INTEGRATING RISK AND EARNED VALUE MANAGEMENT

Similar documents
Project Controls Expo

APPENDIX 1. Transport for the North. Risk Management Strategy

BERGRIVIER MUNICIPALITY. Risk Management Risk Appetite Framework

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION

Programmatic Risk Management in Space Projects

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

Integrated Earned Value Management and Risk Management Approach in Construction Projects

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

Solvency Assessment and Management: Stress Testing Task Group Discussion Document 96 (v 3) General Stress Testing Guidance for Insurance Companies

Appendix B: Glossary of Project Management Terms

Project Risk Management

Goodman Group. Risk Management Policy. Risk Management Policy

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

6 th September not protectively marked 1

Earning Value From Risk

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Learning Le cy Document

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

Risk Management Strategy Draft Copy

PRINCE2-PRINCE2-Foundation.150q

PMI - Dallas Chapter. Sample Questions. March 22, 2002

Earned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

M_o_R (2011) Foundation EN exam prep questions

1.1. This document forms the Council s Risk Management Strategy. It sets out:

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

Earned Schedule in Action

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Risk Video #1. Video 1 Recap

Braindumps.PRINCE2-Foundation.150.QA

Procedure: Risk management

Actualtests.PRINCE2Foundation.120questions

Control: Actual results can be compared against the budget and action is taken as appropriate.

Managing Project Risk DHY

THE VALUE OF EARNED VALUE MANAGEMENT

PROJECT COST MANAGEMENT

SOL PLAATJE MUNICIPALITY

Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0

FOOD AND DRINK SAFETY AND PROTECTION FOR THE FOOD AND DRINK INDUSTRY GLOBAL SPECIALTY LINES

Prince2 Foundation.exam.160q

PMI - Dallas Chapter. PMP Exam Sample Questions

Advanced Operational Risk Modelling

Risk Management. Policy No. 14. Document uncontrolled when printed DOCUMENT CONTROL. SSAA Vic

IP-CIS : CIS Project Management

Risk Management. Seminar June Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small

Earned Value Management. Danielle Kellogg. Hodges University

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

A Second Runway for Gatwick Appendix. A21 Programme Risk Management

Earned Value Management Training Program

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

PRINCE2 Sample Papers

explain why organisations use budgeting and how budgetary systems fit within the performance hierarchy

Project Theft Management,

Business Auditing - Enterprise Risk Management. October, 2018

SECTION II.7 MANAGING PROJECT RISKS

Guidance on satisfactory expected commercial return (SECR)

GPE engineering project management. Project Management in an Engineering Context

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

Earned Value Management - EVM

Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd

GUIDELINE ON ENTERPRISE RISK MANAGEMENT

Risk Management. Webinar - July 2017

THE PMP EXAM PREP COURSE

Project Risk Management

Risk Management Strategy

Flood Risk Management Planning in Scotland: Arrangements for February 2012

PRINCE2 Sample Papers

Policy No. Contact Brian Orpin Version 3.0 Issue Date 28/11/2014 Telephone Review Date IA Date 09/08/2013

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Fit for the future? Analysis of the scope, structure and content of a sample of longer-term viability statements published in 2016 RISK SNAPSHOT

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case

IAIS: Enterprise Risk Management for Capital Adequacy & Solvency Purposes. George Brady. IAIS Deputy Secretary General

Association for Project Management 2008

The Evolution of Risk Management and The Risk Management Process

There are many definitions of risk and risk management.

RISK MANAGEMENT POLICY October 2015

Reservoir safety risk assessment a new guide

RISK MANAGEMENT PROFESSIONAL. 1 Powered by POeT Solvers Limited

Performance measurement

Statement of Guidance for Licensees seeking approval to use an Internal Capital Model ( ICM ) to calculate the Prescribed Capital Requirement ( PCR )

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales

Basel II Briefing: Pillar 2 Preparations. Considerations on Pillar 2 for Subsidiary Banks

ICAAP Pillar 3 Disclosure

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

INSE 6230 Total Quality Project Management

The Value of EVM. Earned Value Management

Prudential Standard APS 117 Capital Adequacy: Interest Rate Risk in the Banking Book (Advanced ADIs)

Overview of the Northern Ireland Ireland - Scotland VA Programme. Electric Vehicles Call Workshop

Ashmore Group plc Pillar 3 Disclosures as at 30 June 2018

CITY OF JOHANNESBURG METROPOLITAN MUNICIPALITY GROUP RISK AND ASSURANCE SERVICES GROUP RISK MANAGEMENT POLICY

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management

B.29[17d] Medium-term planning in government departments: Four-year plans

ASIC s Regulatory Guide 247 Effective Disclosure in an Operating and Financial Review and the International Integrated Reporting Framework

Transfer pricing in the post-beps age The challenge to convert mere compliance into good governance

Perpetual s Risk Management Framework

Risk Management Policy

Transcription:

INTEGRATING RISK AND EARNED VALUE MANAGEMENT A White Paper

Contents Introduction... 3 Integrating Risk and Earned Value Management Processes... 3 Using Risk Mitigation to Improve Value... 4 An Integrated Approach... 6 Benefits of Integrating Risk and Earned Value Management... 8 Conclusion... 9 About Risk Decisions Ltd... 10 About BMT Sigma Ltd... 10 For More Information... 10 Page 2

Introduction In most organisations, Risk and Earned Value (EV) Management are undertaken as separate processes. More often than not, even where the need for a level of integration has been recognised, processes are not in place to assure the correct use of data derived from each of the disciplines. The traditional roles of Risk and EV Management are considered below: Risk Management is primarily concerned with future events: Identifying the potential threats to the programme or project objectives Assessing their significance, in terms of probability and impact Planning the mitigation strategies to deal with them And finally monitoring the effectiveness of the process. All of this seeks to increase the chances of meeting the baseline time, cost and performance targets. EV Management on the other hand, is mainly concerned with progress and performance to date, and what is happening at time now. The trend data provided through the collection and analysis of the EV data, if accurate and stable, can provide the basis upon which to make sound predictions in the form of Estimates at Completion. In some organisations these predictions also take account of the risks identified in the relevant areas of the programme. Integrating information provided by the Risk and EV Management processes properly leads to a far broader and more robust approach to running the programme. This paper considers the benefits of, and some of the key issues related to, integrating these complementary processes. Page 3

Integrating Risk and Earned Value Management Processes Risk and EV Management share common frameworks. EV Management requires a Work (or Project) Breakdown Structure, containing costs, timescales, budgets, and product definitions. When combined with an organisation breakdown structure, one has a logical framework for identifying risks to programme objectives, deciding ownership, and formulating and managing mitigation plans. Activity 1 Risk Management Activity 2 Forecast Activity 3 EVM Progress EAC Time Now Figure 1. Risk and EV Management The Synergy Prior to contract let, a proper risk-based analysis of the proposed performance management baseline will result in a more realistic setting of Management Reserve and a far better understanding of the key areas of uncertainty in a project. Post-contract let, the processes interact in: 1) Monitoring progress 2) Forecasting activities. Process interaction progress In terms of progress to date and what is happening at time now, the greatest influence of the Risk Management process upon the EV system should be through the implementation of risk mitigation actions. A robust risk process will provide pre- and post-management assessments of each risk, to justify expenditure on the risk management strategy. The strategy itself will include mitigation or fallback actions/activities. Many of these actions will require resource and budget not included in the original baseline. In a mature EV and Risk Management culture, there will be a desire to embed these actions into the baseline programme. Page 4

Where the baseline activities cannot accommodate such actions, additional resource and budget will be required i.e. they will require a draw down on Management Reserve. Links are therefore required with the change management and planning elements of the EV system. Process interaction forecasting Control account/project managers must make predictions in the form of Estimates at Completion (EACs). These timescale and cost predictions, should take account of the potential impact of risks on each work package in the programme. Regular outputs will be required from the Risk Management system to support monthly variance reporting. The outputs of qualitative and quantitative risk analysis can enhance this information. A straightforward qualitative analysis of the risks and associated mitigation strategies etc. owned by a control account manager will inform the estimating process. However, quantitative analysis would strengthen this approach. In a mature Risk Management culture, a three-point estimating process will underpin quantitative timescale and cost risk analysis. As a result, sensitivity analysis and what if scenarios, can be considered at both overall programme and sub-system levels to: Determine whether or not risk management strategies have been formulated, and if so whether they have been integrated within the baseline programme Assess whether these mitigation or fallback strategies are having the anticipated impact a real measure of the effectiveness of risk management. The probabilistic outputs from this quantitative analysis contribute to the debate about risk management strategies, and can be compared with the EV-based predictions. Percentage confidence levels (for timescale and budget predictions) can be directly compared with EACs. Significant variances can be investigated. Page 5

Using Risk Mitigation to Improve Value An EV Management system requires us to establish a Performance Measurement Baseline comprising an integrated schedule and associated set of time-phased budgets. The Performance Measurement Baseline and the agreed Management Reserve then combine to provide a Contract Budget Baseline. The tracking of the Actual Costs of Work Performed and Earned Value allows there to be a predictive/trending process. Associated with this, the calculation of Estimates at Completion, and cost and schedule variances can be determined. A well-structured Risk Management process will allow the compilation of a robust risk and opportunity register upon which qualitative and quantitative risk analysis can be undertaken. The quantitative outputs of cost and timescale analysis can be overlaid onto the EV system outputs, as shown in the figure below. Figure 2: Quantitative Risk Analysis vs. EV Management Forecast 160,000 140,000 CBB 120,000 Management Reserve Pre - Mit EAC Cost Range 100,000 Cost 80,000 60,000 PMB 40,000 BCWP 20,000 ACWP Time Range 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Completion Key ACWP Actual Costs of Work Performed CBB Contract Budget Baseline PMB Performance Measurement Baseline BCWP Budgeted Cost of Work Performed EAC Estimates at Completion Quantitative analysis, undertaken in an appropriate simulation tool, allows the production of probabilistic outturns of cost and timescale in the form of percentage confidence levels. First, we can consider the pre-mitigation scenario. The pre-mitigation box, shown above, is bounded by the 10% confidence to the left and bottom, and by the 90% confidence to the top and right. Page 6

However, of more significance is the post-mitigation scenario (see below), which shows the effect of risk on cost and schedule assuming successful implementation of mitigation actions. Comparing the EV-based predictions against that of the quantitative risk analysis can help determine the amount of risk management activity necessary to protect the Performance Measurement Baseline and whether or not this is affordable. Figure 3: Post-Mitigation Quantitative Risk Analysis vs. EV Management Forecast 160,000 Manage Cost 140,000 Cost 120,000 100,000 80,000 Mitigation Costs (drawdown on MR) Management Reserve Post- Mit Pre - Mit Manage Schedule 60,000 PMB 40,000 BCWP 20,000 ACWP 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Completion Key ACWP Actual Costs of Work Performed CBB Contract Budget Baseline PMB Performance Measurement Baseline BCWP Budgeted Cost of Work Performed EAC Estimates at Completion MR Management Reserve By drawing down on Management Reserve, we can begin to manage cost and timescale impacts, and through cost-benefit analysis try to determine an acceptable post-mitigation position against the Contract Budget Baseline. However, to achieve this there needs to be confidence in the figures underpinning the predictions. The challenge in achieving this confidence is to: Ensure that the output data from the Risk and EV management processes are robust and consistent. Integrate this output data in a straightforward and practical way. Project/programme specifics must be addressed in any process developed to support this integration, but a key issue that all organisations must manage is outlined below. The generation of risk exposure forecasts and estimates at completion both require the inclusion of risk mitigation action costs. Page 7

The danger is that the risk mitigation costs are double-counted, or worse not counted at all. This is illustrated in below. EAC Risk action costs Double Counting of Risk Action Costs!! Costs Other direct / indirect costs Time phased budget/ resource Risk action costs Residual Risk (% x Impact) Risk Exposure Forecast Figure 4: Potential Double Counting of Risk Mitigation Costs. Page 8

An Integration Approach An integrated approach, aimed at addressing the double counting issue is outlined below. Mitigation action Release to margin Baseline Budget Management Reserve 6 9 Fallback actions 8 1 Baseline objectives Uncertainty, risks, opportunities Mitigation/fallback strategies 2/7 3 Risk Register Action Register 4/5 Cost-benefit analysis Think again, or accept pre-mitigation Worthwhile? Then build into the baseline and use post-mitigation 1) Agree the Performance Management Baseline around project objectives of time, cost and performance (the deliverables). This, together with the Management Reserve forms the Contract Budget Baseline (see Figure 1). 2) Identify risks and opportunities using the structure provided by the Performance Management Baseline, which as been generated through a robust EV process. 3) Develop mitigation and fallback strategies and record these in an action register. 4) Assess each individual risk/opportunity to ensure that the actions chosen are costbeneficial. Although of course, cost is not the only consideration. 5) Undertake a more holistic cost-benefit analysis to prioritise which mitigating actions to undertake: since projects are cash and resource constrained, they generally cannot afford to undertake all the actions. 6) Transfer actions, once approved, into the baseline plan, drawing down from Management Reserve into the baseline budget. This is effected through the Baseline Change Request or similar. The process ensures a) The movement of planned activity and budget to the Page 9

baseline; and b) that risk actions are flagged (in the register/database) in such a way that they are no longer included in any risk exposure calculation. 7) Assess new risks and opportunities as they are identified, as alternative scenarios or mitigation strategies are formulated, or the availability of budgets/resources changes. 8) As the residual, un-mitigated risks happen draw budget for fallback actions down from Management Reserve. 9) Finally, high performing programmes release Management Reserve to margin. Page 10

Benefits of Integrating Risk and EV Management Integrating the Risk and EV Management processes delivers significant benefits pre- and post-contract award: Identifying and assessing the key programme risks and allowing for the cost and time to carry out mitigating actions ensures that a more realistic baseline is established precontract Taking a view of the programme s post-mitigation (residual) risk exposure informs the decisions and negotiations surrounding the provision of Management Reserve. Identifying and assessing the risks to a programme, and proactively managing the risks, opportunities and mitigating actions increases the chances of meeting the baseline time, cost and performance targets Predictions (in the form of Estimates at Completion) based on EV data will be more accurate and realistic if they properly take account of the identified risks in the programme Finally, a broader and more robust picture of the programme promotes improved confidence amongst stakeholders and customers. Conclusion The benefits of bringing together the Risk and EV Management disciplines are clear, pre- and post-contract award. What is required however, is a pragmatic approach to the integration of the supporting systems. Management Reserve presents a particular challenge, since both disciplines have a call on it. Management Reserve is a key component of EV Management systems: along with the agreed Performance Measurement Baseline, it forms the Contract Budget Baseline. It is therefore essential that programmes can manage Management Reserve effectively and appropriately. Management Reserve is also central to risk management. The most important aspect of effective risk management is the identification, implementation and management of actions that mitigate risks and exploit opportunities. These actions require funding, via draw down of Management Reserve. This paper suggests an approach for ensuring that the risk mitigation costs (a key component of Management Reserve) are not double-counted.. However, this has implications for both the customer and supplier. A good, trusting relationship is essential for communicating risks and agreeing ownership. Finally, there may be a need to take a more pragmatic approach to contracting in the future. This paper was presented in two parts over the first and second UK International Performance Management Symposiums held in October 2002 and October 2003 respectively. Page 11

About Risk Decisions Ltd Risk Decisions has a well-established reputation for delivering best practice risk management solutions to major corporate and government organisations worldwide. These solutions are based on the Predict! software, training and technical helpdesk support, and risk and opportunity management services. Our Predict! software gives you a user-friendly, scalable, flexible and secure environment for identifying risk exposure at every level in your organisation, and for proactively managing critical risks, opportunities and management strategies. By communicating better information about risks and opportunities, Predict! enables you to make better decisions about your business and programmes, and to be confident of achieving objectives on time and to budget. We also provide robust and practical risk and opportunity management services based on best practice, and delivered by our experienced professionals. Each client has unique requirements and we place this foremost in our minds when seeking the best solution for an organisation. We work closely with our customers, transferring skills via training and on-going support to ensure that these solutions become embedded into their organisations for long-lasting effect. In a business environment where effective risk management is essential, you can rely on Risk Decisions' experienced risk professionals to provide long-term expert support. About BMT Sigma Ltd Based in the City of Bath, BMT Sigma s experience and expertise in through life Integrated Performance Management provides the business support to enable you to meet your customer s needs. They achieve this by becoming a true partner and an integral part of your team, acting as an informed independent adviser on strategy and implementation. The company is part of British Maritime Technology, an independent international technical consultancy based in Teddington, London. BMT Sigma staff are experienced in supporting the development and maintenance of a strategic overview from concept to disposal, providing the tools, techniques and processes to achieve governance, control and assurance objectives. Integrating business improvement, programme management and systems engineering processes greatly increases the likelihood of meeting strategic objectives at project or organisational level. At a tactical level their staff work within and move between functionary boundaries, identifying critical interdependencies and forcing lateral information flow. They supply the real time feedback on project progress to the strategic level. In addition to their technical skills, experience and domain knowledge, BMT Sigma staff are able to communicate clearly and concisely at all levels within an organisation. It is this, combined with their independence and objectivity that enables them to gain rapid acceptance and respect. For further information contact: Risk Decisions Ltd Buchan House, Parkway Court Oxford Business Park South Oxford, OX4 2JY, UK T: +44 (0)1865 718666 F: +44 (0)1865 718600 E: enquiries@riskdecisions.com www.riskdecisions.com BMT Sigma Ltd 5 Riverside Court Lower Bristol Road Bath, BA2 3DZ, UK T: +44 (0)1225 820980 F: +44 (0)1225 820981 E: info@bmtsigma.co.uk www.bmtsigma.co.uk Ref: 12/03 Page 12