GLOSSARY OF DEFINITIONS FOR USE WITH THE ECA S ANNUAL REPORT

Similar documents
Official Journal of the European Union

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE COUNCIL

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

An overview of the eligibility rules in the programming period

Council of the European Union Brussels, 6 April 2017 (OR. en)

T HE EUROPEAN COURT OF AUDITORS D EFINITION & T REATMENT OF DAS ERRORS

Having regard to the opinion of the European Economic and Social Committee ( 1 ),

Council of the European Union Brussels, 29 March 2017 (OR. en)

EUROPEAN COMMISSION. EGESIF_ final 22/02/2016

Guidance document on. management verifications to be carried out by Member States on operations co-financed by

Loans for rural development , Estonia. Case Study. - EAFRD - EUR 36 million - Rural enterprise support - Estonia

Committee on Agriculture and Rural Development. of the Committee on Agriculture and Rural Development

JESSICA JOINT EUROPEAN SUPPORT FOR SUSTAINABLE INVESTMENT IN CITY AREAS JESSICA INSTRUMENTS FOR ENERGY EFFICIENCY IN LITHUANIA FINAL REPORT

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT

COMMISSION DELEGATED REGULATION (EU)

C. ENABLING REGULATION AND GENERAL BLOCK EXEMPTION REGULATION

Mono-Beneficiary Model Grant Agreement

Use of new technologies for monitoring Common Agricultural Policy subsidies

Table of contents. Introduction Regulatory requirements... 3

The European Court Of Auditor s Perspective On The Management And Control Of EU Funds

The control system for Cohesion Policy

COMMISSION DELEGATED REGULATION (EU) No /.. of

COMMISSION DECISION. of on technical provisions necessary for the operation of the transition facility in the Republic of Croatia

Experience with the Development and Carrying-out of CAP Audits

Proposal for a COUNCIL REGULATION

Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

COMMISSION STAFF WORKING DOCUMENT. on the assessment of root causes of errors in the implementation of rural development policy and corrective actions

Opinion No 9/2018. (pursuant to Article 287(4) TFEU)

ANNEX. to the Comission Decision. amending Decision C(2013) 1573

Council of the European Union Brussels, 4 May 2017 (OR. en) Mr Jeppe TRANHOLM-MIKKELSEN, Secretary-General of the Council of the European Union

Future of EU finances: reforming how the EU budget operates. Briefing Paper. February 2018

IIEA Conference, Dublin, 5 July 2011

COMMISSION DECISION. of ON THE MANAGEMENT AND CONTROL OF THE SCHENGEN FACILITY IN CROATIA. (only the English text is authentic)

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL AND THE COURT OF AUDITORS

Background paper. The ECA s modified approach to the Statement of Assurance audits in Cohesion

European Structural application: and Investment Funds

Revised 1 Guidance Note on Financial Engineering Instruments under Article 44 of Council Regulation (EC) No 1083/2006

FINANCIAL CONTROL OF FUNDS CO-FINANCED FROM THE EU BUDGET: POSSIBILITIES OF CONSIDERING NEW AND MORE FAVORABLE LEGAL PROVISIONS

PE-CONS 56/17 DGB 1A EUROPEAN UNION. Brussels, 12 December 2017 (OR. en) 2016/0282B (COD) PE-CONS 56/17

FINANCIAL REGULATION

5876/17 ADD 1 RGP/kg 1 DG G 2A

5303/15 ADD 1 AR/kg 1 DG G 2A

Guidance for Member States on the Drawing of Management Declaration and Annual Summary

Amended proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

DRAFT REVISED GUIDANCE NOTE ON MAJOR PROJECTS IN THE PROGRAMMING PERIOD : THRESHOLD AND CONTENTS OF COMMISSION DECISIONS

Guidance on Simplified Cost Options (SCOs):

Financial Regulation of the European Maritime Safety Agency. Adopted by the Administrative Board on 18 December 2013

Financial Regulation and implementing rules applicable to the general budget of the European Communities

Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

1. A BUDGET CONNECTED TO THE PRIORITIES OF THE EUROPEAN UNION

ESIF Financial Instruments: State aid considerations

Funding and functioning of the European Globalisation Adjustment Fund

AUDIT REFERENCE MANUAL FOR THE STRUCTURAL FUNDS

ALDE POSITION PAPER ON EU BUDGET POST 2013

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

GUIDANCE FICHE PERFORMANCE FRAMEWORK REVIEW AND RESERVE IN VERSION 1 9 APRIL 2013 RELEVANT PROVISIONS IN THE DRAFT LEGISLATION

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

European Union Regional Policy Employment, Social Affairs and Inclusion. EU Cohesion Policy Proposals from the European Commission

Guidance for Member States on Article 42(1)(d) CPR Eligible management costs and fees

COMMUNICATION FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT

Quick appraisal of major project application: Guidance for Member States on Financial Instruments - Glossary

EN Basic Payment Scheme for farmers operationally on track, but limited impact on simplification, targeting and the convergence of aid levels

(Legislative acts) REGULATIONS

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 108(4) thereof,

Proposal for a COUNCIL REGULATION

POLICY AREA 05 IN HEADING 2: Justification of the appropriations requested in the Amending Letter No 1 compared to the Draft Budget 2018

Accounting Officer's Status Report to the European Parliament and the Council 30 June 2015

CB/15/S48/4/AN1/REV2/EN(O)

DGB 2 EUROPEAN UNION. Brussels, 17 September 2014 (OR. en) 2013/0398 (COD) PE-CONS 90/14 AGRI 310 AGRIFIN 67 AGRIORG 75 CODEC 1092

REPORT. on the annual accounts of the European Asylum Support Office for the financial year 2016, together with the Office s reply (2017/C 417/12)

EN 1 EN. Annex. Sector Policy Support Programme: Sector budget support (centralised management) DAC-code Sector Trade related adjustments

Version 4: 29 th June 2017

Simplifying. Cohesion Policy for Cohesion Policy

on the Parallel Audit on by the Working Group on Structural Funds

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL. on EAGF expenditure. Early Warning System No 4-6/2018

Guidance for Member States on Preparation, Examination and Acceptance of Accounts

ELIGIBILITY RULES. Rule No 1: Expenditure Actually Paid Out

MID TERM REVIEW OF THE MFF TOWARDS A SIMPLER AND MORE FLEXIBLE SINGLE RULE BOOK FOR THE EU BUDGET

Official Journal of the European Union. (Non-legislative acts) REGULATIONS

FINANCIAL MANAGEMENT OF THE EUROPEAN AGRICULTURAL FUNDS

PROBLEMS WITH THE CAP REFORM PROCESS AND RECOMMENDATIONS FOR SUPPORT FOR SUSTAINABILITY

The investment shall be newly originated (not a refinancing). The investments shall be expected to be financially viable.

EUROPEAN COMMISSION DIRECTORATE-GENERAL COMMUNICATION Representations in the Member States Edinburgh

Incentive Guidelines Certify (Tax Credits)

Multi-Beneficiary Model Grant Agreement

***I DRAFT REPORT. EN United in diversity EN 2011/0280(COD)

REPORT FROM THE COMMISSION TO THE EUROPEAN COURT OF AUDITORS, THE COUNCIL AND THE EUROPEAN PARLIAMENT

FINANCIAL REGULATION

OFFICE FOR HARMONIZATION IN THE INTERNAL MARKET

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE REGIONS

Official Journal of the European Union. (Non-legislative acts) REGULATIONS

Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

Overview of CAP Reform

Obecné nařízení Přílohy obecného nařízení Nařízení pro ERDF Nařízení o podpoře EÚS z ERDF Nařízení pro ESF Nařízení pro FS

Recommendation of the Council on Good Practices for Public Environmental Expenditure Management

Financial Regulation. Applicable to the budget of the European Medicines Agency. 15 January 2014 EMA/MB/789566/2013 Management Board

Discharge 2012: Innovative Medicines Initiative Joint Undertaking

Guide to Financial Issues relating to ICT PSP Grant Agreements

Index. Executive Summary 1. Introduction 3. Audit Findings 11 MANDATE 1 AUDIT PLAN 1 GENERAL OBSERVATION AND MAIN CONCLUSIONS 1 RECOMMENDATIONS 2

Financial Regulation applicable to the general budget of the Union and its rules of application July 2017

Transcription:

GLOSSARY OF DEFINITIONS FOR USE WITH THE ECA S ANNUAL REPORT Introduction This glossary is designed to help readers by setting out clear and simple definitions of technical terms used in the report. For official legal definitions readers should consult the relevant legal texts. More detailed definitions and explanations of the EU institutions and the EU s legislation, accounts and policies can be found: - on the website of the EU Publications Office: http://eur-lex.europa.eu/browse/summaries.html http://eur-lex.europa.eu/summary/glossary.html - on the websites of the Commission Directorates-General (DGs), for example: A http://ec.europa.eu/budget/explained/glossary/glossary_en.cfm https://ec.europa.eu/agriculture/glossary_en http://ec.europa.eu/regional_policy/en/policy/what/glossary https://ec.europa.eu/research/participants/portal/desktop/en/support/reference_term s.html Absorption of EU funds: The proportion of granted EU subsidies that has actually been paid to a beneficiary or group of beneficiaries and that the Commission has accepted as having been spent in accordance with the conditions and rules attached to these subsidies. It is expressed as a percentage of planned EU spending and can relate to either a year or an entire programming period. Annual activity report (AAR): An internal management report submitted to the Commissioners by the director-general of each Commission DG. Each AAR covers the relevant DG s management and internal control, and its performance in relation to the key objectives and activities identified in its management plan. The AAR includes a declaration by the relevant director-general or head of department on the financial information provided in the AAR. Appropriation: An amount authorised for a specific purpose in the budget.

2 Assigned revenue: Revenue which, because of its origin, is assigned to specific expenditure (e.g. contributions of Member States or third countries to specific research programmes). This is an exception to the budgetary principle that total revenue should cover total expenditure. Audit authority: An entity, such as a department of a state chancellery or ministry of finance, which conducts system audits and audits of the operations under an operational programme and reports its findings to the relevant managing and certifying authorities. It submits an annual report to the Commission providing assurance on the proper functioning of management and control systems and, as a consequence, on the legality and regularity of the certified expenditure. This authority must be independent from the bodies managing the funds. (Responsible) authorising officer: Person responsible for implementing revenue and expenditure in accordance with the Financial Regulation and the principles of sound financial management, and for ensuring compliance with legality and regularity requirements. B Basic payment scheme (BPS): Replacing the single payment, this scheme came into effect in 2015, following the 2013 reform of the common agricultural policy. It operates on the basis of payment entitlements allocated for eligible land declared by the applicant in 2015. Each payment entitlement activated together with one hectare of eligible land generates a BPS payment equal to the value of the payment entitlement. The BPS is in operation in 18 Member States, 2016 was the first year payments were made on the basis of these new rules. Beneficiary: A natural or legal person receiving a subsidy from the EU budget. Budget support: A means of providing development aid (MFF heading 4 Global Europe, EDFs). It involves payments to the national treasury account of a partner country, a performance assessment, capacity development and a dialogue with the partner country. The Commission distinguishes three types of budget support: good governance and development, sector reform, and state building contracts. Budgetary authority: The institutions empowered to set the EU budget, i.e. the European Parliament and the Council of Ministers.

3 C Carryover: The transfer of authorised but unused appropriations from one year to the next for justified reasons as specified in the Financial Regulation. Expenditure and revenue are normally only planned and authorised for one year at a time (the principle of annuality ). For operational expenditure, the carryover of appropriations is an exception to this principle. For administrative expenditure, however, appropriations are routinely carried over automatically to pay invoices received the year after the activity in question. Ceiling: Limits of expenditure or revenue fixed by law or by agreement, such as in the own resources decision or the multi-annual financial framework. For commitments, the MFF sets an individual annual ceiling for each expenditure heading, whereas one overall annual ceiling applies to payment appropriations. Certification body: The agricultural sector s equivalent of the audit authority, this is a public or private entity designated by the Member State to certify the truthfulness, completeness and accuracy of the accounts of the accredited paying agency. Certifying authority: An entity which carries out checks on the expenditure declared by managing authorities to verify its legality and regularity in order to then provide assurance to the Commission to that effect. Commitment: Earmarking of an amount from the budget to finance specific items of expenditure if certain conditions are fulfilled. Having these amounts earmarked allows the EU to sign contracts and grant agreements and take other decisions with a financial impact. Common agricultural policy (CAP): A mechanism created in 1962 to guarantee, among other things, food security while ensuring a fair standard of living for the EU s farmers. The CAP underwent major reforms in 1992, 2003 and 2013. Confidence interval: The real level of error can only be known if all transactions are tested. With a sample-based approach, we instead calculate a 95 % confidence interval, meaning we consider there to be a 95 % chance that the actual level of error lies within that interval.

4 Conformity clearance procedure: A Commission procedure seeking to recover EU funds disbursed irregularly by a Member State. Conformity decision: A formal Commission decision quantifying the amounts which Member States must reimburse following a conformity clearance procedure. (EU) Consolidated accounts: The aggregate accounts of all EU institutions and agencies, presented by the Commission in a single summary document, excluding any amounts that they have paid or owe to one another. Contingent liability: In accounting, this is a liability that may occur, depending on the outcome of an uncertain future event. It is recorded in the accounts if it is probable and the amount can be reasonably estimated. Coordination Committee for the Funds (COCOF): The Coordination Committee for the Funds was a permanent monitoring committee at the Commission. Its function was to discuss issues relating to the implementation of the regulations governing certain EU funds, and to issue guidance notes with practical examples and information, without being legally binding or limitative. For the 2014-2020 programming period it was replaced by the Coordination Committee for the European Structural and Investment Funds (COESIF). Corrective capacity: Estimated amount of expenditure involved in breaches of legal and contractual provisions identified and corrected by the relevant Commission DG/authorities after payment has been authorised. The term also refers to the ability of an authority in the Member State or a Commission DG to identify and correct irregular spending. Coupled support: Support tied to the production of a specific agricultural product. Cross-compliance: Mechanism under the common agricultural policy whereby farmers are obliged, in order to receive the full amount of their payments, to follow a set of rules on environmental, public and animal health, animal welfare and land management.

5 Cumulative residual risk: The remaining share of expenditure, since the start of the programming period, which is not legal and regular once all corrective measures have been taken into account (see also residual error/risk rate). D 'De minimis' aid: Amounts of state aid up to a certain ceiling (per recipient, over a three-year period), which are deemed to be compatible with the single market and therefore exempt from the requirement to have them approved by the Commission. De-commitment: An act whereby an existing commitment (or part of it) is cancelled. De-commitment rules: These are applied when the full value of a commitment is not used within set time limits. The maximum time for using commitments under shared management is three years (the N+3 rule ), after which EU legislation requires de-commitment, i.e. the cancellation of commitments. However, this period can be extended in times of crisis. Decoupled support: Support which is not tied to the production of a specific agricultural product. Direct aid/direct support: Income support payments made to farmers in accordance with the common agricultural policy, including coupled aid and decoupled area-related aid. Direct management Management (selecting contractors, awarding grants, transferring funds, monitoring activities, etc.) of a fund or programme directly by the Commission itself, in contrast to shared management. Discharge: Decision by the European Parliament releasing the Commission from its responsibility for managing a given budget and closing it on the basis of a recommendation from the Council and the ECA s annual report and statement of assurance.

6 Draft amending budget: Proposal made by the Commission to amend certain aspects of the adopted budget for the year concerned. E Economic result: The difference, in the EU consolidated accounts, between total revenue and total expenses. The purpose of this accrual-based result is to present the financial impact of events on the accounts of the year concerned. Hence, the economic result differs from the budget outturn which presents the difference between revenue (cash received) and payments made. Equity investment: The provision of capital to a firm, invested directly or indirectly in return for total or partial ownership of that firm, and where the equity investor may assume some management control of the firm and may share the firm's profits. Investors recover their equity investment only when they sell their ownership or when the (net) assets of the firm are liquidated. Also known as an equity contribution. Error: An irregularity arising from non-compliance with legal and contractual requirements. Estimated level of error: Our annual best estimate of the error affecting a class of payments. It is calculated based on the results of tests carried out on a representative sample of transactions. It is expressed as a percentage of erroneous payments in the total value of payments. This percentage lies, with 95 % probability, within a confidence interval defined by a lower and an upper limit. Europe 2020 strategy: The European Union s ten-year jobs and growth strategy launched in 2010 to create the conditions for smart, sustainable and inclusive growth. European Fund for Strategic Investments (EFSI): An investment support mechanism based on a Regulation of the European Parliament and of the Council and implemented through an agreement between the EIB and the European Commission to mobilise finance for strategic projects around the EU. European Structural and Investment Funds (ESIF or ESI funds): The European Regional Development Fund, the European Social Fund, the Cohesion Fund, the European Agricultural Fund for Rural Development, and the European Maritime and

7 Fisheries Fund, which were brought together for the 2014-2020 multiannual financial framework under common rules (Regulation (EU) No 1303/2013 - the Common Provisions Regulation ). Between them, these five shared management funds currently account for over half of EU spending. Their overall aim is to reduce regional imbalances across the EU. Ex-post evaluation: An assessment of the effectiveness, efficiency, coherence, relevance and EU added value of an individual EU intervention. F (Final) recipient: Term used in the Financial Regulation to refer to a natural or legal person receiving a loan or guarantee from, or an investment by, an EU-funded financial instrument. The term is also used for a natural or legal person who does not actually receive a subsidy payment but nonetheless benefits from a specific EU-funded activity such as a person receiving training on an EU-funded course or a participant in an employment initiative (see also beneficiary). Financial instrument: A form of financial support from the EU budget (formerly known as a 'financial engineering instrument ) that may take the form of 'equity or quasi-equity investments, loans or guarantees, or other risk-sharing instruments (see Article 2(p) of the Financial Regulation). Compared with grants, the main advantages of financial instruments are the potential to leverage additional capital and the possibility of re-using, or revolving, funding. Financial Regulation: Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council of 25 October 2012 on the financial rules applicable to the general budget of the EU. The Financial Regulation is the main point of reference for the principles and procedures governing the establishment and implementation of the EU budget and control of the EU s finances. Financial statement discussion and analysis: An explanation of the significant items, transactions and events presented in an entity s financial statements and the factors that influenced them. G General Block Exemption Regulation (GBER): Commission Regulation (EU) No 651/2014 of 17 June 2014 declaring certain categories of aid compatible with the internal market. Categories of state aid named in the GBER are exempt from the requirement to have them approved by the Commission.

8 Grants: Direct financial contributions from the budget to finance action to help implement a specific part of an EU policy or support the functioning of a body which pursues an aim of general European interest or has an objective forming part of an EU policy. Greening: A direct aid scheme introduced under the 2013 CAP reform to promote environmentally friendly farming practices. Farmers receiving direct support under the basic payment scheme (BPS) or the single area payment scheme (SAPS) are obliged to diversify crops, maintain existing permanent grassland and establish ecological focus areas ; if these conditions are met, they may also benefit from greening aid. Gross national income (GNI): The sum of all the incomes of the residents of an economy in a given period. GNI is used to determine the upper limit for EU payments in any given year: they should not exceed 1,20 % of the EU s GNI. A Member State s contribution to EU revenue is largely determined by its GNI as a proportion of the sum of all GNIs in the EU. H I Impact: In performance assessment, the longer-term socio-economic consequences that can be observed after a certain time following completion of a project or programme. Indirect costs: Expenses, also referred to as overheads, that contribute to an EU project or action, but also to other activities by the beneficiary. These costs are not directly linked or attributed to the EU project or action; rather, they are apportioned among the beneficiary s different activities by means of various parameters (cost drivers). Input: In performance assessment, the financial, human, material, organisational or regulatory means needed to implement a policy, project or programme. Integrated administration and control system (IACS): A system used by Member States to manage and check payments made to farmers under the common agricultural policy. It consists of databases storing the details of farmers, aid applications, animals and payment entitlements, and the LPIS database.

9 Interim payment: A payment made by the EU to a beneficiary, based on a claim, before the relevant project or action has been completed. In general, interim payments are made if there has been sufficient progress in the project or action as specified in the contract or grant agreement. Intervention logic: Conceptual framework showing how assessed needs and the objectives pursued tie in with EU action taken, as well as its expected result. Irregularity: An action or omission which leads to non-compliance with EU (or other relevant) rules, and which has a potentially negative impact on the EU's financial interests. Irregularities may be the result of genuine mistakes made by beneficiaries or by the authorities responsible for making payments. A deliberate irregularity may constitute fraud. (see also error) J K L Land parcel identification system (LPIS): A database containing all the agricultural areas (including aerial or satellite photographs) that are eligible for direct aid under the common agricultural policy. Used to check the parcels for which farmers have claimed payment, to ensure that they are paid for the correct area, thus preventing overpayments. M Major project: A large-scale operation comprising a series of works, activities or services and intended to accomplish an indivisible task of a precise economic or technical nature with clearly identified goals. The regulations set financial thresholds above which operations are to be considered major projects, making them subject to specific approval by the Commission on the basis of an independent quality review. For the 2007-2013 and 2014-2020 programming periods the usual threshold is 50 million euro. Managing authority: The national, regional or local public (or private) authority designated by a Member State to manage an operational programme. Its tasks include selecting projects for funding, monitoring their implementation and reporting to the Commission on financial aspects and

10 results achieved. The managing authority also imposes any financial corrections on beneficiaries following audits carried out by the Commission, the European Court of Auditors or any authority in the Member State (e.g. audit authorities). Market measures: Public intervention in the agricultural markets to mitigate the effects of any price drops and to address structural difficulties on the market and sector-specific support (for example for fruit and vegetables, wine and school schemes). Materiality threshold: The level of erroneous or irregular expenditure, in relation to the EU spending audited, beyond which the error is considered to be significant, or material, for auditing purposes and likely to influence the user of the EU consolidated accounts. The ECA uses a 2 % materiality threshold for its opinion, also taking account of the nature and context of the error found. Maximum aid intensity: Total amount of aid that can be paid under the rules applicable to a funding area, expressed as a percentage of eligible costs. The maximum aid intensity varies by programme and by other factors such as the geographical location of a project. Mid-term review: A review of the main aspects of implementation to date of the multiannual financial framework, taking account of the economic situation at the time of the review and the economic outlook (last one published in 2016). Monetary unit sampling (MUS): A statistical sampling method where every euro spent has an equal chance of being selected for examination. In terms of transactions, using MUS guarantees that the probability of selecting a transaction is proportional to its size. The statistical nature of MUS allows the results to be extrapolated from the sample to the whole population. Multiannual financial framework (MFF): The EU's long-term spending plan. The MFF establishes spending priorities and maximum amounts that the EU may spend in particular areas over a fixed period of several years. The current MFF covers 2014-2020, while the previous ones covered 2007-2013 and 2000-2006. The MFF is divided in six parts, or headings.

11 N O Omnibus regulation proposal: A proposal for a regulation of the European Parliament and of the Council on the financial rules applicable to the general budget of the EU, and on amendments to the rules for various sectors of EU expenditure. This is a Commission document (COM(2016) 605 final) which seeks to amend and simplify many regulations currently applicable to the European Structural and Investment Funds. Operational programme: A Commission-approved programme of EU-funded investments by a Member State. It takes the form of a coherent set of priorities comprising measures under which projects are to be co-financed for the duration of the seven-year multiannual financial framework. Output: In performance assessment, this is something that is produced or accomplished with the resources allocated to a project or programme (e.g. training courses delivered to unemployed young people, number of sewage plants, km of road built, etc.). Own resources: Revenue flowing to the EU budget pursuant to the Treaties, the relevant implementing legislation and the annual budget. Customs duties are the most significant source of traditional own resources; there is also an own resource based on VAT and another based on GNI. P Partnership agreements: Agreements between the Commission and each Member State designed to ensure that funds are used in line with the Europe 2020 strategy. Paying agency: The agricultural field s equivalent of the managing and certifying authorities, this body is appointed by the national authorities to administer and control direct support and market measures. Payment entitlement: Right to benefit from basic payment scheme payment equal to the value of the entitlement for each entitlement activated together with one hectare of eligible land.

12 Performance: The extent to which projects or programmes adhere to the principles of sound financial management. Performance reserve: An amount representing 6 % of the funds allocated, for certain goals or measures, to the European Regional Development Fund, the European Social Fund and the Cohesion Fund or the European Agricultural Fund for Rural Development, to be made available after the 2019 performance review if certain targets are met or exceeded. Permanent grassland: Land used to grow grasses or other herbaceous forage crops (whether sown or self-seeded) for more than five consecutive years and not included in a farm s crop rotation scheme. Programme estimate: A document, drawn up by a partner country and endorsed by the European Commission, containing a work programme. It sets out the activities to be carried out, the financial, human and material resources required for their implementation, and the procedures to be followed. Programming period: The multiannual framework within which expenditure is planned and implemented. The duration of a programming period may extend well beyond the years of the multiannual financial framework heading under which funds are spent. This is mainly due to the rules governing the final accounts and the closure of operational programmes. For example, the final accounting year for 2014-2020 agriculture and Cohesion programmes will end in mid- 2024. Provision: In accounting, this is a liability of uncertain timing or amount recorded in the balance sheet. Public procurement: The process by which the EU, national, regional and local public authorities, or bodies governed by public law, purchase products, services and works. Private undertakings are also subject to public procurement rules and/or principles whenever they carry out procurements which are predominantly publicly funded.

13 Q R Regularity: The extent to which transactions have been conducted in accordance with the relevant laws and contracts. Reservation: In the context of the annual activity report, a director-general issues a reservation where he or she is either unable to confirm the regularity of a significant part of the DG s payments or where there are potentially serious implications for the Commission s reputation. Residual error/risk rate: It is the remaining share of expenditure which is not legal and regular once all corrective measures have been taken into account. The terms 'risk' and 'error' are applied synonymously, but in different areas of spending. Result: In performance assessment, this is the measurable immediate effect of a project or a programme. S Shared management: A method of implementing the EU budget in which, in contrast to direct management, the Commission delegates the implementation of tasks to the Member States while retaining final responsibility. The Member State channels funds to beneficiaries and (final) recipients (via paying agencies in the case of agricultural and rural development and via managing authorities for other shared management payments). The Member State has primary responsibility for setting up a management and control system which complies with the requirements of the regulations, ensuring that this system functions effectively and prevents, detects, and corrects irregularities. Simplified cost option: A means of calculating grant amounts independently of the costs actually incurred. The main forms of simplified costs are standard unit costs, flat-rate financing (calculated as a percentage of other categories of eligible costs) and lump sums (tied to specific output or result).

14 Single area payment scheme: Area-related aid scheme applied in 10 Member States, under which equal amounts of aid are granted per hectare. Sound financial management: A concept comprising the principles of economy, efficiency and effectiveness and defined in Article 30(2) of the Financial Regulation: The principle of economy requires that the resources used by the institution for the pursuit of its activities shall be made available in due time, in appropriate quantity and quality and at the best price. The principle of efficiency is concerned with the best relationship between resources employed and results achieved. The principle of effectiveness is concerned with attaining the specific objectives set and achieving the intended results. Specific assessment: An assessment of each specific major area of EU activity, supplementing the ECA s statement of assurance pursuant to the Treaty on the Functioning of the European Union. The ECA regards chapters in its annual report with an assessment on regularity of a multiannual financial framework heading, financial and budgetary management and performance as specific assessments. State aid: Any form of direct or indirect financial support provided by national public authorities to undertakings, which distorts, or threatens to distort, competition by favouring certain undertakings or the production of certain goods. The Treaty on the Functioning of the European Union generally prohibits state aid within the common market unless it is duly justified. The EU's state aid rules clarify when support is deemed to distort (or threatens to distort) competition. The Commission has exclusive competence to assess the compatibility of state aid with the rules subject to review by the European Court of Justice. Statement of assurance: A statement provided annually by the European Court of Auditors to the European Parliament and Council. It contains the Court s audit opinion on the reliability of the accounts of all EU revenue and expenditure and the legality and regularity of the underlying transaction. Otherwise known as the DAS, from the French equivalent Déclaration d'assurance. T Transaction: A receipt, payment or demonstrated use of an advance payment, accepted by the Commission and recorded in the accounts.

15 U V W X Y Z