RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS

Similar documents
Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Project Management Certificate Program

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Risk Assessment of the Niagara Tunnel Project

Chapter-8 Risk Management

California Department of Transportation(Caltrans)

Risk-Based Project Management Approach for Large- Scale Civil Engineering Projects

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Project Risk Management

ISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management

Frumkin, 2e Part 5: The Practice of Environmental Health. Chapter 29: Risk Assessment

Fundamentals of Project Risk Management

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

METHODOLOGY For Risk Assessment and Management of PPP Projects

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management

INSE 6230 Total Quality Project Management

Managing Project Risk DHY

Project Theft Management,

Item. Metro Contingency and Risk Management

Information Technology Project Management, Sixth Edition

Kidsafe NSW Risk Management Plan. August 2014

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

Risk Video #1. Video 1 Recap

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

L U N D S U N I V E R S I T E T. Projektledning och Projektmetodik

Applied Risk Assessment into EPC Projects By Pulung Susilo Rahardjo

Risk Analysis and Management. May 2011 ISO 14971

Identifying and taking opportunities to improve performance as well as taking action to avoid or reduce the chances of something going wrong

SMART Planning Utilizing Risk Assessment Methodologies for Public Safety and Flood Risk Management

Risk and Risk Management. Risk and Risk Management. Martin Schedlbauer, Ph.D., CBAP, OCUP Version 1.1

February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE)

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty?

Remediation and Liability Cost Estimating. Ken Lyon Advisian, WorleyParsons Group RemTech 2015, October 14, Banff, AB

Risk Management Guideline July, 2017

M_o_R (2011) Foundation EN exam prep questions

APPENDIX I. Project Cost

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards

Risk vs. Uncertainty: What s the difference?

Prioritization of Climate Change Adaptation Options. The Role of Cost-Benefit Analysis. Session 8: Conducting CBA Step 7

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management

2) Risk assessment: History and perspective

Probabilistic Benefit Cost Ratio A Case Study

Risk Assessment in the CBA process. Bruxelles, 30/9/2015 Antonio Carrarini JASPERS - Vienna Office

Chapter 7: Risk. Incorporating risk management. What is risk and risk management?

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

Excavation and haulage of rocks

CRAVE. Cost Risk Assessment + Value Engineering. CSVA 2011 Conference Toronto, Ontario Nov 14-16, Ken L. Smith, PE, CVS

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

Risk Evaluation, Treatment and Reporting

Safety Risk Assessment for High Hazard Industries: To Quantify or Not To Quantify?

CEVP Cost Estimate Validation Process

Risk Management for Tunnel Planning, Design and Construction

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

An Introduction to Risk

RISK MANAGEMENT MADE EASY. Susan Parente Project Management Symposium.

1. Define risk. Which are the various types of risk?

Table of Contents Advantages Disadvantages/Limitations Sources of additional information. Standards, textbooks & web-sites.

Sensitivity analysis for risk-related decision-making

The Concept of Risk and its Role in Rational Decision Making on Nuclear Safety Issues

ก ก Tools and Techniques for Enterprise Risk Management (ERM)

Indicate whether the statement is true or false.

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996

Federal Transit Administration United States Department of Transportation Washington, DC 20590

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Methodology for risk analysis in railway tunnels using Monte Carlo simulation

4. Outline of EIA for Development Assistance

A SIMPLE METHOD OF RISK/HAZARD ASSESSMENT IN DREDGING

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

APPENDIX 1. Transport for the North. Risk Management Strategy

Procedure: Risk management

Download slides on SEO Südwest

Adaptation Assessment: Economic Analysis of Adaptation Measures

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Job Safety Analysis Preparation And Risk Assessment

Integrating Contract Risk with Schedule and Cost Estimates

A Framework for Risk Assessment in Egyptian Real Estate Projects using Fuzzy Approach

RISK MANAGEMENT POLICY

Risk Management Made Easy. I. S. Parente 1

Programmatic Risk Management in Space Projects

Fire Australia 2017 Quantification of Fire Safety Fire Safety Engineering Stream

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

Impressions from Applying ISO to an Avalanche Mitigation Project

Procedures for Management of Risk

The Risky Business of. Risk Management

COPYRIGHTED MATERIAL. Index

USACE Levee Screening Tool Understanding the Classification

Marc Rothschild, P.E.

A Study on Risk Analysis in Construction Project

Unexploded Ordnance (UXO) Risk Management Hazard and Risk Assessments in Offshore European Waters. Lee Gooderham Principal Consultant

A Framework for Risk Assessment of Infrastructure in a Multi-Hazard Environment. Stephanie King, PhD, PE

Lecture 13: Introduction to Risk Analysis. February 23, Vandana Srivastava. Stop Order

APPENDIX B Cost Engineering and Risk Analysis

Transcription:

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS Identify, Quantify, and 237 217 200 237 217 200 Manage 237 217 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 80 119 27 252 174.59 110 135 120 112 92 56 62 102 130 102 56 48 130 120 111 Jason Krick, P.E. Justin McDonald, P.E. 25 October 2017 Gulf of Mexico Demonstration Purposes Only The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation. 1

TOPICS OF DISCUSSION Part I: Overview of Risk Part II: Risk in the Planning and Design Phase How do we identify and communicate risk? How do we quantify risk? How do we manage risk? 2

RISK What is Risk? A measure of the probability and consequences of uncertain future events. Simple Conceptual Equation: Risk = Probability x Consequences 4 Main Questions: 1. 2. 3. 4. What can go wrong? What can happen? What are the consequences? How likely is it to happen? 3

ELEMENTS OF RISK 4 Essential Elements of Risk: 1. Trigger - hazard or opportunity 2. Uncertainty - the outcome is unknown 3. Harm - an undesirable outcome 4. Exposure/Probability a sequence of events that result in the harm 4

QUALITATIVE VS. QUANTITATIVE Qualitative: uses descriptive words rankings i.e. high, medium, low not a numerical value Quantitative: is a numerical expression uses deterministic and probabilistic point estimates

RISK ASSESSMENT Generic four-step model Hazard Describe the hazards Consequences Identify what may be harmed by the hazard Likelihood Assess the likelihood of the various consequences Risk Characterization Helps identify the risk drivers and support the decision makers 6

ACCEPTABLE AND TOLERABLE RISK Acceptable: - probability is so small - consequences are minor - benefit is great Tolerable: - Normally a risk we see unacceptable but can be reduced Tolerated for 3 reasons: 1. May be impossible to reduce the risk further 2. The cost to reduce is excessive 3. Magnitude of the benefits associated with the risky activity are too great to reduce anymore 7

RISK MATRIX Consequences Likelihood Very Low Very High High Medium Low Very Low Low Medium High Very High

RISK COMMUNICATION - Open two-way exchange of information - Purpose is to inform our stakeholders and various publics about the risks and how to better manage the risks - Helps stakeholders understand the nature and magnitude of the risk 9

RESIDUAL RISK Residual risk is the risk that remains after you have treated risks. Risk management involves treating risks meaning that a choice is made to avoid, reduce, transfer or accept each individual risk. It is difficult to completely eliminate risk and normally there is a residual risk that remains after each risk has been managed. The following are a few examples of residual risks: 1. Risk Avoidance A business decides to avoid the risk of developing a new technology because the project has many risks. The residual risk is that a competitor will develop the technology instead and the business will become less competitive. 2. Risk Reduction An airline reduces the risk of an accident by improving maintenance procedures. Residual risks remain in the process including a chance of human error such as skipping steps in the procedure.

RISK IN THE PLANNING AND DESIGN PHASE How do we identify and communicate risk? How do we quantify risk? How do we manage risk?

RISK IDENTIFICATION & MANAGEMENT Step 1: Describe the scoping choice. Step 2: Identify the risk of the scoping choice and its cause. What can go wrong? How can it happen? Step 3: Communicate the consequence (and magnitude) if things do go wrong and the likelihood it will occur. Step 4: Rate the risk based on likelihood and magnitude of the consequence. Step 5: Quantify risk through contingency. Step 6: Manage scoping choice to mitigate unacceptable risks.

RISK IDENTIFICATION EXAMPLE Scoping Choice: Use historical borings within the area to develop soil type assumptions for feasibility analysis. Delay geotechnical investigation/borings until final design phase. Risk and Its Cause: No data exists for roughly 50% of the channel beyond the current depth resulting in low confidence in determination of soil conditions where data gaps are present. Consequence (Magnitude): Increased cost estimates/contingencies due to uncertainty in dredging production rates, suitability for placement (beneficial use vs. offshore), and slope stability near existing structures (HIGH) Likelihood: MEDIUM Risk Rating: HIGH

QUANTIFYING RISK CONTINGENCY Abbreviated Risk Analysis (ARA): Based on predefined max cost growth as well as subjective and qualitative feedback from experts Quantifies costs without schedule Results are expressed with a broad overview risk rating and contingency % Useful for high level screening of alternatives Cost Schedule Risk Analysis (CSRA): Crystal Ball software based on Monte Carlo principles with calculated user defined costs and schedule implications of each risk Quantifies potential variances to the project cost and schedule Results are expressed as contingency amounts in the form of dollars and time with reflective confidence levels for successful execution Useful for managing and communicating potential project costs and schedules

RISK MANAGEMENT OPTIONS Option 1: Conduct investigation during feasibility phase to reduce data gaps to 25% of the channel. Resolve the remaining data gap during the final design phase. Cost: $400k Schedule: 6 months Risk Rating: Medium Risk Contingency Reduction from ARA: 6% Option 2: Resolve all data gaps during the feasibility phase. Cost: $650k Schedule: 8 months Risk Rating: Low Risk Contingency Reduction from ARA: 9%

QUESTIONS?