project at maximum efficiency of time and cost (Project network times are not a schedule until resources have been assigned because the basic PERT/CPM procedures are limited in the sense that resource availabilities are not considered in the scheduling process. The procedures assume that available resources are unlimited). To smooth the use of resources for better assignment and levelling of Manpower, equipment, materials, subcontractors, and information (better managing of resource utilization over the life of the project) To estimate cost properly for finding optimum project budget (money resource) and close management control (cost and a budget can not developed until they have been time-phased with resources assigned) To schedule resource constraints properly to take care of shortage of resources (duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands)
Objective of Resource Planning The basic objective of resource management is to supply and support field operations with the resources required so that established time objectives can be met and costs can be kept within the budget. Hence, the goal is to optimize use of limited resources This Requires making trade-offs time constrained resource constrained
How limited resources affect schedule slack? Assume that activities C and G each require the use of a special piece of equipment, such a hoist crane. But only one crane is available. 3 0 9 9 0 13 C I 0 0 3 3 6 9 9 4 13 A 0 3 3 3 5 5 5 5 8 13 0 15 15 0 18 18 0 18 D E J K FINISH 0 0 0 8 2 10 10 3 13 13 2 15 15 3 18 18 0 18 START 0 0 0 5 5 8 F 10 3 13 0 4 5 B 4 5 9 5 4 9 G 9 4 13 9 4 14 H 13 5 18 ES TF EF Activity LS D LF Resources
How limited resources affect schedule slack? Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A C 1 1 1 1 1 1 I J K B G 1 1 1 1 H D E F R 1 1 2 2 2 2
How limited resources affect schedule slack? Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A C 1 1 1 1 1 1 I J K B G 1 1 1 1 H D E F R 1 1 1 1 1 1 1 1 1 1
How limited resources affect schedule slack? The direct result of this resource constraint is that activities C and G can not be performed simultaneously as indicated by the ES timeonly schedule. One or the other of the activities in each pair must be given priority. In general, the following is true: Resource constraints reduce the total amount of schedule slack. Slack depends both upon activity relationships and resource limitations. The critical path in resource-constrained schedule may not be the same continuous chain(s) of activities as occurring in the unlimited resources schedule.
Project Resource Requirement Project Resource Requirement = Resource Loading Diagram = Resource Histogram = Resource Profile and S curve We need: Project network. Resource requirement for each activity. Bar chart or time-scaled network. We make: Resource loading diagram (a diagram that highlights the period-by-period resource implications of a particular project schedule). Period-by-period total requirements of units of resources. Cumulative resource requirement curve (S curve).
Resource Loading Diagram 3 0 9 9 0 13 C I 0 0 3 3 6 9 9 4 13 A 3 R 3 R 0 3 3 3 5 5 5 5 8 13 0 15 15 0 18 18 0 18 3 R D E J K FINISH 0 0 0 8 2 10 10 3 13 13 2 15 15 3 18 18 0 18 START 0 0 0 0 R 4 R 2 R 5 5 8 F 4 R 5 R 0 R 10 3 13 0 4 5 B 4 5 9 5 4 9 G 9 4 13 1 R 9 4 14 H 13 5 18 ES TF EF Activity LS D LF 2 R 3 R 2 R Resource Type R
Resource Loading Diagram based on ES schedule Activity Time A 3 3 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 C 3 3 3 3 3 3 I 3 3 3 3 J 4 4 K 5 5 5 B 2 2 2 2 2 G 3 3 3 3 H 2 2 2 2 2 D 4 4 E 2 2 2 F 1 1 1 R 5 5 5 9 9 9 9 9 6 5 5 5 5 6 4 5 5 5 ΣR 5 10 15 24 33 42 51 60 66 71 76 81 86 92 96 101 106 111 R 2 25 25 25 81 81 81 81 81 36 25 25 25 25 36 16 25 25 25 ΣR 2 25 50 75 156 237 318 399 480 516 541 566 591 616 652 668 693 718 743 10aaa 9 8 7 6 5 4 3 2 1 0 0 0 START 0 0 0 0 R Resource Loading Diagram = Resource Histogram 0 0 3 A 0 3 3 3 R 0 4 5 B 4 5 9 2 R 3 0 9 C 3 6 9 3 R 3 5 5 D 8 2 10 4 R 5 4 9 G 9 4 13 3 R 9 0 13 I 9 4 13 3 R 5 5 8 E 10 3 13 2 R 5 5 8 F 10 3 13 1 R 13 0 15 J 13 2 15 4 R 9 4 14 H 13 5 18 2 R 15 0 18 K 15 3 18 5 R 18 0 18 FINISH 18 0 18 0 R ES TF EF Activity LS D LF Resource Type R
Resource Loading Diagram based on LS schedule Activity Time A 3 3 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 C 3 3 3 3 3 3 I 3 3 3 3 J 4 4 K 5 5 5 B 2 2 2 2 2 G 3 3 3 3 H 2 2 2 2 2 D 4 4 0 0 0 START 0 0 0 0 R 0 0 3 A 0 3 3 3 R 0 4 5 B 4 5 9 2 R 3 0 9 C 3 6 9 3 R 3 5 5 D 8 2 10 4 R 5 4 9 G 9 4 13 3 R 9 0 13 I 9 4 13 3 R 5 5 8 E 10 3 13 2 R 5 5 8 F 10 3 13 1 R 13 0 15 J 13 2 15 4 R 9 4 14 H 13 5 18 2 R 15 0 18 K 15 3 18 5 R 18 0 18 FINISH 18 0 18 0 R ES TF EF Activity LS D LF Resource Type R E 2 2 2 F 1 1 1 R 3 3 3 3 5 5 5 5 5 10 10 9 9 9 6 7 7 7 ΣR 3 6 9 12 17 22 27 32 37 47 57 66 75 84 90 97 104 111 R 2 9 9 9 9 25 25 25 25 25 100 100 81 81 81 36 49 49 49 ΣR 2 9 18 27 36 61 86 111 136 161 261 361 442 523 604 640 689 738 787 10 9 8 7 6 5 4 3 2 1 Resource Loading Diagram = Resource Histogram
Cumulative Resource Requirement Curve Cumulative resource requirement curve (S-curve) may be used for: Planning and Control of progress Preliminary resource allocation
Resource Constraint Criticality 1.Average Daily Requirement Avg. daily requirement = 111 / 18 = 6.2 units/day Suppose the analyzed resource is available at a maximum level of 7 units/day. 126 units could be expended over the 18-day project duration, which is more than 111 units. Project delay is unlikely.. 2.Resource Criticality Index Criticality index = 6.2/7.0 = 0.88 < 1 project on time Suppose the analyzed resource is available at a maximum level of 6 units/day. Criticality index = 6.2/6.0 = 1.03 > 1 project will delay In 18 days a total of only 108 units are will be expended (< 111 units), leaving some work unfinished and thus requiring an extension of the project beyond 18 days. DR where ; DR A A T D Avg. daily requiremen t T Total unit of resources D Project duration I where ; I Criticalit y index C C DR A Max A DR A max A avg. daily units req d max. am t avail. Daily
Resource Constraint Criticality 2. Resource Criticality Index Values of resource criticality index significantly below 1.0 typically are associated with non-constraining resources, while values around and above 1.0 indicate that project delays beyond the original critical path duration will be encountered. Higher values of resource criticality index are associated with the most critical (i.e., most tightly constrained) resources.
Resource Leveling and Allocation Scheduling Procedures for Dealing with Resource Constraints Resource Leveling (Resource Smoothing) Fixed-limits Resource Scheduling (Limited Resource Allocation)
Resource Leveling (Smoothing) Main Aspects Sufficient total resources are available Project must be completed by a specified due date It is desirable or necessary to reduce the amount of variability (peak and valley) in the pattern of resource usage over the project duration. The objective is to level, as much as possible, the demand for each specific resource during the life of the project. Project duration is not allowed to increase in this case.
Fixed Resource Limits Scheduling Main Aspects Also often called constrained-resource scheduling, or limited resource allocation Much more common There are definite limitations on the amount of resources available to carry out the project (or projects) under consideration. Project duration may increase beyond the initial duration determined by the usual time only CPM calculations. The scheduling objective is equivalent to minimizing the duration of the project (or projects) being scheduled, subject to stated constraints on available resources.
Basic General Approach The basic general approach followed in both resource leveling and fixed resource limits scheduling is similar: Set activity priorities according to some criterion and then Schedule activities in the order determined, as soon as their predecessors are completed and adequate resources are available
Resource Leveling (Smoothing) Resource leveling techniques provide a means of distributing resource usage over time to minimize the period-by-period variations in manpower, equipment, or money expended. The essential idea of resource leveling centers about the rescheduling of activities within the limits of available float to achieve better distribution of resource usage. A systematic procedure for leveling resources was developed by Burgess. Burgess method utilized a simple measure of effectiveness given by the sum of the squares of the resource requirements for each day (period) in the project schedule.
Resource Leveling (Smoothing) While the sum of daily resource requirements over the project duration is constant for all complete schedule, the sum of the squares of the daily requirements decreases as the peaks and valleys are leveled. The measure of effectiveness reaches a minimum for a schedule that is level and equals = Eff ( DR ) where ; Eff Effective ness DR Average daily 2 D requiremen t D Project duration Resource Unit Average daily resource requirement (Avg. R) Time
Burgess Leveling Procedure Step 1. List the project activities in order of precedence. Add to this listing the duration, early start, and float (slack) values for each activity. Step 2. Starting with the last activity, schedule it period by period to give the lowest sum of squares of resource requirements for each time unit. If more than one schedule gives the same total sum of squares, then schedule the activity as late as possible to get as much slack as possible in all preceding activities. Step 3. Holding the last activity fixed, repeat Step 2 on the next to the last activity in the network, taking advantage of any slack that may have been made available to it by the rescheduling in Step 2. Step 4. Continue Step 3 until the first activity in the list has been considered; this completes the first rescheduling cycle.
Burgess Leveling Procedure Step 5. Carry out additional rescheduling cycles by repeating Steps 2 through 4 until no further reduction in the total sum of squares of resource requirements is possible, noting that only movement of an activity to the right (schedule later) is permissible under this scheme. Step 6. If this resource is particularly critical, repeat Steps 1 through 5 on a different ordering of the activities. which, of course, must still list the activities in order of precedence. Step 7. Choose the best schedule of those obtained in Steps 5 and 6. Step 8. Make final adjustments to the schedule chosen in Step 7, taking into account factors not considered in the basic scheduling procedure.
Application of Burgess Procedure (initial) Activity Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 C 3 3 3 3 3 3 I 3 3 3 3 J 4 4 K 5 5 5 B 2 2 2 2 2 G 3 3 3 3 H 2 2 2 2 2 D 4 4 E 2 2 2 F 1 1 1 R 5 5 5 9 9 9 9 9 6 5 5 5 5 6 4 5 5 5 ΣR 5 10 15 24 33 42 51 60 66 71 76 81 86 92 96 101 106 111 R 2 25 25 25 81 81 81 81 81 36 25 25 25 25 36 16 25 25 25 ΣR 2 25 50 75 156 237 318 399 480 516 541 566 591 616 652 668 693 718 743 10aaa 9 8 7 6 5 4 3 2 1 Resource Loading Diagram = Resource Histogram
Application of Burgess Procedure Start with Delay activity H one period Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 G 3 3 3 3 E 2 2 2 F 1 1 1 I 3 3 3 3 J 4 4 H 2 2 2 2 2 K 5 5 5 R 5 5 5 9 9 9 9 9 6 3 5 5 5 6 6 5 5 5 R 2 25 25 25 81 81 81 81 81 36 9 25 25 25 36 36 25 25 25 Delay activity H one period R 2 = 747
Application of Burgess Procedure with Delay activity H 2 periods Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 G 3 3 3 3 E 2 2 2 F 1 1 1 I 3 3 3 3 Delay activity H 2 periods R 2 = 755 J 4 4 H 2 2 2 2 2 K 5 5 5 R 5 5 5 9 9 9 9 9 6 3 3 5 5 6 6 7 5 5 R 2 25 25 25 81 81 81 81 81 36 9 9 25 25 36 36 49 25 25
Application of Burgess Procedure with Delay activity H 3 periods Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 G 3 3 3 3 E 2 2 2 F 1 1 1 I 3 3 3 3 Delay activity H 3 periods R 2 = 763 J 4 4 K 5 5 5 H 2 2 2 2 2 R 5 5 5 9 9 9 9 9 6 3 3 3 5 6 6 7 7 5 R 2 25 25 25 81 81 81 81 81 36 9 9 9 25 36 36 49 49 25
Application of Burgess Procedure with Delay activity H 4 periods Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 G 3 3 3 3 E 2 2 2 F 1 1 1 I 3 3 3 3 J 4 4 K 5 5 5 H 2 2 2 2 2 R 5 5 5 9 9 9 9 9 6 3 3 3 3 6 6 7 7 7 R 2 25 25 25 81 81 81 81 81 36 9 9 9 9 36 36 49 49 49 Delay activity H 4 periods R 2 = 771 Hence, Lowest R 2 = 747 with Delay activity H 1 period
Application of Burgess Procedure Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 G 3 3 3 3 E 2 2 2 F 1 1 1 I 3 3 3 3 J 4 4 H 2 2 2 2 2 K 5 5 5 R 5 5 5 9 9 9 9 9 6 3 5 5 5 6 6 5 5 5 R 2 25 25 25 81 81 81 81 81 36 9 25 25 25 36 36 25 25 25 The result = Delay activity H one period R 2 = 747
Application of Burgess Procedure Start Delay activity G 1 period Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 C 3 3 3 3 3 3 I 3 3 3 3 J 4 4 B 2 2 2 2 2 G 3 3 3 3 K 5 5 5 D 4 4 E 2 2 2 F 1 1 1 H 2 2 2 2 2 R 5 5 5 9 9 6 9 9 6 6 5 5 5 6 6 5 5 5 R 2 25 25 25 81 81 36 81 81 36 36 25 25 25 36 36 25 25 25 Delay activity H one period & Delay activity G one period R 2 = 729
Application of Burgess Procedure Continue Delay activities of non critical Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 C 3 3 3 3 3 3 I 3 3 3 3 J 4 4 B 2 2 2 2 2 G 3 3 3 3 K 5 5 5 D 4 4 H 2 2 2 2 2 E 2 2 2 F 1 1 1 R 5 5 5 5 5 7 10 7 7 7 7 7 7 6 6 5 5 5 R 2 25 25 25 25 25 49 100 49 49 49 49 49 49 36 36 25 25 25 Delay activity H 1 period, Delay activity G 1 period, Delay activity F 2 periods, Delay activity E 5 periods, and Delay activity D 2 periods R 2 = 715
Application of Burgess Procedure Minimum values results are: Sequence of major moves of the first rescheduling cycle: Delay activity H one period R 2 = 747 Delay activity G one period R 2 = 729 Delay activity F two periods R 2 = 727 Delay activity E five periods R 2 = 723 Delay activity D two periods R 2 = 715
Estimated Method
Resource Leveling within the limits of available Floats Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 C C 3 3 3 3 3 3 I I 3 3 3 3 J J 4 4 K K 5 5 5 B 2 2 2 2 2 G G 3 3 3 3 H H 2 2 2 2 2 D D 4 4 E E 2 2 2 F F 1 1 1 Daily R 5 5 5 9 9 9 9 9 6 5 5 5 5 6 4 5 5 5 R 5 10 15 24 33 42 51 60 66 71 76 81 86 92 96 101 106 111 R 2 25 50 75 156 237 318 399 480 516 541 566 591 616 652 668 693 718 743 10 9 8 7 6 5 4 3 Resource Loading Diagram = Resource Histogram 2 1
First Trial Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 E 2 2 2 F 1 1 1 I 3 3 3 3 G 3 3 3 3 J 4 4 K 5 5 5 H 2 2 2 2 2 R 5 5 5 9 9 6 6 6 3 6 6 6 6 6 6 7 7 7 R 2 25 25 25 81 81 36 36 36 9 36 36 36 36 36 36 49 49 49 Delay activity H 4 periods & Delay activity G 4 period R 2 = 717
Second Trial Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 E 2 2 2 F 1 1 1 I 3 3 3 3 G 3 3 3 3 J 4 4 K 5 5 5 H 2 2 2 2 2 R 5 5 5 5 5 7 7 6 6 9 6 6 6 6 6 7 7 7 R 2 25 25 25 25 25 49 49 36 36 81 36 36 36 36 36 49 49 49 Delay activity H 4 periods, Delay activity G 4 periods, Delay activity E 2 periods, Delay activity F 2 periods, and Delay activity D 2 periods R 2 = 703
Another Trial Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A 3 3 3 B 2 2 2 2 2 C 3 3 3 3 3 3 D 4 4 E 2 2 2 I 3 3 3 3 G 3 3 3 3 F 1 1 1 J 4 4 K 5 5 5 H 2 2 2 2 2 R 5 5 5 5 5 7 7 5 5 8 7 7 7 6 6 7 7 7 R 2 25 50 75 100 125 174 223 248 273 337 386 435 484 520 556 605 654 703 Delay activity H 4 periods, Delay activity G 4 periods, Delay activity F 5 periods, Delay activity E 2 periods, and Delay activity D 2 periods R 2 = 703
Example 2 Data for small project is listed below: Activity Depends on Duration Resource Rate Activity Depends on Duration Resource Rate A 2 4 F D 2 2 B 1 2 G D 1 1 C A 1 2 E D 1 1 D B, C 4 6 1. Draw Early Start Time-scaled schedule and calculate the corresponding used resource. 1 2 3 4 5 6 7 8 9 10 A C D F 4R 2R 6R 2R B G 2R 1R E 1R 6R 4R 2R 6R 6R 6R 6R 4R 2R 36 52 56 92 128 164 200 216 220 R 2 2. Perform 2 trials Resource Leveling. Also, specify which one of the two trials Timescaled schedules is the final schedule and why..
Example 2 (First Trial) 1 2 3 4 5 6 7 8 9 10 A C D F 4R 2R 6R 2R B 2R G 1R E 1R 4R 4R 4R 6R 6R 6R 6R 4R 2R 16 32 48 84 120 156 192 208 212 R 2
Example 2 (Second Trial) 1 2 3 4 5 6 7 8 9 10 A C D F 4R 2R 6R 2R B G 2R 1R E 1R 4R 4R 4R 6R 6R 6R 6R 3R 3R 16 32 48 84 120 156 192 201 210 R 2 The 2 nd trial schedule is the best Resource Leveling result because it has lowest R 2.
Limited Resource Allocation START Set ES of the START activity equals 1, calculate initial early start (ES) and late start (LS) time for each activity in the project, and set time now equal to 1, i.e., T = 1. Determine the initial eligible activity set (EAS), i.e., those activities with ES T and with all predecessor activities completed. From among the members of the current EAS, determine the ordered scheduling set (OSS) of activities, i.e., activities with ES T, ordered according to LS with smallest values first and within this characteristic, according to least activity duration first. Consider the activities in OSS in the order listed and schedule those activities for which sufficient resources are available for the duration of the activity. As activities are scheduled update the level of resources available, and update the members of EAS. Have all activities been scheduled, i.e., is EAS an empty set? No Yes STOP Set T new = T old + 1 and compute new ES times for the updated EAS.
Example The work of a small engineering project is planned according to the AON shown below. The labour requirement of each activity is shown below each activity box. What will be the minimum contract duration if no more than 6 labours can be made available for the work and if it is assumed that having started an activity it must be completed without a break? 2 B 3 E 8 H 1 Y 2 1 2 3 3 A 4 C 5 F 2 Z 5 X 4 3 3 2 1 5 D 5 7 G 4 ES EF A c tiv ity D e s c riptio n LS D LF Required Labour
Example 3 5 2 B 2 2 5 7 7 7 3 E 0 1 10 10 10 10 8 H 0 2 18 18 18 18 1 Y 0 3 19 19 0 0 3 A 0 4 3 3 3 3 4 C 0 3 7 7 8 12 5 F 4 3 13 17 15 17 2 Z 2 2 17 19 19 19 5 X 0 1 24 24 3 5 5 D 2 5 8 10 8 10 7 G 2 4 15 17 ES D EF A c tiv ity D e s c riptio n LS TF LF Required Labour
EST 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 A 4 4 4 C 3 3 3 3 E 1 1 1 H 2 2 2 2 2 2 2 2 Y 3 X 1 1 1 1 1 B 2 2 D 5 5 5 5 5 F 3 3 3 3 3 G 4 4 4 4 4 4 4 Z 2 2 R 4 4 4 10 10 8 8 6 8 8 9 9 9 6 6 4 4 2 3 1 1 1 1 1 SR 4 8 12 22 32 40 48 54 62 70 79 88 97 103 109 113 117 119 122 123 124 125 126 127 R 2 16 16 16 100 100 64 64 36 64 64 81 81 81 36 36 16 16 4 9 1 1 1 1 1 S R 2 16 32 48 148 248 312 376 412 476 540 621 702 783 819 855 871 887 891 900 901 902 903 904 905 LST 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 A 4 4 4 C 3 3 3 3 E 1 1 1 H 2 2 2 2 2 2 2 2 Y 3 X 1 1 1 1 1 B 2 2 D 5 5 5 5 5 F 3 3 3 3 3 G 4 4 4 4 4 4 4 Z 2 2 DR =(SR/D) = 127/24 = 5.292 Eff =DR 2 *D = (5.291) 2 *24 = 5.292 =672.042 R 4 4 4 3 3 10 10 6 6 6 6 6 9 9 9 9 9 4 5 1 1 1 1 1 SR 4 8 12 15 18 28 38 44 50 56 62 68 77 86 95 104 113 117 122 123 124 125 126 127 R 2 16 16 16 9 9 100 100 36 36 36 36 36 81 81 81 81 81 16 25 1 1 1 1 1 S R 2 16 32 48 57 66 166 266 302 338 374 410 446 527 608 689 770 851 867 892 893 894 895 896 897
Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 EAS OSS Daily R
T 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 E A S A B D D D D H H H F F F F F F F Y Z X C E F D G O S S A C D G F Y Z X B E H D A 4 4 4 C 3 3 3 3 B 2 2 D 5 5 5 5 5 E 1 1 1 G 4 4 4 4 4 4 4 F H 2 2 2 2 2 2 2 2 F 3 3 3 3 3 Y 3 Z 2 2 X 1 1 1 1 1 R 4 4 4 5 5 3 3 6 6 6 5 5 6 6 6 6 6 6 6 5 6 3 3 3 2 2 1 1 1 1 1 R 4 4 4 5 5 3 3 6 6 6 5 5 6 6 6 6 6 6 6 5 6 3 3 3 2 2 1 1 1 1 1 SR 4 8 12 17 22 25 28 34 40 46 51 56 62 68 74 80 86 92 98 103 109 112 115 118 120 122 123 124 125 126 127 R 2 16 16 16 25 25 9 9 36 36 36 25 25 36 36 36 36 36 36 36 25 36 9 9 9 4 4 1 1 1 1 1 S R 2 16 32 48 73 98 107 116 152 188 224 249 274 310 346 382 418 454 490 526 551 587 596 605 614 618 622 623 624 625 626 627
Another Procedure Step 1: T = 1 ES 1 E.A.S. {A} O.S.S. {A} Step 2: T = 4 ES 4 E.A.S. {B, C, D} LS 6, 4, 6 D 2, 4, 5 O.S.S. {C, B, D} Step 3: T = 8 ES 8 E.A.S. {E, D} LS 8, 6 O.S.S. {D, E} Step 4: T = 13 ES 13 E.A.S. {H, F, G} LS 11,13, 11 D 8, 5, 7 O.S.S. {G, H, F} Step 5: T = 20 ES 20 E.A.S. {F} O.S.S. {F} Step 6: T = 21 ES 21 E.A.S. {Y} O.S.S. {Y} Step 7: T = 25 ES 25 E.A.S. {Z} O.S.S. {Z} Step 8:T = 27 ES 27 E.A.S. {X} O.S.S. {X}
Another Procedure T 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 A 4 4 4 C 3 3 3 3 B 2 2 D 5 5 5 5 5 E 1 1 1 G 4 4 4 4 4 4 4 H 2 2 2 2 2 2 2 2 F 3 3 3 3 3 Y 3 Z 2 2 X 1 1 1 1 1 R 4 4 4 5 5 3 3 6 6 6 5 5 6 6 6 6 6 6 6 5 6 3 3 3 2 2 1 1 1 1 1